Juliet Environmental Statement 2012
Transcript of Juliet Environmental Statement 2012
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 1 of 194
All GDF SUEZ E&P UK Ltd Contracts
STANDARD INFORMATION SHEET
Project Name Juliet Field Development
DECC Project Reference No. D/4136/2012
Type of Project Field Development subsea tie-back to existing infrastructure
Undertaker Name GDF SUEZ E&P UK Ltd
Undertaker Address 40 Holborn Viaduct, London, EC1N 2PB
Licences/Owners GDF SUEZ E&P UK Ltd
Short Description GDF SUEZ E&P UK Ltd is planning to develop the Juliet field
located in Block 47/14b in the southern North Sea. The
proposed development lies approximately 37 kilometres to
the east-north-east of the nearest landfall at Theddlethorpe.
The nearest transboundary line is the UK/Dutch line which
lies approximately 148 kilometres to the east of the
proposed development location. License partners include
GDF SUEZ E&P UK Ltd, the operator (51.56%), and First Oil
Expro Ltd (29.44%) and Hansa (19.00%).
The objective of the project is to produce gas from the as yet
undeveloped Juliet field and export it to shore, using a
combination of both new and existing infrastructure. This
will be achieved by drilling two horizontal subsea wells local
to the 47/14b-10 discovery well.
The Juliet subsea wells will be tied back by an export
pipeline and umbilical to the Pickerill A Platform operated by
Perenco UK Ltd, located approximately 22 kilometres to the
east of the Juliet field. Existing infrastructure will be used to
transport the Juliet gas from the Pickerill A Platform to the
onshore Theddlethorpe terminal.
The proposed Juliet development wells are expected to be
drilled using a standard jack-up rig, with the preliminary
spud date provisionally programmed for Q2/3 2013.
Topsides construction phase is provisionally planned for Q3
2012 with subsea construction in Q3 2013. First gas is
currently anticipated in Q4 2013.
Anticipated Commencement of Works Q3 2012
Previously Submitted Environmental
Documents
PON15B for the Juliet (47/14b-10) exploration well
(DECC Ref No. PON15B/105)
The Juliet Field Development Environmental Statement
(DECC Ref No. D/4063/2009)
Significant Environmental Impacts
Identified
None
Statement Prepared By GDF SUEZ E&P UK Ltd in association with RPS Energy.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 2 of 194
All GDF SUEZ E&P UK Ltd Contracts
TABLE OF CONTENTS
NON-TECHNICAL SUMMARY 5
1.0 INTRODUCTION 17
1.1 THE PROJECT 17
1.2 SCOPE 19
1.3 APPLICANT 19
1.4 ENVIRONMENTAL IMPACT ASSESSMENT 19
1.5 CONSULTATIONS 20
1.6 STRUCTURE OF REPORT 21
1.7 CONTACT & INFORMATION REQUEST 21
2.0 THE PROPOSED DEVELOPMENT 23
2.1 THE JULIET FIELD 23
2.2 DEVELOPMENT OBJECTIVE AND CONCEPT 24
2.3 DEVELOPMENT OPTION SELECTION 25
2.4 PROPOSED PROJECT SCHEDULE 29
2.5 PRODUCTION AND EXPORT FACILITIES 31
2.5.1 JULIET SUBSEA FACILITIES 31
2.5.2 GAS EXPORT PIPELINE AND UMBILICAL 32
2.5.3 HOST FACILITY 34
2.6 OFFSHORE CONSTRUCTION AND INSTALLATION 36
2.6.1 PIPELINE AND UMBILICAL INSTALLATION 36
2.6.2 JULIET SUBSEA INSTALLATION 39
2.7 DRILLING OPERATIONS 40
2.7.1 OVERVIEW 40
2.7.2 DRILLING RIG 41
2.7.3 WELL CONSTRUCTION 42
2.7.4 DRILLING MUDS AND CHEMICALS 43
2.7.5 DISPOSAL OF DRILL CUTTINGS 43
2.7.6 WELL COMPLETION 44
2.7.7 INITIAL WELLBORE CLEANING & FINAL WELL CLEAN-UP AND TESTING 44
2.7.8 SUPPORT OPERATIONS 45
2.7.9 TOTAL DRILLING EMISSIONS SUMMARY 45
2.8 PRODUCTION 47
2.8.1 PREDICTED GAS PRODUCTION 47
2.8.2 POWER GENERATION 51
2.8.3 PRODUCTION CHEMISTRY 51
2.8.4 CHEMICAL INJECTION 51
2.8.5 SAND PRODUCTION 51
2.9 MAINTENANCE 52
2.10 DECOMMISSIONING 52
2.11 FUTURE DEVELOPMENT 52
3.0 ENVIRONMENTAL DESCRIPTION 53
3.1 INTRODUCTION 53
3.1.1 DATA SOURCES 53
3.2 GEOGRAPHY 56
3.3 THE SEABED AND BATHYMETRY 57
3.3.1 BATHYMETRY 57
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 3 of 194
All GDF SUEZ E&P UK Ltd Contracts
3.3.2 SEDIMENTS AND SEABED FEATURES 59
3.3.3 HYDROCARBON CONCENTRATIONS 70
3.4 OCEANOGRAPHY 70
3.4.1 WAVES 70
3.4.2 PHYSICAL CHARACTERISTICS 71
3.5 AIR AND CLIMATE 72
3.5.1 WIND 72
3.5.2 AIR QUALITY 73
3.6 FLORA AND FAUNA 73
3.6.1 PLANKTON 73
3.6.2 SEABED COMMUNITIES 73
3.6.3 FISH 74
3.6.4 SEABIRDS 78
3.6.5 MARINE MAMMALS 82
3.6.6 MARINE REPTILES 85
3.7 PROTECTED AND SENSITIVE COASTAL HABITATS 85
3.7.1 COASTAL PROTECTED SITES 85
3.7.2 MARINE PROTECTED AREAS 89
3.8 HUMAN POPULATIONS 94
3.8.1 COMMERCIAL FISHING 94
3.8.2 SHIPPING AND PORTS 96
3.8.3 COLLISION RISK ASSESSMENT 99
3.8.4 MILITARY ACTIVITY 99
3.8.5 PIPELINES, WELLS AND SUBMARINE CABLES 99
3.8.6 DREDGING AND DUMPING ACTIVITY 101
3.8.7 WIND FARMS 103
3.8.8 ARCHAEOLOGY 104
3.8.9 TOURISM AND LEISURE 105
3.9 KEY ENVIRONMENTAL SENSITIVITIES 105
4.0 ENVIRONMENTAL HAZARDS, EFFECTS AND MITIGATION MEASURES 107
4.1 INTRODUCTION 107
4.2 IDENTIFICATION OF INTERACTIONS 108
4.3 DESIGN CONTROL MEASURES 109
4.4 PHYSICAL PRESENCE 110
4.5 SEABED DISTURBANCE 112
4.5.1 SEABED DISTURBANCE RESULTING FROM PIPELAY INSTALLATION 112
4.5.2 SEABED DISTURBANCE RESULTING FROM DRILLING OPERATIONS 114
4.5.3 FOOTPRINT OF THE JACK-UP RIG 115
4.5.4 RIG STABILISATION 115
4.5.5 SEABED DISTURBANCE SUMMARY 116
4.6 NOISE AND VIBRATION 116
4.6.1 POTENTIAL IMPACT ON FISH 117
4.6.2 POTENTIAL IMPACT ON CETACEANS 118
4.7 ATMOSPHERIC EMISSIONS 119
4.7.1 DRILLING AND INSTALLATION PHASES 119
4.7.2 ATMOSPHERIC EMISSIONS DURING PRODUCTION OPERATIONS 122
4.8 MARINE DISCHARGES 122
4.8.1 WATER BASED DRILLING MUD (WBM) 122
4.8.2 COMPLETION FLUIDS 123
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 4 of 194
All GDF SUEZ E&P UK Ltd Contracts
4.8.3 PIPELINE COMMISSIONING 123
4.8.4 DRAINAGE WATER AND SEWAGE 124
4.9 SOLID WASTES 124
4.10 LOSS OF CONTAINMENT 124
4.10.1 OIL SPILL SCENARIOS AND HISTORICAL UKCS SPILL DATA 124
4.10.2 OFFSHORE CONSTRUCTION AND INSTALLATION 126
4.10.3 DRILLING OPERATIONS 126
4.10.4 PRODUCTION AND MAINTENANCE 132
4.11 DECOMMISSIONING 132
4.12 TRANSBOUNDARY IMPACTS 133
4.13 CUMULATIVE IMPACTS 133
5.0 ENVIRONMENTAL MANAGEMENT 137
5.1 INTRODUCTION 137
5.2 GDF SUEZ E&P UKS QHSEMS 137
5.2.1 INTRODUCTION 137
5.2.2 STRUCTURE AND GOALS 137
5.2.3 HSE POLICY 138
5.3 ORGANISATION 141
5.3.1 KEY ROLES & RESPONSIBILITIES 141
5.4 JULIET DEVELOPMENT MANAGEMENT PROCESSES 141
5.4.1 ASSESSMENT 141
5.4.2 PLANNING AND RESOURCING 142
5.4.3 AUDIT AND REVIEW 142
5.5 SUMMARY OF ENVIRONMENTAL COMMITMENTS 143
6.0 CONCLUSIONS 145
7.0 REFERENCES 149
APPENDIX A: STATUTORY FRAMEWORK 153
APPENDIX B: DRILLING OPERATIONS SUPPORTING INFORMATION 156
APPENDIX C: OCNS & HMCS 161
APPENDIX D: AIR QUALITY DATA 174
APPENDIX E: ATMOSPHERIC DISPERSION MODELLING 177
APPENDIX F: SEABED FEATURES ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE
2009A) 179
APPENDIX G: SEABED IMAGERY ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE,
2009A) 182
APPENDIX H: SEABED IMAGERY ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE, 2011)
185
APPENDIX I: JULIET DEVELOPMENT TO PICKERILL A PLATFORM PIPELINE ROUTE IN RESPECT TO THE
TRITTON KNOLLL WINDFARM BOUNDARY 188
APPENDIX J: PRODUCTION FIGURES 189
APPENDIX K: SEABED SAMPLE LOCATIONS FOR 2011 SEABED SURVEY 194
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 5 of 194
All GDF SUEZ E&P UK Ltd Contracts
NON-TECHNICAL SUMMARY
BACKGROUND
GDF SUEZ E&P UK Ltd (hereafter referred to as GDF SUEZ E&P UK) is planning to develop the Juliet gas field, located in Block 47/14b in the southern North Sea gas basin. This
Environmental Statement (ES) has been produced in order to meet the requirements of the
GDF SUEZ E&P UK Quality, Health, Safety and Environment Management System and to
ensure compliance with the Offshore Petroleum Production and Pipelines (Assessment of
Environmental Effects) (Amendment) Regulations 2007. It has been prepared by GDF SUEZ
E&P UK in conjunction with environmental consultants RPS Energy.
PROJECT OVERVIEW
The Juliet development will consist of two horizontal subsea wells local to the 47/14b-10
discovery well. The wells will be tied back to the Pickerill A Platform operated by Perenco UK
Ltd, approximately 22 kilometres to the east of the proposed Juliet development via a 12 inch
export pipeline and control umbilical. Existing infrastructure will be used to transport the Juliet
gas from the Pickerill A Platform to Theddlethorpe terminal onshore.
Subject to necessary consents and approvals, GDF SUEZ E&P UK plans a preliminary spud
date programmed for Q2/23 2013. Pipeline and manifold installation activities are planned
for Q3 2013, with the possibility of some platform works scheduled for Q3 2012. First gas is
currently anticipated in Q4 2013.
The design life of the Juliet development facilities is fifteen years. On cessation of production,
the Juliet field development, including all associated infrastructure will be abandoned in
accordance with the legislation prevailing at the time and consultation with the necessary
authorities.
THE EXISTING ENVIRONMENT
The Juliet field is located in the southern North Sea, approximately 37 kilometres to the east -
north-east of the nearest landfall at Theddlethorpe, and approximately 148 kilometres to the
west of the UK/Dutch median line.
The Juliet area lies on the edge of the Silver Pit where water depths range from approximately
50 to 70 metres (Hydrographer of the Navy, 2002). The water depth at the Juliet wells
location is approximately 56 metres lowest astronomical tide (LAT) (Gardline, 2009a). Along
the pipeline route to the Pickerill A Platform, water depth ranges from 14.3 metres LAT to a
maximum of 55.7 metres LAT within the Silver Pit (Gardline, 2009a, Garline, 2011).
Sediment composition across the survey area was variable, ranging from sand, sligh tly gravelly
and gravelly sand and muddy sand. Despite the variability, sediment in the survey is
comparable to that previously identified within the region. On the southeast slope of the
Silver Pit silty shelly sand and gravel with numerous cobbles and occasional boulders and rare
shell fragments are present. Sediments from the start of the pipeline route have been
identified as an intermittent layer of shelly silty sand and gravel with chalk outcrops and
numerous cobbles and boulders until reaching KP0.180. From here sediments become
predominantly silty shelly sand and gravel with numerous cobbles and occasional boulders
(Gardline, 2011).
Of the ten most dominant species found during the environmental baseline survey for the
development, two were species of annelid polychaete (Spiophanes bombyx, Euclymene
oerstedii), three taxa of mollusca (Abra alba, Abra prismatica, Anomiidae sp.), two taxa of
crustacea (Urothoe elegans, Pisidia longicornis), one echinoderm taxa (Ophiura albida) and
two ascidian taxa (Dendrodoa grossularia, Ascidiella sp) (Gardline, 2011). Three of the most
dominant taxa recorded in the survey were also amongst the ten most dominant taxa in
comparative surveys (GEL, 2007, 2008b and Gardline 2008), suggesting that the faunal
community found within the Juliet survey was relatively typical for the wider area (Gardline,
2009b, Gardline 2011). None of the species listed in the top ten abundance ranking are
considered unusual for the region or sediment type and no evidence of biogenic reefs such as
those made by the tube dwelling polychaete Sabellaria spinulosa were observed during the
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 6 of 194
All GDF SUEZ E&P UK Ltd Contracts
environmental baseline survey for the Juliet field development (Gardline, 2009a, 2009b,
2008). The environmental baseline survey conducted in 2011 confirmed this, with the
univariate statistics suggesting that the macrofaunal community along the proposed pipeline
corridor was a reasonably variable community with moderate species richness and taxonomic
diversity (Gardline, 2011). This was as expected considering the variable nature of the
sediments across the surveyed area. The macrofaunal levels reported in the 2011 survey
were slightly less even and less species rich than the surrounding area (Gardline, 2008;
Gardline, 2009a). This difference in community is likely due to the influence that four
impoverished sampling stations had on the 2011 dataset within an area of large mobile sand
waves, which were not sampled in the previous Juliet to Pickerill A pipeline survey (Gardline,
2011).
Four species spawn in the vicinity of the proposed development area: lemon sole
(Microstomus kitt), sole (Solea solea), sandeels (Spisula sp.) and sprat (Sprattus sprattus). In
addition to spawning grounds, the waters of the development area also act as a nursery area
for lemon sole, sandeels, sprat and whiting (Merlangius merlangus).
The offshore waters of the southern North Sea are visited by several seabird species mainly
for feeding purposes. Among the species using the waters in the vicinity of the proposed Juliet
field development, fulmars are present in highest numbers during the early and late breeding
seasons, leading to peak densities in September. Increased numbers of gannets (Morus
bassanus) occur in November and December when dispersion from breeding sites is at a
maximum. Kittiwakes (Rissa tridactyla) are widely distributed throughout the year. Lesser
black-backed gulls (Larus fuscus) are mainly summer visitors, while in contrast guillemot (Uria
aalge) numbers are present in greatest numbers during winter months. In addition,
substantial numbers of terns (Sterna hirundo) migrate northwards through the offshore North
Sea in April and May, with return passage from July to September (DECC - SEA 2, 2001).
The JNCC ranks seabird vulnerabilities on a four point scale (one is the highest vulnerability
and four the lowest). Seabird vulnerability in Block 47/14 is highest (1 out of 4) during the
months of August, November and December and is moderately high (2 out of 4) during the
months of February, and September. Seabird vulnerability is moderate to low (3 or 4 out of 4)
throughout the remainder of the year. Seabird vulnerability in Block 47/15 is highest (1 out of
4) during the months of August, November and December and is moderately high (2 out of 4)
during the months of February, April, September and October. Seabird vulnerability is
moderate to low (3 or 4 out of 4) throughout the remainder of the year. Seabird vulnerability
in Block 48/11 is highest (1 out of 4) during the months of August and November and is
moderately high (2 out of 4) during the months of February, April, September, October and
December. Seabird vulnerability is moderate to low (3 or 4 out of 4) throughout the remainder
of the year (JNCC, 2009). As such, periods of concern for drilling are in place in Block 47/14
from August to October (DEFRA), and from November to December (JNCC).
The diversity of marine mammals in this area of the southern North Sea is relatively low with
only harbour porpoise sighted in the vicinity of the development area, predominantly during
the late summer months.
The proposed Juliet field development lies within ICES Rectangle 36F0. The highest tonnages
landed from this area by all vessels are crustaceans (lobster, crabs, shrimps), molluscs
(scallops, whelks). Other species fished include cod, mackerel, and whiting. The highest fish
landings by weight occur between April and November with comparatively lower landings being
obtained at all other times of the year. (MMO, 2009).
A shipping study and collision assessment of the Juliet development location was undertaken
in January 2012. There are an estimated 21,307 ships per year passing within 10nm of the
proposed Juliet location, corresponding to an average of 58 vessels per day, mainly
comprising of cargo vessels. Based on installing a Jack-up at the development location, the
annual collision frequency is estimated to be 7.5 x 10 -3, corresponding to a collision return
period of 133 years. This is well above the historical average ship collision frequency for
offshore installations on the UKCS which reflects the very high levels of traffic in the vicinity of
proposed Juliet Drilling Centre. The proposed drilling operation at the Juliet location will have
an impact on the closest passing routes, with vessels likely to adjust their passage to achieve
a clearance of typically 1-2nm from the rig (Anatec, 2012a).
A pipeline risk review was conducted for the Juliet development to Pickerill A Platform pipeline
route in January 2012. The proposed pipeline is in a busy shipping area with an average of 67
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 7 of 194
All GDF SUEZ E&P UK Ltd Contracts
ships per day within 10nm, with the majority being cargo vessels. The shipping density
analysis shows that the shipping activity over the pipeline is ranked as medium/high. There is
regular crossing traffic east/west between Humber/Germany and northwest/southeast
between Tees and Continental Europe, e.g., Rotterdam (Anatec, 2012b).
The Inner Dowsing, Race Bank and North Ridge candidate Special Area of Conservation (cSAC)
lies 15 kilometres to the south of the proposed Juliet development. This candidate SAC has
been considered by the UK Government and added to a list sent to the European Commission.
The Conservation of Habitats and Species Regulations 2010 now apply to this area.
The proposed Juliet development is approximately 37 kilometres to the east-north-east of the
nearest landfall at Theddlethorpe. Numerous protected sites lie along the nearest coastline
including Flamborough Head, The Wash & North Norfolk Coast and the Overstrands Cliff SACs.
The key environmental sensitivities arising from the review of the existing environment and
the proposed Juliet field development are:
Fish spawning area for lemon sole, sole, sandeels and sprat
Nursery area for lemon sole, sandeels, sprat and whiting;
Seabird vulnerability in Block 47/14 is very high during the months of August, November and December.
Seabird vulnerability in Block 47/15 is very high during the months of August, November and December
Seabird vulnerability in Block 48/11 is very high during the months of August and November.
Moderate densities of harbour porpoise in August and September, in addition to lower densities of this species during February and March;
Fishing activity occurs year round in the area, but effort is low compared to other areas of the southern North Sea, predominately concentrated on shellfish species;
Shipping densities are high, with traffic comprised predominantly of cargo vessels.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 8 of 194
All GDF SUEZ E&P UK Ltd Contracts
Seasonal Environmental Sensitivities
Activity in Blocks 47/14, 47/15 and 48/11 surrounding waters and adjacent coast
Component Abundance/Activity J F M A M J J A S O N D
Plankton Phytoplankton and zooplankton
Benthic
Fauna
Benthic faunal communities
Fish
Spawning
Herring
Lemon sole N N N N N
Sole
Sandeels N N N N
Sprat N N N N
Whiting N N N N N
Seabirds
(Offshore
Vulnerability)
Block 47/14 4 2 4 4 4 4 3 1 2 3 1 1
Block 47/15 4 2 3 2 3 4 3 1 2 2 1 1
Block 48/11 4 2 3 2 3 4 1 2 2 1 2
Cetaceans Harbour porpoise abundance
Resource
Users
Commercial fishing (36F0)
Shipping and ports
Military Activity (Block 47/11)
Military Activity (Block 47/15)
Military Activity (Block 48/11)
Oil and gas activity (inc. pipelines /
cables)
Marine Protected Sites
Coastal Protected Sites
Tourism, recreation & leisure
activities
Numbers refer to the seabird vulnerability index used by JNCC (1999) (1) highest vulnerability (4) lowest.
Coastal occurrence Activity in Blocks 47/14, 47/15 and 48/11 and surrounding
waters
Peak Low None Peak High Lo
w
None N Nursery
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 9 of 194
All GDF SUEZ E&P UK Ltd Contracts
HAZARDS, EFFECTS AND MITIGATION MEASURES
The environmental assessment of the Juliet field development indicates that the key hazards,
the resulting environmental effects, and the measures proposed by GDF SUEZ E&P UK to
mitigate those effects are as follows:
ROUTINE HAZARDS
Hazard & Effect(s) Effects and Mitigation Residual Impact
Physical Presence
Disruption to
other sea users
From the review of effect on navigation, it was concluded
that there are high volumes of traffic passing close to the
location. This can be divided into NW-SE traffic heading via
the Outer Dowsing Shoal and East-West traffic heading
to/from the Humber TSS. The proposed drilling operation at
the Juliet location will have an impact on the closest
passing routes, with vessels likely to adjust their passage
to achieve a clearance of typically 1-2nm from the rig.
(Anatec, 2012a)
During drilling operations a 500 metre exclusion zone will
be set up around the drilling rig. A dedicated standby
vessel will be present for the duration of the drilling
programme and will enforce the safety exclusion zone.
Any interference with fishing will be limited to temporary
restrictions around the drilling rig, installation vessels and the
potential for temporary displacement of static fishing gear
along the pipeline route. The pipeline and umbilical will be
buried in order to reduce the risk of potential damage to fishing
gear.
Pipeline installation and trenching will occur
simultaneously and therefore any impact due to
interference with shipping and fishing will be similarly short
term. During pipelay and dive Support Vessel (DSV) works,
a fishing representative will be hired by GDF SUEZ E&P UK
and will be on the vessels to liaise with the fishing vessels
in the area.
Prior to operations commencing, the appropriate
notifications will be made and maritime notices posted.
All vessel activities will be in accordance with national &
international regulations. Appropriate navigation aids will be
used to ensure other users of the sea are made aware of the
presence of vessels.
Negligible. The
work within the
exclusion zone is
expected to have
an effect on other
third parties
although only for
the duration of the
drilling programme.
Seabed
Disturbance
Caused by the
deposition of
cuttings,
disturbance from
installation of
pipeline and
umbilical and
from the footprint
of the rig.
It is estimated that drilling the Juliet development wells will
generate a maximum total of 2,036 tonnes of cuttings. 576
of these are associated with WBM, generated from drilling
the upper hole section of the wells, and will be discharged
directly to the seabed. The remaining 1,460 tonnes of
cuttings are associated with LTOBM from the lower sections
and will be skipped and shipped for processing onshore.
The deposition of cuttings and fine solids can have a direct
effect on seabed fauna. Trenching and placement of rock
dump as well as disturbance due to spud can penetration
can lead to disturbance and smothering of the seabed.
Spot rock dumping along the pipeline may be required if the
post-installation (out of straightness) survey shows remedial
dumping is required to mitigate upheaval buckling in specific
locations. Further rock dump is required at a permanent
subsea crossing location, where the new Juliet pipeline and
Negligible to Minor.
Benthic
communities found
in the area of the
proposed
development are
typical of this
region of the
southern North
Sea. Previous
studies have shown
that biological
communities will
recover rapidly.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 10 of 194
All GDF SUEZ E&P UK Ltd Contracts
ROUTINE HAZARDS
Hazard & Effect(s) Effects and Mitigation Residual Impact
umbilical crosses the existing CMS 26 inch export and 4
inch methanol pipelines. GDF SUEZ E&P UK is committed to
limiting the quantity of rock dumped to keep the impact on
the environment and other users of the sea to a minimum. It
is currently envisaged that a maximum of up to 23,000
tonnes may be required for spot rock dumping along the
Juliet development to the Pickerill A Platform pipeline and
umbilical route covering a total area of 4,600 square
metres. This assumes the rock will be placed at locations of
larger imperfections along the pipeline and the 23,000
tonnes will be laid as spot rock dumps along the proposed
route, apart from the permanent crossing location where an
estimated 2,800 tonnes is required. It has been assumed
that the minimum practical rock placement for the vessel is
2.5 tonnes per metre, which results in a minimum rock
dump height of approximately 0.3 metres based on a rock
berm slope of 30 percent.
The width of pipeline corridor has yet to be confirmed,
however it is envisaged that it will be in the order of
approximately 20 metres including the profile of trench and
spoil piles. A figure of 20 metres has been used as it
provides the maximum width a typical trenching device can
trench. Based on a 20 metre trench width and a 22
kilometre pipeline, the total envisaged footprint on the
seabed is estimated at 440,000 square metres.
As a worst case, therefore, the benthic infaunal communities
over the entire 440,000 square metres of the pipeline
impact corridor could be impacted by the trenching
operations.
Sediments and seabed communities will also be disturbed
around the footprint of the drilling rig at each well. The
placement of the spud cans of the jack-up rig on the seabed
will disturb localised areas and can be expected to impact
approximately 462 square metres per rig location, which
corresponds to 154 square metres at each spud can,
assuming a rig spud can diameter of 14.02 metres (46 feet).
This equates to a total seabed disturbance from the spud
can placement of 924 square metres from the Jack-up rig
positioning for this campaign.
However, effects on benthic organisms are expected to be
limited to a relatively small area around the drilling locations
and along the pipeline and umbilical route and to last for
only a short time period. In addition, from the grab samples
analysed, none of the species listed in the top ten
abundance ranking are considered unusual for the region or
sediment type and no evidence of biogenic reefs such as
those made by the tube dwelling polychaete Sabellaria
spinulosa were observed during the environmental baseline
survey (Gardline, 2011, 2009a, 2009b, 2008).
Noise & Vibration
Noise is thought
to have the
potential to
disturb or confuse
There will be a low number of additional vessel movements
during drilling and installation activities. GDF SUEZ E&P UK
will ensure that the vessels associated with the proposed
Juliet development will avoid using undue speed; cavitation
of vessel propellers will be minimised and vessels will not
Studies indicate
effects are likely to
be negligible.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 11 of 194
All GDF SUEZ E&P UK Ltd Contracts
ROUTINE HAZARDS
Hazard & Effect(s) Effects and Mitigation Residual Impact
cetaceans unnecessarily approach any marine mammals.
Atmospheric
Emissions
Emissions from
vessels required
for both drilling
and installation of
the development
facilities.
Emissions from
power generation
and well clean-up
Additional power generation emissions during installation
and drilling activities will be minimised by advanced
planning to ensure efficient operations, well maintained and
well operated equipment and generators, and regular
monitoring of fuel consumption.
No well test is planned.
GDF SUEZ E&P UK will ensure that high combustion
efficiency burners are used during well clean-up.
GDF SUEZ E&P UK will ensure that contract specification
and control processes require all equipment and generators
to be well maintained and operated.
Negligible. There
will be low local
effect and gases
disperse rapidly.
Emissions from gas
combustion will
contribute towards
global greenhouse
gas emissions.
Marine
Discharges
Will include
discharge of mud
& cuttings,
drainage water,
sewage, well
completion fluids,
hydrotest water
and production
chemicals.
Planned use of seawater and/or water based muds (WBM)
in the upper hole section of the wells with selection of most
environmentally benign mud and cement chemicals. 99
percent of the WBM is comprised of chemicals considered to
pose little or no risk to the environment. Installation of
cuttings / mud cleaning equipment will ensure optimal
cuttings cleaning and continuous mud mass balance will be
maintained throughout the drilling programme.
GDF SUEZ E&P UK will ensure good housekeeping standards
are maintained on the drilling rig to control the amount of
hydrocarbons & other contaminants entering the drainage
system & that appropriate sewage treatment systems are on
all vessels.
During the short duration of flowline hydrotest de-watering,
GDF SUEZ E&P UK will ensure that discharge rates are
controlled to allow maximum dispersion/ dilution.
All drilling & pipeline chemicals will be assessed using the
CHARM methodology where appropriate, in accordance with
the Offshore Chemicals Regulations 2002. Chemicals
identified to be high risk will be substituted for more
environmentally friendly alternatives where practicable.
Negligible. Due to
the low toxicity of
the majority of the
discharges & the
anticipated dilution
& dispersion, all
impacts are
predicted to be
short-term and
localised. Studies
indicate recovery of
benthos following
cuttings deposition
will occur within
months.
Solid Wastes
Wastes will
include OBM
cuttings, scrap
metal, waste oil &
surplus chemicals
Waste will be segregated by type and transported to shore to
be recycled or disposed of in a controlled manner under the
duty of care regulations (EPA 1990). Appropriate Waste Management practices, including provisions for Hazardous
Waste, will be applied by all contractors working on the Juliet
development. As far as reasonably practicable, materials
such as scrap metal, waste oil and surplus chemicals will be
sent for recycle or re-use. OBM contaminated cuttings will
be contained on the drilling rig and returned to shore for
processing and disposal by a licensed contractor. Other
waste will be sent to authorised landfills or incineration
facilities, depending on its nature.
Negligible. Wastes
will be treated
where appropriate.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 12 of 194
All GDF SUEZ E&P UK Ltd Contracts
NON-ROUTINE HAZARDS
Potential Spill
Source
Prevention & Mitigation Measures Taken
Leaks of drilling
mud
Procedural controls on transport and disposal. Transfer protocols similar to those
used for refuelling.
Diesel fuel
bunkering
All efforts shall be made to ensure the drilling rig arrives on site fully bunkered to
negate or reduce the need for diesel fuel bunkering during the project.
Transfer hoses and associated equipment will be inspected to ensure their
integrity. Bulk fuel transfer hoses will have non-return valves, refuelling hoses to
have dead man closures and floatation collars to be used on all hoses. Bunding
will be provided around each of the loading stations and around the main fuel oil,
tank vents on the main deck. Transfer hoses inspected prior to use and replaced
and regular intervals.
Offshore fuel and bulk transfer to the drilling rig will be supervised at all times and
communication links will be tested. All transfers to and from the rig / vessel plus
all internal transfers will be controlled by written work instructions. Fuel transfer
will be restricted to conditions of visibility that allow effective monitoring of the
loading operation and suitable weather conditions (which will be defined with
contractor prior to operations commencing).
Fuel transfer will be stopped if a spill occurs.
Oil, diesel &
aviation fuel and
chemical spills
during bunkering /
refuelling
Bunding to contain spills, spills on rig directed to hazardous drains or slop tanks,
on-board absorbent materials available on all vessels.
Oil spill during on-
board tank filling
Spills directed to the hazardous drains system, where oil will be removed by the
centrifuge or oil skimming apparatus or diverted to the slop/bilge tanks.
Rig storage tank
leaks
A clear record of the chemicals store will be maintained at all times and
compliance with OCR reporting requirements will be observed.
Tanks provided with appropriate bunding. Material directed to the hazardous
drains system, where oil will be removed by the centrifuge or oil skimming
apparatus.
Absorbents provided for spill management of diesel lube oil and stored chemicals.
All such spills directed to hazardous open drains system with trip and alarm
systems in place. Training will be given in spill clean-up techniques.
Special training will be given to personnel with the responsibility of operating
valves, and particularly dump valves. Training in the correct identification and
utilisation of these valves will be provided prior to their use, and awareness will be
raised on the importance of preventing spills.
Hazardous drains system will not be able to remove chemicals prior to discharge so
chemicals could be directed to slop/bilge tanks and taken to shore for treatment.
Procedure to minimise and prevent spills from draining and filling of heating and
cooling systems.
ENVIRONMENTAL MANAGEMENT
The management of environmental risks associated with the Juliet development is integral to
the decision making process. Environmental hazards are identified at all stages in the
development life cycle and risks are assessed and managed within GDF SUEZ E&P UKs Quality & Health, Safety and Environment Management System (QHSEMS).
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 13 of 194
All GDF SUEZ E&P UK Ltd Contracts
The QHSEMS clearly defines the environmental responsibilities of individuals at all levels of
the organisation and provides a framework through which a process of continual improvement
in the environmental awareness is implemented. The system ensures the application of
appropriate management controls thereby reducing any environmental risks arising from GDF
SUEZ E&P UKs operations.
Actions to ensure protection of the environment within this Environmental Statement will be
incorporated into an Environmental Program or Action Plan as defined within the management
system. It will be the responsibility of the Project QHSE team leader, with assistance from the
HSE Advisor, to ensure that these actions are implemented and completed during field
development. When the field goes into production, on-going monitoring and reporting will be
the responsibility of the host facility operator. GDF SUEZ E&P UK will monitor performance
over time to ensure that the production operations continue to meet the environmental
performance required by legislation and defined within this Environmental Statement.
CONCLUSIONS
In summary, although there will be some environmental impact during each phase of the Juliet
field life cycle, adverse long term environmental impacts from the Juliet developme nt will be
negligible. Incremental cumulative impacts of the development will be minimal and there will
be no transboundary effects.
GDF SUEZ E&P UK will manage any potential impacts through careful planning and design
controls.
Environmental management at GDF SUEZ E&P UK is undertaken in accordance with an
established and proven QHSE Management System, which is certified under ISO 14001. GDF
SUEZ E&P UK also has experience in this area of southern North Sea and therefore has a good
understanding of the environmental sensitivities in the vicinity of the Juliet field development.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 14 of 194
All GDF SUEZ E&P UK Ltd Contracts
ABBREVIATIONS
ACOPS Advisory Committee on Protection of the Sea
AIS Automatic Identification System
ALARP As Low as Reasonably Practicable
AoNB Areas of Outstanding Natural Beauty
AoSP Areas of Special Protection
API American Petroleum Institute
BAP Biodiversity Action Plan
BAT Best Available Technique
BERR Department for Business, Enterprise and Regulatory Reform
BGS British Geological Survey
BOP Blow-out Preventer
CAPEX Capital Expenditure
CEFAS Centre for Environment, Fisheries and Aquaculture Science
CEO Chief Executive Officer
CHARM Chemical Hazard Assessment and Risk Management
CO2 Carbon Dioxide
cSAC Candidate Special Area of Conservation
DECC Department of Energy and Climate Change
dB Decibel
dSAC Designated Special Area of Conservation
DST Drill Stem Test
DSV Diving Support Vessel
DTI Department of Trade and Industry
EC50 Effective Concentration for 50% of organisms
EMS Environmental Management System
EIA Environmental Impact Assessment
EPS European Protected Species
ERP Emergency Response Plan
ES Environmental Statement
EU European Union
FEED Front-End Engineering and Design
FPSO Floating Production, Storage and Offload (vessel)
GEL Gardline Environmental Limited
HMCG Her Majestys Coast Guard
HMCS Harmonised Mandatory Control Scheme
Hs Significant wave Height
HSE Health, Safety and Environment
HSS Health and Safety Standard
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 15 of 194
All GDF SUEZ E&P UK Ltd Contracts
ICES International Council for Exploration of the Seas
IRM Intervention and Routine Maintenance
IMO International Maritime Organisation
JNCC Joint Nature Conservation Committee
LTOBM Low Toxicity Oil Based Mud
LAT Lowest Astronomical Tide
LOS Line of Sight
LP Low Pressure
MAOP Maximum Allowable Operating Pressure
MCA Maritime and Coastguard Agency
MFA Marine Fisheries Agency
MoD Ministry of Defence
MRCC Maritime Rescue Co-ordination Centre
MW Mega Watts
nm Nautical Mile
NOx Nitrogen Oxides
No2 Nitrogen Dioxide
OBM Oil Based Mud
OCNS Offshore Chemical Notification Scheme
OCR Offshore Chemical Regulations
OGP Oil and Gas Producers
OGUK Oil & Gas United Kingdom (formerly UKOOA)
OPEP Oil Pollution Emergency Plan
OPEX Operational Expenditure
PHA Polycyclic Aromatic Hydrocarbons
PLONOR Posing Little Or No Risk (to the environment)
PNEC Predicted No Effect Concentration
pSAC (proposed) Special Areas of Conservation
QHSEMS Quality & Health, Safety and Environment Management System
ROV Remotely Operated Vessel
RSPB Royal Society for the Protection of Birds
SACs Special Areas of Conservation
SFF Scottish Fishermans Federation
SGMD Scottish Government Marine Directorate
SOx Sulphur Oxides
SPA Special Protection Area
SSSI Sites of Special Scientific Interest
SWT Scottish Wildlife Trust
TD Total Depth
TOC Total Organic Carbon
TOM Total Organic Matter
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 16 of 194
All GDF SUEZ E&P UK Ltd Contracts
THC Total Hydrocarbon Concentrations
UK United Kingdom
UKCS United Kingdom Continental Shelf
UKOOA United Kingdom Offshore Operators Association
WAT Wax Appearance Temperature
WBM Water Based Mud
WGS World Geodetic System
WPS Well Protection Structure
WHO World Health Organisation
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 17 of 194
All GDF SUEZ E&P UK Ltd Contracts
1.0 INTRODUCTION
1.1 THE PROJECT GDF SUEZ E&P UK Ltd (hereafter referred to as GDF SUEZ E&P UK) is planning to develop the Juliet gas field, located in Block 47/14b in the southern North Sea, approximately 37
kilometres to the east-north-east of the nearest landfall at Theddlethorpe. The nearest
transboundary line is the UK/Dutch line which lies approximately 148 kilometres to the east of
the proposed development location (Figure 1.1).
The Juliet development will consist of two subsea wells drilled local to each other and it is
intended that the two wells will be drilled from the same jack-up rig location. The wells will be
tied back via a single 12 inch export pipeline and controlled by an umbilical from the Pickerill
A Platform owned and operated by Perenco UK Ltd located approximately 22 kilometres east
of the Juliet field.
Reservoir fluids from the Juliet field will be exported to shore from the Pickerill A Platform via
the existing 24 inch Pickerill Theddlethorpe Pipeline into Theddlethorpe Terminal operated by Conoco Phillips. The Juliet subsea wells and infrastructure will be monitored, controlled
and operated on a day to day basis from the onshore control room at the Bacton Terminal
(Although Pickerill ties back to Theddlethorpe gas terminal, control is performed at Bacton) .
The two subsea horizontal development wells will be drilled local to the existing 47/14b-10
discovery well. One will target the west of the Juliet structure, the other the east. It is
anticipated that the wells will be drilled using a standard jack-up rig. Subject to necessary
consents and approvals, GDF SUEZ E&P UK plans a preliminary spud date programmed for
Q2/3 2013. Topsides construction phase is provisionally planned for Q3 2012 with subsea
construction in Q3 2013. First gas is currently anticipated in Q4 2013.
The design life of the Juliet field development facilities is fifteen years. On cessation of
production, the Juliet field development, including all associated infrastructure will be
abandoned in accordance with the legislation prevailing at the time and consultation w ith the
necessary authorities.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 18 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 1.1. Location of the Proposed Juliet Development
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 19 of 194
All GDF SUEZ E&P UK Ltd Contracts
1.2 SCOPE The Environmental Impact Assessment (EIA) carried out for the proposed Juliet development
has assessed the potential impacts on the existing environment in the southern North Sea for
all main phases of the hydrocarbon lifecycle: from drilling, through construction and
installation, to production operations and field decommissioning.
This Environmental Statement (ES) has been prepared to report the EIA, to ensure compliance
with the requirements of the Offshore Petroleum and Pipelines (Assessment of Environmental
Effects) Regulations, 1999 (as amended), and to meet GDF SUEZ E&P UKs QHSE Management System (refer to Section 5). An overview of the statutory fram ework applicable
to offshore oil and gas operations is included in Appendix A.
1.3 APPLICANT GDF SUEZ E&P UK has been active in the UK since 1997, growing rapidly through both
acquisition and active participation in the UK licensing rounds. GDF SUEZ E&P UK is an
established exploration and production operator in the UK, owning interests in more than fifty
offshore gas and oil licences on the UK continental shelf , distributed across West of
Shetlands, central and southern North Sea. The company has interest in fifteen producing
fields, of which the Minke is operated in the southern North Sea.
The UK forms a significant share of the global GDF SUEZ business and makes a significant
contribution to the Groups targets in securing gas supplies through production. As such GDF SUEZ is committed to developing its existing portfolio in the UK. The development of the Juliet
field fits within this target.
GDF SUEZ E&P UKs Health, Safety and Environmental (HSE) Policy is applied to all areas of activity and universally endorses health, safety and environmental excellence as a key
component of the operating philosophy and culture. HSE management is integrated into the
companys activities.
1.4 ENVIRONMENTAL IMPACT ASSESSMENT This Environmental Statement presents the results of the environmental assessment of the
proposed Juliet development. An environmental assessment is an important management
tool which ensures that environmental hazards and effects are identified, evaluated, and that
appropriate control measures are implemented.
The process comprised four main stages:
Characterise the environment and identify the environmental hazards associated with the activity;
Assess the magnitude and significance of the hazards and effects;
Implement control techniques to eliminate or lessen the severity of the effects and to manage the hazard;
Review and, where necessary, develop plans and procedures to manage the consequences of accidental events.
Consultations are undertaken throughout the environmental impact assessment process with
interested parties, including statutory consultees and non-governmental organisations (NGOs).
These consultations focus on potential environmental issues, project goals and environmental
strategies (refer to Section 1.5).
In practice, environmental control measures are an integrated part of planning operations and
in some instances are indirect benefits of other considerations. This environmental
assessment has been undertaken to confirm the effectiveness of standard engineering
controls and to identify specific circumstances that may warrant additional control measures.
This document addresses all offshore operations associated with the Juliet development.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 20 of 194
All GDF SUEZ E&P UK Ltd Contracts
1.5 CONSULTATIONS Prior to submission of this ES to the Department of Energy and Climate Change (DECC) the
views of a number of organisations were solicited by letter in November 2009 and September
2011. The issues raised during this preliminary consultation process have been considered in
detail by GDF SUEZ E&P UK and addressed, where appropriate, in the ES (refer to Table 1.1).
A meeting between GDF SUEZ E&P UK, DECC and the JNCC was held in September 2011 to
discuss the proposed Juliet development and progress so far.
Table 1.1. Summary of Responses Received During the Juliet Consultation Process
Organisation Issues Raised ES Section Reference
JNCC Proposed Inner Dowsing, Race Bank and
North Ridge possible Special Area of
Conservation (pSAC), which is located
south to the Juliet Field in the outer Wash
area should be discussed in the ES.
Section 3.7.2
DECC Juliet is close to an environmentally
sensitive area for birds. Discussion needs
to be included in the ES, although Juliet
development should not have any impact.
Rock dumping quantities and impacted
area should be fully discussed in the ES.
Section 3.6.4
Section 4.5.3
CEFAS The proposed development site lies within
a spawning area for lemon sole, sole,
sandeel and sprat. Due to the presence of
spawning sole, the field development will
be subject to timing restriction on seismic
activities between January and May
(inclusive).
The proposed development lies within
ICES Rectangle 36F0 and not 35F0.
Landings data for 36F0 in 2008 show that
Fishing by English registered vessels in
this block was high and mainly consisted
of potting for crabs, lobster and whelks,
and bottom trawling for whiting.
Section 3.6.3
Section 3.8.1
RWE The RWE Triton Knoll Windfarm
development area lies immediately south
of the Juliet development. The initial
indication is that no proximity agreement
will be needed as the nearest Triton Knoll
turbine location is sufficiently distant.
Consultation has been initiated and is
ongoing.
Section 3.8.7
Ministry of
Defence No Concern Section 3.8.3
National
Federation of
Fishermen's
Organisations
No response received at time of printing. N/A
Natural
England No response received at time of printing. N/A
Consultations and liaison with interested parties is a continuous part of the environmental
management process and will continue throughout the Juliet development.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 21 of 194
All GDF SUEZ E&P UK Ltd Contracts
1.6 STRUCTURE OF REPORT The report is presented in six main sections.
Section 1: Introduction provides a background to the project.
Section 2: The Proposed Development provides details of the proposed field development including project overview and option selection, installation of the facilities, drilling operations,
export of oil and decommissioning.
Section 3: Description of the Environment describes the background physical environmental characteristics in the southern North Sea, identifies the flora and fauna likely to be present
within the vicinity of the development and describes other sea users within this area.
Section 4: Environmental Hazards, Effects and Mitigation Measures identifies the potential interactions of the proposed development with the environment and details the control and
mitigation measures to be implemented to limit the impacts.
Section 5: Environmental Management provides an outline of how GDF SUEZ E&P UK will manage the project to ensure protection of the environment throughout the life of the
development.
Section 6: Conclusions of the Environmental Statement
In addition, the report includes a non-technical summary of the environmental assessment,
highlights its main conclusions, and provides a list of references used to obtain data and
information to support the assessment. Further information is also included in the
appendices.
1.7 CONTACT & INFORMATION REQUEST Any questions, comments or requests for additional information regarding the Environmental
Statement shall be addressed to:
EIA Co-ordinator
Environmental Management Team
Energy Development Unit
Department of Energy and Climate Change
4th Floor, Atholl House
86 88 Guild Street Aberdeen, AB11 6AR
Email: [email protected]
Fax: 01224 254019
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-06-EB-72-00001 Rev C1 Page 22 of 194
All GDF SUEZ E&P UK Ltd Contracts
This page is intentionally blank
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 23 of 194
All GDF SUEZ E&P UK Ltd Contracts
2.0 THE PROPOSED DEVELOPMENT
2.1 THE JULIET FIELD The Juliet field lies in Block 47/14b on the western flank of the southern gas basin,
approximately 22 kilometres west of the Pickerill A Platform operated by Perenco UK Ltd (refer
to Figure 2.1).
Figure 2.1. Juliet Field Location Map
The Juliet field is a dip closed structure that relies in part on a fault seal, notably at its north -
east flank. The fault seal separates the field from Amethyst East. The reservoir consists of
Aeolian dunes with secondary sandsheet and fluvial deposits of the Permian, Rotliegendes,
Lower Leman Sandstone Formation. The field top seal is provided by evaporates of the
overlying Zechstein Group. The general stratigraphy of the development area is shown in
Figure 2.2
The Juliet field is a dry gas discovery sourced from coals and shales of Westphalian and
Namurian age. The structure was discovered in 2008 by the 47/14b-10 well. This well flowed
gas at a sand constrained rate of 38 million standard cubic feet per day (mmscf/d) from a 20
foot interval of high quality sandstone. Reservoir fluid analysis of samples taken from the
47/14b-10 well indicates that the Juliet field contains gas with some condensate. Th e well
test observed an average condensate to gas ratio (CGR) of 12 barrels per million cubic feet of
gas (bbl/mmscf). No hydrogen sulphide was reported. Formation water can be expected from
both Juliet wells.
Further gas discovery potential in the region exists in a fault block adjacent to the field known
as Juliet West. This structure is believed to be separated from the Juliet field by a north
east/south west trending fault.
GDF SUEZ E&P UK is operator of the Juliet field with a net equity interest of 51.56%. First Oil
has a net equity of 29.44% and Hansa a net equity of 19.00%.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 24 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.2. Juliet Stratigraphic Column
2.2 DEVELOPMENT OBJECTIVE AND CONCEPT The objective of the project is to produce gas from the as yet undeveloped Juliet field and
export it to shore, using a combination of both new and existing infrastructure. The current
development plan is to drill two new horizontal wells into the structurally high areas of the
field to maintain the maximum standoff distance from the Gas Water Contact (GWC). The first
well will be drilled towards the west of the field and the second towards the east. The wells
will be tied back to the Perenco UK Ltd operated Pickerill A Platform, located in Block 48/11,
via an approximately 22 kilometre long 12 inch export pipeline and control umbilical.
The Juliet export pipeline will be a fully rated carbon steel pipeline. The Juliet flowline will be
routed between the manifold and the new risers on Pickerill A. The flowline will tie-in to the
Pickerill A Platform riser via a spool tied in to a new riser.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 25 of 194
All GDF SUEZ E&P UK Ltd Contracts
From the Pickerill A Platform, gas from Juliet will be exported onshore to the Conoco Phillips
Theddlethorpe terminal via the existing pipeline from the Pickerill field. On entering the
terminal the gas from Pickerill is processed and any condensate and water separated. The
gas stream is then metered before mixing with other gases and undergoing further processing
in dewpointing and condensate stabilisation facili ties. Gas is then fed into the National Grid
and condensate sent to the Humber Oil Refinery.
The Juliet wells will be monitored by individual gas flow meters and data transmitted through
topside equipment and then by Line of Sight (LOS) to the onshore Bacton terminal. Controls to
the Juliet wells will be via a newly installed control umbilical between the wells and the
Pickerill A Platform. The control umbilical will also carry production chemicals for injection at
each well.
This ES considers the following phases of development:
Offshore Facility Installation and Commissioning
Installation of the Juliet subsea wellheads and protective fishing friendly structures;
Installation of approximately 22 kilometre 12 inch flexible carbon steel pipeline and control umbilical from the Juliet subsea wells to the Pickerill A Platform;
Testing and commissioning of Juliet wellheads, export pipeline and umbilical;
Topsides modifications on Pickerill A Platform.
Development Drilling
The drilling of the Juliet Eastern well (47/14b-J1) from surface location 53033 13.51 North and 0045 20.832 East, targeting the West zone of the Juliet reservoir;
The drilling of the Juliet Western well (47/14b-J2) from surface location 53033 13.26 North and 0o45 21.28 East, targeting the East zone of the Juliet reservoir;
Completion and clean-up of the Juliet development wells.
Production and Maintenance
Export of the Juliet reservoir reserves to the Pickerill A Platform;
Maintenance of facilities.
Decommissioning
Decommissioning of facilities.
These elements, together with a description of the proposed facilities and schedule for
development, are discussed in the following sections.
2.3 DEVELOPMENT OPTION SELECTION Several options were considered for the export route and a screening study undertaken to
identify the option which presented the least risk to the project (GDF Suez E&P UK Ltd, 2011).
To summarise, elements considered as part of the screening study included:
Environmental and safety issues;
Overall capital expenditures (CAPEX) and operational expenditures (OPEX);
Commercial issues;
Technical complexity; and
Schedule.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 26 of 194
All GDF SUEZ E&P UK Ltd Contracts
The options considered included:
Several export routes via mechanical tie-in (subsea and platform);
Several export routes via hot tap (platform only); and
Direct tie-back to the beach (platform only).
An option screening study was undertaken to identify all potential offtake routes for Juliet
fluids. The methodology consisted of a number of important steps prior to final screening and
selection evaluation. These were as follows:
Identification of export route options;
Identify HSE and technical risks associated with each of the options;
Perform preliminary flow assurance work for pipe sizing for each of the export route options;
Determine the likely topsides modifications works associated with each of the export route options;
Produce capital expenditures (CAPEX) and operational expenditure (OPEX) estimates for each of the proposed development options and perform economics on those;
Perform a series of evaluation workshops to determine the preferred export and development type which best suits the Juliet development;
Identify a preferred solution and progress risk based assessments on schedule, costs and HSE criteria;
Produce a high level project execution plan for the project based on the preferred option.
The major technical issues for the Juliet development concept were as follows:
Selection of the number and types of wells - two horizontal wells have been selected based upon initial subsurface work. Technical review concluded that the wells should
be horizontal completions.
Drilling of the wells initial technical review indicated that the wells should be drilled from a single location. Moreover, the existing suspended 47/14b-10 well will not be
side tracked.
One of the key drivers towards the development type (subsea or platform) was the likelihood and type of intervention required. Whether Juliet could be developed through
the use of subsea completions or a wellhead tower.
The initial host options screening considered all local gas infrastructure in the vicinity of Juliet.
The options considered included tie-backs to surrounding platforms, hot tapping into export
pipelines and a direct tie-back to an onshore terminal. However, most of the options
considered were discounted during the concept selection due to High CAPEX and OPEX costs,
environmental impacts, safety concerns and commercial difficulties.
Following the loss of the Amethyst export route in the desired timeframe, an appraisal of the
options the project was recycled back to concept select with consideration given to the
following options:
Subsea development tied back to Pickerill A Platform
Tie into one of the other platforms in the surrounding area (platforms up to 50 kilometres from Juliet wells were considered)
Hot tap into one of the main export routes in the vicinity.
Tieback to the beach
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 27 of 194
All GDF SUEZ E&P UK Ltd Contracts
Whilst all of these have previously been considered, the project revisited all options to identify
a clear export route and development type which limits HSE and commercial risks whilst
achieving as early a first gas date as possible.
The methodology followed to reach a final development concept consisted of a number of
important steps prior to this final screening and selection evaluation. These were as follows:
Identification of export route options.
Perform preliminary flow assurance work for pipe sizing for each of the export route options.
Determine the likely topsides modifications works associated with each of the export route options.
Commence and progress (where possible) commercial agreements with each of the export route owners.
Produce CAPEX and OPEX estimates for each of the proposed development options and perform economics on those.
Identify HSE and technical risks associated with each of the options.
Perform a series of evaluation workshops to determine the preferred export and development type which best suits the Juliet development.
Identify a preferred solution and progress risk based assessments on schedule, costs and HSE criteria.
Produce a project execution plan for the project based on the preferred option.
The conclusion of this work has identified the following preferred option for the Juliet
development which represents the least risk in terms of HSE, schedule, cost and technical
difficulty:
Two new horizontal wells completed with sand screens.
A Subsea Development located in 56 metres water depth.
Tieback to the existing Pickerill A Platform
Following the concept selection stage, the following tie-back type was selected.
Pickerill A Platform (Figure 2.3)
Table 2.1 presents the reasons why this export route was chosen.
Table 2.1. Selected Route
Develop
ment
Type
Export
Route
Distance
from
Juliet
Facilities/
Technical/Cost Environmental
Subsea Pickerill A
Riser
22 km Lowest CAPEX and OPEX cost
Least topsides modifications
required
Not the shortest pipeline tie-back
however the Amethyst A2D
platform was
unavailable for
the Juliet works.
Least amount of offshore construction activity therefore
reduces environmental impact
As there is no new platform with this type of development there
is less operational HSE risks
associated with ship collision,
helicopter travel etc
No significant environmental issues with the seabed along
the proposed route
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 28 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.3. Pickerill A (Subsea)
As shown in Table 2.1, the Pickerill A Platform with new 12 inch riser tieback option (Figure
2.3) was the preferred development option. The following bullet points detail the key reaso ns
for this.
Subsea Development
The Juliet proposed well locations are in an area of high density shipping, with a major shipping lane routing though the area. The addition of a new platform in this area
would cause a significant potential shipping impact risk. This could potentially result in
the need for a new shipping lane route which would be problematic given the existing
platform infrastructure in this area;
Installation of a new platform would add operational hazards including additional risks from ship collision, helicopter traffic, occupational hazards from operating a new
platform etc. There is also additional risks from a construction perspective during the
installation of the platform;
Less CAPEX and OPEX costs for the development, making it more economical.
Less scheduling risk a subsea option is less complex and therefore installation is more straight forward;
It is expected that minor intervention works on the wells is possible later in the field life of Juliet. These interventions will require a drill rig irrespective as the platform type
considered would have been a small unmanned platform, which could not support
intervention works.
Piggybacking the umbilical to the pipeline was considered but was not technically feasible due to the nature of the seabed sediments along the route.
24 63km Pickerill Theddlethorpe
Pipeline
22km 12 Juliet Pickerill Flowline
and Umbilical
THEDDLETHORPE
Juliet Subsea Wells
2 Wells + 1
Spare
Pickerill A
Tie-in via new 12 Riser
26 CMS pipeline
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 29 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.4. Justification diagram for tieback to Pickerill A Platform
2.4 PROPOSED PROJECT SCHEDULE A provisional project schedule for the Juliet development is shown in Table 2. 2. This
programme may change subject to detailed scheduling and, in particular, availability of the
drilling rig and the fabrication times of various key elements.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 30 of 194
All GDF SUEZ E&P UK Ltd Contracts
Table 2.2. Preliminary Schedule for key Project Milestones
Task 2012 2013
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
FEED and
Detailed design
Subsea/Topsides
Detailed Design
Installation
Engineering
Topside
Construction
Phase 1
Development
Drilling
Topside
Construction
Phase 2
Subsea
Installation
First gas
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 31 of 194
All GDF SUEZ E&P UK Ltd Contracts
2.5 PRODUCTION AND EXPORT FACILITIES
2.5.1 Juliet Subsea Facilities
The Juliet subsea facilities will comprise two subsea wells tied into a subsea manifold. The
most likely tie-back option and subsea facilities are shown in Figure 2.5. However, the design
is subject to change once additional engineering studies have been completed. Consideration
will be given to a subsea wet gas meter which will be housed in the manifold. The control
umbilical will come from the Pickerill A Platform and will carry corrosion inhibitor and hydrate
inhibitor and have a wash water injection core for potential Halite treatment. Juliet controls
will be electro-hydraulic and will utilise as much of the existing controls and hydraulic power
as possible to minimise topsides modifications.
Figure 2.5. Diagram of Juliet subsea facilities
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 32 of 194
All GDF SUEZ E&P UK Ltd Contracts
2.5.2 Gas Export Pipeline and Umbilical
Gas and associated reservoir fluids will be exported from the Juliet development wells via a
new 22 kilometre, 12 inch carbon steel pipeline and tied to the base of a new riser, subsea
(Figure 2.6). A new riser will be installed on the platform. A new J Tube will also be installed
which will house the control umbilical.
Fabricated spool pieces will connect the export pipeline and umbilical to the manifold. The
control umbilical will be terminated subsea with a Subsea Umbilical Termination Unit (SUTU)
which will be housed in the manifold. The manifold will also have rigid pipe work for chemical
injection requirements.
The Juliet export pipeline will have a nominal wall thickness of 20.6 millimetres (wall
thickness to be confirmed during FEED and detailed design). The pipe on the bends and the
tie-in spools may be thicker; however this will be confirmed during a later stage of the Juliet
development.
Chemical injection will be from the Pickerill A Platform via dedicated cores within the control
umbilical. Continuous injection of corrosion inhibitor will be required to protect the carbon
steel pipeline, riser and manifold pipe work.
There will be continuous methanol dosing to inhibit hydrate formation during normal
operations. There may be a requirement for a higher rate of dosing during the start up period.
All chemicals discharged will meet the requirements of the Offshore Chemicals (Amendment)
Regulations, 2011 and will be subject to a PON 15C permit under this legislation .
Consideration will be given to a wet gas meter within the manifold to meter production from
each of the wells.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 33 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.6. Juliet Subsea Location and Proposed Export Pipeline / Umbilical Route
(Source GdF)
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 34 of 194
All GDF SUEZ E&P UK Ltd Contracts
2.5.3 Host Facility
The Pickerill A Platform is located approximately 22 kilometres to the west of the Juliet
development. Perenco is the operator of the Pickerill field, situated in Block 48/11 with both
the Pickerill A and Pickerill B platforms which flow gas through a dedicated pipeline to the
terminal at Theddlethorpe.
Subsea inspection and maintenance is the responsibility of GDF SUEZ E&P UK. Maintenance
of the topsides and riser will be the responsibility of the Pickerill owners, Perenco. However, it
is likely that the inspection of the Subsea infrastructure will be performed by GDF SUEZ E&P
UK as part of an overall inspection programme and any remedial works required will be
performed by GDF SUEZ E&P UK.
The offshore modifications to the Pickerill platform will be undertaken by Perenco wi th
assistance from Juliet owners. The offshore work is envisaged to be carried out during
summer 2012 and Q2/3 2013.
The Juliet flowline will be routed between the manifold and the new risers on Pickerill A. The
selection of the Pickerill A allows for a new riser and J tube to be installed on the platform.
This minimises any concerns over integrity of tying into existing risers. By allowing for a new J
tube, previous concerns over the spare J tube mean that there are fewer restrictions on the
umbilical size.
Currently tie-in of the Juliet pipeline to the Pickerill A riser will come from the west, as
illustrated in Figure 2.7.
No offshore gas processing, water or condensate separation will occur on Pickerill A for the
Juliet gas stream. All processing of Juliet fluids will occur onshore at the Theddlethorpe
terminal.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 35 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.7. Pickerill A Platform Approach
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 36 of 194
All GDF SUEZ E&P UK Ltd Contracts
Host Platform Modifications
Modifications on the Pickerill A Platform required to enable Juliet gas to be processed are as
follows:
Controls tie-in;
Extension of the chemical injection system.
New riser
Pipework tie-in
J-tube
As far as possible the existing controls/Hydraulic Power Units (HPU) will be utilised for the
Juliet development to minimise the modifications required.
The control umbilical will come from the Pickerill A platform and will have a wash water
injection core for halite treatment and will also carry corrosion and hydrate inhibitor. HPUs,
topsides umbilical termination units (TUTU), and chemical injection equipment will be required
to be installed at the Pickerill A platform in addition to communications equipment.
Topsides modifications will include:
The installation of a new riser and J tube to the jacket of the platform. The riser will terminate in a topsides Emergency Shutdown Valve (ESDV) located on a new
sub cellardeck access platform to facilitate access to the ESDV, pig receiver, and
control umbilical termination point.
The Julliet flowline will go up to a new allocation flowmeter and eductor (a type of jet pump) located on a new cantilever platform at the cellar deck level.
Pickerill A & B export line to entrain the Pickerill gas in the co-mingled export flowline, which will be connected to the existing export pipeline to Theddlethorpe.
The Juliet wellhead pressures at the commencement of the Juliet field production life are such that there is a high risk of hydrate formation at the wellhead. To mit igate
against this, the Juliet development will re-commission the mothballed methanol
system on Pickerill A. This system is not capable of supplying methanol to the
upstream side of the subsea choke due to the high gas pressure at the start of field
life, therefore the project will install a methanol booster pump to be used during start -
up to address this requirement. This pump will be installed on the cellar deck
adjacent to the existing methanol facilities.
The installation of a new hydraulic power unit (HPU) located on the upper weather deck for topsides and subsea control motive requirements.
Control of all the new Juliet equipment will be achieved, utilising or augmenting the existing
systems on Pickerill A together with Perenco's onshore control room in Bacton. It should be
noted that notification for construction works for the Subsea and topsides works wil l be done
as separate applications.
2.6 OFFSHORE CONSTRUCTION AND INSTALLATION
2.6.1 Pipeline and Umbilical Installation
Pipelay
A rigid reel lay vessel will be commissioned to undertake pipelay operations. The vessel will
be a dynamically positioned offshore construction ship.
The pipeline and umbilical will be laid in separate trenches, approximately 30 metres apart.
Installation of the pipeline will be carried out by two or three reel lay type vessel.
Pipelay operations are expected to take approximately 14 days to complete (not including
mobilisation, demobilisation, transit or weather down time). During this time the pipelay
vessel will lay the pipeline on the seabed ready for trenching.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 37 of 194
All GDF SUEZ E&P UK Ltd Contracts
On completion of pipelay operations a post lay survey will be undertaken to identify the status
of the installed pipelines and debris incidence. This will take approximately one day to
complete. A pipeline systems strength test, lasting one day will be carried out on the newly
installed pipeline to ensure that it has not been damaged during the installation process. This
will be undertaken from either the pipelay vessel or a dedicated survey vessel.
Trenching
Pipeline trenching operations will employ a pipeline plough or mechanical trenching device
which will be supported from a trenching vessel. During normal operations the plough or
mechanical trenching device will deposit the excavated trench spoil either side of the trench.
The trench will then be mechanically backfilled in a separate operation. Once the pipelay and
backfilling operation have been completed a post lay survey will be carried out.
It is anticipated that the pipeline trench will be approximately one metre deep, allowing the
pipeline and umbilical to be buried below the natural seabed level to a depth sufficient to
ensure at least 0.6 metres cover over the top of the pipe. This figure has been chosen to
minimise upheaval buckling and subsequently the need for rock dumping. The pipeline
corridor width has yet to be confirmed, however it is envisaged that it will be in the order of
approximately 20 metres, including the profile of trench and spoil piles. This figure of 20
metres has been used as it provides the maximum width a typical trenching device can trench.
Given a 20 metre trench width a total effected footprint on the seabed of 440,000 square
metres, based on a 22 kilometre pipeline, is envisaged.
For the trenching of the umbilical it is assumed that a 0.75 metre trench corridor will be
required for the entire 22 kilometre umbilical line. A tota l effected footprint on the seabed of
A 16,500 square metres is therefore expected.
The pipeline route survey found that along the majority of the pipeline route seabed sediments
comprise of intermittent layers of very loose to medium dense slightly silty sand with extensive
chalk outcrops with numerous cobbles and boulders also present. There are also small areas ,
approximately half way along the route, where the seabed comprises loose to medium silty
sand with occasional shell fragments. Towards the landward end of the pipeline route seabed
sediments comprised of very loose to medium silty sand with occasional gravel, and numerous
cobbles and boulders, becoming less gravelly and with fewer boulders as the seabed shoals
(Gardline, 2011). These different sediments will be considered when installing the pipeline
however they are not considered to pose an issue with the installation of the pipeline, any
boulders over 0.4 metres will be displaced if necessary. Trenching and backfilling operations
are expected to take a total of nine days to complete.
Spot rock dumping along the pipeline may be required if the post -installation (out of
straightness) survey shows remedial dumping is required to mitigate upheaval buckling in
specific locations (Figure 2.8). Further rock dump will be required at a permanent subsea
crossing location, where the new Juliet pipeline and umbilical crosses the existing CMS 26
inch export and 4 inch methanol pipelines (PL929 & PL930 respectively). GDF SUEZ E&P UK
is committed to limiting the quantity of rock dumped to keep the impact on the environment
and other users of the sea to a minimum. It is currently envisaged that a maximum of up to
23,000 tonnes may be required for spot rock dumping along the Juliet development to the
Pickerill A Platform covering a total area of 4,600 square metres. This assumes the rock will
be placed at locations of larger imperfections along the pipeline and the 23,000 tonnes will
be laid as spot rock dumps along the proposed route, apart from the permanent c rossing
location where an estimated 2,800 tonnes is required. It has been assumed that the minimum
practical rock placement for the vessel is 2.5 tonnes per metre, which results in a minimum
rock dump height of approximately 0.3 metres based on a rock berm slope of 30 percent.
23,000 tonnes is currently an initial worst case estimate of the quantity of rock which will be
dumped along the proposed pipeline route and has been calculated based on the sediments
found over the Juliet development location to Pickerill A pipeline route and previous rock
dumping experience within the vicinity of the proposed development. The total predicted rock
volume and tonnage will be revisited during detailed design and will be included as part of the
pipeline works authorisation.
-
Classification - Extended
GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement
JF00-01-EB-108-00001 Rev C1 Page 38 of 194
All GDF SUEZ E&P UK Ltd Contracts
Figure 2.8. Example of a Spot Rock Dumping Operation over a Fallpipe (AoD, 2009)
Pipeline and Umbilical Tie-Ins
Fabricated spool-pieces