Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

16
Community based Rural Electrification in Nepal Status, Prospect and Challenges Presented by Madhusudhan Adhikari, National Advisor AEPC/NRREP

Transcript of Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

Page 1: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

Community based Rural Electrification in Nepal

Status, Prospect and Challenges

Presented byMadhusudhan Adhikari,

National Advisor AEPC/NRREP

Page 2: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

2

ELECTICTY USE IN NEPAL

74%

26%

Total

94%

6%

Urban

70%30%

Rural47%

41%

12% Grid

Off-Grid

National Census 2011

Population with electricity Population without electricity

World Development Indicator

Page 3: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

3

ENERGY FOR COOKING

64%21%

10%

2% 1%

Total

Fuelwood LPGAnimal dung BiogasKerosene

National Census 2011

26%

68%

2%2%2%

Urban

73%

10%12%

3%1%

Rural

Page 4: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

4

POWER GRID MAP OF NEPAL

Page 6: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

OFF GRID RE TREND IN NEPAL

Solar PVMicrohydro

Page 7: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

0

500

1000

1500

2000

2500

3000

Source: RE Data Book 2012, ESAP, RERL

AEPC ESTABLISHED IN 1996

Total ~36000 kW~28000 kW (AEPC)

7

MICRO HYDRO DEVELOPMENT TREND IN NEPAL

2013

2014

2016

2015

2017

AEPC/NRREP Target~25000 kW

NRREP Year

Page 8: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

MICRO/MINI HYDRO DISTRIDUTION

Page 9: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

TARGET OF AEPC/NRREP (2012-2017)

Page 10: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

IMPLEMENTATION MODEL

Public Private

PartnershipDemand side

Public sector

Supply side

Private sector

Awareness & capacity building

Technical & financial assistance

Planning, coordination & networking

Quality assurance, monitoring & evaluation

Manufacturing & supply

Sales & installation

After sales services, repair & maintenance

Int. Quality control & monitoring

Subsidy

Users/ Beneficiary

Qualification/ Grading/

Evaluation

Standards/ Guidelines

Page 11: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

CHALLENGES OF COMMUNITY BASED RE

Definition of Electrification◦Replacing wick lamp, wood, kerosene lamp???◦Electricity for evening lighting x Wp PV ???◦Availability of electricity for or amount ???

Sustainability and economic benefits of investment◦Role of government◦Awareness of capacity of local

Improvement in Livelihood◦Comparing themselves◦Compare to city or Capital◦Compare to global

Page 12: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

CHALLENGES OF COMMUNITY BASED RE

is

NOT TO PROVIDE ACCESS TO

MODERN LIGHTS its

SUSTAINABILITY OF TECHNICAL SOLUTIN AND INCREASED

LIVING STANDARD OF LOCAL PEOPLE.

Page 13: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

CHALLENGES OF COMMUNITY BASED RE

Up scaling and upgrading – scaling implementation & upgrading quality

Financial viability in business model

Remoteness and difficult geography high transportation cost.

Sustainability – O & M of plant in local level

Integrated planning and inter-connection of off and on grid systems

Page 14: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

BARRIERS IN UPSCALING

High initial upfront costs of technology for end-users

Sub-optimal financing mechanisms – grant/subsidy-long approval process

Lack of access to credit - high transaction costs

Productive consumption of energy produced – end use promotion

Funds to be arranged by community is very high.

Procurement by community - Bidding process, low bargaining power, end with poor quality high cost

Page 15: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

WAY FORWARD To shorten the project development period –subsidy

approval and financial closure.

Promotion of credit facilities in rural area. Expansion of reach of financial institution. Cutting/sharing the overhead cost Subsidized interest rates on credit

Mobilization of urban developers in rural areas – need of FIT

Equitable investment by government by cross subsidy-Urban Vs Rural

Strong policy to promote rural energy based enterprises.

More comprehensive capacity building for local on O & M skills

Page 16: Kathmandu | Apr-15 | Community based Rural Electrification in Nepal Status, Prospect and Challenges

THANKS FOR LISTENING

Madhusudhan Adhikari, National Advisor , Community Electrification