Kemal gezmis rail one

51
Riyadh / KSA | May 6 th , 2014 1 | RHEDA 2000 ® For every application, the optimal solution Kemal Gezmis, Rail.One GmbH Riyadh, May 6 th , 2014

Transcript of Kemal gezmis rail one

Page 1: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 11

| RHEDA 2000®

For every application, the optimal solution

Kemal Gezmis, Rail.One GmbH

Riyadh, May 6th, 2014

Page 2: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 2

� Company profile

� RHEDA 2000® - System design and components

� RHEDA 2000® - Unique solution for different structures

� RHEDA 2000® - Ideal system for dessert regions

� RHEDA 2000® - Modifications

� RHEDA MRT

� RHEDA City

� RHEDA RX

� References

Topics

Page 3: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 3

Rail.OneCompany profile

Page 4: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 4

We offer a broad portfolio of products and services involving all aspects of railways and infrastructure, tailored to individual requirements.

RAIL.ONE – Your one-stop provider

Page 5: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 5

New markets

UnitedStates

SouthAfrica

India

China

Russia

AlgeriaUAE

Kazakhstan

Greece

Poland

Oman

Worldwide activities of RAIL.ONE

Core markets with own production or partnerships

Active business development

Canada

Australia

Brazil

Qatar

Page 6: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

System design and components

Page 7: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 7

The Rheda Development Stages

Page 8: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 8

Ballastless tracks – Cross-section of RHEDA 2000® on embankment

Page 9: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 9

Further development: ballastless track without continuous reinforcement, on hydraulically bonded supporting layer

Page 10: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 10

Ballastless tracksState-of-the-art solutions for high speed lines

Main characteristics:

� Low maintenance

� High availability

� Increased service life

� Reduced life cycle costs

� Low structure height

� Low weight

� High lateral track resistance which allows future speed increases in combination with tilting technology

� No problems with churning of ballast particles at high-speed

Page 11: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 11

Ballastless tracksTrack Status Number Q – Sengeberg-tunnel – Rheda system

Page 12: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 12

� Fully takes into account RHEDA design principles by Prof. Dr. J. Eisenmann

� Is a system with a modified, i.e. low height bi-block sleeper with protruding lattice truss reinforcement along the entire length of sleeper thus providing:

� High durability due to continuously improved composite action effect between sleeper and structural concrete

� Accurate track geometry

� A high level flexibility enabling combination with other types of rail fastening and other device fixations

� A reduction in construction height

� Avoids formation of longitudinal cracks in the slab concrete, due to troughless construction

� Facilitates and improves construction performance thanks to lighter track grid and mechanisation of assembly procedures

� System technology is consistent throughout for all track types, such as earthwork constructions, bridges and tunnels as well as turnouts, expansion joints etc.

Ballastless tracks - RHEDA 2000® – State-of-the-art

RHEDA 2000® is an advanced development of the Rheda design which:

Page 13: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

Unique solution for different structure

Page 14: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 14

The RHEDA 2000® ballastless track system on grade

Page 15: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 15

The RHEDA 2000® ballastless track system on grade

Page 16: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 16

The RHEDA 2000® ballastless track system on bridges

Page 17: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 17

The RHEDA 2000® ballastless track system on bridges

Page 18: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 18

The RHEDA 2000® ballastless track system on bridges

Page 19: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 19

The RHEDA 2000® ballastless track system in tunnels

Page 20: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 20

The RHEDA 2000® ballastless track system in tunnels

Page 21: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 21

Higher vertical

and horizontal loads

RHEDA 2000® heavy-haul

Page 22: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 22

Turnout technology of the RHEDA 2000® ballastless track system

Page 23: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 23

Turnouts installed as part of the RHEDA 2000® ballastless track system, in the Berlin North-South Link

Page 24: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

Ideal system for dessert areas

Page 25: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 25

Main risks from sand drift

� Rail blockade

� Ballast fouling �

� Track stiffening � high wear

� Erosion of sleeper surface

RHEDA 2000® for desert areas

Page 26: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 26

Measures against rail blockade:Elevated rail seat

RHEDA 2000® for desert areas

4-5 cm

Standard RHEDA 2000® slab track

Rail seat

Slab concrete

Page 27: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 27

Measures against erosion:High-abrasive-resistant concrete or attrition material

RHEDA 2000® for desert areas

• Minimization of malfunctions and costs for their correction

• Avoidance of cost-intensive preventive and remedial maintenance

• Special concrete mix designs to withstand sandblasting

• Higher rail bases and fastenings to reduce air resistance

Summary:

Page 28: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

Modifications – RHEDA MRT

Page 29: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 29

RHEDA MRT3rd Rail application

Requirements

� Construction without long blocate

� Accurate and time saving installation of the 3rd rail.

System Application

� Design of a special type of sleeper for fixing the supports of the 3rd rail.

Page 30: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

Modifications – RHEDA City

Page 31: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 31

RHEDA CITY –D (direct supported rail)

Page 32: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 32

RHEDA CITY –C (continues supported rail)

Page 33: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 33

RHEDA CITY –G (Green Track)

Application Karlsruhe

Application Berlin

Page 34: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

RHEDA 2000®

Modifications – RHEDA RX (M-S Systems)

Page 35: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 35

RHEDA 2000® on a mass-spring system with individual point support

Page 36: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 36

RHEDA 2000® on a mass-spring system installed on a strip support

Page 37: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 37

RHEDA 2000® on a mass-spring system installed on entire-surface supports

Page 38: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 38

RHEDA 2000® on a mass-spring system installed on entire-surface supports

Page 39: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014

References

Page 40: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 40

RHEDA 2000® on the High Speed Railway line from Mekkah to Medinah, in KSAConstruction:2013 - ongoing

Page 41: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 41

RHEDA 2000® on the line from Seoul to Busan (2nd phase, Daegu to Busan), in South KoreaConstruction: 2007-10

Page 42: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 42

RHEDA 2000® on the line from Wuhan to Guangzhou, in China; Construction: 2007-2010

Page 43: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 43

RHEDA 2000® for the Guadarrama Tunnel, SpainConstruction: 2006-2007

Page 44: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 44

RHEDA 2000® on the line from Nuremberg to Ingolstadt, GermanyConstruction: 2004-2005

Page 45: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 45

RHEDA 2000® on the Taiwan High Speed Rail Line Construction: 2003-2006

Page 46: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 46

RHEDA 2000® on the high-speed line HSL Zuid in HollandConstruction: 2002-2006

Page 47: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 47

180,000 RHEDA-sleepers for the high-speed line Cologne –Frankfurt Construction: 1999-2002

Page 48: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 48

DublinOver 8 km of RHEDA CITY track, 5.6 km of covered and 2.5 km of open trackConstruction: 2009-10

Page 49: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 49

Over 180 km of track with the systemvariants RHEDA CITY und RHEDA CITY-G in Germany since 1998

Page 50: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 50

Den Haag, The NetherlandsChur, Switzerland

Croydon, England Warsaw PolandExemplary projects with RHEDA CITY in Europe

Page 51: Kemal gezmis rail one

Riyadh / KSA | May 6th, 2014 51

Contact

Kemal GezmisSales Manager Middle East & North Africa (MENA)

RAIL.ONE GmbHIngolstaedter Strasse 5192318 Neumarkt

Tel +49 9181 8952-254Fax +49 9181 8952-5050Mobile +49 172 [email protected]