Landfill Gas Utilization Project County of Santa Cruz

23
Brown, Vence & Associates, Inc. Landfill Gas Utilization Project County of Santa Cruz March 20, 2003 Presented by Thomas D. Vence, Vice President Presented to Institute of Electrical and Electronics Engineers, Inc. SF Chapter

Transcript of Landfill Gas Utilization Project County of Santa Cruz

Page 1: Landfill Gas Utilization Project County of Santa Cruz

Brown, Vence & Associates, Inc.

Landfill Gas Utilization Project

County of Santa Cruz

March 20, 2003Presented by Thomas D. Vence, Vice President

Presented to Institute of Electrical and Electronics Engineers, Inc.

SF Chapter

Page 2: Landfill Gas Utilization Project County of Santa Cruz

The Problem and the Opportunity

VolumeMethane 45-58%Carbon Dioxide 32-45%Nitrogen 0-3%Oxygen less than 1%Hydrogen Sulfide 10-200ppmNMOCs less than 1%

Page 3: Landfill Gas Utilization Project County of Santa Cruz

Landfill Gas Production

1 2 3

1. Active landfilling operation2. Installation of LFG extraction

system at or near end of landfilling operation

3. Long declining phase

Gas

Gen

erat

ion-

CFM

Time

Page 4: Landfill Gas Utilization Project County of Santa Cruz

Options for Managing Landfill Gas

POWER PLANT

SCHEMATIC OF A TYPICAL LFG COLLECTION SYSTEM

Page 5: Landfill Gas Utilization Project County of Santa Cruz

Landfill Gas Flare

Page 6: Landfill Gas Utilization Project County of Santa Cruz

LFG Energy Utilization

450 – 500 BTU/SCFMApproximately 10,500 BTU/KWH Gross HHV1050 – 1167SCFM LFG for 3 MW Gross

Page 7: Landfill Gas Utilization Project County of Santa Cruz

Landfill Gas-to-Electricity Technology

EstablishedTypes• Reciprocating Engine• Microturbines• Gas Turbines

Most 1 MW to 5 MWSteady-state operation

Page 8: Landfill Gas Utilization Project County of Santa Cruz

History1975 First commercial gas energy recovery project1978 PURPA enacted1982 First electricity generating project 1985 End of long-term Standard Offer contracts1986 IRS Section 291992 Energy Policy Act - REPIs1994-1995 New regulations under RCRA, CAA and CWA1996 New Source Performance Standards and

Emission Guidelines of 19961996 AB 1890

Page 9: Landfill Gas Utilization Project County of Santa Cruz

2003

50 LFG power plants in California, 333 in the United StatesAB 1890Federal subsidiesFederal tax creditsGreen power market

Page 10: Landfill Gas Utilization Project County of Santa Cruz

2003 Continued

On site generationCEC Subsidies for renewable energy

Page 11: Landfill Gas Utilization Project County of Santa Cruz

Other Renewable Energy Subsidies

REPIs• For publicly-owned power plants• Up to 1.6 cents/kWh• Depends on annual appropriations by Congress• SWANA lobbying for more funding

Production Tax Credits• Public project can benefit• Based on $/MM BTU (Approx 1-2 cents/KwH)• Eligible through 2002 or 2007

Page 12: Landfill Gas Utilization Project County of Santa Cruz

Example of Economics

Item Per kWhCosts

Debt service……………….2.5 centsRecurring…………………..3.5 cents

Total…………………….. 6.0 centsRevenues

Electricity sales…………….4.5 centsSubsidies/tax credits………2.5 cents

Total…………………….. 7.0 cents

Page 13: Landfill Gas Utilization Project County of Santa Cruz

Project Development Process

Pre-development• Feasibility assessment• Project definition

Development

Page 14: Landfill Gas Utilization Project County of Santa Cruz

Project Development Process Continued

Project Component FeasibilityAssessment

Project Definition ProjectDevelopment

Gas Production PreliminaryEstimate

Sustainable yieldstudy

Ongoing gastesting

Engineering andPermitting

Approximateplant size andtype

Preliminary design(number, size, typeof engines, sitelocation, utilityinterconnections)

Submit permitapplications andobtain permits

Ownership structure Identifyoptions

Select ownershipstructure

Develop andsign contracts

Economic Analysis Preliminarycost estimates,cash flows

Finalize costestimates, finalizecash flow

Potentialchanges to cashflow analysis

Power SalesAgreements

Estimateelectricitypricing

Prepare RFPs andselect buyer

Sign power salescontracts

Tax Credits Estimate PTCvalue

Prepare RFPs andselect buyer

Sign PTCagreements

Other Subsidies Estimate value Apply for subsidies Awardedsubsidies

Project Financing Identifyoptions,estimate rate

Define length offinancing, identifysource of financing,percent equity, costof financing

Close financing

Page 15: Landfill Gas Utilization Project County of Santa Cruz

Buena Vista Location Map

Page 16: Landfill Gas Utilization Project County of Santa Cruz

Buena Vista Site Plan

Page 17: Landfill Gas Utilization Project County of Santa Cruz

Buena Vista Landfill Gas Production

GAS PRODUCTION CURVES

0

500

1000

1500

2000

1998

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

Year

LFG

[s

cfm

] TotalSanta Cruz

Watsonville

Page 18: Landfill Gas Utilization Project County of Santa Cruz

Permit Requirements

Modification to solid waste facilityMinor amendment to land use permitCEQAAuthority to constructPermit to operate

Page 19: Landfill Gas Utilization Project County of Santa Cruz

Ownership Structure

PublicPublic/PrivatePrivate

Page 20: Landfill Gas Utilization Project County of Santa Cruz

Power Sales Agreement

5 year termFixed pricing up to 3 MW for first 5 yearsFor remaining years, commodity energy purchase at power exchange ratePursue opportunity for green premium

Page 21: Landfill Gas Utilization Project County of Santa Cruz

Sensitivity Analysis

Comprehensive due diligencePTCs reduced by 20%Low-MediumPTCs Decrease

Early discussions with Air Board

Capital costs increase by 10%LowEnvironmental Requirements

Increase

Request equipment and construction bids prior to

financing

Capital costs increase by 10%LowCapital Costs Increase

Good operation and maintenance program

O&M costs increase by 10%MediumOperations and Maintenance

Cost (O&M) Increases

Extended warrantee from engine manufacturer; good operation and

maintenance program

Plant availability reduced to 85%LowTechnical Performance

Decreases

Proper management of gas field

Gas production reduced 10%LowGas Production Decreases

No ChangeBase case

Possible Migration MeasuresSensitivity AssumptionsRelative RiskCase

Page 22: Landfill Gas Utilization Project County of Santa Cruz

Financing

EquityDebt• Project Financing• Municipal Financing

Page 23: Landfill Gas Utilization Project County of Santa Cruz

Issues to Consider

Sufficient landfill gasPotential to capture tax creditsLarge on-site electricity usage (optional)Monitor REPIsPotential for another renewablesauction