f LAFS Update LAFS Update Dave McGinnis Fermilab April 18, 2007

description

LAFS Update. Dave McGinnis Fermilab April 18, 2007. Introduction. LAFS = LHC at FNAL Software LAFS is a part of LHC@FNAL LAFS consists of a core group of 14 Fermilab* people 8 computer professionals 6 accelerator physicists LAFS immediate goal is to provide software support for the LHC - PowerPoint PPT Presentation

Transcript of LAFS Update

Page 1: LAFS Update

f

LAFS UpdateLAFS Update

Dave McGinnisFermilab

April 18, 2007

Page 2: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f IntroductionIntroduction

LAFS = LHC at FNAL Software LAFS is a part of LHC@FNAL LAFS consists of a core group of 14 Fermilab*

people 8 computer professionals 6 accelerator physicists

LAFS immediate goal is to provide software support for the LHC With a long term view to be involved in the

commissioning and operations of the LHC LAFS is mutually beneficial to CERN and Fermilab

• We provide CERN with a valuable software service• In return, we are trained on LHC control system so that

we are poised to make valuable accelerator contributions to the LHC in the future

Note: Membership not restricted to Fermilab employees

Page 3: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f LAFS ManagementLAFS Management Although we are part of LHC@FNAL, we view ourselves as a software

team working for CERN’s Accelerator and Beams Department Controls group (AB/CO) under the direction of Hermann Schmickler We have an MOU We follow all the CERN requirements for software engineering

• Programming language and environment• Documentation• Look and Feel• Etc.

We view our main customer is Accelerator and Beams Department Operations group (AB/OP) in which our main contact is Mike Lamont

At Fermilab LAFS reports to the head of LHC@FNAL (Erik Gottschalk) Is lead by Dave McGinnis with Jean Slaughter as deputy Has three project leaders

• Suzanne Gysin• Elliott McCrory• Jim Patrick

Our goal is to have a constant presence at CERN Suzanne Gysin (October 1, 2006 – July 1, 2007) Dennis Nicklaus (Summer 2007) Elliott McCrory (August 1, 2007 – August 1, 2008)

Page 4: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f LAFS ProjectsLAFS Projects

We are involved in 10 projects Each project will have a leader and a contact at CERN With the exception of RBA which is well underway, most

projects are currently involved in writing requirements documents

LAFS Projects Role Based Access Control (S. Gysin) Sequencer Development (J. Patrick) Instrumentation Applications

• Tune Measurement (J. Patrick)• Wire Scanners (E. McCrory)• Synchrotron Radiation Monitor (D. Nicklaus)• Microwave Schottky Monitor (J. Patrick)• Residual Gas Monitor (E. McCrory)• Beam Profile Fit Library (E. McCrory)

Drag and Drop Display Builder (Synoptic Display) (T. Bolshakov)

Sequenced Data Acquisition (on hold) (E. McCrory)

Page 5: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f LAFS-CERN VisitsLAFS-CERN Visits

S. Gysin -> CERN, October 2006 P. Charrue & E. Hatziangeli -> Fermilab, November 15-

17, 2006 E. McCrory -> CERN, November 13-17, 2006 G. Kruk -> Fermilab, December 12-15, 2006

LHC Java Application Development Training Class Over 10 Fermilab people enrolled Huge Success!!!

J. Patrick & D. McGinnis -> CERN, February 14-20, 2007 J. Annala, D. Still, B. Hendricks -> CERN, March 19-23,

2007 D. Nicklaus-> CERN, March 26 – April 2, 2007 E. McCrory ->CERN, March 26 – April 9, 2007 A. Petrov & C. Schumann -> CERN, April 10-20, 2007 P. Charrue & E. Hatziangeli -> Fermilab, April 17-20,

2007

Page 6: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Role Based Access Control (RBAC) S. Role Based Access Control (RBAC) S. GysinGysin

RBAC is software to prevent

An ignorant person from doing anything, anytime.

1. Login using NICE user name and password.

2. No login required in CCC, critical applications being the exception

3. Timeouts

A well meaning person from doing the wrong thing at the wrong time.

1. Access is determined by: role, location, mode, and application

2. Logging

What is a ROLE? A role is a job function

within an organization.Examples: LHC Operator, SPS Operator, RF Expert, BPM Developer …

Roles are defined by the instrument designers in a security policy.

A user may have several roles

What is being ACCESSED? CMW devices which map to

physical devices (power converters, collimators, kickers, etc.)

What TYPE of access? get: the value of a property

once monitor: the property

continuously set: the value of a property

Page 7: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f RBAC OrganizationRBAC Organization

RBAC team leader (S. Gysin - FNAL- LAFS) reports directly to AB-CO-IN section leader (P. Charrue)

Development: Authorization – K. Kostro AB-CO

• CMW - W. Gajewski AB-CO• RBAC server - S. Gysin FNAL-LAFS

Authentication – A. Petrov FNAL-LAFS Database – M. Peryt AB-CO LSA – G. Kruk AB-CO JAPC – R. Gorbonosov AB-OP

Page 8: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Participation in Requirements and DesignParticipation in Requirements and Design

Requirements:

Prepared by: S. Gysin FNAL/ LAFS K. Kostro AB/CO G. Kruk AB/CO M. Lamont AB/OP S. Lueders IT/CO W. Sliwinski AB/CO P. Charrue AB/CO

Checked by: J. Wenninger AB/OP S. Page AB/PO E. Hatziangeli AB/CO V. Kain AB/OP K. Hanke AB/OP R. Schmidt AB/CO R. Steerenberg

AB/OP

Approved by: P. Collier AB/OP H. Schmickler AB/CO R. Bailey AB/OP S. Myers AB

Design:

Prepared by: P. Charrue AB/CO V. Baggiolini AB/CO W. Gajewski AB/CO S. Gysin FNAL/ LAFS V.Kain AB/OP K. Kostro AB/CO G. Kruk AB/CO R. Gorbanosov AB/CO S. Page AB/PO A. Petrov FNAL/LAFS W. Sliwinski AB/CO N. Stapley AB/CO

Design:

Checked by: E. Hatziangeli

AB/CO K. Hanke AB/OP M. Lamont AB/OP S. Lueders IT/CO

R. Schmidt AB/CO R. Steerenberg

AB/OP J. Wenninger

AB/OP

Approved by: P. Collier AB/OP H. Schmickler

AB/CO R. Bailey AB/OP S. Myers AB

Page 9: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f RBAC High Level DesignRBAC High Level Design

A1: User requests to be authenticated. RBAC authenticates user via NICE

user name and password or CERN certificate

RBA returns token to ApplicationA2:

Application sends token to CMW when connecting.

CMW/FE verifies token signature once, and uses the credentials for every subsequent request

CMW checks access map for role, location, application, mode

Application RBAC

RBAC Token:

•Application name

•User name

•IP address/location

•Time of authentication

•Time of expiry

•Roles[ ]

•Digital signature (RBA private key)

CMW client

FESA

CMW server

Access MAP

Page 10: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f RBAC Slice Test SummaryRBAC Slice Test Summary Status:

Working on production release Vertical Slice Test Complete January 18 RBA Review Feb. 16

Successfully executed the vertical slice test for RBAC on January 18 and 19, 2007. The purpose of the test was to verify the design concepts and roughly measure the overhead. We wrote seventeen tests to verify Authentication with an LHC software application via NICE username and password Checking the permissions to set/get a device property for the role obtained in the

first step. The tests also included the generation, storage, and distribution of the public and private keys for the digital signature and its verification.

We tested on Windows and Linux, and used the BPM properties to test the permissions.

All tests passed. Our timing measurements showed that the time it takes to authenticate on Windows or Linux is about 970 ms. The average time to verify a token is 2.3 ms, and the average time to check an access permission is 2.2 ms. The 2.2 ms to check the access permission are part of a command that took about 600 ms to execute, the RBAC overhead is between 0.5 -1% of the total command time.

The test included code for authentication written by Andrey Petrov (FNAL), authorization software in Controls Middle Ware by Wojciech Gajewski, EquipState modifications by Agnieszka Chabrowska and Greg Kruk, JAPC modifications by Roman Gorbonsov, and new authorization code written by Suzanne Gysin. In total, we added about 30 Java classes to the repository, plus the CMW C++ code.

We concluded the design concepts are valid, the added overhead is acceptable, and we can continue with the current design and develop the production <<RBAC_TestReport_070118.doc>> n version of RBAC.

Page 11: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f RBAC Review – February 16, 2007RBAC Review – February 16, 2007

Page 12: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f LHC Sequencer Development (Patrick)LHC Sequencer Development (Patrick)

Automates the very complex sequence of operations required to operate the LHC.

Typical commands Set, get, check devices Wait for conditions Execute more complex

operations Start regular programs Start plots Send data to shot log

Step through commands Stops on error Allow restart at failed

command

Sequencer is used for: Normal operations Studies or special cases

Working with CERN on requirements

LHC State Diagram

Page 13: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Sequencer DevelopmentSequencer Development

Jerry Annala, Brian Hendricks and Dean Still traveled to CERN on behalf of the LAFS sequencer group to collaborate on the LHC sequencer design and development. During this time we met with Reyes Alemany, Mike

Lamont, and Vito Baggiolini and joined various meetings and discussion centered around the current and projected LHC sequencer work.

This also involved a demonstration of the current and proposed Hardware Commissioning (HWC) Sequencer and the LHC Sequencer.

Presented with work currently being developed for a proposed states machine that will be capable of interfacing to the sequencer.

Joined the two meetings that discussed the interactions between the LHC sequencer and the BLM and collimator systems.

Developed a summary of our involvement along with comments and recommendations for continuing progress and development directed at the LHC sequencer work. Not ready for public release

Page 14: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Summary of Sequencer CollaborationSummary of Sequencer Collaboration

Reviewed the different versions of the sequencer.  Evaluated the design choices using the requirements

document generated by CERN. Evaluated CERN’s proposal on implementing a finite

state machine engine.  Encouraged them to continue with the development.

Encouraged sequencer team to begin detailed meetings with each subsystem group to begin the documenting and specifying the communications needed between the subsystems and: sequencer, Finite State Machine engine, timing system, etc.

Page 15: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Tune Measurement Requirement Tune Measurement Requirement DocumentDocument

Page 16: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis 16

f Tune Measurement Prototype Waterfall/Slice DisplayTune Measurement Prototype Waterfall/Slice Display

Page 17: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Wire Scanner Requirements ExampleWire Scanner Requirements Example

Num Title Description Priority Source

2.05 Data 1The WSA shall collect profile data from the wire scanner hardware when it

initiates a scan.Critical

2.10 Data 2The WSA shall collect profile data from the wire scanner hardware when a

scan is initiated by another agent.Expected

2.15 Adjust gains The WSA shall adjust the gains on the wire scanner readout in order to

accommodate the different intensities in the LHC. Critical GC, 26-Mar-07

2.20 Bunch Data The WSA shall plot each of the key parameters for all possible bunches in

the LHC. Critical GA, 28-Mar-07

2.25 Text OutputThe WSA shall provide a textual table of the key parameters for all

possible bunches in the LHCCritical

2.30 Histogram The WSA shall histogram (“frequency distribution”, dX/dn) each of the key

parameters for all possible bunches in the LHC. Critical GA, 28-Mar-07

2.35 Key Parameters

The key parameters returned by the wire scanner front end are understood to be:§Beam Centroid §Beam size/RMS §Sigma of Gaussian fit to the profile §Non-gaussian content of the beam§The 2 and/or the “goodness of fit”

Expected

Page 18: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Synchrotron Light Monitor Requirements Synchrotron Light Monitor Requirements ExampleExample

Page 19: LAFS Update

f Drag and Drop Controls Display and BuilderDrag and Drop Controls Display and Builder(Synoptic Display)(Synoptic Display)

For rapid development, the system expert (operator, engineer, or physicist) should be the one to develop the displays or applications

These advanced control systems can seem overwhelming to non controls experts. This is why Lab View is so popular However Lab View offers little of the benefits of an advanced

control system. Drag and Drop is an environment that gives non-control

system experts the ability to quickly build controls displays which operate inside the control system framework.

Drag and Drop: is easy to use sophisticated enough to handle complex displays operates inside the control system framework. uses web browsers and/or Java Web Start (requires no extra

software installation) is easily extendible is a mature application

• Developed in 2001• Fermilab Cryogenics department are heavy users

Page 20: LAFS Update

f Demo – Builder, Meson Compressor RoomDemo – Builder, Meson Compressor Room

Page 21: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f Demo – Display, Meson Compressor Demo – Display, Meson Compressor RoomRoom

Page 22: LAFS Update

LAFS Update - LARP Collaboration Meeting - McGinnis

f SummarySummary

Since its inception 7 months ago LAFS has grown rapidly. Now has a core group of 14 Fermilab people

• 8 computer professionals• 6 accelerator physicists

Involved in 10 projects• Ranging from a mature project such as RBAC to new

ideas such as Drag and Drop

LAFS immediate goal is to provide software support for the LHC With a long term view to be involved in the

commissioning and operations of the LHC LAFS is mutually beneficial to CERN and Fermilab

• We provide CERN with a valuable software service• In return, we are trained on LHC control system so that

we are poised to make valuable accelerator contributions to the LHC in the future