July 29 Committee Packet

6
 ~ t Q / , Q'f)\Q City of Troy u ~ Wednesday, July 29, 2015, 5:00 P TROY CITY COUNCIL COMMITTEE MEETING NOTICE COUNCIL CHAMBERS, CITY HALL 100 S . MARKET STREET, TROY, OHIO Community Economic Development Committee (Twiss [Chm.] Kendall, Schweser) 1. Provide a recommendation to Council regarding the purchase of the Huelskamp Farm, 1 ,500,000. Consideration of emergency legislation is requested Str eet s Sidewalks Commit te e Phillips [Chm.], Heath, Snee) 1. Provide a recommendation to Council regarding authorizing a Facilities Encroachment Agreement with CSX to bore under the CSX line to install new storm sewer associated with the McKaig Road Improvement Project, Phase 2. Consideration o f emergency legislation is requested . Other Committees/items may be added. 7-28-2015 cc: Council Mayor Mr . Titterington Mr. Livingston Mr. Stickel Department Heads Chamber of Commerce Bd of Education media

Transcript of July 29 Committee Packet

  • ~tQ'/, Q'f)\Q City of Troy us~

    Wednesday, July 29, 2015, 5:00 PM

    TROY CITY COUNCIL COMMITTEE MEETING NOTICE

    COUNCIL CHAMBERS, CITY HALL 100 S. MARKET STREET, TROY, OHIO

    Community & Economic Development Committee (Twiss [Chm.], Kendall, Schweser)

    1. Provide a recommendation to Council regarding the purchase of the Huelskamp Farm, $1 ,500,000. Consideration of emergency legislation is requested

    Streets & Sidewalks Committee (Phillips [Chm.], Heath, Snee)

    1. Provide a recommendation to Council regarding authorizing a Facilities Encroachment Agreement with CSX to bore under the CSX line to install new storm sewer associated with the McKaig Road Improvement Project, Phase 2. Consideration of emergency legislation is requested .

    Other Committees/items may be added.

    7-28-2015

    cc: Council Mayor Mr. Titterington Mr. Livingston Mr. Stickel Department Heads Chamber of Commerce Bd of Education media

  • COMMUNITY& ECONOMIC DEVELOPMENT

    COMMITTEE

  • (;~,)(~:) TROY OHIO

  • STREETS & SIDEWALKS COMMITTEE

  • t-~~~~:J TROY OHIO

    Cfelc~ wlion (~)\~-)

    TO:

    FROM:

    DATE:

    MEMORANDUM

    Mrs. Baker, President of Co& ..

    Patrick E. J. Titterington ~ ~ July 28, 2015

    100 S. Market Street P. 0. Box 3003 Troy, Ohio 45373 www.troyohio.gov phone: (937) 335-1725 fax: (937) 339-8601 [email protected]

    SUBJECT: CSX TRANSPORTATION, INC. FACILITY ENROACHMENT AGREEMENT FOR MCKAIG ROAD IMPROVEMENT PROJECT, PHASE II

    RECOMMENDATION: That Council authorizes the Director of Public Service and Safety to enter into an Encroachment Agreement with CSX Transportation, Inc. related to the McKaig Road Improvement Project, Phase II.

    BACKGROUND: The City has contracted for the construction of the McKaig Road Improvement Project, Phase II. The project includes a new storm sewer crossing under the CSX line. In order to complete this boring, CSX is requiring that the City execute a Facility Encroachment Agreement. The City entered into such agreements associated with the Deltech Water Line Project and Water line Project No.4 (Governors Road crossing under the CSX line).

    REQUESTED ACTION: It would be appreciated if you would assign to a Committee of Council authorizing the Director of Public Service and Safety to enter into a Facility Encroachment Agreement with CSX Transportation, Inc. related to the McKaig Road Improvement Project, Phase II. We are requesting consideration of emergency legislation so that the agreement can be executed as soon as any details are worked out.

    Cc: Mayor Beamish

  • ~tQ'/, Q'(\\Q City of Troy us~

    TO: PATRICK E.J. TITTERINGTON, DIRECTOR OF PUBLIC SERVICE AND SAFETY

    fROM: Jillian Rhoades, PE, City Engineer

    DATE: JULY 28,2015

    SUBJECT: CSX Facility Encroachment Agreement

    For McKaig Road Improvements Phase 2

    Jillion A Rhoades, PE . --

    100 S. Market Street, P. 0. Box 3003 Troy, Ohio 45373-7303 phone: 937-339-2641 /fax: 937-339-9341 [email protected]

    The street reconstruction project on McKaig Avenue includes a new storm sewer crossing under the CSX line. In order to complete this boring, CSX is requiring the Encroachment Agreement from the City of Troy. This is a standard agreement that we have used previously in another railroad crossing.

    Staff is requesting that legislation be prepared to allow the Director of Public and Safety to enter into the Facility Encroachment Agreement with CSX. Staff is also requesting that this be performed as an emergency so to allow the City to proceed with the construction project as quickly as possible.