Critical path:
• No particular issues, but:– Need to consider parallelising (\cite{BushSnr})
assembly to reduce time from completion of shaft to assembly of _TWO_ targets
Installation and commissioning schedule:• Presented / discussed at Target w/s last Friday• Revised version to be presented / discussed at
CM24• Need to have Target w/s with ISIS in June:
– Make sure manufacturing remains on track;– Discuss installation and commissioning plans;– Ensure manpower assumptions for shutdown are valid