TDWG - Sep 13, 2001- L2Plan - L.Ristori 1 checkmarked on Dec 7, 2001
L2 Goals
• Near term (by Oct 8)
– Demonstrate cutting on jets and SVT tracks
• Intermediate term (Nov 17 to end of 2001)
– Come back from shutdown cutting on jets and SVT tracks
– Commission SVT trigger operation
– Commission electron trigger
• Far term (early 2002)
– Establish stable L2 operation
– Commission remaining interface boards (RECES, ISOLIST, MUON) to cut on:
• Electrons• Photons• Muons
done
work in
progress
TDWG - Sep 13, 2001- L2Plan - L.Ristori 2 checkmarked on Dec 7, 2001
L2 near term plan(by Oct 8)
1. Cutting on jets– Reliable CLIST– Reliable L1 board– Sync errors < 10-6 L1As– Automated HRR
2. Cutting on SVT tracks– Solve XTRP problem– Reliable SVTlist– Alfa code
3. Cutting on electrons– Solve XTRP problem– Reliable XTRPlist+CLIST– Solve CLIST eta-phi errors?– Alfa code
Also:
• Magic Bus tests + design new backplane– AC termination– Power supply “sag” vs. improved bypassing
2a. SVT to TS direct path– Kludge card/cable– Firmware– RC work?
SVT parallel path(backup)
done
not finished
~ done done
not done done
done ~ Dec 1
TDWG - Sep 13, 2001- L2Plan - L.Ristori 3 checkmarked on Dec 7, 2001
L2 plans for shutdown(Oct 8 to Nov 17)
• Improve documentation– Protocols
– FPGA firmware
– Etc.
• Prepare tests of MB arbitration (Oct 8-15)
– Remove delays from firmware
– Test different board configurations and characterize collision problem
• Install new MB (Oct 15-22)
– Repeat tests (see above) and compare
– Test at maximum bus load• ISOLIST, RECES, extra TRACKlist, more
Alfas…
• Install new XTRP data boards (mid Oct)
– Full phi coverage
• At a lower priority (in this time frame):– Test multiple Alfa operation
– Tests of ISOLIST and RECES
done
Installed on Dec 4
done
done
in progress
TDWG - Sep 13, 2001- L2Plan - L.Ristori 4 checkmarked on Dec 7, 2001
L2 milestones
• Sept 19?: New Magic Bus review• Oct 25: New Magic Bus working with:
– L1, CLIST, XTRPlist, SVTlist, 1 Alfa
– Artificial delays removed from firmware
– L1A rate ~ 10KHz
– Deadtime from errors < 2%
– Data error rate < 10-7
• Jan 1: New Magic Bus working with:– L1, CLIST, XTRPlist, SVTlist, 4 Alfas (RECES,
ISOLIST)
– L1A rate ~ 25 KHz
– Deadtime from errors < 2%
– Data error rate < 10-7
done
old
~ 20KHz
?
TDWG - Sep 13, 2001- L2Plan - L.Ristori 5 checkmarked on Dec 7, 2001
What if we fail the Oct 25 milestone?
• Implement a modified/simplified arbitration scheme that will allow us to trigger on jets and SVT shortly after we come up on Nov 17
• We need a very precise plan and maybe some preparatory work by Oct 25, so that we are confident it can be implemented by Nov 17
• Brainstorming of ideas must start now