KEARNEY R-1 SCHOOL DISTRICT 2017 RE-ROOF PROJECT HIGH ... · G. Contract Labor: For this project,...
Transcript of KEARNEY R-1 SCHOOL DISTRICT 2017 RE-ROOF PROJECT HIGH ... · G. Contract Labor: For this project,...
December 2016
KEARNEY R-1 SCHOOL DISTRICT
2017 RE-ROOF PROJECT
HIGH SCHOOL-EAST END
TITLE PAGE
KEARNEY SCHOOL DISTRICT 2017 RE-ROOF PROJECT DECEMBER 2016
HIGH SCHOOL EAST END
SECTION 00 01 00 TABLE OF CONTENTS
1.1 INTRODUCTORY INFORMATION
A. Title Page
1.2 PROCUREMENT REQUIREMENTS
A. Invitation to Bid
B. Bid Form
C. Bid Bonds
D. Contractor Qualification Statement
E. E-Verify
F. EMR Rating
G. Contract Labor
H. Prevailing Wage
1.3 CONTRACTING REQUIREMENTS
A. Purchase Order
B. Application for Payment
C. Performance and Payment Bond
D. Certificate of Insurance
1.4 SPECIFICATIONS & DETAILS
A. PVC Roofing
B. Sheet Metal Flashing & Trim
C. Manufacturer’s Details
END OF SECTION 00 01 00 SECTION 001100 INVITATION TO BID
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Notice to Bidders: Qualified bidders are invited to submit bids for Project as described in this
document according to the Invitation to Bid.
B. Project Identification: Roof Improvements.
1. Kearney High School East End, 715 East 19th Street, Kearney, Missouri 64060.
C. Owner: Kearney R-1 School District, 1002 South Jefferson Street, Kearney, Missouri 64060.
1. Owner’s Representative: Doug Sublett; 816.401.3978; [email protected].
D. Construction Contract: Purchase Order will be issued to the best qualified bidder.
1.2 BID SUBMITTAL AND OPENING
A. Owner will receive sealed bids until the bid time and date at the location indicated below.
Owner will consider properly prepared bids and delivered as follows:
1. Bid Date: December 19, 2016.
2. Bid Time: 2:00pm.
3. Location: Kearney R-1 School District Office, 1002 South Jefferson Street, Kearney,
Missouri 64060.
B. Bids will be thereafter opened and read aloud.
C. The intent is to have bid approval at the January school board meeting.
1.3 BID SECURITY
A. Bid security shall be submitted with each bid in the amount of 5 percent of the bid amount. No
bids may be withdrawn for a period of 60 days after opening of bids. Owner reserves the right
to reject any and all bids and to waive informalities and irregularities.
1.4 PRE-BID CONFERENCE
A. A mandatory pre-bid conference for all bidders will be held at Kearney High School on
December 7, 2016 at 2:00pm, local time. Sign in at the high school’s front office. Directions to
the appropriate conference room will be provided by the front office personnel.
1.5 BIDDING DOCUMENT PROCUREMENT
A. Electronic Documents: Obtain after December 2, 2016 by contacting Doug Sublett at
1. Electronic Documents may also be obtained at pre-bid conference, December 7, 2016.
1.6 PROJECT SCHEDULE
A. Work shall begin on receipt of notice to proceed and/or purchase order and shall complete the
Work within the contract time.
B. Completion Schedule Requirement: Must be completed to the extent noted at the time noted
below.
1. March 1, 2017: Submittals, Construction Submittals, and Shop Drawings.
2. May 30, 2017: Pre-installation Conference.
3. June 1, 2017: Begin Roof Construction.
4. June 23, 2017: Substantial Completion.
5. June 30, 2017: Final Completion.
C. Contractor has one week to complete punch list items created by substantial completion.
1.7 BIDDER’S QUALIFICATIONS
A. Bidders must be properly licensed under the laws governing their trade and be able to obtain
insurance and bonds required for the Work. A Performance Bond, a separate Labor and
Payment Bond, and Insurance in a form acceptable to Owner will be required of the successful
Bidder.
END OF SECTION 00 1100
SECTION 004000 BID FORM
PROJECT: 2017 Re-Roof Project (High School East End)
715 East 19th Street
Kearney, Missouri 64060
OWNER: Kearney R-1 School District
1002 South Jefferson
Kearney, Missouri 64060
FROM: Contractor:
Address:
City State Zip:
Bidder, having reviewed specification and details and having inspected actual site conditions, understands
that in signing this Bid waives the right to plead misunderstanding regarding same.
Bidder acknowledges any changes to specifications or details via written clarification and has included
those clarifications in Bid.
Bidder agrees that Bid shall be good for 60 calendar days.
Bidder agrees Owner reserves the right to accept or reject any or all bids.
Bidder agrees to start Work on May 30, 2017 and achieve substantial completion by June 23, 2017 and
final completion on June 30, 2017.
Bidder agrees, if awarded a purchase order, to submit to Owner submittals, construction submittals, and
shop drawings within 14 days of receipt of purchase order or notice to proceed.
BASE BID: Perform all work as specified and detailed. Include $3,000 for unforeseen
conditions.
Lump Sum of $__________________________________
UNIT PRICES Unit Price 1: Board foot cost for replacing 2 x wood blocking: $____________________
NOTE: Subcontractor: List the sub-contractor to be used for project.
Sheet Metal:______________________________________
Roofing Manufacturer:_____________________________
Respectively Submitted,
________________________________________
Name of Corporation
_________________________________________
Title of Officer
_________________________________________
Officer Signature
_________________________________________
Address for Communication
_________________________________________
Date
END OF SECTION 00 4000
SECTION 00 04 30 PROCUREMENTS REQUIREMENTS
1.8 PROCUREMENT REQUIREMENTS
A. Invitation to Bid: Reference Form
B. Bid Form: Reference Form
C. Bid Bonds: AIA Document A310 2010 Edition Bid Bond shall be used. This form is approved
and recommended by the American Institute of Architects (AIA).
D. Contractor’s Qualification Statement: AIA Document A305 1986 Edition Contractor’s
Qualification Statement shall be used. This form is approved and recommended by the
American Institute of Architects (AIA). In addition to this form, contractor is to provide a
reference list of five school districts where they have completed re-roof projects similar to this
project in the last 5 years; include names, phone numbers, and email addresses.
E. E-Verify: U.S. Citizenship and Immigration Services; U.S. law requires companies to employ
only individuals who may legally work in the United States-either as U.S. citizens, or foreign
citizens who have the necessary authorization. This diverse workforce contributes greatly to the
vibrancy and strength of our economy, but that same strength also attracts unauthorized
employment. E-Verify is an interest-based system that allows businesses to determine the
eligibility of their employees to work in the Unites States. E-Verify is fast, free and easy to use-
and it’s the best way employees can insure a legal workforce. E-Verify will be used for this
project.
F. Experience Modification Rating (EMR): An insurance EMR rating is an indication of the
frequency and severity of past worker’s compensation claims. A company’s EMR rating
measures its past history of worker’s compensation claims against others businesses in the same
industry. For federal projects, contractors are required to have an EMR rating of .90 or less.
That is the rating requirement for this project.
G. Contract Labor: For this project, the roofing contractor will not be allowed to use contract labor
forces. All roofing work needs to be performed by the contractor’s employees. Sheet metal
work may be subcontracted to a company and must be listed on the bid form as such.
H. Prevailing Wage: For this project, contractor shall use the Missouri Division of Labor
Standards, Annual Wage Order No. 23, March10, 2016, Section 024, Clay County.
1. Contractor shall file with Owner on a weekly basis certified payrolls. Progress payments
shall not be approved if weekly certified payrolls are not up to date and in proper order.
2. Contractor shall file with Owner upon completion of project, prior to final payment,
enclosed affidavit stating they have fully complied with the provisions and requirements
of “Prevailing Wage Law” Section.
3. Owner shall not approve final pay request until affidavit is filed and is proper form and
order.
END OF SECTION 00 04 30
SECTION 00 05 30 CONTRACTING REQUIREMENTS
1.9 CONTRACTING REQUIREMENTS
A. Purchase Order: District will issue a purchase order to the lowest responsible bidder using the
following projected schedule:
1. December 22, 2016: Bids are received by the District.
2. January 18, 2017: School Board meets to approve the lowest responsible bid.
3. January 25, 2017: Purchase order is issued by the District.
B. Application for Payment: Contractor shall submit pay requests per the following schedule of
values:
1. March 1, 2017, pay application number one: Costs for bonds, warranties, designated
portion of third party services, etc.
2. June 1, 2017, pay application number 2: Cost of materials if stored on school property or
in a bonded warehouse.
3. June 23, 2017, pay application number 3: Substantial completion or 90% leaving 10%
retainage for final payment. Contractor to supply District with substantial completion
certificate.
4. June 30, 2017, pay application number 4: Final completion or 100%. Contractor to
provide close out documents with final pay request including such items as lien waivers,
warranties, etc.
C. Performance and Payment Bond: AIA Document A312 2010 Edition Performance and Payment
Bond shall be used. This form is approved and recommended by the American Institute of
Architects (AIA).
D. Insurance Requirement: Use Acord Document 25-S Certificate of Liability Insurance Form.
Certificate holder is Kearney R-1 School District, 1002 South Jefferson Street, Kearney,
Missouri 64060.
1. Commercial General Liability: Each Occurrence; $1,000,000.
2. Automobile Insurance (any vehicle): Each Accident; $1,000,000.
3. Excess/Umbrella Liability: Occurrence; $3,000,000.
4. Worker’s Compensation: Each Accident; $100,000.
END OF SECTION 00 05 30
SECTION 07 5400–THERMOPLASTIC ROOFING
PART 2 - GENERAL
2.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
2.2 SUMMARY
A. Existing Conditions: Information obtained from roof core cuts; this information does not
relieve contractor’s responsibility from verification of existing conditions; core information was
not tested for asbestos.
1. Granule surfaced modified bitumen membrane and roofing felt system set in asphalt.
2. ½” wood fiber insulation; adhered with asphalt.
3. 1.5” polyisocyanurate roof insulation mechanically attached.
4. 5/8” gypsum board; loose laid.
5. Steel deck.
B. Section Includes:
1. Preparation of existing roof system for a recover roof system, demolition of existing base
flashing, penetration flashing, drainage flashing, strip in flashing, and sheet metal
flashing.
2. Rough carpentry.
3. Drain repair.
4. Cover board.
5. Adhered thermoplastic membrane roofing system.
6. Equipment stands.
C. Related Sections:
1. Section 07 6200 "Sheet Metal Flashing and Trim" for metal roof penetration flashings,
flashings, and counter flashings.
2.3 DEFINITIONS
A. Roofing Terminology: See ASTM D 1079 and glossary in NRCA's "The NRCA Roofing and
Waterproofing Manual" for definition of terms related to roofing work in this Section.
B. Third Party Services: Third party services are divided into two categories; 1) warranty services,
and 2) project technical services. Specifications shall be provided to third party by Owner.
Submittals and shop drawings shall be provided to third party by contractor prior to pre-
installation conference.
1. Warranty Services: Review construction submittals; review roofing shop drawings;
attend pre-installation conference; project start up visit (1st or 2nd day of construction);
interim site visit (every two weeks of construction). If a roofing manufacturer’s technical
department offers these services, contractor is not required to use third party. If not, then
the contractor shall solicit and pay for third party to complete services.
2. Project Technical Services: Third party will attend pre-bid conference; review
manufacturer’s details and red line them to be project specific; review sheet metal shop
drawings; conduct a project start up visit to assist with non-warranted items such as
demolition of unused equipment, any flashing removal; visit the project to review sheet
metal application preferably at the same time the roofing system’s technical
representative is conducting the roofing final inspection. Project technical services are to
be paid directly by contractor to third party agency.
2.4 PERFORMANCE REQUIREMENTS
A. General Performance: Installed membrane roofing and base flashings shall withstand specified
uplift pressures, thermally induced movement, and exposure to weather without failure due to
defective manufacture, fabrication, installation, or other defects in construction. Membrane
roofing and base flashings shall remain watertight.
B. Material Compatibility: Provide roofing materials that are compatible with one another under
conditions of service and application required, as demonstrated by membrane roofing
manufacturer based on testing and field experience.
C. FM Approvals Listing: Provide membrane roofing, base flashings, and component materials
that comply with requirements in FM Approvals 4450 and FM Approvals 4470 as part of a
membrane roofing system, and that are listed in FM Approvals' "Roof Nav" for Class 1 or
noncombustible construction, as applicable. Identify materials with FM Approvals markings.
1. Fire/Windstorm Classification: Class 1A-60.
2. Hail Resistance: SH-Severe Hail.
D. Solar Reflectance Index: Not less than 78 when calculated according to ASTM E 1980, based
on testing identical products by a qualified testing agency.
E. Energy Performance: Provide roofing system that is listed on the DOE's ENERGY STAR
"Roof Products Qualified Product List" for low-slope roof products.
2.5 ACTION SUBMITTALS
A. Product Data and Informational Submittals: For each type of product indicated.
1. Field membrane (fleece back).
2. Flashing membrane (bare back).
3. Membrane and flashing adhesive.
4. Gypsum cover board.
5. Pipe supports.
6. Sample warranty.
7. Manufacturer certificate stating roofing installer is a certified applicator.
8. Safety data sheet for each product data submitted.
9. Cover page for submittal package.
10. Scope of work summary page for submittal package.
11. Submittals shall be reviewed and accepted by roofing membrane manufacturer’s
technical department.
B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.
1. Base flashings and membrane terminations.
2. Attachment pattern of gypsum cover board for field, perimeter, and corner.
3. Strip in flashings.
4. Base flashings.
5. Drainage flashings.
6. Pipe support spacing.
7. Shop drawings shall be reviewed and accepted by roofing membrane manufacturer’s
technical department.
8. Cover page for shop drawing package.
C. Samples for Verification: For the following products:
1. Sheet roofing, of color specified, including T-shaped side and end lap seam.
2. Walkway pads or rolls.
2.6 QUALITY ASSURANCE
A. Manufacturer Qualifications: A qualified manufacturer that is UL listed and FM approved for
membrane roofing system identical to that used for this Project.
B. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by membrane
roofing system manufacturer to install manufacturer's product and that is eligible to receive
manufacturer's special warranty. The installer must use company employees; contract labor is
not acceptable. Full time supervision is required.
C. Exterior Fire-Test Exposure: ASTM E 108, Class A for application and roof slopes indicated,
as determined by testing identical membrane roofing materials by a qualified testing agency.
Materials shall be identified with appropriate markings of applicable testing agency.
D. Pre-installation Roofing Conference: Conduct conference at project site.
1. Meet with Owner, Architect, Owner's insurer if applicable, roofing Installer, roofing
system manufacturer's technical representative, deck Installer, and installers whose work
interfaces with or affects roofing, including installers of roof accessories and roof-
mounted equipment.
2. Review methods and procedures related to roofing installation, including manufacturer's
written instructions.
3. Review and finalize construction schedule and verify availability of materials, Installer's
personnel, equipment, and facilities needed to make progress and avoid delays.
4. Examine deck substrate conditions and finishes for compliance with requirements,
including flatness and fastening.
5. Review structural loading limitations of roof deck during and after roofing.
6. Review base flashings, shop drawings, special roofing details, roof drainage, roof
penetrations, equipment curbs, and condition of other construction that will affect roofing
system.
7. Review governing regulations and requirements for insurance and certificates if
applicable.
8. Review temporary protection requirements for roofing system during and after
installation.
9. Review roof observation and repair procedures after roofing installation.
2.7 DELIVERY, STORAGE, AND HANDLING
A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled
with manufacturer's name, product brand name and type, date of manufacture, approval or
listing agency markings, and directions for storing and mixing with other components.
B. Store liquid materials in their original undamaged containers in a clean, dry, protected location
and within the temperature range required by roofing system manufacturer. Protect stored
liquid material from direct sunlight.
1. Discard and legally dispose of liquid material that cannot be applied within its stated
shelf life.
C. Protect roof insulation materials from physical damage and from deterioration by sunlight,
moisture, soiling, and other sources. Store in a dry location. Comply with insulation
manufacturer's written instructions for handling, storing, and protecting during installation.
D. Handle and store roofing materials and place equipment in a manner to avoid permanent
deflection of deck.
2.8 PROJECT CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted weather
conditions permit roofing system to be installed according to manufacturer's written instructions
and warranty requirements.
2.9 WARRANTY
A. Entire installation of roofing system and flashing work shall be of quality required for
acceptance by membrane manufacturer in order to obtain a Full Systems No Dollar Limit
material and workmanship warranty. Services may be provided by either the roofing membrane
manufacturer’s technical representative or by third party services. Provide guaranty from date
of substantial completion of project.
1. Includes membrane sheets, base flashings, roofing accessories, and other components of
roofing system.
2. Final inspection by membrane manufacturer’s technical representative.
3. Two year follow-up audit by roofing membrane manufacturer’s technical representative.
4. Project start up site visit, typically first or second day of construction by membrane
manufacturer’s technical representative.
5. Interim site visit for every two weeks of construction by membrane manufacturer’s
technical representative.
6. Roofing Warranty Period: 20 years from date of Substantial Completion.
B. Special Project Warranty: Submit roofing Installer's warranty, on warranty form at end of this
Section, signed by Installer, covering the Work of this Section, including all components of
membrane roofing system such as membrane roofing, base flashing, and walkway products, for
the following warranty period:
1. Warranty Period: Two years from date of Substantial Completion.
PART 3 - PRODUCTS
3.1 GYPSUM COVER BOARD
A. Cover Board: ASTM C 1278/C 1278M, cellulosic-fiber-reinforced, water-resistant gypsum
substrate, 3/8 inch thick.
1. Products: Subject to compliance with requirements, provide the following or equal:
a. USG Corporation; Securock.
B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-
resistance provisions in FM Approvals 4470, designed for fastening substrate board through the
existing roof system to load bearing portion of roof deck.
3.2 PVC MEMBRANE ROOFING
A. PVC Sheet: ASTM D 4434, Type II, glass fiber reinforced, felt back.
1. Manufacturers: Subject to compliance with requirements, provide the following:
a. Sarnafil Inc.; Sarnafil G410 felt back.
2. Thickness: 60 mils minimum (guaranteed) ASTM 751.
3. Exposed Face Color: White.
B. PVC Sheet: ASTM D 4434, Type II, glass fiber reinforced, felt back.
1. Manufacturers: Subject to compliance with requirements, provide the following:
a. FiberTite: felt back.
2. Thickness: 60 mils nominal.
3. Exposed Face Color: White.
3.3 AUXILIARY MEMBRANE ROOFING MATERIALS
A. General: Auxiliary membrane roofing materials recommended by roofing system manufacturer
for intended use, and compatible with membrane roofing.
1. Liquid-type auxiliary materials shall comply with VOC limits of authorities having
jurisdiction.
2. Adhesives and sealants that are not on the exterior side of weather barrier shall comply
with the following limits for VOC content when calculated according to 40 CFR 59,
Subpart D (EPA Method 24):
a. Plastic Foam Adhesives: 50 g/L.
b. Multipurpose Construction Adhesives: 70 g/L.
c. Fiberglass Adhesives: 80 g/L.
d. Single-Ply Roof Membrane Adhesives: 250 g/L.
e. Other Adhesives: 250 g/L.
f. Welding Compounds: 510 g/L.
g. Single-Ply Roof Membrane Sealants: 450 g/L.
h. Non Membrane Roof Sealants: 300 g/L.
i. Sealant Primers for Nonporous Substrates: 250 g/L.
j. Sealant Primers for Porous Substrates: 775 g/L.
B. Sheet Flashing: Manufacturer's standard sheet flashing of same material, type, reinforcement,
thickness, and color as sheet membrane, less the fleece back.
C. Bonding Adhesive: Manufacturer's standard solvent based.
D. Metal Termination Bars: Manufacturer's standard, predrilled stainless-steel or aluminum bars,
approximately 1 by 1/8 inch thick; with anchors.
E. Metal Battens: Manufacturer's standard, aluminum-zinc-alloy-coated or zinc-coated steel sheet,
approximately 1 inch wide by 0.05 inch thick, pre-punched.
F. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-
resistance provisions in FM Approvals 4470, designed for fastening membrane to substrate, and
acceptable to membrane roofing system manufacturer.
G. Miscellaneous Accessories: Provide pourable sealers, preformed cone and vent sheet flashings,
preformed inside and outside corner sheet flashings, T-joint covers, lap sealants, termination
reglets, and other accessories.
H. Provide tapered polyisocyanurate edge strips (at drain locations).
1. Dual component polyurethane adhesive used to attach tapered edge strip.
3.4 ROUGH CARPENTRY
A. Wood Curbs and Nailers: Douglas fir 2” by 6”.
B. Plywood: Plywood shall meet the American Association (APA) Standard APA PRP-108.
Thickness is ½”.
C. Fasteners: Non-exposed, ring or barbed shank nail or screw, with a withdraw resistance of a
minimum of 100 psi.
3.5 PLUMBING
A. Existing Drains: New cadmium-plated drain bolts for all clamping rings.
B. New Drains: Josam Model Number 21500 series roof drain with lacquered cast iron body;
ASTM D2729 PVC pipe with solvent welds; removable metal dome strainer.
C. Drain Accessories: membrane flange and clamp; adjustable under deck clamp; waterproofing
flange; controlled flow weir; ASTM C547 Class I 1” glass fiber pipe insulation.
3.6 PIPE SUPPORTS
A. Light-Duty Pipe Supports: Polycarbonate resin base, with all metal parts stainless steel. Pipe
stands should accommodate up to 3” inside diameter pipe.
1. Basis-of-Design: Subject to compliance with requirements, provide the following:
a. Miro Industries: Model Number 3-RAH-7 and 3-RAH-12.
3.7 WALKWAYS
A. Flexible Walkways: Factory-formed, nonporous, heavy-duty, slip-resisting, surface-textured
walkway pads, approximately 3/16 inch thick, and acceptable to membrane roofing system
manufacturer. Locations include working side of units.
3.8 OTHER MATERIALS
A. All other materials not specifically described but required for a complete and proper installation
of the work in this Section shall be as selected by the Contractor, approved by the manufacturer,
and subject to approval by the Owner.
PART 4 - EXECUTION
4.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with
requirements and other conditions affecting performance of the Work:
1. Verify that roof openings and penetrations are in place, curbs are set and braced, and roof
drain bodies are securely clamped in place.
2. Verify that blocking, curbs, and nailers are securely anchored to roof deck at penetrations
and terminations and that nailers match thicknesses of insulation.
3. Prepare existing surfaces to receive new roof system.
4. Prepare written documentation of conditions which could be detrimental to completion or
performance of specified Work before commencing such Work.
5. Photograph interior and exterior equipment and surrounding areas after completion of
construction which may be misconstrued as damage related to demolition. File
photographs with owner’s representative.
4.2 PREPARATION
A. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing installation
according to roofing system manufacturer's written instructions. Remove sharp projections.
B. Prevent materials from entering and clogging roof drains and conductors and from spilling or
migrating onto surfaces of other construction. Remove roof-drain plugs when no work is taking
place or when rain is forecast.
C. Complete terminations and base flashings and provide temporary seals to prevent water from
entering completed sections of roofing system at the end of the workday or when rain is
forecast. Remove and discard temporary seals before beginning work on adjoining roofing.
D. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing installation
according to roofing system manufacturer's written instructions. Remove sharp projections.
E. Existing Roof Demolition and Preparation:
1. Provide temporary barricades and other forms of protection for Owner’s personnel and
public from injury due to demolition Work.
2. Protect from damage existing finish work that is to remain in place and becomes exposed
during demolition operations.
3. Score the existing roof surface in grid pattern of 10’ by 10’.
4. Remove existing base flashings and sheet metal to deck. Clear roof drains of any
material that could restrict drainage. Cut and remove base flashing 6” onto the horizontal
surface of the roof. Mechanically attach a 6” wide by 3/8” thick gypsum fiber board to
the level of the existing roof system.
5. Remove existing flashing at drains. Re-install with similar material in order to keep
existing drain sump.
6. Remove existing lead or metal flashing at penetrations.
7. Remove identified penetrations (approx. 5-6) and fill in with material to match existing.
8. Perform demolition in a systematic manner.
9. Protect against any material or debris dropping into the building or damaging new roof
membrane.
4.3 ROUGH CARPENTRY INSTALLATION
A. Install continuous wood nailers at the perimeter of the entire roof and around roof penetrations
as indicated on detail drawings.
B. Nailers shall be anchored to resist a minimum force of 300 pounds per lineal foot in any
direction. Individual nailer lengths shall not be less than 3’ long. Nail fastener spacing shall be
12” on center staggered 1/3 the nailer width and installed within 6” of each end. Two fasteners
shall be installed at the ends of the nailer lengths. Nailer attachment shall also meet the
requirements of FM loss Prevention data Sheet 1-49.
C. Thickness of nailers shall be required to match substrate or insulation height to allow smooth
transition.
D. Any existing nailer which is to remain shall be firmly anchored in place to resist a minimum
force of 300 pounds per lineal foot in any direction and shall be free of rot, excess moisture or
deterioration.
E. Stainless steel, corrosion resistant, fasteners are required.
4.4 PLUMBING INSTALLATION
A. Existing Drains: Install new clamping ring bolts, all-thread” will not be allowed. Replace all
existing plastic drain strainers and clamping rings as well as drain baskets that are missing,
broken, or cracked. Replace with new cast aluminum or cast steel.
B. New Drains: Install drain according to Josam’s printed instructions.
4.5 COVER BOARD INSTALLATION
A. Install cover board with long joints in continuous straight lines, perpendicular to roof slopes
with end joints staggered between rows. Tightly butt substrate boards together.
1. Fasten substrate board to top flanges of steel deck according to recommendations in FM
Approvals' "Roof Nav" and FM Global Loss Prevention Data Sheet 1-29 for specified
Windstorm Resistance Classification.
2. Fasten substrate board to top flanges of steel deck to resist uplift pressure at corners,
perimeter, and field of roof according to membrane roofing system manufacturers'
written instructions penetrating deck 3/4-inch.
4.6 ADHERED MEMBRANE ROOFING INSTALLATION
A. Adhere membrane roofing over area to receive roofing and install according to membrane
roofing system manufacturer's written instructions.
1. Install sheet according to ASTM D 5036.
B. Start installation of membrane roofing in presence of membrane roofing system manufacturer's
technical personnel.
C. Accurately align membrane roofing and maintain uniform side and end laps of minimum
dimensions required by manufacturer. Stagger end laps.
D. Bonding Adhesive: Apply to substrate and underside of membrane roofing at rate required by
manufacturer and allow to partially dry before installing membrane roofing. Do not apply to
splice area of membrane roofing. Fully adhere. Ribbon pattern of adhesive is unacceptable.
E. In addition to adhering, mechanically fasten membrane roofing securely at terminations,
penetrations, and perimeter of roofing.
F. Apply membrane roofing with side laps shingled with slope of roof deck where possible.
G. Seams: Clean seam areas, overlap membrane roofing, and hot-air weld side and end laps of
membrane roofing and sheet flashings according to manufacturer's written instructions to ensure
a watertight seam installation.
1. Test lap edges with probe to verify seam weld continuity. Apply lap sealant to seal cut
edges of sheet membrane.
2. Verify field strength of seams a minimum of twice daily and repair seam sample areas.
3. Repair tears, voids, and lapped seams in roofing that does not comply with requirements.
H. Spread sealant bed over deck drain flange at roof drains and securely seal membrane roofing in
place with clamping ring.
4.7 BASE FLASHING INSTALLATION
A. Install sheet flashings and preformed flashing accessories and adhere to substrates according to
membrane roofing system manufacturer's written instructions.
B. Apply bonding adhesive to substrate and underside of sheet flashing at required rate and allow
to partially dry. Do not apply to seam area of flashing.
C. Flash penetrations and field-formed inside and outside corners with cured or uncured sheet
flashing.
D. Clean seam areas, overlap, and firmly roll sheet flashings into the adhesive. Hot-air weld side
and end laps to ensure a watertight seam installation.
E. Terminate and seal top of sheet flashings and mechanically anchor to substrate through
termination bars.
4.8 PIPE SUPPORT INSTALLATION
A. Center the stand beneath the pipe so that the cradle allows the pipe to be squarely over and
through the roller of the stand.
B. Adjust the stand to the desired height and to even load with other stands. Make certain the
roller is level.
C. Set the pipe in the stand without dropping or causing undue impact. A protective sheet of
roofing material should be placed under the sand.
D. Spacing: Manufacturer’s recommendation is to not exceed 10 foot centers.
4.9 WALKWAY INSTALLATION
A. Flexible Walkways: Install walkway products in locations indicated. Heat weld to substrate or
adhere walkway products to substrate with compatible adhesive according to roofing system
manufacturer's written instructions.
4.10 PROTECTING AND CLEANING
A. Protect membrane roofing system from damage and wear during remainder of construction
period. When remaining construction will not affect or endanger roofing, inspect roofing for
deterioration and damage, describing its nature and extent in a written report, with copies to
Architect and Owner.
B. Correct deficiencies in or remove membrane roofing system that does not comply with
requirements; repair substrates; and repair or reinstall membrane roofing system to a condition
free of damage and deterioration at time of Substantial Completion and according to warranty
requirements.
C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures
recommended by manufacturer of affected construction.
4.11 ROOFING INSTALLER'S WARRANTY
A. WHEREAS <Insert name> of <Insert address>, herein called the "Roofing Installer," has
performed roofing and associated work ("work") on the following project:
1. Owner: <Insert name of Owner>.
2. Address: <Insert address>.
3. Building Name/Type: <Insert information>.
4. Address: <Insert address>.
5. Area of Work: <Insert information>.
6. Acceptance Date: <Insert date>.
7. Warranty Period: <Insert time>.
8. Expiration Date: <Insert date>.
B. AND WHEREAS Roofing Installer has contracted (either directly with Owner or indirectly as a
subcontractor) to warrant said work against leaks and faulty or defective materials and
workmanship for designated Warranty Period,
C. NOW THEREFORE Roofing Installer hereby warrants, subject to terms and conditions herein
set forth, that during Warranty Period he will, at his own cost and expense, make or cause to be
made such repairs to or replacements of said work as are necessary to correct faulty and
defective work and as are necessary to maintain said work in a watertight condition.
D. This Warranty is made subject to the following terms and conditions:
1. Specifically excluded from this Warranty are damages to work and other parts of the
building, and to building contents, caused by:
a. Lightning;
b. Peak gust wind speed exceeding 115 mph;
c. Fire;
d. Failure of roofing system substrate, including cracking, settlement, excessive
deflection, deterioration, and decomposition;
e. Faulty construction of parapet walls, copings, chimneys, skylights, vents,
equipment supports, and other edge conditions and penetrations of the work;
f. Vapor condensation on bottom of roofing; and
g. Activity on roofing by others, including construction contractors, maintenance
personnel, other persons, and animals, whether authorized or unauthorized by
Owner.
2. When work has been damaged by any of foregoing causes, Warranty shall be null and
void until such damage has been repaired by Roofing Installer and until cost and expense
thereof have been paid by Owner or by another responsible party so designated.
3. Roofing Installer is responsible for damage to work covered by this Warranty but is not
liable for consequential damages to building or building contents resulting from leaks or
faults or defects of work.
4. During Warranty Period, if Owner allows alteration of work by anyone other than
Roofing Installer, including cutting, patching, and maintenance in connection with
penetrations, attachment of other work, and positioning of anything on roof, this
Warranty shall become null and void on date of said alterations, but only to the extent
said alterations affect work covered by this Warranty. If Owner engages Roofing
Installer to perform said alterations, Warranty shall not become null and void unless
Roofing Installer, before starting said work, shall have notified Owner in writing,
showing reasonable cause for claim, that said alterations would likely damage or
deteriorate work, thereby reasonably justifying a limitation or termination of this
Warranty.
5. During Warranty Period, if original use of roof is changed and it becomes used for, but
was not originally specified for, a promenade, work deck, spray-cooled surface, flooded
basin, or other use or service more severe than originally specified, this Warranty shall
become null and void on date of said change, but only to the extent said change affects
work covered by this Warranty.
6. Owner shall promptly notify Roofing Installer of observed, known, or suspected leaks,
defects, or deterioration and shall afford reasonable opportunity for Roofing Installer to
inspect work and to examine evidence of such leaks, defects, or deterioration.
7. This Warranty is recognized to be the only warranty of Roofing Installer on said work
and shall not operate to restrict or cut off Owner from other remedies and resources
lawfully available to Owner in cases of roofing failure. Specifically, this Warranty shall
not operate to relieve Roofing Installer of responsibility for performance of original work
according to requirements of the Contract Documents, regardless of whether Contract
was a contract directly with Owner or a subcontract with Owner's General Contractor.
E. IN WITNESS THEREOF, this instrument has been duly executed this <Insert day> day of
<Insert month>, <Insert year>.
1. Authorized Signature: <Insert signature>.
2. Name: <Insert name>.
3. Title: <Insert title>.
END OF SECTION 07 5400
SECTION 076200 - SHEET METAL FLASHING AND TRIM
PART 5 - GENERAL
5.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
5.2 SUMMARY
A. Section Includes:
1. Formed Products:
a. Formed low-slope roof sheet metal fabrications.
B. Related Sections:
1. Section 07 5400 "Thermoplastic Roofing".
5.3 PERFORMANCE REQUIREMENTS
A. General: Sheet metal flashing and trim assemblies as indicated shall withstand wind loads,
structural movement, thermally induced movement, and exposure to weather without failure due
to defective manufacture, fabrication, installation, or other defects in construction. Completed
sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.
B. Fabricate and install roof edge flashing and copings capable of resisting forces according to
recommendations in SMACNA’s 2012 Edition Manual.
C. Thermal Movements: Provide sheet metal flashing and trim that allows for thermal movements
from ambient and surface temperature changes.
1. Temperature Change: 180 degree F. material surfaces.
5.4 ACTION SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details, material
descriptions, dimensions of individual components and profiles, and finishes for each
manufactured product and accessory.
B. Shop Drawings: Show fabrication and installation layouts of sheet metal flashing and trim,
including plans, elevations, expansion-joint locations, and keyed details. Distinguish the
difference between shop and field-assembled Work. Include the following:
1. Identification of material, thickness, weight, and finish for each item and location in
Project.
2. Details for forming sheet metal flashing and trim, including profiles, shapes, seams, and
dimensions.
3. Details for joining, supporting, and securing sheet metal flashing and trim, including
layout of fasteners, cleats, clips, and other attachments. Include pattern of seams.
4. Details of termination points and assemblies, including fixed points.
5. Details of expansion joints and expansion-joint covers, including showing direction of
expansion and contraction.
6. Details of edge conditions, including eaves, ridges, valleys, rakes, crickets, and counter
flashings as applicable.
7. Details of special conditions.
8. Details of connections to adjoining work.
5.5 QUALITY ASSURANCE
A. Fabricator Qualifications: Shop that employs skilled workers who custom fabricate sheet metal
flashing and trim similar to that required for this Project and whose products have a record of
successful in-service performance.
B. Sheet Metal Flashing and Trim Standard: Comply with SMACNA's "Architectural Sheet Metal
Manual" unless more stringent requirements are specified or shown on Drawings.
C. Pre-installation Conference: Conduct conference at project site.
1. Meet with Owner, Architect, Owner's insurer if applicable, Installer, and installers whose
work interfaces with or affects sheet metal flashing and trim including installers of
roofing materials, roof accessories, unit skylights, and roof-mounted equipment.
2. Review methods and procedures related to sheet metal flashing and trim.
3. Examine substrate conditions for compliance with requirements, including flatness and
attachment to structural members.
4. Review special roof details, roof drainage, roof penetrations, equipment curbs, and
condition of other construction that will affect sheet metal flashing.
5. Document proceedings, including corrective measures and actions required, and furnish
copy of record to each participant.
5.6 DELIVERY, STORAGE, AND HANDLING
A. Do not store sheet metal flashing and trim materials in contact with other materials that might
cause staining, denting, or other surface damage. Store sheet metal flashing and trim materials
away from uncured concrete and masonry.
B. Protect strippable protective covering on sheet metal flashing and trim from exposure to
sunlight and high humidity, except to the extent necessary for the period of sheet metal flashing
and trim installation.
5.7 WARRANTY
A. Special Warranty on Finishes: Manufacturer's standard form in which manufacturer agrees to
repair finish or replace sheet metal flashing and trim that shows evidence of deterioration of
factory-applied finishes within specified warranty period.
1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following:
a. Color fading more than 5 Hunter units when tested according to ASTM D 2244.
b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214.
c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.
2. Finish Warranty Period: 20 years from date of Substantial Completion.
PART 6 - PRODUCTS
6.1 SHEET METALS
A. General: Protect mechanical and other finishes on exposed surfaces from damage by applying a
strippable, temporary protective film before shipping.
B. Metallic-Coated Steel Sheet: Restricted flatness steel sheet, metallic coated by the hot-dip
process and pre-painted by the coil-coating process to comply with ASTM A755/A 755M.
1. Aluminum-Zinc Alloy-Coated Steel Sheet: ASTM A792-08 Grade 40 structural quality.
2. Exposed Coil-Coated Finish:
a. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less
than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply
coating to exposed metal surfaces to comply with coating and resin manufacturers'
written instructions.
3. Color: Zinc Gray.
4. Exposed Coil Coated Finish (coping): Aluminum Zinc Alloy Coated.
5. Concealed Finish: Pretreat with manufacturer's standard white or light-colored acrylic or
polyester backer finish, consisting of prime coat and wash coat with a minimum total dry
film thickness of 0.5 mil.
6. Basis of Design: Berridge Manufacturing.
6.2 UNDERLAYMENT MATERIALS
A. 60 mil thick bare backed PVC membrane.
6.3 MISCELLANEOUS MATERIALS
A. General: Provide materials and types of fasteners, solder, welding rods, protective coatings,
separators, sealants, and other miscellaneous items as required for complete sheet metal flashing
and trim installation and recommended by manufacturer of primary sheet metal unless
otherwise indicated.
B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and
bolts, and other suitable fasteners designed to withstand design loads and recommended by
manufacturer of primary sheet metal.
1. General: Blind fasteners or self-drilling screws, gasketed, with hex-washer head.
a. Exposed Fasteners: Heads matching color of sheet metal using plastic caps or
factory applied coating.
b. Blind Fasteners: High-strength stainless-steel rivets suitable for metal being
fastened.
2. Fasteners for Aluminum-Zinc Alloy-Coated Steel: Series 300 stainless steel.
C. Sealant Tape: Pressure-sensitive, 100 percent solids, gray polyisobutylene compound sealant
tape with release-paper backing. Provide permanently elastic, non-sag, nontoxic, non-staining
tape 1/2 inch wide and 1/8 inch thick.
D. Elastomeric Sealant: ASTM C 920, elastomeric polyurethane or polyether polymer sealant; low
modulus; of type, grade, class, and use classifications required to seal joints in sheet metal
flashing and trim and remain watertight.
6.4 FABRICATION, GENERAL
A. General: Custom fabricate sheet metal flashing and trim to comply with recommendations in
SMACNA's "Architectural Sheet Metal Manual" that apply to design, dimensions, geometry,
metal thickness, and other characteristics of item indicated. Fabricate items at the shop to
greatest extent possible.
1. Fabricate sheet metal flashing and trim in thickness or weight needed to comply with
performance requirements, but not less than that specified for each application and metal.
2. Obtain field measurements for accurate fit before shop fabrication.
3. Form sheet metal flashing and trim without excessive oil canning, buckling, and tool
marks and true to line and levels indicated, with exposed edges folded back to form
hems.
4. Conceal fasteners and expansion provisions where possible. Exposed fasteners are not
allowed on faces exposed to view.
B. Sealed Joints: Form non-expansion but movable joints in metal to accommodate elastomeric
sealant.
C. Expansion Provisions: Where lapped expansion provisions cannot be used, form expansion
joints of intermeshing hooked flanges, not less than 1 inch deep, filled with butyl sealant
concealed within joints.
D. Fabricate cleats and attachment devices from same material as accessory being anchored or
from compatible, noncorrosive metal.
E. Seams: Fabricate nonmoving seams with flat-lock seams. Form seams and seal with
elastomeric sealant unless otherwise recommended by sealant manufacturer for intended use.
F. Do not use graphite pencils to mark metal surfaces.
6.5 LOW-SLOPE ROOF SHEET METAL FABRICATIONS
A. Coping (SMACNA): Fabricate in minimum 96-inch long, but not exceeding 10-foot long,
sections. Fabricate joint plates of same thickness as copings. Furnish with continuous cleats to
support edge of external leg and fasteners on interior leg. Miter corners and seal watertight.
1. Coping Profile: SMACNA figure designation 3.1.
2. Joint Style: Drive Cleat Method.
3. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
4. Continuous Cleat Profile: SMACNA figure designation 3.1.
5. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 22 gauge thick.
B. Roof to Wall Transition Expansion-Joint Cover:
1. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
C. Building Expansion Joint:
1. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
2. Continuous Cleat Profile: SMACNA figure designation 5-5A.
3. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 22 gauge thick.
D. Base Flashing:
1. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
E. Counterflashing:
1. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
F. Roof-Penetration Flashing:
1. Fabricate from the following materials:
a. Aluminum-Zinc Alloy-Coated Steel: 24 gauge thick.
PART 7 - EXECUTION
7.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, to verify actual locations,
dimensions and other conditions affecting performance of the Work.
1. Verify compliance with requirements for installation tolerances of substrates.
2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely
anchored.
B. For the record, prepare written report, endorsed by Installer, listing conditions detrimental to
performance of the Work.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
7.2 UNDERLAYMENT INSTALLATION
A. General: Install underlayment as indicated on Drawings.
B. Coping 60 PVC Underlayment: Install PVC underlayment with adhesive over wood for
anchorage under sheet metal coping. Apply in shingle fashion to shed water with heat welded
joints of not less than 2 inches.
7.3 INSTALLATION, GENERAL
A. General: Anchor sheet metal flashing and trim and other components of the Work securely in
place, with provisions for thermal and structural movement. Use fasteners, solder, welding
rods, protective coatings, separators, sealants, and other miscellaneous items as required to
complete sheet metal flashing and trim system.
1. Install sheet metal flashing and trim true to line and levels indicated. Provide uniform,
neat seams with minimum exposure of solder, welds, and sealant.
2. Install sheet metal flashing and trim to fit substrates and to result in watertight
performance. Verify shapes and dimensions of surfaces to be covered before fabricating
sheet metal.
3. Continuous cleats anchored with fasteners spaced not more than 12-inches on center.
4. Install exposed sheet metal flashing and trim without excessive oil canning, buckling, and
tool marks.
5. Install sealant tape where indicated.
6. Torch cutting of sheet metal flashing and trim is not permitted.
7. Do not use graphite pencils to mark metal surfaces.
B. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space
movement joints at a maximum of 10 feet with no joints allowed within 24 inches of corner or
intersection. Where lapped expansion provisions cannot be used or would not be sufficiently
watertight, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep,
filled with sealant concealed within joints.
C. Fastener Sizes: Use fasteners of sizes that will penetrate wood sheathing not less than 1-1/4
inches for nails and not less than 3/4 inch for wood screws and metal decking not less than
recommended by fastener manufacturer to achieve maximum pull-out resistance.
D. Seal joints as shown and as required for watertight construction.
1. Where sealant-filled joints are used, embed hooked flanges of joint members not less than
1 inch into sealant. Form joints to completely conceal sealant. When ambient
temperature at time of installation is moderate, between 40 and 70 degree F, set joint
members for 50 percent movement each way. Adjust setting proportionately for
installation at higher ambient temperatures. Do not install sealant-type joints at
temperatures below 40 degree F.
2. Prepare joints and apply sealants to comply with requirements in Section 07920 "Joint
Sealants."
7.4 ROOF FLASHING INSTALLATION
A. General: Install sheet metal flashing and trim to comply with performance requirements of
SMACNA's "Architectural Sheet Metal Manual". Provide concealed fasteners where possible,
set units true to line, and level as indicated. Install work with laps, joints, and seams that will be
permanently watertight and weather resistant.
B. SMACNA Coping: Anchor to resist uplift and outward forces according to recommendations in
SMACNA's "Architectural Sheet Metal Manual" and as indicated.
1. Interlock exterior bottom edge of coping with continuous cleat anchored to substrate at
24-inch centers.
2. Anchor interior leg of coping with washers and screw fasteners through slotted holes at
24-inch centers.
C. Counterflashing: Coordinate installation of counterflashing with installation of base flashing.
Insert counterflashing in reglets or receivers and fit tightly to base flashing. Extend
counterflashing 4 inches over base flashing. Lap counterflashing joints a minimum of 4 inches
and bed with sealant.
7.5 ERECTION TOLERANCES
A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerance
of 1/4 inch in 20 feet on slope and location lines as indicated and within 1/8-inch offset of
adjoining faces and of alignment of matching profiles.
7.6 CLEANING AND PROTECTION
A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and
weathering.
B. Clean and neutralize flux materials. Clean off excess solder.
C. Clean off excess sealants.
D. Remove temporary protective coverings and strippable films as sheet metal flashing and trim
are installed unless otherwise indicated in manufacturers written installation instructions. On
completion of installation, remove unused materials and clean finished surfaces. Maintain in a
clean condition during construction.
E. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond
successful repair by finish touchup or similar minor repair procedures.
END OF SECTION 076200