KSCE_1_2005_06_48(C)

14
48 | Vol.53 No.6 June, 2005 | . Introduction The design and construction of cable supported bridges relies to a large extent on past experience, where good and sometimes less good ideas from previous projects are evaluated and incorporated as appropriate in the new designs together with new ideas. Even though long span bridges can appear similar in the concept, all projects have to be individually designed considering the local conditions. Because the number of new long span bridges is relatively small, the development can appear to be slow compared to other industries. However, almost all major bridge projects contribute in one way or another to the development. Furthermore, the construction of a major bridge represents a significant investment where timely and safe construction is important for a successful completion of a project, which in some cases restrain the willingness to innovation. Finally, the basis for the design and construction - the national or international codes - are often established mainly to suit smaller bridges, which are constructed more frequent and there is often a delay in implementing the latest knowledge in the codes. This present paper focuses on state-of-the-art of design and construction of cable stayed and suspension bridges. . Bridge types There are basically two types of cable supported bridges, suspension bridges and cable stayed bridges. While suspension bridges have been designed and constructed for more than 150 years, the cable stayed bridge concept is relatively new and cable stayed bridges have only been constructed since the middle of the 20 th century. Lars HAUGE Chief Project Manager, COWI A/S Lyngby, Denmark [email protected] | ์•ฝ ๋ ฅ| Lars Hauge, born 1962, graduated from the Technical University of Denmark in 1986. Since 1990 he has been employed by COWI A/S in Copenhagen in the department for major bridges, and has been involved in the design of some of the world's largest bridges. He has been working in Korea for the Busan-Geoje Fixed Link for the past two years as project manager for the design of the bridges. Construction and Technology of Long Span Bridges

description

.

Transcript of KSCE_1_2005_06_48(C)

48 | Vol.53 No.6 June, 2005 |

. Introduction

The design and construction of cable supported

bridges relies to a large extent on past experience,

where good and sometimes less good ideas from

previous projects are evaluated and incorporated

as appropriate in the new designs together with

new ideas. Even though long span bridges can

appear similar in the concept, all projects have to

be individually designed considering the local

conditions. Because the number of new long span

bridges is relatively small, the development can

appear to be slow compared to other industries.

However, almost all major bridge projects

contribute in one way or another to the

development. Furthermore, the construction of a

major bridge represents a significant investment

where timely and safe construction is important

for a successful completion of a project, which in

some cases restrain the willingness to innovation.

Finally, the basis for the design and construction -

the national or international codes - are often

established mainly to suit smaller bridges, which

are constructed more frequent and there is often a

delay in implementing the latest knowledge in the

codes.

This present paper focuses on state-of-the-art of

design and construction of cable stayed and

suspension bridges.

. Bridge types

There are basically two types of cable supported

bridges, suspension bridges and cable stayed

bridges. While suspension bridges have been

designed and constructed for more than 150

years, the cable stayed bridge concept is

relatively new and cable stayed bridges have only

been constructed since the middle of the 20th

century.

Lars HAUGEChief Project Manager, COWI A/SLyngby, [email protected]

| ์•ฝ ๋ ฅ |Lars Hauge, born 1962, graduated from the TechnicalUniversity of Denmark in 1986. Since 1990 he has beenemployed by COWI A/S in Copenhagen in the department formajor bridges, and has been involved in the design of some ofthe world's largest bridges. He has been working in Korea forthe Busan-Geoje Fixed Link for the past two years as projectmanager for the design of the bridges.

Construction and Technology of Long Span Bridges

49| Feature Article |

Trends in Design and Construction of Long Span Bridges

A ground anchored suspension bridge has the

bridge deck suspended from main cables by

hangers and the deck has roughly no other

function than to provide a carriageway for the

traffic. The main load carrying elements are the

towers, the anchor structure and the main cable.

The sag of the main cables, which controls the

cable steel quantities, is traditionally between 1 : 9

and 1 : 11. A suspension bridge is constructed by

constructing anchors and pylons first followed by

the main cable and finally the bridge deck which

is suspended from the main cables.

Traditionally a cable stayed bridge is constructed

by constructing the towers followed by the deck,

which is cantilevered from the towers. The height

of the towers above deck is normally not less than

approximately 1/5 times the main span. In a cable

stayed bridge, the deck is utilised as compression

members balancing the horizontal forces from the

cables.

This short description illustrates the main

differences between suspension bridges and cable

stayed bridges:

For the construction of a suspension bridge,

the elements are constructed sequential

leading to a long construction time where

most elements are on the critical path.

A suspension bridge requires an anchor

structure, which normally is expensive and

time critical with regard to construction, while

a cable stayed bridge utilises the bridge deck

to balance the horizontal component of the

cable forces.

The amount of cable steel is significantly

higher in a suspension bridge compared to a

cable stayed bridge, due to the reduced tower

height to span ratio.

It will almost always be economically

advantageous to construct a cable stayed bridge if

possible, unless special conditions prevail as for

instance good rock conditions for main cable

anchorage. However, due to the tower height and

the traditional construction methods there is an

upper limit to how long cable stayed bridge can be

constructed.

Attempts have been made to mitigate the

deficiencies of suspension bridge compared to cable

stayed bridges. Self-anchored suspension bridges

have been designed and constructed thus avoiding the

anchor block structure and utilising the bridge deck to

balance the horizontal forces from the main cables.

However, a major set-back is that the deck has to be

erected on temporary supports prior to cable erection,

which calls for temporary support of the bridge deck

during construction adding the bridge deck to the

critical path. An example of a self anchored

suspension bridge is YongJong Bridge in Korea,

where the span is moderate and where the bridge

deck is sufficiently large to carry the compression

force due to large capacity requirements.

Figure 1. Great Belt Suspension Bridge

50 | Vol.53 No.6 June, 2005 |

Construction and Technology of Long Span Bridges

1. Suspension BridgesA suspension bridge with an anchor block

structure is normally only constructed, if the

required span is longer than what can be

accommodated by a cable stayed bridge. This limit

is today around a main span of 1200 - 1400m, but

has moved over the past 50 years from 600 -

700m. Recent long span suspension bridges

include Akashi Kaikyo - Japan (1990m main

span), Great Belt East Bridge - Denmark (1624m

main span), Tsing Ma - Hong Kong (1377m main

span), Humber Bridge - UK (1410m main span)

and the High Coast Bridge - Sweden (1210m main

span). The High Coast Bridge was constructed

taking advantage of extremely good foundation

conditions for the main cables, thus being

economically optimal with a relatively shorter

span. There is a tendency towards even longer

spans, and the next big leap forward is likely to be

the bridge across the Messina Strait in Italy, where

a main span of 3300m is envisaged. This bridge is

out for tender now (spring/summer 2005).

Suspension bridges are sometimes constructed

with shorter spans. However, this is mostly the

case where the design is governed by other issues

than construction cost and time. Examples hereof

are East Bay Bridge in the US, Millenium Bridge

in the UK and Yong Jong Grand Bridge in Korea.

There are exemptions from these general rules

including Gwang An Bridge in Korea and

Carquinez Bridge in the US.

2. Cable Stayed BridgesCable stayed bridges can roughly be divided in three

groups - short spans, medium spans and long spans.

The Normandy Bridge (856m main span) in

France and the Tatara Bridge (890m main span) in

Japan, which were completed in the mid 1990'ies,

marked with main spans of more than 800 m a

large step forward and have paved the way for the

even longer spans of Stonecutters Bridge (1018m

main span) in Hong Kong and Sutong Bridge

(1088 m main span) in China - both currently

under construction. Al these bridges are

constructed with closed steel box girders in the

main span to increase the torsional rigidity. All the

long spans cable stayed bridges are designed

triangulated cable systems.

The cable configuration layout is important for

a long span cable stayed bridge. An A-tower will

in some cases increases the critical wind speed

by 20% compared to a H-tower. In Korea, the 2nd

YongJong Bridge, which currently are being

designed, and the 2nd Nanjing Yangtze Crossing

in China follows the same principles with

triangulated cable systems and closed steel box

Figure 2. Messina Strait Crossing

51| Feature Article |

Trends in Design and Construction of Long Span Bridges

girders. One of the most important parameters

for long span cable stayed bridges is the span to

with ratio and with a span of more than 40 times

the width, the Normandy Bridge in France is still

one of the slender cable stayed bridges in the

world.

In recent years several cables stayed bridges with

main spans of between 400 and 600m for

roadway traffic have been constructed. A concept

with open plated composite bridge decks and

concrete towers seems to be optimal with regard

to cost and time for construction for this range of

spans. There are several examples of this type of

bridge including: Alex Fraiser Bridge in Canada,

2nd Severn Bridge and Dartford Bridge in the UK,

SeoHae Grand Bridge and Sham Shui Po in

Korea, Uddevalla Bridge in Sweden, Rama 8

Bridge in Thailand (mono tower bridge) and

YangPu, XuPu and Ching Chau Min Yang in

China. The bridges of Busan-Geoje Fixed Link in

Korea and the Cooper River bridge in the US are

currently under construction and will become the

same basic bridge types. For main spans over

600m (500m in typhoon areas) it is difficult for

this bridge type to fulfil the requirement to

aerodynamic stability.

Numerous smaller span cable stayed bridges

have been constructed for various reasons - one

being the landmark quality of cable stayed

bridges.

Recently there has been a trend towards multi-

span cable supported bridges. In Hong Kong Ting

Kau Bridge was inaugurated in 1998 and Rion-

Antirion Bridge in Greece and Viaduc de Maillot

in France has recently been competed. In Korea is

the construction of the bridges of the Busan-Geoje

Fixed Link about to commence and the Link will

include a multi-span cable stayed bridge. For the

crossing of the Canal de Chacao in Chile a multi-

span suspension bridge is currently considered.

. Developments in Design

1. Development in Articulation(1) Cable stayed bridges

Hydraulics is commonly used for bridges

subjected to seismic loading to provide support

during a seismic event in the form of Shock

Transmission Units (STU). There has been a trend

towards utilising hydraulics to control the support

conditions of the bridge.

Figure 3. Normandy Bridge

Figure 4. SeoHae Grand Bridge

52 | Vol.53 No.6 June, 2005 |

Construction and Technology of Long Span Bridges

On the Faroe Bridge - a cable stayed bridge

supported by a single plane of cables; the bridge

deck is only supported laterally and for twist at the

towers, while the bridge deck can move freely

vertically. The static system was obtained by the

use of coupled hydraulic pistons at both sides of

the bridge deck

On Stonecutters Bridge the bridge deck is

supported longitudinally for โ€œquickโ€movements

from dynamic wind and live load, while it is free

to move for โ€œslowโ€movements from temperature

variations. The advantages are that effects from

dynamic wind would have overloaded the back

span piers, if the deck was not supported by the

tower and the effects from temperature would

have overloaded the towers, if the deck had been

fully restrained.

On Sutong Bridge, the longitudinal movements

at the towers will be restrained by speed

dependent hydraulic dampers. (F=3750ยทV 0.4 )The bridge deck is not supported vertically at the

towers.

Another characteristic with the above bridges is

that vertical support at the towers is not provided,

thus eliminating the hard point at the towers,

which will attract large bending moments.

The articulation of the Normandy Bridge with

the 116 m cantilever in concrete and monolithic

joint between the girder and the pylon might seem

a little unconventional. However, having studied

the bridge in detail it is clear that these features are

advantageous for the bridge. During construction

the steel part of the girder acted as if it was

supported - not at the pylons - but 116 m out in the

main span, and thus reducing the deflection. The

fully restrained system was possible because the

pylon was supported on a flexible pile foundation

and because the curvature of the deck is large.

(2) Suspension bridge

Traditionally, suspension bridges have been

designed as โ€œ three span structuresโ€with

expansion joints and supports at the towers.

Experience has shown that maintenance works on

these parts constitute a major part of the

maintenance cost. Therefore a concept with a

continuous girder over the full cable supported

length would be attractive and was implemented

for the Great Belt East Bridge in Denmark and for

the High Coast Bridge in Sweden. One problem

to overcome with the continuous girder trough the

pylons was the handling of the forced bending

moments at the pylons caused by angular rotation

of the main cables over the cable saddles. The

girder deflection would more or less follow the

cable deflection, and bending moments would be

introduced. To minimise the forced moments in

combination with dead and live load actions, the

supporting conditions were optimised based on a

parametric study of hanger distances, hanger types

(locked coil versus parallel wire strands),

regulation of hanger forces, girder stiffness,

supporting of the girder for vertical forces at the

pylons, etc.

As a supplement the longitudinal movements at

the anchor blocks were limited by means of

hydraulic pistons in order to limit the angular

deflection of the hangers and the requirements to

the expansion joints. The system also acts against

quick movements to reduce the wear in the

expansion joints and the bearings.

53| Feature Article |

Trends in Design and Construction of Long Span Bridges

2. Closed box girder conceptThe closed steel box girder concept was first

introduced on the Severn suspension bridge in the

UK and the Little Belt suspension bridge in

Denmark in the 1960โ€™ies. The advantages of the

closed steel box are high torsional stiffness,

relatively simple automated fabrication and easy

maintenance. A complex geometry, many edges

and large exposed surfaces are sensitive to

deterioration. Therefore, simple structural forms

as the closed steel box girder with a minimum of

exposure to the environment are preferred. The

outer surface is completely smooth with a

minimum of exposure and easy to maintain. The

interior, which comprises about 80 percent of the

total steel area with stiffening troughs and

bulkheads, can be corrosion protected by

dehumidification and thus does not need to be

painted. The principle in dehumidification is to

keep the relative humidity inside the box below

40 percent, leaving an adequate margin to 60

percent, the limit above which corrosion may take

place. This can be achieved by installation of a

simple fan system for circulation of the enclosed

air and a dehumidifier unit equipped with

hygroscopic filters. The closed steel box girder is

also superior with regard to aerodynamic

performance. The high torsional stiffness

increases the critical flutter wind speed and low

drag coefficients and derivatives reduce the effects

from wind loading.

3. AerodynamicThe failure of the Tacoma Narrows suspension

bridge in the US resulted in a general set back for

the development of design and construction of

long span bridges. Bridges designed and

constructed in the wake of the accident tended

towards heavier steel truss girder design, while the

sources of the undesired vibrations were

thoroughly investigated. Today substantial wind

tunnel testing is part of every long span bridge

design and comprise as a minimum section model

tests of the bridge deck and often 3D aeroelastic

full bridge model tests. These tests are often

supplemented with High Reynolds number tests,

cable vibration tests, terrain model tests and site

measurements of the wind climate.

As computer power increases, more and more

sophisticated calculations can be performed

providing the bridge designers with useful

information of the behaviour of the structures.

COWI has developed a computer tool, which

can be used with advantage for comparison of

bridge girder concepts, DWMflow. Based on a

description of the cross-section, DWMflow

calculates static wind load coefficients (drag-

coefficients), flutter-coefficients and vortex

shedding response. This means that a qualified

evaluation of for instance, different cross sections

could be carried out in a short time without

Figure 5 Stonecutters Bridge in the Monash wind tunnel

54 | Vol.53 No.6 June, 2005 |

Construction and Technology of Long Span Bridges

recourse to physical wind tunnel tests. The

โ€œartificiallโ€wind tunnel has been compared with

a real wind tunnel with good results.

4. DurabilityThe sixties and the following years have been

characterised by an important economical growth

the result of which has lead to intensive

investments in infrastructure projects, including

thousands of bridges. Efforts have mainly been

concentrated on achieving low initial construction

costs and minimise the construction period.

Today, the effect has begun to show in the form of

an increasing amount of damages on these

bridges.

Therefore, long service life design concepts for

100years or more are becoming a basic

requirement for major projects. The result is a

considerable impact on the development of bridge

construction technology.

The concept of dehumidification first introduced

in bridge construction for the closed steel box

girders has been exported to other areas of the

structure. On the Oresund bridge is the interior of

the truss structure protected from corrosion by

dehumidification, on the Akashi suspension

bridge in Japan are the main cables protected

against corrosion by dehumidification.

Dehumidification of main cables has been

introduced on the Aquitaine Suspension bridge in

France and on the Little Belt Supension Bridge in

Denmark in connection with rehabilitation of the

bridges. Stay cable suppliers are currently

developing a concept where stand cables can be

protected by dehumidification.

A rational approach to concrete durability -

DuraCrete - has been developed through a

substantial research project financed by the

European Community. The philosophy is a

prediction of time to depassivation of the

reinforcement due to chloride ingress using

probabilistic models. The durability of the

concrete structure is thus reliant on concrete cover,

the permeability of the concrete (chloride

diffusion) and the aggressivity of the surroundings

(chloride content).

The use of stainless steel reinforcement in

critical areas of the structure subjected to a harsh

environment is becoming increasingly common.

On Stonecutters Bridge in Hong Kong stainless

steel is used for the outer layer reinforcing bars in

the towers.

5. Probabilistic methodsIn general, probabilistic methods are gaining

Figure 6. Visualisation of simulated flow(Busan-Geoje Fixed Link)

55| Feature Article |

Trends in Design and Construction of Long Span Bridges

more and more momentum in design of bridges.

In addition to durability calculations, probabilistic

methods are also used to establish ship collision

loading. Based on scenarios for the ship traffic,

assumptions and distributions of the navigation of

ships passing the bridge and capacity of the

structures, the probability of collapse can be

determined. AASTHO requires that the

probability of failure due to ship collision shall

correspond to a return period of 10.000 years.

Using this method it is possible to quantify and

take advantage of risk mitigating measures as for

instance use of pilots and surveillance systems in

the calculations. Furthermore, the design can be

optimised by for instance accepting higher risk in

case of poor foundation conditions against

reducing the risk elsewhere. The basis for the ship

collision loading for Busan-Geoje Fixed link has

been established on this basis.

Probabilistic methods are also used in

reassessment of remaining structural service life in

connection with rehabilitation.

. Development in Construction

Fabrication and erection of the major bridges

projects is characterised by off-shore/off-site

prefabrication, large transport distance and

erection of large elements. For the Great Belt

West Bridge altogether 324 pre-fabricated units,

comprising 62 caissons, 124 pier shafts and 138

bridge girders were cast in a pre-fabrication yard

close to the bridge site. The elements were cast in

five production lines and moved on sliding

surfaces by pushing units to the load-out jetties,

where they were lifted off by a large purpose-built

heavy lift crane vessel, the Swan, for further

transportation and installation at the bridge site.

Caissons, weighing up to 7,400 tonnes, were

placed by the Swan on 1.5 m thick crushed stone

foundation beds.

For the Oresund Link between Denmark and

Sweden, fabrication of the steel trusses for the

Oresund Bridges as well as casting of the concrete

deck was carried out in Spain. The complete 140 m

long girder sections, weighing up to 7,000tonnes,

were tugged on flat barges to the bridge site and

Figure 7. Pre-fab Yard for Great Belt West Bridge

Figure 8. Pylons for Busan- Geoje Fixed Link

โ€ฅ

56 | Vol.53 No.6 June, 2005 |

Construction and Technology of Long Span Bridges

lifted into position on the piers by the Swan, the

vessel used for the Storebรฆlt West Bridge. In

between the job on the two Danish bridges, The

Swan has been used to erect the 13km Prince

Edward Island Bridge in Canada after being

modified and having the lifting capacity increased

to 8,700 metric tons.

On the cable-stayed bridge the girder was also

erected in 140m sections on temporary supports

before being suspended by the stays. This method

is unusual for a cable-stayed bridge, but was

attractive due to the availability of the heavy lift

vessel, and it reduced the construction.

For the Busan Geoje Fixed Link it is envisaged to

have caissons, pier shafts and bridge girders for the

approach bridge prefabricated of site and transported

to the site assisted by a large floating crane.

The advantage is a rational industrialised

production in the prefabrication yard, where the

quality more easily can be controlled. Furthermore,

the production is less susceptible to adverse

weather conditions and transport of equipment and

labour to the site can be saved.

. Conclusion

The trends and tendencies in design and

construction of major bridges seem to be

developing in more or less in the same direction

world wide. Because of the size and the

frequency of the projects, it is common early in

the planning process to screen recent similar

projects.

There seems to be a development in the way the

project are procured from traditionally separate

design and construction typically controlled by a

public client, towards design-built project and

BOT projects, where more and more responsibility

is left with the contractor/concessionaire.

Because of the landmark value of these major

projects, there is a tendency towards increased

focus on aesthetics. For the Stonecutters Bridges,

the design was developed though an international

design competition and for the Busan-Geoje

Fixed Link, a special effort was made to give the

bridges an appearance, which would make the

bridges stand-out and which would associate the

bridges with Busan and Geoje Island and vice

versa.

๊ธฐํš : ์‹ ์ˆ˜๋ด‰ ํŽธ์ง‘๊ฐ„์‚ฌ์žฅ [email protected]

57| ๊ธฐํš๊ธฐ์‚ฌ |

. ๋จธ๋ฆฌ๋ง

์ผ€์ด๋ธ”๊ต๋Ÿ‰์˜ ์„ค๊ณ„์™€ ์‹œ๊ณต์€ ๋Œ€๋ถ€๋ถ„ ๊ณผ๊ฑฐ์˜ ๊ฒฝํ—˜์—๊ทผ๊ฑฐํ•˜๋ฉฐ, ์ƒˆ๋กœ์šด๊ต๋Ÿ‰์„ค๊ณ„์‹œ์˜ˆ์ „ํ”„๋กœ์ ํŠธ๋กœ๋ถ€ํ„ฐ ๋ถ„์„๋œ ์žฅ๋‹จ์ ๊ณผ ์ƒˆ๋กœ์šด ์•„์ด๋””์–ด๊ฐ€ ์ ์ ˆํ•˜๊ฒŒ ๋ณ‘ํ•ฉ๋œ๋‹ค. ์žฅ๋Œ€๊ต๋Ÿ‰์€๊ฐœ๋…์ƒ์œ ์‚ฌํ• ์ง€๋ผ๋„, ๋ชจ๋“ ํ”„๋กœ์ ํŠธ๋Š” ๊ฐœ๋ณ„์ ์œผ๋กœ ์ง€์—ญ์  ํŠน์ƒ‰์— ๋งž์ถ”์–ด ์„ค๊ณ„๋˜์–ด์•ผ ํ•œ๋‹ค. ์‹ ์„ค ์žฅ๋Œ€๊ต๋Ÿ‰์˜ ์ˆ˜๊ฐ€ ์ƒ๋Œ€์ ์œผ๋กœ ์ ๊ธฐ ๋•Œ๋ฌธ์—, ํƒ€ ์‚ฐ์—…์— ๋น„ํ•ด ์„ฑ์žฅ์†๋„๊ฐ€ ๋”๋”œ ์ˆ˜๋„ ์žˆ์ง€๋งŒ๊ต๋Ÿ‰ ํ”„๋กœ์ ํŠธ์˜ ์‚ฐ์—…๋ฐœ์ „์— ๋Œ€ํ•œ ๊ธฐ์—ฌ๋„๋ฅผ ๊ฒฐ์ฝ” ๊ฐ„๊ณผํ•  ์ˆ˜ ์—†๋‹ค. ๋”์šฑ์ด, ๊ต๋Ÿ‰์˜ ๊ฑด์„ค์€ ๋Œ€์ฒด์ ์œผ๋กœ ๋Œ€๊ทœ๋ชจ์˜ ํˆฌ์ž๋ฅผ ์˜๋ฏธํ•˜๊ณ , ์ •ํ•ด์ง„ ๊ธฐ๊ฐ„๋‚ด์˜ ์•ˆ์ „์‹œ๊ณต์—ฌ๋ถ€๊ฐ€ ํ”„๋กœ์ ํŠธ์˜ ์„ฑ๊ณต์—ฌ๋ถ€๋ฅผ ์ขŒ์šฐํ•˜๊ธฐ์—, ํ˜์‹ ์—๋Œ€ํ•œ ์˜์ง€๊ฐ€ ๋•Œ๋ก  ์ขŒ์ ˆ๋˜๊ธฐ๋„ ํ•œ๋‹ค. ์„ค๊ณ„์™€ ์‹œ๊ณต๊ธฐ์ค€์ด ๋˜๋Š” ๊ตญ๋‚ด ๋˜๋Š” ๊ตญ์ œ ๊ทœ์ •์€ ๋Œ€๊ฐœ ๋นˆ๋ฒˆํžˆ ์‹ ์ถ•๋˜๋Š” ์†Œ๊ทœ๋ชจ ๊ต๋Ÿ‰์— ์ ํ•ฉํ•˜๊ฒŒ ์ œ์ •์ด ๋˜๋ฉฐ, ์ตœ๊ทผ์˜์ •๋ณด ๋˜๋Š” ์ง€์‹์„ ๊ตญ๋‚ด์™ธ ๊ทœ์ •์— ๋ฐ˜ ํ•˜๊ธฐ๊นŒ์ง„ ์‹œ๊ฐ„์ด๊ฑธ๋ฆฐ๋‹ค. ๋ณธ๊ณ ์—์„œ๋Š”์‚ฌ์žฅ๊ต์™€ํ˜„์ˆ˜๊ต์˜์ตœ์ฒจ๋‹จ์„ค๊ณ„๋ฐ์‹œ๊ณต์—๊ด€ํ•œ๋™ํ–ฅ์„๋‹ด์•„๋‚ด๊ณ ์žํ•œ๋‹ค.

๊ต๋Ÿ‰ ํ˜•์‹

์ผ€์ด๋ธ”๊ต๋Ÿ‰์€๊ธฐ๋ณธ์ ์œผ๋กœ์‚ฌ์žฅ๊ต์™€ํ˜„์ˆ˜๊ต๋กœ๋‚˜๋ˆ„์–ด์ง„๋‹ค. ํ˜„์ˆ˜๊ต๋Š”์„ค๊ณ„์™€์‹œ๊ณต์ด150๋…„์ด์ƒ์ด๋ฃจ์–ด์กŒ์ง€๋งŒ, 20์„ธ๊ธฐ์ค‘๋ฐ˜์ด๋ž˜์ฑ„ํƒ๋œ์‚ฌ์žฅ๊ต๋Š”์ด์—๋น„ํ•ด๋น„๊ต

์ ์ƒˆ๋กœ์šด๊ฐœ๋…์˜๊ต๋Ÿ‰์ด๋‹ค. ํƒ€์ •์‹ํ˜„์ˆ˜๊ต๋Š”์ฃผ์ผ€์ด๋ธ”๋กœ๋ถ€ํ„ฐํ–‰์–ด์—์˜ํ•ด์—ฐ๊ฒฐ๋œ๊ต๋Ÿ‰๊ฑฐ๋”๊ฐ€์žˆ๊ณ , ๊ต๋Ÿ‰๊ฑฐ๋”๋Š”์ฃผ๋กœ์ฐจ๋Ÿ‰ํ†ตํ–‰๋งŒ์„์ œ๊ณตํ•˜๋Š”์—ญํ• ์„์ˆ˜ํ–‰ํ•œ๋‹ค. ํ•˜์ค‘์„์ง€ํƒฑํ•˜๋Š”์ฃผ์š”์š”์†Œ์—๋Š”์ฃผํƒ‘, ์•ต์ปค๋ธ”๋ก๊ณผ์ฃผ์ผ€์ด๋ธ”์ด์žˆ๋‹ค. ์ฃผ์ผ€์ด๋ธ”์˜๊ฐ•์žฌ๋Ÿ‰์„๊ฒฐ์ •ํ•˜๋Š”์ฃผ์š”๋ณ€์ˆ˜์ธ์ƒˆ๊ทธ(sag)๋Š”์ผ๋ฐ˜์ ์œผ๋กœ1 : 9์™€1 : 11 ์‚ฌ์ด์˜๋น„์œจ๋กœ์„ค์น˜๋œ๋‹ค. ํ˜„์ˆ˜๊ต๋Š”์•ต์ปค์™€์ฃผํƒ‘์„๋จผ์ €์„ค์น˜ํ•œํ›„์—์ฃผ์ผ€์ด๋ธ”์„์„ค์น˜ํ•˜๋ฉฐ, ์ฃผ์ผ€์ด๋ธ”์—๋งค๋‹ฌ์•„๊ต๋Ÿ‰๊ฑฐ๋”๋ฅผ๋งˆ์ง€๋ง‰์œผ๋กœ๊ฑด์„คํ•œ๋‹ค. ์‚ฌ์žฅ๊ต๋Š”์ผ๋ฐ˜์ ์œผ๋กœ์ฃผํƒ‘์„๋จผ์ €์„ค์น˜ํ•˜๊ณ , ์ฃผํƒ‘์—์„œ์ผ„ํ‹ธ๋ ˆ๋ฒ„๊ณต๋ฒ•์œผ๋กœ๊ต๋Ÿ‰๊ฑฐ๋”๋ฅผ์„ค์น˜ํ•˜๋Š”๊ณต๋ฒ•์„๋”ฐ๋ฅธ๋‹ค. ๊ต๋Ÿ‰์ƒ๋ถ€์ฃผํƒ‘์˜๋†’์ด๋Š”์ฃผ๊ฒฝ๊ฐ„์˜1/5๋ฐฐ์ด์ƒ์ด์–ด์•ผํ•œ๋‹ค. ์‚ฌ์žฅ๊ต์˜๊ต๋Ÿ‰๊ฑฐ๋”๋Š”์ผ€์ด๋ธ”์žฅ๋ ฅ์˜ ์ˆ˜ํ‰๋ถ„๋ ฅ์„ ๋ถ„๋‹ดํ•˜๋Š” ์••์ถ•๋ถ€์žฌ๋กœ์จ ํ™œ์šฉ๋œ๋‹ค.ํ˜„์ˆ˜๊ต์™€์‚ฌ์žฅ๊ต์˜์ฐจ์ด์ ์„์š”์•ฝํ•˜๋ฉด๋‹ค์Œ๊ณผ๊ฐ™๋‹ค.- ํ˜„์ˆ˜๊ต์˜ ๊ฑด์„ค์€ ๊ธด ์‹œ๊ณต๊ธฐ๊ฐ„ ๋™์•ˆ ๊ฑฐ์˜ ๋ชจ๋“ 

๋‹จ๊ณ„๊ฐ€์ฃผ์š”๊ณต์ •์œผ๋กœ์ˆœ์ฐจ์ ์œผ๋กœ์ง„ํ–‰๋œ๋‹ค.- ํ˜„์ˆ˜๊ต๋Š” ์‹œ๊ณต๊ธฐ๊ฐ„์ด ๊ณ ๋ ค๋˜์–ด์•ผ ํ•˜๊ณ  ๊ฐ’๋น„์‹ผ

์•ต์ปค๊ตฌ์กฐ๋ฌผ์„ํ•„์š”๋กœํ•˜๋Š”๋ฐ˜๋ฉด, ์‚ฌ์žฅ๊ต๋Š”๊ต๋Ÿ‰๊ฑฐ๋”๋ฅผ ์ผ€์ด๋ธ” ์ˆ˜ํ‰ํ•˜์ค‘์˜ ๊ท ํ˜•์„ ์กฐ์ ˆํ•˜๋Š”๋ฐํ™œ์šฉํ•œ๋‹ค.

- ์ฃผํƒ‘์˜๋†’์ด์™€๊ฒฝ๊ฐ„์˜๋น„์œจ๊ฐ์†Œ๋กœ์ธํ•˜์—ฌ, ํ˜„์ˆ˜๊ต์—์‚ฌ์šฉ๋˜๋Š”์ผ€์ด๋ธ”๊ฐ•์žฌ์˜์–‘์ด์‚ฌ์žฅ๊ต์—๋น„ํ•ดํ˜„์ €ํžˆ๋งŽ๋‹ค.

์ฃผ์ผ€์ด๋ธ”์„์ •์ฐฉํ•˜๊ธฐ์—ํŠน๋ณ„ํ•˜๊ฒŒ์ ํ•ฉํ•œ์•”๋ฐ˜์กฐ๊ฑด์ด๋ฐœ๊ฒฌ๋˜์ง€์•Š์€์ด์ƒ, ๊ฐ€๋Šฅํ•˜๋ฉด์‚ฌ์žฅ๊ต๋ฅผ๊ฑด์„คํ•˜๋Š”

์žฅ๋Œ€๊ต๋Ÿ‰ ๊ฑด์„ค ๋ฐ ๊ธฐ์ˆ 

| ์•ฝ ๋ ฅ |

๋ด๋งˆํŠธTechnical University ์กธ์—…

๋ด๋งˆํŠธCOWI A/S ์ฝ”ํŽœํ•˜๊ฒ๋ณธ์‚ฌ๊ต๋Ÿ‰๋ถ€์ž…์‚ฌ

๊ฑฐ๊ฐ€๋Œ€๊ต์˜๊ต๋Ÿ‰์„ค๊ณ„๋ถ€๋ถ„ํ”„๋กœ์ ํŠธ๋งค๋‹ˆ์ €

Lars HAUGEChief Project Manager, COWI A/SLyngby, [email protected]

58 | ์ œ53๊ถŒ ์ œ6ํ˜ธ 2005๋…„ 6์›” |

์žฅ๋Œ€๊ต๋Ÿ‰ ๊ฑด์„ค ๋ฐ ๊ธฐ์ˆ 

๊ฒƒ์ด ๊ฒฝ์ œ์ ์œผ๋กœ ์œ ๋ฆฌํ•˜๋‹ค. ํ•˜์ง€๋งŒ, ์ฃผํƒ‘์˜ ๋†’์ด์™€์ „ํ†ต์ ์ธ ์‹œ๊ณต๋ฐฉ๋ฒ•์„ ๊ณ ๋ คํ•˜๋ฉด ์‚ฌ์žฅ๊ต์˜ ๊ธธ์ด์—๋Š”ํ•œ๊ณ„๊ฐ€์žˆ๋‹ค. ์‚ฌ์žฅ๊ต์™€๋น„๊ตํ•ดํ˜„์ˆ˜๊ต์˜๊ฒฐํ•จ์„์™„ํ™”์‹œํ‚ค๊ธฐ์œ„ํ•œ๋…ธ๋ ฅ์€๊ณ„์†๋˜์–ด์™”๋‹ค. ์•ต์ปค๋ธ”๋Ÿญ๊ตฌ์กฐ๋ฌผ์„ ๋Œ€์‹ ํ•ด ์ž์ •์‹ ํ˜„์ˆ˜๊ต๊ฐ€ ์„ค๊ณ„ ๋ฐ ์‹œ๊ณต๋˜์—ˆ๊ณ , ์ฃผ์ผ€์ด๋ธ”์˜ ์ˆ˜ํ‰ํ•˜์ค‘ ์„ฑ๋ถ„์„ ๋ถ€๋‹ดํ•˜๊ธฐ ์œ„ํ•ด ๊ต๋Ÿ‰๊ฑฐ๋”๋ฅผ์‚ฌ์šฉํ•˜ ๋‹ค. ๊ทธ๋Ÿฌ๋‚˜์ด๋Ÿฌํ•œ๋ฐฉ๋ฒ•์˜๋ฌธ์ œ์ ์€๊ต๋Ÿ‰๊ฑฐ๋”๊ฐ€ ์ผ€์ด๋ธ”์ด ์„ค์น˜๋˜๊ธฐ ์ „์— ๊ฐ€์„ค์ง€์ง€๊ตฌ์กฐ๋ฌผ์—๋จผ์ € ์„ค์น˜๋˜์–ด, ๊ฒฐ๊ณผ์ ์œผ๋กœ ์ž„๊ณ„๊ฒฝ๋กœ์— ๊ต๋Ÿ‰๊ฑฐ๋”๊ฐ€์ถ”๊ฐ€๋œ๋‹ค๋Š”๊ฒƒ์ด๋‹ค. ์ž์ •์‹ํ˜„์ˆ˜๊ต์˜์˜ˆ๋กœ์จ, ํ•œ๊ตญ์˜์ข…๋Œ€๊ต๊ฐ€์žˆ๋‹ค. ์ข…๋Œ€๊ต๋Š”๋ณดํ†ต๊ธธ์ด์˜๊ฒฝ๊ฐ„์„๊ฐ€

์ง„ ๊ต๋Ÿ‰์œผ๋กœ, ๋Œ€์šฉ๋Ÿ‰์กฐ๊ฑด์œผ๋กœ ์ธํ•œ ์••์ถ•ํ•˜์ค‘์„ ๊ฒฌ๋”œ์ •๋„๋กœ์ถฉ๋ถ„ํžˆํฐ๊ต๋Ÿ‰๊ฑฐ๋”๋ฅผ๊ฐ€์ง€๊ณ ์žˆ๋‹ค.

1. ํ˜„์ˆ˜๊ตํ†ต์ƒ์ ์œผ๋กœ ์•ต์ปค๋ธ”๋ก๊ตฌ์กฐ๋ฌผ๋กœ ์ด๋ฃจ์–ด์ง„ ํ˜„์ˆ˜๊ต๋Š”

ํ•„์š”ํ•œ๊ฒฝ๊ฐ„์ด์‚ฌ์žฅ๊ต๊ฐ€์ˆ˜์šฉํ• ์ˆ˜์žˆ๋Š”๊ฑฐ๋ฆฌ์˜์ด์ƒ์ผ๋•Œ๋งŒ ๊ฑด์„ค๋œ๋‹ค. ์ฃผ๊ฒฝ๊ฐ„์˜ ํ•œ๊ณ„๋Š” ๋ณดํ†ต 1200~1400m์ด์ง€๋งŒ, 50๋…„์ „์—๋Š” 600~700m์ด์—ˆ๋‹ค. ์ตœ๊ทผ์—๊ฑด์„ค๋œ์žฅ๋Œ€ํ˜„์ˆ˜๊ต์˜์˜ˆ๋Š”์ผ๋ณธ์˜Akashi Kaikyo(์ฃผ๊ฒฝ๊ฐ„1990m), ๋ด๋งˆํฌ์˜ Great Belt East ๊ต(์ฃผ๊ฒฝ๊ฐ„1624m), ํ™์ฝฉ์˜Tsing Ma ๊ต(์ฃผ๊ฒฝ๊ฐ„ 1377m), ๊ตญ์˜Humber ๊ต(์ฃผ๊ฒฝ๊ฐ„ 1424m), ์Šค์›จ๋ด์˜ High CoastBridge(์ฃผ๊ฒฝ๊ฐ„1210m) ๋“ฑ์ด์žˆ๋‹ค. High Coast Bridge๋Š”์ฃผ์ผ€์ด๋ธ”์„ค์น˜์—๋งค์šฐ์ ํ•ฉํ•œ๊ธฐ์ดˆ๊ณต์‚ฌ์กฐ๊ฑด์œผ๋กœ์ธํ•ด, ๋น„๊ต์ ์งง์€๊ฒฝ๊ฐ„์ผ์ง€๋ผ๋„๊ฒฝ์ œ์ ์œผ๋กœ๋Š”์ตœ์ ํ™”ํ•˜๋‹ค. ํ˜„์žฌ๊ฒฝ๊ฐ„์„๋”์šฑ๊ธธ๊ฒŒ๊ฑด์„คํ•˜๋ ค๋Š”์ถ”์„ธ์ด๋ฉฐ, ํš

๊ธฐ์ ์ธ ๋„์•ฝ์œผ๋กœ์จ 3,300m ๊ฒฝ๊ฐ„์˜ ์ดํƒˆ๋ฆฌ์•„์˜Messina Strait๋ฅผ ๊ฐ€๋กœ์ง€๋ฅด๋Š” ๊ต๋Ÿ‰์ด ๊ณ„ํš๋˜๊ณ  ํ˜„์žฌ(2005๋…„๋ด„/์—ฌ๋ฆ„) ์ž…์ฐฐ์ค‘์ด๋‹ค. ํ˜„์ˆ˜๊ต๋Š”๋•Œ๋ก ์งง์€๊ฒฝ๊ฐ„์œผ๋กœ ์‹œ๊ณต๋˜๊ธฐ๋„ ํ•˜๋Š”๋ฐ, ๊ทธ ์ด์œ ๋Š” ์‹œ๊ณต๋น„์šฉ๊ณผ ์‹œ๊ณต๊ธฐ๊ฐ„์„๋ฐฐ์ œํ•œ๊ธฐํƒ€๋‹ค๋ฅธ์ด์Šˆ๋•Œ๋ฌธ์—์„ค๊ณ„๋˜๋Š”๊ฒฝ์šฐ๋‹ค. ์˜ˆ๋กœ์จ, ๋ฏธ๊ตญ์˜ East Bay Bridge, ๊ตญ์˜Millennium Bridge์™€ํ•œ๊ตญ์˜ ์ข…๋Œ€๊ต๋“ฑ์ด์žˆ๋‹ค. ์ด๋Ÿฌํ•œ์ผ๋ฐ˜์ ์ธ์›์น™์—์˜ˆ์™ธ์ ์ธ์˜ˆ๋กœ์จํ•œ๊ตญ์˜๊ด‘์•ˆ๋Œ€

๊ต์™€๋ฏธ๊ตญ์˜Carginez ๊ต๋“ฑ์„์†๊ผฝ์„์ˆ˜์žˆ๋‹ค.

2. ์‚ฌ์žฅ๊ต์‚ฌ์žฅ๊ต๋Š”ํฌ๊ฒŒ์†Œ๊ฒฝ๊ฐ„, ์ค‘๊ฒฝ๊ฐ„, ์žฅ๋Œ€๊ฒฝ๊ฐ„๊ต๋Ÿ‰์œผ๋กœ๋‚˜

๋‰˜์–ด์ง„๋‹ค. 1990๋…„์ค‘๋ฐ˜์—์™„์„ฑ๋œ800m ์ด์ƒ์˜์ฃผ๊ฒฝ๊ฐ„๋Œ€๊ต๋กœ์จ ํ”„๋ž‘์Šค์˜ Normandy Bridge(์ฃผ๊ฒฝ๊ฐ„ 856m)์™€์ผ๋ณธ์˜Tatara Bridge(์ฃผ๊ฒฝ๊ฐ„890m) ๊ฐ€์žˆ์œผ๋ฉฐ, ์ด๋“ค์€ ๋‚˜์•„๊ฐ€ ํ˜„์žฌ ๊ฑด์„ค์ค‘์ธ ํ™์ฝฉ์˜ StonecuttersBridge(์ฃผ๊ฒฝ๊ฐ„1018m) ์™€์ค‘๊ตญ์˜Sutong Bridge(์ฃผ๊ฒฝ๊ฐ„1018 m) ๋“ฑ์žฅ๋Œ€๊ฒฝ๊ฐ„๊ต๋Ÿ‰์„๊ฑด์„คํ•˜๋Š”๊ณ„๊ธฐ๋ฅผ๋งˆ๋ จํ–ˆ๋‹ค. ์œ„๋ชจ๋“ ๊ต๋Ÿ‰์€๋น„ํ‹ˆ๊ฐ•์„ฑ์„์ฆ๊ฐ€ํ•˜๊ธฐ์œ„ํ•ด์ฃผ๊ฒฝ๊ฐ„์„ ํํ˜• ๊ฐ•๋ฐ•์Šค๊ฑฐ๋”๋กœ ์„ค์น˜ํ•˜ ์œผ๋ฉฐ, ๋ชจ๋“  ์žฅ๋Œ€์‚ฌ์žฅ๊ต๋Š”์‚ผ๊ฐ์ผ€์ด๋ธ”์‹œ์Šคํ…œ์œผ๋กœ์„ค๊ณ„ํ•˜ ๋‹ค.์ผ€์ด๋ธ”์˜ ๋ฐฐ์น˜ ๋ฐ ๋ฐฐ์—ด์€ ์žฅ๋Œ€์‚ฌ์žฅ๊ต๋ฅผ ๊ฑด์„คํ•จ์—

์žˆ์–ดํŠนํžˆ์ค‘์š”ํ•˜๋‹ค. Aํ˜•์ฃผํƒ‘์€Hํ˜•์ฃผํƒ‘์—๋น„ํ•ด์ž„๊ณ„ํ’์†์„ 20%๊นŒ์ง€ ์ฆ๊ฐ€์‹œํ‚จ๋‹ค. ํ•œ๊ตญ์—์„œ ํ˜„์žฌ ์„ค๊ณ„๋˜๊ณ ์žˆ๋Š”์ œ2 ์ข…๊ต์™€์ค‘๊ตญ์˜์ œ2 Nanjing YangtzCrossings ๊ต๋Š”์‚ผ๊ฐ์ผ€์ด๋ธ”์‹œ์Šคํ…œ๋ฐ ํํ˜•๊ฐ•๋ฐ•์Šค๊ฑฐ๋”๋ฅผ์ด์šฉํ•œ๋‹ค. ์žฅ๋Œ€์‚ฌ์žฅ๊ต์˜๊ฐ€์žฅ์ค‘์š”ํ•œ๋ณ€์ˆ˜์ค‘ํ•˜๋‚˜๋Š”ํญ-๊ฒฝ๊ฐ„๋น„์ด๋‹ค. ๊ฒฝ๊ฐ„์ดํญ์˜40๋ฐฐ์ด์ƒ์ธ๊ต๋Ÿ‰์œผ๋กœํ”„๋ž‘์Šค์˜Normandy Bridge ๊ฐ€์—ฌ์ „ํžˆ์„ธ๊ณ„์—์„œ๊ฐ€์žฅํญ์ด์ข์€๊ต๋Ÿ‰์ค‘ํ•˜๋‚˜๋กœ๊ผฝํžŒ๋‹ค.์ตœ๊ทผ ๋“ค์–ด, 400~600m ์ฃผ๊ฒฝ๊ฐ„์˜ ๋„๋กœ๊ตํ†ต์šฉ ์‚ฌ์žฅ

๊ต๊ฐ€๊ฑด์„ค๋˜๊ณ ์žˆ๋‹ค. ์ƒ๊ธฐ๋ฒ”์œ„์˜๊ฒฝ๊ฐ„์—์†Œ์š”๋˜๋Š”๊ณต์‚ฌ๋น„์šฉ๊ณผ๊ธฐ๊ฐ„์„์ตœ์ ํ™”ํ•˜๋Š”๋ฐฉ์•ˆ์œผ๋กœ์จ๊ฐœ๋ฐฉํ˜•ํ”Œ๋ ˆ์ดํŠธํ•ฉ์„ฑ๊ฑฐ๋”์™€์ฝ˜ํฌ๋ฆฌํŠธ์ฃผํƒ‘์ด๋ถ€๊ฐ๋˜๊ณ ์žˆ๋‹ค. ์ด๋Ÿฌํ•œ ํ˜•์‹์˜ ๊ต๋Ÿ‰์œผ๋กœ๋Š” ๋‹ค์Œ ์˜ˆ๊ฐ€ ์žˆ๋‹ค: ์บ๋‚˜๋‹ค์˜Alex Fraiser Bridge, ๊ตญ์˜ ์ œ2 Severn Bridge ์™€Dartfold Bridge, ํ•œ๊ตญ์˜ ์„œํ•ด๋Œ€๊ต์™€ ์‚ผ์ฒœํฌ๋Œ€๊ต, ์Šค์›จ๋ด์˜ Uddevalla Bridge, ํƒœ๊ตญ์˜ Rama 8 Bridge(Mono Tower Bridge), ์ค‘๊ตญ์˜Yangpu ๊ต, XuPu ๊ต,Ching Chau Min Yang ๊ต. ์ด๋“ค๊ณผ๋™์ผํ•œ๊ต๋Ÿ‰ํ˜•์‹์ธํ•œ๊ตญ์˜๊ฑฐ๊ฐ€๋Œ€๊ต์™€๋ฏธ๊ตญ์˜Cooper River Bridge๋Š”ํ˜„์žฌ ๊ฑด์„ค ์ค‘์— ์žˆ๋‹ค. ์ฃผ๊ฒฝ๊ฐ„์ด 600m(ํƒœํ’์ง€์—ญ์€500m)์ด์ƒ์ผ์‹œ, ์œ„์™€๊ฐ™์€ํ˜•์‹์˜๊ต๋Ÿ‰์€๋ฐ”๋žŒ์—์˜

59| ๊ธฐํš๊ธฐ์‚ฌ |

์žฅ๋Œ€๊ต๋Ÿ‰์˜ ์„ค๊ณ„ ๋ฐ ์‹œ๊ณต ๋™ํ–ฅ

ํ•œํ”Œ๋Ÿฌํ„ฐ์•ˆ์ •์„ฑ์„์ถฉ์กฑ์‹œํ‚ค๋Š”๋ฐ์–ด๋ ค์›€์ด์žˆ๋‹ค.๋‹ค์–‘ํ•œ ์ด์œ ๋กœ ์ธํ•ด ๋งŽ์€ ์†Œ๊ฒฝ๊ฐ„ ์‚ฌ์žฅ๊ต๊ฐ€ ๊ฑด์„ค๋˜

๊ณ  ์žˆ๋Š”๋ฐ, ์‚ฌ์žฅ๊ต๊ฐ€ ๊ฐ–๋Š” ๊ธฐ๋…๋น„์  ์ƒ์ง•์„ฑ๋„ ๊ทธ ์ด์œ ์ค‘์—ํ•˜๋‚˜์ด๋‹ค. ์ตœ๊ทผ์—๋Š”๋‹ค๊ฒฝ๊ฐ„์‚ฌ์žฅ๊ต๋ฅผ๊ฑด์„คํ•˜๋Š” ์ถ”์„ธ์ด๋‹ค. ํ™์ฝฉ์—์„œ๋Š” 1998๋…„ Ting Kau Bridge๊ฐ€ ์™„๊ณต๋˜์—ˆ๊ณ , ๊ทธ๋ฆฌ์Šค์˜ Rion-Antirion Bridge์™€ํ”„๋ž‘์Šค์˜ Viaduc de Maillot ์ด ์ตœ๊ทผ์— ์™„๊ณต๋˜์—ˆ๋‹ค.๋‹ค๊ฒฝ๊ฐ„ ์‚ฌ์žฅ๊ต๋Ÿ‰ ํ˜•ํƒœ๋กœ์จ ํ•œ๊ตญ์—๋Š” ๊ฑฐ๊ฐ€๋Œ€๊ต๊ฐ€ ์™„๊ณต๋  ์˜ˆ์ •์ด๋ฉฐ. ์น ๋ ˆ์˜ Chacao ํ•ดํ˜‘์—๋„ ๋‹ค๊ฒฝ๊ฐ„ ํ˜„์ˆ˜๊ต์˜๊ฑด์„ค์ด๊ณ ๋ ค๋˜๊ณ ์žˆ๋‹ค.

. ์„ค๊ณ„์˜ ๋ฐœ์ „

1. ์—ฐ๊ฒฐ๋ถ€์˜ ๋ฐœ์ „โ‘ โ‘ ์‚ฌ์‚ฌ์žฅ์žฅ๊ต๊ต์ง€์ง„๋ฐœ์ƒ์‹œ ๊ต๋Ÿ‰์ด ์ง€์ง„ํ•˜์ค‘์„ ์ง€ํƒฑํ•˜๋„๋ก

STU(Shock Transmission Units)์™€ ๊ฐ™์€ ํ˜•ํƒœ์˜์œ ์••์žฅ์น˜๋“ค์ด ์‚ฌ์šฉ๋œ๋‹ค. ์‚ฌ์šฉ๋˜๋ฉฐ, ๊ต๋Ÿ‰์˜ ์ง€์ง€์กฐ๊ฑด์„ ์กฐ์ ˆํ•˜๊ธฐ ์œ„ํ•ด์„œ๋„ ์œ ์••์žฅ์น˜๊ฐ€ ์ ์šฉ๋˜๋Š” ์ถ”์„ธ๋‹ค.๋‹จ์ผ๋‹จ๋ฉด์ผ€์ด๋ธ”์‚ฌ์žฅ๊ต์ธFaroe Bridge ๊ฒฝ์šฐ, ๊ต๋Ÿ‰๊ฑฐ๋”๋Š” ์ธก๋ฐฉํ–ฅ์œผ๋กœ๋งŒ ์ง€์ง€๋˜๊ณ , ๋น„ํ‹ˆ์€ ์ฃผํƒ‘์—์„œ ๋ฐ›์•„์ฃผ๋ฉฐ, ๊ต๋Ÿ‰๊ฑฐ๋”๋Š” ์ˆ˜์ง์œผ๋กœ๋Š” ์ž์œ ๋กญ๊ฒŒ ์›€์ง์ผ ์ˆ˜์žˆ๋‹ค. ์ •์ ์‹œ์Šคํ…œ์€ ๊ต๋Ÿ‰๊ฑฐ๋”์˜ ์–‘ ์ธก๋ฉด์— ์œ ์••ํ”ผ์Šคํ†ค์„์‚ฌ์šฉํ•˜์—ฌ์–ป์–ด์กŒ๋‹ค.Stonecutter Bridge์˜ ๊ฒฝ์šฐ, ์˜จ๋„๋ณ€ํ™”๋กœ ์ธํ•œ ๋Š

๋ฆฐ ๊ฑฐ๋™์—๋Š” ๊ต๋Ÿ‰๊ฑฐ๋”๊ฐ€ ์ž์œ ๋กญ๊ฒŒ ์›€์ง์ด๋„๋ก ํ•œ ๋ฐ˜๋ฉด, ๋™์ ํ’ํ•˜์ค‘๊ณผํ™œํ•˜์ค‘์œผ๋กœ์ธํ•œ๋น ๋ฅธ๊ฑฐ๋™์—๋Š”๊ต์ถ•๋ฐฉํ–ฅ์œผ๋กœ ์›€์ง์ž„์ด ๊ตฌ์†๋˜๋„๋ก ํ•˜ ๋‹ค. ๊ต๋Ÿ‰๊ฑฐ๋”๊ฐ€ ์ฃผํƒ‘์— ์˜ํ•ด ์ง€์ง€๋˜์ง€ ์•Š๋Š”๋‹ค๋ฉด ๋™์ ํ’ํ•˜์ค‘์œผ๋กœ์ธํ•˜์—ฌ ์ธก๊ฒฝ๊ฐ„์˜ ๊ต๊ฐ์— ๊ณผํ•˜์ค‘์ด ๋ถ€๊ฐ€๋˜๋ฉฐ, ๋ฐ”๋‹ฅํŒ์ด ์™„์ „ํžˆ ๊ณ ์ •๋œ๋‹ค๋ฉด ์˜จ๋„์˜ ํ–ฅ์œผ๋กœ ์ธํ•˜์—ฌ ์ฃผํƒ‘์—๊ณผํ•˜์ค‘์ด๋ถ€๊ฐ€๋ ๊ฒƒ์ด๋‹ค. Sutong Bridge์—์„œ๋Š” ๊ต์ถ•๋ฐฉํ–ฅ ์›€์ง์ž„์ด ์ฃผํƒ‘์—์„œ

์†๋„์— ๋”ฐ๋ผ ๋ณ€ํ•˜๋Š” ์œ ์••๋Œํผ์— ์˜ํ•ด ์–ต์ œ๋œ๋‹ค.(F=3750ยทV 0.4 ) ๊ต๋Ÿ‰๊ฑฐ๋”๋Š”์ฃผํƒ‘์—์„œ์ˆ˜์ง๋ฐฉํ–ฅ์œผ

๋กœ๊ตฌ์†๋˜์ง€์•Š๋Š”๋‹ค. ์œ„๊ต๋Ÿ‰๋“ค์˜๋˜๋‹ค๋ฅธํŠน์ƒ‰์€์ฃผํƒ‘์—์„œ์ˆ˜์ง๋ฐ›์นจ์ด์—†๊ธฐ์—์ฃผํƒ‘์˜hard point๊ฐ€์ œ๊ฑฐ๋ ์ˆ˜์žˆ๋Š”๋ฐ˜๋ฉด, ํฐ๋ชจ๋ฉ˜ํŠธ๋ฅผ์œ ๋ฐœํ• ์ˆ˜๋„์žˆ๋‹ค. Normandy๋Œ€๊ต์˜๊ฒฝ์šฐ, 116m ์ฝ˜ํฌ๋ฆฌํŠธ์บ”ํ‹ธ๋ ˆ๋ฒ„๋ฐ๊ฑฐ๋”์™€์ฃผํƒ‘์‚ฌ์ด์˜ ์ผ์ฒด์‹์ด์Œ์€ ๊ธฐ์กด์˜ ๋ฐฉ์‹๊ณผ๋Š” ๋‹ฌ๋ผ ๋ณด์ด์ง€๋งŒ,์ด๊ต๋Ÿ‰์„๋ณด๋‹ค์ž์„ธํžˆ์—ฐ๊ตฌํ•ด๋ณด๋ฉด์˜คํžˆ๋ ค์ด๋Ÿฌํ•œ๋ฐฉ์‹์ด๊ต๋Ÿ‰์—์œ ๋ฆฌํ•˜๋‹ค๋Š”๊ฒƒ์„์•Œ์ˆ˜์žˆ๋‹ค.์‹œ๊ณต๊ธฐ๊ฐ„๋™์•ˆ, ๊ฑฐ๋”์˜๊ฐ•์žฌ๋ถ€๋ถ„์€์ฃผํƒ‘์ด์•„๋‹Œ์ฃผ

๊ฒฝ๊ฐ„์œผ๋กœ116m ๋–จ์–ด์ง„์ง€์ ์—์„œ์ง€์ง€๋˜๋Š”๊ฒƒ์ฒ˜๋Ÿผ๊ฑฐ๋™ํ•ด์„œ ์ฒ˜์ง์ด ๊ฐ์†Œ๋˜์—ˆ๋‹ค. ์™„์ „๊ตฌ์†์‹œ์Šคํ…œ์ด ๊ฐ€๋Šฅํ–ˆ๋˜ ์ด์œ ๋Š” ์ฃผํƒ‘์ด ์œ ์—ฐํ•œ ๋ง๋š๊ธฐ์ดˆ์— ์ง€์ง€๋˜์—ˆ๊ณ ,๋ฐ”๋‹ฅํŒ์˜๊ณก๋ฅ ์ด์ปธ๊ธฐ๋•Œ๋ฌธ์ด๋‹ค.โ‘กโ‘กํ˜„ํ˜„์ˆ˜์ˆ˜๊ต๊ต์ „ํ†ต์ ์œผ๋กœํ˜„์ˆ˜๊ต๋Š”์‹ ์ถ•์ด์Œ๊ณผ์ฃผํƒ‘์˜์ง€์ง€์—์˜

ํ•ด 3๊ฒฝ๊ฐ„๊ตฌ์กฐ๋กœ์„ค๊ณ„๋œ๋‹ค. ๊ฒฝํ—˜์—์˜ํ•˜๋ฉด์ด๋“ค๋ถ€์œ„์—๋Œ€ํ•œ๊ด€๋ฆฌ๊ฐ€์ „์ฒด์œ ์ง€๊ด€๋ฆฌ๋น„์˜์ƒ๋‹นํ•œ๋ถ€๋ถ„์„์ฐจ์ง€ํ•œ๋‹ค. ๋”ฐ๋ผ์„œ์ผ€์ด๋ธ”์ง€์ง€๊ตฌ๊ฐ„์ „์ฒด์—์„œ์—ฐ์†์ธ๊ฑฐ๋”์‹œ์Šคํ…œ์ด ์„ ํ˜ธ๋˜๋ฉฐ ์ด๋Š” ๋ด๋งˆํฌ์˜ Great BeltEast Bridge ์™€์Šค์›จ๋ด์˜High Coast Bridge ์—์‚ฌ์šฉ๋˜์—ˆ๋‹ค. ์ฃผํƒ‘์„๊ด€ํ†ตํ•˜๋Š”์—ฐ์†ํ˜•๊ฑฐ๋”์—์„œ๊ทน๋ณตํ•ด์•ผํ•  ํ•˜๋‚˜์˜ ๋ฌธ์ œ์ ์€ ์ผ€์ด๋ธ” ์ƒˆ๋“ค๋‚ด ์ฃผ์ผ€์ด๋ธ”์˜ ๊ฐํšŒ์ „์œผ๋กœ ์ธํ•ด ๋ฐœ์ƒํ•˜๋Š” ํœจ๋ชจ๋ฉ˜ํŠธ์„ ์กฐ์ ˆํ•˜๋Š” ๊ฒƒ์ด์—ˆ๋‹ค. ์ผ€์ด๋ธ”์ด ์ฒ˜์ง€๊ฒŒ ๋˜๋ฉด ๊ฑฐ๋”๋„ ๋”ฐ๋ผ ์ฒ˜์ง€๊ฒŒ ๋˜๊ณ ,์ด๋•Œ ํœจ๋ชจ๋ฉ˜ํŠธ๊ฐ€ ๋ฐœ์ƒํ•˜๊ธฐ ๋•Œ๋ฌธ์ด๋‹ค. ๊ณ ์ •ํ•˜์ค‘๊ณผ ํ™œํ•˜์ค‘์œผ๋กœ์ธํ•ด๋ฐœ์ƒํ•˜๋Š”๋ชจ๋ฉ˜ํŠธ๋ฅผ์ตœ์†Œํ™”์‹œํ‚ค๊ณ , ๋ฐ›์นจ์ƒํƒœ๋ฅผ์ตœ์ ํ™”ํ•˜๊ธฐ์œ„ํ•ดํ–‰์–ด๊ฑฐ๋ฆฌ์˜๋ณ€์ˆ˜๋ถ„์„์—ฐ๊ตฌ, ํ–‰์–ด์˜ ์ข…๋ฅ˜ (locked ์ฝ”์ผํ˜• ๋˜๋Š” ํ‰ํ–‰ํ˜• ์ฒ ์„ ),ํ–‰์–ดํ•˜์ค‘์˜์กฐ์ ˆ, ๊ฑฐ๋”์˜๊ฐ•๋„, ์ฃผํƒ‘์—์„œ์˜์ˆ˜์งํ•˜์ค‘์„์ง€์ง€ํ•˜๊ธฐ์œ„ํ•œ๊ฑฐ๋”์˜์ƒํƒœ๋“ฑ์ด๊ณ ๋ ค๋˜์—ˆ๋‹ค.

2. ํํ˜• ๋ฐ•์Šค๊ฑฐ๋”์˜ ๊ฐœ๋…ํํ˜•๊ฐ•๋ฐ•์Šค๊ฑฐ๋”๋Š”1960๋…„๋Œ€๋ด๋งˆํฌ์˜Little Belt

Bridge์™€ ๊ตญ์˜Severn ํ˜„์ˆ˜๊ต์—์„œ์ตœ์ดˆ๋กœ๋„์ž…๋œ๊ฐœ๋…์ด๋‹ค. ํํ˜•๋ฐ•์Šค๊ฑฐ๋”์˜์žฅ์ ์€๋น„ํ‹ˆ๊ฐ•์„ฑ์ด๋†’์€๊ฒƒ๊ณผ๋น„๊ต์ ๋‹จ์ˆœํžˆ์ž๋™ํ™”๋œ์กฐ๋ฆฝ๊ณผ์šฉ์ดํ•œ์œ ์ง€๊ด€๋ฆฌ์—

60 | ์ œ53๊ถŒ ์ œ6ํ˜ธ 2005๋…„ 6์›” |

์žฅ๋Œ€๊ต๋Ÿ‰ ๊ฑด์„ค ๋ฐ ๊ธฐ์ˆ 

์žˆ๋‹ค. ์—ฌ๋Ÿฌ๊ฐœ์˜๋ชจ์„œ๋ฆฌ์™€์™ธ๋ถ€๋…ธ์ถœ๋ฉด์ ์ด๋„“์€๋ณต์žกํ•œํ˜•ํƒœ์˜๊ตฌ์กฐ๋ฌผ์€์‰ฝ๊ฒŒ๋…ธํ›„ํ™”๋˜๋ฏ€๋กœ, ํํ˜•๊ฐ•๋ฐ•์Šค๊ฑฐ๋”์ฒ˜๋Ÿผ์ตœ์†Œํ•œ์˜๋…ธ์ถœ๋งŒ์„ํ—ˆ์šฉํ•˜๋Š”๊ฐ„๋‹จํ•œ๊ตฌ์กฐ๋ฌผํ˜•ํƒœ๊ฐ€์„ ํ˜ธ๋œ๋‹ค. ๋งค๋„๋Ÿฌ์šด์™ธ๊ณฝํ‘œ๋ฉด์€์™ธ๋ถ€์—์ตœ์†Œํ•œ์œผ๋กœ๋…ธ์ถœ์ด๋˜์–ด์œ ์ง€๊ด€๋ฆฌ๊ฐ€์šฉ์ดํ•˜๋‹ค. ๋ฐ•์Šค๊ฑฐ๋”์˜๋‚ด๋ถ€๋Š”๋ณด๊ฐ•์žฌ๊ณผ๊ฒฉ๋ฒฝ์œผ๋กœ์ด๋ฃจ์–ด์ ธ๊ฐ•์žฌ๋ฉด์ ์˜์ด80% ์ •๋„๋ฅผ์ฐจ์ง€ํ•˜๊ณ ์žˆ์œผ๋ฉฐํƒˆ์Šต์€๋ถ€์‹์„๋ฐฉ์ง€ํ•˜๊ธฐ๋•Œ๋ฌธ์—๋„์ƒ‰์„ํ• ํ•„์š”๊ฐ€์—†๋‹ค. ํƒˆ์Šต์˜์›๋ฆฌ๋Š”๋ฐ•์Šค๋‚ด๋ถ€์˜์ƒ๋Œ€์Šต๋„๋ฅผ 40% ์ดํ•˜๋กœ ๋‚ด๋ฆฌ๊ณ , ๋ถ€์‹์ด ๋ฐœ์ƒํ•  ์ˆ˜ ์žˆ๋Š”ํ•œ๊ณ„๋งˆ์ง„์„60% ์ •๋„๊นŒ์ง€์œ ์ง€์‹œํ‚ค๋Š”๊ฒƒ์ด๋‹ค. ์ด๋ฅผ์œ„ํ•ด์„ ๋‚ด๋ถ€์˜๊ณต๊ธฐ๋ฅผ์ˆœํ™˜์‹œํ‚ค๋Š”๊ฐ„๋‹จํ•œํ™˜ํ’์‹œ์Šคํ…œ๊ณผ์Šต๊ธฐํก์ˆ˜ํ•„ํ„ฐ๊ฐ€์žฅ์ฐฉ๋œํƒˆ์Šต๊ธฐ๋ฅผ์„ค์น˜ํ•˜๋ฉด๋œ๋‹ค.

ํํ˜•๊ฐ•๋ฐ•์Šค๊ฑฐ๋”๋Š”๊ณต๊ธฐ์—ญํ•™์ ํšจ์œจ์„ฑ๋„ํƒ์›”ํ•˜๋‹ค. ๋†’์€ ๋น„ํ‹ˆ ๊ฐ•์„ฑ์€ ์ž„๊ณ„ ํ”Œ๋Ÿฌํ„ฐํ’์†์„ ์ฆ๊ฐ€์‹œํ‚ค๋ฉฐ, ๊ณต๊ธฐ๋ ฅ๊ณ„์ˆ˜์™€๊ทธ๊ธฐ์šธ๊ธฐ๋ฅผ์ค„์—ฌ์„œํ’ํ•˜์ค‘ํšจ๊ณผ๋ฅผ๊ฐ์†Œ์‹œํ‚จ๋‹ค.

3. ๊ณต๊ธฐ์—ญํ•™(Aerodynamic)๋ฏธ๊ตญTacoma Narrows ํ˜„์ˆ˜๊ต์˜๋ถ•๊ดด๋Š”์žฅ๋Œ€๊ต๋Ÿ‰

์˜์„ค๊ณ„์™€์‹œ๊ณต๋ฐœ์ „์˜์นจ์ฒดํ˜„์ƒ์„์ดˆ๋ž˜ํ•˜ ๋‹ค. ์ดํ›„์‚ฌ๊ณ ์˜ ๋ผˆ์ €๋ฆฐ ๊ฒฝํ—˜์„ ๋ฐ”ํƒ•์œผ๋กœ ๊ฑด์„ค๋œ ๊ต๋Ÿ‰์—๋Š” ๋‘๊บผ์šด๊ฐ•ํŠธ๋Ÿฌ์Šค๊ฑฐ๋”๊ฐ€์‚ฌ์šฉ๋˜์—ˆ๊ณ , ์˜ˆ์ธก๋ถˆํ—ˆํ•œ์ง„๋™์˜๊ทผ์›๊นŒ์ง€์ฒ ์ €ํžˆ์กฐ์‚ฌ๋˜์—ˆ๋‹ค. ํ˜„์žฌํ’๋™์‹คํ—˜์€๋ชจ๋“ ์žฅ๋Œ€๊ต๋Ÿ‰์„ค๊ณ„์—์žˆ์–ด๊ธฐ๋ณธ์ด๋ฉฐ, ๊ต๋Ÿ‰๊ฑฐ๋”์˜๋ถ€๋ถ„๋ชจํ˜•์‹คํ—˜๋ฐ3์ฐจ์›์ „๊ต๋ชจํ˜•์‹คํ—˜๋“ฑ์˜ํ˜•ํƒœ๋กœ์ด๋ฃจ์–ด์ง„๋‹ค. ๊ฒฝ์šฐ์— ๋”ฐ๋ผ ์ด๋Ÿฌํ•œ ์‹คํ—˜์— High Reynold'sNumber์‹คํ—˜, ์ผ€์ด๋ธ”์ง„๋™์‹คํ—˜, ์ง€ํ˜•๋ชจ๋ธ์‹คํ—˜ ๋˜๋Š”ํ’ํ–ฅ๊ธฐํ›„์˜ ํ˜„์žฅ๊ณ„์ธก ๋“ฑ์ด ์ถ”๊ฐ€๋œ๋‹ค. COWI์‚ฌ๋Š” ์ปดํ“จํ„ฐ ๊ธฐ์ˆ ์„ ํ†ตํ•ด ๊ต๋Ÿ‰๊ฑฐ๋”์™€ ๋น„๊ตํ•ด ๋ณด๋‹ค ํšจ๊ณผ์ ์ธDVMFlow๋ฅผ ๊ฐœ๋ฐœํ•˜ ๋‹ค. ๊ต๋Ÿ‰ ๋‹จ๋ฉด๋„๋ฅผ ๊ธฐ์ดˆ๋กœ,DVMFlow๋Š”์ •์ ๊ณต๊ธฐ๋ ฅ๊ณ„์ˆ˜(ํ•ญ๋ ฅ๊ณ„์ˆ˜), ํ”Œ๋Ÿฌํ„ฐ๊ณ„์ˆ˜,์™€๋ฅ˜์ง„๋™์œผ๋กœ์ธํ•œ๋™์ ๊ฑฐ๋™๋“ฑ์„์‚ฐ์ถœํ•œ๋‹ค. ์ด๋Š”๊ณง๊ฐ๊ธฐ๋‹ค๋ฅธ๋‹จ๋ฉด์—๋Œ€ํ•œํ‰๊ฐ€๋ฅผ๋‹จ์‹œ๊ฐ„๋‚ดํ’๋™์‹คํ—˜์—†์ด์‹คํ–‰ํ• ์ˆ˜์žˆ๋‹ค๋Š”์˜๋ฏธ์ด๊ธฐ๋„ํ•˜๋‹ค. ๊ฐ€์ƒํ’๋™์‹คํ—˜์€์‹ค์ œํ’๋™์‹คํ—˜๋Œ€๋น„์‹œ๋งŒ์กฑํ• ๋งŒํ•œ๊ฒฐ๊ณผ๋ฅผ๋ณด ๋‹ค.

4. ๋‚ด๊ตฌ์„ฑ(Durability)60๋…„๋Œ€์™€ ์ดํ›„ ์„œ๋ฐฉ๊ตญ๊ฐ€์—๊ฒŒ๋Š” ๊ฒฝ์ œ์ ์œผ๋กœ ์ค‘์š”ํ•œ

์„ฑ์žฅ๊ธฐ ๊ณ , ์ด๋Š”๊ณง์ˆ˜์ฒœ๊ฐœ์˜๊ต๋Ÿ‰์„ํฌํ•จํ•ด๊ธฐ๋ฐ˜์‹œ์„ค๋ฌผ์—๋Œ€ํ•œ๋Œ€๋Œ€์ ์ธํˆฌ์ž๋กœ์ด์–ด์กŒ๋‹ค. ์ดˆ๊ธฐ์‹œ๊ณต๋น„์šฉ์„์ €๋ ดํ•˜๊ฒŒ์ฑ…์ •ํ•˜๊ณ ๊ณต์‚ฌ๊ธฐ๊ฐ„์„๋‹จ์ถ•์‹œํ‚ค๋Š”๋ฐ์ง‘์ค‘ํ•œ๊ฒฐ๊ณผ๋Š” ๊ต๋Ÿ‰์— ๋ฐœ์ƒํ•˜๋Š” ์†์ƒ์˜ ์ฆ๊ฐ€๋กœ ์ด์–ด์กŒ๋‹ค. ์ดํ›„,๋Œ€๋ถ€๋ถ„์ฃผ์š”ํ”„๋กœ์ ํŠธ์˜์„ค๊ณ„์š”๊ฑด์œผ๋กœ100๋…„์ด์ƒ์‚ฌ์šฉํ• ์ˆ˜์žˆ๋Š”๊ต๋Ÿ‰์˜์„ค๊ณ„๊ฐ€ํ•„์ˆ˜์กฐ๊ฑด์ด๋˜์—ˆ๊ณ , ๊ฒฐ๊ณผ์ ์œผ๋กœ๊ต๋Ÿ‰์‹œ๊ณต๊ธฐ์ˆ ๋ฐœ์ „์—์ค‘๋Œ€ํ•œ์ „๊ธฐ๋ฅผ๋งˆ๋ จํ•˜ ๋‹ค.๊ต๋Ÿ‰์‹œ๊ณต์—์žˆ์–ดํƒˆ์Šต์›๋ฆฌ๋Š” ํํ˜•๊ฐ•๋ฐ•์Šค๊ฑฐ๋”์—

์„œ ์ตœ์ดˆ๋กœ ๋„์ž…์ด ๋œ ์ด๋ž˜, ํƒ€ ๊ตฌ์กฐ๋ถ„์•ผ์—๋„ ๋นˆ๋ฒˆํžˆ์‘์šฉ๋˜๊ณ  ์žˆ๋‹ค. Oresund Bridge์—์„œ๋Š” ํŠธ๋Ÿฌ์Šค ๊ตฌ์กฐ์˜ ๋‚ด๋ถ€๋ฅผ ํƒˆ์Šตํ•˜์—ฌ ๋ถ€์‹๋ฐฉ์ง€๋ฅผ ํ•˜๋„๋ก ํ•˜ ์œผ๋ฉฐ,์ผ๋ณธ์˜Akashi ํ˜„์ˆ˜๊ต์˜์ฃผ์ผ€์ด๋ธ”์—ญ์‹œํƒˆ์Šต์œผ๋กœ์ธํ•ด๋ถ€์‹์„๋ฐฉ์ง€ํ•˜๊ณ ์žˆ๋‹ค. ์ฃผ์ผ€์ด๋ธ”์˜ํƒˆ์Šต์›๋ฆฌ๋Š”ํ”„๋ž‘์Šค์˜ Agitaine ํ˜„์ˆ˜๊ต์™€ ๋ด๋งˆํŠธ์˜ Little Belt ํ˜„์ˆ˜๊ต์—๋„๋„์ž…๋˜์—ˆ๋‹ค. ๊ต๋Ÿ‰์˜๋ณด์ˆ˜์™€๊ด€๋ จํ•˜์—ฌ, ์‚ฌ์žฅ์ผ€์ด๋ธ” ๊ณต๊ธ‰์—…์ž๋“ค์€ ํ˜„์žฌ ์‚ฌ์žฅ์ผ€์ด๋ธ”์ด ํƒˆ์Šต๋ณดํ˜ธ๋ ์ˆ˜์žˆ๋„๋ก์—ฐ๊ตฌํ•˜๊ณ ์žˆ๋‹ค.์ฝ˜ํฌ๋ฆฌํŠธ์˜ ๋‚ด๊ตฌ์„ฑ์„ ๊ฐ•ํ™”ํ•˜๊ธฐ ์œ„ํ•œ ํ•ฉ๋ฆฌ์ ์ธ ๋ฐฉ

์•ˆ์œผ๋กœ์œ ๋Ÿฝ๊ณต๋™์ฒด์˜์žฌ์ •์ง€์›ํ•˜์—ฐ๊ตฌํ”„๋กœ์ ํŠธ๋ฅผํ†ตํ•ด DuraCrete์ด ๊ฐœ๋ฐœ๋˜์—ˆ๋‹ค. ์ด๋Š” ํด๋กœ๋ผ์ด๋“œ ์นจํˆฌ๋กœ์ธํ•œ์ฒ ๊ทผ์˜ํƒˆ๋ถ€๋™ํƒœํ™”์‹œ๊ฐ„์„ํ™•๋ฅ ์ ๊ณต๋ฒ•์„ํ†ตํ•ด ์˜ˆ์ธกํ•˜๋Š” ์›๋ฆฌ์ด๋‹ค. ์ฝ˜ํฌ๋ฆฌํŠธ๊ตฌ์กฐ๋ฌผ์˜ ๋‚ด๊ตฌ์„ฑ์€์ฝ˜ํฌ๋ฆฌํŠธ๋ฎ๊ฐœ, ์ฝ˜ํฌ๋ฆฌํŠธ์˜ ์นจํˆฌ์„ฑ(ํด๋กœ๋ผ์ด๋“œ ํ™•์‚ฐ),์ฃผ์œ„ ์กฐ๊ฑด ๋“ฑ์—(ํด๋กœ๋ผ์ด๋“œ ํ•จ๋Ÿ‰) ์˜ํ•ด ๊ฒฐ์ •๋œ๋‹ค. ๊ตฌ์กฐ๋ฌผ์˜์ž„๊ณ„๋ฒ”์œ„์—์„œ์•…์ฒœํ›„๋Œ€๋น„์šฉ์œผ๋กœ์Šคํ…Œ์ธ๋ ˆ์Šค์ฒ ๊ทผ์„์‚ฌ์šฉํ•˜๋Š”๊ฒƒ์€์ด๋ฏธ์ผ๋ฐ˜ํ™”๊ฐ€๋˜์—ˆ๋‹ค. ํ™์ฝฉ์˜Stonecutter Bridge ๊ฒฝ์šฐ, ์ฃผํƒ‘์˜ ์™ธ๋ถ€์ธต ๋ณด๊ฐ•์ฒ ๊ทผ์œผ๋กœ์Šคํ…Œ์ธ๋ ˆ์Šค์ฒ ๊ฐ•์„์‚ฌ์šฉํ•œ๋‹ค.

5. ํ™•๋ฅ ๋ก ์  ๋ฐฉ๋ฒ•(Probabilistic Methods)ํ™•๋ฅ ๋ก ์  ๋ฐฉ๋ฒ•์€ ๊ต๋Ÿ‰์˜ ์„ค๊ณ„์— ์žˆ์–ด ์ ์  ๊ฐ๊ด‘์„

๋ฐ›๊ณ  ์žˆ๋‹ค. ๋‚ด๊ตฌ์„ฑ์„ ์‚ฐ์ถœํ•˜๋Š” ๊ฒƒ ์ด์™ธ์—๋„, ํ™•๋ฅ ๋ก ์  ๋ฐฉ๋ฒ•์€ ์„ ๋ฐ• ์ถฉ๋Œํ•˜์ค‘์„ ์‚ฐ์ •ํ•˜๋Š”๋ฐ๋„ ์‚ฌ์šฉ๋˜์–ด

61| ๊ธฐํš๊ธฐ์‚ฌ |

์žฅ๋Œ€๊ต๋Ÿ‰์˜ ์„ค๊ณ„ ๋ฐ ์‹œ๊ณต ๋™ํ–ฅ

์ง„๋‹ค. ํ•ด์ƒํ•ญ๋กœ์˜ ์‹œ๋‚˜๋ฆฌ์˜ค์—์„œ ๊ต๋Ÿ‰์„ ํ†ต๊ณผํ•˜๋Š” ์„ ์  ํ•ญํ•ด์˜ ์ถ”์ • ๋ฐ ๋ถ„ํฌ๋„์— ๋”ฐ๋ผ, ๋ถ•๊ดด์˜ ๊ฐ€๋Šฅ์„ฑ์ด์ถ”์ •๋˜์–ด์ง€๊ธฐ๋„ ํ•œ๋‹ค. AASTHO๋Š” ์„ ๋ฐ•์ถฉ๋Œ๋กœ ์ธํ•œ๋ถ•๊ดดํ™•๋ฅ ์„ 10000๋…„ ์žฌํ˜„์ฃผ๊ธฐ์— ๊ทผ๊ฑฐํ•˜๋„๋ก ๊ทœ์ •ํ•˜๊ณ  ์žˆ๋‹ค. ์ด ๋ฐฉ๋ฒ•์„ ์‚ฌ์šฉํ•  ๊ฒฝ์šฐ, ์˜ˆ์ปจ๋Œ€ ํ•ญ๋กœ์•ˆ๋‚ด์„œ๋˜๋Š” ๊ฐ์‹œ์‹œ์Šคํ…œ ๋“ฑ์„ ํ™œ์šฉํ•ด ์œ„ํ—˜์„ ๋ฏธ์—ฐ์— ์™„ํ™”์‹œํ‚ฌ์ˆ˜์žˆ๋Š”๋ฐฉ๋ฒ•๋“ค์„์ˆ˜์น˜ํ™”ํ• ์ˆ˜์žˆ๋‹ค.๋˜ํ•œ ๋‹ค๋ฅธ ๊ณณ์—์„œ ์œ„ํ—˜์„ ๊ฐ์ˆ˜ํ•˜๊ธฐ ๋ณด๋‹ค ๊ธฐ์ดˆ๊ฐ€ ๋ถ€

์‹คํ•œ ๊ณณ์—์„œ ๋†’์•„์ง„ ์œ„ํ—˜๋ถ€๋‹ด์„ ์ˆ˜์šฉํ•˜๋Š” ๊ฒƒ๊ณผ ๊ฐ™์€๋ฐฉ๋ฒ•์œผ๋กœ์„ค๊ณ„๋Š”์ตœ์ ํ™”๋ ์ˆ˜์žˆ๋‹ค. ๊ฑฐ๊ฐ€๋Œ€๊ต์˜์„ ๋ฐ•์ถœ๋™ํ•˜์ค‘์˜๊ธฐ์ค€๋„์ด๋Ÿฌํ•œ๊ธฐ์ค€์—์˜ํ•ด์ˆ˜๋ฆฝ๋˜์—ˆ๋‹ค.ํ™•๋ฅ ๋ก ์ ๋ฐฉ๋ฒ•์€๋ณด์ˆ˜๊ณต์‚ฌ์‹œ๊ตฌ์กฐ๋ฌผ์˜์ž”์กด์ˆ˜๋ช…์„

์žฌํ‰๊ฐ€ํ•˜๋Š”๋ฐ์‚ฌ์šฉ๋˜๊ธฐ๋„ํ•œ๋‹ค.

. ์‹œ๊ณต์˜ ๋ฐœ์ „

๊ต๋Ÿ‰์˜์กฐ๋ฆฝ๊ณผ์ œ์ž‘์€๋Œ€๋ถ€๋ถ„ํ•ด์•ˆ์ง€์—ญ๋ฐ๊ต๋Ÿ‰์ธ๊ทผ์ง€์—ญ์—์„œ ์ง€์ƒ์กฐ๋ฆฝ์œผ๋กœ ์ด๋ฃจ์–ด์ง„๋‹ค. Great BeltWest Bridge์˜๊ฒฝ์šฐ, ์ด324์˜์ง€์ƒ์กฐ๋ฆฝ๋ถ€๋ถ„์œผ๋กœ์ด๋ฃจ์–ด์กŒ์œผ๋ฉฐ, ์ด์ค‘ ์ผ€์ด์Šจ 26๊ฐœ, 124๊ฐœ์˜ pier shaft,138๊ฐœ์˜ ๊ต๋Ÿ‰๊ฑฐ๋”๋“ฑ์ด ์ธ๊ทผ ์ง€์ƒ์กฐ๋ฆฝ์žฅ์—์„œ ์กฐ๋ฆฝ๋˜์—ˆ๋‹ค. ์ด๋“ค์€ 5๊ณณ์˜ ์ƒ์‚ฐ๋ผ์ธ์„ ํ†ตํ•ด ์ œ์ž‘์ด ๋œ ํ›„,๊ตฌ์กฐ๋ฌผ์€ ๋ฏธ๋„๋ŸผํŒ์„ ํ†ตํ•ด ๋„๋ฅ˜์ œ๋กœ ์ด๋™๋˜๊ณ , ํŠน๋ณ„์กฐ๋ฆฝ๋œ ํ•ด์ƒํฌ๋ ˆ์ธ(The Swan) ์„ ์ด์šฉํ•˜์—ฌ ๊ต๋Ÿ‰๊ฑด์„คํ˜„์žฅ์œผ๋กœ ์ˆ˜์†ก๋œ๋‹ค. ํ•ด์ƒํฌ๋ ˆ์ธ์€ 7,400ํ†ค ๋ฌด๊ฒŒ์˜์ผ€์ด์Šจ์„1.5 m๋‘๊ป˜์˜์‡„์„๊ธฐ์ดˆ์ง€๋ฐ˜์—ํƒ‘์žฌํ•œ๋‹ค. ๋ด๋งˆํฌ์™€ ์Šค์›จ๋ด์„ ์—ฐ๊ฒฐํ•˜๋Š” Oresund Bridge์˜

๊ฒฝ์šฐ, ๊ต๋Ÿ‰์˜ ๊ฐ•ํŠธ๋Ÿฌ์Šค ๋ฐ ์ฝ˜ํฌ๋ฆฌํŠธ๋ฐ”๋‹ฅํŒ์€ ์ŠคํŽ˜์ธ์—์„œ์ œ์ž‘๋˜์—ˆ๋‹ค. ์ด๊ธธ์ด 140m์— 7,000ํ†ค์˜๊ฑฐ๋”๋ถ€๋ถ„์€ ๋ฐ”์ง€์„ ์— ์„ ์ ๋œ ํ›„ ๊ต๋Ÿ‰ํ˜„์žฅ์œผ๋กœ ์ˆ˜์†ก๋˜๊ณ ,Storebalt West Bridge ํ˜„์žฅ์—์„œ๋„ ์‚ฌ์šฉ๋œ ํ•ด์ƒํฌ๋ ˆ์ธ์„์ด์šฉํ•˜์—ฌ๊ต๊ฐ์—์˜ฌ๋ ค๋†“์•„์ง€๊ฒŒ๋œ๋‹ค. ๋ด๋งˆํฌ๋‚ด 2๊ฐœ์˜ ๊ต๋Ÿ‰์˜ ๊ฑด์„ค์— ์‚ฌ์šฉ๋˜์–ด์ง„ ํ•ด์ƒํฌ๋ ˆ์ธ์€๊ธฐ์ค‘๋ ฅ์„8,700ํ†ค์œผ๋กœ์ฆ๊ฐ€ํ•˜๊ณ ์ผ๋ถ€๋ณ€๊ฒฝ์ž‘์—…์„๊ฑฐ

์ณ, ์บ๋‚˜๋‹ค์˜ 13km Prince Edward Island Bridge๋ฅผ๊ฑด์„คํ•˜๋Š”๋ฐ๋„์‚ฌ์šฉ๋˜์—ˆ๋‹ค.๊ต๋Ÿ‰๊ฑฐ๋”๋Š” ๋ชจ๋‘ ํ•ด์ƒํฌ๋ ˆ์ธ์„ ์ด์šฉํ•ด ์„ค์น˜๋˜์—ˆ

๋‹ค. ์‚ฌ์žฅ๊ต์˜๊ฒฝ์šฐ์ผ€์ด๋ธ”๋กœ๋งค๋‹ฌ๊ธฐ์ด์ „ 140m ๊ตฌ์—ญ์—์„œ ๊ฐ€์„ค์ง€์ง€๊ตฌ์กฐ๋ฌผ์— ๊ฑฐ๋”๊ฐ€ ์„ค์น˜๋œ๋‹ค. ๋ณธ ๋ฐฉ๋ฒ•์€์‚ฌ์žฅ๊ต์—์„œ๋Š” ๋“œ๋ฌผ๊ฒŒ ์“ฐ์ด๋Š” ๋ฐฉ๋ฒ•์ด์ง€๋งŒ, ํ•ด์ƒํฌ๋ ˆ์ธ์„ ํ†ตํ•ด ์‹œ๊ณต๊ธฐ๊ฐ„๊ณผ ํ•ด์ƒ๊ตํ†ตํ˜ผ์žก์„ ๊ฐ์†Œ์‹œํ‚ฌ ์ˆ˜์žˆ๊ธฐ์— ์ฐจ์ธฐ ์„ ํ˜ธ๋˜๊ณ  ์žˆ๋‹ค. ๊ฑฐ๊ฐ€๋Œ€๊ต ์—ญ์‹œ ์ผ€์ด์Šจ,๊ต๊ฐ ๋ถ€์žฌ, ๊ต๋Ÿ‰ ๊ฑฐ๋” ๋“ฑ์€ ์ง€์ƒ์กฐ๋ฆฝ์„ ํ†ตํ•ด ์ œ์ž‘์ด๋˜์–ด์ง€๊ณ , ํ•ด์ƒํฌ๋ ˆ์ธ์„ ํ†ตํ•ด ๊ฑด์„คํ˜„์žฅ์œผ๋กœ ์ˆ˜์†ก๋ ์˜ˆ์ •์ด๋‹ค. ์ง€์ƒ์กฐ๋ฆฝ์€ ์ง€๊ทนํžˆ ์‚ฐ์—…ํ™”๋œ ์ƒ์‚ฐ๋ผ์ธ์„ํ†ตํ•ด ๊ตฌ์กฐ๋ฌผ์˜ ์งˆ์„ ์‰ฝ๊ฒŒ ํ–ฅ์ƒ์‹œํ‚ฌ ์ˆ˜ ์žˆ์„ ๋ฟ๋งŒ ์•„๋‹ˆ๋ผ, ์•…์ฒœํ›„์— ๋Œ€ํ•œ ๋Œ€์ฒ˜ ๋ฐ ์žฅ๋น„์˜ ์ˆ˜์†ก์ด ์šฉ์ดํ•˜๊ณ ํ˜„์žฅ์—์„œ์˜๋…ธ๋™๋ ฅ์„์ ˆ๊ฐ์‹œํ‚ฌ์ˆ˜์žˆ๋‹ค.

. ๋งบ์Œ๋ง

์ „์„ธ๊ณ„์ ์œผ๋กœ ๋Œ€๋ถ€๋ถ„์˜ ๊ต๋Ÿ‰์„ค๊ณ„์™€ ์‹œ๊ณต์— ๊ด€ํ•œ์ถ”์„ธ ๋ฐ ๋™ํ–ฅ์€ ๋Œ€์ฒด์ ์œผ๋กœ ํก์‚ฌํ•˜๋‹ค. ๊ต๋Ÿ‰ํ”„๋กœ์ ํŠธ์˜๊ทœ๋ชจ์™€์žฆ์€๋นˆ๋„์ˆ˜๋•Œ๋ฌธ์—, ๊ณต์‚ฌ์ดˆ๊ธฐ๋‹จ๊ณ„์—์„œ๊ทผ๋ž˜์˜์œ ์‚ฌํ•œํ”„๋กœ์ ํŠธ๋ฅผ๊ตฌ๋ณ„ํ• ์ˆ˜์žˆ๋‹ค. ์ด์™€๋งˆ์ฐฌ๊ฐ€์ง€๋กœ, ํ•œ๊ตญ์—์„œ์ตœ๊ทผ์ง„ํ–‰์ค‘์ธํ”„๋กœ์ ํŠธ๋˜ํ•œ์ตœ์ฒจ๋‹จ์„ค๊ณ„์™€์‹œ๊ณต๊ธฐ์ˆ ์„๋ฐ˜ ํ•œ๋‹ค. ์„ค๊ณ„์™€์‹œ๊ณต์ด๋ถ„๋ฆฌ๋ฐœ์ฃผ๋˜๋Š”์ „ํ†ต์ ์ธ๊ณต๊ณต๋ฐœ์ฃผ๋ฐฉ์‹์—์„œ์„ค๊ณ„์™€์‹œ๊ณต์„๋™์‹œ์— ์ˆ˜ํ–‰ํ•˜๋Š” ํ”„๋กœ์ ํŠธ ๋ฐฉ์‹ ๋ฐ BOT(์‹œ๊ณต-์šด ์ดํ›„์†Œ์œ ๊ถŒ์ด์ „) ๋ฐฉ์‹์œผ๋กœ์ „ํ™˜๋˜๊ณ ์žˆ์–ด, ๋„๊ธ‰์ž์˜์ฑ…์ž„์ด์ปค์กŒ๋‹ค. ๋Œ€๋ถ€๋ถ„์ด๋Ÿฌํ•œ์ฃผ์š”ํ”„๋กœ์ ํŠธ๋Š”๊ธฐ๋…๋น„์  ๊ฐ€์น˜๋ฅผ ๊ฐ–๊ฒŒ ๋˜๊ธฐ ๋•Œ๋ฌธ์—, ๋ฏธ๊ด€ ์—ญ์‹œ ์ค‘์š”์‹œํ•˜๋Š”์ถ”์„ธ๋‹ค. Stonecutters Bridge์˜ ๊ฒฝ์šฐ, ๊ตญ์ œ๊ฒฝ์Ÿ์ž…์ฐฐ์„ ํ†ตํ•ด ๊ต๋Ÿ‰์„ค๊ณ„์—…์ฒด๊ฐ€ ์„ ์ •๋˜์—ˆ๋‹ค. ๊ฑฐ๊ฐ€๋Œ€๊ต์˜ ๊ฒฝ์šฐ์—๋„ ๊ต๋Ÿ‰์— ํƒ์›”ํ•œ ์™ธ๊ด€์  ๋ฏธ๊ด€์„ ์ถ”๊ฐ€ํ•˜๊ธฐ ์œ„ํ•œํŠน๋ณ„ํ•œ๋…ธ๋ ฅ์ด๊ธฐ์šธ์–ด์กŒ์œผ๋ฉฐ, ์ด๋กœ์ธํ•ด๋ถ€์‚ฐ-๊ฑฐ์ œ๋„์‚ฌ์ด์˜๊ฐ€๊ต์—ญํ• ์„๋ฉ‹์ง€๊ฒŒ์ˆ˜ํ–‰ํ• ๊ฒƒ์ด๋‹ค.

๊ตญ๋ฌธ๋ฒˆ์—ญ : ์ด์„ธ๋ จ ๋Œ€๋ฆฌ [email protected]