L6 Cooling Tower

download L6 Cooling Tower

of 58

Transcript of L6 Cooling Tower

  • 8/18/2019 L6 Cooling Tower

    1/58

    EXPERIMENTAL MANUAL 

    SOLTEQ®  EQUIPMENT FOR ENGINEERING EDUCATION

    WATER COOLING 

    TOWER 

    WATER COOLING 

    TOWER 

  • 8/18/2019 L6 Cooling Tower

    2/58

    Table of Contents

    Page

    List of Figures............................................................................................................................... i

    1.0 .INTRODUCTION ……………………………………………………………….…………………… 1 

    2.0. GENERAL DESCRIPTIONS 2.1 Components of the HE152 Basic Cooling Tower Unit …………………..….............. 2

    2.2 

    The Process Involved in the Operation ………………………………………………... 52.3 Overall Dimensions……………………………………………………………………….. 52.4 General Requirements……………………………………………………………………. 5

    3.0 SUMMARY OF THEORY 3.1  Basic Principle ………………………………………………………………............... 63.2  Evaporation from a Wet Surface …………………………….................................. 63.3  Cooling Tower Performance………………………………………………………….. 6

    3.4 

    Thermodynamic Property……………………………………………………………… 73.4.1  Dalton’s and Gibbs Laws…………………………………………………….. 73.4.2  Psychometric Chart…………………………………………………………… 8

    3.5 Orifice Calibration…………………………………………………………………………. 93.6  Application of Steady Flow Energy Equation………………………………………….. 103.7 Characteristics Column Study………………………………………………………….. 133.8 Useful Information………………………………………………………………………… 16

    4 0 EXPERIMENTAL PROCEDURE

  • 8/18/2019 L6 Cooling Tower

    3/58

     

     APPENDIX A Experimental Data Sheets

     APPENDIX B Sample Resul ts and Calculation

     APPENDIX C Components Properties and Diagram

     APPENDIX D Process Flow Diagram

  • 8/18/2019 L6 Cooling Tower

    4/58

    List of Figures

    Page

    Figure 1 Parts Identification and Equipment Set-up of Bench Top Cooling Tower 4

    Figure 2 System A 10

    Figure 3 System B 12

    Figure 4 Schematic Representations of the Air and Water Streamsentering and leaving a Block of Packing 13

    Figure 5 Graphical Representation of Tower Characteristics 15

  • 8/18/2019 L6 Cooling Tower

    5/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    1.0 INTRODUCTION

    The SOLTEQ®

     

    Basic Cooling Tower Unit  (Model: HE152) has been designed todemonstrate students the construction, design and operational characteristics of a moderncooling system. The unit resembles a full size forced draught cooling tower and it isactually an "open system" through which two streams of fluid (in this case air and water)pass and in which there is a mass transfer from one stream to the other. The unit is self-contained supplied with a heating load and a circulating pump. Once energy and massbalances are done, students will then be able to determine the effects on the performanceof the cooling tower by the following parameters:

    a)  Temperature and flow rate of waterb)  Relative Humidity and flow rate of airc)  Cooling load

     Additionally, a Packing Characteristics Column (optional) is available for SOLTEQ®

     

    Basic

    Cooling Tower Unit (Model: HE152). This column is designed to facilitate study of waterand air conditions at three additional stations (I, II and III) within the column. This enables

    driving force diagrams to be constructed and the determination of the Characteristic

    Equation for the Tower.

  • 8/18/2019 L6 Cooling Tower

    6/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    2.0  GENERAL DESCRIPTIONS

    2.1 Components of the HE152 Basic Cooling Tower Unit

    The unit comes complete with the following main components:

    i) Load Tank

    The load tank is made of stainless steel having a capacity of approximately 9liters. The tank is fitted with two cartridge heaters, 0.5 kW and 1.0 kW each, toprovide a total of 1.5 kW cooling load. A make-up tank is fixed on top of theload tank. A float type valve at the bottom of the make-up tank is to control theamount of water flowing into the load tank. A centrifugal type pump is suppliedfor circulating the water from the load tank through a flowmeter to the top ofthe column, into the basin and back to the load tank. A temperature sensorand temperature controller is fitted to load tank to prevent overheating. A levelswitch is fitted to the load tank so that when a low level condition occurs, the

    heater and the pump will be switched off.

    ii) Air Distribution Chamber

    The stainless steel air distribution chamber comes with a water collectingbasin and a one-side inlet centrifugal fan. The fan has a capacity ofapproximately 251 CFM of air flow. The air flowrate is adjustable by means ofan intake damper.

  • 8/18/2019 L6 Cooling Tower

    7/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    iv) Measurements

    Temperature sensors are provided to measure the inlet and outlet watertemperatures as well as the make-up tank water temperature. In addition,temperature sensors have been installed to measure the dry bulb and wet bulbtemperatures of inlet and outlet of the air. The followings show the list of codesassigned to each temperature sensors.

    T1 Dry Bulb Temperature of the Inlet AirT2 Wet Bulb Temperature of the Inlet AirT3 Dry Bulb Temperature of the Outlet AirT4 Wet Bulb Temperature of the Outlet AirT5 Inlet Water TemperatureT6 Outlet Water TemperatureT7 Make up Tank TemperatureT8 Hot Water Tank Temperature

     A differential pressure transmitter is provided for the measurement of pressuredrop across the packed column. On the other hand, the differential pressuretransmitter and the orifice are also used to determine the air flowrate.

     A flowmeter is provided for the measurement of water flowrate. The flowmeteris ranged at 0.4 to 4 LPM.

  • 8/18/2019 L6 Cooling Tower

    8/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    1

    2

    6

    4

    5

    3

    7

    8

    9

    10

  • 8/18/2019 L6 Cooling Tower

    9/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    2.2 The Process Involved in the Operation

    i) 

    Water Circuit

    Water temperature in the load tank will be increased before the water ispumped through a control valve and flow meter to the column cap. Beforeentering the column cap, the inlet temperature of the water is measured andthen the water is uniformly distributed over the top packing deck. This createsa large thin film of water, which is exposed to the air stream. The water getscooled down, while passing downward through the packing, due to theevaporation process. The cooled water falls into the basin below the lowestdeck and return to the load tank where it is re-heated before re-circulation. Theoutlet temperature is measured at a point just before the water flows back intothe load tank. Evaporation causes the water level in the load tank to fall. Theamount of water lost by evaporation will be automatically compensated byequal amount from the make-up tank. At steady state, this compensation rateequals the rate of evaporation plus any small airborne droplets discharged with

    the air.

    ii) Air Circuit

     A one-side inlet centrifugal fan draws the air from the atmosphere into thedistribution chamber. The air flow rate is varied by means of an intake damper.The air passes a dry bulb temperature sensor and wet bulb temperaturesensors before it enters the bottom of the packed column. While the air stream

    th h th ki it i t t t i d th t

  • 8/18/2019 L6 Cooling Tower

    10/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    3.0  SUMMARY OF THEORY

    3.1 Basic Princ iple

    First consider an air stream passing over the surface of a warm water droplet orfilm. If we assume that the water is hotter than the air, then the water temperaturewill be cooled down by radiation, conduction and convection, and evaporation. Theradiation effect is normally very small and may be neglected. Conduction andconvection depend on the temperature difference, the surface area, air velocity,etc. The effect of evaporation is the most significant where cooling takes place aswater molecules diffuse from the surface into the surrounding air. During theevaporation process, the water molecules are replaced by others in the liquid fromwhich the required energy is taken.

    3.2  Evaporation from a Wet Surface

    When considering evaporation from a wet surface into the surrounding air, the rate

    is determined by the difference between the vapour pressure at the liquid surfaceand the vapour pressure in the surrounding air. The vapour pressure at the liquidsurface is basically the saturation pressure corresponding with the surfacetemperature, whereas the total pressure of the air and its absolute humiditydetermines the vapour pressure in the surrounding air. Such evaporation processin an enclosed space shall continue until the two vapour pressures are equal. Inother words, until the air is saturated and its temperature equals the surface.

    H if t t d i i t tl li d th t f ill h

  • 8/18/2019 L6 Cooling Tower

    11/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    The effect of these factors will be studied in depth by varying it. In this way,students will gain an overall view of the operation of cooling tower.

    3.4 Thermodynamic Property

    In order to understand the working principle and performance of a cooling tower, abasic knowledge of thermodynamic is essential to all students. A brief review onsome of the thermodynamic properties is presented below.

     At the triple point (i.e. 0.00602 atm and 0.01°C), the specific enthalpy of saturatedwater is assumed to be zero, which is taken as datum. The specific enthalpy ofsaturated water (h f 

     

    ) at a range of temperatures above the datum condition can beobtained from thermodynamic tables.

    Thespecific enthalpy of compressed liquid is given by

    ( )satf f    ppvhh   −+=   (1)

    The correction for pressure is negligible for the operating condition of the coolingtower; therefore we can see that h ≈ hf  

    at a given temperature.

    Specific heat capacity  (Cp) is defined as the rate of change of enthalpy withrespect to temperature (often called the specific heat at constant pressure). For thepurpose of experiment using bench top cooling tower, we may use the followingrelationship:

  • 8/18/2019 L6 Cooling Tower

    12/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    same temperature.

    The Absolute or Specific Humidity is defined as follows:

     Air Dryof Mass

    Vapour Water of MassHumiditySpecific   =ω ,   (4)

    The Relative Humidity is defined as follows:

    etemperatur sametheatVapour Water of essureSaturation

     Air theinVapour Water of essurePartialHumiditylative

    Pr 

    Pr ,Re

    =

    φ   (5)

    The Percentage Saturation is defined as follows:

    TempsametheatVapour Water Satof volsameof Mass Air of VolumegivenainVapour Water of Mass

    SaturationPercentage

    =   (6)

     At high humidity conditions, it can be shown that there is not muchdifference between the "Relative Humidity" and the "PercentageSaturation" and thus we shall regard as the same.

    To measure the moisture content of the atmosphere, this bench top

  • 8/18/2019 L6 Cooling Tower

    13/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    3.5 Orifice Calibration

     As mentioned above, the psychometric chart can be used to determine the valueof the specific volume. However, the values given in the chart are for 1 kg of dry airat the stated total pressure.

    However, for every 1 kg of dry air, there is w kg of water vapour, yielding the totalmass of 1 + w kg.

    Therefore, the actual specific volume of the air/vapor mixture is given by:

    ϖ +=1

    ba

    a

    vv   (7)

    The mass flow rate of air and steam mixture through the orifice is given by

    av

    x

    m  01370

    .

    =

      (8)

    Where,m   = Mass flow rate of air/vapor mixture vax = Orifice differential in mmH

      = Actual specific volume and

    2

     0.

  • 8/18/2019 L6 Cooling Tower

    14/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    3.6 Appl ication of Steady Flow Energy Equation

    Consider System A for the cooling tower defined as in Figure 2. It can be seen thatfor this system, indicated by the dotted line,

    a) Heat transfer at the load tank and possibly a small quantity to surroundingsb) Work transfer at the pumpc) Low humidity air enters at point Ad) High humidity air leaves at point Be) Make-up enters at point E, the same amount as the moisture increase in the

    air stream

     A

    B

    E

    am  

    am  

     E m  

  • 8/18/2019 L6 Cooling Tower

    15/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    Note:

    a) The mass flow rate of dry air ( am ) through a cooling tower is a constant,

    whereas the mass flow rate of moist air increases as the result of evaporationprocess.

    b) The term  E  E hm  can usually be neglected since its value is relatively small.

    Under steady state conditions, by conservation of mass, the mass flow rate of dryair and of water (as liquid or vapour) must be the same at inlet and outlet to anysystem.

    Therefore,

    ( ) ( ) Ba Aa

      mm     =   (13)

    and

    ( ) ( ) Bs E  As   mmm 

      =+   or

    ( ) ( ) As Bs E 

      mmm     −=   (14)

    The ratio of steam to air (ϖ  ) is known for the initial and final state points on thepsychrometric charts. Therefore,

    =

  • 8/18/2019 L6 Cooling Tower

    16/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    Say, we re-define the cooling tower system to be as in Figure 3 where the processheat and pump work does not cross the boundary of the system. In this case warm

    water enters the system at point C and cool water leaves at point D.

    Figure 3: System B 

    Bam  

    C

    wm

     

     A

    am  

    D

     E m  E

  • 8/18/2019 L6 Cooling Tower

    17/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    3.7  Characteristics Column Study

    In order to study the packing characteristics, we define a finite element of thetower (dz) as shown in Figure 4, the energy balances of the water and air streamsin the tower are related to the mass transfer by the following equation:

    ( )hdVaKdTmC WpW ∆=   (20)

    where

    WpC  = Specific heat capacity of water

    Wm  = Mass flow rate of water per unit plan area of packing

    T   = Water TemperatureK   = Mass Transfer Coefficienta   = Area of contact between air and water per unit volume of packingV   = Volume occupied by packing per unit plan areah∆

      = Difference in specific enthalpy between the saturated boundary layer andthe bulk air

    WATER

    INLET

     AIR

    OUTLET

    T2 

    H2

    mw 

    t2 

    h2

    ma 

  • 8/18/2019 L6 Cooling Tower

    18/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    Integrating Equation 21,

    ∫   −=2

    1

    T

    T   aw

    p

    W   hh

    dTCm

    VKaW

      (22)

    The numerical solution to the integral expression Equation 22 using Chebyshevnumerical method gives,

     

     

     

     

    ∆+∆+∆+∆

    =−= ∫ 432112   1111

    4

    2

    1

    hhhh

    TT

    hh

    dTCm

    VKaT

    T aw

    p

    WW

      (23)

    Where

    Wm

    VKa

     = Tower Characteristic

    1h∆   = value of aw   hh   −  at ( )212   1.0   T T T   −+

     2

    h∆   = value of aw   hh   −  at ( )212   40   TTT   −+   .  

    3h∆   = value of aw   hh   −  at ( )211   4.0   T T T    −−  

    4h∆   = value of aw hh   −  at ( )211   1.0   T T T    −−  

    Thermodynamics state that the heat removed from the water must be equal to theheat absorbed by the surrounding air. Therefore, the following equation is derived:

  • 8/18/2019 L6 Cooling Tower

    19/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    Figure 5:Graphical Representation of Tower Characteristics

    The following represents a key to Figure 5: 

    BA = Initial enthalpy driving force

     Air Operating Line

    Enthalpy

    Driving Force

    (hw-ha)

    hw2 (Hot water Temp)

    hw1 (Cold water Temp)

    ha2 (Air out)

    ha1 (Air in)

    Water Operating Line

    C

     Approach Range

    Temperature

    Twb (In) T1 Twb (Out) T2

    L/G A

    D

    B

    Saturation Curve

    Enthalpy

  • 8/18/2019 L6 Cooling Tower

    20/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    3.8 Useful Information

    1. Orifice Calibration Formula:

    Mass flow rate of air and vapor mixture,

    ( )

    bav

     xm

      ϖ +=

      10137.0  

    The mass flow rate of dry air,

    ( )ϖ +=

    10137.0

    ba

    av

     xm  

    Where,

    x  = orifice differential in mmH2

     Ba

    v

    0,

    = specific volume of air at the outlet

    ϖ    = humidity ratio of the mixture

    2. Pump Work Input = 80W (0.08kW)

    3.  Column Inner Dimension = 150 mm x 150 mm x 600 mm

  • 8/18/2019 L6 Cooling Tower

    21/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.0 EXPERIMENTAL PROCEDURES

    4.1 General Operating Procedures

    4.1.1  General Start-up Procedures

    1.  Check to ensure that valves V1 to V6 are closed and valve V7 ispartially opened.

    2.  Fill the load tank with distilled or deionised water. It is done by firstremoving the make-up tank and then pouring the water through the

    opening at the top of the load tank. Replace the make-up tank ontothe load tank and lightly tighten the nuts. Fill the tank with distilled ordeionised water up to the zero mark on the scale.

    3.   Add distilled/deionised water to the wet bulb sensor reservoir to thefullest.

    4.  Connect all appropriate tubing to the differential pressure sensor.5.  Install the appropriate cooling tower packing for the experiment.

    6.  Then, set the temperature set point of temperature controller to 50°C.Switch on the 1.0 kW water heater and heat up the water untilapproximately 40°C.

    7.  Switch on the pump and slowly open the control valve V1 and set thewater flowrate to 2.0 LPM. Obtain a steady operation where the wateris distributed and flowing uniformly through the packing.

    8.  Fully open the fan damper, and then switch on the fan. Check that thedifferential pressure sensor is giving reading when the valve manifold

  • 8/18/2019 L6 Cooling Tower

    22/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.1.2  General Shut-Down Procedure

    1.  Switch off heaters and let the water to circulate through the coolingtower system for 3-5 minutes until the water cooled down.

    2.  Switch of the fan and fully close the fan damper.3.  Switch off the pump and power supply.4.  Retain the water in reservoir tank for the following experiment.5.  Completely drain off the water from the unit if it is not in used.

    4.2 Experiment 1: General Observation of the Forced Draught Cooling Tower

    Objective:

    To observe the processes within a forced draught cooling tower

    1.  Perform the general start-up procedures and observe the forced draughtcooling tower proves.

    2.   As the warm water enters the top of the tower, it is fed into channels fromwhich it flows via water distribution system onto the packing. The channels aredesigned to distribute the water uniformly over the packing with minimumsplashing.

    3.  The packing surfaces are easily wetted and the water spreads over thesurfaces to expose a large area to the air stream.

    4.  The cooled water falls from the lowest packing into the basin and then ispumped to the simulated load in the load tank.

  • 8/18/2019 L6 Cooling Tower

    23/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.3 Experiment 2: End State Properties of Air and Steady Flow Equations

    Objective:To determine the “end state” properties of air and water from tables or chartsTo determine Energy and mass balances using the steady flow equation on theselected systems

    Procedure:

    1.  Prepare and start the cooling tower with according to Section 4.1.1.2.  Set the system under the following conditions and allow stabilizing for about 15

    minutes.Water flow rate : 2.0 LPM Air Flow : MaximumCooling load : 1.0 kWColumn installed : A

    3.  Fill up the make-up tank with distilled water up to zero mark at the level scale,and then start the stop watch.

    4. 

    Determine the make-up water supply in an interval of 10 minutes.5.  In this 10 minutes interval, record a few sets of the measurements (i.e.temperatures (T1–T7), orifice differential pressure (DP1), water flowrate (FT1)and Heater Power (Q1)), then obtain the mean value for calculation andanalysis.

    6.  Determine the quantity of make up water that has been supplied during thetime interval by noting the height reduction in the make-up tank.

    7.  The observation may be repeated at different conditions, i.e. at different water

  • 8/18/2019 L6 Cooling Tower

    24/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.4 Experiment 3: Investigation of the Effect of Cooling Load on Wet Bulb Approach

    Objective:

    To investigate the effect of cooling load on “Wet Bulb Approach”

    Procedure:

    1.  Prepare and start the cooling tower with according to Section 4.1.1.2.  Set the system under the following conditions and allow stabilizing for about 15

    minutes.

    Water flow rate : 2.0 LPM Air Flow : MaximumCooling load : 0 kWColumn installed : A

    3.   After the system stabilizes, record a few sets of measurements (i.e. air inletdry bulb and wet bulb temperature (T1 and T2), water outlet temperature (T6),orifice differential pressure (DP1), water flowrate (FT1) and Heater Power

    (Q1)), then obtain the mean value for calculation and analysis.4.  Without changes in the conditions, increase the cooling load to 0.5 kW. Whenthe system stabilized, record all data.

    5.  Similarly, repeat the experiment at 1.0kW and 1.5kW.6.  Finally, measure the cross sectional area of the column.7.  The four tests may be repeated at another constant airflow.8.  The observation may also be repeated at different conditions, i.e. at different

    water flow rates, or different air flow rates and with different load.

  • 8/18/2019 L6 Cooling Tower

    25/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.5 Experiment 4: Investigation of the Effect of Air Velocity on Wet bulb Approach and Pressure Drop through the Pack ing

    Objective:

    To investigate the effect of air velocity on:(a)  Wet Bulb Approach(b)  The pressure drop through the packing

    Procedure:

    1.  Prepare and start the cooling tower with according to Section 4.1.1.

    2.  Set the system under the following conditions and allow stabilizing for about 15minutes.Water flow rate : 2.0 LPM Air flow rate : MaximumCooling load : 1.0 kWColumn installed : A

    3.  After the system stabilizes, record a few sets of measurements (i.e.temperature (T1-T6), orifice differential pressure (DP1), water flowrate (FT1).heater power (Q1) and pressure drop across packing (DP2)), then obtain themean value for calculation and analysis.

    4.  Repeat the test with 3 different sets of orifice pressure drop values (75%, 50%and 25% of the maximum value) without changing the water flow rate andcooling loads.

    5.  Finally, measure the cross sectional area of the column.6.  The test may be repeated:

  • 8/18/2019 L6 Cooling Tower

    26/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.6  Experiment 5: Investigation of the Relationship between Cooling Load andCooling Range

    Objective:

    To investigate the relationship between cooling load and cooling range

    Procedure:

    1. Prepare and start the cooling tower with according to Section 4.1.1.2. Set the system under the following conditions and allow stabilizing for about 15

    minutes:

    Water flow rate : 2.0 LPM Air flow rate : MaximumCooling load : 0.0 kWColumn installed : A

    3.  After the system stabilized, record a few sets of measurements (i.e.temperature (T1-T6), orifice differential pressure (DP1), water flowrate (FT1)and heater power (Q1)), then obtain the mean value for calculation andanalysis

    9.  Without changes in the conditions, increase the cooling load to 0.5 kW. Whenthe system stabilized, record all data.

    4.  Similarly, repeat the experiment at 1.0kW and 1.5kW.5.  The tests may be repeated:

    i.At other water flow ratesii.At other air flow rate

  • 8/18/2019 L6 Cooling Tower

    27/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.7  Experiment 6:  Investigation of the Effect of Packing Density on thePerformance of the Cooling Tower

    Objective:

    To investigate the effect of packing density on the performance of the coolingtower

    Procedure:

    1. Prepare and start the cooling tower with according to Section 4.1.1.2. Set the system under the following conditions and allow stabilizing for about 15

    minutes:Water flow rate : 2.0 LPMOrifice differential : MaximumCooling load : 1.0kWColumn installed : A

    3.  After the system stabilizes, record a few sets of measurements (i.e.temperature (T1-T6), orifice differential pressure (DP1), water flowrate (FT1).heater power (Q1) and pressure drop across packing (DP2)), then obtain themean value for calculation and analysis.

    4.  Without changing condition, change the column packing to column B. Whenstability is achieved, repeat the observation.

    5.  Repeat step 4 with column B and C.6.  The tests may be repeated:

    i.   At other water flow ratesii.   At other air flow rates

  • 8/18/2019 L6 Cooling Tower

    28/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    4.8  Experiment 7: Determination of Characteristic Equation of the PackingCharacteristic Column

    Objectives:

    To determine the Characteristic Equation of the cooling tower using Packing

    Characteristic Column

    Procedures:

    1. 

    Install the Packing Characteristic Column (Column E) properly.2.  Prepare and start the cooling tower with according to Section 4.1.1.3.  Set the system under the following conditions and allow stabilizing for about 15

    minutes:Water flow rate : 1.5 LPMOrifice differential : MaximumCooling load : 1.0kWColumn installed : E

    4.   After the system stabilizes, record a few sets of measurements (i.e.temperature (T1-T6 and T8-T15), orifice differential pressure (DP1), waterflowrate (FT1) and heater power (Q1)), then obtain the mean value forcalculation and analysis.

    5.  Without changing the air flow rate, and cooling load, change the water flowrate to 2.0 LPM. When stability is achieved, repeat the observation.

    6.  Similarly, repeat the observations at 2.5 LPM.

  • 8/18/2019 L6 Cooling Tower

    29/58

    SOLTEQ® BENCH TOP COOLING TOWER UNIT (MODEL: HE152)

    5.0 REFERENCES

    Perry, R.H., Green, D.W. and Maloney, J.O., “Perry’s Chemical Engineering Handbook”, 6th

     

    Edition, McGraw Hill, 1984.

  • 8/18/2019 L6 Cooling Tower

    30/58

     

     Appendix A

  • 8/18/2019 L6 Cooling Tower

    31/58

    Experiment 2: End State Properties of Air and Steady Flow Equations  

    Results:

    Column Installed : _______

    Initial water level : cm

    Final water level : cm

    Time Interval : minutes

    Packing Density m-1 

     Air Inlet Dry Bulb, T1 ˚C

     Air Inlet Wet Bulb, T2 ˚C

     Air Outlet Dry Bulb, T3 ˚C

     Air Outlet Wet Bulb, T4 ˚C

    ˚

  • 8/18/2019 L6 Cooling Tower

    32/58

  • 8/18/2019 L6 Cooling Tower

    33/58

    Experiment 4: Investigation of the Effect of Ai r Velocity on Wet bulb Approach and Pressure

    Drop through the Packing

    Results:

    Column Installed : _____

    Description Unit

     Air Flow

    100 % 75 % 50 % 25 %

    Packing Density m-1 

     Air Inlet Dry Bulb, T1 ˚C

     Air Inlet Wet Bulb, T2 ˚C

     Air Outlet Dry Bulb, T3 ˚C

     Air Outlet Wet Bulb, T4 ˚C

  • 8/18/2019 L6 Cooling Tower

    34/58

    Experiment 5: Investigation of the Relationship between Cooling Load and Cooling Range 

    Results:

    Column Installed : ____

    Description Unit 0.0kW 0.5kW 1.0kW 1.5kW

    Packing Density m-1 

     Air Inlet Dry Bulb, T1 ˚C

     Air Inlet Wet Bulb, T2 ˚C

     Air Outlet Dry Bulb, T3 ˚C

     Air Outlet Wet Bulb, T4 ˚C

    Water Inlet Temperature, T5 ˚C

  • 8/18/2019 L6 Cooling Tower

    35/58

    Experiment 6: Investigation of the Effect of Packing Density on the Performance of the

    Cooling Tower  

    Results:

    Description UnitColumn

     A B C

    Packing Density m-1 

     Air Inlet Dry Bulb, T1 ˚C

     Air Inlet Wet Bulb, T2 ˚C

     Air Outlet Dry Bulb, T3 ˚C

     Air Outlet Wet Bulb, T4 ˚C

    Water Inlet Temperature, T5 ˚C

  • 8/18/2019 L6 Cooling Tower

    36/58

    Experiment 7: Determination of Characteristic Equation of the Packing Characteristic

    Column

    Result:

    Description UnitWater Flowrate (LPM)

    1.5 2.0 2.5

    Top

     Air Outlet Dry Bulb, T3 ˚C

     Air Outlet Wet Bulb, T4 ˚C

    Water Inlet Temperature, T5 ˚C

    Station III

     Air Dry Bulb, T8˚C

     Air Inlet Wet Bulb, T9 ˚C

    Water Temperature, T14 ˚C

    Station II

    AirDryBulb T10 ˚C

  • 8/18/2019 L6 Cooling Tower

    37/58

     

  • 8/18/2019 L6 Cooling Tower

    38/58

     

  • 8/18/2019 L6 Cooling Tower

    39/58

    Experiment 2: End State Properties of Air and Steady Flow Equations  

    Results:

    Column Installed : A .

    Initial water level : 0 cm

    Final water level : 4.0 cm

    Time Interval : 10 minutes

    Descript ion Unit Value

    Packing Density m-1  110

     Air Inlet Dry Bulb, T1 ˚C 31.6

     Air Inlet Wet Bulb, T2 ˚C 27.1

     Air Outlet Dry Bulb, T3 ˚C 30.2

    ˚

  • 8/18/2019 L6 Cooling Tower

    40/58

    Calculation:

    By plotting the air inlet dry bulb and air inlet wet bulb (point A) and air outlet dry bulb and airoutlet wet bulb (point B) on the Psychrometric chart, the enthalpy and humidity of air mixture is

    obtained and the result is showed as below:

    h A  = 88.0 kJ/kg

    w A = 0.023 kg water/kg dry air

    hB  = 96.0kJ/kgwB  = 0.0268 kg water/kg dry air

    vaB = 0.950 m3/(kg dry air)

    From the orifice calibration,

    ( )baBa

    wv xm+

    =1

    0137.0  

    x = 88Pa x 1mm H2O / 10.13Pa

    = 8.69 mm H2O

  • 8/18/2019 L6 Cooling Tower

    41/58

      1.600

    172.0   −=   skg   

    = 2.867 x 10-4 kg.s-1

    Specific enthalpy of make-up,

    hE = 126.586kJ/kg (at T7)

     Applying the Steady Flow Equation to the system indicated by the chain the (System A)

    EKHPQ     ∆−∆=−  

    Now, solving the left side,

    ( )W W  P Q 65883   −−=−  

    = 948W (Work by pump is estimate –65W)

    On the right side of the equation,

    0≈∆   E  K   (change of air velocity is negligible)

  • 8/18/2019 L6 Cooling Tower

    42/58

    Experiment 3: Investigation of the Effect of Cooling Load on Wet Bulb Approach

    Results:

    Column Installed : A .

    Description Unit 0.0kW 0.5kW 1.0kW 1.5kW

    Packing Density m-1  - 110 110 110

     Air Inlet Dry Bulb, T1 ˚C - 31.5 31.7 31.8

     Air Inlet Wet Bulb, T2 ˚C - 27.1 27.2 27.3

    Water Outlet Temperature, T6 ˚C - 29 30.6 32.1

    Orifice Differential, DP1 Pa - 89 89 89

    Water Flow Rate, FT1 LPM - 2.0 2.0 2.0

  • 8/18/2019 L6 Cooling Tower

    43/58

    Specific volume at outlet = 0.950 m3/kg

    ( x = 89 Pa x 1mm H2O / 10.13 Pa = 8.786mm H2O )

    am  = Bv

     x0137.0  

    =950.0

    786.80137.0  

    = 0.0417 kg/s

    Cross sectional area of column (A) = 0.15 x 0.15 m2 

    = 0.0225m2 

     Air mass flow per unit area = A

    ma

     

    =21

    0225.0

    0417.0   −−mkgs  

    = 1.853kg s-1m-2 

    Water flow rate per unit area = A

    mW

     

    min1kg

  • 8/18/2019 L6 Cooling Tower

    44/58

    Results:

    Description 1 2 3

    Packing Density, m-1 110 110 110

     Air Flow per Unit Area, kgs-1m-2 1.853 1.853 1.853

    Total Cooling Load, kW 0.536 0.964 1.424

     Approach to Wet Bulb, K 1.9 3.6 4.8

  • 8/18/2019 L6 Cooling Tower

    45/58

    Experiment 4: Investigation of the Effect of Ai r Velocity on Wet bulb Approach and Pressure

    Drop through the Packing

    Results:

    Column Installed : A .

    Description Unit Air Flow

    100 % 75 % 50 % 25 %

    Packing Density m-1  110 110 110 110

     Air Inlet Dry Bulb, T1 ˚C  29.5 29.9 30.2 31.0

     Air Inlet Wet Bulb, T2 ˚C 26.3 26.5 26.8 27.2

     Air Outlet Dry Bulb, T3 ˚C  29.4 29.8 30.4 31.8

     Air Outlet Wet Bulb, T4 ˚C 28.4 28.7 29.5 30.7

  • 8/18/2019 L6 Cooling Tower

    46/58

    Calculation:

    By taking the data obtained when 100% of air flow was employed,Inlet wet bulb temperature = 26.3oC

    Outlet water temperature = 30.6 oC

    “Approach to wet bulb” = 30.6 – 26.3 K

    = 4.3K

    Specific volume of air at outlet (by plotting Air Outlet Dry bulb and Air Outlet Wet bulb on the

    Psychometric Chart) = 0.890m3kg-1

     Air mass flow rate = Bv

     x0137.0  

    (x = 89 Pa x 1mm H2O / 10.13 Pa = 8.786 mm H2O)

    =890.0

    786.80137.0  

    = 0.04049 kgs-1 

     Air volume flow rate =Bvm  

    v   = 0.04049 x 0.893 m3s-1 

    v =0.0362m3s-1

  • 8/18/2019 L6 Cooling Tower

    47/58

    Results:

    1 2 3 4

    Nominal Velocity of Air, ms-1  1.7027 1.609 1.2387 0.9064

     Approach to Wet Bulb, K 4.3 3.6 4.5 5.5

    Pressure, mm H2O 0.3949 0.8885 1.4808 1.7769

  • 8/18/2019 L6 Cooling Tower

    48/58

    Experiment 5: Investigation of the Relationship between Cooling Load and Cooling Range 

    Results:

    Column Installed : A .

    Description Unit 0.0kW 0.5kW 1.0kW 1.5kW

    Packing Density m-1  - 110 110 110

     Air Inlet Dry Bulb, T1 ˚C - 30.5 30.8 30.9

     Air Inlet Wet Bulb, T2 ˚C - 27.2 27.3 27.4

     Air Outlet Dry Bulb, T3 ˚C - 28.6 29.3 30.9

     Air Outlet Wet Bulb, T4 ˚C - 28.3 28.7 29.9

    Water Inlet Temperature, T5 ˚C - 32.9 35.4 39.4

  • 8/18/2019 L6 Cooling Tower

    49/58

     

  • 8/18/2019 L6 Cooling Tower

    50/58

    Experiment 6: Investigation of the Effect of Packing Density on the Performance of the

    Cooling Tower  

    Results:

    Description UnitColumn

     A B C

    Packing Density m-1  110 77 200

     Air Inlet Dry Bulb, T1 ˚C 30.1 30.2 31.0

     Air Inlet Wet Bulb, T2 ˚C 27.4 27.3 27.5

     Air Outlet Dry Bulb, T3 ˚C 29.7 30.1 30.4

     Air Outlet Wet Bulb, T4 ˚C 29.4 29.6 29.7

    Water Inlet Temperature, T5 ˚C 37.7 38.6 37.4

  • 8/18/2019 L6 Cooling Tower

    51/58

    Results:

    1 2 3

    Packing Density, m-1 77 110 200

     Approach to Wet Bulb, K 5 4.2 3.8

  • 8/18/2019 L6 Cooling Tower

    52/58

    Experiment 7: Determination of Characteristic Equation of the Packing Characteristic

    Column

    Results:

    Description UnitWater Flowrate (LPM)

    1.5 2.0 2.5

    Top

     Air Outlet Dry Bulb, T3 ˚C 29.9 30.3 30.3

     Air Outlet Wet Bulb, T4 ˚C 29.1 29.8 29.7

    Water Inlet Temperature, T5 ˚C 39.3 38.5 36.2

    Station III

     Air Dry Bulb, T8˚C 31.6 32.1 31.7

     Air Inlet Wet Bulb, T9 ˚C 29.6 30.0 29.8

    Water Temperature, T14 ˚C 35.5 35.6 34.2

    Station II

    AirDryBulb T10 ˚C 297 305 325

  • 8/18/2019 L6 Cooling Tower

    53/58

    Calculation:

    By taking the data obtained when 2.50 LPM of water was used,

     s LPM mw

    60min

    L1kg 50.2   ××=  

    = 0.04167 kg s-1

    vaB = 0.8980 m3/(kg dry air)

    wb = 0.0266 kg water/kg dry air

    ( )baBa

    wv

     xm

    +=

    10137.0  

    x = 49 Pa x 1mmH2O / 10.13Pa = 4.84 mmH2O

    10314.0  −=   kgsma  

    For Air Operating Line,

    T1 = Water Outlet temperature, T6 (31.5°C)

    T2 = Water Inlet temperature, T5 (36.2°C)

  • 8/18/2019 L6 Cooling Tower

    54/58

    ( )212   1.0   T T T    −+   = 35.73̊C 

    ( )212 40   TTT   −+   .   = 34.32̊C 

    ( )211   4.0   T T T    −−   = 33.38̊C ( )211   1.0   T T T    −−   = 31.97̊C 

    Therefore, from the graph,

    1h∆   = 15.92 kJ/kg

    2h∆   = 14.23 kJ/kg

    3h∆   = 12.93 kJ/kg

    4h∆   = 10.09 kJ/kg

    ( )

    ( )12

    12

    TT

    hh

    G

    L   aa

    −=  

    Referring to the Driving Force Diagram Plotted

    L/G =110.84 93.96

    36.2 31.5

    − 

  • 8/18/2019 L6 Cooling Tower

    55/58

     

     Appendix CComponents Properties and Diagrams

  • 8/18/2019 L6 Cooling Tower

    56/58

     

  • 8/18/2019 L6 Cooling Tower

    57/58

     

     Appendix DProcess Flow Diagram

  • 8/18/2019 L6 Cooling Tower

    58/58

    T7

    V2

    T8

    TC

    Temp

    Controller 

    Heater 

    Pump

    Drain

    V8

    V7

    Hot Water 

    Tank

    Make-up

    Tank

    V1

    FT1

    Flowmeter 

    T4

    T2T1

    T3

     Air Blower 

     Air In

    Receiver Tank

    Orifice

     Air Out

    Water 

    Distributor 

    Test Section

    (Packed Column)

    T5

    T6

    V3

    V4V6 V5

     Atm

    DP 1

    High Low

    WATER COOLING TOWER (MODEL: HE152)