JSWEnergy Hedge 090511

download JSWEnergy Hedge 090511

of 21

Transcript of JSWEnergy Hedge 090511

  • 8/6/2019 JSWEnergy Hedge 090511

    1/21

    COMPANY RESEARCH REPORT October 28, 2

    COMPANY RESEARCH REPORTINITIATING COVERAGE

    JSW ENERGY LIMITED

    RECOMMENDATION: BUY

    CMP: Rs. 71

    TARGET: Rs. 95

    HOLDING PERIOD: 1-1.5 Years

    RISK PROFILE: AGGRESSIVE

    2011

  • 8/6/2019 JSWEnergy Hedge 090511

    2/21

    INITIATING COVERAGE- BUY : JSW ENERGY LT

    In a sweet spot due to structural deficitPower sector plays crucial role in the economic progress of the

    country given the importance of electricity in the economic

    activity. Currently, at the end of Jan 2011, the power generation

    capacity stood at 170.229 GW including the renewable energysources such as wind, solar etc. of about 16.787GW. However the

    peak power deficit in Jan 2011 is 11.1% and the normal power

    deficit is 7.6%. Rapid growth of the economy will place a heavy

    demand on electric power.

    Operative capacity to ramp up at a CAGR of 58%JSW energys capacity additions are in full swing with the total

    operative capacity reaching 6570MW by FY2017 against the

    management guidance of 12070 MW. We are very conservative in

    this regard, considering the potential execution delay.

    Potential improvement in margin aheadThe companys margin had affected notably when the fuel cost

    (coal) went up recently. In FY09 and FY11, the fuel cost per unit

    reached at high levels i.e. Rs.3.02 and 2.63 respectively. The

    probable cooling off of the coal prices can bring up the margin.

    Moreover, the coal mines acquisitions which have been in full

    swing, when completes, also, would bring down the fuel cost.

    Outstanding realizations among the peers despite

    concerns.

    The company has been maintaining good realization/unit ofelectricity, compared to the peers. ARPU (average realization per

    unit) remains in the range of Rs. 4.48 in FY08 to Rs. 4.49 in FY11.

    The same is estimated at Rs.4 for FY12E.

    Outlook and Valuations: Attractive; Initiate Coverage

    with BUYWe estimate units generated to post a CAGR of 99% from FY10-

    12E on the back of gigantic capacity build up and an average PLF

    of 0.75. Accordingly, the top line and bottom line, too, are

    estimated to grow at a CAGR of 87.8% and 33.9% respectively

    during the period. Our DCF model with 11.8% discount rate valuesthe company at Rs.95 per share. We initiate coverage with a BUY

    recommendation for a target price of Rs.95. Those with an

    aggressive risk appetite can consider investing in JSW energy at

    current level.

    Sector: Power

    Generation/Distribution

    EPS (TTM): Rs.5.13

    PE (TTM): 14.17

    Industry PE: 21.41

    Mkt. Cap (In crores): 11931.4

    52 Wk high: Rs.136.3

    52 Wk low: Rs.68.55P/BV: 2.10

    Beta: 0.76

    Yield (%): 1.03

    Face Value: 10

    Debt/Equity: 1.65

    Foreign Institutional

    Holding:

    3.94%

    Shareholding Pattern (%)

    Total of Promoter and Promoter Group 7

    Public Shareholding:

    Institutions 9

    Non-Institutions 1

    Total Public Shareholding 2

    0.00

    5000

    1000

    1500

    2000

    2500

    0.00

    50.00

    100.00

    150.00

    01-A

    r-10

    13-Ma-10

    22-Jun-10

    30-Jul-10

    08-Sep-10

    19-Oct-10

    29-Nov-10

    07-Jan-11

    17-Feb-11

    30-Mar-11

    JSWE vs Sensex

    JSW Energy SENSEX

    NSE Code: JSWENERGY

    BSE Code: 533148

    ISIN Code: INE121E01018

    Reuters Code: JSWE.BO

    Bloomberg Code: JSW IN

    Website: www.jsw.in

  • 8/6/2019 JSWEnergy Hedge 090511

    3/21

    INITIATING COVERAGE- BUY : JSW ENERGY LT

    Contents

    Business Summary .....................................................................................................................................................................

    Power Generation: .................................................................................................................................................................

    Power Trading: .......................................................................................................................................................................

    Power Transmission: ..............................................................................................................................................................

    Equipment manufacture and Mining: ....................................................................................................................................

    JSW Energy Projects Update ...................................................................................................................................................

    Investment Rationale .................................................................................................................................................................

    Industry ......................................................................................................................................................................................

    Financials & Valuations ..............................................................................................................................................................

    Sensitivity Analysis .....................................................................................................................................................................

    Risks ...........................................................................................................................................................................................

    Financial Highlights ....................................................................................................................................................................

    Financial Ratios ..........................................................................................................................................................................

    Financials Graph and Peer Group Comparison ..........................................................................................................................

    Analyst Notes And Company News ............................................................................................................................................

    http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204291http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204291http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282
  • 8/6/2019 JSWEnergy Hedge 090511

    4/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    1 May 3, 2011

    Chief among various reasons for

    this impressive performance is

    the exceptionally high PLF (Plant

    Load Factor) of the plant.

    Business Summary

    JSW Energy Ltd (JSWEL) is a fast growing power services comp

    that is part of the prestigious, $4 Billion valued Jindal South W

    (JSW) group. The group has diversified interests in areas rangfrom steel, energy, minerals and mining, aluminum, infrastruc

    and logistics, cement and information technology. Formed in

    year 1994, as a joint venture between the JSW group and Tract

    S.A. of Belgium, JSW Energy commenced operations in the y

    2000 as an Independent Power Producer (IPP), setting up a

    MW power generating unit. The company has the distinction

    being the first Independent Power Producer (IPP) to set

    operations in the state of Karnataka, initially installing 2 unit

    130 MW each, with both units generating power using corex

    and coal. Currently most of its revenue is derived from po

    generation. It is the goal and strategy of the company to becom

    leading full-service integrated power company in the Indian po

    sector with presence across the value chain i.e. both with backw

    integration and forward integration. As part of that strategy

    with the aim of managing sustainable growth and reducing pote

    constraints on such growth, it has entered into various j

    ventures for the development of transmission lines for its po

    generation projects, coal and lignite mining to procure captive

    supply for certain of its power generation projects and

    manufacture of steam turbines and generators for power plant

    is currently exploring opportunities in coal mine acquisitions, podistribution business and generation through non-conventi

    energy sources.

    Power Generation: The power generation business is with

    doubt the mtier of JSW Energy, averaging around 83% of the t

    sales for the last 5 years (FY06-FY10). The company has a ra

    strong expertise in this area, having been involved in the busin

    since 2000. For a considerable period of time (till FY09),

    company source of power generation was limited to its 260 MW

    X 135 MW) unit in Vijaynagar, Karnataka (JSWEL SBU 1). Throthis plant alone, the firm was able to generate income to the t

    of Rs. 1240 crores (in FY09). The Plant Load Factor is the rat

    actual units of power generated by a plant, to the maximum po

    that could theoretically be generated by the power plant during

    contract period.

    JSW energy, already, has

    presence in coal mining,

    equipment manufacturing,

    Transmission and power

    trading and, now, is aiming to

    enter distribution. Currently,

    major chunk of the revenue is

    derived from power

    generation. It is the goal and

    strategy of the company to

    become a leading full-service

    integrated power company in

    the Indian power sector with

    presence across the value

    chain i.e. both with backward

    and forward integration. .

  • 8/6/2019 JSWEnergy Hedge 090511

    5/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    2 May 3, 2011

    The second units of Barmer

    project (135MW) and Ratnagiri

    project (300MW) have got

    commercial operation dates

    during FY11 to take the total

    operative capacity to 1430 MW.

    The power is sold to state utility

    boards through short-term

    power off take arrangements,

    where the price is subject to

    rapid market demand

    luctuations

    In July 2009, the company added to its power generatio

    portfolio by commencing the first of its 600 mw (1 X 300 MW

    coal plant (JSWEL SBU II). This plant too is located in Vijaynaga

    The second unit (2 X 300 MW) was operationalized in Septemb

    2009. In November 2009, the firm also started operations of thfirst unit of its 1080 MW ( RWPL 1 X 135 MW) lignite power pla

    in Barmer, Rajasthan, taking the total capacity to 995 mw by t

    end of fiscal year 2010. And in FY11, the second units of Barm

    project (135MW) and Ratnagiri project (300MW) have g

    commercial operation dates (COD) to take the total operati

    capacity to 1430 MW. JSWELs big aim is to reach a targ

    capacity of 11390 MW by 2015. As of now, the company has

    1430 MW of operational generating capacity and 1490 MW

    generating capacity in the construction or implementation phas

    As far as it sales are concerned, the company secures its powgeneration revenues through a combination of long term PPA

    (Power Purchase Agreements) and short term merchant pow

    sales with various state-owned utilities (SEBs), power tradin

    companies and industrial consumers.

    Power Trading: The Company has been in the power tradin

    business since 2006 and it is carried out by its subsidiar

    JSWPTC (JSW Power Trading Corporation). The Central Electrici

    Regulatory Commission (CERC) has granted the company with a

    F category license, the highest license in India, for pow

    trading. JSWPTC sells power of not only the JSWEL but fro

    external power supplies as well. The power is sold to state utili

    boards through short-term power off take arrangements, whe

    the price is subject to rapid market demand fluctuations. Th

    time period of these short-term arrangements ranges fro

    several hours to 11 months.

    Power Transmission: Power transmission is another powrelated area that the firm has been involved in, rendered throug

    yet another subsidiary JSWPTL (JSW Power Transco Limited). T

    other partner in the venture is the government unit-MSETC

    (Maharashtra State Electricity Transmission Company Limited

    Through its transmission lines the company transmits power fro

    power generation units to state and national grids.

  • 8/6/2019 JSWEnergy Hedge 090511

    6/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    3 May 3, 2011

    Equipment manufacture and Mining: Equipm

    manufacture and mining activities make up the remaining par

    the companys business. Both these activities are condu

    through joint ventures. In 2008, JSWEL signed a deal with Japan

    conglomerate- Toshiba Corporation, for the design, engineer

    manufacturing, assembling and sale of sub-critical and su

    critical steam turbines and generators with capacities ranging f

    500MW to 1000MW. However JSWELs stake in the venture is

    20% so it is not expected to contribute much in terms of cost no

    Project Place Fuel Capacity(MW)

    Expectedoperational

    year

    Ratnagiri I MaharashtraSub critical imported

    coal1200 FY12

    Rajwest I Rajasthan Lignite 1080 FY12

    Kutehr Hydro Project Phase IHimachal

    PradeshHydro power 80 FY14

    Ratnagiri II Phase I MaharashtraSub critical imported

    coal800 FY14

    West Bengal Power project

    Phase IWest Bengal Coal 300 FY15

    Rajwest Power Ltd. II Phase I Rajastan Lignite 135 FY15

    Ratnagiri II Phase II MaharashtraSub critical imported

    coal800 FY15

    Chattisgarh Power project

    Phase IChattisgarh Coal 660 FY16

    Ratnagiri II Phase III MaharashtraSub critical imported

    coal800 FY16

    Kutehr Hydro Project Phase IIHimachal

    PradeshHydro power 80 FY16

    Rajwest Power Ltd. II Phase II Rajasthan Lignite 135 FY17

    JSWEL Vijayanagar Karnataka Sub critical coal 660 FY17

    Ratnagiri II Phase IV Maharashtra Sub critical importedcoal

    800 FY17

    Source: JSWEL, Hedge Research

    In 2008, JSWEL signed a deal

    with Japanese

    conglomerate- Toshiba

    Corporation, for the design,

    engineering, manufacturing,

    assembling and sale of sub-

    critical and super-critical

    steam turbines and

    generators.

    JSW Energy Projects Update

  • 8/6/2019 JSWEnergy Hedge 090511

    7/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    4 May 3, 2011

    The attempts of the company

    or acquiring a couple of coal

    mines abroad are in full

    swing. The Company had

    acquired a majority stake in

    SACMH (South African Coal

    Mining Holding Ltd) in 2009.

    will it benefit much in terms of revenue. Production under Pha

    would commence in 2011 and initially, the unit would prod

    steam turbine and generator (STG) parts. By 2012, it would s

    manufacturing STG sets with a target production capacity of 3

    mega watt per annum by 2014. The JV is targeting sales of $million (around Rs 1,840 crore) only by the end of 2015 fiscal.

    companys mining activities are conducted in the state

    Maharashtra and Orissa. The Maharashtra mining activity is car

    out for the purpose of securing lignite for the (8X 135 MW) 1

    mw lignite plant in Ratnagiri, Maharashtra.

    Investment Rationale

    The key facts which make the stock a flattering one are:

    1) A potential margin outlook supported by the coal macquisitions which will eventually bring in the fuel prices (fuel c

    comprise more than 70% of the total expenditure book) u

    control. In the near future, the margins are expected to go up o

    coal prices come down from the current exorbitant lev

    Meanwhile, in the long run, the company is expected to ben

    from the progressing coal mine acquisitions at the internati

    level, as the price determination will come under the control of

    company.

    2) The business integration model (Both backward integra

    and forward integration) that the company aiming for makes

    unique one. The processes of combining different business

    management systems so that they may interact with one ano

    and thus be used to enhance an enterprise business strategy

    respect of the backward integration, fuel security and tur

    manufacturing are the areas to be possessed, which have alre

    been initiated by the company. The attempts of the company

    acquiring a couple of coal mines abroad are in full swing.

    Company had acquired a majority stake in SACMH (South Afr

    Coal Mining Holding Ltd) through acquisition of shares in R

    Bafokeng Capital (RBC) and the shares of Mainsail which holdsadditional 5% in SACMH. SACMH is a listed South African Comp

    with coal mining assets in the Witbank region with mines in Ulam

    and Illanga. The mines have reserves of about 50 million ton

    with exportable surplus in the range of 14-20 million ton

    Besides, SACMH has allocations in RBCT Phase V of about

    million tpa as also coal preparation plant and railway siding at

    mine site.

    In the outlook, the margins are

    expected to go up once coal

    prices come down from the

    current exorbitant levels

  • 8/6/2019 JSWEnergy Hedge 090511

    8/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    5 May 3, 2011

    Despite the augmented

    generation in the country, the

    energy deficit, as on Q4FY11,

    igured at 13.8%.

    Regarding the forward integration, electricity transmission an

    distribution are the targeted areas, of which JSW has entered th

    former and is sketching to the latter through diversified range joint venture agreements and subsidiaries.

    3) Company is aggressively in the path of ramping up

    electricity generation capacity, which is, currently, stands at a

    operative 1730MW with the commissioning of 2nd phase

    Ratnagiri plant. It is expected to add a further 2880MW operativ

    capacity to take the total figure at 4310MW. Apart from tha

    there are some projects in pipeline which are expected to

    operational beyond 2015. When we take these projects also in

    account, the capacity will touch 6570MW by the fiscal 2017.

    4) The huge disparity in the demand and supply of power

    the country: Despite the augmented generation in the country, t

    energy deficit, as on Q4FY11, figured at 13.8%. As on Dec 20

    the total energy deficit was at 10.1%. The mismatch between t

    two is unlikely to narrow immensely in the future as the growth

    the demand is expected to shoot up in a gigantic way and t

    capacity acceleration will not be sufficient to meet it.

    JSW Energy Ltd

    Backward Integration

    MiningEquipmentManufactu

    ring

    Forward Integration

    Transmission

    PowerTrading

    Distribution(Targeting)

    There are some projects in

    pipeline which are expected to

    be operational beyond 2015.

    When we take these projects

    also into account, the capacity

    will touch 6570MW by the

    fiscal 2017.

  • 8/6/2019 JSWEnergy Hedge 090511

    9/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    6 May 3, 2011

    Though new generation capacity

    addition so far in the current five

    year plan period is greater than

    what it was achieved in each of

    earlier plans, the country is all

    expected to fall short of its revised

    11th five year plan.

    Industry

    Power sector plays crucial role in the economic progress of th

    country given the importance of electricity in the econom

    activity. Rapid growth of the economy will place a heavy deman

    on electric power. Reforms in this sector, for making the pow

    sector efficient and more competitive, have been under way f

    several years and while there has been some progress, shortag

    of power and lack of access continues to be a major constraint o

    the economic growth. Currently, at the end of March 2011, tpower generation capacity stood at 173.626 GW including th

    renewable energy sources such as wind, solar etc. of abo

    16.787GW. However the peak power deficit in Jan 2011 is 11.1

    and the normal power deficit is 7.6%. With the country's pea

    power demand (as on Jan 2011) being 122.470 GW well belo

    the country's current generation capacity, the lower plant loa

    factors on account of scarcity of fuel/feedstock or less efficie

    aged power plants as well as high T&D losses and season

    nature of renewable power capacity. So far in the 11th five ye

    plan period (2007-08 to 20011-12) the country has added abo

    37.900 GW of which about 9.026 GW was renewable energ

    Though new generation capacity addition so far in the curre

    five year plan period is greater than what it was achieved in eac

    of earlier plans, the country is all expected to fall short of i

    revised 11th five year plan target to about 63GW.

    170

    82.2852.53

    35.19

    Total

    installed

    capacity

    State

    sector

    Central

    sector

    Private

    sector

    Source: JSWEL, Hedge Research

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017

    Expected Operative Capacity Build up

    (in MWs)

  • 8/6/2019 JSWEnergy Hedge 090511

    10/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    7 May 3, 2011

    The originally envisaged target

    or current five year Plan at the

    start of the plan period was 78

    GW and was later revised to

    62,374 MW. Capacity addition

    of 32,032 MW was only

    achieved till December 31,2010. At the end of the plan,

    only 50000 MW is likely to be

    added. Meanwhile, the Power

    Ministry has set a target of

    100,000 MW of power capacity

    addition in the upcoming

    Twelfth Plan (2012-17).

    Source: CEA

    The double digit peak power deficit is largely on the cyclic

    slowdown in the industrial sector which began in fiscal 2008 g

    compounded by the global slowdown and was arrested only at t

    beginning of fiscal 2010. In the fiscal 2010, electricity generatio

    emerged from the lackluster growth witnessed in fiscal 2009 anequaled its performance in fiscal 2008. This was achieved despi

    constraints imposed by inadequate availability of coal and th

    dismal hydel-generation scenario due to sub-normal monsoo

    During fiscal 2010, the total energy deficit came down to 10.1

    from 11% during the fiscal 2009, mainly due to increase

    electricity generation. The availability of gas from the KG bas

    (D6) resulted in better utilization of capacity and higher Pla

    Load Factor (PLF) as high growth in electricity generated from g

    based plants.

    The originally envisaged target for current five year Plan at t

    start of the plan period was 78 GW and was later revised

    62,374 MW. Capacity addition of 32,032 MW was only achieve

    till December 31, 2010. At the end of the plan, only 50000 MW

    likely to be added. This is largely on account of environment

    issues as well as delay in coal linkages etc apart from equipme

    supply delays. Meanwhile, the Power Ministry has set a target

    100,000 MW of power capacity addition in the upcoming Twelf

    Plan (2012-17) (2012-13 to 2016-17), of which the share

    thermal power being 76.6 GW, hydel power being 20 GW an

    Nuclear at 3.4 GW. In the 12th five year plan period the countis envisaging a technology transition with embrace of sup

    critical technology in a bigger way. Though super critic

    technology projects were introduced in the 11th five year pla

    period in a smaller way, the share of super critical technology

    all set to increase to 59% (or 43640 MW) of the coal generatio

    capacity in the 12th five year plan.

    On one hand with rising demand for electricity as double dig

    peak demand, the sector is faced with numerous challenges su

    fuel availability, poor financial conditions of state electriciboards as well as various project risks ranging from funding

    environmental etc. The greatest weakness is on the distributio

    front which is entirely the domain of the States. AT&C losses

    most of the State Power Utilities (SPUs) remain as high as 40

    and this has made them financially sick and unable to inve

    adequately in additional generating capacity.

    111034

    456037367

    16787

    169748

    19509

    Indian Energy sources

  • 8/6/2019 JSWEnergy Hedge 090511

    11/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    8 May 3, 2011

    The greatest weakness is on the

    distribution front which is entirelyunder the domain of the States.

    AT&C losses of most of the State

    Power Utilities (SPUs) remain as high

    as 40%.

    Merchant power sales are estimated

    on an average of 66% for FY11-12E.

    Source: JSWEL, Hedge Research, Ace Equity

    For the same reason, these utilities have had only limited succ

    in attracting private investors to set up power plants. The Cen

    with a view to encouraging generation and reducing transmis

    and distribution losses, announced extension of tax holiday for

    power sector by one more year till March 31, 2012. The extensof tax break is part of the government's efforts to scale up

    power generation capacity to meet the growing needs. The

    exemption would benefit projects that are expected to take of

    the remaining period of the XI Plan (2007-12), including u

    mega power projects (UMPPs).

    Financials & Valuations

    Top line to grow at a CAGR of 99%

    The financials look impressive with both the topline and bottom

    inching up by 49% and 46% respectively. The FY10 seems to b

    resumption of growth for the company from the badly affec

    financial figures of FY09. In FY09, while the top line remained

    the profit after tax saw a decline of 32.46%, which was mainly

    account of a surge in the fuel cost. The FY11 financials, too, h

    been decent with the sales shooting up by 82%. Going forw

    we expect, in accordance with the capacity ramp up, the top lin

    grow at a CAGR of 99% during FY10-12E.

    Balanced Sales mix

    JSW Energy, unlike others, has a more or less balanced mix

    merchant power and Power purchase agreements (PPAs) in

    sales portfolio. The former to total sales were 68%, 61% and 7

    respectively for FY08, FY09 and FY10 respectively. The sam

    estimated to be averaged at 66% for FY11-12E. The PPAs (Po

    Purchase Agreements) and short term merchant power sales

    with various state-owned utilities (SEBs), power trading compa

    and industrial consumers like West Bengal Mineral Trading Development Corp (WBMTDC), Government of Chhattisg

    (GoCG) etc

    0

    2000

    4000

    6000

    8000

    10000

    Revenue Break up

    Revenues

    PBIDT

    PBDT

    PBT

    PAT

  • 8/6/2019 JSWEnergy Hedge 090511

    12/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    9 May 3, 2011

    Source: JSWEL, Ace Equity, Hedge Research

    FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12E

    Short term sales 0 833 1527 1425 1259 3671.41 6004 13600.12

    Long term sales 1826 1071 386 643 797 1499.59 3012 7006.125

    0

    5000

    10000

    15000

    20000

    25000

    MillionUnits(Kwh)

    Yearwise Sales Mix

    Q3FY09 Q4FY09 Q1FY10 Q2FY10 Q3FY10 Q4FY10 Q1FY11 Q2FY11 Q3FY11 Q4FY11

    Short term sales 374 300.44 416.8 859.81 1203.0 1217.8 1260.6 1139.8 1605.3 2013

    Long term sales 159 217.56 104.2 351.19 444.96 573.12 566.37 641.16 790.68 1000

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    Million

    Units(Kwh)

    Quarterwise Sales Mix

  • 8/6/2019 JSWEnergy Hedge 090511

    13/21

    INITIATING COVERAGE- BUY : JSW ENERGY LTD

    10 May 3, 2011

    We expect the average

    realization to be Rs.4 for

    FY12E.

    Though there is a potential

    or marginal upside

    movement in the coal price,

    it is not likely to affect our

    valuation significantly as

    we have factored in the

    same at the current higher

    levels.

    Realization to endure at reasonable levels despite the concern

    Since the short term sales put in higher realization for the compa

    the higher proportion of short term sales translates into the bet

    average realization, which stood at Rs.4.44 in FY10 and has behovering in a range of Rs. 4 -4.5. We expect the same to remain at

    4 for FY12E.

    Source: JSWEL, Hedge Researc

    No significant room for change in our valuation by fuel cost

    The fuel cost has been skyrocketed to a higher level in the

    couple of years and now stands in $120-$130/ton range. Thou

    there is a potential for marginal upside movement in the price, i

    not likely to affect our valuation significantly as we have factored

    the fuel cost at higher levels. Fuel cost has been one of m

    sensitive factors to the stock. Thermal coal is the largest source

    energy for the generation of electricity worldwide. The price of chas been buoyed by flooding in Australia's coal-rich state

    Queensland, which interrupted supplies from the world's top therm

    coal exporter. Huge demand for energy resources in China and In

    has pushed the price of thermal coal to an all time high.

    4.48

    6

    4.44

    5.09

    4.34 4.43 4.24.49

    4

    5.25

    7.08

    4.97

    5.77

    4.654.87

    4.5

    4.95

    4.36

    3.413.59 3.59 3.63

    3.3

    FY08 FY09 FY10 Q1FY11 Q2FY11 Q3FY11 Q4FY11 FY11 FY12E

    Average Realisation/Unit Short term Realisation/Unit Long term realisation

  • 8/6/2019 JSWEnergy Hedge 090511

    14/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    11 May 3, 201

    We see the fuel cost per

    unit for FY11E and FY12E to

    be Rs. 2.73 and 2.48

    respectively

    Having accounted for theskyrocketed coal price, the

    profits is expected to grow

    at a CAGR of 34% during

    FY10-FY12E

    Source: JSWEL, Hedge Research, Ace Eq

    The fuel cost per unit of the company has been quite vol

    since FY08. As the company is highly depending on coal as f

    the fuel cost/unit had shot up to an all time high of Rs.3.0

    FY09 on account of the surge in the international coal pric

    $125/ton in FY09. It, then, came down and bounced back in F

    and FY11 respectively. We see the same for FY12E as Rs.2.48

    Profit to post growth at a CAGR of 34%

    With the surge in the coal price and other components in

    expenditure book, the EBITDA and PAT growth confined to

    tune of 32% and 13% respectively for FY11 to touch Rs.1

    crore and 842 crore respectively. Having accounted for

    skyrocketed coal price, the profits are expected to grow a

    CAGR of 34% during FY10-FY12E, driven by a gigantic ramp u

    the capacity and consistent realization ra

    Discounted cash flow values the stock at Rs.95 per share

    Our valuation model based on discounted cash flow give

    value of Rs.95 per share to JSW energy. It has 33.8% ups

    from the current market price of Rs.71. we have used a disco

    rate of 11.8% for the model.

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12E

    Fuel cost per unit

  • 8/6/2019 JSWEnergy Hedge 090511

    15/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    12 May 3, 201

    Sensitivity Analysis

    It has been found from our analysis that JSW energy is very sensitive to

    factors like coal price, plant load factor and realization per unit (ARPU). We h

    done a sensitivity analysis of share price to those factors.

    Average Realization per Unit

    Coal Price

    @58003.75 4 4.25 4.5

    PLF

    0.70 16 52 89 125

    0.75 56 95 133 172

    0.80 95 137 178 220

    0.85 135 179 223 267

    Taking the coal price constant at Rs.5800/ton, PLF between 70% and 80% andARPU between Rs.3.75 and 4.5, the stock is found to have potential to move

    the range of Rs.16 to 267.

    Average Realization per Unit

    Load Factor

    @0.753.75 4 4.25 4.5

    CoalPrice 5200 91 130 169 207

    5500 73 112 151 190

    5800 56 95 133 172

    6200 32 71 110 149

    When we consider the plant load factor at 75%, the coal price between Rs. 52

    and 6200/ton and the ARPU in the range of Rs.3.75 and 4.5, the stock could

    move amid Rs.91 and 149.

    Coal Price

    ARPU @4.00 5200 5500 5800 6200

    P

    LF

    0.70 88 70 52 29

    0.75 130 112 95 71

    0.80 172 155 137 113

    0.85 215 197 179 156

    Also, we also found that the stock may move in the range of Rs.88 and 156

    when we take the ARPU at Rs.4, PLF in the range of 70% to 85% and the coal

    price between Rs.5200 and 6200/ton.

  • 8/6/2019 JSWEnergy Hedge 090511

    16/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    13 May 3, 201

    Due to environmental

    concerns, Indias annual

    thermal coal production

    growth is slowing to 1-2

    per cent now from 6-7 per

    cent earlier.

    Risks

    But among all these, the sector reels under certain major issu

    which act as a bottleneck for the growth of the industry. JS

    Energys earnings and stock valuations are highly sensitive availability of coal and its prices, given that about 46 per cent of

    planned capacity, about 11,390 Mw, is dependent on import

    coal. Fuel availability and its high leveled price is the chief proble

    that the company faces, which further puts brakes on the pl

    process. Thermal coal a key input for power generation h

    become costly in the global markets in the recent months. Sup

    constraints for domestic coal remain and are expected to contin

    going forward. Further, industry estimates suggest that dema

    from China and India could hold the price at current levels or mo

    In the long run, given the nuclear crisis in Japan, any increase

    preference towards coal-based power plants would only lead

    further pressure on coal prices. The situation could have be

    better, had the supply of domestic coal (which costs less) be

    sufficient. Due to environmental concerns, Indias annual therm

    coal production growth is also slowing to 1-2 per cent now fr

    6-7 per cent earlier. Recently, Coal India lowered its product

    growth to 3 per cent. Since domestic coal supply constrai

    remain to continue, some public and private sector entities ha

    embarked upon imported coal as a means to bridge the deficit. T

    has led to some Indian entities to take upon the task of purchasi

    developing and operating coal mines in international geographiWhile this is expected to secure coal supplies it has again thro

    upon further challenges. The failure to achieve the planned targ

    from the captive coal blocks presents itself as a major challenge

    the power sector, as only 24 blocks have become operational out

    the total 210. Experts believe that the non-operational status

    majority of these blocks is attributed to land acquisition (R&

    issues, permit delays and infrastructure problems.

    Declining merchant power realization rates, too, stand as anoth

    concern as almost 67 per cent of JSWs current capacity caters

    merchant power sales. The rate is always competitive and bound

    volatile. Hence, though it remains well above the PPA rate, t

    inability to lock in the cost and the downward trend of t

    merchant rate are seemed to be the key concerns for the compa

  • 8/6/2019 JSWEnergy Hedge 090511

    17/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    14 May 3, 201

    Financial Highlights

    DESCRIPTION Mar-10 Mar-09 Mar-08

    Inc / Exp PerformanceGross Sales 2355.09 1835.02 1293.14

    Total Income 2429.26 1852.16 1326.07

    Total Expenditure 1141.61 1303.17 416.68

    PBIDT 1287.65 548.99 909.39

    PBIT 1151.55 488.78 850.79

    PBT 867.85 367.84 762.24

    PAT 745.49 276.69 625.27

    Cash Profit 881.59 336.90 683.87

    Sources of Funds

    Equity Paid Up 1640.05 546.57 514.76

    Reserves and Surplus 3138.47 932.14 488.87

    Net Worth 4778.52 1478.71 1003.63

    Total Debt 7870.14 5927.16 2272.66

    Capital Employed 12665.56 7422.03 3365.30

    Application of Funds

    Gross Block 3683.89 1169.07 1139.60

    Investments 1434.44 170.47 20.73

    Cash and Bank balance 604.82 175.10 294.94

    Net Current Assets -267.83 -1226.23 0.65

    Total Current Liabilities 1900.64 1766.19 502.82

    Total Assets 12665.56 7422.03 3365.30Cash Flows

    Cash Flow from Operations 846.96 468.31 801.19

    Cash Flow from Investing activities -3582.31 -4045.99 -2251.08

    Cash Flow from Finance activities 4386.14 3461.84 1467.31

    Free Cash flow -2422.29 -3540.36 -1604.85

    Market Cues

    Close Price (Unit Curr.) 111.80 0.00 0.00

    High Price (Unit Curr.) 123.90

    Low Price (Unit Curr.) 99.90

    Market Capitalization 18335.76 0.00 0.00

    Adjusted EPS 4.55 2.02 4.86

    Price / Book Value(x) 3.84 0.00 0.00

    CEPS 5.38 2.47 5.31

    Equity Dividend % 7.50 0.00 20.00

    Source: Ace Equity

  • 8/6/2019 JSWEnergy Hedge 090511

    18/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    15 May 3, 201

    Financial Ratios

    Description Mar-10 Mar-09 Mar-08

    Operational & Financial Ratios

    Earnings Per Share (Rs) 4.55 5.06 12.15

    Adjusted EPS (Rs.) 4.55 2.02 4.86

    CEPS(Rs) 5.38 2.47 5.31

    DPS(Rs) 0.75 0.00 2.00

    Adj DPS(Rs) 0.75 0.00 2.00

    Book Value (Rs) 29.14 27.05 19.50

    Adjusted Book Value (Rs) 29.14 10.82 7.80

    Tax Rate(%) 14.10 24.78 17.97

    Dividend Pay Out Ratio(%) 16.50 0.00 16.47Margin Ratios

    PBIDTM (%) 54.68 29.92 70.32

    EBITM (%) 48.90 26.64 65.79

    Pre Tax Margin(%) 36.85 20.05 58.94

    PATM (%) 31.65 15.08 48.35

    CPM(%) 37.43 18.36 52.88

    Performance Ratios

    ROA (%) 7.42 5.13 18.58

    ROE (%) 23.83 22.29 62.30

    ROCE (%) 11.47 9.06 25.28

    Asset Turnover(x) 0.23 0.34 0.38

    Inventory Turnover(x) 11.67 58.89 43.03

    Debtors Turnover(x) 11.54 17.80 18.66

    Sales/Fixed Asset(x) 0.97 1.59 1.13

    Sales(x)/Working Capital -8.79 -1.50 0.00

    Growth Ratios

    Net Sales Growth(%) 28.34 41.90

    Core EBITDA Growth(%) 134.55 -39.63

    EBIT Growth(%) 135.60 -42.55

    PAT Growth(%) 169.43 -55.75

    EPS Growth(%) -10.21 -58.32

    Financial Stability Ratios

    Total Debt/Equity(x) 1.65 4.01 2.26

    Current Ratio(x) 0.93 0.31 1.32

    Quick Ratio(x) 0.72 0.29 1.24

    Interest Cover(x) 4.06 4.04 9.61

    Source: Ace Equity

  • 8/6/2019 JSWEnergy Hedge 090511

    19/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    16 May 3, 201

    Financials Graph and Peer Group Comparison

    Source: Multiple Sources

    Peer Group Comparison (Consolidated)

    Company NameYearEnd

    Net Sales PBIDT PATAdj.

    EPS(Rs)PBIDTM% PATM% ROCE% ROE%

    Rel.Power 201003 20.72 717.03 683.89 2.85 3459.98 0 4.47 4.84

    Tata Power 201003 18985.84 4442.08 2138.64 82.91 23.38 11.26 12.54 19.74

    NTPC 201003 48311.5 16021.7 8837.7 10.72 32.98 18.19 12.64 14.73

    Adani Power 201003 434.86 275.74 170 0.78 63.41 39.09 2.02 4.22

    NHPC 201003 5227.32 4783.17 2277.56 1.77 91.5 43.57 8.52 10.15

    Source: Ace Equity

    Revenues

    PAT

    EPS

    PE

    0.00

    10000000000.00

    20000000000.00

    30000000000.00

    40000000000.00

    50000000000.00

    60000000000.00

    70000000000.00

    80000000000.00

    90000000000.00

    FY08 FY09 FY10 FY11 FY12E

    Revenues 12930000000. 18350200000. 23550900000. 44280000000. 83800000000.

    PAT 6252700000.0 2766900000.0 7454900000.0 8420000000.0 13388500000.

    EPS 3.81 1.69 4.55 5.13 8.16

    PE 19.12 43.21 16.04 14.20 8.93

    19.12 43.21 16.04 14.20 8.93

    Financials Graph

  • 8/6/2019 JSWEnergy Hedge 090511

    20/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    17

    Analyst Notes And Company News

  • 8/6/2019 JSWEnergy Hedge 090511

    21/21

    INITIATING COVERAGE- BUY : JSW ENERGY L

    18

    Researched and prepared by:

    Muhammed Aslam E

    Fundamental Analyst

    Email:[email protected]

    Ph:(0484) 3040400, 3040419

    In co-operation with:

    Neha Mahajan

    Fundamental Analyst

    Email:[email protected]

    Amar Chandramohan

    Sr. Fundamental Analyst

    Email:[email protected]

    Krishnan Thampi K

    Head of Research and Strategies

    Email:[email protected]

    HEDGE RESEARCH & STRATEGIES GROUP

    Head of Research: Krishnan Thampi K

    Sr. Fundamental Analyst: Amar Chandramohan

    Jr. Fundamental Analyst: Muhammed Aslam E

    Jr. Fundamental Analyst: Neha Mahajan

    Sr. Equity Technical Analyst: Anish Chandran C V

    Sr. Commodity & Equity Technical Analyst: Kesavamoorthy B

    Futures & Options Analyst: Yunus Ismail

    Access all our research reports online at www.HedgeEquities.com

    DIRECT ALL RESEARCH QUERIES TO:

    Research & Strategies Group

    Hedge Equities Ltd

    12 Floor, -Mini Muthoot Tech Towers

    Kaloor, Kochi682017, Kerala, India

    Phone: (0484) 3040400

    Email: [email protected]

    DisclaimerThe information contained in our report does not constitute an offer to sell securities or the solicitation of an offer to buy, any security. This report is prepared fo

    private circulation only. The information in our report is not intended as financial advice. Hedge Equities Ltd does not undertake the responsibility for an

    investment decision taken by the readers based on this report. Moreover, none of the information in the research report is intended as a prospectus within thmeaning of the applicable laws of any jurisdiction. The information and opinions contained in our research reports have been compiled or arrived at from

    sources believed to be reliable in good faith, but no representation or warranty, express or implied, is made by Hedge Equities Ltd, to their accuracy. Moreove

    you should be aware of the fact that investments in securities or other financial instruments involve risks. Past results do not guarantee future performance.

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]