July 7, 2021

16
CONSTRUCTION UPDATE TO THE BOARD OF EDUCATION July 7, 2021 DC BOCES Salt Point Campus Additions & Alterations PROJECT TEAM & DISTRIBUTION LIST: Board of Education, Richard Hooley , Matthew Metzger, KG&D and The Palombo Group

Transcript of July 7, 2021

Page 1: July 7, 2021

CONSTRUCTION UPDATE TO THE

BOARD OF EDUCATION

July 7, 2021

DC BOCES – Salt Point Campus Additions & Alterations

PROJECT TEAM

&

DISTRIBUTION LIST: Board of Education, Richard Hooley , Matthew Metzger, KG&D and

The Palombo Group

Page 2: July 7, 2021

DC BOCES

AGENDA

I. EXECUTIVE SUMMARY

– PRIME CONTRACT PROGRESS OVERVIEW

– SCHEDULE OVERVIEW

II. PROJECT PROGRESS PHOTOS

III. SAFETY

IV. Q & A

Page 3: July 7, 2021

DC BOCES

I. EXECUTIVE SUMMARY

Worth Construction (GC) – Continuing the new addition

foundations, masonry walls and structural steel. Interior

renovations are well under way in both the CTI and SPC

buildings. The CTI renovations include (4+) bathrooms, room

301 reconfiguration and new paint, ceilings and flooring in the

corridors. SPC renovation includes work at the main entrance

vestibule.

S&O Construction (PC) – Working on new addition below

slab piping as needed. Additionally working on interior

renovations in CTI related to (4+) bathrooms and room 301

reconfiguration.

Page 4: July 7, 2021

DC BOCES

I. EXECUTIVE SUMMARY (con’t)

CB Strain (MC) – Currently working in CTI installing new HVAC

equipment in various spaces including the bathrooms and room

301 renovation. Also working in the boiler room preparing piping

to new addition and new boiler installation. Over in SPC new

HVAC equipment will be installed for the renovated main

entrance vestibule.

Upstate Electric (EC) – Currently working in conjunction with

all other prime contractors including the EPC lighting

contractor within the CTI building. Will also be working in

the SPC renovated main entrance vestibule. Planning and

preparing new power service upgrades including multiple

transformers for all buildings.

Page 5: July 7, 2021

I. EXECUTIVE SUMMARY (con’t)

United Safety (AB) – Currently performing asbestos

abatement in CTI in multiple locations including four

bathrooms, room 301 and some incidental remaining

corridor flooring.

Amity Construction (SC) – Continue structural building fill

and corresponding foundation work. Also currently

working on various exterior utilities including sanitary

sewer, storm, water, power and data trenching. Will be

placing portions of new concrete walkways and asphalt

paving in front of SPC in conjunction with the new main

entrance vestibule.

DC BOCES

Page 6: July 7, 2021

I. EXECUTIVE SUMMARY (con’t)

Schedule

Upcoming Weeks: Continue progressing the new addition

foundation and steel erection working toward enclosing

the building envelope. As the new addition takes shape,

the surrounding site work will continue with various

infrastructure, establishment of campus roadways and

site grading. Concurrently, interior renovation work in CTI

and SPC will be continuous through the summer. CTI

work includes renovated bathrooms, room 301

reconfiguration of space, renovated corridors and various

HVAC upgrades. SPC work includes a new main

entrance vestibule, HVAC unit and exterior site

improvements.

DC BOCES

Page 7: July 7, 2021

II. PROJECT PHOTOGRAPHS

The following project photographs were taken during

construction. They represent a flavor of the history and

conditions of all phases of projects that are under

construction and or completed.

DC BOCES

Page 8: July 7, 2021

DC BOCES – New Addition

Stair Tower

Page 9: July 7, 2021

DC BOCES – New Addition

Page 10: July 7, 2021

DC BOCES – New Addition

Page 11: July 7, 2021

DC BOCES – Utility Work

Page 12: July 7, 2021

DC BOCES – Boiler Room & B wing Bathrooms

Page 13: July 7, 2021

DC BOCES – Room 301

Page 14: July 7, 2021

DC BOCES – SPC Bathrooms

Page 15: July 7, 2021

DC BOCES

III. SAFETY

• COVID 19 – Latest protocols will continue to be followed.

• Construction workers are not to work in owner occupied areas

of building.

• All Contractors are Required to Wear ID Badges

• CM has Fulltime Supervision During Construction

• All Communications are through the Construction Manager

Page 16: July 7, 2021

DC BOCES

IV. Q & A