July 01, 2013. Shutdown 2012 - 2013 Machine Status: NTF Treatments and Dosimetry as scheduled ...
-
Upload
pierre-wagers -
Category
Documents
-
view
215 -
download
0
Transcript of July 01, 2013. Shutdown 2012 - 2013 Machine Status: NTF Treatments and Dosimetry as scheduled ...
All Experimenters’ Meeting
July 01, 2013
Shutdown 2012 - 2013
Machine Status: NTF Treatments and Dosimetry as scheduled Proton Source Commissioning and Studies
RFQ Injector Line (RIL) Linac Booster
Main Injector Power Supply studies on weekends
TeV & Muon Rings – Partially available for tours with approval and appropriate training
MSS Bypass Project
MSS Bypass Project – Impact Areas Project Completion Date
July 17th – July 25th
A0 Parking Lot WorkTeV road closure at A1 (Tuesday, July 2nd and
Wednesday, July 3rd from 0700-1530)TeV road reduction at A1 (Thursday, June 20th for
about 3 weeks during cable terminations)Power off to A1, A2, & A3 (Daily for ~ 3weeks)Pave parking lot on Tuesday, July 2nd
MSS Bypass Project – Impact Areas Cont.
CHL ~5 day outage/reduction (only house power available) Monday, June 24th through Friday, June 28th Two 5 minute power outages needed Monday, June 24th @ 0730 – 0735 (Completed) Friday, June 28th @ 0700 – 0705 (Completed) Cable pulls and splices in PMH 210
Meson Two 15 minute outages one week apart Monday, June 17th @ 0700 – 0715 (Completed) Monday, June 24th @ 0700 – 0715 (Completed) Monday, June 24th @ 0815-1215 (Bonus MCC-2 outage @
MS3) Cable pulls and splices in PMH 110 Impacts MCC, Holometer, MW9, all enclosures, systems, and buildings
Kautz Road SubStation Status
MI backfed from Master SubStation○ Using Feeder 45 for MI conventional power which is
normally T85 on KRSWe ordered 6+ new surge arrestors (4.7k each)
from Hubbell and wait for delivery in 8-9 weeksSchedule a ~1-2 day KRS outage (not really an
outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87
There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed
Shutdown 2012
Schedules and Links:Schedule can be accessed from the Operations Home Page
- Schedules -> Operations Schedule
Direct link to schedule
- http://www-ad.fnal.gov/ops/schedule.html