LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder...

33
LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 1

Transcript of LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder...

Page 1: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

LADWP Transmission Planning Stakeholder Meeting

Attachment K Planning Q2 Meeting June 8, 2018

1

Page 2: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Agenda 1. Welcome & Introductory Remarks – 10 minutes 2. Safety Moment – 5 minutes 3. Overview of LADWP’s Local Transmission Planning Process – 30 minutes 4. LADWP’s Attachment K 2018 Planning Cycle – 20 minutes 5. LADWP’s Attachment K 2018 Website – 5 minutes 6. Draft Business Practice Preview –5 minutes 7. Break – 15 minutes 8. Planning Assumptions, Methodology, and Criteria for 2018 – 30 minutes 9. LADWP Transmission Plan from 2017 Planning Cycle – 45 minutes 10.Next Steps & Next Public Meeting

2

Page 3: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Welcome & Introductory Remarks

• Introductions • FERC Standards of Conduct • Critical Energy Infrastructure Information (CEII)

restrictions • Purpose of Local Transmission Planning Open

Public Meeting • LADWP serves as a Transmission Planner for its

system and as a Transmission Coordinator for the embedded municipal systems

3

Page 4: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Safety Moment

• Review surroundings • Emergency exit locations

4

Page 5: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Overview of LADWP’s Local Transmission Planning Process • Incorporated in Attachment K of the OATT • Separate Processes Different Than

– Generator to Transmission Interconnection – Transmission to Transmission Interconnection – Once-Thru Cooling (OTC) Study – 100% Renewable Energy Study

• Feeds into the regional and inter-regional planning processes

5

Page 6: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Overview of LADWP’s Local Transmission Planning Process • Comports with Order No. 890 Principles

– Open Public Participation – Purpose of Planning Studies, among other things:

• Transparent process that aligns with the FERC Planning Principles

• Provide adequate transmission for resources in order to reliably and economically serve Network and Native Load requirements for planned loads and resources.

• Accommodate requests for long-term transmission access.

6

Page 7: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Overview of LADWP’s Local Transmission Planning Process • Annual process • Ten year focus • Aligns with LADWP’s Strategic Long-Term Resource Plan • Factors in Public Policy Requirements applicable to LADWP and our

customers • Two types of Local Planning Studies

– Local Reliability Studies. – Local Economic Studies.

• Introduces a process to exchange data between LADWP and our customers – Network customers are obligated to provide load and resource forecasts – Non-disclosure agreement to protect confidential data – May be an additional restriction on supplying information to competitive duty

personnel (e.g., marketers)

7

Page 8: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Overview of LADWP’s Local Transmission Planning Process • Relationship to regional and inter-regional planning

processes – The LADWP local transmission planning process

coordinates with regional transmission planning processes through the Southwest Area Transmission (SWAT) group of WestConnect

– LADWP engages in regional planning and coordination within the WestConnect regional planning process

– LADWP coordinates its transmission plan on a west-wide inter-regional basis through SWAT and WestConnect

8

Page 9: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Attachment K 2018 Planning Cycle – Key Dates • May – July 2018: Transmission Planning Process (TPP) Model Development • June 2018: TPP Study Plan Finalized • June 8, 2018: Q2 Stakeholder Meeting

– Status of any unresolved issues from prior local TPP cycle – Base cases, assumptions, and plan for local transmission planning study process – Local needs identified on the system to be considered – Alternatives under consideration to be evaluated

• July – September 2018: TPP Analysis • November 2018: Draft TPP Results Released • Q4 Stakeholder Meeting

– Overview and review of the local transmission planning study and draft results – Update on planned local transmission projects and non-transmission alternatives

• December 2018: Final TPP Report Released

9

Page 10: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Attachment K Website

• http://www.oasis.oati.com/LDWP/ • Transmission Planning Folder

– Attachment K meeting notices – Presentations

10

Page 11: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Draft Business Practice In Development • LADWP is developing an Attachment K business

practice • Will be posted on OASIS in draft for stakeholder

comment before being finalized • Expected to be posted in Q3 2018 • Focus of Business Practice will be -

– Process and Timing for requesting local economic transmission planning studies

– Deposit requirements – Mechanisms to make requests

• Economic study request process & form

11

Page 12: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Discussion

12

Page 13: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Meeting Break

13

Page 14: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology, & Criteria • Base cases intended for use in the local transmission planning study

• WECC base cases model expected seasonal power flows throughout the West • All heavy summer cases will be stressed for High PDCI and VIC-LA conditions • Light Winter case will be stressed to reflect PDCI South to North flow and high

voltage conditions in LADWP system

Study Year Season WECC Base Case 2020 Heavy Summer 21HS2a

2023

Heavy Summer 23HS2a1 Light Winter 18LW2a1 Heavy Winter 23HW1a1 Light Spring 21LSP1a1

2028 Heavy Summer 28HS1a1

14

Page 15: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Assumptions planned for use in the local

transmission planning study – Modeled at the Receiving Station (RS) Bank Level

• Historical Power Factors • Historical Loading • Station/Field Capacitors

– Aggregate Load Forecast • Sept. 2017 Retail Electric Sales and Demand Forecast

(detailed on next slide) • 1-in-10 heat storm throughout the City of Los Angeles

15

Page 16: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • System Load Assumptions:

* Assume only 50% of the 2017 forecasted EE will be installed.

A B1 B2 C=A+B D E=C+D F G=E‐F

Year Net 1-in-10

Coincident Peak of Native Generation

Gross 1-in-10 Energy Efficiency *

Gross 1-in-10 + EE

Adjustments

Owens Valley

Load & Tran

Losses

Coincidental Peak

CHP Solar NEM

2018 6371 193 118 6682 46 6729 673 6055 2019 6353 193 128 6674 76 6750 679 6071 2020 6357 193 139 6689 101 6790 685 6105 2021 6374 193 149 6716 115 6831 693 6138 2022 6423 193 159 6775 124 6899 698 6201 2023 6469 193 170 6832 131 6963 700 6262 2024 6529 193 182 6904 135 7039 706 6333 2025 6580 193 200 6973 137 7110 713 6396 2026 6640 193 212 7044 139 7183 720 6463 2027 6698 193 222 7113 140 7253 727 6526 2028 6761 193 232 7187 142 7329 724 6605 2029 6819 193 242 7254 144 7398 714 6684 2030 6882 193 252 7327 147 7474 711 6763 2031 6938 193 263 7394 149 7543 699 6844 2032 7020 193 273 7486 151 7637 711 6926 2033 7064 193 283 7541 151 7692 683 7009 2034 7133 193 293 7620 151 7771 678 7093 2035 7197 193 302 7692 151 7843 665 7179 2036 7288 193 303 7784 151 7936 671 7265

16

Page 17: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Assumptions planned for use in the local

transmission planning study – Solar Generation Output Assumptions:

Seasons Months Hours Solar Generation Dispatch

Heavy Summer Jun-Aug 14:00-16:00 70% of Pmax Heavy Winter Dec-Feb 17:00-19:00 0 Light Winter Dec-Feb 02:00-04:00 0 Light Spring Mar-Apr 12:00-14:00 100% of Pmax

17

Page 18: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Internal Generation Assumptions:

Resource Type 2018 Capacity (MW) Pumped Storage 1265 Natural Gas (Basin Thermal) 3404 Wind (Pine Tree) 135

Solar (Pine Tree, Beacon, Adelanto, RE-Cinco, Spring Bok(1 & 2), Spring Bok 3(In-service by 2019)

679

Hydroelectric (Owens Gorge, PP1 & PP2)

220

Total Internal Generation 5703 % of Total Generation 61.5%

18

Page 19: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • External Generation Assumptions:

Resource Type 2018 Capacity (MW) Hydroelectric 496 Wind (Milford and PPM Wyoming)

369

Solar (Copper Mtn3, Moapa) 460 Coal (Intermountain) 1202 Geothermal 120 Nuclear (Palo Verde) 387 Natural Gas 531 Total External Generation 3565 % of Total Generation 38.5%

19

Page 20: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Renewable Energy Resources (2017 IRP)

Project Type Capacity MW Status Location 2020 2023 2028

Pine Tree Wind 135 Existing Barren Ridge 135 135 135 Milford1 Wind 200 Existing IPP 185 185 185 Milford2 Wind 102 Existing IPP 102 102 102

CopperMountain Solar 210 Existing Marketplace 210 210 210

Pine Tree Solar 8.5 Existing Barren Ridge 8.5 8.5 8.5 Adelanto Solar 10 Existing Adelanto 10 10 10

Solar-Owens Solar 150 New Inyo-Barren Ridge x x 199

Springbok_65 Solar 105 Existing Barren Ridge 105 105 105 Sprinkbok2-65 Solar 155 Existing Barren Ridge 155 155 155 Springbok3-65 Solar 90 New Barren Ridge 90 90 88

Beacon Solar 250 Existing Barren Ridge 250 250 250 Recinco Solar 60 Existing Barren Ridge 60 60 60

Moapa Solar 250 Existing Southern Nevada 250 250 250

20

Page 21: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Renewable Energy Resources (2017 IRP) continued

Project Type Capacity MW Status Location 2020 2023 2028

Solar_PPA_2021_E + 200 BESS (2hr) Solar 200 New Barren Ridge x 200 200

Solar_PPA_2023_E2 + 200 BESS (2hr) Solar 200 New Barren Ridge x 200 200

Solar_PPA_2020_L + 140 BESS (4hr) Solar 200 New IPP 200 200 200

Solar_PPA_2022_M + 185 BESS (4hr) Solar 370 New Mohave x 370 370

Compressed Air Energy Storage

Energy Storage 160 New IPP x x 160

21

Page 22: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Major WECC Path Flow

Transmission Corridor Path Rating SOL (MW)

Flow Range (MW)

Pacific DC Intertie (Path 65) 3220/-3100 500 to 3220

Intermountain DC (Path 27) 2400 400 to 2400

East-of-Colorado River (Path 49) 10100 3300 to 7500

West-of-Colorado River (Path 46) 11200 5000 to 8500

Victorville-Lugo 500 kV (Path 61) 2400/-900 300 to 2300

LADWP-SCE @ Sylmar (Path 41) 1600/1600 -600 to 1300

Adelanto-Toluca 500 kV Adelanto-Rinaldi 500 kV

Victorville-Rinaldi 500 kV Victorville-Century 287 kV Ln 1 &

Ln 2

3800

3800

22

Page 23: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Study plan to guide the local transmission planning

study – System Reliability Assessment

• Subject to NERC TPL-001-4 • WECC Planning Voltage Criteria • LADWP Voltage Criteria

– Support LADWP IRP Goals • 33% RPS by 2020 • Coal-Free by 2025 • 55% RPS by 2030 • 65% RPS by 2036

23

Page 24: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria

– Sensitivity Scenarios: Sensitivity Study Year Season Planning

Horizon Maximum Renewable Output

2020 Heavy Summer Near-Term 2023 Heavy Summer Near-Term 2023 Light Spring Near-Term 2028 Heavy Summer Long-Term

High PDCI (3220)

2020 Heavy Summer Near-Term 2023 Heavy Summer Near-Term 2023 Light Spring Near-Term 2028 Heavy Summer Long-Term

24

Page 25: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria

– Sensitivity Scenarios (continued): Sensitivity Study

Year Season Planning

Horizon High Vic-LA 2020 Heavy Summer Near-Term

2023 Heavy Summer Near-Term 2028 Heavy Summer Long-Term

Load Growth 5% 2020 Heavy Summer Near-Term 2023 Heavy Summer Near-Term 2023 Heavy Winter Near-Term 2023 Light Winter Near-Term 2023 Light Spring Near-Term 2028 Heavy Summer Long-Term

25

Page 26: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Study plan to guide the local transmission planning

study – Steady state and stability analyses for the LADWP Bulk

Electric System – Transient Stability for most severe single contingency

and multiple contingencies and critical transmission paths, identifying any inter-regional impacts

– Post-transient stability and reactive margins – Short circuit analysis – Identify mitigations to alleviate issues

26

Page 27: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Local needs identified on the system to be

considered in the study – Native load forecast – Renewable IRP additions – Intermountain Coal Replacement

27

Page 28: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Planned projects incorporated in the study

Modeled Year Infrastructure Improvements In-Service 2020 Beacon Solar Dec-2017

2020 Upgrade circuit ratings: Olive-Northridge, Haskell-Olive 230 kV Lines Apr-2018

2020 Beacon Battery Energy Storage System May-2018

2020 Scattergood-Olympic 230 kv Cable A May-2018

2020 Re-Conductor both Valley-Rinaldi 230 kV Lines Jun-2018

2020 Springbok Solar III Apr-2019

2020 Upgrade CVT and Wave Traps at Victorville to operate at 300kV Install new auto-transformer at Victorville 500/287 kV Transformer Bank K Jun-2020

2020 Shunt Reactor at Fairfax(completed) and Toluca Jun-2019

28

Page 29: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Planned Projects incorporated in study (continued)

Modeled Year Infrastructure Improvements In-Service 2023 Sylmar Filter Replacement Jan-2020

2023 Upgrade Toluca 500/230 kV Bank H Jun-2021

2023 Re-conductor Valley-Toluca 230kV Line 1&2 Jun-2020

2023 Lugo - Victorville upgrade Jun-2021

2023 New Rosamond Station Jun-2023

2023 Upgrade transformer bank E and F at Olympic Receiving Station Dec-2021

2023 Add voltage support in the LA Basin: Shunt Capacitors at Century, Wilmington, and Hollywood Jun-2021

2023 Convert PP1&PP2-Olive 115kV Lines 230kV Lines Sep-2022

2023 Re-Conductor Barren Ridge-Haskell Canyon 230 kV Line 1 Dec-2022

2023 Barren Ridge SVC Jun-2021

2023 Re-conductor Rinaldi-Tarzana 230kV Line 1 & 2 Jun-2022

2023 Increase Rinaldi Circuit Breakers (2 sets) and disconnect switches (3 sets) rating to 5000A Dec-2022

2023 RS-X Apr-2022

2023 Scattergood-Pershing-Olympic Cable B Jun-2020

29

Page 30: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

2018 Planning Assumptions, Methodology & Criteria • Planned Projects incorporated in study (continued)

Modeled Year Infrastructure Improvements In-Service 2028 Intermountain Coal Units Replacement to maximum of 1200 MW Dec-2025

2028 STS Replacement Project Dec-2025

30

Page 31: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Discussion

31

Page 32: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Sneak Peak at 2019 Attachment K Dates • February 1, 2019: Network customer load and resource forecasts due • Q2 Stakeholder Meeting

– Status of any unresolved issues from prior local TPP cycle – Base cases, assumptions, and plan for local transmission planning study process – Local needs identified on the system to be considered – Alternatives under consideration to be evaluated

• May – July 2019: Transmission Planning Process (TPP) Model Development • June 2019: TPP Study Plan Finalized • July – September 2019: TPP Analysis • November 2019: Draft TPP Results Released • Q4 Stakeholder Meeting

– Overview and review of the local transmission planning study and draft results – Update on planned local transmission projects and non-transmission alternatives

• December 2019: Final TPP Report Released

32

Page 33: LADWP Transmission Planning Stakeholder Meeting€¦ · LADWP Transmission Planning Stakeholder Meeting Attachment K Planning Q2 Meeting June 8, 2018 . 1 . ... (detailed on next slide)

Next Steps and Next Public Meeting

• Sign-up to participate or receive additional information by filling out the Planning Participation request form and sending it via email to : [email protected]

• Feedback and comments are welcome • Q4 Public Meeting date TBD

33