KBP Catch-Up Plan

18
KBP Catch-Up Plan For CSAFP September 8, 2009

description

KBP Catch-Up Plan. For CSAFP September 8, 2009. TOTAL PROJECTS. REMAINING PROJECTS. TOTAL-REMAINING PROJECTS. TOTAL Projects. REMAINING Projects. ANALYSIS. * 18 on-going (1 not yet started at Gumaca, Quezon). ASSESSMENT. * 18 on-going (1 not-yet started at Gumaca, Quezon). - PowerPoint PPT Presentation

Transcript of KBP Catch-Up Plan

Page 1: KBP Catch-Up Plan

KBP Catch-Up PlanFor CSAFP

September 8, 2009

Page 2: KBP Catch-Up Plan

UNIT KBP 2005-07 KBP 2008 (1,2,3) KBP 2009 TOTAL

LUZON

51EBde, PA 290 52 146 488

54EBde, PA 32 88 176 296

NCBde, PN 49 24 39 112

355AEW, PAF 31 11 31 73

MINDANAO

52EBde, PA 45 165 46 256

55EBde, PA 6 20 78 104

VISAYAS

53EBde, PA 48 337 123 508

TOTAL 501 697 639 1,837

TOTAL PROJECTS

Page 3: KBP Catch-Up Plan

UNIT KBP 2005-07 KBP 2008 (1,2,3) KBP 2009 TOTAL

LUZON

51EBde, PA 19 52 146 217

54EBde, PA 0 74 176 250

NCBde, PN 0 21 39 60

355AEW, PAF 0 14 31 45

MINDANAO

52EBde, PA 0 72 46 118

55EBde, PA 0 14 78 92

VISAYAS

53EBde, PA 0 272 123 395

TOTAL 19 519 639 1,177

REMAINING PROJECTS

Page 4: KBP Catch-Up Plan

TOTAL-REMAINING PROJECTS

TOTAL ProjectsREMAINING Projects

Page 5: KBP Catch-Up Plan

ANALYSISUNIT KBP 2005-07 KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 19* 52 146 217 55

54EBde, PA 0 74 176 250 81

NCBde, PN 0 21 39 60 13

355AEW, PAF 0 14 31 45 14

MINDANAO

52EBde, PA 0 72 46 118 53

55EBde, PA 0 14 78 92 33

VISAYAS

53EBde, PA 0 272 123 395 102

TOTAL 19 519 639 1,177 351

*18 on-going (1 not yet started at Gumaca, Quezon)

Page 6: KBP Catch-Up Plan

ASSESSMENT

UNIT KBP 2005-07

KBP 2008

KBP 2009 TOTAL F-M-R REMARKS

LUZON

51EBde, PA 19 52 146 217 55 No major concern

54EBde, PA 0 74 176 250 81 Minor concern

NCBde, PN 0 21 39 60 13 No major concern

355AEW, PAF 0 14 31 45 14 No major concern

*18 on-going (1 not-yet started at Gumaca, Quezon)

For Luzon, the only concern of NADESCOM is at 54EBde considering the number of FMR projects located in Kalinga, Apayao, Cagayan areas and

the prevailing weather condition.

Page 7: KBP Catch-Up Plan

ASSESSMENT

UNIT KBP 2008

KBP 2009 TOTAL F-M-R REMARKS

MINDANAO

52EBde, PA 72 46 118 53 No major concern

55EBde, PA 14 78 92 33 No major concern

For Mindanao, NADESCOM has no major concern. However, if security situation will change, it will definitely affect our targets.

Page 8: KBP Catch-Up Plan

ASSESSMENT

UNIT KBP 2008

KBP 2009 TOTAL F-M-R REMARKS

VISAYAS

53EBde, PA 272 123 395 102 Major concern

For the Visayas, NADESCOM’s concern is the number of projects allocated in the area given the

time frame, geographical locations, and other factors such as weather and security situations.

Page 9: KBP Catch-Up Plan

KBP ADMIN UPDATE

• We will start implementing projects for KBP 2009 by September 2009 based on the following:–Approval of SPP– Evaluation and Approval of POW–Approval of Implementing Guidelines for

DO 132

Page 10: KBP Catch-Up Plan

Our action plans…

• FACILITATE additional support to 53EBde and 54EBde in that priority

• CONTINUE our monthly meeting, conference

• FOLLOW-UP the approval of all documentary requirements NLT 15 September 2009

Page 11: KBP Catch-Up Plan

REMAINING PROJECTS(END of AUGUST 2009)

UNIT KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 71* 146 217 55

54EBde, PA 74 176 250 81

NCBde, PN 21 39 60 13

355AEW, PAF 14 31 45 14

MINDANAO

52EBde, PA 72 46 118 53

55EBde, PA 14 78 92 33

VISAYAS

53EBde, PA 272 123 395 102

TOTAL 538 639 1,177 351

Page 12: KBP Catch-Up Plan

TARGET ACCOMPLISMENT(By END of SEPTEMBER 2009)

UNIT KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 50 140 190 53

54EBde, PA 60 170 230 80

NCBde, PN 21 39 60 13

355AEW, PAF 14 31 45 14

MINDANAO

52EBde, PA 60 40 100 51

55EBde, PA 10 75 85 31

VISAYAS

53EBde, PA 250 115 355 100

TOTAL 465 610 1,065 342

Page 13: KBP Catch-Up Plan

TARGET ACCOMPLISHMENT(By END of OCTOBER 2009)

UNIT KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 30 100 130 45

54EBde, PA 40 120 160 70

NCBde, PN 15 30 45 10

355AEW, PAF 10 25 35 12

MINDANAO

52EBde, PA 30 30 60 40

55EBde, PA 5 50 55 25

VISAYAS

53EBde, PA 200 90 290 90

TOTAL 330 445 775 292

Page 14: KBP Catch-Up Plan

TARGET ACCOMPLISHMENT (By END of NOVEMBER 2009)

UNIT KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 20 50 70 25

54EBde, PA 25 70 95 40

NCBde, PN 10 20 30 6

355AEW, PAF 7 15 22 7

MINDANAO

52EBde, PA 5 20 25 25

55EBde, PA 5 35 40 15

VISAYAS

53EBde, PA 120 50 170 60

TOTAL 192 260 452 178

Page 15: KBP Catch-Up Plan

TARGET ACCOMPLISHMENT (By END of DECEMBER 2009)

UNIT KBP 2008 KBP 2009 TOTAL F-M-R

LUZON

51EBde, PA 0 0 0 0

54EBde, PA 2 8 10 10

NCBde, PN 0 0 0 0

355AEW, PAF 0 0 0 0

MINDANAO

52EBde, PA 0 0 0 0

55EBde, PA 0 0 0 0

VISAYAS

53EBde, PA 10 20 30 30

TOTAL 12 28 40 40

Page 16: KBP Catch-Up Plan

TARGET ACCOMPLISHMENT

As of Aug 2009 by Sept 2009 by Oct 2009 by Nov 2009 by Dec 2009

Page 17: KBP Catch-Up Plan

OVERALL ASSESSMENT

• All vertical projects will be completed.• The remaining horizontal projects (F-M-R) are

all on-going by the end of 2009.

Page 18: KBP Catch-Up Plan

WHAT WE NEED…

• Since Centcom committed to provide additional pers to 53EBde, we still need two (2) Engineering Construction coys by the start of 4Qtr 2009:– 1 ECCs to 53EBde and 1 ECC to 54EBde