  • CNOOC UGANDA LIMITED

    DESIGN FOR A MATERIALS YARD AT KING FISHER

    DISCOVERY AREA

    ENGINEERS ESTIMATE

    FOR

    CONSTRUCTION OF THE MATERIALS YARD

    DOCUMENT REFERENCE NUMBER: KF-DD-RPT-SUP-CE-002

    JULY 2013

  • P 1

    PREAMBLE TO BILLS OF QUANTITIES

    1. Objectives

    The objectives of the Bill of Quantities are (a) To provide sufficient information on the quantities of Works to be performed to enable

    bids to be prepared efficiently and accurately; and (b) When a Contract has been entered into, to provide a priced Bill of Quantities for use in

    the periodic valuation of Works executed.

    In order to attain these objectives, Works have been itemized in the Bill of Quantities in sufficient detail to distinguish between the different classes of Works, or between Works of the same nature carried out in differently or in other circumstances which may give rise to different considerations of cost.

    2. The Bills of Quantities for the Works comprise the following:

    Preamble to Bill of Quantities List of principal Quantities Grand Summary Bill 100 Preliminary and General Items

    Bill 200 Access road Bill 300 Materials Yard Bill 400 Chemical shed Bill 500 Electrical Installations Bill 600 Water supply and sewer systems Bill 700 Fire fighting system Bill 800 Waste collection shed Bill 900 Day Works

    3. The Contractors unit rates in these bills are to cover supplying of materials, taking delivery, transporting, loading and off loading inspection, storage, stacking, landing, and preparation, installation including provision of all labour, requirement false work, temporary support, surface preparation and testing of the works. The rates shall include all applicable taxes and duty. The cost of testing of the materials to be used in the works unless otherwise provided is to be included in the rates of the respective Bill items.

    Measurement for payment shall be for the complete installation and having passed all necessary tests.

  • P 2

    4. Rock is any material which, in the opinion of the Engineer, requires for its removal the use of explosives, sledgehammers and wedges, breaking tools or which cannot be removed by a 145 KW tractor with rear-mounted heavy duty ripper.

    Individual boulders shall be included in rock when their nature and size are such that they cannot be removed without recourse to the stated methods. Where their aggregate volume is 50% or more of the total volume of material removed, the material shall be measured as rock throughout.

    5. Work shall not be executed on a Day work basis unless ordered in writing by the Consultant on approval by the Employer. The rates entered in the Day works Bill of Quantities shall apply to any quantity of Day work instructed by the Consultant. Nominal quantities have been indicated against each item to permit the extended total to be carried forward to the Grand Summary.

    6. Payments for labour under Day works shall be made against records of the time of arrival of the

    labour at the site of the work to be executed to the time of departure but excluding meal breaks and rest periods. Only the time of classes of labour directly doing the work will be paid for; charge hands (working gangers) actually working with their gangs will also be recorded for payment but the time of foremen or other supervisory personnel will not be paid.

    7. Payment for the classes of labour will be made at the rates entered in this Bill. These rates shall

    cover all direct costs including, but not limited to, the amount of wages paid to such labour, transportation time, overtime, subsistence allowances and such social benefits as required by law.

    8. The rates for labour shall also be deemed to cover the Contractors profit, overheads, superintendence, administrative costs, liabilities, insurance and allowances to labour and the use of consumable stores, water, lighting and power, workshop and stores, staging and scaffolding, portable power tools, hand tools and equipment and any charges incidental to the foregoing.

    9. Payment for materials used in Day works shall be made at the rates entered in this Bill. These rates shall include invoiced price, freight, and insurance, handling charges, unavoidable damage and delivery to store and / or site together with stockpiling as required. These rates shall also include the Contractors profit and overheads.

    10. Where materials other than those entered in this Bill are to be procured for use on the Works, the

    basic rate shall be calculated on the invoiced purchase price plus the costs of insurance, handling charges, unavoidable damage and delivery to store or site. Payment will be made in the currency expended upon presentation of supporting documentation. In addition, a percentage on the base rates will be allowed to cover the Contractors overheads and profit: this percentage must be stated in this Bill.

    11. The cost of hauling and handling materials for use on Day works from store or stockpile to the

    place of usage will be paid in accordance with the labour and Contractors equipment rates in this Bill.

    12. Payment for equipment available at site in respect of Day works shall be made at the rates

    entered in this Bill. These rates shall be deemed to include allowance for depreciation, interest, indemnity and insurance, repair and maintenance, supplies, fuel, lubricants and other consumables, overheads, profit and administrative costs related to the use of such equipment.

    13. The costs of drivers, plant operators and assistants in respect of plant and equipment deployed

    on Day works shall be paid for separately under the appropriate items in the labour section of the Day works.

    14. Payment for the Equipment shall only be made against actual hours worked except that where

    applicable, and with prior agreement of the Engineer, the traveling time to and from the Day work location shall also be included for payment.

  • P 3

    15. Rates and prices shall be inserted in the rate and total columns of the Bill of Quantities in United States Dollars (USD)

    Bills of Quantities are to be read in conjunction with the Instructions to Bidders, the Conditions of Contract Data, the Specifications and the Drawings. The quantities stated against each item in the Bills of Quantities, with the exception of those items specifically marked sum, are the estimated quantities of the Work to be executed by the Contractor in fulfillment of his obligations under the Contract.

    16. The Contractor is required to check the number of the pages and should any be found to be missing or in duplicate he must inform the Consultant at once and have the same rectified.

    17. No liability whatever will be admitted or claim allowed in respect of errors in the Contractors

    tender due to mistakes in the Bills of Quantities which should have been rectified in the manner described above.

    The contractor shall not alter or otherwise qualify the text of these Bills of Quantities. Any alteration or qualification made without authority will be ignored and the text of the Bills of Quantities as printed will be adhered to.

    18. Each item in the Bills of Quantities is to be priced. If any items are left un-priced it will be assumed that the value of the work described there under is elsewhere allowed for. The prices and rates to be inserted in the Bills of Quantities are to be fully inclusive of all costs and expenses which may be required for the construction of the work described, together with general risks, liabilities and obligations set forth or implied in these documents.

    19. In no case will any claim for expenses incurred by the Contractor in preparation of this Tender be allowed. The Contractor is solely responsible for the accurate ordering of materials in accordance with the Specifications, Drawings and Engineers Instructions and no claim for any loss or expense will be entertained for orders for materials based on the Bills of Quantities.

    20. The quantities given in the Bills of Quantities are estimated and no claim by the Contractor for the final quantities being larger or smaller than the quantities given in the Bills of Quantities will be permitted except in accordance with Clause 38 of the Conditions of Contract.

    21. Provisional Item designated in the Bill of Quantities for the execution of any part of the Works may be carried out in whole or in part, or not at all on the instruction of the Engineer.

    22. The dimensions given in the Drawings are generally in millimeters unless otherwise indicated. Levels are given in meters.

    23. The term provide or supply used for any item shall be deemed to include transport to site, handling, storage and fixing complete, and the Bidders rate shall include for this.

    24. The following abbreviations have been used in the Bills of Quantities:- kg - kilogram t - tonne m - metre m

    2 - square metre

    m3 - cubic metre

    mm - millimetre Nr. - Number uPVC - un-plasticized poly vinyl chloride HDPE - high density polyethylene MS - Mild steel BS - British Standards Sum - Lump Sum PS - Provisional Sum

  • P 4

    General Items

    Unless otherwise provided there are no separate measurement items for Contractual requirements. The Contractor is deemed to have included his costs for the Contractual requirements in other unit rates.

  • MATERIALS YARD AT KING FISHER - ENGINEERS ESTIMATE

    GRAND SUMMARY

    BILL 100: PRELIMINARIES & GENERAL 96,500.00

    BILL 200: ACCESS ROADS 29,590.08

    BILL 300: MATERIALS YARD 733,444.83

    BILL 400: CHEMICAL SHED 156,782.14

    BILL 500: ELECTRICAL INSTALLATIONS 219,128.50

    BILL 600: WATER SUPPLY AND SEWER SYSTEMS 49,834.00

    BILL 700 FIRE FIGHTING SYSTEM 89,650.00

    BILL 800 WASTE COLLECTION SHED 51,367.80

    BILL 900 DAY WORKS5,415.69

    CONTRACT AMOUNT 1,431,713.04

    CONTINGENCY 5%71,585.65

    GRAND TOTAL 1,503,298.69

  • Bill 100 - Preliminaries

    RATE Amount

    (USD) (USD)

    100 PRELIMINARIES & GENERAL

    101 Initial mobilisation of equipment and personel to King Fisher Area

    LS 8000 1.00 8,000.00

    102 Final demobilisation from King Fisher Area

    LS 2,500.00 1.00 2,500.00

    103 Provision of Contractor's main staff camp in King Fisher area including set up of site welfare facilities.

    LS 12,000.00 1.00 12,000.00

    114 Provision of Performance Bond LS 1.00 10,000.00

    115 Provision of Contractor's All Risks Insurance (Third Party Limit up to $1million)

    LS 1.00 50,000.00

    116 Provision of vehicles with seat belts, roll over protection and suitably qualified driver for transporting contractor's staff; Allow for all consumables including fuel and maintaince

    Month 8,000.00 1.00 8,000.00

    117 Provision of all necessary indicators, signs and protection to services, buildings and structures

    LS 2,000.00 1.00 2,000.00

    118 Allow for personal protective equipment, fire extinguishers, first aid kit

    LS 4,000.00 1.00 4,000.00

    SUB - TOTAL BILL 100: PRELIMINARIES 96,500.00

    Bills of quantities for King Fisher materials yard

    Pay't

    Item

    DESCRIPTION Unit Quantity

    1/1

  • Bill 200 - Access Road

    RATE Amount

    (USD) (USD)

    200 ACCESS ROADS

    SITE CLEARANCE

    201

    Establishment of the road

    alignment and setting out of the

    road works.

    m 200 1.10 220.00

    202

    Clear site of all grass, bushes

    and boulders (up to 1.5m

    maximum girth) and Grub all

    roots of grass and bushes

    including excavation of top soil

    from road formation .

    m2 2,000.00 0.50 1,000.00

    203

    Load and cart to spoil all

    excess materials resulting from

    site clearance and clear all

    inlets and outlets of drainage

    structures of debris

    m3 600 6.87 4,122.00

    204

    Shape to camber ,Water and

    Compact the resultant surface

    to 95% MDDm

    2 2,000 1.50 3,000.00

    Earth works and Pavement

    layers of gravel

    205Preparation of borrow site

    consisting of clearing

    vegetation and removing topsoil

    m2 400 1.50 600.00

    206Excavation of side drains and

    off shoots.m

    3 92 5.14 472.88

    207

    Supply, damp approved gravel,

    spread and compact to 98%

    MDD BS Heavy to form 350mm

    thick layer over the 8m wide

    road. Rate to include

    allowances for Contractor's QA

    m3 560 16.69 9,346.40

    208

    Stabilisation of 200mm thick

    layer with 3% cement including

    shaping, compation to 98%

    MDD

    m3 320 33.84 10,828.80

    SUB - TOTAL BILL 200: ACESS ROADS 29,590.08

    Bills of quantities for King Fisher materials yard

    Pay't Item DESCRIPTION Unit Quantity

    2/1

  • Bill 300 - Materials Yard

    RATE Amount

    (USD) (USD)

    300 Materials Yard

    301 Clearing site and scraping off top soil average

    250mm thick and stockpile where directed for

    future usem

    3 9,250 5.14 47,545.00

    Gravel Material

    302 Excavation, hauling, placing, watering and

    compaction of approved ganular fill material in

    the whole yard area .m

    3 5,550 16.69 92,629.50

    303 175mm thick selected imported murram from

    borrow to make up levels of gravel base in

    150mm layers and compacted to 98% MDD m3 6,475 16.69 108,067.75

    304 Cement for stabilisation at 3%tons 234 400.00 93,600.00

    Fences

    309 Supply and install 2100mm high chain link

    fencing on Steel Angle bar posts. Refer to drg

    CNOOC/KF/YARD/23

    m 765 32.14 24,587.10

    310 Supply and install 1000 mm high coffee tray

    snake proofing m 765 13.00 9,945.00

    Gates and Gate house

    311 Construction of gate house including 1 WC,

    hand washing facilities and notice boards Refer

    to drg CNOOC/KF/YARD/ 22 & 22ANo. 1.0 1,000.00 1,000.00

    Supply and install

    312 Security gate size 8m x 2m high No. 1.0 1,928.00 1,928.00

    313 Pedestrian gate size 1.5m X 2m high No. 2.0 514.36 1,028.72

    314 Steel emergency exit gate (Judas Gate) ; 1.5m

    wide and 1.8m high No. 1 514.36 514.36

    314a Supply and install 2 No T- card boards as per

    detail drg CNOOC/KF/YARD/28 Item 2 600.00 1,200.00

    Culverts

    315 Supply and install 600 mm diameteter concrete

    culvert pipe rings including bedding, and backfill

    with approved materialm 112 250.75 28,084.00

    Yard walk ways

    316 Construction of a 1200 mm wide camp walkway

    using approved precast concrete slabs 600 x 600

    x 50 mm of 40 N/mm2 minimum crushing

    strength on 50mm thick levelling sand to the

    satisfaction of the Engineer

    sm 75.0 45.00 3,375.00

    Oil Water Separator

    317 Fabrication of a steel oil/water

    separators/Interceptor, 6m x 2.4m x 2m depth

    (Internal dimensions) with baffle wall and

    drainage inlet and outlet as per drawing no.

    CNOOC/KF/YARD/08

    no 2 4,500.00 9,000.00

    317a Ditto 6m x 2.4m x 0.9m no 1 2,600.00 2,600.00

    Sub Total Carried to Summary 425,104.43

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    3/1

  • Bill 300 - Materials Yard

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Anchor blocks and Casings

    318 C25/20 Reinforced Concrete Anchor blocks

    6000mm long X 450mm wide X 450 high

    including lifting eyes for pipes and casings Refer

    to drg CNOOC/KF/YARD/ 12

    no 84 576 48,384.00

    319 Well treated hard wood timber batterns 75 x 100

    mm m 9,072 9.00 81,648.00

    Fire fiting equipment

    320 Allow for supply and installation of fire fighting

    equipment including fire hoses, fire extinguishers

    and sand buckets and sand bagsItem 1 30,000.00 30,000.00

    Marine shed

    Refer to drgs CNOOC/KF/YARD/17-19

    321 Provide and install 75mm thick cement/sand

    paving blocks at the Marine shedm

    2 135 40.00 5,400.00

    322 Supply 50 x 50 x 3mm rectangular steel hollow

    sections cut to size and welded to form a

    trusses. Allow for offsite welding, transporting

    and placing in place

    m 400 15.00 6,000.00

    323 Supply 100 x 100 x 4mm SHS columns cut to

    size and welded all around to the plate with 6mm

    weld of E70XX Electrodes

    m 17 35.00 588.00

    324Supply and install 150 x 150 x 4mm SHS m 48 50.00 2,400.00

    325 Supply and install 254 X 102 X UB 28 m 62 85.00 5,270.00

    326 Supply and install 60 x 60 x 5mm MSA bracingm 160 18.50 2,960.00

    327 Marine twist lock including connecting plates

    including connecting plates and fabrication of

    corner casting

    No. 12 150.00 1,800.00

    328 Provide and install 100mm deep Z- purlins to rest

    on steel trusses m 276 15.00 4,140.00

    329 Supply and install Gauge 28 pre-painted sheets

    cladding roof covering over the steel section

    frame to Marine shed.m

    2 326 30.50 9,943.00

    330 Supply and install 100 mm diameter PVC rain

    water guttersm 23 10.00 230.00

    331 Supply and install 100 mm diameter PVC down

    pipem 20 10.00 200.00

    Waste pit

    Refer to drgs CNOOC/KF/YARD/16

    332 Excavation for the waste pit and dispose

    excavated material as directed m3 4 5.14 20.56

    333 Blinding concrete of grade 15/20, 75mm thick at

    base of excavation m3 0.10 170.61 17.06

    334 Vibrated Grade 25 reinforced concrete in walls,

    base and slab of the waste pit m3 3.40 255.00 867.00

    Sub Total Carried to Summary

    199,867.62

    3/2

  • Bill 300 - Materials Yard

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    335 Sawn formwork

    (a) Sides of the retaining walls m2 10 8.63 86.30

    (b) Sofits and sides of the slabm

    2 4 8.63 34.52

    336 High yield twisted bars reinforcement to BS

    4449

    (a) 8mm Diameter bar. Kg 0 1.57 -

    (b) 10mm Ditto. Kg 0 1.49 -

    (c) 12mm Ditto. Kg 404 1.49 601.96

    337 SignageProvide and erect information, warning and

    safety type signs as per details in drawing

    No.CNOOC/KF/YARD-29

    No. 40 195.00 7,800.00

    Chemical Storage yard

    338 supply and Install poly liner over the

    chemical aream

    2 1,050.0 1.50 1,575.00

    339 50 mm thick sand blinding over the entre

    aream

    2 1,050.0 30.00 31,500.00

    340 Construct an earthbund around the chemical

    area using approved material as per details m3 75.00 25.00 1,875.00

    341 Supply and install chemical shower

    including all fittings and 1000 litre PVC

    elevated tank

    No. 1.0 2,500.00 2,500.00

    Administration Block and Toilets

    342 supply and Install standard office

    containers reffer to drawing

    CNOOC/KF/YARD/20

    Item 3.0 15,000.00 45,000.00

    343 supply and Install Toilet containers refer to

    drawing CNOOC/KF/YARD/20aItem 1.0 17,500.00 17,500.00

    Sub Total Carried to Summary 108,472.78

    Sub total Page 1 425,104.43

    Sub total Page 2 199,867.62

    Sub total Page 3 108,472.78

    Total carried to Main Summary 733,444.83

    SUMMARY

    3/3

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    400 CHEMICAL SHED

    Refer to drgs CNOOC/KF/YARD/13-15

    Element A - SUBSTRUCTURE

    401 Excavate foundation trench not exceeding 1.50m

    deep. m

    3 80 5.140 411.20

    402 Do. But for column base. m3 40 5.140 205.60

    403 Return, fill in and ram imported approved murram

    around foundations.m

    3 180 16.69 3,004.20

    404 Load, wheel and deposit surplus as directed. m3 230 4.50 1,035.00

    405 200mm Bed of approved imported hard core

    well spread, rammed and consolidated under

    floor slab and blinded with and including 50mm

    layer of sand well watered and rolled to receive

    concrete (measured separately).

    m2 367 25.00 9,175.00

    406 Treat surfaces of hardcore, sides and bottom of

    excavations with "Aldrex 48" or other equal and

    approved anti-termite solution in accordance with

    manufacturer's instructions.

    m2 645 0.78 503.10

    407 1000 Gauge diothene or other equal approved

    polythene sheeting as damp proof membrane

    laid on blinded hard core (measured separately)

    with welted joints and minimum 200mm end and

    side laps.

    m2 367 3.00 1,101.00

    408 75mm Concrete blinding grade 15 m2 26 15.00 390.00

    Vibrated reinforced concrete grade 25 in

    410 Strip foundations. m3 20 280.00 5,600.00

    412 Column bases. m3 12.00 280.00 3,360.00

    413 Columns studs. m3 2 280.00 560.00

    414 150mm Floor bed laid on damp proof membrane.

    (m/s)m

    3 56 300.00 16,800.00

    415 150mm average concrete ramp m3 3.3 300.00 990.00

    Sub Total Carried to Summary 43,135.10

    Pay't

    Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    4/4

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    Pay't

    Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    High yield twisted bars reinforcement to BS

    4449

    416 8mm Diameter bar. Kg 64 3.50 224.00

    417 10mm Ditto. Kg - 3.50 -

    418 12mm Ditto. Kg 894 3.50 3,129.00

    419 16mm Ditto. Kg 341 3.50 1,193.50

    420 Steel wire fabric mesh reinforcement to B.S 4483

    Ref. A142 weighing 2.22kg/m2 in concrete floor

    bed with minimum 300mm end and side laps. m2 367 10.72 3,934.24

    Sawn formwork

    421 Edge of slab 75 - 150mm high. m2 22 15.00 330.00

    422 Sides of column base m2 - 15.00 -

    423 Sides of column stud m2 32 15.00 480.00

    Plinth wall

    425 230mm Thick concrete block walling bedded

    and jointed in cement sand (1:3) mortar with 25 x

    1.5mm thick metal strip at every second coarse

    (Plinth wall).

    m2 132 50.00 6,600.00

    426 Pluvex No.1' or other equal and approved

    horizontal damp proof course to B.S.743, 220mm

    wide under walling (measured net no allowance

    for laps).

    m 88 2.50 220.00

    Plinth wall Finish

    427 15mm thick cement and sand (1:4) rendering to

    plinths externally.m

    2 132 9.6 1,267.20

    428 Prepare and apply three coats of bitumastic or

    equal approved water resistant paint rendered

    plinths externally.

    m2 132 10.72 1,415.04

    Splash apron

    429 100mm Thick concrete grade 20 splash apron on

    and including 100mm compacted murram base

    and 150mm thick brick wall edge to detail. m2 53 32.00 1,696.00

    430 Sawn formwork to edge of slab 75 - 150mm high.m 15 15.00 225.00

    431 20mm Cement sand (1:3) screed on splash

    apron steel trowelled hard and smooth.m

    2 53 12.00 636.00

    Sub Total Carried to Summary 21,349.98

    4/4

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    Pay't

    Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    Element B - WALLING AND FRAME

    432 75 x 315mm concrete Grade 25 Window cill

    reinforced with weld mesh and bedding in

    position.

    m 88 8.00 705.60

    433 150 mm thick block walling bedded and jointed

    in cement sand mortar (1:4) with 25 x 1.5mm

    metal strip every third course. (rate only) m2 231 30.00 6,930.00

    434 Steel louvered clading including mosquito wire in

    frame to detail m2 140 150.00 21,000.00

    UB Stanchions

    435 254 x 146 x 31kg / m stanchion. Kg 3,069 2.54 7,795.26

    436 330 x 230 x12mm Base plate fixed to concrete

    Column stud with 4No. J bolts.No 18 22.50 405.00

    Element C - ROOF

    437 254 x 146 x 31kg /m rafters Kg 2,812 2.54 7,142.48

    438 175 x 50 x 2 mm Z purlins. m 475 13.50 6,412.50

    439 210mm x 1.5mm thick pre-formed m.s fascia

    boards welded to angle cleats at rafter ends to

    detail.

    m 100 9.50 950.00

    441 400mm wide x 250mm deep x 2mm U shaped

    gutter. m 70 48.50 3,395.00

    442 75 x 75 x 6mm Angle cleats fixed to rafters as

    per details.No 110 4.80 528.00

    443 Eaves Girder 89x89x19.5kg/m kg 2,153 2.54 5,468.62

    444 75x75x6 Angle Bracing kg 940 2.54 2,387.60

    445 Supply and install 16 mm diameter anti sag rodskg 250 3.50 875.00

    446 26 Gauge pre-painted galvanized IT4 sheet and

    fixing accessories as manufactured by Messrs

    Roofings Ltd or other approved manufacturers

    lapped and fixed to steel Z purlins with self

    lapping screws in accordance with the

    manufacturers instructions.

    m2 550 22.50 12,375.00

    447 Standard 26 gauge ridge caping dressed over

    IT4 Sheets.m 35 10.00 350.00

    448 Matching anti-bat rubber filler beneath ridges as

    supplied by Roofings Ltd and fixed in place in

    accordance with manufacturer's instructions.m 140 2.50 350.00

    449 Supply and install 100 mm diameter PVC rain water gutters

    m 70 10.00 700.00

    450 Supply and install 100 mm diameter PVC down pipem 50 10.00 500.00

    Sub Total Carried to Summary 78,270.06

    4/4

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    Pay't

    Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    Element D - DOORS

    Metal Doors

    451 Solid steel door complete with framing, hinges,

    bolts, padlocks, size 6000 x 4300mm all to

    details. (D01)No 1 2,000.00 2,000.00

    Painting

    452 Prepare, prime and paint one undercoat and two

    finishing coats of gloss oil paint on surfaces of

    louvres , and door m

    2 350 8.00 2,800.00

    453 Allow for preparing, priming and painting one

    undercoat and two finishing coats of gloss oil

    paint on surfaces stanchions, rafters, Z purlins

    and angle bracings

    Item 2,000.00

    Element F - FLOOR FINISHES

    452 19 x 100mm cement sand mortar skirting with

    rounded top edge curved at junction with floor

    screed. (Provisional)

    m 85 3.80 323.00

    453 40mm thick Cement sand mortor floor screed in

    ration of 1:3 m2 367 12.00 4,404.00

    454 Supply and install chemical shower including all

    fittings and 1000 litre PVC elevated tank No. 1.0 2,500.00 2,500.00

    Sub Total Carried to Summary 14,027.00

    SUMMARY

    Sub total Page 1 43,135.10

    Sub total Page 2 21,349.98

    Sub total Page 3 78,270.06

    Sub total Page 4 14,027.00

    Total carried to Main Summary 156,782.14

    4/4

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)

    500 ELECTRICAL INSTALATION

    Note : The works are to be carried out in

    full accordance with the specifications

    and drawings and are to include for all

    necessary fixing and other works

    ,whether or not specfically measured or

    described below, required for the

    installation. All builders work required

    for the installation shall be includede for

    in the prices whether or not specifically

    measurred,plugging,making good

    finishing, painting or prepainting, etc for

    suface mounted installation

    POWER SUPPLY AND DISTRIBUTION

    BOARD

    501 Allow a provisional sum of USD 1000 for

    three (3) phase power supply connection to

    site

    sum 1 1,000.00 1,000.00

    502 100A TPN locakable loop in box complete

    with earthing to required standards No. 3 800.00 2,400.00

    503 75 X 75 mm lockable adaptable c/m

    earthingNo. 3 300.00 900.00

    504 Free stand metal cased with lockable

    hinged door 6 way TPN MCB type flush

    mounted distribution board with 200 A TP

    main intergral switch, bus,bars,neutral and

    earth terminal blocks or as to crab tree list

    No 1806/21B C/W barrel lock as crab tree

    equal and approved

    No. 1 3000.00 3,000.00

    505 70 mm sq-4 core PVC/SWA/PVC coppper

    cables connected from power supply and

    terminated on to above distribution bed

    m 170 58.85 10,004.50

    506 Trench ing and backfilling m 190 10.00 1,900.00

    ELECTRICAL INSTALLATION

    ADMINSTRATION OFFICES

    507 50 mm sq 4-core PVC/SWA/PVC copper

    cables ,connected from main distribution

    board and terminated on to looping box at

    the Fire pump house

    m 12 47.50 570.00

    508 Dito but to marine shed m 370 47.50 17,575.00

    509 Metal cased with lockable hinged door 4

    way TPN MCB type flush mounted

    distribution board with 100 A TP main

    intergral switch, bus,bars,neutral and earth

    terminal blocks or as to crab tree list No

    1806/21B C/W barrel lock as crab tree

    equal and approved

    No. 1 200.00 200.00

    510 Lighting points wired from consumer unit

    adaptable box with 3x1.5 mm2 PVC cable

    drawn in new 20 mm GI conduitNo. 22 40.00 880.00

    38,429.50

    Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    5/1

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    511 4x18 W HPF T8 600X600 cat 4 flouresent

    mirror brite recess lumirare quated c-line

    FQCZ 418

    No. 6 100.00 600.00

    512 16W 2D Compact florescent apal diffused

    ceiling lummare approved equal 1x36W

    1200mm weather proof florescent light as

    thorm or approved equal

    No. 8 80.00 640.00

    514 One gang 1 way 6A moulded switch as MK

    or approved equalNo. 1 3.00 3.00

    .

    515 Two gang 1way 6A moulded switch as MK

    or approved equalNo. 5 6.00 30.00

    516 Socket outlet point wired from distribution

    board by 3x2.5 mm2 sq PVC Copper

    cables HG Conduit complete with all

    accessories

    No. 6 48.00 288.00

    517 Ditto to Air conditioner outlets No. 3 48.00 144.00

    1,705.00

    5/2

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    518 13A two gang switched socket outlet as MK

    or equal approvedNo. 6 14.00 84.00

    519 Data and telephone wall socket outlet LJ

    Secondary modelNo. 6 14.00 84.00

    520 20A DP switch as M.K or approved equal No. 5 14.00 70.00

    521 2KW 240V -50Hz Hand dryer as SADIAL

    manfacture or approved equalNo. 2 480.00 960.00

    522 3 compartment 192 x6o mm UPVC DADO

    TRUNKING AS Made by cente president

    complete with accessories such as

    compliers, angles,end caps,3No outlet

    boxes at each working stations etc laid

    along walls

    m 10 120.00 1,200.00

    523 3x32 mm PVC conduits in floor/Wall slab

    link up linking voice and data working

    stations

    No. 5 30.00 150.00

    524 Air conditionier split system complete with

    12000 BTW out door unitNo. 5 20.00 100.00

    SITE ELECTRICAL INSTALLLATION

    525 Photocell as Legrand

    manufactureconnected with wiring through

    15A contactor

    No. 2 600.00 1,200.00

    526 Two court: 9X Thorn QC6TC columns Set 1 19000.00 19,000.00

    16X Sonapak OTLGB 250-4 Flood lights

    4XQCB TCFB 1-way brackets

    4XQCB TC FB 2-way brackets

    1XQCB TC FB 4-way brackets

    527 Sonapack OTLGB 250-4 Flood light

    mounted columns above No. 8 700.00 5,600.00

    528 4XQCB TCFB 1-way brackets No. 8 200.00 1,600.00

    529 6mm sq 4-core PVC/SWA/PVC copper

    cable connected from photocell to flood

    lights mounted on TC columns

    m 950 15.00 14,250.00

    530 Earthing TC columns by 1200mm copper

    electrodes No. 9 200.00 1,800.00

    531 Trenching and backfilling for above

    undrground cables laid minimum 600mm

    deep in ground and surrounded with

    concrete at roads and paved areas

    m 850 10.00 8,500.00

    GUARD HOUSE

    532 Guard monitoring points on 2m stand pole

    with weather proof push button wired to 4-

    zone indicator / display board complete with

    all necessary accessories

    No. 5 200.00 1,000.00

    533 Allow for commisioning of the installation LS 1 400.00 400.00

    534 4core 1.5mm PVC/SWA/PVC cable to

    above pointsm 950 5.00 4,750.00

    60,748.00

    5/3

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    535 4 way 60A flush type mounted consumer

    unit with 60A SP main intergral switch, bus

    bars,neutral and earth terminal blocks or as

    to crab tree list No 1806/21B c/w barrel lock

    as crab tree equal and approved

    No. 1 200.00 2,000.00

    536 10 mm sq-4 core PVC/SWA/PVC coppper

    cable connected from main LV Distribution

    Board and terminated to above consumer

    unit

    m 250 25.00 6,250.00

    537 Lighting points wired from consumer unit

    with 3x1.5 mm2 PVC cable drawn in new 20

    mm HD PVC conduitNo. 4 40.00 160.00

    538 1x36 w 1200mm weather proof flourescent

    light as Thorm or approved equal No. 3 60.00 180.00

    539 1x16 W 2D compact flouresent opal

    diffused ceiling luminaireas Thorn or

    approved equal No. 1 80.00 80.00

    540 One gang 1 way 6A moulded switch as MK

    or approved equalNo. 3 3.00 9.00

    541 One gang 1 way 6A weather proof switch as

    MK or approved equal No. 1 5.00 5.00

    542 Socket outlet point wired from consumer

    unit by 3 x 2.5 mm2 sq PVC Copper cables

    HG Conduit complete with all accessoriesNo. 2 48.00 96.00

    543 13A two gang switched socket outlet as MK

    or equal approved No. 2 14.00 28.00

    545 Data and telephone wall socket outlet LJ

    Secondary modelNo. 2 14.00 28.00

    FIRE DETECTION SYSTEM

    546 Megalarm standalone Alarm P300W

    Wireless site alarm call point intalled

    complete with:SETS 5 750.00 3,750.00

    i)Roburst and durable ABS plastic housing

    ii)Powerful siren sounding 90 dB at 2m.

    iii)9V Battrey powered - Supplied

    iv)Ideal for tempororary building applications

    v)Resettable call point stardard

    vi)Accessed Battrey compartment

    vii)Low battrey warning signal

    viii)Possible interlink up to 10 units at 100m

    distance between including all other

    necessary accessories

    547 Ditto but C300W SETS 4.0 100.00 400.00

    Megalam wireless resettable call point

    designed to link in with the rest of megalam

    product ideal for ativating megalam system

    where the sounder unit is not required

    meant for guard patrol call points

    548 How/er H01 Free Link Control Panel model

    H01/FL/XS Site AlarmNo. 1.0 1000.00 1,000.00

    549 NC 822 Solo smoke /Heat detection Test

    /Removal kit with 3 -5 different sounds. No. 10.0 2000.00 20,000.00

    33,986.00

    5/4

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    LIGHTNING PROTECTION - MARINE

    SHED

    Supply,install,connect annd set to work:

    552 Earth electrodes including Test clamps,

    copper tape down conductor and concrete

    earth pit with cover

    No. 2.0 800.00 1,600.00

    553 Air Termination Spike complete with Base

    cast and fixed on roof No. 2.0 300.00 600.00

    554 Copper tape bonding of metal structure to

    marine equipment shed, warehouse

    container, waste container pipes casings

    and marine shed complete with earth rods

    clamps connection, concrete earth pits with

    cover and all necessary accessories

    m 190.0 32.00 6,080.00

    LIGHTNING PROTECTION -CHEMICAL

    SHED

    Supply,install, connect annd set to work:

    555 Earth electrodes including Test clamps,

    copper tape down conductor and concrete

    earth pit with coverNo. 2.0 800.00 1,600.00

    556 Air Termination Spike complete with Base

    cast and fixed on roof No. 2.0 300.00 600.00

    557 Copper tape bonding of metal structure to

    marine equipment shed, warehouse

    container, waste container pipes casings

    and marine shed complete with earth rods

    clamps connection, concrete earth pits with

    cover and all necessary accessories

    m 190.0 32.00 6,080.00

    558 Allow for testing and commissioning the

    installationsItem 1.0 200.00 200.00

    16,760.00

    5/5

  • Bill 500 - Electrical Installations

    RATE Amount

    (USD) (USD)Pay't Item

    Bills of quantities for King Fisher materials yard

    DESCRIPTION Unit Quantity

    Fire Pump Set559 Fire set E65-20 Single stage and suction

    electric pump driven by 30 KW 415 V -2-

    Pole motor -2900 rpm, 72 m3/hr,65m Head

    as Dayliff manufacture model FLA 120-60

    m3/hr norminal flow constructed complete

    set with the following

    Item 36,500.00

    i)DB4-60 Horizontal centrifugal jokey pump

    fitted with 1 KW Electric Motor with pressure

    output of 4.5 Bar

    ii)Varem 300 Liter Vertical pressure vessel

    fitted with butyl rubber diaphram

    iii)Suitably sized 100mm dia piping and

    fitting for sunction and delivery connection

    including isolating gate valves non return

    valves or system outlet

    iv)Manual/Auto control panel integrally

    mounted as starndard incoporating in

    coming mains isolator and MCB ,Voltage

    Control relay 100A mcb and Stan Delta

    Starter 10A MCB and Dolstarter pump rum/

    trip/no water indicator

    Sewage pump Set

    560 2.2 KW 240V/5A Sewage submersiive

    pumps 450W duty and standby

    automatically remote opererated pumps as

    Dayliff manufacture model SLI 80.80.22 790

    H 788W complete with 10 m rubber drop

    cable connected to remote control panel

    with MCBs, Relays and all the necessary

    accessories

    set 1.0 30,000.00 30,000.00

    561 Allow for testing and commissioning the

    above pumps 1,000.00

    Total carried to Summary 67,500.00

    SUMMARY

    Sub total Page 1 38,429.50

    Sub total Page 2 1,705.00

    Sub total Page 3 60,748.00

    Sub total Page 4 33,986.00

    Sub total Page 5 16,760.00

    Sub total Page 6 67,500.00

    Total carried to Main Summary 219,128.50

    5/6

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    600 WATER SUPPLY

    PIPEWORK - PIPES

    uPVC pipes to PN 16 to BS3505

    with flexible rubber ring joints

    601OD 110mm uPVC, pipe in trench

    depth not exceeding 1.5m.m 120 20.00 2,400.00

    uPVC pipes to PN 10 to BS3505

    with flexible rubber ring joints

    602OD 25mm uPVC distribution pipe

    m 370 10.00 3,700.00

    PIPEWORK - FITTINGS AND

    VALVES

    Pipe fittings to PN 16

    Junctions and branches

    603DN 200 x 100mm DI Flanged Tee.

    Nr. 1 520.00 520.00

    604 DN 100 x 50mm DI Flanged Tee. Nr. 4 250.00 1,000.00

    Adaptors

    605 DN 200mm DI Flanged Adaptor Nr. 2 280.00 560.00

    606 DN 100mm DI Flanged Adaptor Nr. 3 200.00 600.00

    Pipe fittings to PN 10

    Bends

    607OD 25mm uPVC 90

    o Socket Bend. Nr. 20 35.00

    700.00

    Sub Total Carried to Summary 9,480.00

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    6/1

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Junctions and branches

    608 OD 25 x 25mm socket Tee Nr. 8 50.00 400.00

    609 25 x 25 x 12mm reducing Tee Nr. 5 50.00 250.00

    Hand operated cast iron gate

    valves to BS 5163, to PN 20

    610 DN 100mm Flanged Gate Valve. Nr. 1 340.00 340.00

    PIPEWORK - MANHOLES AND

    PIPEWORK ANCILLARIES

    Other Stated Chambers

    611Washout chamber Type 1 not

    exceeding 1.5mNr. 2 295.00 590.00

    MISCELLANEOUS WORK

    612

    2500 litre Upvc water storage tank

    complete with ball valve and all

    other connections and fabricated

    water tank tower 3500mm high

    from ground level including

    concrete base, steel plates, bolts

    and excavation, backfilling and

    disposal of surplus excavated

    materials and painting all exposed

    steel surfaces.

    Nr. 1 6,800.00 6,800.00

    613

    500 litre Upvc water storage tank

    complete with ball valve and all

    other connections and fabricated

    water tank tower 3500mm high

    from ground level including

    concrete base, steel plates, bolts

    and excavation, backfilling and

    disposal of surplus excavated

    materials and painting all exposed

    steel surfaces.

    Nr. 1 2,500.00 2,500.00

    614Allow for water connection to the

    mainsItem 4,454.00

    Sub Total Carried to Summary 15,334.00

    6/2

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    SANITARY FITTINGS

    615

    White viterous china wash hand

    basin single centre tap hole as

    twyfords with pedestal stand at 900

    above floor level

    no. 4 200.00 800.00

    -

    616

    White viterous china wc pan (p-

    trap) as GP 1148WH with dual

    flush 6/4L cistern and wc outlet

    connector (WF 1240WH) as

    twyfords or other approved

    no. 5 300.00 1,500.00

    -

    617

    S5095 (75490BH) Screw-to-wall

    toilet roll holder as Amitage Shanks

    with chrome plated finish

    no. 5 60.00 300.00

    -

    618

    Mirror size 450 x 600 x 6mm high

    with bevelled edges on plywood

    backing: fixed with Chrome Plated

    screws with dome covers: plugged

    to wall as approved by the

    Supervision.

    no. 4 120.00 480.00

    -

    619 Bowl Urinals with 9 litre automatic

    flushing cistern, complete

    no. 2 1,300.00 2,600.00

    -

    620

    S5010 (2044100) 150 x 150mm

    fully recessed viteous china soap

    dish as Armitage Shanks

    no. 1 60.00 60.00

    -

    621

    Chromium plated shower

    comprisimg 12mm 900 bend

    connected to concealed galvanised

    water supply pipes, 12mm stop

    valve, 915mm long riser pipe

    97804000, 405mm projection

    straight shower arm

    66904k1,100mm diametre shower

    head 97804000, complete with

    fixing clips to tiled wall as armitage

    shanks or equal and approved.

    no. 1 800.00 800.00

    Sub Total Carried to Summary 6,540.00

    6/3

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    622 200x200mm Floor Trap no. 2 100.00 200.00

    -

    623

    Allow for testing the whole of the

    sanitary installation during the

    progress of the works and again at

    completion and leave in perfect

    working order to the satisfaction of

    the relevant authority.

    sum 1 200.00 200.00

    PLUMBING PIPE WORK

    62412mm pipe fixed to wall in chase.

    m 15 12.00 180.00

    625 Ditto but to 20mm m 20 15.00 300.00

    626

    20mm galvanised pipe laid in the

    ground including excavation and

    backfill.(prov)

    m 370 15.00 5,550.00

    EXTRA OVER FOR

    627 20mm plug no. 10 10.00 100.00

    628 20mm equal tee no. 10 10.00 100.00

    629 20mm reducing tee no. 10 9.00 90.00

    630 12mm union no. 10 12.00 120.00

    631 12mm - 20mm elbows no. 15 10.00 150.00

    632 12mm equal tee. no. 10 10.00 100.00

    63312mm High pressure ball valve

    jointed to steel galvanised pipeno. 10 10.00 100.00

    634

    Allow for the sterilisation and

    flushing out of the entire cold water

    installation.

    Item 1 200.00 200.00

    635Bulider's work in connection with

    plumbing services.Item 1 380.00 380.00

    Sub Total Carried to Summary 7,770.00

    6/4

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    INTERNAL PLUMBING AND

    DRAINAGE

    TENDERERS MUST ALLOW IN

    THEIR PIPE WORK PRICE FOR

    ALL COUPLING, CONNECTORS

    AND JOINTS ETC. REQUIRED IN

    THE RUNNING LENGTH OF

    PIPEWORK AND ALSO WHERE

    STATED FOR PIPE FIXING CLIP

    OR HOLDERBATS PLUGGED

    AND SCREWED.

    636

    100mm Upvc Soil and vent fixed to

    wall with and include approved

    pipe clip

    m 10 25.00 250.00

    637

    110mm HD UPVC soil pipe laid in

    the ground including excavation

    and backfill.(prov)

    m 55 25.00 1,375.00

    638

    150x150mm gully trap completed

    with cover one 100mm outlet

    including bedding and surrounding

    with 150mm plain concrete grade

    "20" and joining to uPVC drain pipe

    and all necessary excavation

    disposal and form work

    no. 4 90.00 360.00

    639

    Manhole size 600x450x600mm

    deep intenally comprising 100mm

    thick concrete grade 20 base with

    225mm thick solid concrete block

    walls, rendered internally

    600x450mm precast concrete

    manhole cover with 2 No. lifting

    rings set in 75mm reinforced

    concrete slab including excavation,

    backfilling, removing surplus

    excavated material and all

    accessories to detail.

    no. 4 360.00 1,440.00

    Sub Total Carried to Collection 3,425.00

    6/5

  • Bill 600 - Water Supply and Sewerage System

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Sewer System

    Demolition and clearance

    640General clearance of working

    width, 2.5 mm

    2 425 5.00 2,125.00

    Pipework - Pipes

    641PN 6 uPVC sewer pipe to BS 4660

    with flexible rubber ring joints

    642 OD 110mm sewer pipe m 170 15.00 2,550.00

    PIPEWORK - MANHOLES AND PIPEWORK ANCILLARIES

    Blockwork manholes complete with

    benching and precast concrete

    covers. (concrete class 35/20) at

    connections from interceptor tanks

    643 Manholes depth not exceeding 1.5m nr. 3 250.00 750.00

    644 Manholes depth 1.5 - 2.0m nr 3 340.00 1,020.00

    645 Manholes depth 2.0 - 2.5m nr 2 420.00 840.00

    Sub Total Carried to Summary 7,285.00

    SUMMARY

    Sub total Page 1 9,480.00

    Sub total Page 2 15,334.00

    Sub total Page 3 6,540.00

    Sub total Page 4 7,770.00

    Sub total Page 5 3,425.00

    Sub total Page 6 7,285.00

    Total carried to Main Summary 49,834.00

    6/6

  • Bill 700 - Fire Water Main and Fire Tank

    RATE Amount

    (USD) (USD)

    700FIRE WATER MAIN AND

    FIRE TANK

    PIPEWORK - PIPES

    uPVC pipes to PN 10 to BS3505

    with flexible rubber ring joints

    701 OD 110mm uPVC, pipe in trench

    depth not exceeding 1.5m.

    m 270 15.00 4,050.00

    PIPEWORK - FITTINGS AND

    VALVES

    Pipe fittings to PN 10

    Bends

    702OD 110mm uPVC 90

    o Socket

    Bend. Nr. 10 100.00 1,000.00

    Junctions and branches

    703 OD 100 x 100mm socket Tee Nr. 10 200.00 2,000.00

    -

    Adaptors -

    -

    704 DN 100mm DI Flanged Adaptor Nr. 4 200.00 800.00

    -

    Hand operated cast iron gate

    valves to BS 5163, to PN 20 -

    -

    705 DN 100mm Flanged Gate Valve. Nr. 2 340.00 680.00

    Sub Total Carried to Summary 8,530.00

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    7/1

  • Bill 700 - Fire Water Main and Fire Tank

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Fire Hydrant

    706

    Surface (pillar) fire hydrant screw-

    down type with screwed outlet, PN

    16

    Nr. 2 2,000.00 4,000.00

    MISCELLANEOUS WORK

    707Pump house including , pipework

    and fittings1 16,000.00 16,000.00

    Fire tank

    DEMOLITION AND SITE

    CLEARANCE

    EARTHWORKS

    Excavation for foundations

    708 Reservoir m3 20 5.00 100.00

    General excavation

    Topsoil

    709 Reservoir m3 20 5.00 100.00

    Rock, depth not exceeding 1m

    710 Reservoir m3 20 60.00 1,200.00

    Excavation Ancillaries

    Disposal of excavated material

    711 Rock m3 20 8.00 160.00

    Double handling of excavated

    material

    712 Topsoil to reservoir site m3 20 4.00 80.00

    713

    Material other than topsoil, rock or

    artificial hard material; reservoir

    sitem3 20 5.00 100.00

    PIPEWORK - PIPES

    Galvanised Iron Pipes to PN 16

    714 DN 100mm GI pipe, not in trench m 10 25.00 250.00

    Sub Total Carried to Summary 21,990.00

    7/2

  • Bill 700 - Fire Water Main and Fire Tank

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    715 uPVC pipes to PN 20 to BS3505

    716OD 160mm uPVC, pipe in trench

    depth not exceeding 1.5m.m 30 40.00 1,200.00

    PIPEWORK - FITTINGS AND

    VALVES

    Galvanised Iron pipe fittings to

    PN 16

    Bends

    717 DN 100mm GI 90o Flanged bend Nr. 2 40.00 80.00

    718 DN 150mm GI 90o Flanged Bend Nr. 6 45.00 270.00

    Tees

    719 DN 150 x 150mm GI Flanged Tee Nr. 1 75.00 75.00

    Adaptors

    720 DN 100mm GI Flanged Adaptor Nr. 3 195.00 585.00

    721 DN 150mm GI Flanged Adaptor Nr. 3 235.00 705.00

    Bellmouths

    722 DN 150mm GI Bellmouth Nr. 1 520.00 520.00

    Straight Specials

    723 Double Flanged Pipe Piece

    Length not exceeding 1m

    724 DN 150mm GI Nr. 5 55.00 275.00

    Length 1 - 2m

    725 DN 100mm GI Nr. 3 45.00 135.00

    726 DN 150mm GI Nr. 1 100.00 100.00

    Length 2 - 4m

    727 DN 150mm GI Nr. 1 185.00 185.00

    Sub Total Carried to Summary 4,130.00

    7/3

  • Bill 700 - Fire Water Main and Fire Tank

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Single Flanged Pipe Piece, length

    not exceeding 1m

    728 DN 150mm GI Nr. 1 55.00 55.00

    uPVC pipe fittings to PN 20 to

    BS3505

    Bends

    729OD 110mm uPVC 90

    o Socket

    BendNr. 1 155.00 155.00

    Valves to PN 20

    Hand operated Cast Iron Gate

    Valves

    730 DN 100mm Flanged Gate Valve Nr. 1 340.00 340.00

    731 DN 150mm Flanged Gate Valve Nr. 2 460.00 920.00

    Flap valves

    732 DN 150mm GI Flap Valve Nr. 1 280.00 280.00

    Ball Float Valves

    733 DN 100mm Ball Float Valve Nr. 1 1,530.00 1,530.00

    Water Meters

    Helix 'Woltman' bulk water meter

    to BS 5728

    734 for inlet DN 100mm pipe Nr. 1 1,470.00 1,470.00

    735 for outlet DN 150mm pipe Nr. 1 2,140.00 2,140.00

    PIPEWORK - PIPEWORK

    ANCILLARIES

    Other Stated Chambers

    736

    Water meter Chamber (Drawing

    No. BHLWS - STD/DWG 001)

    depth not exceeding 1.5m

    Nr. 1 520.00 520.00

    MISCELLANEOUS

    METALWORK

    737 Water level indicator Nr. 1 920.00 920.00

    Sub Total Carried to Summary 8,330.00

    7/4

  • Bill 700 - Fire Water Main and Fire Tank

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    738

    Hot Pressed Steel Sectional Tank

    115m3 elevated 6m above the

    ground complete with reinforced

    concrete dwarf walls, access

    ladder and lockable inspection

    cover

    Sum 1 45,000.00 45,000.00

    739

    Fire Hydrant: Supply and install a

    surface (pillar) fire hydrant screw

    down type with screwed outlet PN

    10

    No. 5 2,000.00 10,000.00

    Sub Total Carried to Summary 55,000.00

    SUMMARY

    Sub total Page 1 8,530.00

    Sub total Page 2 21,990.00

    Sub total Page 3 4,130.00

    Sub total Page 4 55,000.00

    Total carried to Main Summary 89,650.00

    7/5

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    800 WASTE COLLECTION SHED

    Element A - SUBSTRUCTURE

    801 Excavate column base not exceeding 1.50m

    deep. m

    3 5.83 5.14 29.98

    802 Return, fill in and ram imported approved murram

    around foundations.m

    3 3.89 16.69 64.89

    803 Load, wheel and deposit surplus as directed. m3 1.94 4.50 8.75

    804 50 mm Concrete blinding grade 15 m2 4.86 15.00 72.90

    Vibrated reinforced concrete grade 25 in

    805 Column bases. m3 1.46 280.00 408.24

    806 Columns studs. m3 0.65 280.00 181.44

    High yield square twisted bars reinforcement

    to BS 4449

    807 8 mm Diameter bar. Kg 19.22 3.50 67.27

    808 12 mm Ditto. Kg 108.69 3.50 380.42

    Sawn formwork

    809 Sides of column stud m2 8.64 15.00 129.60

    Sub Total Carried to Summary 1,343.48

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    8/1

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Element B - FRAME

    UB Stanchions

    810 100 x 100 x 4 mm SHS stanchion. Kg 288 2.54 731.52

    811 300 x 300 x 6 mm Base plate fixed to concrete

    Column stud with 4No. J bolts.No 6 22.50 135.00

    812 60 x60 x5 mm MSA diagonal bracing Kg 264 2.54 669.54

    Element C - ROOF

    813 Supply and assemble 50 x50 x 3 SHS members

    to form truss as indicated Kg 7,657 2.54 19,448.88

    80x 40x 3 mm RHS RaftersKg 356 2.54 903.34

    814 100 x 50 x 2 mm Z purlins. m 80 13.50 1,080.00

    815 30 mm x 1.5 mm thick pre-formed m.s fascia

    boards welded to angle cleats at rafter ends to

    detail.

    m 14 9.50 133.00

    816 150mm wide x 100mm deep x 2mm U shaped

    gutter.m 14 48.50 679.00

    817 75 x 75 x 6mm Angle cleats fixed to rafters as per

    details.No 30 4.80 144.00

    822 26 Gauge pre-painted galvanized IT4 sheet and

    fixing accessories as manufactured by Messrs

    Roofings Ltd or other approved manufacturers

    lapped and fixed to steel Z purlins with self

    lapping screws in accordance with the

    manufacturers instructions.

    m2 220 22.50 4,945.05

    Sub Total Carried to Summary 28,869.32

    8/2

  • Bill 400 - Chemical Shed

    RATE Amount

    (USD) (USD)

    Bills of quantities for King Fisher materials yard

    Pay't

    ItemDESCRIPTION Unit Quantity

    Element D - FLOOR FINISHES

    823 supply and Install poly liner over the Waste

    collection and waste casing area m2 630.0 1.50 945.00

    824 Construct an earthbund around the Waste

    collection area using approved material as per

    detailsm

    3 8.40 25.00 210.00

    825 Supply and install waste bins/skips in the Waste

    collection shed No. 5 4,000.00 20,000.00

    Sub Total Carried to Summary 21,155.00

    SUMMARY

    Sub total Page 1 1,343.48

    Sub total Page 2 28,869.32

    Sub total Page 3 21,155.00

    Total carried to Main Summary 51,367.80

    8/3

  • Bill 800 Day works

    RATE Amount

    (USD) (USD)

    900 DAY WORKS

    Labour

    901 Mason Hour 1 10.00 10.00

    902 Welder Hour 1 10.00 10.00

    903 Steel fixer Hour 1 10.00 10.00

    904 Equipment operator Hour 1 12.00 12.00

    905 Electrician Hour 1 10.00 10.00

    -

    906 Plumber Hour 1 10.00 10.00

    907 Unskilled labour Hour 1 5.00 5.00

    Materials

    908Supply,dump approved

    gravel, spreadand compact to

    98% MDD

    m3 1 16.69 16.69

    909 Ordinary portland cement ton 1 400.00 400.00

    910 C25/20 concrete m3 1 300.00 300.00

    91112 mm High tensile

    reiforcement barkg 1 4.00 4.00

    912 Formwork m2 1 15.00 15.00

    913 230 mm blockwork m2 1 50.00 50.00

    914 150 mm block work m2 1 30.00 30.00

    915 Hot rolled steel section kg 1 3.00 3.00

    Daily Equipment Hire

    Provisional

    916 Grader Hire 240G Day 1 600.00 600.00

    917 Bull dozer Hire D7 Day 1 800.00 800.00

    918 Wheel loader Hire 938 Day 1 750.00 750.00

    919 Track Excavator Hire 225 Day 1 800.00 800.00

    920 Vibratory roller Hire 10 ton Day 1 600.00 600.00

    921 Water bowser Hire 5m3 Day 1 200.00 200.00

    922 20 ton Tipper truck Day 1 100.00 100.00

    923Low bed truck and Trailer hire

    Day 1 600.00 600.00

    924 Pedstrian Roller 2 ton Day 1 80.00 80.00

    SUB - TOTAL BILL 800: DAY WORKS 5,415.69