KEY NOTE HILLSTA EXTERNAL v2

40
Fan Hao 范范 •Master in 2014 , Tongji University •Joined CCDC 2014 Site Engineer in HILLSTA 2014. 8 ~ 2016.4 in charge of External works Site Engineer in ECO 2016.4 ~ Now in charge of 34 Townhouses

Transcript of KEY NOTE HILLSTA EXTERNAL v2

Page 1: KEY NOTE HILLSTA EXTERNAL v2

Fan Hao 范灏• Master in 2014 , Tongji University • Joined CCDC 2014

• Site Engineer in HILLSTA• 2014. 8 ~ 2016.4 in charge of External works

• Site Engineer in ECO • 2016.4 ~ Now in charge of 34 Townhouses

Page 2: KEY NOTE HILLSTA EXTERNAL v2

External WorkHillsta Project

Shared by FAN HAO

Page 3: KEY NOTE HILLSTA EXTERNAL v2
Page 4: KEY NOTE HILLSTA EXTERNAL v2

Hillsta (at CCK/Bukit Panjang)•3 Blocks (20-23 stories), 20 townhouse units, totally 416

units•1 MSCP (5 decks)•A lot of Lifestyle facilities and landscape.

Page 5: KEY NOTE HILLSTA EXTERNAL v2

External work Scope•Drain, Sewage, underground service.(PUB SP)•Road, retaining wall (FSSD LTA)• Swimming pools •Pavilions, canopies, link ways• Landscape plantings (NPARK)• External floor finishing•Common area ID works

Page 6: KEY NOTE HILLSTA EXTERNAL v2
Page 7: KEY NOTE HILLSTA EXTERNAL v2

Duration and Critical date• Started at 2012.11• First T.O.P. inspection time was 2015.11.30. (36 Months)• Main Building structure finished at 2014.10. (24 Months)• External Work started at 2014.9 and finished at 2015.11, (15 Months)

Page 8: KEY NOTE HILLSTA EXTERNAL v2
Page 9: KEY NOTE HILLSTA EXTERNAL v2

Challenges of External Works•Drawings complicated•Proper construction sequence•Weather: prey to Dragon King•Critical task of each project•Site Coordination

Page 10: KEY NOTE HILLSTA EXTERNAL v2
Page 11: KEY NOTE HILLSTA EXTERNAL v2

Example1: External work between Tower A and B

• Spa Pavilions • Spa pool and Children pool• Feature Wall• Function Room• Relaxation pool

How was it built?

Page 12: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (1). Excavation and cast pump room and water tank 1

Page 13: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (2). Excavation and cast pump room and water tank 2

Page 14: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (3). cast pool 1, pool 2, pool 3

Page 15: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (4). Cast Retaining wall 1; cast pool 4 base

Page 16: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (5). Cast Retaining wall2; bend starter bars of pool4; backfill with long arm

Page 17: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (6). Cast of function room, Remove steel plate and excavate pool 5

Page 18: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and B• (7). Cast pool 4 wall

Page 19: KEY NOTE HILLSTA EXTERNAL v2
Page 20: KEY NOTE HILLSTA EXTERNAL v2

Example2: External work between Tower A and C• Meeting Pavilion• Relaxation Pool• Feature Wall• Function Room• Fire engine access• Drop-off canopy

How was it built?

Page 21: KEY NOTE HILLSTA EXTERNAL v2
Page 22: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (1). Excavation and cast pump room and water tank

Page 23: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (2). Pavilion slab and function room

Page 24: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (3). Swimming pool base(after A B inside work finish)

Page 25: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (4). Retaining wall

Page 26: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (5). Backfill and compact

Page 27: KEY NOTE HILLSTA EXTERNAL v2

External work between Tower A and C• (6). Cast Driveway slab, pavilion steel structure hoisting

Page 28: KEY NOTE HILLSTA EXTERNAL v2
Page 29: KEY NOTE HILLSTA EXTERNAL v2

Example3: Driveway before Townhouse E• Guardhouse• Flower Arbor• Power Cable and

Telecom cables• Alarm control wires• Hydro pipe, main water

inlet• Gas trench• Unit water supply

How was it built?

Page 30: KEY NOTE HILLSTA EXTERNAL v2
Page 31: KEY NOTE HILLSTA EXTERNAL v2

Driveway before Townhouse E• Excavation and boundary wall

Page 32: KEY NOTE HILLSTA EXTERNAL v2

Driveway before Townhouse E• Drain along driveway 1st

finish

Page 33: KEY NOTE HILLSTA EXTERNAL v2

Driveway before Townhouse E• Underground services

Page 34: KEY NOTE HILLSTA EXTERNAL v2

Driveway before Townhouse E• Driveway casting and gas trench• Continue excation

Page 35: KEY NOTE HILLSTA EXTERNAL v2

Driveway before Townhouse E• Flower arbor hoisting

Page 36: KEY NOTE HILLSTA EXTERNAL v2
Page 37: KEY NOTE HILLSTA EXTERNAL v2

Some Advices• External structure excavate from deepest 1st,• Don’t forget Unground services. Careful about Power cable.• As Maincon, must understand different department. • If possible, develop a real time as-built drawing, for coordination. • Drainage is first to consider. Road follow drainage• Be aware of storm water during construction

Page 38: KEY NOTE HILLSTA EXTERNAL v2
Page 39: KEY NOTE HILLSTA EXTERNAL v2
Page 40: KEY NOTE HILLSTA EXTERNAL v2

很惭愧,做了一些微小的工作,谢谢大家!