L2468-VIE: Health Care in the South Central Coast …...Social Monitoring Report External...
Transcript of L2468-VIE: Health Care in the South Central Coast …...Social Monitoring Report External...
Social Monitoring Report External Resettlement Monitoring Report January 2015
L2468-VIE: Health Care in the South Central Coast
Region Project
Prepared by the Ministry of Health, Socialist Republic of Viet Nam, for the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
MINISTRY OF HEALTH, VIETNAM
FINAL REPORT
on
Land Acquisition and Resettlement Activities for
Health Care in the South Central Coast Region
Project (ADB Loan 2468)
Vietnam, November 2014
- 2 -
CONTENTS
LIST OF ABBREVIATIONS ....................................................................................... - 3 -
GLOSSARY ................................................................................................................... - 4 -
PART I. OVERVIEW ................................................................................................... - 6 -
PART II. ASSESSMENT METHODOLOGY ........................................................... - 7 -
PART III. STATUS OF IMPLEMENTATION ......................................................... - 8 -
1. Summary Scope of Land Acquisition and Resettlement Impacts ............................................... - 8 -
2. Detailed on the Status of Land Acquisition and Resettlement in Project Provinces/Cities .... - 11 -
3. Implementation procedure ............................................................................................................ - 16 -
PART IV. RESULTS OF LAND ACQUISITION ACTIVITIES .......................... - 22 -
CONCLUSIONS AND RECOMMENDATIONS .................................................... - 27 -
ANNEX 1 ..................................................................................................................... - 29 -
ANNEX 2 ..................................................................................................................... - 31 -
ANNEX 3 ..................................................................................................................... - 32 -
- 3 -
LIST OF ABBREVIATIONS
ADB
AP
CPC
DH(s)
ha
HHs
km
m
MOH
PMC
PMU
PPC
PPMU
RP
SMS
US
VNĐ
Asian Development Bank
Affected person
Commune People’s Committee
District Hospital(s)
Hectare
Households
Kilometer
Meter
Ministry of Health
Preventive Medicine Center
Project Management Unit
Provincial People’s Committee
Provincial Project Management Unit
Resettlement Plan
Secondary medical school
The United States
Vietnam Dong
- 4 -
GLOSSARY
Affected person
(AP)
means any person or persons, household, firm, private or public institution that, on account of changes resulting from the Project, will have its (i) standard of living adversely affected; (ii) right, title or interest in any house, land (including residential, commercial, agricultural, forest, salt mining and/or grazing land), water resources or any other moveable or fixed assets acquired, possessed, restricted or otherwise adversely affected, in full or in part, permanently or temporarily; and/or (iii) business, occupation, place of work or residence or habitat adversely affected, with or without displacement
Affected
household
members residing under one roof and operating as a single economic unit, who are adversely affected by a project or any of its components.
Compensation means payment in cash or in kind to replace losses of land, housing, income and other assets caused by the Project. All compensation is based on the principle of replacement cost, which is the method of valuing assets to replace the loss at current market rates, plus any transaction costs such as administrative charges, taxes, registration and titling costs
Entitlement means a range of measures comprising compensation, income restoration support, transfer assistance, income substitution, and relocation support which are due to affected people, depending on the nature of their losses, to restore their economic and social base
Land acquisition means the process whereby an individual, household, firm or private institution is compelled by a public agency to alienate all or part of the land it owns or possesses to the ownership and possession of that agency for public purposes in return for compensation equivalent to the replacement costs of affected assets.
Relocation means assistance provided to project affected persons due to the loss of productive assets, incomes, employment or sources of living, to supplement payment of compensation for acquired assets, in order to achieve, at a minimum, full restoration of living standards and quality of life
Resettlement means all measures taken to mitigate any and all adverse impacts of a projection AP property and/or livelihoods, including compensation, relocation (where relevant), and rehabilitation as needed
- 5 -
Resettlement
Plan (RP)
is a time-bound action plan with budget setting out compensation and resettlement strategies, objectives, entitlement, actions, responsibilities, monitoring and evaluation. The RP must be prepared and approved prior to loan appraisal for the Project.
Severely affected
persons
Mean APs who will (i) lose 10% or more of their total productive land and/or assets; (ii) relocate due to insufficient remaining residential land to rebuild; and/or (iii) lose 10% or more of their total income sources due to the Project.
- 6 -
PART I. OVERVIEW
The Socialist Republic of Vietnam received a loan of $ 72,000,000 from the Asian
Development Bank (ADB) and with the Vietnamese Government’s counterpart fund of $8,000,000 to implement the Health Care in the South Central Coast Region Project. The
Project supported eight provinces/cities in the South Central Coast Region, including Da
Nang City, Quang Nam, Quang Ngai, Binh Dinh, Phu Yen, Khanh Hoa, Ninh Thuan,
and Binh Thuan over a six years period from 2009 to 2015. The overall goal of the
Project is to improve the health status of the population in the eight Project
provinces/cities. The Project’s expected outcome is a more comprehensive and well
managed and better used provincial health systems in the eight Project provinces/cities
with a focus on health care for the poor, women and children and ethnic minorities
through 4 components: (A) improving health facilities, (B)strengthening human
resources through improved workforce planning and training capacity and specific
training programs, (C) improving access to health services for the poor, and (D)
strengthening provincial health systems by improving management and monitoring of the
provincial health systems and hospitals.
In Component A, the Project upgraded or constructed a total of 25 facilities, including
11 district hospitals (DHs), 05 regional hospitals, 01 provincial hospital, 01
rehabilitation hospital, 01 traditional medicine hospital, 01 secondary medical school
(SMS), and 05 Preventive Medicine Centers (PMCs). The upgrading/construction in
some sites involved land acquisition and resettlement. A resettlement plan (RP) was
prepared to address the land acquisition and resettlement impacts from the subprojects.
RP implementation is required to be monitored internally with the objective of
providing feedback to management on implementation and identifying problems and
successes as early as
possible to facilitate timely adjustment of implementation arrangements. Internal
monitoring and supervision are expected to determine if:
a. Compensation and other entitlements are computed at rates and procedures as
provided in the approved RP, with no discrimination according to gender,
membership in an ethnic group or any other factor;
b. Affected households are paid their compensation and other entitlements as per
approved updated RP, ensuring that all entitlements are delivered as planned and
agreed, including compensation in cash or in kind, allowances, replacement land,
resettlement sites developed and people moved onto them;
c. income restoration programs designed and delivered including modifications in the
programs and provision of additional cash and in-kind assistance to the participating
affected households as and when necessary; and
- 7 -
d. Public information, public consultation and grievance redress procedures are
followed as described in the approved updated RP.
Independent monitoring of resettlement activities was conducted in November 2010. This was followed-up by safeguards review mission by the ADB VRM in April-June 2011 and in April 2012 during the mid-term review. All land acquisition and resettlement activities were completed in 2012.
ADB policy on involuntary resettlement requires that upon completion of the project, the
project should(i) provide a concise history of the involuntary resettlement aspects of the
project and/or program to completion, (ii) conduct an evaluation of the implementation
of the resettlement plan and or resettlement framework and involuntary resettlement loan
covenants,(iii) assess the executing agencies performance; and (vi) summarize the
monitoring and evaluation reports. This report aims to support in meeting this
requirement. The report summarizes the land acquisition and resettlement impacts from
the project, the activities undertaken to address such impacts, and the result of the
resettlement plan implementation on the affected people.
PART II. ASSESSMENT METHODOLOGY
1. Assessment methodology
Reviewed the socio-economic situation of the selected locality, the policies,
provisions and legal documents provided by the State and the guidelines on
resettlement activities of the ADB.
Conducted in-depth interviews with representatives from 15 households affected by
the land acquisition and resettlement activities in the project area to collect the
detailed information related to their attitudes and reactions toward the implementation
process of the related organization, as well as examining qualitatively the impacts of
land acquisition and resettlement activities on the affected people’s lives.
2. Assessment timeline
The assessment was conducted by eight PPMUs in October 2014. In early November
2014, eight PPMUs submitted the report to PMU for synthesizing.
3. Assessment sites
The assessment was undertaken in eight provinces/cities covered by the Health Care in
the South Central Coast Region Project, including Da Nang City, Binh Dinh, Binh
Thuan, Khanh Hoa, Ninh Thuan, Phu Yen, Quang Nam, and Quang Ngai.
- 8 -
4. Study objects
Representatives from all related provincial units at eight project provinces/cities, who
were able to clearly give answers to the survey questions on the situation of land
acquisition and resettlement in the area due to the construction of health facilities
belonged to the Health Care in the South Central Coastal Region Project.
5. Data processing
All collected data were cleaned and analyzed according to the set objectives.
PART III. STATUS OF IMPLEMENTATION
1. Summary Scope of Land Acquisition and Resettlement Impacts
Out of 25 sub-projects of eight project provinces, only nine sub-projects in six
provinces involved land acquisition and resettlement activity. The other sub-projects
were constructed within the existing compounds of hospitals/preventive medicine
centers or sites that are already under the possession of the hospitals.
For the nine subprojects with land acquisition impacts, a total of 120,978.2 m2 of land
were acquired, of which 85% was productive land, 14% was public land and only 1%
was residential land. There were 84 affected objectives, including 80 households and 4
public organizations(Commune/Ward People’s committees, District Youth Union,
government-owned company, etc). Of the 80 households that were affected by the
Project, five households lost more than 10% of their productive land and six households
needed to be relocated1. A total of VND 10,322,041,151covered by provincial’s budget was used as compensation and allowances for the affected people. This amount included
the cost of compensation for land, provision or purchase of other land for farmers (in
cases of land for land compensation were applied), compensation for loss of houses,
structures, crops and business, relocation, and living standards rehabilitation measures.
1 The Project was initially categorized as ‘A’ for involuntary resettlement, but was recategorized to ‘B’
because of the reduced impacts from the subprojects.
- 9 -
SCOPE OF LAND ACQUISITION AND RESETTLEMENT IMPACTS
No. Province/ Health facilities
Acquired land (m2) Total of
affected HHs /
organizations
HHs to
be
relocated
APs losing
>=10% of
productive
assets
Other
impacts Residential
land
Agricultural
land Tree land
Public
land
I DA NANG
1 Hoa Vang District Hospital 0 0 0 0 0 0 0 0
2 Da Nang city Rehabilitation Hospital 0 0 0 0 0 0 0 0
II QUANG NAM
5 Dong Giang District Hospital 0 0 0 0 0 0 0 0
3 Bac Tra My District Hospital 0 0 0 0 0 0 0 0
4 Quang Nam Regional Hospital 0 0 0 0 0 0 0 0
6 Dien Ban Preventive Medicine Centre
0 0 0 0 0 0 0 0
III QUANG NGAI
8 Son Tay District Hospital 1,061.5 7,056.6 0 0 19 3 5 0
9 Tay Tra District Hospital 300 21,052.8 0 0 27 1 0 0
10 Tra Bong District Hospital 0 0 0 0 0 0 0 0
7 Ba To District Hospital 0 0 0 0 0 0 0 0
11 Mo Duc Preventive Medicine Centre 0 0 0 0 0 0 0 0
IV BINH DINH
12 OPD-Binh Dinh Provincial Hospital 0 0 0 0 0 0 0 0
13 Traditional Medicine Hospital 0 18,212.4 0.0 1,042.7 12 0 0
14 Phu My District Hospital 0 0 0 0 0 0 0 0
- 10 -
SCOPE OF LAND ACQUISITION AND RESETTLEMENT IMPACTS
No. Province/ Health facilities
Acquired land (m2) Total of
affected HHs /
organizations
HHs to
be
relocated
APs losing
>=10% of
productive
assets
Other
impacts Residential
land
Agricultural
land Tree land
Public
land
V PHU YEN
16 Tay Hoa District Hospital 0 0 0 0 0 0 0 0
17 Song Cau District Hospital 0 0 0 0 0 0 0 0
15 Tuy An Regional Hospital 0 0 0 0 0 0 0 0
18 Song Cau Preventive Medicine Centre
0 0 2,427.6 272.4 5 0 0 0
VI KHANH HOA
19 Cam Ranh Regional Hospital 0 0 0 0 0 0 0 0
20 Van Ninh District Hospital 0 22,908.2 0 0 1 0 0 0
21 Ninh Hoa Prevent Medicine Centre 0 0 0 0 0 0 0 0
VII NINH THUAN
22 Secondary Medical School 0 23,918 7,613 3,816 17 0 0 0
VIII BINH THUAN
23 North Regional Hospital (Bac Binh) 240 0 0 11,057 3 2 0 0
24 South Regional Hospital (Duc Linh) 0 0 0 0 0 0 0 0
25 Phan Thiet Preventive Medicine Centre
0 0 0 0 0 0 0 0
Total 1,601.5 93,148.0 10,040.6 16,188.1 84 6 5 0
- 11 -
2. Details on the Status of Land Acquisition and Resettlement in Project
Provinces/Cities
2.1. Da Nang City
Da Nang City had constructed a new general DH and two new departments onadult
and children rehabilitation and treatment. No resettlement or land acquisition
wasrequired for the construction works.
- The Hoa Vang DHis located at Hoa Nhon commune, Hoa Vang District, Da Nang
city. The land for constructing the Hoa Vang DH was handed over by the City
Government to Da Nang City Health Department2009 by virtue of Decision No.
4947/QĐ-UBND dated 01 July 2009 by the Da Nang City People’s Committee.
- The Da Nang City Rehabilitation Hospital is located at My An Ward, Ngu Hanh Son
District. The Project built two more departments, for adult and children rehabilitation
treatment for poor patients. The construction of the two new departments was on
vacant land owned by the hospital. No resettlement or land acquisition was required
for this construction work.
2.2. Quang Nam Province
Quang Nam province upgrade done regional hospital and two DHs, and built a new
PMC. There is no land acquisition or resettlement impact for all project facilities in
the province as the civil works were within the hospitals/center’s campuses.
- Quang Nam Regional Hospital is located in Vinh Dien town, Dien Ban District. The
Quang Nam Regional Hospital constructed a new building with 4 floors for the OPD
– Emergency, Technical Professional Block, and E.N.T to replace the existing
structure. The construction of the new building did not require any land acquisition
because the land and structure were already owned by the hospital and there were no
resettlement effects.
- Bac Tra My DH is located in Tra My town, Bac Tra My district. The Bac Tra My DH
replaced all of the medical examination and treatment departments. The construction
works did not require any land acquisition or caused any resettlement effects.
- Dong Giang DH is located in Prao town, Dong Giang district. The Dong Giang DH
replaced all of the medical examination and treatment departments. The new
construction works did not require any land acquisition or caused any resettlement
effects.
- Dien Ban District Department of Preventive Medicine is located at the Vinh Dien
Town, Dien Ban District, Quang Nam Province. The land was handed over by the
Quang Nam Provincial People’s Committee according to Official Dispatch No.
- 12 -
653/UBND-VP Dated 26/6/2009 and there are no land acquisition nor resettlement
requirements for construction works.
2.3. Quang Ngai Province
Quang Ngai province upgraded four DHs and built one PMC. There was no need for
land acquisition and resettlement for Tra Bong DH, Ba To DH, and Mo Duc PMC. Son
Tay DH and Tay Tra DH required land acquisition.
- Son Tay DH is located in Son Tay District. The hospital needed 8,118.1 m2
additional land for the upgrading. There were 19 affected households, of which three
households needed to be relocated and 5 households lost 100% their agricultural
(rice field). Three relocated HHs had their own land in other places, therefore, they
only asked for cash compensation and and built new houses by themselves. The Son
Tay District People’s Committee did not provide land for them. Other affected HHs,
including 5 HHs lost all their productive land received cash compensation and
support for changing occupation and job creation. The compensation and support to
affected households were approved by Decision No. 1549/ QĐ-UBND of the Quang
Ngai People’s Committee on 20 October 2010. All land acquisition activities already
completed according to the approved plan and there was no complaints received.
- The Tra Bong DH was constructed on an area of 10,274m2“clean” land. There was no
requirement for land acquisition or resettlement effects.
- The Ba To DH was constructed on an area of 19,458 m2of available/cleared land.
There was no requirement for land acquisition or resettlement effects.
- The Tay Tra DH is located in Tra Phong Town, Tay Tra District. The hospital needed
21,352.8 m2of additional land. There were 27 affected households, of which 01 HH
was resettled while the other have only their productive assets, crops and trees
affected. The District Resettlement Board paid compensation all 27 affected
households and allocated a land plot for 1 relocating HH about 100 meters from
his original residence. All affected HHs received and were satisfied with the
compensation and allowance. All land acquisition activities were completed in
February 2012.
- Mo Duc Preventive Medicine Center was constructed on 2,200 m2land at Duc Thach
Commune, Mo Duc District, Quang Ngai. The Quang Ngai Province People’s Committee issued Decision No. 47/QĐ- UBND on 15 March 2010 allocating the
required land for the center. Thus, the construction works did not require any
additional land acquisition or caused any resettlement effects.
- 13 -
2.4. Binh Dinh Province
Binh Dinh province upgraded 3 hospitals, i.e., one provincial hospital, one traditional
medicine hospital and one DH. There was no land acquisition and resettlement
required for Binh Dinh Provincial Hospital and Phu My DH as the civil works are
within the hospitals’ compounds. For the traditional medicine hospital, the land was
acquired by the Provincial Center for Land Resource Development.
- Binh Dinh Provincial Hospital has a total land area of 58,000 m2. The hospital
constructed a new building with 6 floors for the OPD under Health care in the South
Central Coast Region Project. The construction of the new building did not require
any land acquisition since the land was owned by the hospital and there was no
resettlement effects.
- Phu My DH has a total land area of 27,360 m2 and Project funded three new
buildings for operating theaters, pharmacy and intensive care unit. The construction
of these buildings is on existing land of the hospital and therefore, there was no
requirement on land acquisition and resettlement.
- The Traditional Medicine Hospital is located on a new site in Nhon Phu Ward, Quy
Nhon city. Total area of land acquired for the hospital is 19,455 m2, of which
residential land is 200 m2 belonging to two households and 19,255 m2 is agricultural
land. There are 13 affected HHs and 1 Commune People’s Committee (of which 2
HHs lose their houses, 10 HHs lose their agricultural land and one household lose
8.6m2 garden and 657 m2 of agricultural land). Compensation was made for 10
households for the affected agricultural land and these households received the
compensation without complaints because the affected agricultural land areas are
minor (each household losing less than 100 m2). The remaining 03 households
refused compensation due disagreement with the compensation price for land and
tree. Two of these households have affected residential land (with houses) and garden
land. They refused compensation because they claim that(i) the compensation unit
rates for residential land/garden land and assets upon lands (houses and trees) were
much lower compared to the market rates, and (ii) the replacement residential land in
the resettlement site is smaller than the affected residential land. In 2011, these
complaints were resolved. The household who lost agricultural land was compensated
by “land for land” as their request and he was satisfied with this compensation. For
the two other households, PPMU adjusted the alignment of the fence surrounding the
hospital to avoid impacting on the land of these households. All of the land
acquisition and resettlement activities were implemented by the Provincial Center for
Land Resource Development and completed in July 2011 with total 1,013,756,000
VND of compensation.
- 14 -
2.5. Phu Yen Province
Phu Yen subprojects coveredthe upgrading and expansion of Tuy An Regional
Hospital, Tay Hoa DH and Song Cau DH and construction of the Song Cau PMC.
Only Song Cau Preventive Medicine Center has land acquisition impacts. Civil works
in the three other subprojects are within land that is under the possession of the
hospitals. Civil works in these three hospitals that involved land acquisition were
funded through the Government Bonds which are not part to the project.
- Tuy An Regional Hospital was built on its old location, with minor expansion. Civil
works under the Project were done within the existing hospital compound. The minor
expansion of the hospital was funded through the Government Bonds which are not
part of the project.
- Civil works under the Project for the Song Cau DH were limited to the existing
20,519.5 m2 of the hospital. Minor expansion of the hospital funded by the
Government Bonds involved the acquisition of 5,694 m2. These works are not related
to the project.
- The Tay Hoa DH is located at Phu Thu Town. Civil works under the Project were
done within the existing hospital compound. The minor expansion of the hospital was
funded through the Government Bonds which are not part of the project.
- Song Cau Preventive Medicine Center at first were proposed to locate in Le Uyen
Village and would affect to 7 HHs, of which 3 HHs would be resettled. However, this
area were allocated to another project by Phu Yen PPC. Therefore, Phu Yen DOH,
PPMU and Song Cau Commune People’s Committee decided to move the sub-
project to a new location in Trung Trinh Village with 2,700m2 of acquired land. There
were 04 affected households which lost minor productive land and one small land of
Xuan Phu Ward People’s Committee. None of the affected households had to
relocate. The chairman of Song Cau District People’s Committee issued Decision No. 1007/QĐ-UBND approving the compensation plan for construction of Song Cau
Preventive Medicine Center and the land acquisition activities already completed in
2012 with total compensation of VND22,600,000.
2.6. Khanh Hoa Province
The Khanh Hoa Health Care Subproject includes upgrading of one DH district, one
regional hospital, and 01 PMC. There were no land acquisition and resettlement
requirements for Cam Ranh Hospital and Ninh Hoa PMC as the civil works were
within the hospital and department’s campuses, while the Van Ninh Hospital required
compensation for the Van Luong Commune People’s Committee.
- Cam Ranh Regional Hospital has a total area of 19,800 m2 land and it is located at 97
Nguyen Thai Hoc Street, Cam Ranh Town. The replacement of old buildings is
- 15 -
within the existing hospital premises and did not require any land acquisition or
resettlement effects.
- Ninh Hoa PMC is located at 8 Village, Ninh Hoa District, Khanh Hoa City. It is built
in the former site of the PMC and did not require any land acquisition or resettlement
effects.
- Van Ninh DH: In 2009, Khanh Hoa PPMU the land handed over to PPMU in 2009
for construction of Van Ninh DH was “clean”. Before that, an area of
22,902.2m2aquaculture land of Van Luong Commune People’s Committee was
acquired. Compensation was paid to the Communal People’s Committee and it has
been used (VND 453,582,000) for the commune’s infrastructure constructions. The leaders of Van Luong Communal People’s Committee and the local people are satisfied with the compensation in-terms of compensation unit rates and the
compensation manner. The compensation implementation is compliant with the
provision on “compensation for public assets” of the approved Project Resettlement Framework. During constructions of the Government funded components of Van
Ninh District Hospital, there were two households who had land temporarily affected
and the impacts have been compensated properly by the construction contractors; and
the affected households are satisfied with the compensation. In short, the land
acquisition and compensation implementation by Van Ninh District Hospital
Subproject conforms with the provisions of the approved Resettlement Plan and
Project Resettlement Framework.
2.7. Ninh Thuan Province
The Ninh Thuan Subproject supports the construction of one new DH in Thuan Bac
District, and one new Secondary Medical School in Phan Rang-Thap Cham city. All
land acquisition and compensation activities were completed according to the
approved plan.
- The Secondary Medical School is located at Van Hai Ward and a part of Khanh Hai
town, Phan Rang-Thap Cham city. There were 17 affected households. A total of
VND 5,463,653,899 was spent on compensation for acquiring 24,640 m2 agricultural
land, construction works, crops and trees as well as support for settlement, changing
occupation and job creation as clearly defined in Decision No 3769/ QĐ-UBND of
Ninh Thuan Provincial People’s Committee on 21 September 2009. There was one
complaint about low allowance. The Board provided additional allowance for that AP
and he was satisfied with the additional allowance. The land acquisition activities for
the sub-projectwere successfully completed in 2009.
- 16 -
2.8. Binh Thuan Province
The Binh Thuan Health Care subproject supports civil works in the upgrading of
Northern Regional Hospital, Southern Region Hospital and Phan Thiet PMC. No land
acquisition and resettlement requirements for the Southern Region Hospital and the
Phan Thiet PMC as the civil works are within the premises’ campuses. - The Northern Regional Hospital is located at Cho Lau Town, Bac Binh District in the
campus of the former Bac Binh Health. It required an additional 11,347 m2 for the
proposed expansion. This expansion severely affected two households who had
residential land and houses in the area (total of 240m2). At first, these households
disagreed with the resettlement site because of these following reasons: (i) the offered
replacement residential land ground is lower than the surrounding houses which
makes it expensive to fill; (ii) it is expensive for the households to build a fence
around the residential land; (iii) it will cost significant amount for the households to
connect electricity and water; (iv) the offered replacement residential land has no
location advantage over the affected residential land (the affected residential land of
two households is in front of the large alley); and (v) the households have not yet
been consulted on the compensation, assistance and resettlement policy, so they do-
not know what allowances they will be entitled to for relocation. After receiving the
grievance, the Board provided other places near the AHs’ previous residence (about
100m). There was also one district-owned TV station affected due to loss of land and
structures. The land was acquired and handed over in 2011. All the households and
the TV station were compensated and were satisfied with the compensation levels
that they received.
- The Southern Regional Hospital located at Duc Linh Commune, Duc Linh District
currently owns a total land area of 28,216 m2. The construction work did not require
additional land and there were no resettlement effects.
- Phan Thiet City Department of Preventive Medicine is located at the Xuan An Ward,
Phan Thiet City, with an area of 1000 m2. There was no need for land acquisition
and resettlement.
3. Implementation procedure
3.1. Organizational structure model
In order to carry out the land acquisition and resettlement activities, a managing
organization structure has been set up in different levels. This model of organizational
structure at project provinces/cities composed of the steering and implementation levels.
The steering level included the steering committees of provinces, districts and communes
with the role of speeding up the implementation of actions, carried out every regulations
relating to land acquisition and resettlement activities, and directly provided guidance to
- 17 -
settlement of any complaints that arose during the implementation of land acquisition
and resettlement activities. The implementation level included the Board for
compensation and land clearance (the Board) and representatives of the supporters such
as: the Health Department, the Resources and Environment Department, the Finance
Department, and other provincial organizations with the responsibilities of
implementing, settling the issues relating to compensation and resettlement activities.
3.2. Procedure to implement compensation and site clearance
The Board was responsible for reporting plans to get appraisal from the Department of
Natural Resources and Environment, Department of Planning. After getting their
approvals, related agencies were informed and consulted, such as Department of Finance,
Planning, Natural Resources and Environment, Health Service all to consider plans
according to land law, Provincial decisions on land price, and other related regulations.
Having results of appraisal, the Board made decision on approving plans of
compensation and resettlement. Province made decision on land recovery and approved
the level of compensation after confirmation from the affected households.. Province
assigned the Board to implement compensation and site clearance. The Department of
Health played as investor, other involved departments acted as supervisors.
The Board conducted detailed measurement surveys (DMS) and verified if relocation
will be required. The Board together with local authorities organized meetings with
people to communicate the purposes of land recovery for constructing
hospitals/departments of preventive medicines. The Board had responsibilities for
communicating the social nature, usefulness of hospital construction to each household.
After this, the Board and representatives from involved and affected households clarified
ground, arable and other works in planned area. Communicating and measuring land,
IMPLEMENTING
LEVEL
Province People’s Committee
Com. People’s Committee
The Project
Management
Board
Land
clearance and
compensation
Local related
Departments,
Organizations
STEERING LEVEL District People’s Committee
- 18 -
estimating crop and tree loss etc. Results of measuring land, estimating losses in site had
to be confirmed by each household. Once completing the statistics of measuring, the
Board made plans of compensation, emigration and estimated the compensation levels
according to the current government regulations, and then submitted to Province for
appraisal. After getting response of appraisal, the Board in corporation with local
authorities, representatives of affected households communicated and published levels of
compensation approved by Province. After completing file of compensation, Health
Service Department in coordination with the Board, local authorities gave compensation
for all affected households in each sub-project area.
3.3. Consultation and Disclosure
The consultation and disclosure activities were well implemented at the project areas by
the Board for compensation and land clearance. At the early stages of project
preparation, local authorities and leaders of different administrative levels in each of the
Project towns/districts/communes were informed about the project proposal, its
objectives, and proposed activities. They were consulted on development needs and land
acquisition and/or resettlement issues, their perception toward project objectives,
technical designs, and their tasks and roles in project planning and implementation.
Affected persons have also been informed about the proposed Project on an individual
household basis and using different communication channels including direct and
indirect forms, such as: community meetings, households visits, official letters sent to
each affected households, and officially notices displayed at the commune People’s Committees’ billboards.
The affected households were consulted about how the Project was going to directly
affect them. They have been involved in developing the proposed resettlement and
compensation packages and expressed their preferences for the type of compensation.
Disclosure of the RP to the affected people was done prior to appraisal, using locally
appropriate information booklets. All affected households were well informed of all
related information on the land acquisition, resettlement and compensation activities due
to the sub-projects.
3.4. Entitlements
A total of VND 10,322,041,151 covered by provincial’s budget was used as the compensation and allowances for the affected people. This amount included the cash cost
of land acquisition, provision or purchase of other land for farmers (in cases of land for
land compensation were applied), compensation for loss of houses, structures, crops and
business, relocation, and living standards rehabilitation measures.
- 19 -
All compensations were based on the principle of replacement cost. Compensation and
provision of assistance were provided and income restoration programs were put in place
prior to relocation of affected households from their houses/or land acquisition activities.
The APs received not only compensations for their own property like land, crops and
trees, work structure, but also various types of allowances like transition subsistence
allowance, transportation allowance, training allowance, business transition allowance,
incentive allowance, social assistance allowance. For vulnerable APs, the PPCs provided
support for changing occupation or job creation by sending affected households for job
training/vocational training for technical assistance or providing cash assistance at the
request of the affected households. Practically, the APs agreed to receive money instead
of joining job training/vocational training. The APs received monetary support for 6
months income restoration and support for job training to stabilize their living standard.
- 20 -
COMPENSATION AND MONETARY SUPPORT FOR LAND ACQUISITION ACTIVITY
Unit: VND
No. Provinces / Health facilities
Compensation
for residential
land
Compensation
for productive
land
Compensation
for trees,
crops,
structures
Monetary
supports(for moving,
living stabilization,
changing occupation
and job creation…)
Total of
compensation
and monetary
support
I DA NANG
1 Hoa Vang District Hospital 0 0 0 0 0
2 Da Nang city Rehabilitation Hospital 0 0 0 0 0
II QUANG NAM
5 Dong Giang District Hospital 0 0 0 0 0
3 Bac Tra My District Hospital 0 0 0 0 0
4 Quang Nam Regional Hospital 0 0 0 0 0
6 Dien Ban Preventive Medicine Centre 0 0 0 0 0
III QUANG NGAI
8 Son Tay District Hospital 206,220,000 690,208,200 585,340,840 67,656,000 1,549,425,040
9 Tay Tra District Hospital 0 433,003,200 56,297,000 1,005,188,000 1,494,488,200
10 Tra Bong District Hospital 0 0 0 0 0
7 Ba To District Hospital 0 0 0 0 0
11 Mo Duc Preventive Medicine Centre 0 0 0 0 0
IV BINH DINH
12 OPD-Binh Dinh Provincial Hospital 0 0 0 0 0
13 Traditional Medicine Hospital 0 773,900,000 216,647,000 23,209,000 1,013,756,000
14 Phu My District Hospital 0 0 0 0 0
- 21 -
COMPENSATION AND MONETARY SUPPORT FOR LAND ACQUISITION ACTIVITY
Unit: VND
No. Provinces / Health facilities
Compensation
for residential
land
Compensation
for productive
land
Compensation
for trees,
crops,
structures
Monetary
supports(for moving,
living stabilization,
changing occupation
and job creation…)
Total of
compensation
and monetary
support
V PHU YEN
16 Tay Hoa District Hospital 0 0 0 0 0
17 Song Cau District Hospital 0 0 0 0 0
15 Tuy An Regional Hospital 0 0 0 0 0
18 Song Cau Preventive Medicine Centre 0 0 22,600,000 0 22,600,000
VI KHANH HOA
19 Cam Ranh Regional Hospital 0 0 0 0 0
20 Van Ninh District Hospital 0 453,582,000 0 0 453,582,000
21 Ninh Hoa Prevent Medicine Centre 0 0 0 0 0
VII NINH THUAN
22 Secondary Medical School 0 5,086,118,544 178,666,450 69,503,280 5,334,288,274
VIII BINH THUAN
23 North Regional Hospital (Bac Binh) 192,000,000 0 207,901,637 54,000,000 453,901,637
24 South Regional Hospital (Duc Linh) 0 0 0 0 0
25 Phan Thiet Preventive Medicine Centre
0 0 0 0 0
TOTAL 10,322,041,151
- 22 -
3.5. Concerns/complaints resolution
The responsibility and coordination between divisions in the land acquisition and
compensation management bodies were clearly defined. As mentioned above, the
managing organization structure was set up in functions or activated in accordance with
recent regulations of Vietnam. The Board for compensation and land clearance (the
Board) included representatives of commune president, representatives of functional
divisions like finance, natural resources and environment, construction and
representative of the hospital that was to be constructed. In which, the commune
president played a crucial role in the compensation, land acquisition and resettlement
process to ensure directly affected and in-directly affected people understood the benefits
of the sub-projects and supported the activities. Communal authorities were closest body
to the local residents and they were efficiently dealing with concerns/complaints that
may arise during the process of land acquisition and/or resettlement.
There were 6 cases of complaints that were received during the process of compensation,
land acquisition and resettlement.
For the subproject Binh Dinh Traditional Medicine Hospital, there were 3 HHs that
disagreed with the compensation price for land and tree. One household losing
agricultural land did not agree to receive the compensation because the household
believed that the compensation unit rates for the affected land and trees were much lower
compared to the market rates. He opted for “land for land” compensation. Two other households who had residential land (with houses) and garden land effected, refused the
compensation because the replacement residential land in the resettlement site is smaller
than the affected residential land. In 2011, the Board resolved these grievances. The
household who lost agricultural land was satisfied with the replacement land that was
provided to him. For two other households, PPMU adjusted the alignment of the fence
surrounding the hospital to avoid impacting on the land of these households.
The Ninh Thuan SMS also dealt with one complaint about low allowance. After
receiving the grievance, the Board reviewed and provided additional allowance for that
AP and he was satisfied with the additional allowance.
In Binh Thuan North Regional Hospital, there were 2 HHs who needed to relocated and
at first, these households disagreed with the resettlement site because living conditions in
the site was not similar to the original one. The Board resolved by providing other places
for these households with their concurrence.
PART IV. RESULTS OF LAND ACQUISITION ACTIVITIES
The land acquisition and resettlement compensation implementation processes at project
provinces/cities were published, transparent and conform with ADB’s social safeguards
- 23 -
requirements and current regulations of Viet Nam. The impacts of the land acquisition
and resettlement activities on the socio-economic recovery of the affected
people/households in each sub-project areas were quite minor.
Although there were few concerns/complaints arose during the land acquisition and
resettlement process, the PPMUs and related stakeholders of the Resettlement Boards
have settled all these complaints in accordance with recent regulations of Vietnam and in
harmony with the wish of affected people.
Out of nine sub-projects having land acquisition impacts, four sub-projects have
outstanding issue because of resettlement requirement and large number of affected
households.
Binh Thuan North Regional Hospital: The relocated households have moved to
locations near their previous residence and have the same conditions prior to their
relocation. These households are families under preferential treatment policy, thus they
receive monthly allowance from Government. Besides, they have a small counter to sell
beverage near the hospital. Therefore, the resettlement did not affect seriously their
livelihood and standard of living.
Picture 1. Two new houses which Binh Thuan PPC built for two Vietnamese heroic
mother households, who had to resettle due to construction of North Regional Hospital.
Binh Dinh Traditional Medicine Hospital: Twelve households were affected by this
sub-project. They all lost just a small portion of land at the back of their houses while
- 24 -
their main income sources from the stores in the front were not affected. These
households were satisfied with the compensation they received for their lost land.
Picture 2. The households who lost a part of their backyards due to construction of
Binh Dinh Traditional Medicine Hospital.
Ninh Thuan Secondary Medical School: There were seventeen affected households
due to the construction of Ninh Thuan Secondary Medical School. They all lost part of
their agriculture land and tree land. They received the compensation for the lost land and
- 25 -
have continued cultivate on the remaining land to maintain their livelihoods. Some
households also opened stores to improve their income.
Picture 3. The remaining rice field and garden of the affected households in Ninh Thuan
Picture 4. The grocery store which Mr. Nguyen Van Tho, one of affected households in
Ninh Thuan SMS built on the remaining land.
Tay Tra District Hospital: Out of 27 households affected by the project (mostly lost
small agriculture land), one household of Mr. Ho Minh Duc needed resettlement. This
household received compensation for its lost assets and built a house in another area with
- 26 -
the same conditions as the old one. The main income of this household is from the salary
of the husband who is working for a Medicine Center, therefore the land acquisition did
not affect to their livelihoods.
Picture 5. Mr. Ho Minh Duc and his new house
Son Tay District Hospital: There were 8 households that were seriously affected by this
subproject. The others only lost small assets. Three households who lost their residential
land with houses moved to new location and built temporary houses after receiving
compensation. They and the other five vulnerable AP(s) also received monetary support
to stabilize their livelihood. hey could cultivate on the remaining land to restore their
main income sources from agricultural, gardening and breeding activities. Besides, some
of them have salaries from their work or allowances from the Government (retirement
pension, allowance for contribution to revolution).Thus, their livelihoods were not
seriously affected by the land acquisition impacts.
Generally, local residents were very supportive to the Project as they saw the real
benefits for the communities when the new hospitals are in operation. Before project, the
hospitals in project area were very overloaded and degraded with lack of modern
equipment that did not meet the demands for health care and treatment. But now, the
construction of new health facilities had already completed, and all health facilities had
operated providing health care services to local residents. The local residents, including
affected people, can now easily access to more qualified health care services with more
spacious and modern hospitals/health facilities. Particularly, the opening of Ninh Thuan
Secondary Medical School facilitated local residents and people in surrounding areas in
saving time and cost for studying since they do not have to go to universities/schools in
Ho Chi Minh City.
- 27 -
CONCLUSIONS AND RECOMMENDATIONS
1. It can be concluded that the eight provinces/cities in the South Central Coastal
Region that were covered by the Project did not face with major challenges in land
acquisition and resettlement activities unlike many other projects.
2. Out of 25 sub-projects in eight provinces/cities, seven sub-projects in six
provinces/cities required land acquisition/resettlement activities. All sites already
completed land acquisition and/or resettlements activities in early 2012.
3. Generally, the land acquisition and resettlement objectives have been met. The
impacts of the land acquisition and resettlement activities on the socio-economic
recovery of the affected people/households were quite minor. The activities were in
compliance with ADB’s social safeguards requirements and recent regulations of
the Vietnamese Government.
4. Entitlements and compensation standards were clearly specified and adequate.
5. The compensation and site clearance implementation processes at project
provinces/cities were conformity with current regulations, publicity and
transparency. It was also clear in the process that local people (both directly
affected and in-directly affected households) directly took part in compensation and
site clearance.
6. The communication activities through different channels used at the commune-level
and commune authorities played crucial role in the compensation, land acquisition
and resettlement process to ensure directly affected and in-directly affected people
understood the benefits of the sub-projects and support the activities. Commune
authorities were the closest body to the local residents and they were efficiently
dealing with concerns/complaints that arose during the process of land acquisition
and/or resettlement.
7. The responsibility and coordination between divisions in the land acquisition and
compensation management bodies were clearly defined. The managing organization
structure was established fully and in accordance with recent regulations of
Vietnam. The managing organization structure was set up in functions or activated,
with responsibilities and coordinative relations clearly defined. The effective
coordination between Project Management Unit, the Steering Committee and the
Board of Land Clearance and Compensation was showed in every activity of land
acquisition and resettlement.
8. Generally, communities in the sub-project areas highly supported the Project as
they saw the real benefits for the communities. The current hospitals were very
overloaded and degraded with lack of modern equipment that did not meet the
- 28 -
demands for health care and treatment of the local people. Both local authorities
and local residents were satisfied and supported the Project.
9. Initially, affected households had limited knowledge on the Project and levels of
compensations they would receive according to current legislations and agreed
policy framework for the project. Thus communication activities had to be
implemented through different channels, such as community meetings, household
visits, official letters sent to each affected household, and official noticeswere
displayed at the Commune People’s Committee offices etc. to ensure local residents fully understand about the benefits of the sub-projects as well the impacts on their
families.
- 29 -
ANNEX 1
IN-DEPTH INTERVIEW GUIDELINE
REPRESENTATIVE OF AFFECTED HOUSEHOLDS
Province: …………………………
Objectives:
To qualitatively assess the impacts of the land acquisition and resettlement activities for the Health Care in the SCCR Project on the livelihoods of affected households
Required jobs before implementing deep-interviews
1. Interviewer introduces some information about himself/herself: name, job, interests etc.
2. Explain objectives and nature of the interview, reasons that interviewee is selected for interview, and importance of his/her participation
3. Inform interviewee about confidentiality of information and identification in announcing results.
4. Tell interviewee that there are no right or wrong answers and encourage interviewee to share his/her opinions and experiences.
5. Tell interviewee that he/she can ask again if not clear about questions, can refuse to answer, or can expose any comment or opinion if he/she think it is not appropriate.
6. Ask interviewee’s permission for recording the interview and explain reasons.
ASSESSMENT AND COMMENTS ON THE LAND ACQUISITION AND
RESETTLEMENT ACTIVITIES OF THE SUB-PROJECTS IN THE
PROVINCE/CITY AND IMPACTS (IF ANY) ON THE LIVELIHOOD OF
AFFECTED HOUSEHOLDS 1. Please tell me if your family is affected by the land acquisition and resettlement
activities of the Health Care in the SCCR Project?
2. Please describe the business activities of your family; what activities bring largest
amount of income to your family? Does the business activities of your family
change? If yes, how does it change?
Code: …………….. File name Name of interviewee: ……………………………………………. Name of head of household: ……………………………………………. House address ………………………………………………………………….. Date: ………/……./……….. Time started: ……… Time ended the interview: ………
Interviewer: ………………………………
- 30 -
3. What is your family monthly income before and after land acquisition? Any
changes? In what ways?
4. Your family living conditions: have your family’s accessibility to public services (such as clean water, electricity, transportation, health care services, schools etc.)
changed after land acquisition?
5. What are the influences on security, environment, social status that your family
have to face?
6. In general, could you assess the level of impacts that the land acquisition and resettlement activities of the project on your family’s life?
7. Do you have any comments, recommendations to PPMU and local authorities in order to effectively implement the land acquisition and resettlement activities for the Health Care in the SCCR Project in the province/city according to plan?
THANK YOU FOR YOUR TIME AND OPINIONS!
- 31 -
ANNEX 2
LIST OF INTERVIEWED HOUSEHOLDS
No. Province Health Facilities Name of interviewed
household
1 Quang Ngai
Tay Tra District Hospital Mr. Hồ Minh Đức,
Mrs. Hồ Thị Trang
Son Tay District Hospital
Mr. Đinh Văn Sáu, Mrs. Đinh Thị Trà,
Mr. Đinh Văn Đuối, Mr. Đinh Văn Vênh,
Mr. Nguyễn Hồng Hải, Mr. Hồ Minh Dụng,
Mr. Lê Văn Hùng,
Mr. Đinh Hồng Nhía,
Mr. Nguyễn Quốc Dũng,
Mrs. Đinh Thị Đèo,
2 Ninh Thuan Secondary Medical School Mr. Nguyễn Văn Thọ
3 Binh Thuan North Regional Hospital Mrs. Lê Thị Cang
Mrs. Võ Thị Thanh
- 32 -
ANNEX 3
LIST OF PPMU STAFF INVOLVED IN THE ASSESSMENT
No. Province Name of staff Designation
1 Da Nang Đặng Văn Tường Engineer
2 Quang Nam Phan Anh Thống Civil work consultant
3 Quang Ngai Lê Thành Phương Civil work consultant
4 Binh Dinh Phạm Minh Hùng Civil work consultant
5 Phu Yen Nguyễn Công Thành Civil work staff
6 Khanh Hoa Nguyễn Bình Quốc Civil work consultant
7 Ninh Thuan Dương Thanh Tân Civil work consultant
8 Binh Thuan Huỳnh Ngọc Tú Civil work consultant