KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015...
Transcript of KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015...
![Page 1: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/1.jpg)
KINGSTON SOLAR LP Sol-Luce Project Overview
May 27, 2015
![Page 2: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/2.jpg)
KINGSTON SOLAR LP | 2
TABLE OF CONTENTS
• Project Update
• Overview of the Project Schedule
• Work Completed to Date
• Remaining Construction Plans
• Mitigating Road Conditions
• Update re Berm Construction and Landscaping
• Questions / Clarifications
• Contact Info
![Page 3: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/3.jpg)
KINGSTON SOLAR LP | 3
CONSTRUCTION WELL UNDERWAY
Civil Works
• Storm Water Management Plan
• Clearing & Grubbing, Landscaping
• Access Road Construction
• Final Grading & Drainage
• Seeding & Landscaping
Structural Works
• Inverter House Foundations
• Switchyard Foundations
• Solar Racking Foundations
• Pole Line Foundations
Electrical Works
• Panel Installation
• Inverter House Installation
• Switchyard Equipment Installation
• Pole Line Conductor and Telecom Installation
All activities underway except those shown in red
![Page 4: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/4.jpg)
KINGSTON SOLAR LP | 4
OVERVIEW OF THE PROJECT SCHEDULE
Milestone Date Achieved Full Notice to Proceed Sept. 2, 2014 Yes Civil Engineering Package Nov. 25, 2014 Yes Electrical Engineering Package Dec. 15, 2014 Yes Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module Installation Complete August 2015 Not yet Acceptance Testing Starts September 2015 Not yet Substantial Project Completion September 2015 Not yet Final Project Completion November 2015 Not yet
![Page 5: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/5.jpg)
KINGSTON SOLAR LP | 5
PROJECT DIVIDED INTO 6 ZONES
![Page 6: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/6.jpg)
KINGSTON SOLAR LP | 6
CONTRUCTION STATUS (AS OF MAY 22nd)
Zone 1 2 3 4 5 6 Total Piles installed 90% 98% 85% 91% 94% 56% 88% A-Frames 38% 91% 85% 91% 41% 0% 69% Rack complete 20% 91% 83% 84% 25% 0% 60% DC trenches 2% 98% 96% 91% 94% 9% 72% DC cables 0% 92% 74% 91% 71% 0% 60% Panels installed 5% 78% 71% 68% 3% 0% 46% Panels wired 5% 78% 71% 68% 3% 0% 46%
Total contractor manpower onsite = 759 people + 10 for Canadian Solar + 8 for Kingston Solar
= 777 total workforce on May 22nd
![Page 7: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/7.jpg)
KINGSTON SOLAR LP | 7
COMMENTS ON PROJECT STATUS
• Majority of heavy civil construction already complete
• Approximately 85% of deliveries to site complete
• Some berm construction remains
• Site manpower at peak; will decrease over time
• Drilling operations to be completed in July
• Road work ongoing and to be completed in June
• Project final completion expected to be on time in Q4
• Long-term O&M staff of 6-9 people plus subcontractors
![Page 8: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/8.jpg)
KINGSTON SOLAR LP | 8
ZONE 1 PILES
![Page 9: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/9.jpg)
KINGSTON SOLAR LP | 9
ZONE 3 OVERVIEW
![Page 10: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/10.jpg)
KINGSTON SOLAR LP | 10
ZONE 3 ARRAYS
![Page 11: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/11.jpg)
KINGSTON SOLAR LP | 11
MV STATION
![Page 12: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/12.jpg)
KINGSTON SOLAR LP | 12
TRANSFORMER FOUNDATION
![Page 13: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/13.jpg)
KINGSTON SOLAR LP | 13
BARN SWALLOW STRUCTURE
![Page 14: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/14.jpg)
KINGSTON SOLAR LP | 14
ACTIVE MITIGATION OF ROAD CONDITIONS
• Complying with Road Use Agreements and Traffic
Management Plan with respect to safety and road
maintenance
• Kingston Solar continues to work closely with City of Kingston
and Loyalist Township concerning road maintenance
• Focus on increased sweeping and watering
• Temporary fix on Unity Road near entrance to Hydro One
power corridor, with remediation planned when work is
complete
![Page 15: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/15.jpg)
KINGSTON SOLAR LP | 15
STRICT ADHERENCE TO ROAD SAFETY RULES
![Page 16: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/16.jpg)
KINGSTON SOLAR LP | 16
UPDATE RE BERM CONSTRUCTION AND LANDSCAPING
• Landscaping to begin in next four to six weeks, subject to weather conditions
• Estimated 8 weeks of work to complete
• Securities are in place with City of Kingston and Loyalist Township to ensure that landscaping is done in accordance with the plans
![Page 17: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/17.jpg)
KINGSTON SOLAR LP | 17
LANDSCAPING PLAN – TYPES OF VEGETATION
![Page 18: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/18.jpg)
KINGSTON SOLAR LP | 18
DETAILS OF LANDSCAPING PLANS - BUFFERS A AND B
![Page 19: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/19.jpg)
KINGSTON SOLAR LP | 19
DETAILS OF LANDSCAPING PLANS – BUFFER C
![Page 20: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/20.jpg)
KINGSTON SOLAR LP | 20
LANDSCAPING PLAN – VISUAL SIMULATIONS
![Page 21: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/21.jpg)
KINGSTON SOLAR LP | 21
LANDSCAPING PLAN – MITIGATION PLANTING
![Page 22: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/22.jpg)
KINGSTON SOLAR LP | 22
QUESTIONS AND CLARIFICATIONS
![Page 23: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/23.jpg)
KINGSTON SOLAR LP | 23
CONTACT INFORMATION
Name Title Company Phone Email Jason Woods Project
Director Kingston Solar
(613) 449-7478 [email protected]
Chris Moran Project Manager
Kingston Solar
(613) 449-6308 [email protected]
Kingston Solar Construction Hotline (343) 333-5911
Email = [email protected]
![Page 24: KINGSTON SOLAR LP287gn72iptha3xmrvq4d3hts-wpengine.netdna-ssl.com/wp...Site Grading Jan. 16, 2015 Yes Foundations Complete July 2015 Not yet Racking Complete July 2015 Not yet Module](https://reader034.fdocuments.in/reader034/viewer/2022042406/5f20e2d32e9b5123c14f45a9/html5/thumbnails/24.jpg)
Connor, Clark & Lunn Infrastructure Ltd. 181 University Ave, Suite 300 Toronto, ON M5H 3M7
www.cclifrastructure.com