Karin Corfee | Feed-in Tariff Case Studies

30
Experience you can trust. Feed-in Tariff Case Studies Institute for Analysis of Solar Energy Kickoff Symposium “Solar Energy: A Solution to Energy and Environmental Problems?” Karin Corfee April 24 th , 2009

Transcript of Karin Corfee | Feed-in Tariff Case Studies

Page 1: Karin Corfee | Feed-in Tariff Case Studies

Experience you can trust.

Feed-in Tariff Case Studies

Institute for Analysis of Solar EnergyKickoff Symposium“Solar Energy: A Solution to Energy and Environmental Problems?”

Karin CorfeeApril 24th, 2009

Page 2: Karin Corfee | Feed-in Tariff Case Studies

Agenda

• KEMA Overview• Case Studies recent projects on Feed-in Tariffs

– California– Hawaii

Page 3: Karin Corfee | Feed-in Tariff Case Studies

• Consulting Services

• Technical and Operational Services

• Testing and Certification

• Customers in 70 countries

• 1,700 employees, 50 offices in 20 countries

• Incorporated in 1927

KEMA Services Cover the Entire Energy Value Chain

www.kema.com

Page 4: Karin Corfee | Feed-in Tariff Case Studies

What’s Happening in California?

Page 5: Karin Corfee | Feed-in Tariff Case Studies

California – Two State Agencies Evaluating Feed-in Tariffs

• California Energy Commission (CEC) – Feed-in Tariff Docket (CEC Docket # 03-RPS-1078)

• California Public Utilities Commission – CPUC Feed-in Tariff OIR (08-08-009)

Page 6: Karin Corfee | Feed-in Tariff Case Studies

California Energy Commission (CEC)Activities on Feed-In Tariffs• CEC Docket # 03-RPS-1078

– 2 recent reports on the topic of Feed-In Tariffs • Exploring Feed-in Tariffs for California: Feed-in Tariff

Design Issues and Options– Publication No. CEC-2008-003

• California Feed-in Tariff Design and Policy Options– Publication No. CEC-2008-009D

– KEMA supported development of both of these reports with support from Sustainable Energy Advantage, Wilson Rickerson and Exeter Associates

– Both reports can be found on CEC website• http://www.energy.ca.gov/portfolio/documents

Page 7: Karin Corfee | Feed-in Tariff Case Studies

CA Feed-in Tariff Goals, Objectives & Policy Drivers

Goals: e.g. -reduce GHG-Reduce fossil fuel use- manage ratepayer cost & risk-Etc.

Objectives: e.g. -20% RE by 2010-33% RE by 2020

CEC staff and Renewable Energy Committee identified ‘Policy Drivers’for feed-in tariffs: • High priority:

Quantity of renewable energyFinancial security

• Medium priorityDiversity ‘A’ = Diverse mix of

technology & operational characteristics

Sustainable renewable energy

Price stabilizationLower priority

Diversity ‘B’ = other policy objectives (e.g. biomass)

Subject to constraints…• Available transmission• Siting/permitting• Feasible build-out time• Cost-effectiveness• Environmental/resource sustainability

7

Page 8: Karin Corfee | Feed-in Tariff Case Studies

Key Benefits and Features of FITsIdentified• Guaranteed price• Guaranteed buyer• Long-term guaranteed revenue stream• Generally, unbounded market regardless of

completion date• Minimizes transaction costs• Minimizes complexity of responding to solicitations• Few buyers with irregular shopping schedules

(timing of market)• Reduces buyer credit or financing concerns• Generally, guaranteed interconnection

Page 9: Karin Corfee | Feed-in Tariff Case Studies

9

Feed-in Tariff Issues and Options

Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and Options (referred to herein as the Issues & Options Report, KEMA

Page 10: Karin Corfee | Feed-in Tariff Case Studies

10

Feed-in Tariff Design Issues and Options (2)

Source: Exploring Feed-in Tariffs for California: Feed-in Tariff Design and Implementation Issues and Options (referred to herein as the Issues & Options Report, KEMA

Page 11: Karin Corfee | Feed-in Tariff Case Studies

FIT Design and Policy Options for CA

11

#1 #2 #3

Full-Market, unlimited size, differentiated cost-based w/

competitive benchmark, conditional triggered

> 20 MW, undifferentiated value-based 3-yr pilot in 1

utility

Differentiated Cost-based CREZ-Only,

> 1.5 MW

Resource TypeAll All All

Vintage New, separate price for repowering

New + repowering New

SizeNo limit > 20 >1.5

Timing If RPS<20% contracted by 2010, start in 2012-13

Now (available for 3-year duration)

automatically in 2010-11 (so projects developed with transmission)

ScopeFull Market Pilot (limited time, 1 utility) CREZ-Only

Setting the Price Cost-based with initial differentiated auction without MPR to set competitive benchmark for subsequent tariff

Value Based (time & peak differentiated with CO2 & other adders)

Cost-based

Contract

Duration

Long-term Long-term Long-term

Tariff

Differentiation

Differentiation by technology & size

Not Applicable Wind by size, geothermal, biomass by size, solar by technology

Limits Capped at RPS targets; caps on more expensive technologies

Uncapped Capped at CREZ Transmission limit

Page 12: Karin Corfee | Feed-in Tariff Case Studies

FIT Design and Policy Options for CA

12

#4 #5 #6

Solar > net metering pilot in 1 utility, cost-based

with competitive benchmark

Sustainable biomass > 1.5 MW only, cost-based

Full market < 20 MW cost-based differentiated by

technology & size

Resource Type Solar Biomass (sustainable) All

Vintage New New New, separate price for repowering

Size > Net metering threshold >1.5 <20

Timing Now Now Now

Scope Pilot within one utility Full Market Full Market

Setting the Price Cost-Based w/ Competitive benchmark

Cost-based, calculated to consider sustainable yield of local biomass sources

Cost-based

Contract Duration Long-term Short- or Medium Term Long-term

Tariff Differentiation By size, type By fuel and size Differentiation by technology & size

Limits Capacity limit will be established for the sponsoring utility.

Uncapped Uncapped

Page 13: Karin Corfee | Feed-in Tariff Case Studies

CA IOU Contracted Capacity for Renewable Generation

IOU Contracted Capacity - Contracts IOU Contracted Capacity - MW

Source: Energy Commission’s Database of Investor-Owned Utilities’ Contracts for Renewable Generation, Contracts Signed Towards Meeting the California RPS Targets webpage, updated January 18, 2009, http://www.energy.ca.gov/portfolio/contracts_database.html.

Page 14: Karin Corfee | Feed-in Tariff Case Studies

Recommendation of CEC Staff

14

• Establish feed-in tariff initially for projects up to 20 MW– Cost-based, must take tariff offering long-term contracts– Open to all RPS-eligible resource types– For new projects (separate tariff could be explored for repowering)– No waiting– Technology- and size-differentiated

• Consider recommended feed-in tariff as a potential bridge to broader scale implementation of feed-in tariffs for – Projects > 20 MW, Projects in CREZs

• As greater experience is gained with smaller project feed-in tariffs

• As transmission and other barriers are addressed• If conditions merit expansion

Page 15: Karin Corfee | Feed-in Tariff Case Studies

CPUC Feed-in Tariff Activities• CPUC approved Feed-in Tariffs in February 2008 (Phase I)

– Originally authorized by AB 1969 (Yee, 2006) for generators < 1.5 MW owned by

public water and wastewater facilities

• Facilitates a streamlined interconnection process

– Expanded to include “all customers” of the 3 IOUs

– Statewide cumulative capacity up to 498 MW

– Two contract choices depending upon customer choice

• Full scale production

• Excess sales (after on-site usage)

• CPUC R.08-08-009 is currently considering Phase II

– Expansion of installation size cap between 1.5 and 20 MW

– Expansion of FIT to 3rd party ownership of RPS eligible facilities

– Counting excess sales toward program limits

– Does not include modification of tariff structureSource: CPUC

Page 16: Karin Corfee | Feed-in Tariff Case Studies

CA Small Renewable Energy Generation Tariffs - Price

• Rate is currently determined by Market Price Referent (MPR) with Time of Delivery (TOD) adjustments– Reference point of MPR is

set by law as a new Combined Cycle gas plant

– In AB 1969, the MPR (and annual #) is adjusted for season and time of delivery

15 year Annual Average

($/MWh)

IOU MPR Solar

Estimate*

PG&E $0.09 $0.11

SCE $0.09 $0.13

SDG&E $0.09 $0.11

* Solar produces largely on peak so receives a slightly higher average rate

Source: CPUC

Page 17: Karin Corfee | Feed-in Tariff Case Studies

CPUC

• SCE

– Currently offers standard offer contracts for biomass projects up to 20 MW

• Price set at MPR

• 3 contracts offered (<1 MW, 1-5 MW, 5-20 MW)

– 5-20 MW contracts include performance and development security

requirements

– SCE proposes in its RPS procurement plan to expand standard offer

contracts to all renewable technologies

• Two contracts will be offered: 1.5 -5 MW and 5-20 MW

• PG&E

– Proposing a Feed-in Tariff Pilot Program for Feed-in Tariffs

• Streamlined the contracting process for RE generators of all sizes

• CPUC “pre-approved contract

• Price at or below MPR

Page 18: Karin Corfee | Feed-in Tariff Case Studies

CPUC Energy Division Staff ProposalNote the project size cut-off

Page 19: Karin Corfee | Feed-in Tariff Case Studies

Hawaii

Page 20: Karin Corfee | Feed-in Tariff Case Studies

Hawaiian Clean Energy Initiative Agreement (HCEI)

• Energy Agreement among the State of Hawaii, Division of Consumer Advocacy (CA) and the Hawaiian Electric Companies (HECO Companies)

• FIT Components to HCEI Agreement– PUC to determine the best design for FITs• March 2009

– PUC to adopt a set of FITs and prices • July 2009

– Utility PPA of RE made using the PUC approved FIT would be approved for rate recovery

– Utility purchases of RE under the FIT would be counted towards the RPS

Page 21: Karin Corfee | Feed-in Tariff Case Studies

Hawaiian Public Utilities Commission (PUC) Order • Docket No. 2008-0273

– Investigate the Implementation of Feed-in Tariffs• Order Initiating Investigation

– Filed on October 24, 2008– Required HECO Companies and the Consumer

Advocate to file a Joint Proposal on FIT Program Design

• HECO Feed-In Tariff Program Plan – Developed by KEMA to support the development of

the Joint Proposal • The HECO Companies and the Consumer

Advocate filed a Joint Proposal on FITs (HI FIT Proposal) on December 23, 2008

Page 22: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Proposal – Key Design Objectives

• A FIT is best suited for renewable energy projects that lend themselves to the use of standardized energy payment rates and power purchase contract terms and conditions, and which can be developed and interconnected to the utility grid in a relatively predictable and systematic manner

Page 23: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Proposal – Key Elements

• Renewable resources initially targeted in the proposed FIT are those that:

– Do not require complex environmental and land use permitting.

– Do not typically require extensive and lengthy interconnection studies or the need for significant interconnection requirements.

– Do not trigger complex financial accounting issues relative to utility power purchase contracts.

– Have already been, or are currently in the process of being implemented in Hawaii in commercial application.

Page 24: Karin Corfee | Feed-in Tariff Case Studies

FIT Program Eligibility

• Proposal is that a subset of renewable electricity technologies and project sizes will be targeted initially

Oahu MauiHawaii Island Lanai Molokai

PV Systems ≤ 500 kW ≤ 250 kW ≤ 250 kW ≤ 100 kW ≤ 100 kWCSP Systems ≤ 500 kW ≤ 500 kW ≤ 500 kW ≤ 100 kW ≤ 100 kWIn-Line Hydro Systems ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kWWind power systems ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW ≤ 100 kW

24

Page 25: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Proposal - Program Eligibility• The FIT Update (Phase II) will examine adding:

– Wave energy generating systems– Landfill gas generating systems– Sewage based digester gas generating systems– Biomass, including biomass crops, agricultural and

animal wastes, and municipal solid waste– Liquid biofuel-fired systems

25

Page 26: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Proposal - Setting the Tariff Rate

• Tariffs should be based on cost of generation plus a reasonable profit

• The tariff rate should be based on the costs of developing a “typical” project

• All costs and operating estimates will be Hawaii specific due to Hawaii’s unique geography that affects cost of generation to the best extent possible

• Tariff rates should differentiate between:– Technology type– Project size– Project location

26

Page 27: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Program Design Matrix

Island “X”

Technical Attributes Annual Quantity Target

Curtailable

Expanded Voltage/Frequency

Ride Through 2010

2011 FIT Rate, ¢/kWh

Yes Required 8 MW 8 MW 22 100 kW <PV≤

250 kW … Required 2 MW 2 MW 18

Yes Required 5 MW 5 MW 23 30 kW ≤ PV ≤ 100 kW … Required 2 MW 2 MW 19

… Yes 3 MW 3 MW 24

PV < 30 kW … … 1 MW 1 MW 20

27

• Hypothetical Values

Page 28: Karin Corfee | Feed-in Tariff Case Studies

HI FIT Proposal - Contract Duration• Contracts would be a standard length depending on the

technology– New PV Systems – 20 years– New CSP – 10 years– Additional information is being gathered for in-line

hydropower and small scale wind• Following the initial contract term, projects could be

allowed to extend, subject to a new FIT rate

28

Page 29: Karin Corfee | Feed-in Tariff Case Studies

29

Interconnection

• Interconnection of eligible renewable generation to follow Rule 14.H technical standards

• Generators responsible for interconnection costs, consistent with current practices

• Reasonable FIT generator interconnection costs will be considered in the development of the tariff rates, as differentiated by technology and size

Page 30: Karin Corfee | Feed-in Tariff Case Studies

Experience you can trust.

Thank you

Karin Corfee, KEMA Inc.

Senior Principal

Sustainable Market Strategies

Tel: 510-891-0446, x4112

[email protected]

Please visit our website www.kema.com