Landfill Grading Using GPS Machine Control NC SWANA April 2018 Presented by: Bernie Garrett, PE Garrett & Moore Inc. & Gabe Leach Cooper Barnette & Page Inc. 1

Transcript of Landfill Grading Using GPS Machine Control · Landfill Grading Using GPS Machine Control NC SWANA...

Landfill Grading Using

GPS Machine Control

NC SWANA

April 2018

Presented by:

Bernie Garrett, PE

Garrett & Moore Inc.

&

Gabe Leach

Cooper Barnette & Page Inc.

1

Purpose

2

• Work flow processes used by Engineers,

Surveyors, and Contractors to construct

landfill base grades using GPS Machine

Control Technology

Background

3

• Global Positioning Systems (GPS) have

evolved in recent years to the point where

reliability and accuracy of GPS is utilized to

control construction equipment used for

grading

• CADD programs utilized by Engineers have

capabilities to efficiently develop 3-D

models of grading plans.

Software Programs

4

• Engineer:– Autodesk: Civil 3D

– Bentley: Microstation

– Trimble: Terramodel

• Surveyor:– Trimble: Trimble Business Center

– Hexagon Geosystems: LEICA Geosystems

– Topcon Positioning Systems: Geo-positioning Module

– Autodesk: Civil 3D/Trimble Link

• Contractor– Trimble: Trimble Business Center

– Hexagon Geosystems: LEICA Machine Control

– Topcon Positioning Systems: Machine Control Module

Work Flow – Engineering Design

5

• Permit Drawings:

– Prepared for the full build-out of a Landfill

– Approved by a Regulatory Agency

– Grading plans are lines on paper

• Construction Drawings:

– Depict a phase of landfill construction; not the entire landfill.

– Incorporate “phase” specific features, such as erosion control measures, interim anchor trench/berm, and interim access roads.

6

7

8

9

Work Flow with Contours as Engineer’s

Grading Plan Data

10

Exports Contours in .dwg format

Contours in .dwgformat

Engineer Contractor Surveyor

Contours in .dwgformat

Builds a 3-D Model in a Trimble format

Checks 3-D Model versus Engineer’s

Contours

Creates a Trimble file (.ttm)

Loads .ttm file into Operators Computer

QC/Approval of 3-D Model versus

Engineer’s Contours

11

Work Flow with 3-D Model as Engineer’s

Grading Plan Data

12

Creates a Trimble file (.ttm)

Checks .ttm file versus Engineer’s

Contours

Engineer Contractor Surveyor

Loads .ttm file into Operators Computer

Work Flow – Contractor

13

• Coordination with Surveyor:

– Surveyor establishes and accurately measures

a network of Control Points that surround the

limits of work.

– Collected data is post processed and sent to

contractor.

Surveyed Control Points

14

Site Calibration

A Base Station is installed on

the job site and calibrated

based on the data collected

from surveyor.

-Site Calibration is required to

define a relationship between

global and local coordinate

systems.

-Precision of the calibration is

crucial as it will directly relate to

the projects overall accuracy.

15

Office Data Prep

• CAD Data Import

– CAD data from the design engineer is

imported and organized according to scope of

work.

– All CAD data is compared to the official

Construction Drawings.

– Once the CAD files are verified Digital Terrain

Models are built to represent the Construction

Drawings.

16

3D Surface Model

-Once complete, the surface is reviewed in 3D space.

-After confirmation that the surface is error free and conforms to the

Official Construction Drawings the files are exported for use in the field.

17

Field QA/QC Checks

-Dozer and Excavators are measured for blade or

bucket wear and verified accurate before and during

the project.

-Benchmarks are installed on-site and operators check

elevations on them daily before beginning work.

-Small test pad graded to a known elevation for

certifying surveyor to check. This will insure our

equipment is set up accurately and the grades we

provide will meet the certification plan.

18

Machine Control

Once imported to the machines control box the operator can see

exactly where he is on the project and how much cut or fill is

required.

19

Why Do We Use Machine Control?

• Gives us a technical edge over our competitors.

• Saves time and resources on the job.– Decreased stakeout work by up to 90%

– Eliminates reworked areas to meet certification grades.

• Increase productivity– Decreased material handling and material waste.

– Decreases operator fatigue.

– Increased accuracy. Grades can be met the first time accurately and efficiently.

20

Grade Control Equipped Excavator

21

Grade Control Equipped Dozer

22

Technical Abilities Required for GPS

Manager

• High level computer skills for managing and organizing multiple file types over multiple job sites.

• Proficiency with AutoCAD software.

– Take-Offs for bids.

– Surface creation and export once job is awarded.

– Assist with material quantity updates for production studies throughout the job.

• Solid understanding of heavy construction equipment and practices.

23

Technical Abilities Required for

GPS Manager

• Basic knowledge of Survey principals for

Site Calibration, Topos, and Stakeouts as

needed.

• Extensive knowledge of GPS components

installed on machines for maintenance,

repair, and operator training.

24

Summary

• Landfill Owners – Be certain that your

Engineer, Surveyor, and Contractor are all

utilizing the best technology available.

25