Juliet Environmental Statement 2012

196

Transcript of Juliet Environmental Statement 2012

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 1 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    STANDARD INFORMATION SHEET

    Project Name Juliet Field Development

    DECC Project Reference No. D/4136/2012

    Type of Project Field Development subsea tie-back to existing infrastructure

    Undertaker Name GDF SUEZ E&P UK Ltd

    Undertaker Address 40 Holborn Viaduct, London, EC1N 2PB

    Licences/Owners GDF SUEZ E&P UK Ltd

    Short Description GDF SUEZ E&P UK Ltd is planning to develop the Juliet field

    located in Block 47/14b in the southern North Sea. The

    proposed development lies approximately 37 kilometres to

    the east-north-east of the nearest landfall at Theddlethorpe.

    The nearest transboundary line is the UK/Dutch line which

    lies approximately 148 kilometres to the east of the

    proposed development location. License partners include

    GDF SUEZ E&P UK Ltd, the operator (51.56%), and First Oil

    Expro Ltd (29.44%) and Hansa (19.00%).

    The objective of the project is to produce gas from the as yet

    undeveloped Juliet field and export it to shore, using a

    combination of both new and existing infrastructure. This

    will be achieved by drilling two horizontal subsea wells local

    to the 47/14b-10 discovery well.

    The Juliet subsea wells will be tied back by an export

    pipeline and umbilical to the Pickerill A Platform operated by

    Perenco UK Ltd, located approximately 22 kilometres to the

    east of the Juliet field. Existing infrastructure will be used to

    transport the Juliet gas from the Pickerill A Platform to the

    onshore Theddlethorpe terminal.

    The proposed Juliet development wells are expected to be

    drilled using a standard jack-up rig, with the preliminary

    spud date provisionally programmed for Q2/3 2013.

    Topsides construction phase is provisionally planned for Q3

    2012 with subsea construction in Q3 2013. First gas is

    currently anticipated in Q4 2013.

    Anticipated Commencement of Works Q3 2012

    Previously Submitted Environmental

    Documents

    PON15B for the Juliet (47/14b-10) exploration well

    (DECC Ref No. PON15B/105)

    The Juliet Field Development Environmental Statement

    (DECC Ref No. D/4063/2009)

    Significant Environmental Impacts

    Identified

    None

    Statement Prepared By GDF SUEZ E&P UK Ltd in association with RPS Energy.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 2 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    TABLE OF CONTENTS

    NON-TECHNICAL SUMMARY 5

    1.0 INTRODUCTION 17

    1.1 THE PROJECT 17

    1.2 SCOPE 19

    1.3 APPLICANT 19

    1.4 ENVIRONMENTAL IMPACT ASSESSMENT 19

    1.5 CONSULTATIONS 20

    1.6 STRUCTURE OF REPORT 21

    1.7 CONTACT & INFORMATION REQUEST 21

    2.0 THE PROPOSED DEVELOPMENT 23

    2.1 THE JULIET FIELD 23

    2.2 DEVELOPMENT OBJECTIVE AND CONCEPT 24

    2.3 DEVELOPMENT OPTION SELECTION 25

    2.4 PROPOSED PROJECT SCHEDULE 29

    2.5 PRODUCTION AND EXPORT FACILITIES 31

    2.5.1 JULIET SUBSEA FACILITIES 31

    2.5.2 GAS EXPORT PIPELINE AND UMBILICAL 32

    2.5.3 HOST FACILITY 34

    2.6 OFFSHORE CONSTRUCTION AND INSTALLATION 36

    2.6.1 PIPELINE AND UMBILICAL INSTALLATION 36

    2.6.2 JULIET SUBSEA INSTALLATION 39

    2.7 DRILLING OPERATIONS 40

    2.7.1 OVERVIEW 40

    2.7.2 DRILLING RIG 41

    2.7.3 WELL CONSTRUCTION 42

    2.7.4 DRILLING MUDS AND CHEMICALS 43

    2.7.5 DISPOSAL OF DRILL CUTTINGS 43

    2.7.6 WELL COMPLETION 44

    2.7.7 INITIAL WELLBORE CLEANING & FINAL WELL CLEAN-UP AND TESTING 44

    2.7.8 SUPPORT OPERATIONS 45

    2.7.9 TOTAL DRILLING EMISSIONS SUMMARY 45

    2.8 PRODUCTION 47

    2.8.1 PREDICTED GAS PRODUCTION 47

    2.8.2 POWER GENERATION 51

    2.8.3 PRODUCTION CHEMISTRY 51

    2.8.4 CHEMICAL INJECTION 51

    2.8.5 SAND PRODUCTION 51

    2.9 MAINTENANCE 52

    2.10 DECOMMISSIONING 52

    2.11 FUTURE DEVELOPMENT 52

    3.0 ENVIRONMENTAL DESCRIPTION 53

    3.1 INTRODUCTION 53

    3.1.1 DATA SOURCES 53

    3.2 GEOGRAPHY 56

    3.3 THE SEABED AND BATHYMETRY 57

    3.3.1 BATHYMETRY 57

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 3 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    3.3.2 SEDIMENTS AND SEABED FEATURES 59

    3.3.3 HYDROCARBON CONCENTRATIONS 70

    3.4 OCEANOGRAPHY 70

    3.4.1 WAVES 70

    3.4.2 PHYSICAL CHARACTERISTICS 71

    3.5 AIR AND CLIMATE 72

    3.5.1 WIND 72

    3.5.2 AIR QUALITY 73

    3.6 FLORA AND FAUNA 73

    3.6.1 PLANKTON 73

    3.6.2 SEABED COMMUNITIES 73

    3.6.3 FISH 74

    3.6.4 SEABIRDS 78

    3.6.5 MARINE MAMMALS 82

    3.6.6 MARINE REPTILES 85

    3.7 PROTECTED AND SENSITIVE COASTAL HABITATS 85

    3.7.1 COASTAL PROTECTED SITES 85

    3.7.2 MARINE PROTECTED AREAS 89

    3.8 HUMAN POPULATIONS 94

    3.8.1 COMMERCIAL FISHING 94

    3.8.2 SHIPPING AND PORTS 96

    3.8.3 COLLISION RISK ASSESSMENT 99

    3.8.4 MILITARY ACTIVITY 99

    3.8.5 PIPELINES, WELLS AND SUBMARINE CABLES 99

    3.8.6 DREDGING AND DUMPING ACTIVITY 101

    3.8.7 WIND FARMS 103

    3.8.8 ARCHAEOLOGY 104

    3.8.9 TOURISM AND LEISURE 105

    3.9 KEY ENVIRONMENTAL SENSITIVITIES 105

    4.0 ENVIRONMENTAL HAZARDS, EFFECTS AND MITIGATION MEASURES 107

    4.1 INTRODUCTION 107

    4.2 IDENTIFICATION OF INTERACTIONS 108

    4.3 DESIGN CONTROL MEASURES 109

    4.4 PHYSICAL PRESENCE 110

    4.5 SEABED DISTURBANCE 112

    4.5.1 SEABED DISTURBANCE RESULTING FROM PIPELAY INSTALLATION 112

    4.5.2 SEABED DISTURBANCE RESULTING FROM DRILLING OPERATIONS 114

    4.5.3 FOOTPRINT OF THE JACK-UP RIG 115

    4.5.4 RIG STABILISATION 115

    4.5.5 SEABED DISTURBANCE SUMMARY 116

    4.6 NOISE AND VIBRATION 116

    4.6.1 POTENTIAL IMPACT ON FISH 117

    4.6.2 POTENTIAL IMPACT ON CETACEANS 118

    4.7 ATMOSPHERIC EMISSIONS 119

    4.7.1 DRILLING AND INSTALLATION PHASES 119

    4.7.2 ATMOSPHERIC EMISSIONS DURING PRODUCTION OPERATIONS 122

    4.8 MARINE DISCHARGES 122

    4.8.1 WATER BASED DRILLING MUD (WBM) 122

    4.8.2 COMPLETION FLUIDS 123

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 4 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    4.8.3 PIPELINE COMMISSIONING 123

    4.8.4 DRAINAGE WATER AND SEWAGE 124

    4.9 SOLID WASTES 124

    4.10 LOSS OF CONTAINMENT 124

    4.10.1 OIL SPILL SCENARIOS AND HISTORICAL UKCS SPILL DATA 124

    4.10.2 OFFSHORE CONSTRUCTION AND INSTALLATION 126

    4.10.3 DRILLING OPERATIONS 126

    4.10.4 PRODUCTION AND MAINTENANCE 132

    4.11 DECOMMISSIONING 132

    4.12 TRANSBOUNDARY IMPACTS 133

    4.13 CUMULATIVE IMPACTS 133

    5.0 ENVIRONMENTAL MANAGEMENT 137

    5.1 INTRODUCTION 137

    5.2 GDF SUEZ E&P UKS QHSEMS 137

    5.2.1 INTRODUCTION 137

    5.2.2 STRUCTURE AND GOALS 137

    5.2.3 HSE POLICY 138

    5.3 ORGANISATION 141

    5.3.1 KEY ROLES & RESPONSIBILITIES 141

    5.4 JULIET DEVELOPMENT MANAGEMENT PROCESSES 141

    5.4.1 ASSESSMENT 141

    5.4.2 PLANNING AND RESOURCING 142

    5.4.3 AUDIT AND REVIEW 142

    5.5 SUMMARY OF ENVIRONMENTAL COMMITMENTS 143

    6.0 CONCLUSIONS 145

    7.0 REFERENCES 149

    APPENDIX A: STATUTORY FRAMEWORK 153

    APPENDIX B: DRILLING OPERATIONS SUPPORTING INFORMATION 156

    APPENDIX C: OCNS & HMCS 161

    APPENDIX D: AIR QUALITY DATA 174

    APPENDIX E: ATMOSPHERIC DISPERSION MODELLING 177

    APPENDIX F: SEABED FEATURES ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE

    2009A) 179

    APPENDIX G: SEABED IMAGERY ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE,

    2009A) 182

    APPENDIX H: SEABED IMAGERY ALONG THE JULIET PIPELINE ROUTE AND WELL SITE (GARDLINE, 2011)

    185

    APPENDIX I: JULIET DEVELOPMENT TO PICKERILL A PLATFORM PIPELINE ROUTE IN RESPECT TO THE

    TRITTON KNOLLL WINDFARM BOUNDARY 188

    APPENDIX J: PRODUCTION FIGURES 189

    APPENDIX K: SEABED SAMPLE LOCATIONS FOR 2011 SEABED SURVEY 194

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 5 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    NON-TECHNICAL SUMMARY

    BACKGROUND

    GDF SUEZ E&P UK Ltd (hereafter referred to as GDF SUEZ E&P UK) is planning to develop the Juliet gas field, located in Block 47/14b in the southern North Sea gas basin. This

    Environmental Statement (ES) has been produced in order to meet the requirements of the

    GDF SUEZ E&P UK Quality, Health, Safety and Environment Management System and to

    ensure compliance with the Offshore Petroleum Production and Pipelines (Assessment of

    Environmental Effects) (Amendment) Regulations 2007. It has been prepared by GDF SUEZ

    E&P UK in conjunction with environmental consultants RPS Energy.

    PROJECT OVERVIEW

    The Juliet development will consist of two horizontal subsea wells local to the 47/14b-10

    discovery well. The wells will be tied back to the Pickerill A Platform operated by Perenco UK

    Ltd, approximately 22 kilometres to the east of the proposed Juliet development via a 12 inch

    export pipeline and control umbilical. Existing infrastructure will be used to transport the Juliet

    gas from the Pickerill A Platform to Theddlethorpe terminal onshore.

    Subject to necessary consents and approvals, GDF SUEZ E&P UK plans a preliminary spud

    date programmed for Q2/23 2013. Pipeline and manifold installation activities are planned

    for Q3 2013, with the possibility of some platform works scheduled for Q3 2012. First gas is

    currently anticipated in Q4 2013.

    The design life of the Juliet development facilities is fifteen years. On cessation of production,

    the Juliet field development, including all associated infrastructure will be abandoned in

    accordance with the legislation prevailing at the time and consultation with the necessary

    authorities.

    THE EXISTING ENVIRONMENT

    The Juliet field is located in the southern North Sea, approximately 37 kilometres to the east -

    north-east of the nearest landfall at Theddlethorpe, and approximately 148 kilometres to the

    west of the UK/Dutch median line.

    The Juliet area lies on the edge of the Silver Pit where water depths range from approximately

    50 to 70 metres (Hydrographer of the Navy, 2002). The water depth at the Juliet wells

    location is approximately 56 metres lowest astronomical tide (LAT) (Gardline, 2009a). Along

    the pipeline route to the Pickerill A Platform, water depth ranges from 14.3 metres LAT to a

    maximum of 55.7 metres LAT within the Silver Pit (Gardline, 2009a, Garline, 2011).

    Sediment composition across the survey area was variable, ranging from sand, sligh tly gravelly

    and gravelly sand and muddy sand. Despite the variability, sediment in the survey is

    comparable to that previously identified within the region. On the southeast slope of the

    Silver Pit silty shelly sand and gravel with numerous cobbles and occasional boulders and rare

    shell fragments are present. Sediments from the start of the pipeline route have been

    identified as an intermittent layer of shelly silty sand and gravel with chalk outcrops and

    numerous cobbles and boulders until reaching KP0.180. From here sediments become

    predominantly silty shelly sand and gravel with numerous cobbles and occasional boulders

    (Gardline, 2011).

    Of the ten most dominant species found during the environmental baseline survey for the

    development, two were species of annelid polychaete (Spiophanes bombyx, Euclymene

    oerstedii), three taxa of mollusca (Abra alba, Abra prismatica, Anomiidae sp.), two taxa of

    crustacea (Urothoe elegans, Pisidia longicornis), one echinoderm taxa (Ophiura albida) and

    two ascidian taxa (Dendrodoa grossularia, Ascidiella sp) (Gardline, 2011). Three of the most

    dominant taxa recorded in the survey were also amongst the ten most dominant taxa in

    comparative surveys (GEL, 2007, 2008b and Gardline 2008), suggesting that the faunal

    community found within the Juliet survey was relatively typical for the wider area (Gardline,

    2009b, Gardline 2011). None of the species listed in the top ten abundance ranking are

    considered unusual for the region or sediment type and no evidence of biogenic reefs such as

    those made by the tube dwelling polychaete Sabellaria spinulosa were observed during the

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 6 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    environmental baseline survey for the Juliet field development (Gardline, 2009a, 2009b,

    2008). The environmental baseline survey conducted in 2011 confirmed this, with the

    univariate statistics suggesting that the macrofaunal community along the proposed pipeline

    corridor was a reasonably variable community with moderate species richness and taxonomic

    diversity (Gardline, 2011). This was as expected considering the variable nature of the

    sediments across the surveyed area. The macrofaunal levels reported in the 2011 survey

    were slightly less even and less species rich than the surrounding area (Gardline, 2008;

    Gardline, 2009a). This difference in community is likely due to the influence that four

    impoverished sampling stations had on the 2011 dataset within an area of large mobile sand

    waves, which were not sampled in the previous Juliet to Pickerill A pipeline survey (Gardline,

    2011).

    Four species spawn in the vicinity of the proposed development area: lemon sole

    (Microstomus kitt), sole (Solea solea), sandeels (Spisula sp.) and sprat (Sprattus sprattus). In

    addition to spawning grounds, the waters of the development area also act as a nursery area

    for lemon sole, sandeels, sprat and whiting (Merlangius merlangus).

    The offshore waters of the southern North Sea are visited by several seabird species mainly

    for feeding purposes. Among the species using the waters in the vicinity of the proposed Juliet

    field development, fulmars are present in highest numbers during the early and late breeding

    seasons, leading to peak densities in September. Increased numbers of gannets (Morus

    bassanus) occur in November and December when dispersion from breeding sites is at a

    maximum. Kittiwakes (Rissa tridactyla) are widely distributed throughout the year. Lesser

    black-backed gulls (Larus fuscus) are mainly summer visitors, while in contrast guillemot (Uria

    aalge) numbers are present in greatest numbers during winter months. In addition,

    substantial numbers of terns (Sterna hirundo) migrate northwards through the offshore North

    Sea in April and May, with return passage from July to September (DECC - SEA 2, 2001).

    The JNCC ranks seabird vulnerabilities on a four point scale (one is the highest vulnerability

    and four the lowest). Seabird vulnerability in Block 47/14 is highest (1 out of 4) during the

    months of August, November and December and is moderately high (2 out of 4) during the

    months of February, and September. Seabird vulnerability is moderate to low (3 or 4 out of 4)

    throughout the remainder of the year. Seabird vulnerability in Block 47/15 is highest (1 out of

    4) during the months of August, November and December and is moderately high (2 out of 4)

    during the months of February, April, September and October. Seabird vulnerability is

    moderate to low (3 or 4 out of 4) throughout the remainder of the year. Seabird vulnerability

    in Block 48/11 is highest (1 out of 4) during the months of August and November and is

    moderately high (2 out of 4) during the months of February, April, September, October and

    December. Seabird vulnerability is moderate to low (3 or 4 out of 4) throughout the remainder

    of the year (JNCC, 2009). As such, periods of concern for drilling are in place in Block 47/14

    from August to October (DEFRA), and from November to December (JNCC).

    The diversity of marine mammals in this area of the southern North Sea is relatively low with

    only harbour porpoise sighted in the vicinity of the development area, predominantly during

    the late summer months.

    The proposed Juliet field development lies within ICES Rectangle 36F0. The highest tonnages

    landed from this area by all vessels are crustaceans (lobster, crabs, shrimps), molluscs

    (scallops, whelks). Other species fished include cod, mackerel, and whiting. The highest fish

    landings by weight occur between April and November with comparatively lower landings being

    obtained at all other times of the year. (MMO, 2009).

    A shipping study and collision assessment of the Juliet development location was undertaken

    in January 2012. There are an estimated 21,307 ships per year passing within 10nm of the

    proposed Juliet location, corresponding to an average of 58 vessels per day, mainly

    comprising of cargo vessels. Based on installing a Jack-up at the development location, the

    annual collision frequency is estimated to be 7.5 x 10 -3, corresponding to a collision return

    period of 133 years. This is well above the historical average ship collision frequency for

    offshore installations on the UKCS which reflects the very high levels of traffic in the vicinity of

    proposed Juliet Drilling Centre. The proposed drilling operation at the Juliet location will have

    an impact on the closest passing routes, with vessels likely to adjust their passage to achieve

    a clearance of typically 1-2nm from the rig (Anatec, 2012a).

    A pipeline risk review was conducted for the Juliet development to Pickerill A Platform pipeline

    route in January 2012. The proposed pipeline is in a busy shipping area with an average of 67

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 7 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    ships per day within 10nm, with the majority being cargo vessels. The shipping density

    analysis shows that the shipping activity over the pipeline is ranked as medium/high. There is

    regular crossing traffic east/west between Humber/Germany and northwest/southeast

    between Tees and Continental Europe, e.g., Rotterdam (Anatec, 2012b).

    The Inner Dowsing, Race Bank and North Ridge candidate Special Area of Conservation (cSAC)

    lies 15 kilometres to the south of the proposed Juliet development. This candidate SAC has

    been considered by the UK Government and added to a list sent to the European Commission.

    The Conservation of Habitats and Species Regulations 2010 now apply to this area.

    The proposed Juliet development is approximately 37 kilometres to the east-north-east of the

    nearest landfall at Theddlethorpe. Numerous protected sites lie along the nearest coastline

    including Flamborough Head, The Wash & North Norfolk Coast and the Overstrands Cliff SACs.

    The key environmental sensitivities arising from the review of the existing environment and

    the proposed Juliet field development are:

    Fish spawning area for lemon sole, sole, sandeels and sprat

    Nursery area for lemon sole, sandeels, sprat and whiting;

    Seabird vulnerability in Block 47/14 is very high during the months of August, November and December.

    Seabird vulnerability in Block 47/15 is very high during the months of August, November and December

    Seabird vulnerability in Block 48/11 is very high during the months of August and November.

    Moderate densities of harbour porpoise in August and September, in addition to lower densities of this species during February and March;

    Fishing activity occurs year round in the area, but effort is low compared to other areas of the southern North Sea, predominately concentrated on shellfish species;

    Shipping densities are high, with traffic comprised predominantly of cargo vessels.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 8 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Seasonal Environmental Sensitivities

    Activity in Blocks 47/14, 47/15 and 48/11 surrounding waters and adjacent coast

    Component Abundance/Activity J F M A M J J A S O N D

    Plankton Phytoplankton and zooplankton

    Benthic

    Fauna

    Benthic faunal communities

    Fish

    Spawning

    Herring

    Lemon sole N N N N N

    Sole

    Sandeels N N N N

    Sprat N N N N

    Whiting N N N N N

    Seabirds

    (Offshore

    Vulnerability)

    Block 47/14 4 2 4 4 4 4 3 1 2 3 1 1

    Block 47/15 4 2 3 2 3 4 3 1 2 2 1 1

    Block 48/11 4 2 3 2 3 4 1 2 2 1 2

    Cetaceans Harbour porpoise abundance

    Resource

    Users

    Commercial fishing (36F0)

    Shipping and ports

    Military Activity (Block 47/11)

    Military Activity (Block 47/15)

    Military Activity (Block 48/11)

    Oil and gas activity (inc. pipelines /

    cables)

    Marine Protected Sites

    Coastal Protected Sites

    Tourism, recreation & leisure

    activities

    Numbers refer to the seabird vulnerability index used by JNCC (1999) (1) highest vulnerability (4) lowest.

    Coastal occurrence Activity in Blocks 47/14, 47/15 and 48/11 and surrounding

    waters

    Peak Low None Peak High Lo

    w

    None N Nursery

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 9 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    HAZARDS, EFFECTS AND MITIGATION MEASURES

    The environmental assessment of the Juliet field development indicates that the key hazards,

    the resulting environmental effects, and the measures proposed by GDF SUEZ E&P UK to

    mitigate those effects are as follows:

    ROUTINE HAZARDS

    Hazard & Effect(s) Effects and Mitigation Residual Impact

    Physical Presence

    Disruption to

    other sea users

    From the review of effect on navigation, it was concluded

    that there are high volumes of traffic passing close to the

    location. This can be divided into NW-SE traffic heading via

    the Outer Dowsing Shoal and East-West traffic heading

    to/from the Humber TSS. The proposed drilling operation at

    the Juliet location will have an impact on the closest

    passing routes, with vessels likely to adjust their passage

    to achieve a clearance of typically 1-2nm from the rig.

    (Anatec, 2012a)

    During drilling operations a 500 metre exclusion zone will

    be set up around the drilling rig. A dedicated standby

    vessel will be present for the duration of the drilling

    programme and will enforce the safety exclusion zone.

    Any interference with fishing will be limited to temporary

    restrictions around the drilling rig, installation vessels and the

    potential for temporary displacement of static fishing gear

    along the pipeline route. The pipeline and umbilical will be

    buried in order to reduce the risk of potential damage to fishing

    gear.

    Pipeline installation and trenching will occur

    simultaneously and therefore any impact due to

    interference with shipping and fishing will be similarly short

    term. During pipelay and dive Support Vessel (DSV) works,

    a fishing representative will be hired by GDF SUEZ E&P UK

    and will be on the vessels to liaise with the fishing vessels

    in the area.

    Prior to operations commencing, the appropriate

    notifications will be made and maritime notices posted.

    All vessel activities will be in accordance with national &

    international regulations. Appropriate navigation aids will be

    used to ensure other users of the sea are made aware of the

    presence of vessels.

    Negligible. The

    work within the

    exclusion zone is

    expected to have

    an effect on other

    third parties

    although only for

    the duration of the

    drilling programme.

    Seabed

    Disturbance

    Caused by the

    deposition of

    cuttings,

    disturbance from

    installation of

    pipeline and

    umbilical and

    from the footprint

    of the rig.

    It is estimated that drilling the Juliet development wells will

    generate a maximum total of 2,036 tonnes of cuttings. 576

    of these are associated with WBM, generated from drilling

    the upper hole section of the wells, and will be discharged

    directly to the seabed. The remaining 1,460 tonnes of

    cuttings are associated with LTOBM from the lower sections

    and will be skipped and shipped for processing onshore.

    The deposition of cuttings and fine solids can have a direct

    effect on seabed fauna. Trenching and placement of rock

    dump as well as disturbance due to spud can penetration

    can lead to disturbance and smothering of the seabed.

    Spot rock dumping along the pipeline may be required if the

    post-installation (out of straightness) survey shows remedial

    dumping is required to mitigate upheaval buckling in specific

    locations. Further rock dump is required at a permanent

    subsea crossing location, where the new Juliet pipeline and

    Negligible to Minor.

    Benthic

    communities found

    in the area of the

    proposed

    development are

    typical of this

    region of the

    southern North

    Sea. Previous

    studies have shown

    that biological

    communities will

    recover rapidly.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 10 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    ROUTINE HAZARDS

    Hazard & Effect(s) Effects and Mitigation Residual Impact

    umbilical crosses the existing CMS 26 inch export and 4

    inch methanol pipelines. GDF SUEZ E&P UK is committed to

    limiting the quantity of rock dumped to keep the impact on

    the environment and other users of the sea to a minimum. It

    is currently envisaged that a maximum of up to 23,000

    tonnes may be required for spot rock dumping along the

    Juliet development to the Pickerill A Platform pipeline and

    umbilical route covering a total area of 4,600 square

    metres. This assumes the rock will be placed at locations of

    larger imperfections along the pipeline and the 23,000

    tonnes will be laid as spot rock dumps along the proposed

    route, apart from the permanent crossing location where an

    estimated 2,800 tonnes is required. It has been assumed

    that the minimum practical rock placement for the vessel is

    2.5 tonnes per metre, which results in a minimum rock

    dump height of approximately 0.3 metres based on a rock

    berm slope of 30 percent.

    The width of pipeline corridor has yet to be confirmed,

    however it is envisaged that it will be in the order of

    approximately 20 metres including the profile of trench and

    spoil piles. A figure of 20 metres has been used as it

    provides the maximum width a typical trenching device can

    trench. Based on a 20 metre trench width and a 22

    kilometre pipeline, the total envisaged footprint on the

    seabed is estimated at 440,000 square metres.

    As a worst case, therefore, the benthic infaunal communities

    over the entire 440,000 square metres of the pipeline

    impact corridor could be impacted by the trenching

    operations.

    Sediments and seabed communities will also be disturbed

    around the footprint of the drilling rig at each well. The

    placement of the spud cans of the jack-up rig on the seabed

    will disturb localised areas and can be expected to impact

    approximately 462 square metres per rig location, which

    corresponds to 154 square metres at each spud can,

    assuming a rig spud can diameter of 14.02 metres (46 feet).

    This equates to a total seabed disturbance from the spud

    can placement of 924 square metres from the Jack-up rig

    positioning for this campaign.

    However, effects on benthic organisms are expected to be

    limited to a relatively small area around the drilling locations

    and along the pipeline and umbilical route and to last for

    only a short time period. In addition, from the grab samples

    analysed, none of the species listed in the top ten

    abundance ranking are considered unusual for the region or

    sediment type and no evidence of biogenic reefs such as

    those made by the tube dwelling polychaete Sabellaria

    spinulosa were observed during the environmental baseline

    survey (Gardline, 2011, 2009a, 2009b, 2008).

    Noise & Vibration

    Noise is thought

    to have the

    potential to

    disturb or confuse

    There will be a low number of additional vessel movements

    during drilling and installation activities. GDF SUEZ E&P UK

    will ensure that the vessels associated with the proposed

    Juliet development will avoid using undue speed; cavitation

    of vessel propellers will be minimised and vessels will not

    Studies indicate

    effects are likely to

    be negligible.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 11 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    ROUTINE HAZARDS

    Hazard & Effect(s) Effects and Mitigation Residual Impact

    cetaceans unnecessarily approach any marine mammals.

    Atmospheric

    Emissions

    Emissions from

    vessels required

    for both drilling

    and installation of

    the development

    facilities.

    Emissions from

    power generation

    and well clean-up

    Additional power generation emissions during installation

    and drilling activities will be minimised by advanced

    planning to ensure efficient operations, well maintained and

    well operated equipment and generators, and regular

    monitoring of fuel consumption.

    No well test is planned.

    GDF SUEZ E&P UK will ensure that high combustion

    efficiency burners are used during well clean-up.

    GDF SUEZ E&P UK will ensure that contract specification

    and control processes require all equipment and generators

    to be well maintained and operated.

    Negligible. There

    will be low local

    effect and gases

    disperse rapidly.

    Emissions from gas

    combustion will

    contribute towards

    global greenhouse

    gas emissions.

    Marine

    Discharges

    Will include

    discharge of mud

    & cuttings,

    drainage water,

    sewage, well

    completion fluids,

    hydrotest water

    and production

    chemicals.

    Planned use of seawater and/or water based muds (WBM)

    in the upper hole section of the wells with selection of most

    environmentally benign mud and cement chemicals. 99

    percent of the WBM is comprised of chemicals considered to

    pose little or no risk to the environment. Installation of

    cuttings / mud cleaning equipment will ensure optimal

    cuttings cleaning and continuous mud mass balance will be

    maintained throughout the drilling programme.

    GDF SUEZ E&P UK will ensure good housekeeping standards

    are maintained on the drilling rig to control the amount of

    hydrocarbons & other contaminants entering the drainage

    system & that appropriate sewage treatment systems are on

    all vessels.

    During the short duration of flowline hydrotest de-watering,

    GDF SUEZ E&P UK will ensure that discharge rates are

    controlled to allow maximum dispersion/ dilution.

    All drilling & pipeline chemicals will be assessed using the

    CHARM methodology where appropriate, in accordance with

    the Offshore Chemicals Regulations 2002. Chemicals

    identified to be high risk will be substituted for more

    environmentally friendly alternatives where practicable.

    Negligible. Due to

    the low toxicity of

    the majority of the

    discharges & the

    anticipated dilution

    & dispersion, all

    impacts are

    predicted to be

    short-term and

    localised. Studies

    indicate recovery of

    benthos following

    cuttings deposition

    will occur within

    months.

    Solid Wastes

    Wastes will

    include OBM

    cuttings, scrap

    metal, waste oil &

    surplus chemicals

    Waste will be segregated by type and transported to shore to

    be recycled or disposed of in a controlled manner under the

    duty of care regulations (EPA 1990). Appropriate Waste Management practices, including provisions for Hazardous

    Waste, will be applied by all contractors working on the Juliet

    development. As far as reasonably practicable, materials

    such as scrap metal, waste oil and surplus chemicals will be

    sent for recycle or re-use. OBM contaminated cuttings will

    be contained on the drilling rig and returned to shore for

    processing and disposal by a licensed contractor. Other

    waste will be sent to authorised landfills or incineration

    facilities, depending on its nature.

    Negligible. Wastes

    will be treated

    where appropriate.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 12 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    NON-ROUTINE HAZARDS

    Potential Spill

    Source

    Prevention & Mitigation Measures Taken

    Leaks of drilling

    mud

    Procedural controls on transport and disposal. Transfer protocols similar to those

    used for refuelling.

    Diesel fuel

    bunkering

    All efforts shall be made to ensure the drilling rig arrives on site fully bunkered to

    negate or reduce the need for diesel fuel bunkering during the project.

    Transfer hoses and associated equipment will be inspected to ensure their

    integrity. Bulk fuel transfer hoses will have non-return valves, refuelling hoses to

    have dead man closures and floatation collars to be used on all hoses. Bunding

    will be provided around each of the loading stations and around the main fuel oil,

    tank vents on the main deck. Transfer hoses inspected prior to use and replaced

    and regular intervals.

    Offshore fuel and bulk transfer to the drilling rig will be supervised at all times and

    communication links will be tested. All transfers to and from the rig / vessel plus

    all internal transfers will be controlled by written work instructions. Fuel transfer

    will be restricted to conditions of visibility that allow effective monitoring of the

    loading operation and suitable weather conditions (which will be defined with

    contractor prior to operations commencing).

    Fuel transfer will be stopped if a spill occurs.

    Oil, diesel &

    aviation fuel and

    chemical spills

    during bunkering /

    refuelling

    Bunding to contain spills, spills on rig directed to hazardous drains or slop tanks,

    on-board absorbent materials available on all vessels.

    Oil spill during on-

    board tank filling

    Spills directed to the hazardous drains system, where oil will be removed by the

    centrifuge or oil skimming apparatus or diverted to the slop/bilge tanks.

    Rig storage tank

    leaks

    A clear record of the chemicals store will be maintained at all times and

    compliance with OCR reporting requirements will be observed.

    Tanks provided with appropriate bunding. Material directed to the hazardous

    drains system, where oil will be removed by the centrifuge or oil skimming

    apparatus.

    Absorbents provided for spill management of diesel lube oil and stored chemicals.

    All such spills directed to hazardous open drains system with trip and alarm

    systems in place. Training will be given in spill clean-up techniques.

    Special training will be given to personnel with the responsibility of operating

    valves, and particularly dump valves. Training in the correct identification and

    utilisation of these valves will be provided prior to their use, and awareness will be

    raised on the importance of preventing spills.

    Hazardous drains system will not be able to remove chemicals prior to discharge so

    chemicals could be directed to slop/bilge tanks and taken to shore for treatment.

    Procedure to minimise and prevent spills from draining and filling of heating and

    cooling systems.

    ENVIRONMENTAL MANAGEMENT

    The management of environmental risks associated with the Juliet development is integral to

    the decision making process. Environmental hazards are identified at all stages in the

    development life cycle and risks are assessed and managed within GDF SUEZ E&P UKs Quality & Health, Safety and Environment Management System (QHSEMS).

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 13 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    The QHSEMS clearly defines the environmental responsibilities of individuals at all levels of

    the organisation and provides a framework through which a process of continual improvement

    in the environmental awareness is implemented. The system ensures the application of

    appropriate management controls thereby reducing any environmental risks arising from GDF

    SUEZ E&P UKs operations.

    Actions to ensure protection of the environment within this Environmental Statement will be

    incorporated into an Environmental Program or Action Plan as defined within the management

    system. It will be the responsibility of the Project QHSE team leader, with assistance from the

    HSE Advisor, to ensure that these actions are implemented and completed during field

    development. When the field goes into production, on-going monitoring and reporting will be

    the responsibility of the host facility operator. GDF SUEZ E&P UK will monitor performance

    over time to ensure that the production operations continue to meet the environmental

    performance required by legislation and defined within this Environmental Statement.

    CONCLUSIONS

    In summary, although there will be some environmental impact during each phase of the Juliet

    field life cycle, adverse long term environmental impacts from the Juliet developme nt will be

    negligible. Incremental cumulative impacts of the development will be minimal and there will

    be no transboundary effects.

    GDF SUEZ E&P UK will manage any potential impacts through careful planning and design

    controls.

    Environmental management at GDF SUEZ E&P UK is undertaken in accordance with an

    established and proven QHSE Management System, which is certified under ISO 14001. GDF

    SUEZ E&P UK also has experience in this area of southern North Sea and therefore has a good

    understanding of the environmental sensitivities in the vicinity of the Juliet field development.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 14 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    ABBREVIATIONS

    ACOPS Advisory Committee on Protection of the Sea

    AIS Automatic Identification System

    ALARP As Low as Reasonably Practicable

    AoNB Areas of Outstanding Natural Beauty

    AoSP Areas of Special Protection

    API American Petroleum Institute

    BAP Biodiversity Action Plan

    BAT Best Available Technique

    BERR Department for Business, Enterprise and Regulatory Reform

    BGS British Geological Survey

    BOP Blow-out Preventer

    CAPEX Capital Expenditure

    CEFAS Centre for Environment, Fisheries and Aquaculture Science

    CEO Chief Executive Officer

    CHARM Chemical Hazard Assessment and Risk Management

    CO2 Carbon Dioxide

    cSAC Candidate Special Area of Conservation

    DECC Department of Energy and Climate Change

    dB Decibel

    dSAC Designated Special Area of Conservation

    DST Drill Stem Test

    DSV Diving Support Vessel

    DTI Department of Trade and Industry

    EC50 Effective Concentration for 50% of organisms

    EMS Environmental Management System

    EIA Environmental Impact Assessment

    EPS European Protected Species

    ERP Emergency Response Plan

    ES Environmental Statement

    EU European Union

    FEED Front-End Engineering and Design

    FPSO Floating Production, Storage and Offload (vessel)

    GEL Gardline Environmental Limited

    HMCG Her Majestys Coast Guard

    HMCS Harmonised Mandatory Control Scheme

    Hs Significant wave Height

    HSE Health, Safety and Environment

    HSS Health and Safety Standard

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 15 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    ICES International Council for Exploration of the Seas

    IRM Intervention and Routine Maintenance

    IMO International Maritime Organisation

    JNCC Joint Nature Conservation Committee

    LTOBM Low Toxicity Oil Based Mud

    LAT Lowest Astronomical Tide

    LOS Line of Sight

    LP Low Pressure

    MAOP Maximum Allowable Operating Pressure

    MCA Maritime and Coastguard Agency

    MFA Marine Fisheries Agency

    MoD Ministry of Defence

    MRCC Maritime Rescue Co-ordination Centre

    MW Mega Watts

    nm Nautical Mile

    NOx Nitrogen Oxides

    No2 Nitrogen Dioxide

    OBM Oil Based Mud

    OCNS Offshore Chemical Notification Scheme

    OCR Offshore Chemical Regulations

    OGP Oil and Gas Producers

    OGUK Oil & Gas United Kingdom (formerly UKOOA)

    OPEP Oil Pollution Emergency Plan

    OPEX Operational Expenditure

    PHA Polycyclic Aromatic Hydrocarbons

    PLONOR Posing Little Or No Risk (to the environment)

    PNEC Predicted No Effect Concentration

    pSAC (proposed) Special Areas of Conservation

    QHSEMS Quality & Health, Safety and Environment Management System

    ROV Remotely Operated Vessel

    RSPB Royal Society for the Protection of Birds

    SACs Special Areas of Conservation

    SFF Scottish Fishermans Federation

    SGMD Scottish Government Marine Directorate

    SOx Sulphur Oxides

    SPA Special Protection Area

    SSSI Sites of Special Scientific Interest

    SWT Scottish Wildlife Trust

    TD Total Depth

    TOC Total Organic Carbon

    TOM Total Organic Matter

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 16 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    THC Total Hydrocarbon Concentrations

    UK United Kingdom

    UKCS United Kingdom Continental Shelf

    UKOOA United Kingdom Offshore Operators Association

    WAT Wax Appearance Temperature

    WBM Water Based Mud

    WGS World Geodetic System

    WPS Well Protection Structure

    WHO World Health Organisation

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 17 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    1.0 INTRODUCTION

    1.1 THE PROJECT GDF SUEZ E&P UK Ltd (hereafter referred to as GDF SUEZ E&P UK) is planning to develop the Juliet gas field, located in Block 47/14b in the southern North Sea, approximately 37

    kilometres to the east-north-east of the nearest landfall at Theddlethorpe. The nearest

    transboundary line is the UK/Dutch line which lies approximately 148 kilometres to the east of

    the proposed development location (Figure 1.1).

    The Juliet development will consist of two subsea wells drilled local to each other and it is

    intended that the two wells will be drilled from the same jack-up rig location. The wells will be

    tied back via a single 12 inch export pipeline and controlled by an umbilical from the Pickerill

    A Platform owned and operated by Perenco UK Ltd located approximately 22 kilometres east

    of the Juliet field.

    Reservoir fluids from the Juliet field will be exported to shore from the Pickerill A Platform via

    the existing 24 inch Pickerill Theddlethorpe Pipeline into Theddlethorpe Terminal operated by Conoco Phillips. The Juliet subsea wells and infrastructure will be monitored, controlled

    and operated on a day to day basis from the onshore control room at the Bacton Terminal

    (Although Pickerill ties back to Theddlethorpe gas terminal, control is performed at Bacton) .

    The two subsea horizontal development wells will be drilled local to the existing 47/14b-10

    discovery well. One will target the west of the Juliet structure, the other the east. It is

    anticipated that the wells will be drilled using a standard jack-up rig. Subject to necessary

    consents and approvals, GDF SUEZ E&P UK plans a preliminary spud date programmed for

    Q2/3 2013. Topsides construction phase is provisionally planned for Q3 2012 with subsea

    construction in Q3 2013. First gas is currently anticipated in Q4 2013.

    The design life of the Juliet field development facilities is fifteen years. On cessation of

    production, the Juliet field development, including all associated infrastructure will be

    abandoned in accordance with the legislation prevailing at the time and consultation w ith the

    necessary authorities.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 18 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 1.1. Location of the Proposed Juliet Development

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 19 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    1.2 SCOPE The Environmental Impact Assessment (EIA) carried out for the proposed Juliet development

    has assessed the potential impacts on the existing environment in the southern North Sea for

    all main phases of the hydrocarbon lifecycle: from drilling, through construction and

    installation, to production operations and field decommissioning.

    This Environmental Statement (ES) has been prepared to report the EIA, to ensure compliance

    with the requirements of the Offshore Petroleum and Pipelines (Assessment of Environmental

    Effects) Regulations, 1999 (as amended), and to meet GDF SUEZ E&P UKs QHSE Management System (refer to Section 5). An overview of the statutory fram ework applicable

    to offshore oil and gas operations is included in Appendix A.

    1.3 APPLICANT GDF SUEZ E&P UK has been active in the UK since 1997, growing rapidly through both

    acquisition and active participation in the UK licensing rounds. GDF SUEZ E&P UK is an

    established exploration and production operator in the UK, owning interests in more than fifty

    offshore gas and oil licences on the UK continental shelf , distributed across West of

    Shetlands, central and southern North Sea. The company has interest in fifteen producing

    fields, of which the Minke is operated in the southern North Sea.

    The UK forms a significant share of the global GDF SUEZ business and makes a significant

    contribution to the Groups targets in securing gas supplies through production. As such GDF SUEZ is committed to developing its existing portfolio in the UK. The development of the Juliet

    field fits within this target.

    GDF SUEZ E&P UKs Health, Safety and Environmental (HSE) Policy is applied to all areas of activity and universally endorses health, safety and environmental excellence as a key

    component of the operating philosophy and culture. HSE management is integrated into the

    companys activities.

    1.4 ENVIRONMENTAL IMPACT ASSESSMENT This Environmental Statement presents the results of the environmental assessment of the

    proposed Juliet development. An environmental assessment is an important management

    tool which ensures that environmental hazards and effects are identified, evaluated, and that

    appropriate control measures are implemented.

    The process comprised four main stages:

    Characterise the environment and identify the environmental hazards associated with the activity;

    Assess the magnitude and significance of the hazards and effects;

    Implement control techniques to eliminate or lessen the severity of the effects and to manage the hazard;

    Review and, where necessary, develop plans and procedures to manage the consequences of accidental events.

    Consultations are undertaken throughout the environmental impact assessment process with

    interested parties, including statutory consultees and non-governmental organisations (NGOs).

    These consultations focus on potential environmental issues, project goals and environmental

    strategies (refer to Section 1.5).

    In practice, environmental control measures are an integrated part of planning operations and

    in some instances are indirect benefits of other considerations. This environmental

    assessment has been undertaken to confirm the effectiveness of standard engineering

    controls and to identify specific circumstances that may warrant additional control measures.

    This document addresses all offshore operations associated with the Juliet development.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 20 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    1.5 CONSULTATIONS Prior to submission of this ES to the Department of Energy and Climate Change (DECC) the

    views of a number of organisations were solicited by letter in November 2009 and September

    2011. The issues raised during this preliminary consultation process have been considered in

    detail by GDF SUEZ E&P UK and addressed, where appropriate, in the ES (refer to Table 1.1).

    A meeting between GDF SUEZ E&P UK, DECC and the JNCC was held in September 2011 to

    discuss the proposed Juliet development and progress so far.

    Table 1.1. Summary of Responses Received During the Juliet Consultation Process

    Organisation Issues Raised ES Section Reference

    JNCC Proposed Inner Dowsing, Race Bank and

    North Ridge possible Special Area of

    Conservation (pSAC), which is located

    south to the Juliet Field in the outer Wash

    area should be discussed in the ES.

    Section 3.7.2

    DECC Juliet is close to an environmentally

    sensitive area for birds. Discussion needs

    to be included in the ES, although Juliet

    development should not have any impact.

    Rock dumping quantities and impacted

    area should be fully discussed in the ES.

    Section 3.6.4

    Section 4.5.3

    CEFAS The proposed development site lies within

    a spawning area for lemon sole, sole,

    sandeel and sprat. Due to the presence of

    spawning sole, the field development will

    be subject to timing restriction on seismic

    activities between January and May

    (inclusive).

    The proposed development lies within

    ICES Rectangle 36F0 and not 35F0.

    Landings data for 36F0 in 2008 show that

    Fishing by English registered vessels in

    this block was high and mainly consisted

    of potting for crabs, lobster and whelks,

    and bottom trawling for whiting.

    Section 3.6.3

    Section 3.8.1

    RWE The RWE Triton Knoll Windfarm

    development area lies immediately south

    of the Juliet development. The initial

    indication is that no proximity agreement

    will be needed as the nearest Triton Knoll

    turbine location is sufficiently distant.

    Consultation has been initiated and is

    ongoing.

    Section 3.8.7

    Ministry of

    Defence No Concern Section 3.8.3

    National

    Federation of

    Fishermen's

    Organisations

    No response received at time of printing. N/A

    Natural

    England No response received at time of printing. N/A

    Consultations and liaison with interested parties is a continuous part of the environmental

    management process and will continue throughout the Juliet development.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 21 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    1.6 STRUCTURE OF REPORT The report is presented in six main sections.

    Section 1: Introduction provides a background to the project.

    Section 2: The Proposed Development provides details of the proposed field development including project overview and option selection, installation of the facilities, drilling operations,

    export of oil and decommissioning.

    Section 3: Description of the Environment describes the background physical environmental characteristics in the southern North Sea, identifies the flora and fauna likely to be present

    within the vicinity of the development and describes other sea users within this area.

    Section 4: Environmental Hazards, Effects and Mitigation Measures identifies the potential interactions of the proposed development with the environment and details the control and

    mitigation measures to be implemented to limit the impacts.

    Section 5: Environmental Management provides an outline of how GDF SUEZ E&P UK will manage the project to ensure protection of the environment throughout the life of the

    development.

    Section 6: Conclusions of the Environmental Statement

    In addition, the report includes a non-technical summary of the environmental assessment,

    highlights its main conclusions, and provides a list of references used to obtain data and

    information to support the assessment. Further information is also included in the

    appendices.

    1.7 CONTACT & INFORMATION REQUEST Any questions, comments or requests for additional information regarding the Environmental

    Statement shall be addressed to:

    EIA Co-ordinator

    Environmental Management Team

    Energy Development Unit

    Department of Energy and Climate Change

    4th Floor, Atholl House

    86 88 Guild Street Aberdeen, AB11 6AR

    Email: [email protected]

    Fax: 01224 254019

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-06-EB-72-00001 Rev C1 Page 22 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    This page is intentionally blank

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 23 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    2.0 THE PROPOSED DEVELOPMENT

    2.1 THE JULIET FIELD The Juliet field lies in Block 47/14b on the western flank of the southern gas basin,

    approximately 22 kilometres west of the Pickerill A Platform operated by Perenco UK Ltd (refer

    to Figure 2.1).

    Figure 2.1. Juliet Field Location Map

    The Juliet field is a dip closed structure that relies in part on a fault seal, notably at its north -

    east flank. The fault seal separates the field from Amethyst East. The reservoir consists of

    Aeolian dunes with secondary sandsheet and fluvial deposits of the Permian, Rotliegendes,

    Lower Leman Sandstone Formation. The field top seal is provided by evaporates of the

    overlying Zechstein Group. The general stratigraphy of the development area is shown in

    Figure 2.2

    The Juliet field is a dry gas discovery sourced from coals and shales of Westphalian and

    Namurian age. The structure was discovered in 2008 by the 47/14b-10 well. This well flowed

    gas at a sand constrained rate of 38 million standard cubic feet per day (mmscf/d) from a 20

    foot interval of high quality sandstone. Reservoir fluid analysis of samples taken from the

    47/14b-10 well indicates that the Juliet field contains gas with some condensate. Th e well

    test observed an average condensate to gas ratio (CGR) of 12 barrels per million cubic feet of

    gas (bbl/mmscf). No hydrogen sulphide was reported. Formation water can be expected from

    both Juliet wells.

    Further gas discovery potential in the region exists in a fault block adjacent to the field known

    as Juliet West. This structure is believed to be separated from the Juliet field by a north

    east/south west trending fault.

    GDF SUEZ E&P UK is operator of the Juliet field with a net equity interest of 51.56%. First Oil

    has a net equity of 29.44% and Hansa a net equity of 19.00%.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 24 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.2. Juliet Stratigraphic Column

    2.2 DEVELOPMENT OBJECTIVE AND CONCEPT The objective of the project is to produce gas from the as yet undeveloped Juliet field and

    export it to shore, using a combination of both new and existing infrastructure. The current

    development plan is to drill two new horizontal wells into the structurally high areas of the

    field to maintain the maximum standoff distance from the Gas Water Contact (GWC). The first

    well will be drilled towards the west of the field and the second towards the east. The wells

    will be tied back to the Perenco UK Ltd operated Pickerill A Platform, located in Block 48/11,

    via an approximately 22 kilometre long 12 inch export pipeline and control umbilical.

    The Juliet export pipeline will be a fully rated carbon steel pipeline. The Juliet flowline will be

    routed between the manifold and the new risers on Pickerill A. The flowline will tie-in to the

    Pickerill A Platform riser via a spool tied in to a new riser.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 25 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    From the Pickerill A Platform, gas from Juliet will be exported onshore to the Conoco Phillips

    Theddlethorpe terminal via the existing pipeline from the Pickerill field. On entering the

    terminal the gas from Pickerill is processed and any condensate and water separated. The

    gas stream is then metered before mixing with other gases and undergoing further processing

    in dewpointing and condensate stabilisation facili ties. Gas is then fed into the National Grid

    and condensate sent to the Humber Oil Refinery.

    The Juliet wells will be monitored by individual gas flow meters and data transmitted through

    topside equipment and then by Line of Sight (LOS) to the onshore Bacton terminal. Controls to

    the Juliet wells will be via a newly installed control umbilical between the wells and the

    Pickerill A Platform. The control umbilical will also carry production chemicals for injection at

    each well.

    This ES considers the following phases of development:

    Offshore Facility Installation and Commissioning

    Installation of the Juliet subsea wellheads and protective fishing friendly structures;

    Installation of approximately 22 kilometre 12 inch flexible carbon steel pipeline and control umbilical from the Juliet subsea wells to the Pickerill A Platform;

    Testing and commissioning of Juliet wellheads, export pipeline and umbilical;

    Topsides modifications on Pickerill A Platform.

    Development Drilling

    The drilling of the Juliet Eastern well (47/14b-J1) from surface location 53033 13.51 North and 0045 20.832 East, targeting the West zone of the Juliet reservoir;

    The drilling of the Juliet Western well (47/14b-J2) from surface location 53033 13.26 North and 0o45 21.28 East, targeting the East zone of the Juliet reservoir;

    Completion and clean-up of the Juliet development wells.

    Production and Maintenance

    Export of the Juliet reservoir reserves to the Pickerill A Platform;

    Maintenance of facilities.

    Decommissioning

    Decommissioning of facilities.

    These elements, together with a description of the proposed facilities and schedule for

    development, are discussed in the following sections.

    2.3 DEVELOPMENT OPTION SELECTION Several options were considered for the export route and a screening study undertaken to

    identify the option which presented the least risk to the project (GDF Suez E&P UK Ltd, 2011).

    To summarise, elements considered as part of the screening study included:

    Environmental and safety issues;

    Overall capital expenditures (CAPEX) and operational expenditures (OPEX);

    Commercial issues;

    Technical complexity; and

    Schedule.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 26 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    The options considered included:

    Several export routes via mechanical tie-in (subsea and platform);

    Several export routes via hot tap (platform only); and

    Direct tie-back to the beach (platform only).

    An option screening study was undertaken to identify all potential offtake routes for Juliet

    fluids. The methodology consisted of a number of important steps prior to final screening and

    selection evaluation. These were as follows:

    Identification of export route options;

    Identify HSE and technical risks associated with each of the options;

    Perform preliminary flow assurance work for pipe sizing for each of the export route options;

    Determine the likely topsides modifications works associated with each of the export route options;

    Produce capital expenditures (CAPEX) and operational expenditure (OPEX) estimates for each of the proposed development options and perform economics on those;

    Perform a series of evaluation workshops to determine the preferred export and development type which best suits the Juliet development;

    Identify a preferred solution and progress risk based assessments on schedule, costs and HSE criteria;

    Produce a high level project execution plan for the project based on the preferred option.

    The major technical issues for the Juliet development concept were as follows:

    Selection of the number and types of wells - two horizontal wells have been selected based upon initial subsurface work. Technical review concluded that the wells should

    be horizontal completions.

    Drilling of the wells initial technical review indicated that the wells should be drilled from a single location. Moreover, the existing suspended 47/14b-10 well will not be

    side tracked.

    One of the key drivers towards the development type (subsea or platform) was the likelihood and type of intervention required. Whether Juliet could be developed through

    the use of subsea completions or a wellhead tower.

    The initial host options screening considered all local gas infrastructure in the vicinity of Juliet.

    The options considered included tie-backs to surrounding platforms, hot tapping into export

    pipelines and a direct tie-back to an onshore terminal. However, most of the options

    considered were discounted during the concept selection due to High CAPEX and OPEX costs,

    environmental impacts, safety concerns and commercial difficulties.

    Following the loss of the Amethyst export route in the desired timeframe, an appraisal of the

    options the project was recycled back to concept select with consideration given to the

    following options:

    Subsea development tied back to Pickerill A Platform

    Tie into one of the other platforms in the surrounding area (platforms up to 50 kilometres from Juliet wells were considered)

    Hot tap into one of the main export routes in the vicinity.

    Tieback to the beach

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 27 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Whilst all of these have previously been considered, the project revisited all options to identify

    a clear export route and development type which limits HSE and commercial risks whilst

    achieving as early a first gas date as possible.

    The methodology followed to reach a final development concept consisted of a number of

    important steps prior to this final screening and selection evaluation. These were as follows:

    Identification of export route options.

    Perform preliminary flow assurance work for pipe sizing for each of the export route options.

    Determine the likely topsides modifications works associated with each of the export route options.

    Commence and progress (where possible) commercial agreements with each of the export route owners.

    Produce CAPEX and OPEX estimates for each of the proposed development options and perform economics on those.

    Identify HSE and technical risks associated with each of the options.

    Perform a series of evaluation workshops to determine the preferred export and development type which best suits the Juliet development.

    Identify a preferred solution and progress risk based assessments on schedule, costs and HSE criteria.

    Produce a project execution plan for the project based on the preferred option.

    The conclusion of this work has identified the following preferred option for the Juliet

    development which represents the least risk in terms of HSE, schedule, cost and technical

    difficulty:

    Two new horizontal wells completed with sand screens.

    A Subsea Development located in 56 metres water depth.

    Tieback to the existing Pickerill A Platform

    Following the concept selection stage, the following tie-back type was selected.

    Pickerill A Platform (Figure 2.3)

    Table 2.1 presents the reasons why this export route was chosen.

    Table 2.1. Selected Route

    Develop

    ment

    Type

    Export

    Route

    Distance

    from

    Juliet

    Facilities/

    Technical/Cost Environmental

    Subsea Pickerill A

    Riser

    22 km Lowest CAPEX and OPEX cost

    Least topsides modifications

    required

    Not the shortest pipeline tie-back

    however the Amethyst A2D

    platform was

    unavailable for

    the Juliet works.

    Least amount of offshore construction activity therefore

    reduces environmental impact

    As there is no new platform with this type of development there

    is less operational HSE risks

    associated with ship collision,

    helicopter travel etc

    No significant environmental issues with the seabed along

    the proposed route

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 28 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.3. Pickerill A (Subsea)

    As shown in Table 2.1, the Pickerill A Platform with new 12 inch riser tieback option (Figure

    2.3) was the preferred development option. The following bullet points detail the key reaso ns

    for this.

    Subsea Development

    The Juliet proposed well locations are in an area of high density shipping, with a major shipping lane routing though the area. The addition of a new platform in this area

    would cause a significant potential shipping impact risk. This could potentially result in

    the need for a new shipping lane route which would be problematic given the existing

    platform infrastructure in this area;

    Installation of a new platform would add operational hazards including additional risks from ship collision, helicopter traffic, occupational hazards from operating a new

    platform etc. There is also additional risks from a construction perspective during the

    installation of the platform;

    Less CAPEX and OPEX costs for the development, making it more economical.

    Less scheduling risk a subsea option is less complex and therefore installation is more straight forward;

    It is expected that minor intervention works on the wells is possible later in the field life of Juliet. These interventions will require a drill rig irrespective as the platform type

    considered would have been a small unmanned platform, which could not support

    intervention works.

    Piggybacking the umbilical to the pipeline was considered but was not technically feasible due to the nature of the seabed sediments along the route.

    24 63km Pickerill Theddlethorpe

    Pipeline

    22km 12 Juliet Pickerill Flowline

    and Umbilical

    THEDDLETHORPE

    Juliet Subsea Wells

    2 Wells + 1

    Spare

    Pickerill A

    Tie-in via new 12 Riser

    26 CMS pipeline

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 29 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.4. Justification diagram for tieback to Pickerill A Platform

    2.4 PROPOSED PROJECT SCHEDULE A provisional project schedule for the Juliet development is shown in Table 2. 2. This

    programme may change subject to detailed scheduling and, in particular, availability of the

    drilling rig and the fabrication times of various key elements.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 30 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Table 2.2. Preliminary Schedule for key Project Milestones

    Task 2012 2013

    Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    FEED and

    Detailed design

    Subsea/Topsides

    Detailed Design

    Installation

    Engineering

    Topside

    Construction

    Phase 1

    Development

    Drilling

    Topside

    Construction

    Phase 2

    Subsea

    Installation

    First gas

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 31 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    2.5 PRODUCTION AND EXPORT FACILITIES

    2.5.1 Juliet Subsea Facilities

    The Juliet subsea facilities will comprise two subsea wells tied into a subsea manifold. The

    most likely tie-back option and subsea facilities are shown in Figure 2.5. However, the design

    is subject to change once additional engineering studies have been completed. Consideration

    will be given to a subsea wet gas meter which will be housed in the manifold. The control

    umbilical will come from the Pickerill A Platform and will carry corrosion inhibitor and hydrate

    inhibitor and have a wash water injection core for potential Halite treatment. Juliet controls

    will be electro-hydraulic and will utilise as much of the existing controls and hydraulic power

    as possible to minimise topsides modifications.

    Figure 2.5. Diagram of Juliet subsea facilities

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 32 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    2.5.2 Gas Export Pipeline and Umbilical

    Gas and associated reservoir fluids will be exported from the Juliet development wells via a

    new 22 kilometre, 12 inch carbon steel pipeline and tied to the base of a new riser, subsea

    (Figure 2.6). A new riser will be installed on the platform. A new J Tube will also be installed

    which will house the control umbilical.

    Fabricated spool pieces will connect the export pipeline and umbilical to the manifold. The

    control umbilical will be terminated subsea with a Subsea Umbilical Termination Unit (SUTU)

    which will be housed in the manifold. The manifold will also have rigid pipe work for chemical

    injection requirements.

    The Juliet export pipeline will have a nominal wall thickness of 20.6 millimetres (wall

    thickness to be confirmed during FEED and detailed design). The pipe on the bends and the

    tie-in spools may be thicker; however this will be confirmed during a later stage of the Juliet

    development.

    Chemical injection will be from the Pickerill A Platform via dedicated cores within the control

    umbilical. Continuous injection of corrosion inhibitor will be required to protect the carbon

    steel pipeline, riser and manifold pipe work.

    There will be continuous methanol dosing to inhibit hydrate formation during normal

    operations. There may be a requirement for a higher rate of dosing during the start up period.

    All chemicals discharged will meet the requirements of the Offshore Chemicals (Amendment)

    Regulations, 2011 and will be subject to a PON 15C permit under this legislation .

    Consideration will be given to a wet gas meter within the manifold to meter production from

    each of the wells.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 33 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.6. Juliet Subsea Location and Proposed Export Pipeline / Umbilical Route

    (Source GdF)

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 34 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    2.5.3 Host Facility

    The Pickerill A Platform is located approximately 22 kilometres to the west of the Juliet

    development. Perenco is the operator of the Pickerill field, situated in Block 48/11 with both

    the Pickerill A and Pickerill B platforms which flow gas through a dedicated pipeline to the

    terminal at Theddlethorpe.

    Subsea inspection and maintenance is the responsibility of GDF SUEZ E&P UK. Maintenance

    of the topsides and riser will be the responsibility of the Pickerill owners, Perenco. However, it

    is likely that the inspection of the Subsea infrastructure will be performed by GDF SUEZ E&P

    UK as part of an overall inspection programme and any remedial works required will be

    performed by GDF SUEZ E&P UK.

    The offshore modifications to the Pickerill platform will be undertaken by Perenco wi th

    assistance from Juliet owners. The offshore work is envisaged to be carried out during

    summer 2012 and Q2/3 2013.

    The Juliet flowline will be routed between the manifold and the new risers on Pickerill A. The

    selection of the Pickerill A allows for a new riser and J tube to be installed on the platform.

    This minimises any concerns over integrity of tying into existing risers. By allowing for a new J

    tube, previous concerns over the spare J tube mean that there are fewer restrictions on the

    umbilical size.

    Currently tie-in of the Juliet pipeline to the Pickerill A riser will come from the west, as

    illustrated in Figure 2.7.

    No offshore gas processing, water or condensate separation will occur on Pickerill A for the

    Juliet gas stream. All processing of Juliet fluids will occur onshore at the Theddlethorpe

    terminal.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 35 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.7. Pickerill A Platform Approach

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 36 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Host Platform Modifications

    Modifications on the Pickerill A Platform required to enable Juliet gas to be processed are as

    follows:

    Controls tie-in;

    Extension of the chemical injection system.

    New riser

    Pipework tie-in

    J-tube

    As far as possible the existing controls/Hydraulic Power Units (HPU) will be utilised for the

    Juliet development to minimise the modifications required.

    The control umbilical will come from the Pickerill A platform and will have a wash water

    injection core for halite treatment and will also carry corrosion and hydrate inhibitor. HPUs,

    topsides umbilical termination units (TUTU), and chemical injection equipment will be required

    to be installed at the Pickerill A platform in addition to communications equipment.

    Topsides modifications will include:

    The installation of a new riser and J tube to the jacket of the platform. The riser will terminate in a topsides Emergency Shutdown Valve (ESDV) located on a new

    sub cellardeck access platform to facilitate access to the ESDV, pig receiver, and

    control umbilical termination point.

    The Julliet flowline will go up to a new allocation flowmeter and eductor (a type of jet pump) located on a new cantilever platform at the cellar deck level.

    Pickerill A & B export line to entrain the Pickerill gas in the co-mingled export flowline, which will be connected to the existing export pipeline to Theddlethorpe.

    The Juliet wellhead pressures at the commencement of the Juliet field production life are such that there is a high risk of hydrate formation at the wellhead. To mit igate

    against this, the Juliet development will re-commission the mothballed methanol

    system on Pickerill A. This system is not capable of supplying methanol to the

    upstream side of the subsea choke due to the high gas pressure at the start of field

    life, therefore the project will install a methanol booster pump to be used during start -

    up to address this requirement. This pump will be installed on the cellar deck

    adjacent to the existing methanol facilities.

    The installation of a new hydraulic power unit (HPU) located on the upper weather deck for topsides and subsea control motive requirements.

    Control of all the new Juliet equipment will be achieved, utilising or augmenting the existing

    systems on Pickerill A together with Perenco's onshore control room in Bacton. It should be

    noted that notification for construction works for the Subsea and topsides works wil l be done

    as separate applications.

    2.6 OFFSHORE CONSTRUCTION AND INSTALLATION

    2.6.1 Pipeline and Umbilical Installation

    Pipelay

    A rigid reel lay vessel will be commissioned to undertake pipelay operations. The vessel will

    be a dynamically positioned offshore construction ship.

    The pipeline and umbilical will be laid in separate trenches, approximately 30 metres apart.

    Installation of the pipeline will be carried out by two or three reel lay type vessel.

    Pipelay operations are expected to take approximately 14 days to complete (not including

    mobilisation, demobilisation, transit or weather down time). During this time the pipelay

    vessel will lay the pipeline on the seabed ready for trenching.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 37 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    On completion of pipelay operations a post lay survey will be undertaken to identify the status

    of the installed pipelines and debris incidence. This will take approximately one day to

    complete. A pipeline systems strength test, lasting one day will be carried out on the newly

    installed pipeline to ensure that it has not been damaged during the installation process. This

    will be undertaken from either the pipelay vessel or a dedicated survey vessel.

    Trenching

    Pipeline trenching operations will employ a pipeline plough or mechanical trenching device

    which will be supported from a trenching vessel. During normal operations the plough or

    mechanical trenching device will deposit the excavated trench spoil either side of the trench.

    The trench will then be mechanically backfilled in a separate operation. Once the pipelay and

    backfilling operation have been completed a post lay survey will be carried out.

    It is anticipated that the pipeline trench will be approximately one metre deep, allowing the

    pipeline and umbilical to be buried below the natural seabed level to a depth sufficient to

    ensure at least 0.6 metres cover over the top of the pipe. This figure has been chosen to

    minimise upheaval buckling and subsequently the need for rock dumping. The pipeline

    corridor width has yet to be confirmed, however it is envisaged that it will be in the order of

    approximately 20 metres, including the profile of trench and spoil piles. This figure of 20

    metres has been used as it provides the maximum width a typical trenching device can trench.

    Given a 20 metre trench width a total effected footprint on the seabed of 440,000 square

    metres, based on a 22 kilometre pipeline, is envisaged.

    For the trenching of the umbilical it is assumed that a 0.75 metre trench corridor will be

    required for the entire 22 kilometre umbilical line. A tota l effected footprint on the seabed of

    A 16,500 square metres is therefore expected.

    The pipeline route survey found that along the majority of the pipeline route seabed sediments

    comprise of intermittent layers of very loose to medium dense slightly silty sand with extensive

    chalk outcrops with numerous cobbles and boulders also present. There are also small areas ,

    approximately half way along the route, where the seabed comprises loose to medium silty

    sand with occasional shell fragments. Towards the landward end of the pipeline route seabed

    sediments comprised of very loose to medium silty sand with occasional gravel, and numerous

    cobbles and boulders, becoming less gravelly and with fewer boulders as the seabed shoals

    (Gardline, 2011). These different sediments will be considered when installing the pipeline

    however they are not considered to pose an issue with the installation of the pipeline, any

    boulders over 0.4 metres will be displaced if necessary. Trenching and backfilling operations

    are expected to take a total of nine days to complete.

    Spot rock dumping along the pipeline may be required if the post -installation (out of

    straightness) survey shows remedial dumping is required to mitigate upheaval buckling in

    specific locations (Figure 2.8). Further rock dump will be required at a permanent subsea

    crossing location, where the new Juliet pipeline and umbilical crosses the existing CMS 26

    inch export and 4 inch methanol pipelines (PL929 & PL930 respectively). GDF SUEZ E&P UK

    is committed to limiting the quantity of rock dumped to keep the impact on the environment

    and other users of the sea to a minimum. It is currently envisaged that a maximum of up to

    23,000 tonnes may be required for spot rock dumping along the Juliet development to the

    Pickerill A Platform covering a total area of 4,600 square metres. This assumes the rock will

    be placed at locations of larger imperfections along the pipeline and the 23,000 tonnes will

    be laid as spot rock dumps along the proposed route, apart from the permanent c rossing

    location where an estimated 2,800 tonnes is required. It has been assumed that the minimum

    practical rock placement for the vessel is 2.5 tonnes per metre, which results in a minimum

    rock dump height of approximately 0.3 metres based on a rock berm slope of 30 percent.

    23,000 tonnes is currently an initial worst case estimate of the quantity of rock which will be

    dumped along the proposed pipeline route and has been calculated based on the sediments

    found over the Juliet development location to Pickerill A pipeline route and previous rock

    dumping experience within the vicinity of the proposed development. The total predicted rock

    volume and tonnage will be revisited during detailed design and will be included as part of the

    pipeline works authorisation.

  • Classification - Extended

    GDF SUEZ E&P UK Ltd Juliet Field Development Environmental Statement

    JF00-01-EB-108-00001 Rev C1 Page 38 of 194

    All GDF SUEZ E&P UK Ltd Contracts

    Figure 2.8. Example of a Spot Rock Dumping Operation over a Fallpipe (AoD, 2009)

    Pipeline and Umbilical Tie-Ins

    Fabricated spool-pieces