JWPCP Steam System

35
JWPCP JWPCP Steam System Steam System Startup and Commissioning February 27, 2014

description

JWPCP Steam System. Startup and Commissioning. February 27, 2014. History. Total E nergy Facility ● Placed into operation in 1986 Combined cycle power plant Three gas turbines (7.2 MW each) One steam turbine (5.5 MW) Generates ~14 MW ● Capital cost of ~$45 million. HRSG’s. - PowerPoint PPT Presentation

Transcript of JWPCP Steam System

Page 1: JWPCP  Steam System

JWPCPJWPCP Steam System Steam System

Startup and Commissioning

February 27, 2014

Page 2: JWPCP  Steam System

HistoryHistory

Total Energy Facility● Placed into operation in 1986

Combined cycle power plant

Three gas turbines (7.2 MW each)

One steam turbine (5.5 MW)

Generates ~14 MW

● Capital cost of ~$45 million

Page 3: JWPCP  Steam System

HRSG’sHRSG’s

Page 4: JWPCP  Steam System

Steam TurbineSteam Turbine

Page 5: JWPCP  Steam System

History (cont.)History (cont.)

1994 Consent Decree

● Federal and state governments, NRDC and Heal the Bay

● Full secondary by December 31, 2002

Four new Reactor/clarifier trains

New cryogenic oxygen plant

Seven new digesters

● Higher electricity/steam demand

● Higher digester gas production

Page 6: JWPCP  Steam System

JWPCP (before)JWPCP (before)

Page 7: JWPCP  Steam System

JWPCP (after) JWPCP (after)

Page 8: JWPCP  Steam System

History (cont.)History (cont.)

TEF Modifications

● Conduct in two stages

1. Replace gas turbines

7.2 MW to 9.9 MW

Completed in 2001

2. Replace steam system

5.5 MW to 8.7 MW

New HRSG’s

Page 9: JWPCP  Steam System

ChronologyChronology

Equipment Procurement

● Steam Turbine

Purchased in 2005 for $2.4 million

Placed in storage in 2005

● HRSG’s

Purchased in 2005 for $3.3 million

Stored outside, beginning 2005

Page 10: JWPCP  Steam System

Chronology (cont.)Chronology (cont.)

2007 Advertisement● Advertise for Engineering, Procurement and

Construction (EPC) contractor

● No takers

Contractors unable to locate consultants to complete engineering design

● Advertisement terminated

● Negotiate with Engineer to complete design

● Anticipate construction completion in April 2011

Page 11: JWPCP  Steam System

Chronology (cont.)Chronology (cont.)

Steam Turbine Overspeed Event● April 3, 2008

● Board authorizes emergency repairs for $2.5 million

Page 12: JWPCP  Steam System

Steam TurbineSteam Turbine

Page 13: JWPCP  Steam System

Chronology (cont.)Chronology (cont.)

Expedite ProjectSplit into two phases in summer 2008

● Phase I: mechanical installation of steam turbine and HRSG’s

● Phase II: balance-of-plant installation and startup & commissioning

Advance procure additional equipment

Anticipated construction completion in May 2010

Page 14: JWPCP  Steam System

The PlayersThe Players

Sanitation Districts

Engineering Design

Field Engineering

JWPCP Engineer (designer) Phase I Contractor Phase II Contractor Systems Integrator Startup & Commissioning (S&C) Contractor Equipment Suppliers

Page 15: JWPCP  Steam System

ConstructionConstruction

Phase I● Begins August, 2009

● Ends ~April, 2010

● Demolish steam turbine and HRSG’s

● Install new steam turbine and HRSG’s

Mechanical installation only

Page 16: JWPCP  Steam System

HRSG’sHRSG’s

Page 17: JWPCP  Steam System

Steam TurbineSteam Turbine

Page 18: JWPCP  Steam System

Construction (cont.)Construction (cont.)

Phase II● Begins May, 2010

● Estimated completion March, 2011

● Balance-of-plant equipment

● Electrical and instrumentation

● Startup and commissioning

Page 19: JWPCP  Steam System

Construction (cont.)Construction (cont.)

Phase II Construction Delays● Equipment approvals

● Equipment fabrication

● Equipment erection

Cooling towers

High-pressure gas pretreatment

● In part, due to the multitude of players

Page 20: JWPCP  Steam System

Construction (cont.)Construction (cont.)

Steam Blows● Conducted in October 2011

● Precedes startup and commissioning

● Startup & commissioning contractor needed detailed start up documents

● Startup and commissioning halted for safety reasons

Page 21: JWPCP  Steam System

NegotiationsNegotiations

JWPCP

EngineerSystems IntegratorEngineering Design

S&C ContractorField Engineering

Phase II Contractor

Page 22: JWPCP  Steam System

Negotiations (cont.)Negotiations (cont.)

Topics● Functional descriptions

● Functional test plan

● Functional testing

● Control descriptions

● Logic diagrams

● O&M manuals

● Training manuals

● Training

Page 23: JWPCP  Steam System

Negotiations (cont.)Negotiations (cont.)

Summary● S&C Contractor

Didn’t want to provide materials, or wasn’t going to provide materials unless paid more

● Engineer and Systems Integrator

Wanted more money; however, we were not confident they had the expertise to do it

Page 24: JWPCP  Steam System

Negotiations (cont.)Negotiations (cont.)

May 2012

● Districts parties agree

1. Remove startup and commissioning from Phase II contract

2. End Phase II contract

3. End contract with Engineer and Systems Integrator

4. Turnover startup and commissioning to JWPCP

5. Engineering Design to assist JWPCP

Page 25: JWPCP  Steam System

ProposalProposal

June 2012● JWPCP solicits proposals from four contractors

● Two proposals received

● Select contractor

Offers expert in steam systems

● On June 27, 2012, Board of Directors authorizes Purchase Order for $415,000

Page 26: JWPCP  Steam System

Proposal (cont.)Proposal (cont.)

Proposal Deliverables● Functional test plan

● Functional testing

● Logic diagrams

● Control descriptions

● O&M manuals

Including startup, shutdown, operating, troubleshooting and emergency procedures

● Training manuals

● Training

Page 27: JWPCP  Steam System

Proposal (cont.)Proposal (cont.)

Proposal Deliverables (cont.)● Schedule

Seven-month schedule, completing in February, 2013

● Programmer

Logic review

Make changes to programming (200 hours)

● Expertise

Make recommendations for improvements

● Project team dedicated to project

Page 28: JWPCP  Steam System

Startup & CommissioningStartup & Commissioning

Divided into Three Stages1. Document review

2. Document development

3. Startup and commissioning

Page 29: JWPCP  Steam System

Startup & Commissioning Startup & Commissioning (cont.)(cont.)

Issues● Steam turbine

In storage since 2005

● Steam blows

Conducted more than one year ago

● Chemical cleaning

Conducted more than one year ago

Page 30: JWPCP  Steam System

Startup & Commissioning Startup & Commissioning (cont.)(cont.)

Completed in March, 2013

One month behind scheduleFifty-two recommendations

Most implementedApproximately $85,000 in extra work

Implementing recommendations

Page 31: JWPCP  Steam System

Power ProductionPower Production

Page 32: JWPCP  Steam System

Steam TurbineSteam Turbine

Page 33: JWPCP  Steam System

HRSG’sHRSG’s

Page 34: JWPCP  Steam System

Lessons LearnedLessons Learned

Limit involved partiesAvoid advance purchased equipmentTighten startup and commissioning

language in specificationsPurchase all equipment under same

contract

Page 35: JWPCP  Steam System

QuestionsQuestions