CONSTRUCTION UPDATE TO THE
BOARD OF EDUCATION
July 7, 2021
DC BOCES – Salt Point Campus Additions & Alterations
PROJECT TEAM
&
DISTRIBUTION LIST: Board of Education, Richard Hooley , Matthew Metzger, KG&D and
The Palombo Group
DC BOCES
AGENDA
I. EXECUTIVE SUMMARY
– PRIME CONTRACT PROGRESS OVERVIEW
– SCHEDULE OVERVIEW
II. PROJECT PROGRESS PHOTOS
III. SAFETY
IV. Q & A
DC BOCES
I. EXECUTIVE SUMMARY
Worth Construction (GC) – Continuing the new addition
foundations, masonry walls and structural steel. Interior
renovations are well under way in both the CTI and SPC
buildings. The CTI renovations include (4+) bathrooms, room
301 reconfiguration and new paint, ceilings and flooring in the
corridors. SPC renovation includes work at the main entrance
vestibule.
S&O Construction (PC) – Working on new addition below
slab piping as needed. Additionally working on interior
renovations in CTI related to (4+) bathrooms and room 301
reconfiguration.
DC BOCES
I. EXECUTIVE SUMMARY (con’t)
CB Strain (MC) – Currently working in CTI installing new HVAC
equipment in various spaces including the bathrooms and room
301 renovation. Also working in the boiler room preparing piping
to new addition and new boiler installation. Over in SPC new
HVAC equipment will be installed for the renovated main
entrance vestibule.
Upstate Electric (EC) – Currently working in conjunction with
all other prime contractors including the EPC lighting
contractor within the CTI building. Will also be working in
the SPC renovated main entrance vestibule. Planning and
preparing new power service upgrades including multiple
transformers for all buildings.
I. EXECUTIVE SUMMARY (con’t)
United Safety (AB) – Currently performing asbestos
abatement in CTI in multiple locations including four
bathrooms, room 301 and some incidental remaining
corridor flooring.
Amity Construction (SC) – Continue structural building fill
and corresponding foundation work. Also currently
working on various exterior utilities including sanitary
sewer, storm, water, power and data trenching. Will be
placing portions of new concrete walkways and asphalt
paving in front of SPC in conjunction with the new main
entrance vestibule.
DC BOCES
I. EXECUTIVE SUMMARY (con’t)
Schedule
Upcoming Weeks: Continue progressing the new addition
foundation and steel erection working toward enclosing
the building envelope. As the new addition takes shape,
the surrounding site work will continue with various
infrastructure, establishment of campus roadways and
site grading. Concurrently, interior renovation work in CTI
and SPC will be continuous through the summer. CTI
work includes renovated bathrooms, room 301
reconfiguration of space, renovated corridors and various
HVAC upgrades. SPC work includes a new main
entrance vestibule, HVAC unit and exterior site
improvements.
DC BOCES
II. PROJECT PHOTOGRAPHS
The following project photographs were taken during
construction. They represent a flavor of the history and
conditions of all phases of projects that are under
construction and or completed.
DC BOCES
DC BOCES – New Addition
Stair Tower
DC BOCES – New Addition
DC BOCES – New Addition
DC BOCES – Utility Work
DC BOCES – Boiler Room & B wing Bathrooms
DC BOCES – Room 301
DC BOCES – SPC Bathrooms
DC BOCES
III. SAFETY
• COVID 19 – Latest protocols will continue to be followed.
• Construction workers are not to work in owner occupied areas
of building.
• All Contractors are Required to Wear ID Badges
• CM has Fulltime Supervision During Construction
• All Communications are through the Construction Manager
DC BOCES
IV. Q & A