THE PLANNING CENTER
Kinder Morgan Pipeline Assessment
Kinder Morgan Pipeline Assessment
June 16, 2008
Dr. Cathy Fitzgerald, P.E.
June 16, 2008
Dr. Cathy Fitzgerald, P.E.
THE PLANNING CENTER
![Page 2: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/2.jpg)
THE PLANNING CENTER
ISSUES
• Manual vs. automatic valves
• If the pipeline breaks, where will the product flow
• What happens in an earthquake
• What happens if product gets into the storm drain
![Page 3: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/3.jpg)
THE PLANNING CENTER
San Juan Hills HS
Kinder Morgan 16-Inch Pipeline
![Page 4: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/4.jpg)
THE PLANNING CENTER
San Juan Hills HS
Kinder Morgan 16-Inch Pipeline
Check Valve Elev. 331 msl
High Point Elev. 1,022 msl
![Page 5: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/5.jpg)
THE PLANNING CENTER
![Page 6: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/6.jpg)
THE PLANNING CENTER
![Page 7: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/7.jpg)
THE PLANNING CENTER
![Page 8: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/8.jpg)
THE PLANNING CENTER
![Page 9: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/9.jpg)
THE PLANNING CENTER
![Page 10: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/10.jpg)
THE PLANNING CENTER
![Page 11: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/11.jpg)
THE PLANNING CENTER
![Page 12: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/12.jpg)
THE PLANNING CENTER
![Page 13: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/13.jpg)
THE PLANNING CENTER
![Page 14: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/14.jpg)
THE PLANNING CENTER
Probability of Pipeline Failure
• All refined product pipelines in California –1986-2001
• Annual failure probability– 1.3 x 10-3
• One incident every 769 years• No. 1 cause of failure – third party damage• Earthquake
![Page 15: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/15.jpg)
THE PLANNING CENTER
Earthquakes and Pipelines
• Failure mechanisms• Ground shaking• Liquefaction/lateral spreading• Landslides• Maximum credible earthquake – MMI 6.6• Newport-Inglewood Fault – 7 miles SW• Failure probability – 5.1 x 10-3
• Once every 196 years
![Page 16: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/16.jpg)
THE PLANNING CENTER
Earthquakes and Pipelines (cont.)
• Northridge Earthquake -1994• All petroleum product pipelines shut down within
1 minute – regulatory requirement• 2 petroleum pipeline breaks• Kinder Morgan pipeline – low probability of
break given earthquake occurs• Buried 3 feet below ground surface• Steel pipelines ductile – less susceptible to
ground movement• New pipe (<25 yrs old) – corrosion less likely
![Page 17: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/17.jpg)
THE PLANNING CENTER
Pipeline Failure – What Happens and Where Does the Product Go?
• Leak – 5 times more likely than full break• Product travels along backfill below
ground surface• Most likely never reaches the surface• Worst case scenario – full pipeline rupture
![Page 18: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/18.jpg)
THE PLANNING CENTER
Pipeline Shutdown and Manual vs Automatic Valves
• Manual shutoff valves – Ortega Highway and Talega Creek – 14.6 miles apart
• One-way check valve – La Pata Road• Kinder Morgan control center – Orange, CA• Staffed with 16 people operating 24/7• Continuous monitoring of pipeline for pressure,
flow rate, temperature, etc. with SCADA system• Automatic shutdown time – 0 to 30 seconds,
assume 1 minute
![Page 19: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/19.jpg)
THE PLANNING CENTER
What Happens After Shutdown?• Pumps turned off• Assume discharge of product for one
minute prior to shutdown• 6,000 bbl/hr = 4,200 gallons in one minute• Distance to school site = 2,150 feet • 7 football fields• Product adsorbed into soil• Never reaches school site
![Page 20: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/20.jpg)
THE PLANNING CENTER
What Happens After Shutdown?
• In addition to product released during shutdown period
• Gravity drainage from pipeline • Amount discharged based on elevation
profile and break location
![Page 21: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/21.jpg)
THE PLANNING CENTER
![Page 22: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/22.jpg)
THE PLANNING CENTER
![Page 23: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/23.jpg)
THE PLANNING CENTER
![Page 24: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/24.jpg)
THE PLANNING CENTER
![Page 25: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/25.jpg)
THE PLANNING CENTER
![Page 26: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/26.jpg)
THE PLANNING CENTER
![Page 27: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/27.jpg)
THE PLANNING CENTER
San Juan Hills HS
Kinder Morgan 16-Inch Pipeline
Check Valve Elev. 331 msl
High Point Elev. 1,022 msl
Segment A Segment B
![Page 28: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/28.jpg)
THE PLANNING CENTER
How Much Product Is Released?Distance from High Point (ft)
Amount Released
During Shutdown (gal)
Amount Released
During Gravity Drainage (gal)
Total Amount Released (gal)
0 4,200 0 4,200
500 4,200 5,221 9,421
1,000 4,200 10,442 14,642
4,300 4,200 44,901 49,101
30-foot Round Pool,
4 feet deep
![Page 29: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/29.jpg)
THE PLANNING CENTER
How Far Will Product Travel?
• Worst case scenario – 49,100 gallons released – volumes of 2.3 aboveground swimming pools
• Discharge into drainage channel• Lateral spreading, infiltration, adhesion, and
evaporation• Assume 30 foot wide channel• Product infiltrates into soil within 300 to 600 feet• Distance from pipeline to storm drain – 2,100
feet• Product will not reach storm drain
![Page 30: Kinder Morgan Pipeline Assessment - Environmental Risk](https://reader030.fdocuments.in/reader030/viewer/2022041000/624ed6f405373c510a304ae4/html5/thumbnails/30.jpg)
THE PLANNING CENTER