PRESENTATION
ON
GULF OF KHAMBHAT DEVELOPMENT PROJECT(WR)
Kalpasar as a prospective Water solution
- Saurashtra
A Truly Match less Project
-
7/28/2019 Kal Pasar Presentation e 22910
2/39
MISSION
-
7/28/2019 Kal Pasar Presentation e 22910
3/39
VISION
To create worlds largest fresh water reservoir
in sea, by constructing 30 km long dam in the
Gulf of Khambhat, to store more than 10,000
MCM of surface water, i.e. 25% of volume of
States average annual rain water inflow.
-
7/28/2019 Kal Pasar Presentation e 22910
4/39
-
7/28/2019 Kal Pasar Presentation e 22910
5/39
-
7/28/2019 Kal Pasar Presentation e 22910
6/39
-
7/28/2019 Kal Pasar Presentation e 22910
7/39
Per Capita Availability of Water
Bhuj
MEHSANA
PALANPUR
GANDHINAGAR
GODHRAKHEDA
VADODARA
BHARUCH
BHAVNAGAR
AMRELI
JUNAGADH
RAJKOT
JAMNAGAR
SURENDRANAGAR
RANN OF
KUTCH
LITTLE RANN
AHMEDABAD
SURAT
DANGVALSAD
Kutch
North
Gujarat
Saurashtra
Central &
South
Gujarat
730 m3/Annum343 m3/Annum
540 m3/Annum
1880 m3/Annum
Note : As per M. Falkenmark if renewable freshwater availability falls below 1000 M3 per
capita, water supply begins to hamper health, economy growth and human well being.
Per Capita Availability of Water (Year 2001)
-
7/28/2019 Kal Pasar Presentation e 22910
8/39
-
7/28/2019 Kal Pasar Presentation e 22910
9/39
-
7/28/2019 Kal Pasar Presentation e 22910
10/39
1. Gujarat is a water scarce state, with 6.39% of
geographical area, 5% of population & only 2%
of water resources.2. 71% of water resources available in 25% of
geographical area of central & south Gujarat.
3. In Saurashtra region per capita wateravailability is only 540 M3/annum against 1700
m3/annumminimum requirement.
4. In Saurashtra region,only 15 lakh haagricultural land will cover under irrigation
(including Sardar Sarovar Project), against 42
lakh ha agricultural land. Hence, 27 lakh ha
agricultural land will remain rainfed.
-
7/28/2019 Kal Pasar Presentation e 22910
11/39
5. The excessive pumping of groundwater resulted
in intrusion of saline water up to 10 km of entirecoastal belt of Saurashtra.
6. The water storage capacity of Gujarat state is
20480 Mm3 in 196 medium & major reservoirs,
against the total rainwater availability of 38000
MCM per annum.
7. Non availability of any suitable site for major
irrigation scheme in the state, the Gulf of
Khambhat Development Project is the only
option available to store 10,000 MCM rainwater.
-
7/28/2019 Kal Pasar Presentation e 22910
12/39
-
7/28/2019 Kal Pasar Presentation e 22910
13/39
GULF OF KHAMBHAT DEVELOPMENT PROJECT (W.R.)
-
7/28/2019 Kal Pasar Presentation e 22910
14/39
-
7/28/2019 Kal Pasar Presentation e 22910
15/39
1 Length of dam between two shores of Gulf Approx. 30 km
2 Top of dam 100m wide10 lane road + railway
3 Reservoir features:
(i) Full Reservoir Level(FRL)
(ii) Maximum Water Level(MWL)
(iii) Minimum Draw Down Level(MDDL)
(iv) Live storage
(v) Storage between MWL & FRL
(vi) Reservoir area
(+) 3.0m
(+) 4.0m
(-) 4.0m
10500 Mm3
1900 Mm3
2000 Sq.km
4 Bhadbhut Barrage & NarmadaDiversion Canal
(i) Barrage including earthen dykes
(ii) Narmada Diversion Canal
Discharge
Length
10 to 12 km
100000 cusecs
32 km
Salient features (Tentative)
-
7/28/2019 Kal Pasar Presentation e 22910
16/39
5 Irrigation Command
(i) Water envisaged for irrigation 6558 Mm3
(ii) Envisaged three garland canal
Discharge 4000 to 6000 cusecs
Length 600 to 700 km
Elevation EL50 m, EL80 m, EL100 m
6 Life of reservoir 400 to 500 years
7 Ground Water Quality
Improvement in Catchment
area
7,00000 Ha
8 Land recover between
EL + 5.0m to EL+ 8.0m
150000 to 200000 ha
-
7/28/2019 Kal Pasar Presentation e 22910
17/39
9 Reduction in distance
Bhavnagar Dahej 200 km
Bhavnagar South Gujarat 225 km
10 Ports Bhavnagar port will be
rejuvenate, Dahej port will be
outside of reservoir, New
ports are proposed at downstream of dam.
11 Rivers debouching in the
reservoir
Sabarmati, Mahi, Dhadhar,
Narmada (through diversion
canal), Limbadi Bhogavo,Sukhbhadar, Utavali, Keri,
and Vagad
12 Construction of dam 5 to 7 years
-
7/28/2019 Kal Pasar Presentation e 22910
18/39
Earlier the dam was envisaged between Ghogha
to Hansot having length of 64 km. wherein tidalpower component was combined alongwith
development of fresh water reservoir in the Gulf.
As per pre-feasibility report of the project, thecost of project was estimated of Rs. 53,000 crore
(base year 1998) in which the tidal power
component was Rs.33000 crore. Considering,
average 8% inflation per annum present costworks out to approximate Rs.1,40,000 crore, in
which the tidal power component is Rs.86,000
crore.
Estimated Cost of the Project
-
7/28/2019 Kal Pasar Presentation e 22910
19/39
Recently, tidal power component is delinked
from the project and the dam alignment is
shifted northward by 15 km, leads to reduction
of length of dam from 64 km to 30 km & height of
dam is also reduced from 55 m to 35 m.
Considering above the approximate project cost
at present is Rs. 50,000 to 60,000 crore.
-
7/28/2019 Kal Pasar Presentation e 22910
20/39
Benefits of the Project
-
7/28/2019 Kal Pasar Presentation e 22910
21/39
GULF OF KHAMBHAT DEVELOPMENT PROJECT (W.R.)
Irrigation Benefit
-
7/28/2019 Kal Pasar Presentation e 22910
22/39
10.54 lakh ha. land in 39 talukas of 6
districts of Saurashtra region will get
irrigation facilities including rejuvenation
of rivers and filling of more than 60existing dams as well as check dams,
tidal regulators, spreading channels
permanently.
Irrigation Benefit
-
7/28/2019 Kal Pasar Presentation e 22910
23/39
PerceivedAgricultural Benefits
-
7/28/2019 Kal Pasar Presentation e 22910
24/39
Transportation Benefits
-
7/28/2019 Kal Pasar Presentation e 22910
25/39
Substantial saving in travel time and fuel dueto reduction in distance by about 200 km
between Bhavnagar and Surat.
Surat is one of the fastest growing city in thecountry and the diamond oriented business
hub of the world.
Most of the diamond workers (more than 10lakhs) are migrated from Saurashtra (Mostly,
from Bhavanagr, Amreli district).
Transportation Benefit
-
7/28/2019 Kal Pasar Presentation e 22910
26/39
After the completion of dam and Bhadbhut
Barrage, the route from Bhavnagar to Surat
will be BhavnagarDahejHansotOlpadSurat.
New coastal highway will be developed to
connect present petro-chemical hub Hazira(Surat) to future petro-chemical hub PCPIR
(Dahej).
10 lane road is proposed on the top of thedam. 75000 vehicles per day is estimated for
year 2020, and 1,00,000 vehicles per day for
year 2030.
-
7/28/2019 Kal Pasar Presentation e 22910
27/39
The toll-tax generation is estimatedapproximately Rs. 1500 crore for year 2020
and Rs. 2000 crore for year 2030.
Considering 10% I.R.R., Capital investment of
Rs.15,000 crore to Rs. 20,000 crore may likely
available from transport component (30% to
40% cost of the project)
-
7/28/2019 Kal Pasar Presentation e 22910
28/39
Gulf of Khambhat is one of the Gulf in world
having maximum tide of 11 m and the averagetide of 8.8 m .
During the high tide and flood in Narmada, Mahi,
Sabarmati river etc., the sea water rise up to
level of +7.0 m to +8.0 m from MSL.
After closure of the Gulf of Khambhat, land
which is frequently submerged during high tide
will be permanently opened.
About 1.5 to 2 lakh ha land along the periphery
of reservoir will be opened which can be used
for the project development.
Land Reclamation Benefits
-
7/28/2019 Kal Pasar Presentation e 22910
29/39
-
7/28/2019 Kal Pasar Presentation e 22910
30/39
Land recovery (As per BISAG Study)
-
7/28/2019 Kal Pasar Presentation e 22910
31/39
Value Addition Of Land
Projects in vicinity of Kalpasar project
Dholera SIR
Fedara International Airport
PCPIR at Dahej
SEZ, GIDC etc.
Delhi- Mumbai Industrial Corridor
-
7/28/2019 Kal Pasar Presentation e 22910
32/39
Proposed 10 lane road for Ahmedabad-
Bhavnagar route
2000 sq. km worlds biggest fresh water
reservoir (in sea) with 6-lane periphery road of270 km long
Solar and Wind power, Tourism, Bio-fuel park,
Transportation, Fisheries etc. project
components / benefits
-
7/28/2019 Kal Pasar Presentation e 22910
33/39
In coastal region of Saurashtra and
Central Gujarat, saline ground water
will be converted into sweet water,
resulting reduction in inland salinity
Benefit -Reduction in Salinity
-
7/28/2019 Kal Pasar Presentation e 22910
34/39
Benefit- Port Development on
d/s of DamProject presents highly attractive locational
attributes for port development downstream of
the dam such as increased water level, lowercurrent velocity, reduced sedimentation
-
7/28/2019 Kal Pasar Presentation e 22910
35/39
NIO MODEL STUDY
i. Model study results show that after the
construction of the dam the tide level
increases at all the port locations.
i. The currents decrease at the locations near
to the dam (Bhavnagar, Ghoga).
i. Sediment transport results indicate that the
sediment concentration reduces in the
southern gulf (outside the dam) with amaximum reduction at Dahej and Gogha.
Bhavnagar port will be rejuvenated, therefore
this region will be speedily developed
-
7/28/2019 Kal Pasar Presentation e 22910
36/39
Wind and solar power would begenerated which will also be used for
lifting of fresh water of reservoir.
Benefits- Generation ofNon-conventional Energy
-
7/28/2019 Kal Pasar Presentation e 22910
37/39
Wind Energy
Wind energy is planned to be used forpumping of irrigation water. Approximately
250 crore unit will be required for lifting
irrigation water. As per Suzlon study, 1600MW with an estimated cost of about Rs. 9000
crore can be generated by installing wind
mills/ solar units. Wind mill will have addedbenefit of its installation after dam
construction.
-
7/28/2019 Kal Pasar Presentation e 22910
38/39
Benefits-fisheries Development
Fish production to the tune of 3,00,000
tonnes per annum amounting to Rs.22,500
Million at full development stage
Direct employment to approximately 1,00,000
beneficiaries and indirect employment to
approximately 3,00,000 beneficiaries.
-