7/28/2019 Justification of Questions
1/10
Jaipur CMP
Percent Share of public transit- buses: 31% (2009)
Public Transit Improvement Strategy:
Alternative Scenarios considered:
1. Do Nothing2. Bus Fleet Augmentation
3. Augment Jaipur Commuter/ Regional rail system
4. Bus rapid transit system (BRTS)
5. High capacity rail based systems (Monorail/ LRT/ Metro)
-
7/28/2019 Justification of Questions
2/10
Jaipur CMP
Bus Augmentation
Existing fleet- 2200Minibuses 1900
Concerns:
1. Unregulated routes
2. Poor quality of buses
3. Safety problems
Steps to implement:
1. Rationalize, add routes
2. Modern buses (2450 new)
3. ITS application
Commuter Rail/ Regional Rail
Augmentation
4 rail corridors at present: Jaipur- Phulera
Jaipur- Chomu
Jaipur- Dausa
Jaipur- Shivdaspura
Concerns:1. Inadequate capacity
2. Less terminals
3. No dedicated tracks
Steps to implement:
1. More terminals (1-2 KM)2. Dedicated lines
-
7/28/2019 Justification of Questions
3/10
Jaipur CMP
Bus Rapid Transit System:
Studies done on the BRTS have
identified the complete networkfor the city.
Concerns:
1. ROW
2. Traffic flows
3. Future growth centres
NB: the authorities did not spend
time on the route alignment,
preferring to take the shortest
distance between 2 points.
-
7/28/2019 Justification of Questions
4/10
Jaipur CMP
Higher Order Mass Transit System:
Studies done on the BRTS have
identified the complete network forthe city.
Concerns:
1. ROW
2. Traffic flows
3. Future growth centres
NB: the authorities did not spend
time on the route alignment,
preferring to take the shortest
distance between 2 points.
-
7/28/2019 Justification of Questions
5/10
-
7/28/2019 Justification of Questions
6/10
Jaipur CMP
Public Transit Improvement Plan: 2011-2031
A ring and radial network has been envisaged for the study area. It is proposed that the
mobility corridors will be developed as multi modal corridors
2011 2016 2021 2031
-
7/28/2019 Justification of Questions
7/10
The authorities had initially decided to implement light rail, but then they went ahead
with the bus rapid transit system under JnNURM.
Metro started undergoing construction before the BRT was completed.
P L A N N E D R A P I D T R A N S I T S Y S T E M
PHASE BRT METRO
I- East- West Modifications
to be approved
9.2 KM
II- North-
South
26 KM, 5 KM
dedicated lane
Yet to begin
The system recommended by the CMP:
The authorities, when preparing the mobility
plan talked about mode integration of BRT, Metroand Mono rail with the network feeder system
(personalized vehicles, autos, taxis) in a
systematic manner.
Source: Comprehensive Mobility Plan- Jaipur
-
7/28/2019 Justification of Questions
8/10
BRT plan
P L A N N E D R A P I D T R A N S I T S Y S T E M
Metro plan
Source: Comprehensive Mobility Plan- Jaipur
Superimposing the 2 plans:
Overlaps are seen between the blue
and the green lines.
Legend:
Metro lines
BRT lines
-
7/28/2019 Justification of Questions
9/10
BRT kick started by the
government under the
JnNURM schemeChange in government
results in Metro given
prominence
Work for both continuingsimultaneously
Jaipur BRT: Feasibility study done by PDCOR Ltd.
Only about 5 KM of BRT lane
created.
After disruptions and delays, BRT
now has an open system, with the
buses intermingling in the mixedtraffic.
Infrastructure needed for the BRT is
still not completed.
Jaipur Metro: Feasibility study done by DMRC.
Two routes of 12 and 23 KM have
been proposed.
Infrastructure construction is still
ongoing.
No idea if the Metro is supposed toact as feeder to the BRT, or the BRT
is to be support for Metro
j a i p u r B R T v / s M E T R O : p r e s e n t c o n d i t i o n
Source: Comprehensive Mobility Plan- Jaipur
-
7/28/2019 Justification of Questions
10/10
1. Why do cities decide on one thing, change their mind halfway through, and then go
ahead with another thing with modifications to old ones? What lead to this change
of mind?
2. What will be the probable impact of these decisions on the mode? What will be the
final outcome of the transit plan?
Q U E S T I O N S :
I N F E R E N C E S :
1. A comprehensive alternative analysis of the city is missing.
2. The timeline decided for transit infrastructure has not been followed.
3. The BRTS corridors are incomplete.