DOEA Form 701C Assessment Training July 13, 2010 Elder Options.
July 13, 2010
-
Upload
flavia-dorsey -
Category
Documents
-
view
32 -
download
1
description
Transcript of July 13, 2010
July 13, 2010
Temporary Terminal Presentation
Program Status
• Finalizing Temporary Terminal construction
• Striping and traffic changes in progress
• SFMTA and other operators move to Temporary Terminal on August 7th
• Demolition of existing ramps and Terminal begin on August 14th
• Seven year schedule for construction of the new Transit Center
Temporary Terminal Access
Temporary Terminal
Phase 1 Temporary Terminal Operation
August to November 2010
10871
71L82X
5
3838L
4138
38L
Temporary Terminal
Phase 2 Temporary Terminal Operation
Key Outreach Dates
• Install banners & re-launch website July 1st
• Handouts available at Terminal July 19th
• Ambassador Training July 19th
• Launch ambassador program July 21th
• Commemoration Event July 30th
• Open House at Temporary Terminal August 3rd
• Begin Operations at Temporary Terminal August 7th
• Transit Center Groundbreaking Event August 11th
Outreach Signage
Signage
Wayfinding Signage
Signage
Outreach Materials
trifold
Outreach Materials
Fold-out map
Website
Questions?