WG Belgian Grid June 19 th , 2017 David Zenner Large Infrastructure Projects

Transcript of Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian...

Page 1: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

WG Belgian Grid

June 19th, 2017

David Zenner

Large Infrastructure Projects

Page 2: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Investment Program of the Elia Group

Page 3: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Elia’s investment portfolio composition

3

2017-2021, EUR million, net CAPEX budget numbers

9043

9080

6486

6367

57113

753

Dense Grid CentralDense Grid North 1Dense Grid North 2

Dense Grid SouthDispersed Grid…Dispersed Grid…Dispersed Grid…Dispersed Grid…Dispersed Grid…

Other (incl needs)Total

111

40

24

390

-6

3

561

Stevin

Boucle de l'Est

Noorderkempen DP

MOG

MOG Onshore

Other (incl needs)

Total

Renewables developments Customers & DSO

Regional reliability of supply

4Functional and technological conformity

5

European markets and security of supply

5 59

3 50

5 46

9 654

Total

3 71

880

25

2 31

# of projects# of programs

The portfolio is clusteredinto 5 societal drivers

▪ Driver 1: All big European driven projects

▪ Driver 2: All big renewables driven projects

▪ Driver 3: All customer driven projects and not part of long term studies

▪ Driver 4: Long-term studies linked to regional reinforcements of the network and reliability of supply

▪ Driver 5: Remaining transversal programs that require minor changes transversally across several assets

programs

projects

Million €

239

235 + 1 °

197

153

144

27

995

Nemo

Alegro

Mercator Avelin

Brabo

Interco/Backbone

Other (incl needs)

Total

15

17

36

14

82

Client

DSO

Google

Other (incl needs)

TotalMillion € Million €

Million €34

13

90

138

BOM

Fiber

Other (incl needs)

Total

Million €

Page 4: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Elia’s investment program for the next 5 years

4

All over the countryBuild connections with industrials to support economic growth.

5

5. Boucle de l’EstReinforce the grid to integraterenewable production

1. BraboReinforce the Port of Antwerp & increase cross-border capacity with NL

2. ALEGrOIncrease cross-border capacity with Germany with the first HVDC on land

4. Nemo LinkSubsea HVDC-interconnection with UK

3. StevinIntegrate offshore wind & benefit fromcross-border trading with UK on land

6. MOGConnection of wind farms in North Sea with the onshore grid

UK4

2

136

Page 5: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Interconnections in Belgium: reinforce ordevelop the grid at each border

5

1

23

4

5

(1) HVDC : High Voltage Direct Current(2) HTLS : High Temperature Low Sag – High performance conductors(3) With a temporary solution as from the winter of 2015(3) PST : Phase Shifting Transformer

1 NEMO [2019]: GB-BE HVDC (1)undersea interconnection

2 ALEGrO [2020]: DE-BE HVDC underground interconnection

3 Avelin-Avelgem-Horta [2022]: HTLS conductor (2)

4 Brabo I [ 2016 (3)]: PST(4) in Zandvliet& Doel-Zandvliet 380 kVBrabo II [2020]: Zandvliet-Lillo-Liefkenshoek 380 kVBrabo III [2023]: Liefkenshoek-Mercator 380 kV

5 PST Schiffelange [CREOS-2015]

6

6

6

6

66 In the longer term [under analysis]

2 cables 220 kV BE-LU Additional reinforcements at the borders

of NL and FR 2nd interconnection with DE 2nd interconnection with UK

6

Page 6: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Reinforce the backbone of the internal Belgian grid 380kV

6

12

3

5

(*)HTLS : High Temperature Low Sag – High performance conductors

4

6

6

1 STEVIN [2017]: Corridor Zomergem-Zeebrugge 380 kV

2 Mercator-Horta [2019]: HTLS conductors

3Gramme-Van Eyck[2015] : 2nd circuit 380 kV and substation Van Eyck

4 Lixhe-Herderen [2017] : 2nd circuit 380 kV and substation Lixhe

5 Capacitor bank and reactance shunt [2016]

In the longer term: 2nd circuit Van Eyck-Massenhoven 380

kV HTLS conductors on the corridor

Gramme-Van Eyck 380 kV

6

Page 7: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Capex managed by Elia Belgium will double over 2016-2019

7

400

200

0

600

2016

13

75

2017

13

86

20182010 2011 2012 2013 2014 2015

13

14

77

2019

Elia Belgium CAPEX (M€)

203

114

525

138113 137

344

115 71

130

373

150

36084

254

509

132

205

518

110

178

29

202137

RedeployHistoricalNon-elec. Infra.EU IntegrationNemo

Maintain

170

Avg. CAPEX 2016-2019

Avg. CAPEX 2010-2014

478

+181%

2010-2016 Elia Belgium Capex Evolution

Source: Elia Infrastructure Organisation presentation 11/2015, Elia projects database, Elia business plan 2016-2020, BCG analysis

Capex Committed to the regulatorfor 2016-2019 Period

Page 8: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Alegro

Page 9: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

MARKUS BERGER | 16/06/20169

ALEGrO

➔ First HVDC-interconnection between BE (Elia) and GE (Amprion)

➔ European priority project

➔ 100 km underground cable between Lixhe(BE) and Oberzier (GE)

➔ Transmission capacity of approx. 1000 MW

➔ Operational 2019

Page 10: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

ALEGrO : main characteristics of the project

10

Timing Scope

Budget

➔ 94 km underground cable link between Lixhe (BE) and Oberzier (GE) (49 km BE / 45 km GE)

➔ Transmission capacity of approx. 1000 MW

➔ Applied DC voltage: +- 320 kV

➔ Applied convertor technology: VSC multilevel symmetricmonopole

➔ Applied cable technology: HVDC XLPE cable

➔ Reinforcement works in Lixhe ( extra bays GIS + TFO )

Page 11: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

ALEGrO: main focus areas in 2017

11

• Start detailed engineering converter and cable in order to start the production on time (Valves,

TFO, cable, …) and to finalize the CW design (building, tunnel, …)

• Type tests cable (started on 22/02/2017, end expected by July 2017)

• Start cable production (foreseen Q3/2017)

• First delivery of cable (FAT) (foreseen Q4/2017)

• Start of application procedure according to PCI-regulations (started on 20/02/2017)

• Permits Belgium:

o Introduction of the permit file (20/02/2017)

o Public consultation (May-June 2017)

o Obtaining the global decision on the permits (December 2017)

Page 12: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

MOG: the Modular Offshore Grid

Page 13: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

The strategic importance of the MOG in a further offshore griddevelopment

13

The MOG will create valuable advantages for Belgium’s positionin the future offshore development:

• Readiness for more offshore production in Belgian waters: Additional wind mills on existing concessions, additional concessions, other power sources.

• An electric node in place for a link to 380kV grid via another route than Stevin (e.g. cable to Doel)

• A forward base for future interconnections:Connection to Dutch offshore grid, new interconnector with the UK, first Belgian building block of the future offshore supergrid.

• MOG can be built for a similar cost as the sum of individual connections that would be needed

• Greater robustness than individual connections:MOG’s 3 cable redundancy will convey more energy to shore

= yearly the equivalent of 10.000 additional households consumption.• Modular build-up:

synchronization with OWP’s planning : limits risk of stranded assets.• Smaller impact on the environment:

shorter total cable length: +/- 160 km vs 200 km

These future advantages will be achieved without an additional cost for the community.

Page 14: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

The technical concept ofthe MOG and perimeterfor Elia

14

Perimeter of MOG Infrastructure

Perimeter offshore windfarms

Northwester 2

Mermaid

Seastar

OSY

Rentel

Stevin

?

Page 15: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Project schedule

15

Page 16: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Stevin

Page 17: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Stevin

17

Page 18: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Stevin

18

➔ Grid reinforcement project (150 kV to 380 kV) in Belgium’s coastal region

➔ Essential for further economic development and for integration and transportation of offshore wind energy

➔ 37 km lines & 10 km cables

➔ Operational 2017

Page 19: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Stevin

19

17km new 380kV OHL parallel to existing 150kV OHL which will be brought undergroundClassic conductors, Insulating cross-arms

12km upgrade existing 380kV OHLHTLS-conductors

8km partial upgrade of existing 150kV OHL, partial new 380kV OHL Classic conductors, Insulating cross-arms

Gezelle

Van Maerlant

Stevin

10km new underground cable 380kV 4 circuits 2500mmCuEm

Demolition existing 150kV OHL

Horta

1,5km underground connection with local grid 150kV

Page 20: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Program timeline

20

Page 21: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Nemo Link

Page 22: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Nemo Link

MARKUS BERGER | 16/06/201622

First• interconnector with the UK• subsea interconnector• HVDC XLPE cable J-Power Systems• converter station with SIEMENS HVDC Plus

technology at 400kV• common regulatory framework

Page 23: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Project description

23

• National Grid and Elia are developing an electrical interconnector (1000 MW HVDC) between the UK (Richborough) and Belgium (Zeebrugge‐Herdersbrug).

• The interconnector will allow electricity to flow in either direction between the two countries. • Nemo will be regulated through the ‘cap and floor’ regulatory regime• It will collect congestion revenues through explicit and implicit capacity auctioning mechanisms 

• Commercial operation is scheduled for Q1 2019• Estimated total project budget for construction : € 721 million of which 50% for Elia• Elia System Operator will therefore take a 50% stake in NemoLink; NGIH will take the other 50%

(Elia System Operator ‐ESO)

(National Grid Interconnector Holdings ‐ NGIH)

Page 24: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

MARKUS BERGER | 16/06/20162424

Converter station (Herdersbrug site)

Nemo onshore HVDC cable (approx

9km)

HDDOffshore

380kV connection

Gezelle substation

Stevin

Geographical overviewn Belgium

Page 25: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Project timeline

25

Page 26: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Brabo

Page 27: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Phase 1Zandvliet - Doel + Zandvliet 2nd Phase Shifter End 2016

Brabo

27

Page 28: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Phase 2Rechteroever: Zandvliet - Lillo LiefkenshoekEnd 2018 - 2019Phase 1

Zandvliet - Doel + Zandvliet 2nd Phase Shifter End 2016

Brabo

28

Page 29: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Phase 2Rechteroever: Zandvliet - Lillo LiefkenshoekEnd 2018 - 2019

Phase 3Linkeroever: Liefkenshoek - Mercator End 2023

Phase 1Zandvliet - Doel + Zandvliet 2nd Phase Shifter End 2016

Brabo

29

Page 30: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Phase 2Rechteroever: Zandvliet - Lillo LiefkenshoekEnd 2018 - 2019

Phase 3Linkeroever: Liefkenshoek - Mercator End 2023

Phase 1Zandvliet - Doel + Zandvliet 2nd Phase Shifter End 2016

Brabo - Reinforcement interconnexion with the Netherlands

30

➔ Grid reinforcement project in the Port of Antwerp area

➔ Essential for further economic growth &connection of new production plants

➔ Increases cross border exchange possibilities with the Netherlands

Page 31: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Brabo II – Scope

31

Lillo

Noordland/Zandvliet

Oorderen

150 kV cable: • Lillo – Noordland: 2 x 10 km• Lillo – Oorderen: 2 x 5 km• Ketenisse – Doel: 1 x 3.5 km

380 kV line: • Step 1: Lillo – Liefkenshoek: (Schelde-

crossing)• ~3 km• 10 pylons

• Step 2: Lillo – Zandvliet:• ~ 16 km• 48 pylons

Ketenisse

Doel

Liefkens-hoek

Schelde

LegendExisting: 150 kV line (2 circuits)

First part: 150 kV cable

Second part: 380 kV line (2 circuits)

Page 32: Large Infrastructure Projects - Elia/media/files/Elia/users-group/WG Belgian Grid/20170619...Additional reinforcements at the borders ... • Start detailed engineering converter and

Timing Scope

Budget

➔ Ondergronds brengen van 150kV:

o 2 x Lillo-Noordland

o 2 x Oorderen-Lillo

o 1 x Ketenisse-Doel(18N)

o Postwerken

➔ Nieuwe lijn 380kV:

o Lillo-Zandvliet

o Lillo-Liefkenshoek(koppeling met bestaande lijn Doel-Mercator)

32

06/2018

Target MSIBrabo II

Mark-Up

01/2017

Building permit Cables

Building permit Line

10/2017 31/12/20

Cable fullMSI

Building permit line(380kV line)

Project MER (380kV line)

Building permit 150kV cable Lillo – NoordlandDesign Cable

Lil.– No.

Building permit150kV cable Oord – Lillo

DesignCable Oord

–Lil.

Building permit150 kV cable Ket. – Doel

150kV cable pulling & commissioning Lillo - Noordland

150kV cable pulling & comm. Oord. – Lillo

150kV cable pulling & comm. Ketenisse - DoelDesign Cable

Ket. -Doel

Tower detailed design step 2.2 (380kV line)

Tower detailed design step 1 + 2.1 (380kV line)

Towers specs

GRUP Approval

31/12/19

Target MSIBrabo II

Timely compl.

Tower proc. & production step 2.2.4-5

Remo-val 150 kV line

CW, tower ass.& elec. works step 1 + 2.1

Tower procurement & production step 1 +2.1

Declaration of public utility

Substation works – Lillo – 150KV

Substations Zandvliet – Noordland - connection 150kV

~4m

Replacement Bay Protections in Mercator & Doel

~6m

Tower proc. & production step 2.2.1/2/3

Substation works – Lillo –380KV

2nd cable1

~2m

2nd cable1

Summary: Brabo II

CW step 2.2

Elec. works step 2.2.3/4/5

Tower assembly 2.2.3/4/5