Lansing BWL: REO Town construction RFP

download Lansing BWL: REO Town construction RFP

of 250

Transcript of Lansing BWL: REO Town construction RFP

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    1/250

    page 1 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Reo Town Plant Construction ManagerRequest for Proposal

    BWL Reo Town Plant1203 S. Washington Ave

    Lansing, MI 48910

    Submittal Due Date:May 19, 2011

    2:00pm Local Time

    Prepared by:

    Kramer Management Group, Inc.

    Owners Representative1232 Haco Dr.Lansing, MI 48912517-702-6076

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    2/250

    BWL Reo Town Plant Page 2 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Table of Contents1 General Information & Requirements ...............................................................3

    1.1 General Information ...............................................................................31.2 Public Information ..................................................................................31.3 Type of Contract .....................................................................................31.4 Clarifications and Interpretations ............................................................41.5 Submission Requirements .....................................................................41.6 Point-Of-Contact ....................................................................................51.7 No Reimbursement for Costs .................................................................51.8 Eligible Respondents .............................................................................51.9 Evaluation of Proposal ...........................................................................51.10 Owners Reservation of Rights ...............................................................51.11 Acceptance of Evaluation Methodology .................................................6

    2 Project Summary ..............................................................................................62.1 General Scope of Work ..........................................................................6

    3 Project Milestone Schedule ..............................................................................74 Requirements for Proposal ...............................................................................8

    4.1 Criteria 1: Update of Qualifications ........................................................84.2 Criteria 2: Pre Construction Phase Services ..........................................84.3 Criteria 3: Construction Phase Services ................................................94.4 Criteria 4: Start Up and Commissioning Plan ........................................94.5 Criteria 5: Coordination of Information. ..................................................94.6 Criteria 6: Detailed Project Schedule .....................................................94.7 Criteria 7: LEED Certification Support and Administration ...................104.8 Criteria 8: Site Logistics Plan ................................................................104.9 Criteria 9: Financial Proposal ................................................................104.10 Criteria 10: Alternate for CCIP ..............................................................104.11 Criteria 11: Understanding and Acceptance of Owners Agreement .....114.12 Criteria 12: Execution of Proposal Form ...............................................11

    5 Format for Proposal ..........................................................................................115.1 General Instructions ...............................................................................11

    6 Attachments ......................................................................................................136.1 Attachment A- Project Description .........................................................136.2 Attachment B- CM Scope of Work .........................................................196.3 Attachment C- Proposal Form ................................................................236.4 Attachment D Opinion of Probable Cost Template ..............................246.5 Attachment E General Conditions Cost Format ..................................256.6 Attachment F Site Survey (Plant and Depot) ......................................266.7 Attachment G Preliminary Design Concept .........................................266.8 Attachment H Permit to Install .............................................................266.9 Attachment I Proposed Agreement ...................................................266.10 Attachment J Preliminary Geotechnical Report ..................................266.11 Attachment K Labor Management Cooperation Agreement ................26

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    3/250

    BWL Reo Town Plant Page 3 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    1 General Information & Requirements

    1.1 General Information

    The Lansing BWL (Owner) is soliciting Proposals (Proposals) for selection of a

    Construction Manger at Risk firm (CM) for the Reo Town Plant (Project), inaccordance with the terms, conditions, and requirements set forth in this Request forProposal (RFP). This RFP is part two of the three part selection process previouslydescribed in the Request for Qualifications (RFQ).

    Only the Recipients of this RFP previously selected by the Owner, through theQualifications step, to advance to the second step of this process will be allowed topropose on this Project. As such, the Owner will not consider Proposals fromindividuals that did not adequately respond to the RFQ and were not specifically invitedto respond to this RFP.

    This RFP requires specific technical responses regarding the selected firms approach andability to provide the services required for this project. Based upon the review of this

    Proposal, some or all of the respondents will be required to attend an interview with theOwner to support their proposal and answer any additional questions.

    The successful firm must demonstrate to the Owner that they best meet the Criteriadefined in this RFP, and the previously submitted RFQ.

    After the interview process has been completed and by utilizing weighted averageselection criteria, the Owner may then identify the firm that provides the overall bestvalue to the Owner and request further clarifications of that firm, or enter into finalnegotiations for a professional services Agreement for the Project.

    1.2 Public Information

    The BWL is subject to the Freedom of Information Act (MCL 15.231 et seq.). Allinformation, documentation, and other materials submitted in response to this solicitationare considered non-confidential and/or non-proprietary and are subject to publicdisclosure. The BWL will make the compiled information available for public inspectionat the end of its evaluation process.

    1.3 Type of Contract

    The selected firm shall enter into the Owners Agreement for Construction ManagementServices included within this RFP. The Owner intends to execute this document asprovided herein except for the incorporation of information required to complete theAgreement. Any requested modifications to the terms and conditions must be clearly

    defined by the Respondent in their Proposal for consideration by the Owner. Requestedmodifications to the Agreement should be limited and may be considered relevant in theselection process. Owner will not consider any other form of agreement submitted by theRespondent.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    4/250

    BWL Reo Town Plant Page 4 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    1.4 Clarifications and Interpretations

    Requests for information must be provided in writing to the Point of Contact andsubmitted no later than May 9, 2011.

    Any clarifications and/or interpretations of this RFP that materially affect and/or changeits requirements will be issued by a written Amendment by the Owner and sent to each

    qualifying firm. Firms shall be responsible to acknowledge receipt of and incorporateeach into its Proposal.

    Interpretations and/or clarifications in any other form, including oral statements, will notbe binding on the Owner and should not be relied on in preparing the Proposal

    The Owner will allow all Respondents the opportunity to schedule an optional 1 hourprivate consultation with the Owner for no more than 2 members of the Respondingteam. This consultation will not allow for any presentation of marketing or proposalinformation of any kind and is being offered solely for the benefit of allowing theRespondent to ask detailed questions about the project. Any questions raised during thisconsultation may be answered to all Respondents via Addendum to the RFP if suchquestions require modifications to the requirements of the RFP. Respondents must

    contact the Owner through the Point of Contact listed in this RFP to set up thisconsultation.

    Any other contact with the Owner, EA or Agents of the Owner during this solicitation,other than through the P.O.C, may result in disqualification of Respondent from furtherconsideration.

    1.5 Submission Requirements

    The submission due date for sealed Proposals is Thursday May 19, 2011 at 2:00 P.M.Local Time as specified on the Notice to Bidders. Any proposals received after theestablished time and date will be returned unopened and excluded from consideration.

    Firms shall be required to submit eight (8) copies of their Proposal which shall includethe following: eight (8) identical copies of the Proposal package, along with one (1)electronic submittal copy in non-protected, Adobe PDF format. Each copy of theProposal package must include an original signature to be included on the Proposaldocument submitted. Electronic copies shall be on a USB Flash Drive or DVD within thesealed package.

    Firms are hereby notified that the Owner will not acknowledge and/or receive Proposalsthat are delivered and/or sent by telephone, facsimile (fax), or electronic mail (e-mail).

    Firms are hereby notified that late Proposals will not be considered.

    Proposals will not be returned to Respondent.

    Proposal materials must be enclosed in a sealed envelope, box or container, and

    addressed as specified in the Notice to Bidders, and received no later than the date andtime listed above.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    5/250

    BWL Reo Town Plant Page 5 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    1.6 Point-Of-Contact

    The Owner designates the following person as its representative and Point-of-Contact for thisRFP. Respondents shall restrict all contact with the Owner and direct all questions regarding thisRFP, including questions regarding terms and conditions, to the Point-of-Contact person.

    Pete Kramer

    Owners Representative

    Reo Town Plant

    1232 Haco Dr.

    Lansing, MI 48912

    [email protected]

    Ship/Mail Clearly Marked Proposals to:

    Lansing BWL

    Attn: Dan MacLennan

    Manager, Purchasing and Warehouse Operations

    Reo Town Plant- Proposal

    1110 S. Pennsylvania

    Lansing, MI 48912

    1.7 No Reimbursement for Costs

    Respondents acknowledge and accept that any costs incurred from their companysparticipation in this RFP process shall be at the sole risk and responsibility of theRespondent. Owner shall not reimburse or otherwise compensate Respondents for thecost of submitting a Proposal.

    1.8 Eligible Respondents

    Only individual firms or lawfully formed business organizations may apply (this does notpreclude a firm from utilizing consultants). The Owner shall contract only with anindividual firm or a formalized business organization that submits a Proposal.Respondents shall demonstrate proper registration and licensing of their firm related tothe services requested in this RFP.

    1.9 Evaluation of Proposal

    The evaluation of the Proposal shall be based on the requirements described in this RFP.

    Following the Owners selection process, some or all of the respondents will then beinvited to the final stage (Part 3 Owners Selection Committee Interview).

    1.10 Owners Reservation of Rights

    The Owner may evaluate the Proposal based on the anticipated completion of all or anyportion of the Project. The Owner reserves the right to divide the Project into multiple

    http://c/Users/owner/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/RTW4P50L/[email protected]://c/Users/owner/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/RTW4P50L/[email protected]://c/Users/owner/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/RTW4P50L/[email protected]
  • 7/31/2019 Lansing BWL: REO Town construction RFP

    6/250

    BWL Reo Town Plant Page 6 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    parts (including the components of services outlined in this RFP), to reject any and/or allProposals and re-solicit for new Proposals, or to reject any and all proposals andtemporarily or permanently abandon the Project. Owner makes no representations,written or oral, that it will enter into any form of agreement with any respondent to thisRFP for any project and no such representation is intended or should be construed by the

    issuance of this RFP.

    1.11 Acceptance of Evaluation Methodology

    By submitting its Proposal in response to this RFP, respondent accepts the Ownersevaluation process and acknowledges and accepts that determination of the mostqualified firm(s) and the best value to the Owner will require subjective judgments bythe Owner related to the evaluated firms response to the Criteria outlined in section 4 ofthis RFP. Respondent hereby waives any claim against the Owner related to thisevaluation method.

    2 Project Summary

    2.1 General Scope of Work

    Generally, the scope of the CM services under this RFP will include all Pre-Construction,Construction, Start Up, Commissioning, Performance Testing, Certifications, and Close outresponsibilities for the completion of the Reo Town Plant in its entirety, including but not limitedto the general elements summarized below.

    Infrastructure, Utilities, and Site Improvements for entire BWL property includingconnection to the public infrastructure (including Depot site improvements and utilities)

    Building Structure, Architecture, Enclosure, Mechanical, Electrical, and Plumbing, forthe Plant facility

    Core and Shell for approximately 45,000 sf office as a component of the Plant facility

    Expedite delivery, Receive, Inspect, Properly Store, Install, Start up, and Commission allEquipment Provided by the Owner.

    Provide the Balance of Plant and all Systems required for completed facility

    Start Up, Commissioning, Performance Testing, and Transition (Turn Over, Training) forall Plant systems.

    Plant Switchyard and On-Site Structures required to connect to existing 138 kVtransmission systems.

    Outgoing Steam Line construction from the Plant to the Property Line. All other CM work required for a complete and operational facility not specifically

    excluded in the following section.

    More detailed CM Scope of Work assignments and responsibilities are described in AttachmentB to this RFP and the Agreement.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    7/250

    BWL Reo Town Plant Page 7 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Services specifically excluded from the Work requested under this RFP are:

    Construction Management services for the commercial interiors of the 45,000 sf PlantOffice Building.

    Construction Management services for the adaptive reuse of the historic Grand TrunkWestern Depot

    Offsite Utilities and Infrastructure projects required beyond the Owner's Property Line, orotherwise provided by the Owner except for the connection of site utilities to the publicinfrastructure.

    Decommissioning and Demolition work in the Existing Moores Park Station.

    3 Project Milestone Schedule

    The following schedule outlines the general milestones required for the design and construction

    of the Reo Town Plant subject to adjustment and modification by the Owner. This schedule issubject to the final negotiation of major equipment procurement dates. Proposals must addressany anticipated modifications to this schedule.

    Activity Completion Date

    Issued CTG/STG/HRSG Bid Packages April 18, 2011

    Issued CM RFP April 19, 2011

    CTG/STG/HRSG Bids Due May 6, 2011

    CM Proposals Due May 19, 2011

    CM Interviews May 26, 2011

    Award CM Contract June 1, 2011

    Award CTG/STG/HRSG Purchase Orders June 1-June 15, 2011Owners Commencement of onsite Construction Activities (Steam Vault) June 15, 2011

    Bid/Award Piling and Site Utilities/Infrastructure Packages July 1/July 30, 2011

    CM Commence On Site Construction Activities August 1, 2011

    Receive Foundation, Structure, Enclosure bid package August , 2011

    Receive Balance of Plant Bid Documents December, 2011

    Submit GMP Proposal January 30, 2012

    Receive CTG/STG/HRSG Equipment June/July 2012

    Mechanical Completion of Plant April 1, 2013

    Substantial Completion/Commercial Operations Date June 1, 2013

    Final Completion & Close Out August 1, 2013

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    8/250

    BWL Reo Town Plant Page 8 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    4 Requirements for Proposal

    Respondents shall carefully read the information contained in the following Criteria and submit aresponse to all questions in this section, formatted as directed in Section 5Format Requirementsfor Proposal. Incomplete Proposals may be considered non-responsive and rejected in their

    entirety.

    4.1 Criteria 1: Update of Qualifications

    Based on the additional information provided in this RFP, Respondent may updatepreviously submitted Qualifications to reflect the current understanding of the ProjectRequirements.

    Re-submit team member chart and/or description of individual team memberresponsibilities identifying any changes from the previously submitted Qualifications.

    For any team members, who are not full time employees of the Respondent, providespecific details as to the contractual relationship between the CM and the individual teammembers or consultants. Describe sufficiently the contractual obligation such individualsor consultants have to the Owner and how the performance of such services are to beguaranteed to the satisfaction of the Owner.

    4.2 Criteria 2: Pre Construction Phase Services

    Provide your approach for pre construction phase services on this project. Specificallyaddress your work plan and description of tasks required to ensure the project is plannedin accordance with the Owners Operating Characteristics, the Construction Documentsand within the Owners required Budget and Schedule.

    Describe your approach to secure the performance of sub contractors. If products other

    than PLM Bonds are proposed for this project, provide a description of the methodsproposed and the costs of such products. Include the costs of such products in youropinion of probable cost.

    Provide your opinion of probable cost for the completion of the Plant in the formatrequested in Attachment D. The Owner has just released bidding documents for theCTG, HRSG, and STG Equipment packages. Therefore Respondents must not contact orrequest preliminary pricing from vendors for those three items, or interfere with thatbidding process in any way. Any opinion of cost on those three items must be providedbased on your historical data and experience as a qualified bidder for this work.Maintain the separation of costs for all other Major Equipment being provided by theOwner. Identify your anticipated Cost of the Work as described in the Agreement.

    Include the cost of your services and associated items, proposed as multipliers to the Costof Work, as required in Criteria 9.

    Describe your proposed methodology for providing a Guaranteed Maximum PriceProposal as described in the Agreement in accordance with the Milestone Schedule.Specifically address your approach to establishing the GMP Contingency.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    9/250

    BWL Reo Town Plant Page 9 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    4.3 Criteria 3: Construction Phase Services

    Describe your approach for construction phase services on this project. Specificallyaddress your work plan and description of tasks required to ensure the project iscompleted in accordance with the Construction Documents.

    Describe your understanding of the critical issues, administrative challenges, and

    opportunities associated with providing services for the Project and your strategy formanaging and resolving these issues.

    Discuss how your approach may be unique or more beneficial to the Owner than others.

    4.4 Criteria 4: Start Up and Commissioning Plan

    Provide your work plan and description of tasks for the Start Up and CommissioningResponsibilities required for this project. Describe specifically if these services arebeing provided by your own staff members, or through start-up and commissioningconsultants or leased employees.

    Describe how your team will interact with the EA and the Owners Operators during this

    phase. Describe specific examples where the staff proposed on this project has successfully

    managed the start up of similar cogeneration facilities. Describe in such examples, yourunderstanding and experience with the requirements specific to the LM6000 and theSTG-800 Turbine systems being considered for this project, and the associated HRSG/STG cycles unique to the Reo Town Plant. Describe if the staff for your start up teamwould change based on the equipment selected by the Owner.

    Describe why your team is best suited to manage this critical element of the project.

    4.5 Criteria 5: Coordination of Information.

    Describe your experience working with the Smart Plant design platform being used bythe EA on the Project. Discuss how you propose to coordinate the work of your staff andtrade contractors with this design platform.

    What means and methods do you propose to use for the coordination of work between theprimary trade contractors on this project.

    4.6 Criteria 6: Detailed Project Schedule

    Describe your approach to establish and manage the Project Schedule and who willprovide the overall leadership of the project scheduling process. Discuss the tracking ofresources, manpower, and installation of commodities and critical components in thescheduling process.

    Based on the information provided in this RFP provide a detailed project scheduleidentifying all critical path elements required to meet the milestone schedule.

    Confirm that your proposed schedule reflects the most optimal schedule for the overallfinancial benefit of the owner related to overtime and sequencing of work and will resultin the completion of the Project in a reasonable and expedient manner.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    10/250

    BWL Reo Town Plant Page 10 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Identify any recommended modifications to the proposed milestone schedule which mayprove financially beneficial to the Owner if accepted. Provide justification for any suchrecommendation and the anticipated cost benefit to the Owner.

    4.7 Criteria 7: LEEDCertification Support and Administration

    The Owner intends to obtain LEED Certification for the Project. Describe the servicesincluded in this Proposal related to the management of the LEED Certification processfor this Project.

    Provide an alternate costs proposal to serve as the LEED Administrator for all projects onthe Owners Site. Include all services required to coordinate and administer the LEEDCertification process for this Project, as well as the Plant Offices, and the DepotRenovation Projects. LEED Administrator would be responsible for incorporating allrequired documentation and coordinate the LEED Certification requirements for all threedesign teams, and construction teams related to those projects.

    4.8 Criteria 8: Site Logistics Plan Provide a detailed site logistics plan describing your approach to deal with the constraints

    of the project site and requirements throughout all phases of the project. Provide yourplan for receipt, storage and installation of major and supplementary equipment. Identifyerection sequence and site requirements for critical project elements. Response may bea combination of narrative and graphical descriptions of the plan.

    4.9 Criteria 9: Financial Proposal

    Based on the proposed Agreement, provide a detailed cost proposal for CM Services.Respondent shall propose the cost for all services as described in Articles 4, 5 and 6 of

    the Agreement. Provide proposed costs for the following categories. Guaranteed Maximum Price for Pre Construction Services and Reimbursable

    Expenses.

    Guaranteed Maximum Price for CM Labor and General Conditions.

    Construction Managers Fee.

    Allowance for all Bonds and Insurance.

    Proposed GMP Contingency

    Propose changes to the base proposal for the alternate services requested inCriteria 7 and 10.

    4.10 Criteria 10: Alternate for CCIP

    Describe your capability and approach to providing a contractor controlled insuranceprogram (CCIP) for the project including program coverage and structure, enrollingsubcontractors, and sharing of risk and reward with LBWL. Provide a brief cost/benefitanalysis including an estimate of fixed cost, contractor/sub-contractors deductions, andvariable (loss) costs and compare to the standard method currently described in the

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    11/250

    BWL Reo Town Plant Page 11 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Agreement. Describe any additional services or charges that you would apply if youprovided a CCIP.

    Describe your overall opinion related to the feasibility of this alternate.

    4.11 Criteria 11: Understanding and Acceptance of Owners Agreement

    Provide a statement of understanding and acceptance of the proposed Agreement betweenthe Owner and CM.

    In order to facilitate and expedite execution of the Agreement, any requestedmodifications to the Scope of Work, or Terms and Conditions specified in the Agreementmust be provided in the Proposal. Respondents may request reasonable modifications;however substantial requested modifications or qualifications may affect the Ownersconsideration for selection.

    4.12 Criteria 12: Execution of Proposal Form

    The Respondent must complete, sign and return the Proposal Form included asAttachment F. The company official(s) who are authorized to commit to such a submittalmust sign this document. Failure to sign this form will subject the submittal todisqualification.

    5 Format for Proposal

    5.1 General Instructions

    Proposals shall be prepared simply and economically, providing a straightforward,concise description of the firms ability to meet the requirements of this RFP. Emphasis

    shall be on the quality, completeness, clarity of content, responsiveness to therequirements, and an understanding of Owner's needs.

    Proposals shall be a MAXIMUM of eighty (80) printed pages, including any appendix oradditional information for consideration. The cover, table of contents, divider sheets andProposal Form do not count as printed pages. Pages with printing on both sides shall beconsidered as two (2) pages.

    Respondents shall carefully read the information contained in this RFP and submit acomplete response to all requirements and questions in the order presented. IncompleteProposals will be considered non-responsive and subject to rejection.

    Proposals and any other information submitted by respondents in response to this RFPshall become the property of the Owner.

    Proposals that are qualified with conditional clauses, alterations, items not called for inthe RFP documents, or irregularities of any kind are subject to rejection by the Owner, atits option.

    The Owner makes no representations of any kind that an award will be made as a resultof this RFP, or subsequent Interviews. The Owner reserves the right to accept or reject

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    12/250

    BWL Reo Town Plant Page 12 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    any or all Proposals, waive any formalities or minor technical inconsistencies, or deleteany item/requirements from this RFP when deemed to be in Owner's best interest.

    Proposals shall include responses to all Criteria described in Section 4 of the RFP.

    Failure to comply with all requirements contained in this RFP may result in the rejectionof the Proposals.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    13/250

    BWL Reo Town Plant Page 13 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    6 Attachments

    6.1 Attachment A- Project Description

    In addition to the General Description of the Project provided in section 2 of the RFP, the

    following information is provided to further define the Project.

    1. Owners Legal Name

    Lansing Board of Water and Light

    1232 Haco Dr.Lansing, MI 48912

    2. Site Definition

    The Project Site is commonly defined as 1203 S. Washington Avenue, Lansing,

    MI 48910

    The Property limits are as provided on Attachment C Zoning for this project falls under two categories. The western 90 of the

    property is zoned F-Commercial District. The balance of the Site to the East is

    zoned H-Light Industrial. Zoning interpretations have been conducted allowing

    for the Reo Town Plant to be constructed under Light Industrial zoning.

    3. Required Operating Characteristics

    This project is designed to replace two major production assets in the BWLs central steam andelectric operations. The most immediate replacement will be the Moores Park steam production

    plant. Additionally, the new plant will eventually replace electric capacity and energyproduction from Eckert electric generating units 1, 2, and 3.

    Steam Production Requirements

    The Owner has maintained a central steam supply system for 91 years. The central steam systemconsists of the Moores Park steam production facility and a distribution system comprised of twogeographical sections.

    The Moores Park steam production facility is located adjacent to the Eckert electric generatingplant. Moores Park consists of four stoker bottom, coal fired boilers that produce steam, but notelectricity. The steam produced at Moores Park is used to supply heat and hot water to buildingsin downtown Lansing.

    The distribution systems first geographical area, the downtown central steam loop, consists of12 miles of distribution mains including a 12 inch and an 18 inch high pressure transmission

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    14/250

    BWL Reo Town Plant Page 14 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    main that encompass an 80 square block area. This section also feeds a major industrialcustomer through two dedicated 12 inch high pressure mains. The second section, supplied by a20 inch high pressure main, served three major industrial facilities, which are now all closed.This section has been capped but remains in place for possible future development of the formerindustrial sites.

    Currently, the BWL has approximately 225 steam customers in its downtown central steam loop,with maximum demand of approximately 300,000 pounds of steam per hour and 1,000,000 Mlbsof steam consumption per year. Steam sales declined sharply from 2005 to 2008 with theretirement of major industrial facilities in Lansing. Sales have stabilized since 2008 and areexpected to grow very modestly with the addition of new customers. Steam production loadcurves are shown below:

    Maximum send out to our customers is assumed to be 300,000 lbs/hr. It is assumed that the

    proposed plant equipment can be over-fired to meet the peak demand. Total send out steam forthe composite years is about 989,000 Mlbs

    Actual steam production is the sum of send out and internal uses. Internal uses include steam fordeaeration, feed water heating and blow down. Send out production conditions are 275 psig atdual temperatures of 480F and 650F.

    Steam Production Load Duration CurveSteam Leaving Moores Park to all Customers

    0

    100,000

    200,000

    300,000

    400,000

    500,000

    600,000

    700,000

    800,000

    0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000

    Hour of Year

    Steam

    ProductionFlow,

    lb/hr

    FY 2004 FY 2005 FY 2006 FY 2007 FY 2008 FY 2009

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    15/250

    BWL Reo Town Plant Page 15 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    Since steam must be produced locally, the Plant will be designed to meet maximum load with thelargest steam producer out of service. Thus the system consists of three half sized units eachcapable of producing at least 150,000 lb/hr for a total capacity of 450,000 lb/hr. This could beany combination of gas fired boilers and gas turbines with heat recovery steam generators.

    Electric Generation Requirements

    The BWL currently has a maximum retail demand of approximately 500 MW and retail sales ofapproximately 2,200,000 MWhs annually. The BWL also sells electric energy and capacity towholesale customers. Annual sales are approximately 1,100,000 MWhs annually.

    All of the BWLs generating units are base load coal fired units, six at the Eckert plant and oneunit at Erickson. Three of the Eckert units are relatively small, each with 40 MW gross capacity,and lack reheat cycles and are, therefore, comparatively inefficient. The BWL anticipatesretiring these units by the end of 2015 due to their relative inefficiency, high fixed operation and

    maintenance costs, and projected environmental retrofit costs. The BWL also has a powerpurchase agreement for approximately 150 MW of capacity and energy from Detroit EdisonsBelle River generating plant.

    The anticipated electric generation configuration consists of two combustion turbine generators(CTG), each paired with a heat recovery steam generator (HRSG), and a steam turbine generator(STG), with condenser. The steam turbine will be used when excess steam is available due tolow central steam demand conditions. This will allow quicker steam load following and increaseelectric generation and capacity.

    In order to meet peak electric needs and qualify to provide ancillary services, each combinedcycle combination will include a bypass stack for combustion turbine electricity production only.Otherwise, it is anticipated that the combined cycle operation, making full use of the steamturbines, will occur for the months of June through September. Actual combined cycle operationwill depend on market and demand conditions.

    4. Local Building Authority

    The project is within the jurisdiction of the City of Lansing, and must adhere to all

    local building codes and requirements of the Authority.

    5. Office Building Requirements

    This Project must incorporate general office space for approximately 180 BWLemployees.

    Programming and specific office uses have not yet been developed, but are

    anticipated to require approximately 45,000 gross square feet. This office space

    does not include office or program space required for plant operations or

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    16/250

    BWL Reo Town Plant Page 16 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    maintenance functions. Plant specific office and maintenance functions will be

    provided within the Plant Facility.

    6. Building Architecture

    The building is intended to fit in well with the Reo Town district and the

    neighboring areas.

    The Owner desires the building to be constructed with durable exterior materials

    similar to the other BWL owned properties in the downtown Lansing area. Long

    term life cycle costs for building exterior materials are important. Stone, brick,

    precast concrete, glass & metals, or other suitable durable materials will be

    considered.

    The building shall also be aesthetically pleasing and functionally appropriate.

    7. Site and Infrastructure Description

    Outgoing Steam Delivery shall be designed by the Owner. The exiting steam will

    be provided in two 12 delivery lines each at the same pressure, but will provide

    steam to the district at 480F and 650F. The CM shall install all steam lines fromthe Plant to the Property Limit and coordinate with the Owner and the Owner's

    Contractor for the transition of work to the Owners off site utility contractor.

    New Water Services for the plant shall be designed and constructed by the Owner

    to the meter inside the Plant or to the flange for the fire protection system. The

    CM shall coordinate with the Owner for the installation of such lines. This

    includes all domestic, fire protection, or process water sources for the Project.

    The Permanent Natural Gas service shall be provided by Consumers Energy and

    will enter the site from South Street. The service is currently being designed as a

    12 service, providing a nominal 250psi to the Project. The CM shall coordinate

    with the Owner and Consumers Energy regarding the installation of this line and

    metering structures on the site.

    All telecommunications and miscellaneous services shall be provided by the

    Owner to an appropriate location within the Plant. The CM shall coordinate with

    the EA to provide sufficient site and building infrastructure to facilitate the

    installation of all telecommunications requirements by the Owners vendors.

    Site storm and sanitary systems shall be provided by the CM to tie into the City of

    Lansing utility systems. CM shall coordinate with the Owners other Contractors

    and the City of Lansing to connect all utility lines from the Plant property to the

    public infrastructure system. All site utility descriptions apply to both the Plant and the Depot facilities.

    8. Owners Other Projects

    Coinciding with the Work described in this RFP, the Owner intends to enter into aseparate General Contract Agreement or Agreements for the adaptive reuse andrenovation of the Reo Town Depot. The Depot is located on a separate legal

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    17/250

    BWL Reo Town Plant Page 17 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    parcel, adjacent to the Reo Town Plant. The work on this Depot is intended tobegin in the summer of 2011 with the replacement of the building roof andstructural repairs. The balance of work for the renovation of the depot will start inthe first quarter 2012. The Depot Project includes connection to Utilities startingat 5 outside of the building and all Architectural, Structural, Mechanical and

    Electrical work inside the building. All Site Improvements outside the buildingfootprint remain in the scope of the Plant Construction Manager.

    The Owner intends to enter into a separate General Contract Agreement for theinterior construction related to the commercial interiors for the Reo Town Offices.The Offices will be located in the approximately 45,000 gsf core and shell officebuilding provided by the Reo Town Plant CM. The CM shall be required to assistin the coordination of the transition points between the CMs trade contractorsand the Office General Contractor to ensure proper definition and coordination ofwork is provided in the respective bid packages prior to issuing for constructionbids.

    The Owner intends to enter into a separate General Contract Agreement for the

    construction of the off site steam utility distribution work required to tie the ReoTown Plant steam system into the existing distribution system .

    9. Equipment Procurement

    The Owner intends to directly purchase the following Major Equipment packages

    in coordination with the EA. The CM shall be required to receive, inspect,

    properly store, install, commission and start up all equipment provided by the

    Owner as described in the Scope of Work and the Agreement. All other

    equipment shall be furnished and installed by the CM. For the equipment

    currently out for bids, Respondents may download the major equipment bid

    documents on the Lansing BWL website.

    i. Combustion Turbine Generators (currently out for bids)ii. HRSGs (currently out for bids)

    iii. Steam Turbine Generators (currently out for bids)

    iv. Steam Condensers

    v. Auxiliary Boiler

    vi. Gas Compressors

    vii. Cooling Tower

    viii. Water Treatment System

    ix. Boiler Feed Pumps

    x. Black Start Generator

    xi. 138kV Switchyard

    xii. Step-Up Transformers

    xiii. DCS

    xiv. 15kV Switchgear

    xv. CEMS

    xvi. Sample Panel

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    18/250

    BWL Reo Town Plant Page 18 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    10.Labor Management Cooperation Agreement

    The Owner intends to require the CM to enter into a Labor Management

    Cooperation Agreement with the Michigan Construction Building Trades for thisproject so long as terms consistent with those currently in effect on similar

    projects in the region are negotiated to the satisfaction of the Owner. A copy of

    the basic Agreement intended for this project is provided as Attachment K.

    The General Contractor for the Reo Town Office interiors shall be required to

    independently accept and execute the final Labor Management Cooperation

    Agreement negotiated by this CM for their work within the Office Core and Shell.

    The General Contractor or Contractors for the Depot Renovation will be required

    to provide their work under current prevailing wage requirements. Final

    negotiations between the CM and the Building Trades must accommodate this

    requirement as a prerequisite for establishing an Agreement on the Plant.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    19/250

    BWL Reo Town Plant Page 19 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    6.2 Attachment B- CM Scope of Work

    For further clarification to the General Responsibilities described in section 2 of the RFP, and theAgreement, the following items are identified, to describe in more detail, the required Scope ofWork for the CM. They shall not be interpreted to be inclusive of all services or obligations ofthe CM, and are meant to augment the services required in the Agreement. The CM shall be

    responsible for all Procurement and Construction Work required, complying with the ContractDocuments and the Agreement, other than for those responsibilities specifically excluded ornoted as to be provided by others.

    Pre-Construction Phase

    1. Provide all Preconstruction phase services as described in the Agreement.

    2. Perform constructability reviews, and provide comments and recommendations as design

    develops.

    3. Perform detailed estimating throughout project duration including for various sub-elements

    of the project as needed or directed by the Owner to facilitate decision making.

    4. Provide value analysis and value engineering services, including life cycle cost analysis andrecommendations for cost savings.

    5. Negotiate and execute the Labor Management Cooperation Agreement for the benefit of the

    Owner as described in this RFP.

    6. Receive technical specifications and construction documents from EA and prepare bid

    packages for procurement of all equipment, labor and services required for a complete

    project. All bid packages must be established to allow for the maximum competitive benefit

    to the Owner. Where possible, create bid packages appropriate to allow for involvement of

    locally available trade contractors and labor. Manage procurement responsibilities in

    accordance with the requirements of the Owner.

    7. Prequalification of bidders as may be necessary for critical elements of the project.

    8. Procure Design/Build trade contracts for select items of work as specified in the Contract

    Documents.

    9. Develop project specific Division 00 and Division 01 front-end specifications and scope of

    work assignments for all subcontracted work, and submit to Owner and EA for review,

    comment and approval prior to issuing for bids.

    10.Prepare and maintain a comprehensive project budget including Owner direct costs related to

    the Plant in a format accessible by the Owner.

    11.Provide all project planning activities as required to support LEED Certification for the

    Work.12.Provide and Maintain schedules for various levels of detail, including but not limited to:

    a. Master Project Schedule describing engineering, procurement, and construction

    activities for the entire project.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    20/250

    BWL Reo Town Plant Page 20 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    b. Detailed commodities installed report for major elements of the work tracking

    projected installation quantities/manpower vs. actual installed quantities. These

    reports must be prepared and managed for all critical balance of plant elements.

    c. Detailed start-up and commissioning schedule

    13.Prepare a Guaranteed Maximum Price Proposal for the Work in accordance with the

    Agreement at a time determined to be most beneficial by the Owner.

    Procurement Management

    14.Provide all procurement management services for equipment provided under this Agreement.

    15.Procure equipment under reasonably available commercial terms most beneficial to the

    Owner related to cost, schedule, performance and warranty.

    16.Ensure all Engineered Drawings provided under this Agreement are expedited to allow for

    timely completion of the EAs subsequent design responsibilities. Process all approval

    documents as required by the EA to coordinate with their document control system.

    17.Assist the EA in expediting delivery of Owner provided equipment following approval ofEngineered Drawings as necessary to maintain project schedule.

    18.Maintain detailed procurement status logs and report on a bi-weekly basis.

    19.Manage all Receipt, Inspection, and Storage of all Equipment including major equipment

    provided by the Owner.

    Construction and Contract Management

    20.Provide overall management and control of the entire Project Site including all perimeter

    security and site logistics as required.

    21.Provide all construction responsibilities as required to construct and complete the Facility as

    an operable and maintainable cogeneration facility in accordance with Prudent UtilityPractices and the Construction Documents.

    22.Manage the erection and installation and start up of all equipment and materials including

    major equipment provided by the Owner.

    23.Provide testing services for all equipment and systems

    24.Temporary construction facilities and services including site security measures.

    25.Maintain as built documentation of all systems on a monthly basis.

    26.Maintenance of the Soil Erosion and Sedimentation Control Plan

    27.Maintain site and facilities in a clean and orderly state.

    28.Provide all equipment, tools, construction materials and craft labor until all testing is

    complete

    29.Provide all Construction Management activities required to support the LEED Certification

    process and forward all documentation to the LEED Administrator. Coordinate all LEED

    Certification activities with those of the Owners other Consultants or Contractors.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    21/250

    BWL Reo Town Plant Page 21 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    30.Coordinate with the Owners other Contractors to provide access to other Projects on site

    ensuring productivity and cooperation for all parties to the benefit of the Owner. Provide for

    a separate dedicated entrance to the Depot Site from Washington Avenue.

    31.Provide a single site Waste Management Plan incorporating all waste and debris for the Reo

    Town Plant, Plant Office Interiors, and the Depot Renovation projects in accordance with the

    requirements for LEED Certification. Provide all Waste Management Documentation to the

    LEED Administrator.

    32.Provide a separate and dedicated office trailer for the Owner on site and in close proximity to

    the CM. Allow for meeting space for up to 8 people with white board wall and office space

    for up to three. Provide all furniture, temporary power, security, and wireless internet

    connection as required by the Owner. Provide 4 dedicated adjacent parking spaces for

    Owners use.

    33.CM shall be responsible for the cost and replacement of any spare parts used or lost by the

    CM or its subcontractors from the Owners stock prior to Substantial Completion for all

    equipment provided by the Owner, or the CM.34.The CM shall coordinate with the Owner and Owners vendors to provide all lubricants and

    chemicals associated with construction and start up of the facility, the cost of which shall be

    by the Owner.

    35.Provide site specific safety plan for the project and provide a designated Safety Officer on

    site for the duration of significant construction activities. Safety Officer shall coordinate with

    Owners other Contractors working on site to ensure all construction activities are conducted

    in accordance with the highest standard of care. Provide notification to Owner of all safety

    incidents, and provide copy of all reports to owner within two days of submitting reports

    pursuant to MIOSHA requirements.

    36.Provide quality control services and enforcement of quality standards for all construction

    activities to assure compliance with design documents and specifications, including but not

    limited to:

    a. Shop fabrication inspections and reporting, as required

    b. Material and equipment receiving inspections and reporting

    c. Construction installations and workmanship, certifications and reporting as specified

    d. Start-up testing and commissioning compliance and reporting

    e. Plant and major equipment performance testing and reporting

    f. Environmental emissions testing as required by the Permit to Install.

    Start Up, Testing, Commissioning

    37.Develop, schedule, and execute the Start Up Plan, and Testing Protocol as required in the

    Agreement. Coordinate with Owner and Owners designated operators during all start up,

    commissioning, and performance testing activities.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    22/250

    BWL Reo Town Plant Page 22 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    38.Coordinate and schedule all activities related to all equipment vendors whether provided by

    the CM or Owner.

    39.Maintain documentation of all start-up, commissioning and testing activities and results

    40.Perform and document performance testing for both overall plant performance and major

    equipment performance.

    41.Maintain overall responsibility for the Plant and activities on site until Substantial

    Completion.

    Close Out and Turnover

    42.Coordinate all closeout requirements including all subcontractors, vendors and equipment

    suppliers.

    43.Coordinate with the EA to provide all Owner Training and Documentation required for

    proper turnover of all Plant systems and documentation.

    44.Assemble final operations and maintenance manuals, as approved by the plant engineer and

    Owner. Provide two (2) final bound set of all operations and maintenance manuals, and oneconsolidated and organized electronic file copy in an efficiently organized format suitable for

    ease of use by the Owner. Organize documents so that the Plant Operations are organized

    separately from the Office Building Systems.

    45.Maintain project closeout logs and project documentation, and assemble into organized files

    for final transfer to Owner.

    46.Coordinate with the EA to provide final As Built documentation in electronic form.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    23/250

    BWL Reo Town Plant Page 23 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    6.3 Attachment C- Proposal Form

    Provide the following business and contact information:

    Legal Name: Federal ID or Social Security Number:

    Address: State of Incorporation

    City: State & Zip: Primary E-Mail:

    Type of Organization: __ Corporation __ LLC __ LLP __ Sole Proprietor __Partnership __ S-Corporation

    __ Other (Explain)

    Office Phone: Alternate Office Phone: Office Fax:

    Primary Contact: Contact Phone: Contact Fax:

    Contact Mobile: Contact E-Mail: Website URL:

    The undersigned Bidder hereby acknowledges receipt of the following addenda:

    Enter addenda numbers if applicable

    The undersigned Bidder states that this proposal is made in conformity with the Proposal Documents andagrees that, in the event of any discrepancies or differences between any conditions of their proposal andthe Proposal Documents, the provisions of the latter shall prevail. No verbal or written agreements or

    understandings considered or entered into prior to signing of a contract in the form of a purchase order,shall be binding after the signing of the contract unless incorporated in the contract.

    The undersigned Bidder certifies that this proposal is made in good faith, without collusion or connectionwith any other person or persons submitting proposals for the work.

    Company Name:

    Signature:

    Name:

    Title:

    Date:

    END OF PROPOSAL FORM

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    24/250

    BWL Reo Town Plant Page 24 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    6.4 Attachment D Opinion of Probable Cost Template

    Provided in the documents attached to this RFP.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    25/250

    BWL Reo Town Plant Page 25 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    6.5 Attachment E General Conditions Cost Format

    Respondent shall utilize the following format to propose Pre-Construction and ConstructionGeneral Conditions as requested in the RFP. Provide the Construction Managers Personnel andStaffing Plan, and the General Conditions Costs Budget as described in section 5.3 of the

    Agreement. Respondent shall propose all reasonably appropriate General Conditions Costsbased on their experience with similar projects and in accordance with the Milestone Schedule.Provide detailed breakdown of all costs not otherwise anticipated to be included in the Cost ofthe Work.

    Staff Position Hours/Wk # Weeks Hourly Rate Total Cost

    GeneralConditions Item

    Quantity Unit Rate Total Cost

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    26/250

    BWL Reo Town Plant Page 26 of 26Reo Town Plant Construction Manager Request for Proposal

    Reo Town PlantLansing Board of Water and Light, 1232 Haco Dr. 2011-04-19 pwkLansing, MI 48912 Ph: (517) 702-6076 Fax: (517) 702-6855www.lbwl.com

    The following Attachments are included in this RFP

    6.6 Attachment F Site Survey (Plant and Depot)

    6.7 Attachment G Preliminary Design Concept

    6.8 Attachment H Permit to Install

    6.9 Attachment I Proposed Agreement

    6.10 Attachment J Preliminary Geotechnical Report

    6.11 Attachment K Labor Management Cooperation Agreement

    END OF SOLICITATION

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    27/250

    REO TOWN PLANTOpinion of Probable Costs Plant Grade Level (sf) 45,000Prepared by: Plant Mezzanines (sf) 28,800

    Corporate Offices (sf) 45,000

    Nominal Electrical Output (kW) 108,000

    Gross Steam Output (pph) 300,000

    Descriptions

    Owner Provided Equipment TotalsCombustion Turbine Generators

    Heat Recovery Steam Generators with Stacks

    Steam Turbine Generators

    Fuel Gas Compressors

    Auxiliary Boiler

    Cooling Tower

    Steam Surface Condensers

    Water Treatment System

    Boiler Feed Pumps

    Step-up Transformers

    15kV SwitchgearDistributed Control System

    Black-Start Gas Generator

    138kV Switchyard

    CEM Equipment

    Sample Panel

    Subtotal 0

    Cost of the WorkEquipment /

    Materials Installation Totals

    Install Owner Supplied Equipment 0

    Plant Building Core & Shell 0

    Office Building Core & Shell 0

    Balance of Plant Equipment 0

    Instrumentation and Controls 0

    Electrical Work 0

    Mechanical Work 0

    Balance of Plant Work 0

    Site Improvements/Infrastructure 0

    Subtotals 0 0 0

    General Conditions Cost

    Preconstruction Services and Reimbursables

    Construction Manager's Personnel Labor

    General Conditions Costs

    Subtotal 0

    Contingency

    Contingency

    Subtotal 0

    Subtotal 0

    Indirect Costs % Multiplier

    Construction Manager's Fee

    Permits and Insurance Allowance

    PLM Bonds Allowance

    Total 0

    Proposed Gross Values

    1 of 1

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    28/250

    Center Post ofSec. 21 (See Sheet 3)

    S.

    WashingtonAve.

    E. South St.

    S.

    GrandAve.

    C.N.R.R.

    E. 1/4 Corner ofSec. 21 (See Sheet 3)

    PlattSt.

    W. South St.

    N-S1/4Line

    E-W 1/4 Line

    N.E. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    N.W. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    S.E. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    S.W. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    Ea

    stLineofSection21

    F-8 G-8

    *Note: The Surveyed Parcel shown is part of a 5.3062 acre parcel (City of LansingParcel No. 33-01-01-21-261-004). A Lot Split Application must be submittedto the City of Lansing (and approved) before this parcel split can take effect.

    NORTH

    NORTH

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    29/250

    face of brick

    S. Grand Ave. (82.5')

    S. Washington Ave.(115.5' P.)

    PlattSt.

    E.

    Sou

    thSt.(82

    .5'P

    .)

    82.40' M.

    4.4

    0'M

    .

    Cana

    dian

    Na

    tiona

    lRa

    ilway

    137.75' M.

    E. 1/4 Cor. of Sec. 21

    82.40' M.

    82.35' M.

    82.25' M.

    82.75' M.Fd. P. top I.P.

    Fd. 1/2" bar in gravel driveway 82.60' M.

    Fd. bar with cap L. Bryan #25832

    Set 3/4" I.P. with alum. cap #30897

    Set 3/4" I.P. withalum. cap #30897

    210

    .45'C

    alc

    .

    5.4

    2'M

    .

    SetP.K.Nail

    Set 3/4" I.P. withalum. cap #30897

    1

    2

    3

    4

    5

    Sparrow

    'sSu

    bdivision

    ofBloc

    k200o

    fthe

    Orig.

    Plat

    Block 203,Orig. Plat of Lansing

    Block 202,Orig. Plat of Lansing

    Block 209,Orig. Plat of Lansing

    Block 201,Orig. Plat of Lansing

    Vac. S. Grand Ave.

    33' Alley

    Notes:

    1. Per F.E.M.A. N.F.I.P. Flood Insurance Rate Map(Community Panel No. 260090 0006 B), part ofthe extreme east end of the Surveyed Parcel iswithin the 100 Year Floodplain and/or the 500Year Floodplain of the Red Cedar River.

    2. Most site improvements existing on this parcel

    catch basins, storm sewer lines, utility polesand utility lines, etc.) are not shown on this survey.

    Surveyed Parcel (shaded)

    TelCom Bldg. Easement Area (cross-hatched)(*Ref. L. 2646, PP. 976-978 of Ingham Co., Mich. deeds)

    (*Ref. L. 2646, PP. 976-978 of Ingham Co., Mich. deeds)

    (*Ref. L. 2804, P. 609 of Ingham Co., Mich. deeds)

    10 ft. wide x 79 ft. long Drainage Ease. Area(*Ref. L. 2824, P. 1048 of Ingham Co., Mich. deeds)

    (E.

    1/4Cor.

    toCen.

    Po

    st)

    (formerly Lee St.)

    *65.83' C. North of 1/4 Line

    (formerly Lee St.)

    face of brick

    (incl. fencing, asphalt paving, curb & gutter,

    G-8

    191.93' M.

    71.60' M.

    Set 3/4" I.P. with alum. cap #30897

    (SurveyedDescriptionPointofBeginning)

    Setmasonrynailinasphaltdrive

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    30/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    31/250

    8ft.ch.lk.fc.

    Set 3/4" iron pipe with alum. cap #30897

    *Did not set -

    *Did not set - in fenced & secured yard

    210.45'Calc.

    metal-sided bldg. (enc.)

    NORTHScale: 1 inch = 30 feet

    4'

    4'

    8ft.ch.lk.fc.(enc.)

    in unstable slope

    Zayo Bandwith

    10 ft. wide x 79 ft. long Drainage Ease. Area (shaded)*Ref. L. 2824, P. 1048 of Ingham Co., Mich. deeds

    Owner: Kris J. Keller

    Owner:

    Christman Constructors

    Owner:

    SurveyedParcel

    Bandwith yard onto

    Surveyed Parcel

    8ft ch lk

    Set 3/4" iron pipe with alum. cap #30897

    *Did not set - in fenced & secured yard

    210.45'Calc.

    metal-sided bldg. (enc.)

    NORTH

    Scale: 1 inch = 30 feet

    4'

    4'

    8ft.ch.lk.fc.(enc)

    Zayo Bandwith

    Owner: Kris J. Keller

    Owner:

    Christman ConstructorsOwner:

    Surveyed

    Bandwith yard onto

    Surveyed Parcel

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    32/250

    Center Post ofSec. 21 (See Sheet 3)

    S.

    WashingtonAve.

    E. South St.

    S.

    GrandAve.

    C.N.R.R.

    E. 1/4 Corner ofSec. 21 (See Sheet 3)

    PlattSt.

    W. South St.

    N-S1/4Line

    E-W 1/4 Line

    N.E. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    N.W. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    S.E. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    S.W. 1/4 of Section 21,T. 4 N., R. 2 W.,City of Lansing ,Ingham County, Mich.

    Ea

    stLineofSection21

    F-8 G-8

    *Notes: 1. The Surveyed Parcel shown is part of a 5.3062 acre parcel (City of LansingParcel No. 33-01-01-21-261-004). A Lot Split Application must be submittedto the City of Lansing (and approved) before this parcel split can take effect.

    2. Most site improvements existing on this parcel (including fencing, asphalt paving,curb & gutter, catch basins, storm sewer lines, utility poles andutility lines, etc.) are not shown on this survey.

    NORTH

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    33/250

    Cen. Post

    S.GrandAve.(82.5')

    S.

    WashingtonAve.

    (115.5

    'P.)

    E. South St. (82.5' P.)

    Canadian National Railway66.1

    5'M.

    115.42' M.

    Sparrow's Subdivisionof Block 200 of the Orig. Plat

    Block 201,Orig. Plat of Lansing

    Vac.

    S.

    GrandAve.

    33'Alley

    of Sec. 21

    Surveyed

    (E. 1/4 Cor. G-8 to Cen. Post F-8)

    (formerlyLeeSt.)

    (formerlyLeeSt.)

    W. SouthStreet

    F-8

    71.6

    0'M.

    Setm

    asonry

    nailin

    asph

    altdrive

    Set 3/4" I.P. with

    Found 1/2" rod(Surveyed Desc.Point of Beginning)

    Parcel (shaded)

    221'

    bldg. overhang

    bldg. overhang

    Cov.Porch

    *Outline of brick depot bldg.

    Set3

    /4"I.P

    .with

    alum.

    cap#

    30897

    alum. cap #30897

    3.55' brick bldg. corner enc. onto R.R. land

    3.2' brick bldg. corner enc. onto R.R. land

    71.6

    0'M.

    *For conditions of the vacation of S. Grand Ave. (formerly Lee St.),refer to Lansing City Council Proceedings of Jan 8 1912)

    1

    Found 1/2" rod1 (Surveyed Desc. Point of Beginning)

    S.W. West 8.05' to the east edge of the 5 ft. wide concrete sidewalkSouth 33.33' to the centerline of the northerly of 2 rail tracks

    South 46.65' to the centerline of the southerly of 2 rail tracks

    2

    2 Set masonry nail in asphalt drive

    N. 12.8' to vertical rail section buried in lawn area behind curb

    3

    4

    Set 3/4" I.P. with alum. cap #308973

    S. 5.85' to E-W 6 ft. high chain link fenceS.E. 10.2' to the center of a corner post at

    northeast cor. of 6 ft. high chain lk. fc.

    Set 3/4" I.P. with alum. cap #308974

    S. 13.75' to E-W 6 ft. high chain link fenceE. 10.25' to N-S 6 ft. high chain link fenceS. 45.55' to the centerline of the southerly

    of 2 rail tracks

    NORTH

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    34/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    35/250

    6.7 Attachment G Preliminary Design Concept

    Table of Contents

    Plant and Office Building Narratives

    Proposed Site Plan SK-C001-E

    Proposed Ground Floor General Arrangement SKM210A

    Proposed Upper Floors General Arrangements SKM210B

    Proposed Roof Plan General Arrangement SKM210C

    Preliminary Facility Elevation Sketch SKM005

    Proposed Control Room Layout SKJ001-A

    Proposed Electronics Room Layout SKJ002-A

    Preliminary Equipment List for CM Package, Rev. A

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    36/250

    1

    REO TOWN PLANT AND OFFICE BUILDING

    The Reo Town Project consists of a 110 MW nominal Combined Cycle Power Plant and an Office

    Building. The Project is located in Lansing MI, at the intersection of South Washington Ave and East

    South Street. The Reo Town Plant will house the majority of the generating equipment necessary for

    Plant operations. The Office Building front faade is located on South Washington Ave; the Plant is

    located directly east of the Office Building. The Reo Town Plant is approximately 150 feet by 300 feet;

    the Reo Town Office Building is approximately 115 feet by 150 feet.

    Roof elevations vary along the length of the Plant, with a maximum roof height in the HRSG area

    approximately 92 feet above the Ground Floor. The top of the cooling tower, located on the HRSG area

    roof, is 148 feet above the Ground Floor. The HRSG and by-pass stack height is 160 feet above the

    Ground Floor.

    The exterior architectural treatment for both the Plant and Office Building will be selected to provide a

    uniform cohesive appearance. The exterior walls will be brick-faced masonry, tied to the

    superstructure.

    Reo Town PlantThe Reo Town Plant is sub-divided into three distinct areas, as follows:

    Steam Turbine, Control Room, Maintenance and Storage Areas

    The Steam Turbine, Control Room, Maintenance and Storage Areas occupy the western portion of the

    Plant. This area occupies approximately 96 feet of the overall Plant length, and includes a Ground Floor,

    Second Floor, and Third Floor; the roof height is approximately 70 feet above the Ground Floor.

    The Ground Floor area includes the Steam Turbine Generator (STG) pedestal and Condenser, a Water

    Treatment Area, Black Start Generator, Auxiliary Boiler and ancillary support equipment.

    The Second Floor includes the Control Room, Electronics Room, Offices, Lunch Room and Restroom

    facilities. This floor extends east to the STG area, and serves as the STG operating floor area.

    The Third Floor includes Maintenance Shops, Storage Rooms, a Back-Up Control Center, and Locker

    Room facilities.

    Stairwells will be located within this area to allow access to all floors.

    HRSG Area

    The Heat Recovery Steam Generator (HRSG) area is located in the central portion of the Plant, and

    occupies approximately 120 feet of the overall Plant length. This portion of the Plant includes two

    HRSGs, Chemical Feed Area, Boiler Feed Pumps and various other equipment areas. Within this area,

    the roof height is approximately 92 feet above the Ground Floor.

    A stair and elevator located in the HRSG area will provide access to the roof, and will also provide access

    to the Second Floor Control Room Area and the Third Floor Maintenance and Storage Areas.

    CTG Area

    The Combustion Turbine Generator (CTG) area occupies the eastern portion of the Plant, and occupies

    approximately 84 feet of the overall Plant length. This portion of the Plant includes two CTGs, PCMs,

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    37/250

    2

    and ancillary support equipment. Within this area, the roof is located approximately 40 feet above the

    Ground Floor. Two CTG Inlet Filters are located above the roof in this area of the Plant.

    Electrical Room

    A separate Electrical Room is located adjacent to the east wall of the Plant, and includes transformers,

    switchgear, MCCs, UPS and a Battery Room. The Electrical Room is approximately 50 feet wide, with the

    roof located approximately 25 feet above the Ground Floor.

    Reo Town Office Building

    The Reo Town Office Building is located adjacent to the Reo Town Plant. The Building will include offices

    and covered parking on the Ground Floor. As required by the final program requirements, two to three

    floors of office space will be required above the Ground Floor.

    REO TOWN PLANT STRUCTURE

    Superstructure

    The Reo Town Plant superstructure will be structural steel braced frame construction. Roof support will

    be provided by purlins, supported on girder or truss chord members. Vertical and horizontal bracing willbe provided to transfer horizontal loads to the foundation system. All interior steel will be painted; all

    exterior steel will be galvanized.

    The roof of the Plant will be galvanized steel metal roof deck, with membrane roofing system above.

    The cooling towers will be supported on a superstructure system located above the roof, and will be

    enclosed by a screen wall on all sides.

    Floor SystemsThe Ground Floor will be a concrete slab; elevated floors will be concrete filled metal decking floor slabs,

    with steel grating located as required for equipment access and maintenance. Top surface of concrete

    floor slabs will be steel trowel finished, surface hardened and sealed. Floors will be sloped to trench

    drains in areas where leakage is probable or wash down is usual.

    All floor drain water will be collected in sumps, and discharged into the site waste water system by

    pumping or by gravity. Sumps will be covered with checkered plate; trenches will be covered with

    grating.

    Foundation Systems

    Pending results of the geotechnical investigation, it is anticipated that the Plant foundation system will

    be pile-supported, and the ground floor slab will be a pile supported structural slab system.

    REO TOWN OFFICE BUILDING STRUCTURE

    The Reo Town Office Building superstructure will be structural steel moment braced frame and/or

    masonry shear wall construction. The Ground Floor will be a concrete slab on grade; elevated floors

    will be concrete filled metal decking floor slabs. Pending results of the geotechnical investigation, the

    foundation system will be either grade supported or pile-supported foundations.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    38/250

    3

    REO TOWN PLANT OFFICE BUILDING CORE AND SHELL WORK

    The following description outlines the basic requirements of the Plant Office Building Core and Shell

    Work.

    a. Building structure, envelope, vertical circulation, core toilet rooms(unfinished)

    b. Base structure, including foundations, beams, columns, floor slabs, and roof structure

    c. Building envelope includes insulated exterior walls, exterior glazing, and roofing systemd. Vertical circulation, including elevators (finished) and stairs and related

    shafts(unfinished)

    e. Electrical and mechanical main equipment (i.e. heat source, cooling source, air handlers,

    pumps, control systems, sub metering etc.)

    f. Fire protection pumps, standpipes, sprinkler system and central fire alarm system, all

    valved and/or stubbed into the future office space

    g. Core areas for each floor, including elevators, shafts, toilet rooms, potable domestic

    water riser(s), properly sized sanitary and storm drain systems, electrical distribution

    panels, designated connection point to the central fire alarm system, and a distribution

    backboard within a wire closet

    h. Work required to effect proper transition between Core and Shell and Office Interior

    Work.

    Plant Facility support spaces (i.e. control room, locker rooms, break room, related corridors and

    inside parking) are not part of the 45,000sf of office spaces and shall be finished complete as

    part of the CMs scope of work

    All site improvements are part of this CMs scope of work

    Elements NOT included in building core and shell Work that will be part of the offices interior

    build-out & finishes:

    a. Gypsum wallboard on exterior perimeter walls and interior core walls

    b. All interior building finishes, including all ceilings, walls, floors, toilet rooms, stair wells,

    doors, fit-out elements, etc. (except elevator interiors included above)

    c. Electrical and mechanical distribution systems and components (i.e. ductwork,

    plumbing, conduit, cabling, sensors, fixtures, grills, finish elements, etc.)

    d. Security system, payment center related systems (i.e. air tube transfer system), office

    related communications systems, etc.

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    39/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    40/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    41/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    42/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    43/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    44/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    45/250

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    46/250

    PROJECT: Reo Town Plant LIST NO.:

    W.O. NUMBER: 03116-001 BY:

    REV. NO.: A REV. DATE: 4/19

    EQUIPMENT ESTIMATED REMARKS AND RE

    UNIT SYS EQUIP SEQ # SUFFIX DESCRIPTION POWER REQM'T ESTIMATED EQUIPMENT SIZES N

    0 PWS TK 001 Admin Area Potable Water Heater 4 kW 240 V Electrically heated tank

    0 IAS CR 001 A Air Compressor (A) 100 hp 350 scfm @ 125 psig

    0 IAS CR 001 B Air Compressor (B) 100 hp 350 scfm @ 125 psig

    0 IAS DR 001 A Air Dryer (A) --- 300 scfm net outlet flow @ 110 psig & -40F dewpoint - heatless type

    0 IAS DR 001 B Air Dryer (B) --- 300 scfm net outlet flow @ 110 psig & -40F dewpoint - heatless type

    0 IAS TK 001 Air Receiver --- 1,000 gallon vertical ASME tank rated at 150 psig

    0 SAX BO 001 Auxiliary Boiler 750 hp 150,000 lb/hr @ 300 psig & 650F

    0 SAX TK 001 Auxiliary Boiler Blowdown Tank --- Purchased under "Auxiliary Boiler" spec

    0 SAX DA 001 Auxiliary Boiler Deaerator --- Purchased under "Auxiliary Boiler" spec

    0 SAX PP 001 A Auxiliary Boiler Feedwater Pump A --- Purchased under "Auxiliary Boiler" spec

    0 SAX PP 001 B Auxiliary Boiler Feedwater Pump B --- Purchased under "Auxiliary Boiler" spec

    0 ACW PP 001 A Auxiliary Cooling Water Pump (A) 100 hp 2,500 gpm @ 100 ft TDH

    0 ACW PP 001 B Auxiliary Cooling Water Pump (B) 100 hp 2,500 gpm @ 100 ft TDH

    0 ACW PP 001 C Auxiliary Cooling Water Pump (C) 100 hp 2,500 gpm @ 100 ft TDH

    0 PWS SP 001 Battery Room Area Emergency Shower/Eye Wash 108 kW Electrically heat 25 gpm of potable water 29F

    1 FWS PP 001 A Boiler Feedwater Pump (1A) 150 hp 400 gpm @ 1000 ft TDH

    1 FWS PP 001 B Boiler Feedwater Pump (1B) 150 hp 400 gpm @ 1000 ft TDH

    2 FWS PP 001 A Boiler Feedwater Pump (2A) 150 hp 400 gpm @ 1000 ft TDH

    2 FWS PP 001 B Boiler Feedwater Pump (2B) 150 hp 400 gpm @ 1000 ft TDH

    1 CWS PP 001 A Circulating Water Pump (1A) 300 hp 11,000 gpm @ 75 ft TDH

    1 CWS PP 001 B Circulating Water Pump (1B) 300 hp 11,000 gpm @ 75 ft TDH

    2 CWS PP 001 A Circulating Water Pump (2A) 300 hp 11,000 gpm @ 75 ft TDH

    2 CWS PP 001 B Circulating Water Pump (2B) 300 hp 11,000 gpm @ 75 ft TDH

    0 PWS SP 001 City (Potable) Water Meter ---

    1 CTG CT 001 Co mbustion Turbine Ge nerator (CT G) (A) & Accessorie s --- Purchased under "CTG" spec

    1 CTG TK 001 CTG False Start Drain Tank (A) --- 100 gallon CS tank designed for 50 psig @ 130F

    PRELIMINARY EQUIPMENT LIST FOR CM PACKAGE

    BURNS AND ROE ENTERPRISES, INC.

    TAG NUMBER

    Preliminary Equipment List.xlsx 1 of 5 Printed Date: 4/19/2011

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    47/250

    PROJECT: Reo Town Plant LIST NO.:

    W.O. NUMBER: 03116-001 BY:

    REV. NO.: A REV. DATE: 4/19

    EQUIPMENT ESTIMATED REMARKS AND RE

    UNIT SYS EQUIP SEQ # SUFFIX DESCRIPTION POWER REQM'T ESTIMATED EQUIPMENT SIZES N

    PRELIMINARY EQUIPMENT LIST FOR CM PACKAGE

    BURNS AND ROE ENTERPRISES, INC.

    TAG NUMBER

    1 CTG TK 002 CTG Water Wash Drain Tank (A) --- 1000 gallon CS tank designed for 50 psig @ 130F

    2 CTG CT 001 Combustion Turbine Generator (CTG) (B) & Accessories --- Purchased under "CTG" spec

    2 CTG TK 001 CTG False Start Drain Tank (B) --- 100 gallon CS tank designed for 50 psig @ 130F

    2 CTG TK 001 CTG Water Wash Drain Tank (B) --- 1000 gallon CS tank designed for 50 psig @ 130F

    0 CTG WK 001 CTG Water Wash Skid --- Purchased under "CTG" spec

    1 CNS PP 001 A Condensate Pump (1A) 50 hp 400 gpm @ 320 ft TDH

    1 CNS PP 001 B Condensate Pump (1B) 50 hp 400 gpm @ 320 ft TDH

    1 CNS TK 001 Condensate Storage Tank (1) --- 10,000 gals.

    2 CNS PP 001 A Condensate Pump (2A) 50 hp 400 gpm @ 320 ft TDH

    2 CNS PP 001 B Condensate Pump (2B) 50 hp 400 gpm @ 320 ft TDH

    2 CNS TK 001 Condensate Storage Tank (2) --- 10,000 gals.

    1 CNS CD 001 Condenser (1) ---

    2 CNS CD 001 Condenser (2) ---

    1 CNS PP 002 A Condenser Vacuum Pump (1A) 30 hp furnished with condenser

    1 CNS PP 002 B Condenser Vacuum Pump (1B) 30 hp furnished with condenser

    2 CNS PP 002 A Condenser Vacuum Pump (2A) 30 hp furnished with condenser

    2 CNS PP 002 B Condenser Vacuum Pump (2B) 30 hp furnished with condenser

    1 CWS CT 001 A Cooling Tower (1A) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    1 CWS CT 001 B Cooling Tower (1B) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    1 CWS CT 001 B Cooling Tower (1C) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    2 CWS CT 001 A Cooling Tower (2A) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    2 CWS CT 001 B Cooling Tower (2B) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    2 CWS CT 001 B Cooling Tower (2C) 75 hp 34 MMBTU/hr total heat load; 86F cooling water outlet

    0 PWS SP 002Cooling Tower Chem Feed Area Emergency Shower/Eye

    Wash108 kW Electrically heat 25 gpm of potable water 29F

    0 TCF CK 001 Cooling Tower Chem Feed Skid 5 hp

    Elevator 35 hp 3,500 lb. Capacity

    Preliminary Equipment List.xlsx 2 of 5 Printed Date: 4/19/2011

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    48/250

    PROJECT: Reo Town Plant LIST NO.:

    W.O. NUMBER: 03116-001 BY:

    REV. NO.: A REV. DATE: 4/19

    EQUIPMENT ESTIMATED REMARKS AND RE

    UNIT SYS EQUIP SEQ # SUFFIX DESCRIPTION POWER REQM'T ESTIMATED EQUIPMENT SIZES N

    PRELIMINARY EQUIPMENT LIST FOR CM PACKAGE

    BURNS AND ROE ENTERPRISES, INC.

    TAG NUMBER

    0 FPS PP 002 Fire Pump Jockey 5 hp20 gpm @ 125 psi TDH - Purchased under "Firewater Pumps and

    Accessories" spec

    0 FPS PP 001 Fire Pump Motor Driven 250 hp 2500 gpm @ 125 psi TDH

    0 FPS PP 002 Fire Pump Motor Driven 250 hp 2500 gpm @ 125 psi TDH

    0 FGS AC 001 Fuel Gas Accumulator --- Purchased with Compressors

    0 FGS CR 001 A Fuel Gas Compressor A 800 hp 8500 SCFM natural gas compressor from 250 to 700 psig

    0 FGS CR 001 B Fuel Gas Compressor B 800 hp 850 0 SCFM n atural g as compre ssor from 250 to 70 0 psig

    0 FGS TK 001 A Fuel Gas Condensate Drain Tank A ---250 gallon ASME CS vessel designed for 125 psig @ 300F, Purchased with

    Compressors

    0 FGS TK 001 B Fuel Gas Condensate Drain Tank B ---250 gallon ASME CS vessel designed for 125 psig @ 300F, Purchased with

    Compressors

    0 FGS FL 001 A Fuel Gas Filter/Coalescer A --- Purchased with Fuel Gas Compressors

    0 FGS FL 001 B Fuel Gas Filter/Coalescer B --- Purchased with Fuel Gas Compressors

    0 FGS CT 001 A Fuel Gas Fin-Fan Air Cooler A 50 hp Purchased with Fuel Gas Compressors

    0 FGS CT 001 B Fuel Gas Fin-Fan Air Cooler B 50 hp Purchased with Fuel Gas Compressors

    1 FGS FL 001 Fuel Gas Inlet Scrubber 1 --- Purchased with Fuel Gas Compressors

    2 FGS FL 001 Fuel Gas Inlet Scrubber 2 --- Purchased with Fuel Gas Compressors

    1 FGS FL 002 Fuel Gas Interstage Scrubber 1 --- Purchased with Fuel Gas Compressors

    2 FGS FL 002 Fuel Gas Interstage Scrubber 2 --- Purchased with Fuel Gas Compressors

    0 FGS SP 001 Fuel Gas Meter ---

    1 HRF HR 001 Heat Recovery Steam Generator (HRSG) (1) ---

    1 BBS TK 001 HRSG Blowdown Tank (1) --- 750 gal. (4.5' OD x 8' H) ASME CS vessel designed for 15 psig @ 300F

    2 HRF HR 001 Heat Recovery Steam Generator (HRSG) (2) ---

    2 BBS TK 001 HRSG Blowdown Tank (2) --- 750 gal. (4.5' OD x 8' H) ASME CS vessel designed for 15 psig @ 300F

    0 PWS SP 003 HRSG Chem Feed Area Emergency Shower/Eye Wash 108 kW Electrically heat 25 gpm of potable water 29F

    0 CCF CK 001 HRSG Chem Feed Skid 5 hp

    0 WWC SR 001 Oily Waste Separator --- Underground tank s ized for 200 gpm gravi ty inf low of oily water

    0 WWC PP 001 A Oily Waste Separator Sump Pump (A) 5 hp 200 gpm @ 50 ft TDH, Purchased with Oily Waste separator

    0 WWC PP 001 B Oily Waste Separator Sump Pump (B) 5 hp 200 gpm @ 50 ft TDH, Purchased with Oily Waste separator

    Preliminary Equipment List.xlsx 3 of 5 Printed Date: 4/19/2011

  • 7/31/2019 Lansing BWL: REO Town construction RFP

    49/250

    PROJECT: Reo Town Plant LIST NO.:

    W.O. NUMBER: 03116-001 BY:

    REV. NO.: A REV. DATE: 4/19

    EQUIPMENT ESTIMATED REMARKS AND RE

    UNIT SYS EQUIP SEQ # SUFFIX DESCRIPTION POWER REQM'T ESTIMATED EQUIPMENT SIZES N

    PRELIMINARY EQUIPMENT LIST FOR CM PACKAGE

    BURNS AND ROE ENTERPRISES, INC.

    TAG NUMBER

    0 SWS PP 001 A Service Water Pump (A) 15 hp200 gpm @ 150 ft. TDH

    (City Water pressure can be as low as 35 psig)

    0 SWS PP 001 B Service Water Pump (B)