Indooroopilly Shopping Centre

Zone 2 Level 4 Roof Framing

Indooroopilly Shopping Centre

Structured for Success

Zone 2 Level 4 Roof Framing

Erection Sequence Grid S25-S24 / D-A1Step 1Install RA1 Raking angles as per lift sequence Install SC1 columnsInstall TR11 then TR12Install purlins & bridging

LIFT 1LIFT 2LIFT 4LIFT 3

Erection Sequence Grid S25-S24 / D-A1Step 2Assemble walkway frames on the ground Cladding to be complete once frames or installed

Erection Sequence Grid S25-S24 / D-A1Step 3Install B13 to U/S Slab on Grid S24Install B16s with mini crane as per lift sequence Install SC1 column and B13 on Grid B as per lift sequence

LIFT 1LIFT 2LIFT 3LIFT 4LIFT 5LIFT 7LIFT 6

Erection Sequence Grid S25-S24 / D-A1Step 4Install SC1 columns supported by B16s & B13Install 2/TR9s as per lift sequence

LIFT 1LIFT 2LIFT 3LIFT 4

Erection Sequence Grid S25-S24 / D-A1

FRAMESTEEL WEIGHT (kg)CLADDING WEIGHT (kg) (Approx.)TOTAL WEIGHT (Approx.)LENGTHWIDTHHEIGHTFrame 5172170024211070018502570Frame 66564001056365018502570Frame 712606001860917016003070

Step 5Install walkway frames as per lift sequenceTemporary propping as required Install R3 & HC1s Between Grids C-BB9s & JoistsInstall Walkway TrussesLIFT 4 & 5LIFT 6 & 7

Erection Sequence Grid S25-S24 / D-A1Step 5Install R1 rafter on Grid B / R1 rafter on Between Grids B-A as per lift sequenceInstall SC1 & 2/TR9s as per lift sequence Install struts, bracing, purlins, bridging & fly bracing as required

LIFT 1LIFT 3LIFT 2LIFT 4LIFT 5

Erection Sequence Lower Roof Grid A-D Step 1Install SC1 as per lift sequence Install B12 transfer beams Install rafters to tie back to structure

Erection Sequence Lower Roof Grid A-D Step 2Install SC1s as per lift sequenceInstall Rafter to tie back to B12 with 4 tonne mini craneInstall WH1(u) and S1 as per lift sequence Install Bracings, Raking angles, Fly bracings and Purlins as required

Erection Sequence Lower Roof Grid A-D Step 3Install Trusses as per lift sequence

Erection Sequence Lower Roof Grid D-F Step 1Install SC1 & SC3 as per lift sequenceInstall B1 on grid S26Install rafters to tie back to B1 with 4 tonne mini craneInstall S1, and WH1 (u) as per Lift sequenceInstall Bracings, Fly bracings and Purlins as required

Erection Sequence Lower Roof Grid D-F

Step 2Install trusses as per lift sequence

Erection Sequence Lower Roof Grid F-H Step 1Install SC1, SC3 & SC4 as per lift sequenceInstall B1 on grid 26 Install rafters to tie structure back to B1 with 4 tonne mini craneInstall S1 & WH1 (u) as per lift sequenceInstall bracings, fly bracing, Raking angles and purlins as required

Erection Sequence Lower Roof Grid F-H Step 2Lift and secure trusses as per lift sequence

Erection Sequence Grid S24-S21Step 1Assemble walkway frames at HSS yard Allow Wadsworth Contractors to Clad at HSS yard

Erection Sequence Grid S24-S21Step 2Install walkway framing North of grid 2AAssemble columns, rafters & beams as per assembly detailLift assembled frames into position as per lift sequence Install S2 struts to tie columns & rafters back to exist. Structure as per lift sequenceInstall temporary bracing as required

FRAMESTEEL WEIGHT (kg)TOTAL WEIGHTWIDTHHEIGHTFrame 112401240326013350Frame 212201220326013350Frame 311301130326013350Frame 410901090276013350

Erection Sequence Grid S24-S21Step 3Lift walkway frames into position and secure as per lift sequenceInstall SC4 Column as per lift sequenceInstall TR5 trusses as per lift sequenceInstall rafter to tie back to existing structureLift walkway 4 and secure as per lift sequenceInstall Purlins and bracings as requiredFRAMESTEEL WEIGHT (kg)CLADDING WEIGHT (kg) (Approx.)TOTAL WEIGHT (Approx.)LENGTHWIDTHHEIGHTFrame 112226001822527017504260Frame 210645001564620017502900Frame 310435001543604017502900Frame 4 7004001100384017502900

Erection Sequence Grid S24-S21Step 4Lift TR5 trusses into position and secure as per lift sequenceRemove temporary bracing

LIFT 7LIFT 8LIFT 9

Erection Sequence Upper Roof Framing FRAMESTEEL WEIGHT (kg)TOTAL WEIGHTLENGTHWIDTHHEIGHTFrame 1521052101124011200250Frame 2521052101124011200250

Step 1Install SC2 on Grid C-D/S26Assemble Upper roof frame grids C-E/S26-S28 on the groundInstall assembled roof frame Repeat process for roof frame on grids F-H/S26-S28LIFT 1LIFT 2

Erection Sequence Awning Roof Grid A-H Step 1Install SC2 as per lift sequenceInstall B2 Rafter as per lift sequence Install P2 to be bolted to B3 on ground and lifted into placeRepeat Process from Grids A-H

ASSEMBLYSTEEL WEIGHT (kg)LENGTHWIDTHHEIGHTAssembly 1160060005060460

Erection Grid A1-D1

Step 1Lift Trusses and hangers assembly into position and secureInstall R8 to hangersInstall B14 between grids 2A - 3A as per lift sequenceInstall purlins between grids 2A - 3A