KSCE_1_2005_06_48(C)
description
Transcript of KSCE_1_2005_06_48(C)
48 | Vol.53 No.6 June, 2005 |
. Introduction
The design and construction of cable supported
bridges relies to a large extent on past experience,
where good and sometimes less good ideas from
previous projects are evaluated and incorporated
as appropriate in the new designs together with
new ideas. Even though long span bridges can
appear similar in the concept, all projects have to
be individually designed considering the local
conditions. Because the number of new long span
bridges is relatively small, the development can
appear to be slow compared to other industries.
However, almost all major bridge projects
contribute in one way or another to the
development. Furthermore, the construction of a
major bridge represents a significant investment
where timely and safe construction is important
for a successful completion of a project, which in
some cases restrain the willingness to innovation.
Finally, the basis for the design and construction -
the national or international codes - are often
established mainly to suit smaller bridges, which
are constructed more frequent and there is often a
delay in implementing the latest knowledge in the
codes.
This present paper focuses on state-of-the-art of
design and construction of cable stayed and
suspension bridges.
. Bridge types
There are basically two types of cable supported
bridges, suspension bridges and cable stayed
bridges. While suspension bridges have been
designed and constructed for more than 150
years, the cable stayed bridge concept is
relatively new and cable stayed bridges have only
been constructed since the middle of the 20th
century.
Lars HAUGEChief Project Manager, COWI A/SLyngby, [email protected]
| ์ฝ ๋ ฅ |Lars Hauge, born 1962, graduated from the TechnicalUniversity of Denmark in 1986. Since 1990 he has beenemployed by COWI A/S in Copenhagen in the department formajor bridges, and has been involved in the design of some ofthe world's largest bridges. He has been working in Korea forthe Busan-Geoje Fixed Link for the past two years as projectmanager for the design of the bridges.
Construction and Technology of Long Span Bridges
49| Feature Article |
Trends in Design and Construction of Long Span Bridges
A ground anchored suspension bridge has the
bridge deck suspended from main cables by
hangers and the deck has roughly no other
function than to provide a carriageway for the
traffic. The main load carrying elements are the
towers, the anchor structure and the main cable.
The sag of the main cables, which controls the
cable steel quantities, is traditionally between 1 : 9
and 1 : 11. A suspension bridge is constructed by
constructing anchors and pylons first followed by
the main cable and finally the bridge deck which
is suspended from the main cables.
Traditionally a cable stayed bridge is constructed
by constructing the towers followed by the deck,
which is cantilevered from the towers. The height
of the towers above deck is normally not less than
approximately 1/5 times the main span. In a cable
stayed bridge, the deck is utilised as compression
members balancing the horizontal forces from the
cables.
This short description illustrates the main
differences between suspension bridges and cable
stayed bridges:
For the construction of a suspension bridge,
the elements are constructed sequential
leading to a long construction time where
most elements are on the critical path.
A suspension bridge requires an anchor
structure, which normally is expensive and
time critical with regard to construction, while
a cable stayed bridge utilises the bridge deck
to balance the horizontal component of the
cable forces.
The amount of cable steel is significantly
higher in a suspension bridge compared to a
cable stayed bridge, due to the reduced tower
height to span ratio.
It will almost always be economically
advantageous to construct a cable stayed bridge if
possible, unless special conditions prevail as for
instance good rock conditions for main cable
anchorage. However, due to the tower height and
the traditional construction methods there is an
upper limit to how long cable stayed bridge can be
constructed.
Attempts have been made to mitigate the
deficiencies of suspension bridge compared to cable
stayed bridges. Self-anchored suspension bridges
have been designed and constructed thus avoiding the
anchor block structure and utilising the bridge deck to
balance the horizontal forces from the main cables.
However, a major set-back is that the deck has to be
erected on temporary supports prior to cable erection,
which calls for temporary support of the bridge deck
during construction adding the bridge deck to the
critical path. An example of a self anchored
suspension bridge is YongJong Bridge in Korea,
where the span is moderate and where the bridge
deck is sufficiently large to carry the compression
force due to large capacity requirements.
Figure 1. Great Belt Suspension Bridge
50 | Vol.53 No.6 June, 2005 |
Construction and Technology of Long Span Bridges
1. Suspension BridgesA suspension bridge with an anchor block
structure is normally only constructed, if the
required span is longer than what can be
accommodated by a cable stayed bridge. This limit
is today around a main span of 1200 - 1400m, but
has moved over the past 50 years from 600 -
700m. Recent long span suspension bridges
include Akashi Kaikyo - Japan (1990m main
span), Great Belt East Bridge - Denmark (1624m
main span), Tsing Ma - Hong Kong (1377m main
span), Humber Bridge - UK (1410m main span)
and the High Coast Bridge - Sweden (1210m main
span). The High Coast Bridge was constructed
taking advantage of extremely good foundation
conditions for the main cables, thus being
economically optimal with a relatively shorter
span. There is a tendency towards even longer
spans, and the next big leap forward is likely to be
the bridge across the Messina Strait in Italy, where
a main span of 3300m is envisaged. This bridge is
out for tender now (spring/summer 2005).
Suspension bridges are sometimes constructed
with shorter spans. However, this is mostly the
case where the design is governed by other issues
than construction cost and time. Examples hereof
are East Bay Bridge in the US, Millenium Bridge
in the UK and Yong Jong Grand Bridge in Korea.
There are exemptions from these general rules
including Gwang An Bridge in Korea and
Carquinez Bridge in the US.
2. Cable Stayed BridgesCable stayed bridges can roughly be divided in three
groups - short spans, medium spans and long spans.
The Normandy Bridge (856m main span) in
France and the Tatara Bridge (890m main span) in
Japan, which were completed in the mid 1990'ies,
marked with main spans of more than 800 m a
large step forward and have paved the way for the
even longer spans of Stonecutters Bridge (1018m
main span) in Hong Kong and Sutong Bridge
(1088 m main span) in China - both currently
under construction. Al these bridges are
constructed with closed steel box girders in the
main span to increase the torsional rigidity. All the
long spans cable stayed bridges are designed
triangulated cable systems.
The cable configuration layout is important for
a long span cable stayed bridge. An A-tower will
in some cases increases the critical wind speed
by 20% compared to a H-tower. In Korea, the 2nd
YongJong Bridge, which currently are being
designed, and the 2nd Nanjing Yangtze Crossing
in China follows the same principles with
triangulated cable systems and closed steel box
Figure 2. Messina Strait Crossing
51| Feature Article |
Trends in Design and Construction of Long Span Bridges
girders. One of the most important parameters
for long span cable stayed bridges is the span to
with ratio and with a span of more than 40 times
the width, the Normandy Bridge in France is still
one of the slender cable stayed bridges in the
world.
In recent years several cables stayed bridges with
main spans of between 400 and 600m for
roadway traffic have been constructed. A concept
with open plated composite bridge decks and
concrete towers seems to be optimal with regard
to cost and time for construction for this range of
spans. There are several examples of this type of
bridge including: Alex Fraiser Bridge in Canada,
2nd Severn Bridge and Dartford Bridge in the UK,
SeoHae Grand Bridge and Sham Shui Po in
Korea, Uddevalla Bridge in Sweden, Rama 8
Bridge in Thailand (mono tower bridge) and
YangPu, XuPu and Ching Chau Min Yang in
China. The bridges of Busan-Geoje Fixed Link in
Korea and the Cooper River bridge in the US are
currently under construction and will become the
same basic bridge types. For main spans over
600m (500m in typhoon areas) it is difficult for
this bridge type to fulfil the requirement to
aerodynamic stability.
Numerous smaller span cable stayed bridges
have been constructed for various reasons - one
being the landmark quality of cable stayed
bridges.
Recently there has been a trend towards multi-
span cable supported bridges. In Hong Kong Ting
Kau Bridge was inaugurated in 1998 and Rion-
Antirion Bridge in Greece and Viaduc de Maillot
in France has recently been competed. In Korea is
the construction of the bridges of the Busan-Geoje
Fixed Link about to commence and the Link will
include a multi-span cable stayed bridge. For the
crossing of the Canal de Chacao in Chile a multi-
span suspension bridge is currently considered.
. Developments in Design
1. Development in Articulation(1) Cable stayed bridges
Hydraulics is commonly used for bridges
subjected to seismic loading to provide support
during a seismic event in the form of Shock
Transmission Units (STU). There has been a trend
towards utilising hydraulics to control the support
conditions of the bridge.
Figure 3. Normandy Bridge
Figure 4. SeoHae Grand Bridge
52 | Vol.53 No.6 June, 2005 |
Construction and Technology of Long Span Bridges
On the Faroe Bridge - a cable stayed bridge
supported by a single plane of cables; the bridge
deck is only supported laterally and for twist at the
towers, while the bridge deck can move freely
vertically. The static system was obtained by the
use of coupled hydraulic pistons at both sides of
the bridge deck
On Stonecutters Bridge the bridge deck is
supported longitudinally for โquickโmovements
from dynamic wind and live load, while it is free
to move for โslowโmovements from temperature
variations. The advantages are that effects from
dynamic wind would have overloaded the back
span piers, if the deck was not supported by the
tower and the effects from temperature would
have overloaded the towers, if the deck had been
fully restrained.
On Sutong Bridge, the longitudinal movements
at the towers will be restrained by speed
dependent hydraulic dampers. (F=3750ยทV 0.4 )The bridge deck is not supported vertically at the
towers.
Another characteristic with the above bridges is
that vertical support at the towers is not provided,
thus eliminating the hard point at the towers,
which will attract large bending moments.
The articulation of the Normandy Bridge with
the 116 m cantilever in concrete and monolithic
joint between the girder and the pylon might seem
a little unconventional. However, having studied
the bridge in detail it is clear that these features are
advantageous for the bridge. During construction
the steel part of the girder acted as if it was
supported - not at the pylons - but 116 m out in the
main span, and thus reducing the deflection. The
fully restrained system was possible because the
pylon was supported on a flexible pile foundation
and because the curvature of the deck is large.
(2) Suspension bridge
Traditionally, suspension bridges have been
designed as โ three span structuresโwith
expansion joints and supports at the towers.
Experience has shown that maintenance works on
these parts constitute a major part of the
maintenance cost. Therefore a concept with a
continuous girder over the full cable supported
length would be attractive and was implemented
for the Great Belt East Bridge in Denmark and for
the High Coast Bridge in Sweden. One problem
to overcome with the continuous girder trough the
pylons was the handling of the forced bending
moments at the pylons caused by angular rotation
of the main cables over the cable saddles. The
girder deflection would more or less follow the
cable deflection, and bending moments would be
introduced. To minimise the forced moments in
combination with dead and live load actions, the
supporting conditions were optimised based on a
parametric study of hanger distances, hanger types
(locked coil versus parallel wire strands),
regulation of hanger forces, girder stiffness,
supporting of the girder for vertical forces at the
pylons, etc.
As a supplement the longitudinal movements at
the anchor blocks were limited by means of
hydraulic pistons in order to limit the angular
deflection of the hangers and the requirements to
the expansion joints. The system also acts against
quick movements to reduce the wear in the
expansion joints and the bearings.
53| Feature Article |
Trends in Design and Construction of Long Span Bridges
2. Closed box girder conceptThe closed steel box girder concept was first
introduced on the Severn suspension bridge in the
UK and the Little Belt suspension bridge in
Denmark in the 1960โies. The advantages of the
closed steel box are high torsional stiffness,
relatively simple automated fabrication and easy
maintenance. A complex geometry, many edges
and large exposed surfaces are sensitive to
deterioration. Therefore, simple structural forms
as the closed steel box girder with a minimum of
exposure to the environment are preferred. The
outer surface is completely smooth with a
minimum of exposure and easy to maintain. The
interior, which comprises about 80 percent of the
total steel area with stiffening troughs and
bulkheads, can be corrosion protected by
dehumidification and thus does not need to be
painted. The principle in dehumidification is to
keep the relative humidity inside the box below
40 percent, leaving an adequate margin to 60
percent, the limit above which corrosion may take
place. This can be achieved by installation of a
simple fan system for circulation of the enclosed
air and a dehumidifier unit equipped with
hygroscopic filters. The closed steel box girder is
also superior with regard to aerodynamic
performance. The high torsional stiffness
increases the critical flutter wind speed and low
drag coefficients and derivatives reduce the effects
from wind loading.
3. AerodynamicThe failure of the Tacoma Narrows suspension
bridge in the US resulted in a general set back for
the development of design and construction of
long span bridges. Bridges designed and
constructed in the wake of the accident tended
towards heavier steel truss girder design, while the
sources of the undesired vibrations were
thoroughly investigated. Today substantial wind
tunnel testing is part of every long span bridge
design and comprise as a minimum section model
tests of the bridge deck and often 3D aeroelastic
full bridge model tests. These tests are often
supplemented with High Reynolds number tests,
cable vibration tests, terrain model tests and site
measurements of the wind climate.
As computer power increases, more and more
sophisticated calculations can be performed
providing the bridge designers with useful
information of the behaviour of the structures.
COWI has developed a computer tool, which
can be used with advantage for comparison of
bridge girder concepts, DWMflow. Based on a
description of the cross-section, DWMflow
calculates static wind load coefficients (drag-
coefficients), flutter-coefficients and vortex
shedding response. This means that a qualified
evaluation of for instance, different cross sections
could be carried out in a short time without
Figure 5 Stonecutters Bridge in the Monash wind tunnel
54 | Vol.53 No.6 June, 2005 |
Construction and Technology of Long Span Bridges
recourse to physical wind tunnel tests. The
โartificiallโwind tunnel has been compared with
a real wind tunnel with good results.
4. DurabilityThe sixties and the following years have been
characterised by an important economical growth
the result of which has lead to intensive
investments in infrastructure projects, including
thousands of bridges. Efforts have mainly been
concentrated on achieving low initial construction
costs and minimise the construction period.
Today, the effect has begun to show in the form of
an increasing amount of damages on these
bridges.
Therefore, long service life design concepts for
100years or more are becoming a basic
requirement for major projects. The result is a
considerable impact on the development of bridge
construction technology.
The concept of dehumidification first introduced
in bridge construction for the closed steel box
girders has been exported to other areas of the
structure. On the Oresund bridge is the interior of
the truss structure protected from corrosion by
dehumidification, on the Akashi suspension
bridge in Japan are the main cables protected
against corrosion by dehumidification.
Dehumidification of main cables has been
introduced on the Aquitaine Suspension bridge in
France and on the Little Belt Supension Bridge in
Denmark in connection with rehabilitation of the
bridges. Stay cable suppliers are currently
developing a concept where stand cables can be
protected by dehumidification.
A rational approach to concrete durability -
DuraCrete - has been developed through a
substantial research project financed by the
European Community. The philosophy is a
prediction of time to depassivation of the
reinforcement due to chloride ingress using
probabilistic models. The durability of the
concrete structure is thus reliant on concrete cover,
the permeability of the concrete (chloride
diffusion) and the aggressivity of the surroundings
(chloride content).
The use of stainless steel reinforcement in
critical areas of the structure subjected to a harsh
environment is becoming increasingly common.
On Stonecutters Bridge in Hong Kong stainless
steel is used for the outer layer reinforcing bars in
the towers.
5. Probabilistic methodsIn general, probabilistic methods are gaining
Figure 6. Visualisation of simulated flow(Busan-Geoje Fixed Link)
55| Feature Article |
Trends in Design and Construction of Long Span Bridges
more and more momentum in design of bridges.
In addition to durability calculations, probabilistic
methods are also used to establish ship collision
loading. Based on scenarios for the ship traffic,
assumptions and distributions of the navigation of
ships passing the bridge and capacity of the
structures, the probability of collapse can be
determined. AASTHO requires that the
probability of failure due to ship collision shall
correspond to a return period of 10.000 years.
Using this method it is possible to quantify and
take advantage of risk mitigating measures as for
instance use of pilots and surveillance systems in
the calculations. Furthermore, the design can be
optimised by for instance accepting higher risk in
case of poor foundation conditions against
reducing the risk elsewhere. The basis for the ship
collision loading for Busan-Geoje Fixed link has
been established on this basis.
Probabilistic methods are also used in
reassessment of remaining structural service life in
connection with rehabilitation.
. Development in Construction
Fabrication and erection of the major bridges
projects is characterised by off-shore/off-site
prefabrication, large transport distance and
erection of large elements. For the Great Belt
West Bridge altogether 324 pre-fabricated units,
comprising 62 caissons, 124 pier shafts and 138
bridge girders were cast in a pre-fabrication yard
close to the bridge site. The elements were cast in
five production lines and moved on sliding
surfaces by pushing units to the load-out jetties,
where they were lifted off by a large purpose-built
heavy lift crane vessel, the Swan, for further
transportation and installation at the bridge site.
Caissons, weighing up to 7,400 tonnes, were
placed by the Swan on 1.5 m thick crushed stone
foundation beds.
For the Oresund Link between Denmark and
Sweden, fabrication of the steel trusses for the
Oresund Bridges as well as casting of the concrete
deck was carried out in Spain. The complete 140 m
long girder sections, weighing up to 7,000tonnes,
were tugged on flat barges to the bridge site and
Figure 7. Pre-fab Yard for Great Belt West Bridge
Figure 8. Pylons for Busan- Geoje Fixed Link
โฅ
56 | Vol.53 No.6 June, 2005 |
Construction and Technology of Long Span Bridges
lifted into position on the piers by the Swan, the
vessel used for the Storebรฆlt West Bridge. In
between the job on the two Danish bridges, The
Swan has been used to erect the 13km Prince
Edward Island Bridge in Canada after being
modified and having the lifting capacity increased
to 8,700 metric tons.
On the cable-stayed bridge the girder was also
erected in 140m sections on temporary supports
before being suspended by the stays. This method
is unusual for a cable-stayed bridge, but was
attractive due to the availability of the heavy lift
vessel, and it reduced the construction.
For the Busan Geoje Fixed Link it is envisaged to
have caissons, pier shafts and bridge girders for the
approach bridge prefabricated of site and transported
to the site assisted by a large floating crane.
The advantage is a rational industrialised
production in the prefabrication yard, where the
quality more easily can be controlled. Furthermore,
the production is less susceptible to adverse
weather conditions and transport of equipment and
labour to the site can be saved.
. Conclusion
The trends and tendencies in design and
construction of major bridges seem to be
developing in more or less in the same direction
world wide. Because of the size and the
frequency of the projects, it is common early in
the planning process to screen recent similar
projects.
There seems to be a development in the way the
project are procured from traditionally separate
design and construction typically controlled by a
public client, towards design-built project and
BOT projects, where more and more responsibility
is left with the contractor/concessionaire.
Because of the landmark value of these major
projects, there is a tendency towards increased
focus on aesthetics. For the Stonecutters Bridges,
the design was developed though an international
design competition and for the Busan-Geoje
Fixed Link, a special effort was made to give the
bridges an appearance, which would make the
bridges stand-out and which would associate the
bridges with Busan and Geoje Island and vice
versa.
๊ธฐํ : ์ ์๋ด ํธ์ง๊ฐ์ฌ์ฅ [email protected]
57| ๊ธฐํ๊ธฐ์ฌ |
. ๋จธ๋ฆฌ๋ง
์ผ์ด๋ธ๊ต๋์ ์ค๊ณ์ ์๊ณต์ ๋๋ถ๋ถ ๊ณผ๊ฑฐ์ ๊ฒฝํ์๊ทผ๊ฑฐํ๋ฉฐ, ์๋ก์ด๊ต๋์ค๊ณ์์์ ํ๋ก์ ํธ๋ก๋ถํฐ ๋ถ์๋ ์ฅ๋จ์ ๊ณผ ์๋ก์ด ์์ด๋์ด๊ฐ ์ ์ ํ๊ฒ ๋ณํฉ๋๋ค. ์ฅ๋๊ต๋์๊ฐ๋ ์์ ์ฌํ ์ง๋ผ๋, ๋ชจ๋ ํ๋ก์ ํธ๋ ๊ฐ๋ณ์ ์ผ๋ก ์ง์ญ์ ํน์์ ๋ง์ถ์ด ์ค๊ณ๋์ด์ผ ํ๋ค. ์ ์ค ์ฅ๋๊ต๋์ ์๊ฐ ์๋์ ์ผ๋ก ์ ๊ธฐ ๋๋ฌธ์, ํ ์ฐ์ ์ ๋นํด ์ฑ์ฅ์๋๊ฐ ๋๋ ์๋ ์์ง๋ง๊ต๋ ํ๋ก์ ํธ์ ์ฐ์ ๋ฐ์ ์ ๋ํ ๊ธฐ์ฌ๋๋ฅผ ๊ฒฐ์ฝ ๊ฐ๊ณผํ ์ ์๋ค. ๋์ฑ์ด, ๊ต๋์ ๊ฑด์ค์ ๋์ฒด์ ์ผ๋ก ๋๊ท๋ชจ์ ํฌ์๋ฅผ ์๋ฏธํ๊ณ , ์ ํด์ง ๊ธฐ๊ฐ๋ด์ ์์ ์๊ณต์ฌ๋ถ๊ฐ ํ๋ก์ ํธ์ ์ฑ๊ณต์ฌ๋ถ๋ฅผ ์ข์ฐํ๊ธฐ์, ํ์ ์๋ํ ์์ง๊ฐ ๋๋ก ์ข์ ๋๊ธฐ๋ ํ๋ค. ์ค๊ณ์ ์๊ณต๊ธฐ์ค์ด ๋๋ ๊ตญ๋ด ๋๋ ๊ตญ์ ๊ท์ ์ ๋๊ฐ ๋น๋ฒํ ์ ์ถ๋๋ ์๊ท๋ชจ ๊ต๋์ ์ ํฉํ๊ฒ ์ ์ ์ด ๋๋ฉฐ, ์ต๊ทผ์์ ๋ณด ๋๋ ์ง์์ ๊ตญ๋ด์ธ ๊ท์ ์ ๋ฐ ํ๊ธฐ๊น์ง ์๊ฐ์ด๊ฑธ๋ฆฐ๋ค. ๋ณธ๊ณ ์์๋์ฌ์ฅ๊ต์ํ์๊ต์์ต์ฒจ๋จ์ค๊ณ๋ฐ์๊ณต์๊ดํ๋ํฅ์๋ด์๋ด๊ณ ์ํ๋ค.
๊ต๋ ํ์
์ผ์ด๋ธ๊ต๋์๊ธฐ๋ณธ์ ์ผ๋ก์ฌ์ฅ๊ต์ํ์๊ต๋ก๋๋์ด์ง๋ค. ํ์๊ต๋์ค๊ณ์์๊ณต์ด150๋ ์ด์์ด๋ฃจ์ด์ก์ง๋ง, 20์ธ๊ธฐ์ค๋ฐ์ด๋์ฑํ๋์ฌ์ฅ๊ต๋์ด์๋นํด๋น๊ต
์ ์๋ก์ด๊ฐ๋ ์๊ต๋์ด๋ค. ํ์ ์ํ์๊ต๋์ฃผ์ผ์ด๋ธ๋ก๋ถํฐํ์ด์์ํด์ฐ๊ฒฐ๋๊ต๋๊ฑฐ๋๊ฐ์๊ณ , ๊ต๋๊ฑฐ๋๋์ฃผ๋ก์ฐจ๋ํตํ๋ง์์ ๊ณตํ๋์ญํ ์์ํํ๋ค. ํ์ค์์งํฑํ๋์ฃผ์์์์๋์ฃผํ, ์ต์ปค๋ธ๋ก๊ณผ์ฃผ์ผ์ด๋ธ์ด์๋ค. ์ฃผ์ผ์ด๋ธ์๊ฐ์ฌ๋์๊ฒฐ์ ํ๋์ฃผ์๋ณ์์ธ์๊ทธ(sag)๋์ผ๋ฐ์ ์ผ๋ก1 : 9์1 : 11 ์ฌ์ด์๋น์จ๋ก์ค์น๋๋ค. ํ์๊ต๋์ต์ปค์์ฃผํ์๋จผ์ ์ค์นํํ์์ฃผ์ผ์ด๋ธ์์ค์นํ๋ฉฐ, ์ฃผ์ผ์ด๋ธ์๋งค๋ฌ์๊ต๋๊ฑฐ๋๋ฅผ๋ง์ง๋ง์ผ๋ก๊ฑด์คํ๋ค. ์ฌ์ฅ๊ต๋์ผ๋ฐ์ ์ผ๋ก์ฃผํ์๋จผ์ ์ค์นํ๊ณ , ์ฃผํ์์์ผํธ๋ ๋ฒ๊ณต๋ฒ์ผ๋ก๊ต๋๊ฑฐ๋๋ฅผ์ค์นํ๋๊ณต๋ฒ์๋ฐ๋ฅธ๋ค. ๊ต๋์๋ถ์ฃผํ์๋์ด๋์ฃผ๊ฒฝ๊ฐ์1/5๋ฐฐ์ด์์ด์ด์ผํ๋ค. ์ฌ์ฅ๊ต์๊ต๋๊ฑฐ๋๋์ผ์ด๋ธ์ฅ๋ ฅ์ ์ํ๋ถ๋ ฅ์ ๋ถ๋ดํ๋ ์์ถ๋ถ์ฌ๋ก์จ ํ์ฉ๋๋ค.ํ์๊ต์์ฌ์ฅ๊ต์์ฐจ์ด์ ์์์ฝํ๋ฉด๋ค์๊ณผ๊ฐ๋ค.- ํ์๊ต์ ๊ฑด์ค์ ๊ธด ์๊ณต๊ธฐ๊ฐ ๋์ ๊ฑฐ์ ๋ชจ๋
๋จ๊ณ๊ฐ์ฃผ์๊ณต์ ์ผ๋ก์์ฐจ์ ์ผ๋ก์งํ๋๋ค.- ํ์๊ต๋ ์๊ณต๊ธฐ๊ฐ์ด ๊ณ ๋ ค๋์ด์ผ ํ๊ณ ๊ฐ๋น์ผ
์ต์ปค๊ตฌ์กฐ๋ฌผ์ํ์๋กํ๋๋ฐ๋ฉด, ์ฌ์ฅ๊ต๋๊ต๋๊ฑฐ๋๋ฅผ ์ผ์ด๋ธ ์ํํ์ค์ ๊ท ํ์ ์กฐ์ ํ๋๋ฐํ์ฉํ๋ค.
- ์ฃผํ์๋์ด์๊ฒฝ๊ฐ์๋น์จ๊ฐ์๋ก์ธํ์ฌ, ํ์๊ต์์ฌ์ฉ๋๋์ผ์ด๋ธ๊ฐ์ฌ์์์ด์ฌ์ฅ๊ต์๋นํดํ์ ํ๋ง๋ค.
์ฃผ์ผ์ด๋ธ์์ ์ฐฉํ๊ธฐ์ํน๋ณํ๊ฒ์ ํฉํ์๋ฐ์กฐ๊ฑด์ด๋ฐ๊ฒฌ๋์ง์์์ด์, ๊ฐ๋ฅํ๋ฉด์ฌ์ฅ๊ต๋ฅผ๊ฑด์คํ๋
์ฅ๋๊ต๋ ๊ฑด์ค ๋ฐ ๊ธฐ์
| ์ฝ ๋ ฅ |
๋ด๋งํธTechnical University ์กธ์
๋ด๋งํธCOWI A/S ์ฝํํ๊ฒ๋ณธ์ฌ๊ต๋๋ถ์ ์ฌ
๊ฑฐ๊ฐ๋๊ต์๊ต๋์ค๊ณ๋ถ๋ถํ๋ก์ ํธ๋งค๋์
Lars HAUGEChief Project Manager, COWI A/SLyngby, [email protected]
58 | ์ 53๊ถ ์ 6ํธ 2005๋ 6์ |
์ฅ๋๊ต๋ ๊ฑด์ค ๋ฐ ๊ธฐ์
๊ฒ์ด ๊ฒฝ์ ์ ์ผ๋ก ์ ๋ฆฌํ๋ค. ํ์ง๋ง, ์ฃผํ์ ๋์ด์์ ํต์ ์ธ ์๊ณต๋ฐฉ๋ฒ์ ๊ณ ๋ คํ๋ฉด ์ฌ์ฅ๊ต์ ๊ธธ์ด์๋ํ๊ณ๊ฐ์๋ค. ์ฌ์ฅ๊ต์๋น๊ตํดํ์๊ต์๊ฒฐํจ์์ํ์ํค๊ธฐ์ํ๋ ธ๋ ฅ์๊ณ์๋์ด์๋ค. ์ต์ปค๋ธ๋ญ๊ตฌ์กฐ๋ฌผ์ ๋์ ํด ์์ ์ ํ์๊ต๊ฐ ์ค๊ณ ๋ฐ ์๊ณต๋์๊ณ , ์ฃผ์ผ์ด๋ธ์ ์ํํ์ค ์ฑ๋ถ์ ๋ถ๋ดํ๊ธฐ ์ํด ๊ต๋๊ฑฐ๋๋ฅผ์ฌ์ฉํ ๋ค. ๊ทธ๋ฌ๋์ด๋ฌํ๋ฐฉ๋ฒ์๋ฌธ์ ์ ์๊ต๋๊ฑฐ๋๊ฐ ์ผ์ด๋ธ์ด ์ค์น๋๊ธฐ ์ ์ ๊ฐ์ค์ง์ง๊ตฌ์กฐ๋ฌผ์๋จผ์ ์ค์น๋์ด, ๊ฒฐ๊ณผ์ ์ผ๋ก ์๊ณ๊ฒฝ๋ก์ ๊ต๋๊ฑฐ๋๊ฐ์ถ๊ฐ๋๋ค๋๊ฒ์ด๋ค. ์์ ์ํ์๊ต์์๋ก์จ, ํ๊ตญ์์ข ๋๊ต๊ฐ์๋ค. ์ข ๋๊ต๋๋ณดํต๊ธธ์ด์๊ฒฝ๊ฐ์๊ฐ
์ง ๊ต๋์ผ๋ก, ๋์ฉ๋์กฐ๊ฑด์ผ๋ก ์ธํ ์์ถํ์ค์ ๊ฒฌ๋์ ๋๋ก์ถฉ๋ถํํฐ๊ต๋๊ฑฐ๋๋ฅผ๊ฐ์ง๊ณ ์๋ค.
1. ํ์๊ตํต์์ ์ผ๋ก ์ต์ปค๋ธ๋ก๊ตฌ์กฐ๋ฌผ๋ก ์ด๋ฃจ์ด์ง ํ์๊ต๋
ํ์ํ๊ฒฝ๊ฐ์ด์ฌ์ฅ๊ต๊ฐ์์ฉํ ์์๋๊ฑฐ๋ฆฌ์์ด์์ผ๋๋ง ๊ฑด์ค๋๋ค. ์ฃผ๊ฒฝ๊ฐ์ ํ๊ณ๋ ๋ณดํต 1200~1400m์ด์ง๋ง, 50๋ ์ ์๋ 600~700m์ด์๋ค. ์ต๊ทผ์๊ฑด์ค๋์ฅ๋ํ์๊ต์์๋์ผ๋ณธ์Akashi Kaikyo(์ฃผ๊ฒฝ๊ฐ1990m), ๋ด๋งํฌ์ Great Belt East ๊ต(์ฃผ๊ฒฝ๊ฐ1624m), ํ์ฝฉ์Tsing Ma ๊ต(์ฃผ๊ฒฝ๊ฐ 1377m), ๊ตญ์Humber ๊ต(์ฃผ๊ฒฝ๊ฐ 1424m), ์ค์จ๋ด์ High CoastBridge(์ฃผ๊ฒฝ๊ฐ1210m) ๋ฑ์ด์๋ค. High Coast Bridge๋์ฃผ์ผ์ด๋ธ์ค์น์๋งค์ฐ์ ํฉํ๊ธฐ์ด๊ณต์ฌ์กฐ๊ฑด์ผ๋ก์ธํด, ๋น๊ต์ ์งง์๊ฒฝ๊ฐ์ผ์ง๋ผ๋๊ฒฝ์ ์ ์ผ๋ก๋์ต์ ํํ๋ค. ํ์ฌ๊ฒฝ๊ฐ์๋์ฑ๊ธธ๊ฒ๊ฑด์คํ๋ ค๋์ถ์ธ์ด๋ฉฐ, ํ
๊ธฐ์ ์ธ ๋์ฝ์ผ๋ก์จ 3,300m ๊ฒฝ๊ฐ์ ์ดํ๋ฆฌ์์Messina Strait๋ฅผ ๊ฐ๋ก์ง๋ฅด๋ ๊ต๋์ด ๊ณํ๋๊ณ ํ์ฌ(2005๋ ๋ด/์ฌ๋ฆ) ์ ์ฐฐ์ค์ด๋ค. ํ์๊ต๋๋๋ก ์งง์๊ฒฝ๊ฐ์ผ๋ก ์๊ณต๋๊ธฐ๋ ํ๋๋ฐ, ๊ทธ ์ด์ ๋ ์๊ณต๋น์ฉ๊ณผ ์๊ณต๊ธฐ๊ฐ์๋ฐฐ์ ํ๊ธฐํ๋ค๋ฅธ์ด์๋๋ฌธ์์ค๊ณ๋๋๊ฒฝ์ฐ๋ค. ์๋ก์จ, ๋ฏธ๊ตญ์ East Bay Bridge, ๊ตญ์Millennium Bridge์ํ๊ตญ์ ์ข ๋๊ต๋ฑ์ด์๋ค. ์ด๋ฌํ์ผ๋ฐ์ ์ธ์์น์์์ธ์ ์ธ์๋ก์จํ๊ตญ์๊ด์๋
๊ต์๋ฏธ๊ตญ์Carginez ๊ต๋ฑ์์๊ผฝ์์์๋ค.
2. ์ฌ์ฅ๊ต์ฌ์ฅ๊ต๋ํฌ๊ฒ์๊ฒฝ๊ฐ, ์ค๊ฒฝ๊ฐ, ์ฅ๋๊ฒฝ๊ฐ๊ต๋์ผ๋ก๋
๋์ด์ง๋ค. 1990๋ ์ค๋ฐ์์์ฑ๋800m ์ด์์์ฃผ๊ฒฝ๊ฐ๋๊ต๋ก์จ ํ๋์ค์ Normandy Bridge(์ฃผ๊ฒฝ๊ฐ 856m)์์ผ๋ณธ์Tatara Bridge(์ฃผ๊ฒฝ๊ฐ890m) ๊ฐ์์ผ๋ฉฐ, ์ด๋ค์ ๋์๊ฐ ํ์ฌ ๊ฑด์ค์ค์ธ ํ์ฝฉ์ StonecuttersBridge(์ฃผ๊ฒฝ๊ฐ1018m) ์์ค๊ตญ์Sutong Bridge(์ฃผ๊ฒฝ๊ฐ1018 m) ๋ฑ์ฅ๋๊ฒฝ๊ฐ๊ต๋์๊ฑด์คํ๋๊ณ๊ธฐ๋ฅผ๋ง๋ จํ๋ค. ์๋ชจ๋ ๊ต๋์๋นํ๊ฐ์ฑ์์ฆ๊ฐํ๊ธฐ์ํด์ฃผ๊ฒฝ๊ฐ์ ํํ ๊ฐ๋ฐ์ค๊ฑฐ๋๋ก ์ค์นํ ์ผ๋ฉฐ, ๋ชจ๋ ์ฅ๋์ฌ์ฅ๊ต๋์ผ๊ฐ์ผ์ด๋ธ์์คํ ์ผ๋ก์ค๊ณํ ๋ค.์ผ์ด๋ธ์ ๋ฐฐ์น ๋ฐ ๋ฐฐ์ด์ ์ฅ๋์ฌ์ฅ๊ต๋ฅผ ๊ฑด์คํจ์
์์ดํนํ์ค์ํ๋ค. Aํ์ฃผํ์Hํ์ฃผํ์๋นํด์๊ณํ์์ 20%๊น์ง ์ฆ๊ฐ์ํจ๋ค. ํ๊ตญ์์ ํ์ฌ ์ค๊ณ๋๊ณ ์๋์ 2 ์ข ๊ต์์ค๊ตญ์์ 2 Nanjing YangtzCrossings ๊ต๋์ผ๊ฐ์ผ์ด๋ธ์์คํ ๋ฐ ํํ๊ฐ๋ฐ์ค๊ฑฐ๋๋ฅผ์ด์ฉํ๋ค. ์ฅ๋์ฌ์ฅ๊ต์๊ฐ์ฅ์ค์ํ๋ณ์์คํ๋๋ํญ-๊ฒฝ๊ฐ๋น์ด๋ค. ๊ฒฝ๊ฐ์ดํญ์40๋ฐฐ์ด์์ธ๊ต๋์ผ๋กํ๋์ค์Normandy Bridge ๊ฐ์ฌ์ ํ์ธ๊ณ์์๊ฐ์ฅํญ์ด์ข์๊ต๋์คํ๋๋ก๊ผฝํ๋ค.์ต๊ทผ ๋ค์ด, 400~600m ์ฃผ๊ฒฝ๊ฐ์ ๋๋ก๊ตํต์ฉ ์ฌ์ฅ
๊ต๊ฐ๊ฑด์ค๋๊ณ ์๋ค. ์๊ธฐ๋ฒ์์๊ฒฝ๊ฐ์์์๋๋๊ณต์ฌ๋น์ฉ๊ณผ๊ธฐ๊ฐ์์ต์ ํํ๋๋ฐฉ์์ผ๋ก์จ๊ฐ๋ฐฉํํ๋ ์ดํธํฉ์ฑ๊ฑฐ๋์์ฝํฌ๋ฆฌํธ์ฃผํ์ด๋ถ๊ฐ๋๊ณ ์๋ค. ์ด๋ฌํ ํ์์ ๊ต๋์ผ๋ก๋ ๋ค์ ์๊ฐ ์๋ค: ์บ๋๋ค์Alex Fraiser Bridge, ๊ตญ์ ์ 2 Severn Bridge ์Dartfold Bridge, ํ๊ตญ์ ์ํด๋๊ต์ ์ผ์ฒํฌ๋๊ต, ์ค์จ๋ด์ Uddevalla Bridge, ํ๊ตญ์ Rama 8 Bridge(Mono Tower Bridge), ์ค๊ตญ์Yangpu ๊ต, XuPu ๊ต,Ching Chau Min Yang ๊ต. ์ด๋ค๊ณผ๋์ผํ๊ต๋ํ์์ธํ๊ตญ์๊ฑฐ๊ฐ๋๊ต์๋ฏธ๊ตญ์Cooper River Bridge๋ํ์ฌ ๊ฑด์ค ์ค์ ์๋ค. ์ฃผ๊ฒฝ๊ฐ์ด 600m(ํํ์ง์ญ์500m)์ด์์ผ์, ์์๊ฐ์ํ์์๊ต๋์๋ฐ๋์์
59| ๊ธฐํ๊ธฐ์ฌ |
์ฅ๋๊ต๋์ ์ค๊ณ ๋ฐ ์๊ณต ๋ํฅ
ํํ๋ฌํฐ์์ ์ฑ์์ถฉ์กฑ์ํค๋๋ฐ์ด๋ ค์์ด์๋ค.๋ค์ํ ์ด์ ๋ก ์ธํด ๋ง์ ์๊ฒฝ๊ฐ ์ฌ์ฅ๊ต๊ฐ ๊ฑด์ค๋
๊ณ ์๋๋ฐ, ์ฌ์ฅ๊ต๊ฐ ๊ฐ๋ ๊ธฐ๋ ๋น์ ์์ง์ฑ๋ ๊ทธ ์ด์ ์ค์ํ๋์ด๋ค. ์ต๊ทผ์๋๋ค๊ฒฝ๊ฐ์ฌ์ฅ๊ต๋ฅผ๊ฑด์คํ๋ ์ถ์ธ์ด๋ค. ํ์ฝฉ์์๋ 1998๋ Ting Kau Bridge๊ฐ ์๊ณต๋์๊ณ , ๊ทธ๋ฆฌ์ค์ Rion-Antirion Bridge์ํ๋์ค์ Viaduc de Maillot ์ด ์ต๊ทผ์ ์๊ณต๋์๋ค.๋ค๊ฒฝ๊ฐ ์ฌ์ฅ๊ต๋ ํํ๋ก์จ ํ๊ตญ์๋ ๊ฑฐ๊ฐ๋๊ต๊ฐ ์๊ณต๋ ์์ ์ด๋ฉฐ. ์น ๋ ์ Chacao ํดํ์๋ ๋ค๊ฒฝ๊ฐ ํ์๊ต์๊ฑด์ค์ด๊ณ ๋ ค๋๊ณ ์๋ค.
. ์ค๊ณ์ ๋ฐ์
1. ์ฐ๊ฒฐ๋ถ์ ๋ฐ์ โ โ ์ฌ์ฌ์ฅ์ฅ๊ต๊ต์ง์ง๋ฐ์์ ๊ต๋์ด ์ง์งํ์ค์ ์งํฑํ๋๋ก
STU(Shock Transmission Units)์ ๊ฐ์ ํํ์์ ์์ฅ์น๋ค์ด ์ฌ์ฉ๋๋ค. ์ฌ์ฉ๋๋ฉฐ, ๊ต๋์ ์ง์ง์กฐ๊ฑด์ ์กฐ์ ํ๊ธฐ ์ํด์๋ ์ ์์ฅ์น๊ฐ ์ ์ฉ๋๋ ์ถ์ธ๋ค.๋จ์ผ๋จ๋ฉด์ผ์ด๋ธ์ฌ์ฅ๊ต์ธFaroe Bridge ๊ฒฝ์ฐ, ๊ต๋๊ฑฐ๋๋ ์ธก๋ฐฉํฅ์ผ๋ก๋ง ์ง์ง๋๊ณ , ๋นํ์ ์ฃผํ์์ ๋ฐ์์ฃผ๋ฉฐ, ๊ต๋๊ฑฐ๋๋ ์์ง์ผ๋ก๋ ์์ ๋กญ๊ฒ ์์ง์ผ ์์๋ค. ์ ์ ์์คํ ์ ๊ต๋๊ฑฐ๋์ ์ ์ธก๋ฉด์ ์ ์ํผ์คํค์์ฌ์ฉํ์ฌ์ป์ด์ก๋ค.Stonecutter Bridge์ ๊ฒฝ์ฐ, ์จ๋๋ณํ๋ก ์ธํ ๋
๋ฆฐ ๊ฑฐ๋์๋ ๊ต๋๊ฑฐ๋๊ฐ ์์ ๋กญ๊ฒ ์์ง์ด๋๋ก ํ ๋ฐ๋ฉด, ๋์ ํํ์ค๊ณผํํ์ค์ผ๋ก์ธํ๋น ๋ฅธ๊ฑฐ๋์๋๊ต์ถ๋ฐฉํฅ์ผ๋ก ์์ง์์ด ๊ตฌ์๋๋๋ก ํ ๋ค. ๊ต๋๊ฑฐ๋๊ฐ ์ฃผํ์ ์ํด ์ง์ง๋์ง ์๋๋ค๋ฉด ๋์ ํํ์ค์ผ๋ก์ธํ์ฌ ์ธก๊ฒฝ๊ฐ์ ๊ต๊ฐ์ ๊ณผํ์ค์ด ๋ถ๊ฐ๋๋ฉฐ, ๋ฐ๋ฅํ์ด ์์ ํ ๊ณ ์ ๋๋ค๋ฉด ์จ๋์ ํฅ์ผ๋ก ์ธํ์ฌ ์ฃผํ์๊ณผํ์ค์ด๋ถ๊ฐ๋ ๊ฒ์ด๋ค. Sutong Bridge์์๋ ๊ต์ถ๋ฐฉํฅ ์์ง์์ด ์ฃผํ์์
์๋์ ๋ฐ๋ผ ๋ณํ๋ ์ ์๋ํผ์ ์ํด ์ต์ ๋๋ค.(F=3750ยทV 0.4 ) ๊ต๋๊ฑฐ๋๋์ฃผํ์์์์ง๋ฐฉํฅ์ผ
๋ก๊ตฌ์๋์ง์๋๋ค. ์๊ต๋๋ค์๋๋ค๋ฅธํน์์์ฃผํ์์์์ง๋ฐ์นจ์ด์๊ธฐ์์ฃผํ์hard point๊ฐ์ ๊ฑฐ๋ ์์๋๋ฐ๋ฉด, ํฐ๋ชจ๋ฉํธ๋ฅผ์ ๋ฐํ ์๋์๋ค. Normandy๋๊ต์๊ฒฝ์ฐ, 116m ์ฝํฌ๋ฆฌํธ์บํธ๋ ๋ฒ๋ฐ๊ฑฐ๋์์ฃผํ์ฌ์ด์ ์ผ์ฒด์์ด์์ ๊ธฐ์กด์ ๋ฐฉ์๊ณผ๋ ๋ฌ๋ผ ๋ณด์ด์ง๋ง,์ด๊ต๋์๋ณด๋ค์์ธํ์ฐ๊ตฌํด๋ณด๋ฉด์คํ๋ ค์ด๋ฌํ๋ฐฉ์์ด๊ต๋์์ ๋ฆฌํ๋ค๋๊ฒ์์์์๋ค.์๊ณต๊ธฐ๊ฐ๋์, ๊ฑฐ๋์๊ฐ์ฌ๋ถ๋ถ์์ฃผํ์ด์๋์ฃผ
๊ฒฝ๊ฐ์ผ๋ก116m ๋จ์ด์ง์ง์ ์์์ง์ง๋๋๊ฒ์ฒ๋ผ๊ฑฐ๋ํด์ ์ฒ์ง์ด ๊ฐ์๋์๋ค. ์์ ๊ตฌ์์์คํ ์ด ๊ฐ๋ฅํ๋ ์ด์ ๋ ์ฃผํ์ด ์ ์ฐํ ๋ง๋๊ธฐ์ด์ ์ง์ง๋์๊ณ ,๋ฐ๋ฅํ์๊ณก๋ฅ ์ด์ปธ๊ธฐ๋๋ฌธ์ด๋ค.โกโกํํ์์๊ต๊ต์ ํต์ ์ผ๋กํ์๊ต๋์ ์ถ์ด์๊ณผ์ฃผํ์์ง์ง์์
ํด 3๊ฒฝ๊ฐ๊ตฌ์กฐ๋ก์ค๊ณ๋๋ค. ๊ฒฝํ์์ํ๋ฉด์ด๋ค๋ถ์์๋ํ๊ด๋ฆฌ๊ฐ์ ์ฒด์ ์ง๊ด๋ฆฌ๋น์์๋นํ๋ถ๋ถ์์ฐจ์งํ๋ค. ๋ฐ๋ผ์์ผ์ด๋ธ์ง์ง๊ตฌ๊ฐ์ ์ฒด์์์ฐ์์ธ๊ฑฐ๋์์คํ ์ด ์ ํธ๋๋ฉฐ ์ด๋ ๋ด๋งํฌ์ Great BeltEast Bridge ์์ค์จ๋ด์High Coast Bridge ์์ฌ์ฉ๋์๋ค. ์ฃผํ์๊ดํตํ๋์ฐ์ํ๊ฑฐ๋์์๊ทน๋ณตํด์ผํ ํ๋์ ๋ฌธ์ ์ ์ ์ผ์ด๋ธ ์๋ค๋ด ์ฃผ์ผ์ด๋ธ์ ๊ฐํ์ ์ผ๋ก ์ธํด ๋ฐ์ํ๋ ํจ๋ชจ๋ฉํธ์ ์กฐ์ ํ๋ ๊ฒ์ด์๋ค. ์ผ์ด๋ธ์ด ์ฒ์ง๊ฒ ๋๋ฉด ๊ฑฐ๋๋ ๋ฐ๋ผ ์ฒ์ง๊ฒ ๋๊ณ ,์ด๋ ํจ๋ชจ๋ฉํธ๊ฐ ๋ฐ์ํ๊ธฐ ๋๋ฌธ์ด๋ค. ๊ณ ์ ํ์ค๊ณผ ํํ์ค์ผ๋ก์ธํด๋ฐ์ํ๋๋ชจ๋ฉํธ๋ฅผ์ต์ํ์ํค๊ณ , ๋ฐ์นจ์ํ๋ฅผ์ต์ ํํ๊ธฐ์ํดํ์ด๊ฑฐ๋ฆฌ์๋ณ์๋ถ์์ฐ๊ตฌ, ํ์ด์ ์ข ๋ฅ (locked ์ฝ์ผํ ๋๋ ํํํ ์ฒ ์ ),ํ์ดํ์ค์์กฐ์ , ๊ฑฐ๋์๊ฐ๋, ์ฃผํ์์์์์งํ์ค์์ง์งํ๊ธฐ์ํ๊ฑฐ๋์์ํ๋ฑ์ด๊ณ ๋ ค๋์๋ค.
2. ํํ ๋ฐ์ค๊ฑฐ๋์ ๊ฐ๋ ํํ๊ฐ๋ฐ์ค๊ฑฐ๋๋1960๋ ๋๋ด๋งํฌ์Little Belt
Bridge์ ๊ตญ์Severn ํ์๊ต์์์ต์ด๋ก๋์ ๋๊ฐ๋ ์ด๋ค. ํํ๋ฐ์ค๊ฑฐ๋์์ฅ์ ์๋นํ๊ฐ์ฑ์ด๋์๊ฒ๊ณผ๋น๊ต์ ๋จ์ํ์๋ํ๋์กฐ๋ฆฝ๊ณผ์ฉ์ดํ์ ์ง๊ด๋ฆฌ์
60 | ์ 53๊ถ ์ 6ํธ 2005๋ 6์ |
์ฅ๋๊ต๋ ๊ฑด์ค ๋ฐ ๊ธฐ์
์๋ค. ์ฌ๋ฌ๊ฐ์๋ชจ์๋ฆฌ์์ธ๋ถ๋ ธ์ถ๋ฉด์ ์ด๋์๋ณต์กํํํ์๊ตฌ์กฐ๋ฌผ์์ฝ๊ฒ๋ ธํํ๋๋ฏ๋ก, ํํ๊ฐ๋ฐ์ค๊ฑฐ๋์ฒ๋ผ์ต์ํ์๋ ธ์ถ๋ง์ํ์ฉํ๋๊ฐ๋จํ๊ตฌ์กฐ๋ฌผํํ๊ฐ์ ํธ๋๋ค. ๋งค๋๋ฌ์ด์ธ๊ณฝํ๋ฉด์์ธ๋ถ์์ต์ํ์ผ๋ก๋ ธ์ถ์ด๋์ด์ ์ง๊ด๋ฆฌ๊ฐ์ฉ์ดํ๋ค. ๋ฐ์ค๊ฑฐ๋์๋ด๋ถ๋๋ณด๊ฐ์ฌ๊ณผ๊ฒฉ๋ฒฝ์ผ๋ก์ด๋ฃจ์ด์ ธ๊ฐ์ฌ๋ฉด์ ์์ด80% ์ ๋๋ฅผ์ฐจ์งํ๊ณ ์์ผ๋ฉฐํ์ต์๋ถ์์๋ฐฉ์งํ๊ธฐ๋๋ฌธ์๋์์ํ ํ์๊ฐ์๋ค. ํ์ต์์๋ฆฌ๋๋ฐ์ค๋ด๋ถ์์๋์ต๋๋ฅผ 40% ์ดํ๋ก ๋ด๋ฆฌ๊ณ , ๋ถ์์ด ๋ฐ์ํ ์ ์๋ํ๊ณ๋ง์ง์60% ์ ๋๊น์ง์ ์ง์ํค๋๊ฒ์ด๋ค. ์ด๋ฅผ์ํด์ ๋ด๋ถ์๊ณต๊ธฐ๋ฅผ์ํ์ํค๋๊ฐ๋จํํํ์์คํ ๊ณผ์ต๊ธฐํก์ํํฐ๊ฐ์ฅ์ฐฉ๋ํ์ต๊ธฐ๋ฅผ์ค์นํ๋ฉด๋๋ค.
ํํ๊ฐ๋ฐ์ค๊ฑฐ๋๋๊ณต๊ธฐ์ญํ์ ํจ์จ์ฑ๋ํ์ํ๋ค. ๋์ ๋นํ ๊ฐ์ฑ์ ์๊ณ ํ๋ฌํฐํ์์ ์ฆ๊ฐ์ํค๋ฉฐ, ๊ณต๊ธฐ๋ ฅ๊ณ์์๊ทธ๊ธฐ์ธ๊ธฐ๋ฅผ์ค์ฌ์ํํ์คํจ๊ณผ๋ฅผ๊ฐ์์ํจ๋ค.
3. ๊ณต๊ธฐ์ญํ(Aerodynamic)๋ฏธ๊ตญTacoma Narrows ํ์๊ต์๋ถ๊ดด๋์ฅ๋๊ต๋
์์ค๊ณ์์๊ณต๋ฐ์ ์์นจ์ฒดํ์์์ด๋ํ ๋ค. ์ดํ์ฌ๊ณ ์ ๋ผ์ ๋ฆฐ ๊ฒฝํ์ ๋ฐํ์ผ๋ก ๊ฑด์ค๋ ๊ต๋์๋ ๋๊บผ์ด๊ฐํธ๋ฌ์ค๊ฑฐ๋๊ฐ์ฌ์ฉ๋์๊ณ , ์์ธก๋ถํํ์ง๋์๊ทผ์๊น์ง์ฒ ์ ํ์กฐ์ฌ๋์๋ค. ํ์ฌํ๋์คํ์๋ชจ๋ ์ฅ๋๊ต๋์ค๊ณ์์์ด๊ธฐ๋ณธ์ด๋ฉฐ, ๊ต๋๊ฑฐ๋์๋ถ๋ถ๋ชจํ์คํ๋ฐ3์ฐจ์์ ๊ต๋ชจํ์คํ๋ฑ์ํํ๋ก์ด๋ฃจ์ด์ง๋ค. ๊ฒฝ์ฐ์ ๋ฐ๋ผ ์ด๋ฌํ ์คํ์ High Reynold'sNumber์คํ, ์ผ์ด๋ธ์ง๋์คํ, ์งํ๋ชจ๋ธ์คํ ๋๋ํํฅ๊ธฐํ์ ํ์ฅ๊ณ์ธก ๋ฑ์ด ์ถ๊ฐ๋๋ค. COWI์ฌ๋ ์ปดํจํฐ ๊ธฐ์ ์ ํตํด ๊ต๋๊ฑฐ๋์ ๋น๊ตํด ๋ณด๋ค ํจ๊ณผ์ ์ธDVMFlow๋ฅผ ๊ฐ๋ฐํ ๋ค. ๊ต๋ ๋จ๋ฉด๋๋ฅผ ๊ธฐ์ด๋ก,DVMFlow๋์ ์ ๊ณต๊ธฐ๋ ฅ๊ณ์(ํญ๋ ฅ๊ณ์), ํ๋ฌํฐ๊ณ์,์๋ฅ์ง๋์ผ๋ก์ธํ๋์ ๊ฑฐ๋๋ฑ์์ฐ์ถํ๋ค. ์ด๋๊ณง๊ฐ๊ธฐ๋ค๋ฅธ๋จ๋ฉด์๋ํํ๊ฐ๋ฅผ๋จ์๊ฐ๋ดํ๋์คํ์์ด์คํํ ์์๋ค๋์๋ฏธ์ด๊ธฐ๋ํ๋ค. ๊ฐ์ํ๋์คํ์์ค์ ํ๋์คํ๋๋น์๋ง์กฑํ ๋งํ๊ฒฐ๊ณผ๋ฅผ๋ณด ๋ค.
4. ๋ด๊ตฌ์ฑ(Durability)60๋ ๋์ ์ดํ ์๋ฐฉ๊ตญ๊ฐ์๊ฒ๋ ๊ฒฝ์ ์ ์ผ๋ก ์ค์ํ
์ฑ์ฅ๊ธฐ ๊ณ , ์ด๋๊ณง์์ฒ๊ฐ์๊ต๋์ํฌํจํด๊ธฐ๋ฐ์์ค๋ฌผ์๋ํ๋๋์ ์ธํฌ์๋ก์ด์ด์ก๋ค. ์ด๊ธฐ์๊ณต๋น์ฉ์์ ๋ ดํ๊ฒ์ฑ ์ ํ๊ณ ๊ณต์ฌ๊ธฐ๊ฐ์๋จ์ถ์ํค๋๋ฐ์ง์คํ๊ฒฐ๊ณผ๋ ๊ต๋์ ๋ฐ์ํ๋ ์์์ ์ฆ๊ฐ๋ก ์ด์ด์ก๋ค. ์ดํ,๋๋ถ๋ถ์ฃผ์ํ๋ก์ ํธ์์ค๊ณ์๊ฑด์ผ๋ก100๋ ์ด์์ฌ์ฉํ ์์๋๊ต๋์์ค๊ณ๊ฐํ์์กฐ๊ฑด์ด๋์๊ณ , ๊ฒฐ๊ณผ์ ์ผ๋ก๊ต๋์๊ณต๊ธฐ์ ๋ฐ์ ์์ค๋ํ์ ๊ธฐ๋ฅผ๋ง๋ จํ ๋ค.๊ต๋์๊ณต์์์ดํ์ต์๋ฆฌ๋ ํํ๊ฐ๋ฐ์ค๊ฑฐ๋์
์ ์ต์ด๋ก ๋์ ์ด ๋ ์ด๋, ํ ๊ตฌ์กฐ๋ถ์ผ์๋ ๋น๋ฒํ์์ฉ๋๊ณ ์๋ค. Oresund Bridge์์๋ ํธ๋ฌ์ค ๊ตฌ์กฐ์ ๋ด๋ถ๋ฅผ ํ์ตํ์ฌ ๋ถ์๋ฐฉ์ง๋ฅผ ํ๋๋ก ํ ์ผ๋ฉฐ,์ผ๋ณธ์Akashi ํ์๊ต์์ฃผ์ผ์ด๋ธ์ญ์ํ์ต์ผ๋ก์ธํด๋ถ์์๋ฐฉ์งํ๊ณ ์๋ค. ์ฃผ์ผ์ด๋ธ์ํ์ต์๋ฆฌ๋ํ๋์ค์ Agitaine ํ์๊ต์ ๋ด๋งํธ์ Little Belt ํ์๊ต์๋๋์ ๋์๋ค. ๊ต๋์๋ณด์์๊ด๋ จํ์ฌ, ์ฌ์ฅ์ผ์ด๋ธ ๊ณต๊ธ์ ์๋ค์ ํ์ฌ ์ฌ์ฅ์ผ์ด๋ธ์ด ํ์ต๋ณดํธ๋ ์์๋๋ก์ฐ๊ตฌํ๊ณ ์๋ค.์ฝํฌ๋ฆฌํธ์ ๋ด๊ตฌ์ฑ์ ๊ฐํํ๊ธฐ ์ํ ํฉ๋ฆฌ์ ์ธ ๋ฐฉ
์์ผ๋ก์ ๋ฝ๊ณต๋์ฒด์์ฌ์ ์ง์ํ์ฐ๊ตฌํ๋ก์ ํธ๋ฅผํตํด DuraCrete์ด ๊ฐ๋ฐ๋์๋ค. ์ด๋ ํด๋ก๋ผ์ด๋ ์นจํฌ๋ก์ธํ์ฒ ๊ทผ์ํ๋ถ๋ํํ์๊ฐ์ํ๋ฅ ์ ๊ณต๋ฒ์ํตํด ์์ธกํ๋ ์๋ฆฌ์ด๋ค. ์ฝํฌ๋ฆฌํธ๊ตฌ์กฐ๋ฌผ์ ๋ด๊ตฌ์ฑ์์ฝํฌ๋ฆฌํธ๋ฎ๊ฐ, ์ฝํฌ๋ฆฌํธ์ ์นจํฌ์ฑ(ํด๋ก๋ผ์ด๋ ํ์ฐ),์ฃผ์ ์กฐ๊ฑด ๋ฑ์(ํด๋ก๋ผ์ด๋ ํจ๋) ์ํด ๊ฒฐ์ ๋๋ค. ๊ตฌ์กฐ๋ฌผ์์๊ณ๋ฒ์์์์ ์ฒํ๋๋น์ฉ์ผ๋ก์คํ ์ธ๋ ์ค์ฒ ๊ทผ์์ฌ์ฉํ๋๊ฒ์์ด๋ฏธ์ผ๋ฐํ๊ฐ๋์๋ค. ํ์ฝฉ์Stonecutter Bridge ๊ฒฝ์ฐ, ์ฃผํ์ ์ธ๋ถ์ธต ๋ณด๊ฐ์ฒ ๊ทผ์ผ๋ก์คํ ์ธ๋ ์ค์ฒ ๊ฐ์์ฌ์ฉํ๋ค.
5. ํ๋ฅ ๋ก ์ ๋ฐฉ๋ฒ(Probabilistic Methods)ํ๋ฅ ๋ก ์ ๋ฐฉ๋ฒ์ ๊ต๋์ ์ค๊ณ์ ์์ด ์ ์ ๊ฐ๊ด์
๋ฐ๊ณ ์๋ค. ๋ด๊ตฌ์ฑ์ ์ฐ์ถํ๋ ๊ฒ ์ด์ธ์๋, ํ๋ฅ ๋ก ์ ๋ฐฉ๋ฒ์ ์ ๋ฐ ์ถฉ๋ํ์ค์ ์ฐ์ ํ๋๋ฐ๋ ์ฌ์ฉ๋์ด
61| ๊ธฐํ๊ธฐ์ฌ |
์ฅ๋๊ต๋์ ์ค๊ณ ๋ฐ ์๊ณต ๋ํฅ
์ง๋ค. ํด์ํญ๋ก์ ์๋๋ฆฌ์ค์์ ๊ต๋์ ํต๊ณผํ๋ ์ ์ ํญํด์ ์ถ์ ๋ฐ ๋ถํฌ๋์ ๋ฐ๋ผ, ๋ถ๊ดด์ ๊ฐ๋ฅ์ฑ์ด์ถ์ ๋์ด์ง๊ธฐ๋ ํ๋ค. AASTHO๋ ์ ๋ฐ์ถฉ๋๋ก ์ธํ๋ถ๊ดดํ๋ฅ ์ 10000๋ ์ฌํ์ฃผ๊ธฐ์ ๊ทผ๊ฑฐํ๋๋ก ๊ท์ ํ๊ณ ์๋ค. ์ด ๋ฐฉ๋ฒ์ ์ฌ์ฉํ ๊ฒฝ์ฐ, ์์ปจ๋ ํญ๋ก์๋ด์๋๋ ๊ฐ์์์คํ ๋ฑ์ ํ์ฉํด ์ํ์ ๋ฏธ์ฐ์ ์ํ์ํฌ์์๋๋ฐฉ๋ฒ๋ค์์์นํํ ์์๋ค.๋ํ ๋ค๋ฅธ ๊ณณ์์ ์ํ์ ๊ฐ์ํ๊ธฐ ๋ณด๋ค ๊ธฐ์ด๊ฐ ๋ถ
์คํ ๊ณณ์์ ๋์์ง ์ํ๋ถ๋ด์ ์์ฉํ๋ ๊ฒ๊ณผ ๊ฐ์๋ฐฉ๋ฒ์ผ๋ก์ค๊ณ๋์ต์ ํ๋ ์์๋ค. ๊ฑฐ๊ฐ๋๊ต์์ ๋ฐ์ถ๋ํ์ค์๊ธฐ์ค๋์ด๋ฌํ๊ธฐ์ค์์ํด์๋ฆฝ๋์๋ค.ํ๋ฅ ๋ก ์ ๋ฐฉ๋ฒ์๋ณด์๊ณต์ฌ์๊ตฌ์กฐ๋ฌผ์์์กด์๋ช ์
์ฌํ๊ฐํ๋๋ฐ์ฌ์ฉ๋๊ธฐ๋ํ๋ค.
. ์๊ณต์ ๋ฐ์
๊ต๋์์กฐ๋ฆฝ๊ณผ์ ์์๋๋ถ๋ถํด์์ง์ญ๋ฐ๊ต๋์ธ๊ทผ์ง์ญ์์ ์ง์์กฐ๋ฆฝ์ผ๋ก ์ด๋ฃจ์ด์ง๋ค. Great BeltWest Bridge์๊ฒฝ์ฐ, ์ด324์์ง์์กฐ๋ฆฝ๋ถ๋ถ์ผ๋ก์ด๋ฃจ์ด์ก์ผ๋ฉฐ, ์ด์ค ์ผ์ด์จ 26๊ฐ, 124๊ฐ์ pier shaft,138๊ฐ์ ๊ต๋๊ฑฐ๋๋ฑ์ด ์ธ๊ทผ ์ง์์กฐ๋ฆฝ์ฅ์์ ์กฐ๋ฆฝ๋์๋ค. ์ด๋ค์ 5๊ณณ์ ์์ฐ๋ผ์ธ์ ํตํด ์ ์์ด ๋ ํ,๊ตฌ์กฐ๋ฌผ์ ๋ฏธ๋๋ผํ์ ํตํด ๋๋ฅ์ ๋ก ์ด๋๋๊ณ , ํน๋ณ์กฐ๋ฆฝ๋ ํด์ํฌ๋ ์ธ(The Swan) ์ ์ด์ฉํ์ฌ ๊ต๋๊ฑด์คํ์ฅ์ผ๋ก ์์ก๋๋ค. ํด์ํฌ๋ ์ธ์ 7,400ํค ๋ฌด๊ฒ์์ผ์ด์จ์1.5 m๋๊ป์์์๊ธฐ์ด์ง๋ฐ์ํ์ฌํ๋ค. ๋ด๋งํฌ์ ์ค์จ๋ด์ ์ฐ๊ฒฐํ๋ Oresund Bridge์
๊ฒฝ์ฐ, ๊ต๋์ ๊ฐํธ๋ฌ์ค ๋ฐ ์ฝํฌ๋ฆฌํธ๋ฐ๋ฅํ์ ์คํ์ธ์์์ ์๋์๋ค. ์ด๊ธธ์ด 140m์ 7,000ํค์๊ฑฐ๋๋ถ๋ถ์ ๋ฐ์ง์ ์ ์ ์ ๋ ํ ๊ต๋ํ์ฅ์ผ๋ก ์์ก๋๊ณ ,Storebalt West Bridge ํ์ฅ์์๋ ์ฌ์ฉ๋ ํด์ํฌ๋ ์ธ์์ด์ฉํ์ฌ๊ต๊ฐ์์ฌ๋ ค๋์์ง๊ฒ๋๋ค. ๋ด๋งํฌ๋ด 2๊ฐ์ ๊ต๋์ ๊ฑด์ค์ ์ฌ์ฉ๋์ด์ง ํด์ํฌ๋ ์ธ์๊ธฐ์ค๋ ฅ์8,700ํค์ผ๋ก์ฆ๊ฐํ๊ณ ์ผ๋ถ๋ณ๊ฒฝ์์ ์๊ฑฐ
์ณ, ์บ๋๋ค์ 13km Prince Edward Island Bridge๋ฅผ๊ฑด์คํ๋๋ฐ๋์ฌ์ฉ๋์๋ค.๊ต๋๊ฑฐ๋๋ ๋ชจ๋ ํด์ํฌ๋ ์ธ์ ์ด์ฉํด ์ค์น๋์
๋ค. ์ฌ์ฅ๊ต์๊ฒฝ์ฐ์ผ์ด๋ธ๋ก๋งค๋ฌ๊ธฐ์ด์ 140m ๊ตฌ์ญ์์ ๊ฐ์ค์ง์ง๊ตฌ์กฐ๋ฌผ์ ๊ฑฐ๋๊ฐ ์ค์น๋๋ค. ๋ณธ ๋ฐฉ๋ฒ์์ฌ์ฅ๊ต์์๋ ๋๋ฌผ๊ฒ ์ฐ์ด๋ ๋ฐฉ๋ฒ์ด์ง๋ง, ํด์ํฌ๋ ์ธ์ ํตํด ์๊ณต๊ธฐ๊ฐ๊ณผ ํด์๊ตํตํผ์ก์ ๊ฐ์์ํฌ ์์๊ธฐ์ ์ฐจ์ธฐ ์ ํธ๋๊ณ ์๋ค. ๊ฑฐ๊ฐ๋๊ต ์ญ์ ์ผ์ด์จ,๊ต๊ฐ ๋ถ์ฌ, ๊ต๋ ๊ฑฐ๋ ๋ฑ์ ์ง์์กฐ๋ฆฝ์ ํตํด ์ ์์ด๋์ด์ง๊ณ , ํด์ํฌ๋ ์ธ์ ํตํด ๊ฑด์คํ์ฅ์ผ๋ก ์์ก๋ ์์ ์ด๋ค. ์ง์์กฐ๋ฆฝ์ ์ง๊ทนํ ์ฐ์ ํ๋ ์์ฐ๋ผ์ธ์ํตํด ๊ตฌ์กฐ๋ฌผ์ ์ง์ ์ฝ๊ฒ ํฅ์์ํฌ ์ ์์ ๋ฟ๋ง ์๋๋ผ, ์ ์ฒํ์ ๋ํ ๋์ฒ ๋ฐ ์ฅ๋น์ ์์ก์ด ์ฉ์ดํ๊ณ ํ์ฅ์์์๋ ธ๋๋ ฅ์์ ๊ฐ์ํฌ์์๋ค.
. ๋งบ์๋ง
์ ์ธ๊ณ์ ์ผ๋ก ๋๋ถ๋ถ์ ๊ต๋์ค๊ณ์ ์๊ณต์ ๊ดํ์ถ์ธ ๋ฐ ๋ํฅ์ ๋์ฒด์ ์ผ๋ก ํก์ฌํ๋ค. ๊ต๋ํ๋ก์ ํธ์๊ท๋ชจ์์ฆ์๋น๋์๋๋ฌธ์, ๊ณต์ฌ์ด๊ธฐ๋จ๊ณ์์๊ทผ๋์์ ์ฌํํ๋ก์ ํธ๋ฅผ๊ตฌ๋ณํ ์์๋ค. ์ด์๋ง์ฐฌ๊ฐ์ง๋ก, ํ๊ตญ์์์ต๊ทผ์งํ์ค์ธํ๋ก์ ํธ๋ํ์ต์ฒจ๋จ์ค๊ณ์์๊ณต๊ธฐ์ ์๋ฐ ํ๋ค. ์ค๊ณ์์๊ณต์ด๋ถ๋ฆฌ๋ฐ์ฃผ๋๋์ ํต์ ์ธ๊ณต๊ณต๋ฐ์ฃผ๋ฐฉ์์์์ค๊ณ์์๊ณต์๋์์ ์ํํ๋ ํ๋ก์ ํธ ๋ฐฉ์ ๋ฐ BOT(์๊ณต-์ด ์ดํ์์ ๊ถ์ด์ ) ๋ฐฉ์์ผ๋ก์ ํ๋๊ณ ์์ด, ๋๊ธ์์์ฑ ์์ด์ปค์ก๋ค. ๋๋ถ๋ถ์ด๋ฌํ์ฃผ์ํ๋ก์ ํธ๋๊ธฐ๋ ๋น์ ๊ฐ์น๋ฅผ ๊ฐ๊ฒ ๋๊ธฐ ๋๋ฌธ์, ๋ฏธ๊ด ์ญ์ ์ค์์ํ๋์ถ์ธ๋ค. Stonecutters Bridge์ ๊ฒฝ์ฐ, ๊ตญ์ ๊ฒฝ์์ ์ฐฐ์ ํตํด ๊ต๋์ค๊ณ์ ์ฒด๊ฐ ์ ์ ๋์๋ค. ๊ฑฐ๊ฐ๋๊ต์ ๊ฒฝ์ฐ์๋ ๊ต๋์ ํ์ํ ์ธ๊ด์ ๋ฏธ๊ด์ ์ถ๊ฐํ๊ธฐ ์ํํน๋ณํ๋ ธ๋ ฅ์ด๊ธฐ์ธ์ด์ก์ผ๋ฉฐ, ์ด๋ก์ธํด๋ถ์ฐ-๊ฑฐ์ ๋์ฌ์ด์๊ฐ๊ต์ญํ ์๋ฉ์ง๊ฒ์ํํ ๊ฒ์ด๋ค.
๊ตญ๋ฌธ๋ฒ์ญ : ์ด์ธ๋ จ ๋๋ฆฌ [email protected]