Birmingham Public Schools 2015 Bond Program Monthly Construction Update
July 2016
Brief Project Description
On June 20, 2016 construction began at several buildings for the 2015 Bond Program. The scope of work
includes new secured entries at Beverly, Bingham Farms, Greenfield, Harlan, Pembroke, Pierce, Quarton
and Birmingham Covington. All existing unit ventilators are being replaced along with the existing
temperature controls at Pierce. A few other projects at Pierce include updating the softball field and
replacing the door system off Pierce Street. New lockers are being installed at Covington. Fuel pumps
have been replaced at the Transportation building. The boilers and domestic water heaters are being
replaced at Groves and the pool locker rooms have received new epoxy flooring. Lastly at Seaholm and
Groves new scoreboards will be installed for the football and varsity baseball and softball fields, and the
tennis courts are being repaved and resurfaced.
Construction Schedule Update
Inspections will be scheduled for the week of 8/29.
Groves
At the tennis courts, fencing is ongoing and expected to be complete on or before 8/10.
Acrylic coating and striping is starting following the fencing and will take roughly one‐week
weather depending.
Tennis courts should be ready for use by 8/22 at the latest.
Domestic hot water replacement is almost complete, hot water is scheduled to be back on by
8/8.
Piping is ongoing for the boiler replacement.
The epoxy floor in the locker rooms is completed, ready for punchlist.
Pierce Unit Ventilators
Temperature controls are approximately 70% complete. Unit ventilators and louvers are all on
site.
Piping unit ventilators began on Saturday 7/30 and the unit ventilator installation is on track to
be completed by 8/12.
Start‐up, Controls, testing and balancing of the unit ventilators will begin on 8/15.
Counter tops in the classrooms will begin being installed following the completion of the unit
ventilators the week of 8/15.
Secured Entries
Drywall finishing at all of the secured entries will be complete by 8/5.
Painting is ongoing and is scheduled to be complete next week.
Reworking ceiling grid/tile will begin this week.
Aluminum framed entrances will be installed this week at Beverly and Pembroke.
Hollow metal doors and frames have all been installed.
Door hardware and access control installation is approximately 80% complete.
FRP doors and frames for Covington, Quarton and Harlan will be delivered and installed the
week of 8/8.
FRP doors and frames for Greenfield and Pierce will be delivered and installed the week of 8/29.
Existing casework has been installed. Millwork should be installed week of 8/8 and casework
will be delivered and installed week of 8/22.
Owner installed floor covering can begin at all of the schools the week of 8/8.
Miscellaneous Projects
Transportation Fuel Pumps are completed, ready for punchlist scheduled on 8/3.
Seaholm Tennis Courts are completed. Waiting on bangboards to be delivered in approximately
2 weeks.
Electrical boring for the football scoreboards started last week and is ongoing.
Demo of the existing beams and scoreboards, and pouring concrete for new beams next week.
Scoreboards are shipping 8/4 and the new beams will be delivered and installed the week of
8/15.
Locker installation at Covington is on track to be completed this week.
Translucent panels in Bingham Farms Multipurpose room have been completed.
Safety
All contractors will go through Clark Construction Company’s site specific safety orientation
before beginning work on site. To date over 100 contractors have been through orientation.
Hard hats, safety glasses and safety vests will be required 100% of the time on site.
Clark’s BRAVO program (Being Resistant Against Violations Openly) is being utilized on this
project. This program is to ensure everyone has their eyes open to potential safety hazards and
is looking out for one another.
Clark has set this project up with a MIOSHA SET Alliance.
There have been 5,280 trade hours worked to date with no safety incidents.
Logs
Attached is an updated potential change order log
Attached is an updated material tracking log.
Attached is a 3 week look ahead schedule.
To date, there have been 9 bulletins issued by TMP.
To date, 82 RFIs issued and 81 have been answered.
To date, 142 submittals have been submitted and completed.
Material Status ReportCCC Job No.: xxxx
Run Date: 7/29/2016
Project Name: Birmingham Public Schools
BP / Division Contractor Description LocationSubmittal Package
NumberSubmittal Status
Date Required On
Site
Confirmed Delivery
Beverly 081113 Reviewed/Approved 7/1/2016 6/27/2016
Bingham 081113 Reviewed/Approved 7/1/2016 6/27/2016
Covington 081113 Reviewed/Approved 7/1/2016 6/27/2016
Greenfield 081113 Reviewed/Approved 7/1/2016 6/27/2016
Harlan 081113 Reviewed/Approved 7/1/2016 6/27/2016
Pembroke 081113 Reviewed/Approved 7/1/2016 6/27/2016
Pierce 081113 Reviewed/Approved 7/1/2016 6/27/2016
Quarton 081113 Reviewed/Approved 7/1/2016 6/27/2016
Seaholm 081113 Reviewed/Approved 7/1/2016 6/27/2016
Beverly Reviewed/Approved 7/1/2016 8/22/2016
Bingham Reviewed/Approved 7/1/2016 8/22/2016
Covington Reviewed/Approved 7/1/2016 8/22/2016
Greenfield Reviewed/Approved 7/1/2016 8/22/2016
Harlan Reviewed/Approved 7/1/2016 8/22/2016
Pembroke Reviewed/Approved 7/1/2016 8/22/2016
Pierce Reviewed/Approved 7/1/2016 8/22/2016
Quarton Reviewed/Approved 7/1/2016 8/22/2016
Seaholm Reviewed/Approved 7/1/2016 8/22/2016
Wood Doors 081113 Reviewed/Approved 7/1/2016 7/5/2016
Beverly 087100 Reviewed/Approved 7/1/2016 On Site
Bingham 087101 Reviewed/Approved 7/1/2016 On Site
Covington 087102 Reviewed/Approved 7/1/2016 On Site
Greenfield 087103 Reviewed/Approved 7/1/2016 On Site
Harlan 087104 Reviewed/Approved 7/1/2016 On Site
Pembroke 087105 Reviewed/Approved 7/1/2016 On Site
Pierce 087106 Reviewed/Approved 7/1/2016 On Site
Quarton 087107 Reviewed/Approved 7/1/2016 On Site
Seaholm 087108 Reviewed/Approved 7/1/2016 On Site
Pierce 082250 Reviewed/Approved 7/1/2016 8/22/2016
Pembroke 082250 Reviewed/Approved 7/1/2016 8/22/2016
Quarton 082250 Reviewed/Approved 7/1/2016 8/22/2016
Greenfield 082250 Reviewed/Approved 7/1/2016 8/22/2016
Covington 082250 Reviewed/Approved 7/1/2016 8/22/2016
Harlan 082250 Reviewed/Approved 7/1/2016 8/22/2016
Beverly 082250 Reviewed/Approved 7/1/2016 8/22/2016
Pierce 087100 Reviewed/Approved 7/1/2016 On Site
Pembroke 087100 Reviewed/Approved 7/1/2016 On Site
Quarton 087100 Reviewed/Approved 7/1/2016 On Site
Bingham 087100 Reviewed/Approved 7/1/2016 On Site
Greenfield 087100 Reviewed/Approved 7/1/2016 On Site
Covington 087100 Reviewed/Approved 7/1/2016 On Site
Harlan 087100 Reviewed/Approved 7/1/2016 On Site
Beverly 087100 Reviewed/Approved 7/1/2016 On Site
Greenfield 082250 Reviewed/Approved 7/1/2016 6/29/2016
Covington 084413 Reviewed/Approved 7/1/2016 6/29/2016
Harlan 084414 Reviewed/Approved 7/1/2016 6/29/2016
Translucent panels Bingham 084523 Reviewed/Approved 7/1/2016 6/22/2016
Fire Rated Aluminum Doors Pierce 081116 Reviewed/Approved 7/1/2016 8/30/2016
Glass & Glazing All 088000 Reviewed/Approved 7/1/2016 8/4/2016
10
Steel Equipment Co.David (248) 334-1900cell: (248) 930-1800
Lockers Covington Reviewed/Approved 7/1/2016 6/22/2016
Unit Ventilators 238223 Reviewed/Approved 7/1/2016 7/14/2016
Louvers 238223 Reviewed/Approved 7/1/2016 7/8/2016
23BOscar Larson
Jeff (248) 620-0070 x [email protected]
Pumps Transporation Reviewed/Approved 7/1/2016 On Site
Scoreboards Groves 116843 Reviewed/Approved 7/1/2016 8/4/2016
Scoreboards Seaholm 116843 Reviewed/Approved 7/1/2016 8/4/2016
Access control and visitor notifiation system Beverly Revise & Resubmit 7/1/2016 7/10/2016
Access control and visitor notifiation system Bingham Revise & Resubmit 7/1/2016 7/10/2016
Access control and visitor notifiation system Greenfield Revise & Resubmit 7/1/2016 7/10/2016
Chainlink Fence - Vinyl Groves 323130 Reviewed/Approved On Site
Chainlink Fence - Vinyl Seaholm Reviewed/Approved On Site
Chainlink Fence - Galvanized Pierce 323102 Reviewed/Approved On Site
06AAxiom
Deib (248) [email protected]
Hollow metal
Casework
Hardware
FRP and AMP doors (aluminum)
Hardware08
Peterson GlassKevin (248) 541-6800
Curtain Wall
23Johnson and Wood
Jon Clark (810) [email protected]
26 OSC
Rick/Jayson (810) [email protected]
32T&M
Ken (248) 529-2465
409FR037 Version 1
Material Status ReportCCC Job No.: xxxx
Run Date: 7/29/2016
BP / Division Contractor Description LocationSubmittal Package
NumberSubmittal Status
Date Required On
Site
Confirmed Delivery
Water Heater Groves 223400 Reviewed/Approved On Site
Boilers Groves 235216 Reviewed/Approved On Site
Storage Tanks Groves 221223 Reviewed/Approved On Site
Industrial Process PipingBP4 - 02, 23, & 26
409FR037 Version 1
BirminghamSchools‐2700MeetingDate:
M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa
7/25/2016
THREE‐WEEKLOOKAHEAD ScheduledActivities
MeetingNo.4WORK ACTIVITES FORWEEK: 7/25/2016
BP School Contractor PlannedCommitments CommentsAxiom Modifylouveropenings(interior&exterior) x xJ&W Controlwiring x x x x x x x x x x x x x x x x x x x xJ&W InstallUnitVentilators x x x x x x x x x x x x x x x x x x x xT&M ReinstallfenceatSoftballField x x xAxiom TapeandFinishdrywall x x x x x xAxiom Fieldmeasurecountertops xAxiom Muralcolumms x xOSC InstallLightsinStairwell xAxiom AcousticalCeillingTileinStairwell x x x xAxiom Painting x xAxiom InstallHMdoorsandframes x
Axiom Fieldweldendofwindowlight xAxiom InstallHMdoorsandframes x xAxiom Sandbulkhead xAxiom Paint x xPeterson ReinstallAluminumframeanddoors x x x x xPeterson Measureglass x xOSC Completeaccesscontrols x xAxiom PrepA3doors x x
Axiom SetHMFrames(Grout&Anchor)2doors x xAxiom FinshDrywall x x xOSC Relocatelights,sensor,speaker x xAxiom Paint x xPeterson ResetAluminumframeanddoors x xAxiom Reinstallceilinggrid xOSC Completeaccesscontrols x xAxiom PrepA3doors x x
Axiom SetHMframesandmasonry x xAxiom PrepA3Doors xAxiom Metalstudsdrywall x xOSC Roughelectric x xAxiom Removeandreinstallboilerdoor x xAxiom DrywallFinish x x xAxiom Paintng x x xAxiom Reinstallceilinggrid xOSC Relocatelighting xOwner Carpet x xAxiom Setreceptiondesk x x xOSC Trimoutelectricalandlowvoltage x x
Axiom SetnewHMframe x xAxiom WeldFramePeterson AluminumEntryInstall x xAxiom PatchandrepairsoffitandPaint x x xAxiom Reworklay‐inceiling x xPeterson Measureglass x xAxiom PrepA3Doors x x x
Axiom DrywallFinish x x xAxiom Paint xPeterson InstallAluminumEntrance x xAxiom PerpA3Door x x x
Axiom DrywallTapeandFinish x x x xAxiom Paint x xSteelEq. NewLockerInstall x x x xAxiom Ceilingrework x xAxiom PrepA3Doors x x x
Axiom InstallHMdoorsandframes xAxiom Tape&FinishDrywall x x xAxiom PrepexistingdoorsforAccesscontro x xAxiom Paint xAxiom ReworkCeilingGrid x xAxiom ReinstallMillwork x x xOSC FinishElectric x
OscarLarson FinalDEQInspection xOscarLarson CreatePunchlist x x
T&M Fencing x x x x x x x x x x x x xT&M Colorcoatandmarkings&Netpostinstallation x x x x xT&M Restoration x x xT&M Punchlist
Seaholm T&M BangBoards x
IPP PipingDomesticHotWater x x x x x
IPP PipingBoilers x x x x x x x x x x
IPP PressureTest x
IPP Inspection x x x
8/2
WORKACTIVITESFORWEEK: 7/25/2016
7/25
7/26
7/27
7/28
7/29
7/30
7/31
8/1
8/3
8/4
8/5
8/6
8/7
8/8
8/9
8/10
8/11
8/12
8/13
Groves
4 Groves
1
Pierce
Pembroke
Beverly
Quarton
Harlan
Greenfield
Covington
BinghamFarms
Transportation
Potential Change Order
Summary Log
Birmingham Public Schools Clark Construction CompanyProject # 15-2700
31301 Evergreen, Beverly Hills Michigan 48025 Tel: Fax:
Budget Cost
Number Description PCCO No Approximate
(Anticipated)
Pending Approved Approximate
(Anticipated)
Pending Approved Contingency
Funds
001 Covington: Revise lockers to a knock down locker in lieu
of welded and 3 point latchign in lieu of single point.
Also add a 4" metal Z base. This was a voluntary
alterante at bid time.
2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$22,400.00 $0.00
002 Operations - Credit to not replace the fuel island pump at
Operations.
2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$42,080.00 $0.00
003 Seaholm and Groves - Remove cost to paint the pool
and gym locker rooms.
2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 -$45,000.00 $0.00
004 All Secured Entries - Add alternate A3. 2700 - 001 $0.00 $0.00 $0.00 $0.00 $0.00 $49,131.00 $0.00
005 Bulletin #2 - Revise the secured entrance at Pembroke,
Beverly, Greenfield and Quarton due to comments from
Bureau of Fire Services. Also miscellaenous RFIs.
2700 - 002 $0.00 $0.00 $26,292.00 $0.00 $0.00 $26,292.00 -$26,292.00
006 Pierce - RFI 003 add light fixture in stairwell A218 where
the acoustical ceiling is being installed.
2700 - 002 $0.00 $0.00 $1,210.00 $0.00 $0.00 $1,210.00 -$1,210.00
007 Bulletin #4 - Remove cabinet unit heater at Pembroke
and add electrical at Sealhom and Groves.
2700 - 002 $0.00 $0.00 -$13,072.00 $0.00 $0.00 -$13,072.00 $13,072.00
008 Bulletin #3 - Casework revisions at Bingham Farms and
Quarton.
2700 - 002 $0.00 $0.00 $2,484.00 $0.00 $0.00 $2,484.00 -$2,484.00
009 Covington - Removal of concrete bases for lockers in
cubbies per ASI #1.
2700 - 002 $0.00 $0.00 $4,886.00 $0.00 $0.00 $4,886.00 -$4,886.00
010 Seaholm and Groves - Add the team name message
centers and electronic captions to the football
scoreboards
2700 - 002 $0.00 $0.00 $22,185.00 $0.00 $0.00 $22,185.00 -$22,185.00
011 Make Bid Pack #1 and #4 Budgets Whole 2700 - 003 $0.00 $0.00 $49,452.00 $0.00 $0.00 $0.00 -$49,452.00
012 Harlan - Relocate sprinkler head that is in conflict with
new curtain wall and modify existing bulkhead.
$5,100.00 $0.00 $0.00 $5,100.00 $0.00 $0.00 -$5,100.00
013 Covington - Relocate an existing pull station that is in
conflict with the new curtain wall per RFI 004.
2700 - 002 $0.00 $0.00 $865.00 $0.00 $0.00 $865.00 -$865.00
014 Covington & Quarton - Remove and salvage carpet tile
in the main office per RFI 004.
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$3,000.00
015 Bingham Farms - Furnish and install a lintel for new door
opening B111 per RFI 15, this was not shown to be
masonry.
2700 - 002 $0.00 $0.00 $383.00 $0.00 $0.00 $383.00 -$383.00
Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 1
Potential Change Order
Summary Log
Budget Cost
Number Description PCCO No Approximate
(Anticipated)
Pending Approved Approximate
(Anticipated)
Pending Approved Contingency
Funds
016 Quarton - furnish and install decorative caps for the
removed push bars per RFI 013.
017 Cost to re-certify the fire rated doors that need to be
modified per Alternate 3.
$0.00 $3,827.00 $0.00 $0.00 $3,827.00 $0.00 -$3,827.00
018 Bulletin #6 - Revise door hardware on fire rated doors at
Pierce.
2700 - 002 $0.00 $0.00 $3,277.00 $0.00 $0.00 $3,277.00 -$3,277.00
019 Groves - Glycol backcharge -$21,232.00 $0.00 $0.00 -$21,232.00 $0.00 $0.00 $21,232.00
020 Groves and Seaholm - Delete the protective nettings
from this summers work.
2700 - 002 $0.00 $0.00 -$65,200.00 $0.00 $0.00 -$65,200.00 $65,200.00
021 Groves - Add 3 - 8" valves to seperate chilled and
heating systems to drain glycol because existing valves
are not holding.
2700 - 002 $0.00 $0.00 $9,960.00 $0.00 $0.00 $9,960.00 -$9,960.00
022 Groves - Sawcut existing concrete where fencing posts
are embedded and extend asphalt per RFI 027.
2700 - 002 $0.00 $0.00 $2,500.00 $0.00 $0.00 $2,500.00 -$2,500.00
023 Demo Scoreboards and Foundations at Seaholm and
Groves
2700 - 002 $0.00 $0.00 $11,000.00 $0.00 $0.00 $11,000.00 -$11,000.00
024 Remove existing VCT where carpet is shown to be
installed at Bingham Farms, Harlan and Pierce.
025 Remove and replace toilets in the locker rooms at
Seaholm and Groves for the epoxy flooring.
$5,000.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 -$5,000.00
026 Investigate domestic water piping at Pierce to see if it
needs to be replaced next summer.
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$5,000.00
027 Transportation - Patch asphalt where new conduits are
being installed.
$1,800.00 $0.00 $0.00 $1,800.00 $0.00 $0.00 -$1,800.00
028 Pierce - provide engineered stamped drawings for cold
formed metal framing for the louver openings per
Addendum #1.
2700 - 002 $0.00 $0.00 $863.00 $0.00 $0.00 $863.00 -$863.00
029 Seaholm - drill and epoxy dowels into the existing
foundations for the tennis court nets because there is not
enough room to get the full depth foundation with the
exisitng foundations there.
$1,500.00 $0.00 $0.00 $1,500.00 $0.00 $0.00 -$1,500.00
030 Transportation - Replace the concrete in the island
around the fuel pumps per request by Birmingham
Public Schools.
2700 - 002 $0.00 $0.00 $6,273.00 $0.00 $0.00 $6,273.00 -$6,273.00
031 Pierce - Remove receptacles being fed through univents
and refeed with the new univent.
$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00
032 Groves - Sawcut existing sidewalk and replace after the
edgedrain is installed per RFI 31.
2700 - 002 $0.00 $0.00 $1,922.00 $0.00 $0.00 $1,922.00 -$1,922.00
033 Transportation - Pump out water and put a test well in so
the tanks do not float.
$8,970.00 $0.00 $0.00 $8,970.00 $0.00 $0.00 $0.00
034 Transportation - Test the column supporting the canopy $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 -$923.00
Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 2
Potential Change Order
Summary Log
Budget Cost
Number Description PCCO No Approximate
(Anticipated)
Pending Approved Approximate
(Anticipated)
Pending Approved Contingency
Funds
over the fuel pumps to make sure it is structurally sound.
035 Groves - Bulletin #1 Bid Pack #4 - Furnish and Install a
SpiroTherm Air and Dirt Serperator in tbe boiler room.
2700 - 002 $0.00 $0.00 $0.00 $0.00 $0.00 $30,332.00 $0.00
036 Transportation - Remove the asphalt around the
concrete island and regrade so the concrete island will
drain properly and there will not be standing water by the
fuel pumps. Replace this perimieter with new concrete.
2700 - 002 $0.00 $0.00 $7,400.00 $0.00 $0.00 $7,400.00 -$7,400.00
037 Pembroke - Relocate electrical outlet found in display
case when demo'd. Conduit is in the floor so this can be
moved over to the adjacent wall.
$1,000.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 -$1,000.00
038 Quarton - Relocate two 1" conduits found in demo'd wall
per RFI 51.
$1,000.00 $0.00 $0.00 $1,000.00 $0.00 $0.00 -$1,000.00
039 Covington - Build two metal stud and drywall walls to
accomodate U shape locker configuration per RFI #56.
$0.00 $1,859.00 $0.00 $0.00 $1,859.00 $0.00 -$1,859.00
040 Quarton - Build a chase wall for the fire alarm panel
location in the main office per RFI 29.
$717.00 $0.00 $0.00 $717.00 $0.00 $0.00 -$717.00
041 Transportation - RFI 64 - Furnish and install sump
sensors that are required by law and existing sensors
were damaged and not working.
$1,746.00 $0.00 $0.00 $1,746.00 $0.00 $0.00 -$1,746.00
042 Covington - There were 5 receptacles behind lockers
that needed to be removed per code in order to re-install
lockers.
$450.00 $0.00 $0.00 $450.00 $0.00 $0.00 -$450.00
043 Pierce - RFI 58 - Furnish and install isolation valves for
2nd floor gym finned tube radiation on both sides of the
control valve.
$439.00 $0.00 $0.00 $439.00 $0.00 $0.00 -$439.00
044 Pierce - RFI 60 - Furnish and install a metal pipe
enclosure at the art rooms to match the unit ventilators.
$5,000.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 -$5,000.00
045 Pierce - glycol needed to bring system to 35% propylene
glycol per RFI 37.
$2,775.00 $0.00 $0.00 $2,775.00 $0.00 $0.00 -$2,775.00
046 Greenfield - furnish electric strikes per RFI 44. The
specified strike Von Duprin 6111 does not fit.
$1,086.00 $0.00 $0.00 $1,086.00 $0.00 $0.00 -$1,086.00
047 Covington - Paint all locker areas per RFI 65. $0.00 $9,000.00 $0.00 $0.00 $9,000.00 $0.00 -$9,000.00
048 Pierce - relocate receptacle found in door opening
A119C per RFI 41.
$300.00 $0.00 $0.00 $300.00 $0.00 $0.00 -$300.00
049 Pierce - Backcharge to Axiom to replace conduit that
was damaged by masons while modifying louver
openings.
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
050 Pierce - Furnish and install a 90 minute fire rated door,
frame and hardware for PIerce due to the late delivery of
the permenant door.
$0.00 $1,682.00 $0.00 $0.00 $1,682.00 $0.00 -$1,682.00
051 Bulletin No. 8 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 3
Potential Change Order
Summary Log
Budget Cost
Number Description PCCO No Approximate
(Anticipated)
Pending Approved Approximate
(Anticipated)
Pending Approved Contingency
Funds
052 Bulletin #6 - tie hardware into fire alarm panel. $0.00 $6,745.00 $0.00 $0.00 $6,745.00 $0.00 -$6,745.00
053 Covington - Furnish and install break metal or EIFS at
Covington to cover 2" gap between new door and head
per RFI 70.
$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00
054 Pierce - Furnish and install sheet metal below wall
sleeve where louver is over 4" off ground creating a gap
per RFI 75.
$2,500.00 $0.00 $0.00 $2,500.00 $0.00 $0.00 -$2,500.00
055 Pierce - Furnish and install a removable metal pipe
enclosure to conceal the exposed pipes per RFI 76.
$1,500.00 $0.00 $0.00 $1,500.00 $0.00 $0.00 -$1,500.00
056 Modify escutcheon plates to accomodate surface
mounted raceways.
057 Beverly - Add a removable mullion at the boiler room
door. The door and frame that was ordered does not fit
the existing opening per RFI 67.
$0.00 $863.00 $0.00 $0.00 $863.00 $0.00 -$863.00
058 Pierce - Funish and Install a new woord door at A123 per
RFI 79.
059 Bulletin 7 $0.00 $6,557.00 $0.00 $0.00 $6,557.00 $0.00 -$6,557.00
060 Bulletin 10
Project Totals: $24,651.00 $30,533.00 $72,680.00 $24,651.00 $30,533.00 -$6,789.00 -$127,817.00
Prolog Converge Printed on: 8/2/2016 Prolog_Converge Page 4