Kusdhianto Setiawan Gadjah Mada University Defining the Project.

70
Kusdhianto Setiawan Gadjah Mada University Defining the Project

Transcript of Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Page 1: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Defining the Project

Page 2: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-1

Project Management Trade-Offs

Performance

Quality

Cost Time

Page 3: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-2

Project Priority Matrix

Constrain

Enhance

Accept

Time Performance Cost

Page 4: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-3

Hierarchical Breakdown of the WBS

1

2

3

4

Project

Deliverable

Subdeliverable

Lowest subdeliverable

Cost account*

Work package

5

Complete project

Major deliverables

Supporting deliverables

Lowest managementresponsibility level

Grouping of work packagesfor monitoring progress andresponsibility

Identifiable work activities

Level Hierarchical breakdown Description

*This breakdown groups work packages by type of work within a deliverable and allows assignment ofresponsibility to an organizational unit. This extra step facilities a system for monitoring project progress(discussed in Chapter 12).

Page 5: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-4

Work Breakdown StructurePersonal computer

prototype

Vendor,software,

applications

Mouse,keyboard,

voice

Diskstorageunits

Microprocessorunit

Moreitems

Floppy HardOptical Internalmemory

unit

BIOS (basicinput/output

system)

ROM RAM I/O File Utilities

Motor Circuitboard

Chassisframe

Read/writehead

WP-1M WP-1 CB WP-1 CF WP-1 RWHWP-2 CB WP-2 CF WP-2 RWHWP-3 CB WP-3 CF WP-3 RWHWP-4 CB WP-4 RWHWP-5 CB WP-5 RWHWP-6 CBWP-7 CB

~ ~ ~ ~ ~

~ ~

~ ~

Work packages

Lowest manageablesubdeliverables

Level1

2

3

4

5

Page 6: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-5

Integration of WBS and OBS

Time

Cost accountnumber

Personal computerprototype

Vendor,software,

applications

Mouse,keyboard,

voice

Diskstorageunits

Microprocessorunit

Moreitems

Floppy HardOptical Internalmemory

unit

BIOS (basicinput/output

system)

ROM RAM I/O File Utilities

Motor Circuitboard

Chassisframe

Read/writehead

~ ~ ~ ~ ~

~ ~

~ ~

Lowest manageablesubdeliverables

Level1

2

3

4

5

1.0

1.2 1.3 1.1 1.4

1.1.1 1.1.2 1.1.31.4.1 1.4.2

1.4.1.1 1.4.1.2 1.4.2.1 1.4.2.2 1.4.2.3

1.1.3.1 1.1.3.2 1.1.3.3 1.1.3.4

Cost 1.1.3.4.1account

Cost Costaccount account

Cost Costaccount account

Costaccount

Costaccount

Work packages WP1.1.3.4.2.1 WP1.1.3.4.2.2 WP1.1.3.4.2.3

Budget byperiod

Production

Design

Test

Purchasing

Software

Manufacturing

Organization

Page 7: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-8

Read/Write Head Design

Cost

Direct Costs Low Average High

Design engineers $ 80 $100 $150Proto engineers 130 150 280Materials 25 25 25Equipment rental 25 25 30

Total direct costs $260 $300 $485

Work package cost estimate

Page 8: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 3-9

Three Views of Cost

Project Duration

CommittedActual costScheduled budget

Cos

ts$6,000

5,000

4,000

3,000

2,000

1,000

Page 9: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Developing a Network Plan

Page 10: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-1

Rollup of Network Plans

WP-2

A

B

C

D

E

F

WP-1

WP-4

WP-3

Level 1 - Milestone Plan

Level 2 - Plans

Level 3 - Plans

Page 11: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-2

WBS/Work Packages to Network

Circuitboard

Designcost

account

Productioncost

account

Testcost

account

Softwarecost

account

Lowestelement

Organizatio

Units

DesignWP D-1-1 SpecificationsWP D-1-2 Documentation

ProductionWP P-10-1 Proto 1WP P-10-2 Final Proto 2

Test systemsWP T-13-1 Test

SoftwareWP S-22-1 Software preliminaryWP S-22-1 Software final version

BProto 1

5

DFinal

proto 24

ASpecifications

and documentation2

CPreliminary

software3

FFinal

software2

KTest

3

AD-1-1D-1-2

BP-10-1

DP-10-2

FS-22-2

KT-13-1

CS-22-1

Page 12: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-3

Activity-on-Node Network Fundamentals

X

Y

Z

Y and Z are preceded by X

Y and Z can begin at thesame time, if you wish

(B)

A B C

A is preceded by nothingB is preceded by AC is preceded by B

(A)

J

K

L

M

J, K, & L can all begin atthe same time, if you wish(they need not occursimultaneously)

All (J, K, L) must becompleted before M canbegin

but

X Z

AAY

(C)

(D)

Z is preceded by X and Y

AA is preceded by X and Y

Page 13: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-6

Activity-on-Node Network Fundamentals

KOLL BUSINESS CENTERCounty Engineers Design Department

B

15

Constructionplans

C

10

Trafficstudy

D

5

Servicecheck

A

5

Applicationapproval

ES ID EF

SL

LS Dur LF

Description

F

10

Commissionapproval

G

170

Wait for construction

H

35

Occupancy

E

15

Staff report

EF

Page 14: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-7

Activity-on-Node Network Forward Pass

5 B 20

15

Constructionplans

C

10 10 20

Trafficstudy

D

15 5 20

Servicecheck

A

0 5 5

Applicationapproval

ES ID EF

SL

LS Dur LF

Description

F

20 10 30

Commissionapproval

G

30 170 200

Wait for construction

H

200 35 235

Occupancy

20 E 35

15

Staff report

EF

KOLL BUSINESS CENTERCounty Engineers Design Department

20

15

20

15

10

200

35

Page 15: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-8

Activity-on-Node Network Backward Pass

B

5 15 20

Constructionplans

C

10 10 20

Trafficstudy

D

15 5 20

Servicecheck

A

0 5 5

Applicationapproval

ES ID EF

SL

LS Dur LF

Description

F

20 10 30

Commissionapproval

G

30 170 200

Wait for construction

H

200 35 235

Occupancy

E

185 15 200

Staff report

LS

KOLL BUSINESS CENTERCounty Engineers Design Department

20

20

185

185

10

15

5

20

Page 16: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-9

Activity-on-Node Network with Slack

5 B 20

0

5 15 20

Constructionplans

5 C 15

5

10 10 20

Trafficstudy

5 D 10

10

15 5 20

Servicecheck

0 A 5

0

0 5 5

Applicationapproval

ES ID EF

SL

LS Dur LF

Description

20 F 30

0

20 10 30

Commissionapproval

30 G 200

0

30 170 200

Wait for construction

200 H 235

0

200 35 235

Occupancy

20 E 35

165

185 15 200

Staff report

LS EF

KOLL BUSINESS CENTERCounty Engineers Design Department

20

15

185

185

10

15

5

20

20

20

10

20

15

Page 17: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-10

Software Conversion ProjectResponsibility Matrix

Engineeringdepartment

R A C

Kim C C

Ron C R A A A

Holly R

James R

Chuck A A

Wendy A R

Documentsdepartment

R R C

Sys

tem

spec

ific

atio

ns

Cod

ing

Use

rm

anua

l

For

ms

Cro

ssov

erpl

an

Tra

in s

taff

Tes

tActivities

Org

aniz

atio

nU

nit/

Indi

vidu

al Legend

R = ResponsibilityC = ContributesA = Advises

Page 18: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-12

Air Control Inc., Custom OrderProject—Network Diagram

1 Orderreview

20 20 2

2

3

4

5

Softwaredevelopment

Orderstandard

parts

Producestandard

parts

Designcustom parts

18 2 2022 40

15 2 1715 30

10 2 12 5 15

13 2 12 5 15

6

7 8

Manufacturecustom

hardware

Assemble Test

Activity8#

Legend

1515 3015 30

1030 4030 40

540 4540 45

DurationES EFLS LF

Page 19: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-13

Air Control Inc., Custom OrderProject—Gantt Chart

0 7 14 21 28 35 42 49

2

13

15

10

18

15

10

5

Order review

Design custom parts

Order standard parts

Produce standard parts

Software development

Manufacture customhardware

Assemble

Test

Page 20: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-14

Air Control Inc., Custom OrderProject—Network with Dates

1 Orderreview

2 1-Jan 2-Jan 1-Jan 2-Jan

2

3

4

5

Softwaredevelopment

Order standard parts

Produce standard parts

Designcustom parts

18 2-Jan 20-Jan22-Jan 9-Jan

15 2-Jan 17-Jan 15-Jan 30-Jan

10 2-Jan 12-Jan 5-Jan 15-Jan

13 2-Jan 15-Jan 2-Jan 15-Jan

6

7 8

Manufacturecustom

hardware

Assemble Test

Activity8#

Legend

15 15-Jan 30-Jan 15-Jan 30-Jan

10 30-Jan 9-Jan 30-Jan 9-Jan

5 9-Jan 14-Jan 9-Jan 14-Jan

DurationES date EF dateLS date LF date

Page 21: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-15

Example of Laddering UsingFinish-to-Start Relationship

Trench1/3

Trench1/3

Trench1/3

Lay pipe1/3

Lay pipe1/3

Lay pipe1/3

Refill1/3

Refill1/3

Refill1/3

AON network

Page 22: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-16

Finish-to-Start Relationship

X YLag 2

Page 23: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-17

Start-to-Start Relationship

ActivityM

ActivityN

ActivityP

ActivityQ

Lag 5

A B

Page 24: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-18

Use of Lags to Reduce Detail

Trench1 mile

Lay pipe1 mile

Lag 3

Refill1 mile

Lag 3

Page 25: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-19

Finish-to-Finish Relationship

Lag 4Prototype

Testing

Page 26: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-20

Start-to-Start Relationship

Lag 3

Systemdocumentation

Testing

Page 27: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-21

Combination Relationships

Lag 2

Code

Debug

Lag 4

Page 28: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-22

Network Using Lags

5 B 15

00

5 10 15

10 D 25

1111

21 15 36

0 A 5

0 0

0 5 5

ES ID EF

SL SL

LS Dur LF

15 E 30

05

30 10 45

30 F 40

05

30 10 45

40 H 50

5 0

45 5 50

15 C 20

5 5

20 5 25

Legend25 G 40

110

36 4 40

Lag 5

Lag 10

Lag 10

Lag 5Lag 10

Page 29: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 4-23

Hammock Activity Example

5 B 6

0

5 1 6

11 E 21

0

11 10 21

0 A 5

0

0 5 5

ES ID EF

SL

LS Dur. LF

Description

6 D 10

8

14 4 18

10 F 13

8

18 3 21

21 F 25

0

21 4 25

6 C 11

0

6 5 11

Legend5 G 13

Hammock

8

Page 30: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Managing Risk

Page 31: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 5-1

Risk Event Graph

Risk

High

Cost

Low

Project life cycle

Chances of risksoccurring

Cost to fixrisk event

Page 32: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 5-2

Risk Assessment Matrix

Systemfreezing

Low High High Startup

Userbacklash

High Medium MediumPost

installation

Hadwaremalfunctioning

Medium High High Installation

Risk eventChance-

LMHSeverity-

LMH

Detectiondifficulty-

LMH When

Page 33: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 5-3

Risk Schedules

Best-case schedule

Baseline schedule

Worst-case schedule

Actual scheduleForecast completion

schedule

10%

50%

90%

470 days

500 days

590 days

550 days300 days

Actual tracking schedule

Page 34: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 5-4

Responses to Risk Matrix

Risk eventAccept, reduce,share, transfer

Contingencyplan Trigger

Systemfreezing

Reduce Reinstall OSStill frozenafter 1 hour

Userbacklash

ReduceIncrease staff

supportCall from topmanagement

Hadwaremalfunctioning

TransferOrder different

brandReplacementdoesn't work

Page 35: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 5-5

Change RequestProject _________________

Originator ________________

Description of change

Install Y2K compatible chip in six computer controlled milling machines

Date _________________

Phone ________________

Y2K-Machine Dept.

CEG

3/29/

Ext. 4942

Impact Areas Baseline Impact

Deliverable # __________

Work Package # __________Cost Account # __________

Organization Unit __________

1.3M

1.313M1.31M

IS-M Dept.

Scope

Budget

Schedule

Contingency

Staff

Equipment

X

X X

X

Justification (include impact if not implemented)

Reprogramming cost is higher than estimated, and risk of old chips failing is higherthan estimated. (Eliminating reprogramming cost is -$10,000. Cost of Y2K chipsinstalled is +$15,000)

Disposition

Approve

Approve as amended

Disapprove

Deferred

XPriority

Emergency

Urgent

Routine

X

Funding Source

Mgmt. Reserve $ _____________

Budget. Reserve $ _____________

Other $ _____________

5,000.

Authorized _________________

Date ______________________

Scheduled start _________________

Scheduled finish ________________

S.P

4/3/

4/7/

5/10/

Page 36: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Chapter 6

Reducing Project Time

Page 37: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-1

Project Cost-Time Graph60

50

40

30

20

10

04 6 8 10 12 14 16

Totalcosts

Optimumcost-time

point

Directcosts

Indirectcosts

Low-costplan duration

point

Project duration

Cos

ts

Page 38: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-2

Activity Graph

$800

600

400

200

00 5 10

Activity duration (units)

Act

ivit

y co

stCrashcost

Normalcost

Crash point

Normalpoint

Page 39: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-3

Cost-Time Trade-Off ExampleDirect cos ts

Normal CrashAct ivity

IDSlope

Maximumcrasht ime Time Cos t Time Cost

ABCDEFG

204030253030 0

1 2 1 4 2 1 0

3 $506 80

10 6011 50

8 1005 406 70

2 $704 1609 907 1506 1604 706 70

Total direct cost $450

A

3

B

6

C

10

D

11

E

8

F

5

G

6

(a)

Time 25

A

2x

B

6

C

10

D

11

E

8

F

5

G

6

(b)

Time 24

LegendACT

DUR

Initial totaldirect cost $ 450

Totaldirect cost $ 470

Activities changed A $20

Page 40: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-4

Cost-Time Trade-Off Example (continued)

A

2x

B

6

C

9x

D

9

E

7

F

4x

G

6

(c)

Time 21

A

2x

B

6

C

10

D

10

E

8

F

5

G

6

(a)

Time 23

A

2x

B

6

C

10

D

10

E

6

F

4x

G

6

(b)

Time 22

Totaldirect cost $ 495

Activities changed D $25

Totaldirect cost $ 525

Activities changed F $30

Totaldirect cost $ 610

Activities changed F D E $30 $25 $30

Page 41: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-5

Summary Costs by Duration

Projectduration

Directcosts

+Indirect

costs=

Totalcosts

25 450 400 $85024 470 350 82023 495 300 79522 525 250 77521 610 200 810

Page 42: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 6-6

Project Cost-Time Graph$1000

800

600

400

200

0

20 21 22 23 24 25

$775

Duration (units)

Totalindirect

cost

Totaldirectcost

Totalproject

cost

Optimumcost-time

pointC

ost

Page 43: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Chapter 7

Resource Scheduling

Page 44: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-1

Constraint Examples

Pour Frame Roof

Design Code Test

Technical constraints

(A)

Plan

Purchaserefreshments

ReceptionDecoratehall

Hire band

(B)

Resource constraints

Plan Hire bandDecorate

hallPurchase

refreshmentsReception(C)

Page 45: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-2a

Time Constrained Network

2 B 8

2 2 2

4 6 10

2 C 6

0 2 0

2 4 6

2 D 4

6 1 6

8 2 10

0 A 2

0 2 0

0 2 2

ES ID EF

SL RES SLK

LS DUR LF

6 F 10

0 1 0

6 4 10

10 G 12

0 1 0

10 2 12

6 E 8

2 1 2

8 2 10

Legend

Page 46: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-2b

Time Constrained Network

A 2 2 0 2 0 2 2

B 2 6 2 10 2 2 2 2 2 2 2

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 1 1

E 1 2 6 10 2 1 1

F 1 4 6 10 0 1 1 1 1

G 1 2 10 12 0 1 1

2 2 5 5 4 4 4 4 1 1 1 1Total resource load

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

2 2 5 5 4 4 4 4 1 1 1 1

0 1 2 3 4 5 6 7 8 9 10 11 125432

1

Total resource load

Early start leveled resource profile

ES resource load chart

Page 47: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-3a

Leveled Resource Schedule

A 2 2 0 2 0 2 2

B 2 6 2 10 2 X X 2 2 2 2 2 2

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 1 1

E 1 2 6 10 2 1 1

F 1 4 6 10 0 1 1 1 1

G 1 2 10 12 0 1 1

2 2 3 3 4 4 4 4 3 3 1 1Total resource load

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

2 2 3 3 4 4 3 3 3 3 1 1

0 1 2 3 4 5 6 7 8 9 10 11 125432

1

Leveled resource profile

Leveled resource schedule A

Page 48: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-3b

Leveled Resource Schedule

A 2 2 0 2 0 2 2

B 2 6 2 10 2 X X 2 2 2 2

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 x x x x x x 1 1

E 1 2 6 10 2 x x 1 1

F 1 4 6 10 0 1 1 1 1

G 1 2 10 12 0

2 2 4 4 4 4 3 3 3 3 1 1Total resource load

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

2 2 4 4 4 4 3 3 3 3 1 1

0 1 2 3 4 5 6 7 8 9 10 11 125432

1

Leveled resource profile

Leveled resource schedule B

Page 49: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-4a

Resource Constrained Schedulethrough Period 2-3

2 B 8

2 2 2

4 6 10

2 C 6

0 2 0

2 4 6

2 D 4

6 1 6

8 2 10

0 A 2

0 2 0

0 2 2

ES ID EF

SLK RES SLK

LS DUR LF

6 F 10

0 1 0

6 4 10

10 G 12

0 1 0

10 2 12

6 E 8

2 1 2

8 2 10

Legend

Page 50: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-4b

Resource Constrained Schedulethrough Period 2-3

Lev

eled

res

ourc

e pr

ofil

e

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

A 2 2 0 2 0 2 2

B 2 6 2 10 2 X

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 1 1

E 1 2 6 10 2

F 1 4 6 10 0

G 1 2 10 12 0

2 2 3 3 2 2

3 3 3 3 3 3 3 3 3 3 3 3

Total resource load

Resource available

3 1

13 14

ES

res

ourc

e lo

ad c

hart

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

A 2 2 0 2 0 2 2

B 2 6 2 10 2 2 2 2 2 2 2

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 1 1

E 1 2 6 10 2 1 1

F 1 4 6 10 0 1 1 1 1

G 1 2 10 12 0 1 1

2 2 5 5 4 4 4 4 1 1 1 1Total resource load

13 14

Page 51: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-5a

Resource Constrained Schedulethrough Period 5-6

Res

ourc

e co

nstr

aine

d sc

hedu

leth

roug

h pe

riod

5-6

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

A 2 2 0 2 0 2 2

B 2 6 10 X X X X

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 6 1 1

E 1 2 6 10 2

F 1 4 6 10 0

G 1 2 X X

2 2 3 3 2 2

3 3 3 3 3 3 3 3 3 3 3 3

Total resource load

Resource available

13 14

2 3 45 6

2 1 0-1 -2

10 11 12

12 13 14

0 -1 -2

Fin

al r

esou

rce

cons

trai

ned

sche

dule

ID RES DUR ES LF TS 0 1 2 3 4 5 6 7 8 9 10 11 12

A 2 2 0 2 0 2 2

B 2 6 10 X X X X 2 2 2 2 2 2

C 2 4 2 6 0 2 2 2 2

D 1 2 2 10 1 1 S S

E 1 2 10 X X X X 1 1

F 1 4 6 1 1 1 1

G 1 2 X X 1 1

2 2 3 3 2 2 3 3 3 3 3 3 1 1

3 3 3 3 3 3 3 3 3 3 3 3 3 3

Total resource load

Resource available

13 14

2 3 45 6

2 1 0-1 -2

10 11 12

12 13 14

0 -1 -2

0 1 2

10 11 12

6 7 89 10

2 1 0-1 -2

6 2

Page 52: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-5b

Resource Constrained Schedulethrough Period 5-6

6 B 12

0 2 0

6 6 12

2 C 6

0 2 0

2 4 6

2 D 4

2 1 2

4 2 6

0 A 2

0 2 0

0 2 2

ES ID EF

SLK RES SLK

LS DUR LF

6 F 10

0 1 0

6 4 10

12 G 14

0 1 0

12 2 14

10 E 12

0 1 0

10 2 12

Legend

Page 53: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-6b

Original Network Plan

2 6 7

8 2A 8

10 5 15

2 4 5

4 2C 4

6 3 9

4 5 9

0 2C 0

4 5 9

0 2 3

6 1A 6

6 3 9 9 8 12

0 2B 0

9 3 12

14 10 16

1 2A 1

15 2 179 7 14

1 2B 1

10 5 15

0 1 2

4 1A 4

4 2 6

0 3 4

0 2B 0

0 4 4

4 9 7

5 2A 5

9 3 12

12 11 17

0 2C 0

12 5 17

ES ID EF

SLK RES SLK

LS DUR LF

Legend

Resourcesavailable,2 each ofA, B, C

Page 54: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-6b

Original Network Plan

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

S 0 6 S S S S S S

3 S 8 7

4 5 11 S S

102

1

15 16 17 18 19 20

A

B

C

Resource loading chart

ACT ES LS EF LF Slack1 0 4 2 6 42 0 6 3 9 63 0 0 4 4 04 2 6 5 9 45 4 4 9 9 06 2 10 7 15 87 9 10 14 15 18 9 9 12 12 09 4 9 7 12 510 14 15 16 17 111 12 12 17 17 0

Plan scheduleACT RES ESR LSR EFR LFR Slack

1 1A 0 0 2 2 02 1A 0 7 3 10 73 2B 0 1 4 5 14 2C 2 2 5 5 05 2C 5 5 10 10 06 2A 7 13 12 18 67 2B 13 13 18 18 08 2B 10 10 13 13 09 2A 4 10 7 13 610 2A 18 18 20 20 011 2C 13 15 18 20 2

New resource schedule

Page 55: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-7

Splitting/Multitasking

Activity duration without splitting

Activity duration split into three segments—A, B, C

Activity A Activity B Activity C

Activity A Activity B Activity C

Startup Shutdown

Activity duration split with shutdown and startup

Page 56: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-8

Responsibility Matrix for aMarket Research Project

Task Richard Dan Dave Linda Elizabeth

Identify target customers R S S

Develop draft questionnaire R S S

Pilot-test questionnaire R S

Finalize questionnaire R S S S

Print questionnaire R

Prepare mailing labels R

Mail questionnaires R

Receive and monitor returned questionnaires R S

Input response data R

Analyze results R S S

Prepare draft of report S R S S

Prepare final report R S

Project teamR = ResponsibleS = Supports/assists

Page 57: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 7-9

Responsibility Matrix for the ComputerControlled Conveyor Belt Project

DeliverablesDesign Develop-

mentDocumen-

tationAssembly Testing Purchas-

ingQuality

assuranceManufac-

turing

Architechural design 1 2 2 3 3

Hardware specifications 2 1 2 3

Kernal specifications 1 3 3

Utilities specification 2 1 3

Hardware design 1 3 3 3

Disk drivers 3 1 2

Memory management 1 3 3

Operating system documentation 2 2 1 3

Prototypes 5 4 1 3 3 3 4

Integrated acceptance test 5 2 2 1 5 5

Organization

Legend

1 Responsible 2 Support3 Consult 4 Notification5 Approval

Page 58: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Chapter 8

Organization

Page 59: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 8-1

Functional Organizations

Delta Manufacturing, Inc.President

Humanresources

Finance andadministration

Marketing Engineering Manufacturing Procurement

Electronicsengineering

Softwareengineering

Mechanicalengineering

DesignReceiving &inspection

Purchasing

Customerservice

Domesticsales

Internationalsales

Fabrication Assembly TestingProductionscheduling

Projectcoordination

Page 60: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 8-2

Dedicated Project Team

Zeus Electronics, Inc.President

Humanresources

Finance andadministration

Marketing Engineering Manufacturing Procurement

Project manager

Project team

Page 61: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Figure 8-3

Project Organization Structure

Central Engineering Systems, Inc.President

MarketingHuman

resources

Engineering Manufacturing Procurement

Finance andadministration

Legal

Alpha ProjectProject Manager

Beta ProjectProject Manager

Engineering Subcontractors

Manufacturing Procurement

Otherprojects

Otherprojects

ElectricalMechanicalSoftware

FabricationAssemblyTest

SystemsHardwareSoftware

Subcontractor XSubcontractor YSubcontractor Z

AssemblyTest

Kusdhianto Setiawan Gadjah Mada University

Page 62: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan Gadjah Mada University

Figure 8-4

Matrix Organization Structure

Zeus Electronics, Inc.President

Humanresources

Finance

Director ofprojects Engineering Manufacturing Marketing

Projectadministration

Designengineering

Electronicsengineering

Softwareengineering

Mechanicalengineering

Technicaldocumentation

Assembly Testing Quality Domesticsales

Internationalsales

Customerservice

Project Aproject

manager

Project Bproject

manager

Project Cproject

manager

1

1

1/2

2

3

1

1

1 1

2

1

1

1

2

1

1/2

1

1

1 1

1/2

2

2

1

2

Page 63: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Table 8-1

Division of Project Manager and Functional Manager Responsibilities in a Matrix Structure

Project manager Negotiated issues Functional manager

What has to be done? Who will do the task? How will it be done?

When should the task bedone?

Where will the task bedone?

How much money isavailable to do the task?

Why will the task be done? How will the projectinvolvement impact normalfunctional activities?

How well has the totalproject been done?

Is the task satisfactorilycompleted?

How well has the functionalinput been integrated?

Gadjah Mada University

Page 64: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-6

Key Dimensions Defining anOrganization’s Culture

Gadjah Mada University

Job 1. Member identity Organization

Individual 2. Team emphasis Group

Task 3. Management focus People

Independent 4. Unit integration Interdependent

Loose 5. Control Tight

Low 6. Risk tolerance High

Performance 7. Reward criteria Other

Low 8. Conflict tolerance High

Means 9. Means-ends orientation Ends

Internal 10. Open-system focus External

Page 65: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-8

Cultural Dimensions of an OrganizationSupportive of Project Management

Gadjah Mada University

Job 1. Member identity

Organization

Individual 2. Team emphasis

Group

Task 3. People focus

People

Independent 4. Unit integration

Interdependent

Loose 5. Control

Tight

Low 6. Risk tolerance

High

Performance 7. Reward criteria

Other

Low 8. Conflict tolerance

High

Means 9. Means-ends orientation

Ends

Internal10. Open-system focus

External

Page 66: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-9

Organization of Product DevelopmentProjects at ORION

Gadjah Mada University

Project manager

Deputyplanning and control management

Electronicssystem engineer

Mechanicssystem engineer

Team leader

Team leader

Team leader

Team leader

Page 67: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-10

Traditional Master Plan at ORION

Gadjah Mada University

Activities/time 4-7 Years 1-4 Years

Design reviews

Design anddevelopment

Production anddelivery

ILS

SDR PDR CDR TRR PRR

Laboratory tests Environmental tests

Build production lineand test equipment

Documentation andtraining program

Training

Production and deliveries

Page 68: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-11

Proposed Project Organizationfor the Jaguar Project

Gadjah Mada University

Project manager

Deputyproduction manager

Electronicssystem engineer

Mechanicssystem engineer

Team leader

Team leader

Team leader

Team leader

Deputyplanning and control management

QAmanager

ILSmanager

Page 69: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure 8-12

Jaguar Master Plan

Gadjah Mada University

Activities/time 3-4 Years 1-4 Years

Design reviews

Design anddevelopment

Production anddelivery

ILS

SDR PDR CDR TRR PRR

Laboratory tests Environmentaltests

Build production lineand test equipment

Documentation andtraining program

Training

Production and deliveries

Page 70: Kusdhianto Setiawan Gadjah Mada University Defining the Project.

Kusdhianto Setiawan

Figure A8-1

Mechanisms for SustainingOrganizational Culture

Gadjah Mada University

Methods for maintaining organizational culture

• Formal statement of principles• Top management behavior• Reactions to organizational crisis• Allocation of rewards and status• Rituals, stories, and symbols

Recruitment ofemployees whofit the culture

Organizationalculture

Removal ofemployees who

deviate fromthe culture