TDWG - Sep 13, 2001- L2Plan - L.Ristori 1 checkmarked on Dec 7, 2001 L2 Goals Near term (by Oct 8) Demonstrate cutting on jets and SVT tracks Intermediate term (Nov 17 to end of 2001) Come back from shutdown cutting on jets and SVT tracks Commission SVT trigger operation Commission electron trigger Far term (early 2002) Establish stable L2 operation Commission remaining interface boards (RECES, ISOLIST, MUON) to cut on: Electrons Photons Muons done work in progress

description

L2 Goals.  done. Near term (by Oct 8) Demonstrate cutting on jets and SVT tracks Intermediate term (Nov 17 to end of 2001) Come back from shutdown cutting on jets and SVT tracks Commission SVT trigger operation Commission electron trigger Far term (early 2002) - PowerPoint PPT Presentation

Transcript of L2 Goals

Page 1: L2 Goals

TDWG - Sep 13, 2001- L2Plan - L.Ristori 1 checkmarked on Dec 7, 2001

L2 Goals

• Near term (by Oct 8)

– Demonstrate cutting on jets and SVT tracks

• Intermediate term (Nov 17 to end of 2001)

– Come back from shutdown cutting on jets and SVT tracks

– Commission SVT trigger operation

– Commission electron trigger

• Far term (early 2002)

– Establish stable L2 operation

– Commission remaining interface boards (RECES, ISOLIST, MUON) to cut on:

• Electrons• Photons• Muons

done

work in

progress

Page 2: L2 Goals

TDWG - Sep 13, 2001- L2Plan - L.Ristori 2 checkmarked on Dec 7, 2001

L2 near term plan(by Oct 8)

1. Cutting on jets– Reliable CLIST– Reliable L1 board– Sync errors < 10-6 L1As– Automated HRR

2. Cutting on SVT tracks– Solve XTRP problem– Reliable SVTlist– Alfa code

3. Cutting on electrons– Solve XTRP problem– Reliable XTRPlist+CLIST– Solve CLIST eta-phi errors?– Alfa code

Also:

• Magic Bus tests + design new backplane– AC termination– Power supply “sag” vs. improved bypassing

2a. SVT to TS direct path– Kludge card/cable– Firmware– RC work?

SVT parallel path(backup)

done

not finished

~ done done

not done done

done ~ Dec 1

Page 3: L2 Goals

TDWG - Sep 13, 2001- L2Plan - L.Ristori 3 checkmarked on Dec 7, 2001

L2 plans for shutdown(Oct 8 to Nov 17)

• Improve documentation– Protocols

– FPGA firmware

– Etc.

• Prepare tests of MB arbitration (Oct 8-15)

– Remove delays from firmware

– Test different board configurations and characterize collision problem

• Install new MB (Oct 15-22)

– Repeat tests (see above) and compare

– Test at maximum bus load• ISOLIST, RECES, extra TRACKlist, more

Alfas…

• Install new XTRP data boards (mid Oct)

– Full phi coverage

• At a lower priority (in this time frame):– Test multiple Alfa operation

– Tests of ISOLIST and RECES

done

Installed on Dec 4

done

done

in progress

Page 4: L2 Goals

TDWG - Sep 13, 2001- L2Plan - L.Ristori 4 checkmarked on Dec 7, 2001

L2 milestones

• Sept 19?: New Magic Bus review• Oct 25: New Magic Bus working with:

– L1, CLIST, XTRPlist, SVTlist, 1 Alfa

– Artificial delays removed from firmware

– L1A rate ~ 10KHz

– Deadtime from errors < 2%

– Data error rate < 10-7

• Jan 1: New Magic Bus working with:– L1, CLIST, XTRPlist, SVTlist, 4 Alfas (RECES,

ISOLIST)

– L1A rate ~ 25 KHz

– Deadtime from errors < 2%

– Data error rate < 10-7

done

old

~ 20KHz

?

Page 5: L2 Goals

TDWG - Sep 13, 2001- L2Plan - L.Ristori 5 checkmarked on Dec 7, 2001

What if we fail the Oct 25 milestone?

• Implement a modified/simplified arbitration scheme that will allow us to trigger on jets and SVT shortly after we come up on Nov 17

• We need a very precise plan and maybe some preparatory work by Oct 25, so that we are confident it can be implemented by Nov 17

• Brainstorming of ideas must start now