JSWEnergy Hedge 090511
-
Upload
paramasivan-vinayakam -
Category
Documents
-
view
230 -
download
0
Transcript of JSWEnergy Hedge 090511
-
8/6/2019 JSWEnergy Hedge 090511
1/21
COMPANY RESEARCH REPORT October 28, 2
COMPANY RESEARCH REPORTINITIATING COVERAGE
JSW ENERGY LIMITED
RECOMMENDATION: BUY
CMP: Rs. 71
TARGET: Rs. 95
HOLDING PERIOD: 1-1.5 Years
RISK PROFILE: AGGRESSIVE
2011
-
8/6/2019 JSWEnergy Hedge 090511
2/21
INITIATING COVERAGE- BUY : JSW ENERGY LT
In a sweet spot due to structural deficitPower sector plays crucial role in the economic progress of the
country given the importance of electricity in the economic
activity. Currently, at the end of Jan 2011, the power generation
capacity stood at 170.229 GW including the renewable energysources such as wind, solar etc. of about 16.787GW. However the
peak power deficit in Jan 2011 is 11.1% and the normal power
deficit is 7.6%. Rapid growth of the economy will place a heavy
demand on electric power.
Operative capacity to ramp up at a CAGR of 58%JSW energys capacity additions are in full swing with the total
operative capacity reaching 6570MW by FY2017 against the
management guidance of 12070 MW. We are very conservative in
this regard, considering the potential execution delay.
Potential improvement in margin aheadThe companys margin had affected notably when the fuel cost
(coal) went up recently. In FY09 and FY11, the fuel cost per unit
reached at high levels i.e. Rs.3.02 and 2.63 respectively. The
probable cooling off of the coal prices can bring up the margin.
Moreover, the coal mines acquisitions which have been in full
swing, when completes, also, would bring down the fuel cost.
Outstanding realizations among the peers despite
concerns.
The company has been maintaining good realization/unit ofelectricity, compared to the peers. ARPU (average realization per
unit) remains in the range of Rs. 4.48 in FY08 to Rs. 4.49 in FY11.
The same is estimated at Rs.4 for FY12E.
Outlook and Valuations: Attractive; Initiate Coverage
with BUYWe estimate units generated to post a CAGR of 99% from FY10-
12E on the back of gigantic capacity build up and an average PLF
of 0.75. Accordingly, the top line and bottom line, too, are
estimated to grow at a CAGR of 87.8% and 33.9% respectively
during the period. Our DCF model with 11.8% discount rate valuesthe company at Rs.95 per share. We initiate coverage with a BUY
recommendation for a target price of Rs.95. Those with an
aggressive risk appetite can consider investing in JSW energy at
current level.
Sector: Power
Generation/Distribution
EPS (TTM): Rs.5.13
PE (TTM): 14.17
Industry PE: 21.41
Mkt. Cap (In crores): 11931.4
52 Wk high: Rs.136.3
52 Wk low: Rs.68.55P/BV: 2.10
Beta: 0.76
Yield (%): 1.03
Face Value: 10
Debt/Equity: 1.65
Foreign Institutional
Holding:
3.94%
Shareholding Pattern (%)
Total of Promoter and Promoter Group 7
Public Shareholding:
Institutions 9
Non-Institutions 1
Total Public Shareholding 2
0.00
5000
1000
1500
2000
2500
0.00
50.00
100.00
150.00
01-A
r-10
13-Ma-10
22-Jun-10
30-Jul-10
08-Sep-10
19-Oct-10
29-Nov-10
07-Jan-11
17-Feb-11
30-Mar-11
JSWE vs Sensex
JSW Energy SENSEX
NSE Code: JSWENERGY
BSE Code: 533148
ISIN Code: INE121E01018
Reuters Code: JSWE.BO
Bloomberg Code: JSW IN
Website: www.jsw.in
-
8/6/2019 JSWEnergy Hedge 090511
3/21
INITIATING COVERAGE- BUY : JSW ENERGY LT
Contents
Business Summary .....................................................................................................................................................................
Power Generation: .................................................................................................................................................................
Power Trading: .......................................................................................................................................................................
Power Transmission: ..............................................................................................................................................................
Equipment manufacture and Mining: ....................................................................................................................................
JSW Energy Projects Update ...................................................................................................................................................
Investment Rationale .................................................................................................................................................................
Industry ......................................................................................................................................................................................
Financials & Valuations ..............................................................................................................................................................
Sensitivity Analysis .....................................................................................................................................................................
Risks ...........................................................................................................................................................................................
Financial Highlights ....................................................................................................................................................................
Financial Ratios ..........................................................................................................................................................................
Financials Graph and Peer Group Comparison ..........................................................................................................................
Analyst Notes And Company News ............................................................................................................................................
http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204291http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204291http://c/Users/user/Desktop/JSWupdtd2.docx%23_Toc292204282 -
8/6/2019 JSWEnergy Hedge 090511
4/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
1 May 3, 2011
Chief among various reasons for
this impressive performance is
the exceptionally high PLF (Plant
Load Factor) of the plant.
Business Summary
JSW Energy Ltd (JSWEL) is a fast growing power services comp
that is part of the prestigious, $4 Billion valued Jindal South W
(JSW) group. The group has diversified interests in areas rangfrom steel, energy, minerals and mining, aluminum, infrastruc
and logistics, cement and information technology. Formed in
year 1994, as a joint venture between the JSW group and Tract
S.A. of Belgium, JSW Energy commenced operations in the y
2000 as an Independent Power Producer (IPP), setting up a
MW power generating unit. The company has the distinction
being the first Independent Power Producer (IPP) to set
operations in the state of Karnataka, initially installing 2 unit
130 MW each, with both units generating power using corex
and coal. Currently most of its revenue is derived from po
generation. It is the goal and strategy of the company to becom
leading full-service integrated power company in the Indian po
sector with presence across the value chain i.e. both with backw
integration and forward integration. As part of that strategy
with the aim of managing sustainable growth and reducing pote
constraints on such growth, it has entered into various j
ventures for the development of transmission lines for its po
generation projects, coal and lignite mining to procure captive
supply for certain of its power generation projects and
manufacture of steam turbines and generators for power plant
is currently exploring opportunities in coal mine acquisitions, podistribution business and generation through non-conventi
energy sources.
Power Generation: The power generation business is with
doubt the mtier of JSW Energy, averaging around 83% of the t
sales for the last 5 years (FY06-FY10). The company has a ra
strong expertise in this area, having been involved in the busin
since 2000. For a considerable period of time (till FY09),
company source of power generation was limited to its 260 MW
X 135 MW) unit in Vijaynagar, Karnataka (JSWEL SBU 1). Throthis plant alone, the firm was able to generate income to the t
of Rs. 1240 crores (in FY09). The Plant Load Factor is the rat
actual units of power generated by a plant, to the maximum po
that could theoretically be generated by the power plant during
contract period.
JSW energy, already, has
presence in coal mining,
equipment manufacturing,
Transmission and power
trading and, now, is aiming to
enter distribution. Currently,
major chunk of the revenue is
derived from power
generation. It is the goal and
strategy of the company to
become a leading full-service
integrated power company in
the Indian power sector with
presence across the value
chain i.e. both with backward
and forward integration. .
-
8/6/2019 JSWEnergy Hedge 090511
5/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
2 May 3, 2011
The second units of Barmer
project (135MW) and Ratnagiri
project (300MW) have got
commercial operation dates
during FY11 to take the total
operative capacity to 1430 MW.
The power is sold to state utility
boards through short-term
power off take arrangements,
where the price is subject to
rapid market demand
luctuations
In July 2009, the company added to its power generatio
portfolio by commencing the first of its 600 mw (1 X 300 MW
coal plant (JSWEL SBU II). This plant too is located in Vijaynaga
The second unit (2 X 300 MW) was operationalized in Septemb
2009. In November 2009, the firm also started operations of thfirst unit of its 1080 MW ( RWPL 1 X 135 MW) lignite power pla
in Barmer, Rajasthan, taking the total capacity to 995 mw by t
end of fiscal year 2010. And in FY11, the second units of Barm
project (135MW) and Ratnagiri project (300MW) have g
commercial operation dates (COD) to take the total operati
capacity to 1430 MW. JSWELs big aim is to reach a targ
capacity of 11390 MW by 2015. As of now, the company has
1430 MW of operational generating capacity and 1490 MW
generating capacity in the construction or implementation phas
As far as it sales are concerned, the company secures its powgeneration revenues through a combination of long term PPA
(Power Purchase Agreements) and short term merchant pow
sales with various state-owned utilities (SEBs), power tradin
companies and industrial consumers.
Power Trading: The Company has been in the power tradin
business since 2006 and it is carried out by its subsidiar
JSWPTC (JSW Power Trading Corporation). The Central Electrici
Regulatory Commission (CERC) has granted the company with a
F category license, the highest license in India, for pow
trading. JSWPTC sells power of not only the JSWEL but fro
external power supplies as well. The power is sold to state utili
boards through short-term power off take arrangements, whe
the price is subject to rapid market demand fluctuations. Th
time period of these short-term arrangements ranges fro
several hours to 11 months.
Power Transmission: Power transmission is another powrelated area that the firm has been involved in, rendered throug
yet another subsidiary JSWPTL (JSW Power Transco Limited). T
other partner in the venture is the government unit-MSETC
(Maharashtra State Electricity Transmission Company Limited
Through its transmission lines the company transmits power fro
power generation units to state and national grids.
-
8/6/2019 JSWEnergy Hedge 090511
6/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
3 May 3, 2011
Equipment manufacture and Mining: Equipm
manufacture and mining activities make up the remaining par
the companys business. Both these activities are condu
through joint ventures. In 2008, JSWEL signed a deal with Japan
conglomerate- Toshiba Corporation, for the design, engineer
manufacturing, assembling and sale of sub-critical and su
critical steam turbines and generators with capacities ranging f
500MW to 1000MW. However JSWELs stake in the venture is
20% so it is not expected to contribute much in terms of cost no
Project Place Fuel Capacity(MW)
Expectedoperational
year
Ratnagiri I MaharashtraSub critical imported
coal1200 FY12
Rajwest I Rajasthan Lignite 1080 FY12
Kutehr Hydro Project Phase IHimachal
PradeshHydro power 80 FY14
Ratnagiri II Phase I MaharashtraSub critical imported
coal800 FY14
West Bengal Power project
Phase IWest Bengal Coal 300 FY15
Rajwest Power Ltd. II Phase I Rajastan Lignite 135 FY15
Ratnagiri II Phase II MaharashtraSub critical imported
coal800 FY15
Chattisgarh Power project
Phase IChattisgarh Coal 660 FY16
Ratnagiri II Phase III MaharashtraSub critical imported
coal800 FY16
Kutehr Hydro Project Phase IIHimachal
PradeshHydro power 80 FY16
Rajwest Power Ltd. II Phase II Rajasthan Lignite 135 FY17
JSWEL Vijayanagar Karnataka Sub critical coal 660 FY17
Ratnagiri II Phase IV Maharashtra Sub critical importedcoal
800 FY17
Source: JSWEL, Hedge Research
In 2008, JSWEL signed a deal
with Japanese
conglomerate- Toshiba
Corporation, for the design,
engineering, manufacturing,
assembling and sale of sub-
critical and super-critical
steam turbines and
generators.
JSW Energy Projects Update
-
8/6/2019 JSWEnergy Hedge 090511
7/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
4 May 3, 2011
The attempts of the company
or acquiring a couple of coal
mines abroad are in full
swing. The Company had
acquired a majority stake in
SACMH (South African Coal
Mining Holding Ltd) in 2009.
will it benefit much in terms of revenue. Production under Pha
would commence in 2011 and initially, the unit would prod
steam turbine and generator (STG) parts. By 2012, it would s
manufacturing STG sets with a target production capacity of 3
mega watt per annum by 2014. The JV is targeting sales of $million (around Rs 1,840 crore) only by the end of 2015 fiscal.
companys mining activities are conducted in the state
Maharashtra and Orissa. The Maharashtra mining activity is car
out for the purpose of securing lignite for the (8X 135 MW) 1
mw lignite plant in Ratnagiri, Maharashtra.
Investment Rationale
The key facts which make the stock a flattering one are:
1) A potential margin outlook supported by the coal macquisitions which will eventually bring in the fuel prices (fuel c
comprise more than 70% of the total expenditure book) u
control. In the near future, the margins are expected to go up o
coal prices come down from the current exorbitant lev
Meanwhile, in the long run, the company is expected to ben
from the progressing coal mine acquisitions at the internati
level, as the price determination will come under the control of
company.
2) The business integration model (Both backward integra
and forward integration) that the company aiming for makes
unique one. The processes of combining different business
management systems so that they may interact with one ano
and thus be used to enhance an enterprise business strategy
respect of the backward integration, fuel security and tur
manufacturing are the areas to be possessed, which have alre
been initiated by the company. The attempts of the company
acquiring a couple of coal mines abroad are in full swing.
Company had acquired a majority stake in SACMH (South Afr
Coal Mining Holding Ltd) through acquisition of shares in R
Bafokeng Capital (RBC) and the shares of Mainsail which holdsadditional 5% in SACMH. SACMH is a listed South African Comp
with coal mining assets in the Witbank region with mines in Ulam
and Illanga. The mines have reserves of about 50 million ton
with exportable surplus in the range of 14-20 million ton
Besides, SACMH has allocations in RBCT Phase V of about
million tpa as also coal preparation plant and railway siding at
mine site.
In the outlook, the margins are
expected to go up once coal
prices come down from the
current exorbitant levels
-
8/6/2019 JSWEnergy Hedge 090511
8/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
5 May 3, 2011
Despite the augmented
generation in the country, the
energy deficit, as on Q4FY11,
igured at 13.8%.
Regarding the forward integration, electricity transmission an
distribution are the targeted areas, of which JSW has entered th
former and is sketching to the latter through diversified range joint venture agreements and subsidiaries.
3) Company is aggressively in the path of ramping up
electricity generation capacity, which is, currently, stands at a
operative 1730MW with the commissioning of 2nd phase
Ratnagiri plant. It is expected to add a further 2880MW operativ
capacity to take the total figure at 4310MW. Apart from tha
there are some projects in pipeline which are expected to
operational beyond 2015. When we take these projects also in
account, the capacity will touch 6570MW by the fiscal 2017.
4) The huge disparity in the demand and supply of power
the country: Despite the augmented generation in the country, t
energy deficit, as on Q4FY11, figured at 13.8%. As on Dec 20
the total energy deficit was at 10.1%. The mismatch between t
two is unlikely to narrow immensely in the future as the growth
the demand is expected to shoot up in a gigantic way and t
capacity acceleration will not be sufficient to meet it.
JSW Energy Ltd
Backward Integration
MiningEquipmentManufactu
ring
Forward Integration
Transmission
PowerTrading
Distribution(Targeting)
There are some projects in
pipeline which are expected to
be operational beyond 2015.
When we take these projects
also into account, the capacity
will touch 6570MW by the
fiscal 2017.
-
8/6/2019 JSWEnergy Hedge 090511
9/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
6 May 3, 2011
Though new generation capacity
addition so far in the current five
year plan period is greater than
what it was achieved in each of
earlier plans, the country is all
expected to fall short of its revised
11th five year plan.
Industry
Power sector plays crucial role in the economic progress of th
country given the importance of electricity in the econom
activity. Rapid growth of the economy will place a heavy deman
on electric power. Reforms in this sector, for making the pow
sector efficient and more competitive, have been under way f
several years and while there has been some progress, shortag
of power and lack of access continues to be a major constraint o
the economic growth. Currently, at the end of March 2011, tpower generation capacity stood at 173.626 GW including th
renewable energy sources such as wind, solar etc. of abo
16.787GW. However the peak power deficit in Jan 2011 is 11.1
and the normal power deficit is 7.6%. With the country's pea
power demand (as on Jan 2011) being 122.470 GW well belo
the country's current generation capacity, the lower plant loa
factors on account of scarcity of fuel/feedstock or less efficie
aged power plants as well as high T&D losses and season
nature of renewable power capacity. So far in the 11th five ye
plan period (2007-08 to 20011-12) the country has added abo
37.900 GW of which about 9.026 GW was renewable energ
Though new generation capacity addition so far in the curre
five year plan period is greater than what it was achieved in eac
of earlier plans, the country is all expected to fall short of i
revised 11th five year plan target to about 63GW.
170
82.2852.53
35.19
Total
installed
capacity
State
sector
Central
sector
Private
sector
Source: JSWEL, Hedge Research
0
1000
2000
3000
4000
5000
6000
7000
FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017
Expected Operative Capacity Build up
(in MWs)
-
8/6/2019 JSWEnergy Hedge 090511
10/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
7 May 3, 2011
The originally envisaged target
or current five year Plan at the
start of the plan period was 78
GW and was later revised to
62,374 MW. Capacity addition
of 32,032 MW was only
achieved till December 31,2010. At the end of the plan,
only 50000 MW is likely to be
added. Meanwhile, the Power
Ministry has set a target of
100,000 MW of power capacity
addition in the upcoming
Twelfth Plan (2012-17).
Source: CEA
The double digit peak power deficit is largely on the cyclic
slowdown in the industrial sector which began in fiscal 2008 g
compounded by the global slowdown and was arrested only at t
beginning of fiscal 2010. In the fiscal 2010, electricity generatio
emerged from the lackluster growth witnessed in fiscal 2009 anequaled its performance in fiscal 2008. This was achieved despi
constraints imposed by inadequate availability of coal and th
dismal hydel-generation scenario due to sub-normal monsoo
During fiscal 2010, the total energy deficit came down to 10.1
from 11% during the fiscal 2009, mainly due to increase
electricity generation. The availability of gas from the KG bas
(D6) resulted in better utilization of capacity and higher Pla
Load Factor (PLF) as high growth in electricity generated from g
based plants.
The originally envisaged target for current five year Plan at t
start of the plan period was 78 GW and was later revised
62,374 MW. Capacity addition of 32,032 MW was only achieve
till December 31, 2010. At the end of the plan, only 50000 MW
likely to be added. This is largely on account of environment
issues as well as delay in coal linkages etc apart from equipme
supply delays. Meanwhile, the Power Ministry has set a target
100,000 MW of power capacity addition in the upcoming Twelf
Plan (2012-17) (2012-13 to 2016-17), of which the share
thermal power being 76.6 GW, hydel power being 20 GW an
Nuclear at 3.4 GW. In the 12th five year plan period the countis envisaging a technology transition with embrace of sup
critical technology in a bigger way. Though super critic
technology projects were introduced in the 11th five year pla
period in a smaller way, the share of super critical technology
all set to increase to 59% (or 43640 MW) of the coal generatio
capacity in the 12th five year plan.
On one hand with rising demand for electricity as double dig
peak demand, the sector is faced with numerous challenges su
fuel availability, poor financial conditions of state electriciboards as well as various project risks ranging from funding
environmental etc. The greatest weakness is on the distributio
front which is entirely the domain of the States. AT&C losses
most of the State Power Utilities (SPUs) remain as high as 40
and this has made them financially sick and unable to inve
adequately in additional generating capacity.
111034
456037367
16787
169748
19509
Indian Energy sources
-
8/6/2019 JSWEnergy Hedge 090511
11/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
8 May 3, 2011
The greatest weakness is on the
distribution front which is entirelyunder the domain of the States.
AT&C losses of most of the State
Power Utilities (SPUs) remain as high
as 40%.
Merchant power sales are estimated
on an average of 66% for FY11-12E.
Source: JSWEL, Hedge Research, Ace Equity
For the same reason, these utilities have had only limited succ
in attracting private investors to set up power plants. The Cen
with a view to encouraging generation and reducing transmis
and distribution losses, announced extension of tax holiday for
power sector by one more year till March 31, 2012. The extensof tax break is part of the government's efforts to scale up
power generation capacity to meet the growing needs. The
exemption would benefit projects that are expected to take of
the remaining period of the XI Plan (2007-12), including u
mega power projects (UMPPs).
Financials & Valuations
Top line to grow at a CAGR of 99%
The financials look impressive with both the topline and bottom
inching up by 49% and 46% respectively. The FY10 seems to b
resumption of growth for the company from the badly affec
financial figures of FY09. In FY09, while the top line remained
the profit after tax saw a decline of 32.46%, which was mainly
account of a surge in the fuel cost. The FY11 financials, too, h
been decent with the sales shooting up by 82%. Going forw
we expect, in accordance with the capacity ramp up, the top lin
grow at a CAGR of 99% during FY10-12E.
Balanced Sales mix
JSW Energy, unlike others, has a more or less balanced mix
merchant power and Power purchase agreements (PPAs) in
sales portfolio. The former to total sales were 68%, 61% and 7
respectively for FY08, FY09 and FY10 respectively. The sam
estimated to be averaged at 66% for FY11-12E. The PPAs (Po
Purchase Agreements) and short term merchant power sales
with various state-owned utilities (SEBs), power trading compa
and industrial consumers like West Bengal Mineral Trading Development Corp (WBMTDC), Government of Chhattisg
(GoCG) etc
0
2000
4000
6000
8000
10000
Revenue Break up
Revenues
PBIDT
PBDT
PBT
PAT
-
8/6/2019 JSWEnergy Hedge 090511
12/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
9 May 3, 2011
Source: JSWEL, Ace Equity, Hedge Research
FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12E
Short term sales 0 833 1527 1425 1259 3671.41 6004 13600.12
Long term sales 1826 1071 386 643 797 1499.59 3012 7006.125
0
5000
10000
15000
20000
25000
MillionUnits(Kwh)
Yearwise Sales Mix
Q3FY09 Q4FY09 Q1FY10 Q2FY10 Q3FY10 Q4FY10 Q1FY11 Q2FY11 Q3FY11 Q4FY11
Short term sales 374 300.44 416.8 859.81 1203.0 1217.8 1260.6 1139.8 1605.3 2013
Long term sales 159 217.56 104.2 351.19 444.96 573.12 566.37 641.16 790.68 1000
0
500
1000
1500
2000
2500
3000
3500
Million
Units(Kwh)
Quarterwise Sales Mix
-
8/6/2019 JSWEnergy Hedge 090511
13/21
INITIATING COVERAGE- BUY : JSW ENERGY LTD
10 May 3, 2011
We expect the average
realization to be Rs.4 for
FY12E.
Though there is a potential
or marginal upside
movement in the coal price,
it is not likely to affect our
valuation significantly as
we have factored in the
same at the current higher
levels.
Realization to endure at reasonable levels despite the concern
Since the short term sales put in higher realization for the compa
the higher proportion of short term sales translates into the bet
average realization, which stood at Rs.4.44 in FY10 and has behovering in a range of Rs. 4 -4.5. We expect the same to remain at
4 for FY12E.
Source: JSWEL, Hedge Researc
No significant room for change in our valuation by fuel cost
The fuel cost has been skyrocketed to a higher level in the
couple of years and now stands in $120-$130/ton range. Thou
there is a potential for marginal upside movement in the price, i
not likely to affect our valuation significantly as we have factored
the fuel cost at higher levels. Fuel cost has been one of m
sensitive factors to the stock. Thermal coal is the largest source
energy for the generation of electricity worldwide. The price of chas been buoyed by flooding in Australia's coal-rich state
Queensland, which interrupted supplies from the world's top therm
coal exporter. Huge demand for energy resources in China and In
has pushed the price of thermal coal to an all time high.
4.48
6
4.44
5.09
4.34 4.43 4.24.49
4
5.25
7.08
4.97
5.77
4.654.87
4.5
4.95
4.36
3.413.59 3.59 3.63
3.3
FY08 FY09 FY10 Q1FY11 Q2FY11 Q3FY11 Q4FY11 FY11 FY12E
Average Realisation/Unit Short term Realisation/Unit Long term realisation
-
8/6/2019 JSWEnergy Hedge 090511
14/21
INITIATING COVERAGE- BUY : JSW ENERGY L
11 May 3, 201
We see the fuel cost per
unit for FY11E and FY12E to
be Rs. 2.73 and 2.48
respectively
Having accounted for theskyrocketed coal price, the
profits is expected to grow
at a CAGR of 34% during
FY10-FY12E
Source: JSWEL, Hedge Research, Ace Eq
The fuel cost per unit of the company has been quite vol
since FY08. As the company is highly depending on coal as f
the fuel cost/unit had shot up to an all time high of Rs.3.0
FY09 on account of the surge in the international coal pric
$125/ton in FY09. It, then, came down and bounced back in F
and FY11 respectively. We see the same for FY12E as Rs.2.48
Profit to post growth at a CAGR of 34%
With the surge in the coal price and other components in
expenditure book, the EBITDA and PAT growth confined to
tune of 32% and 13% respectively for FY11 to touch Rs.1
crore and 842 crore respectively. Having accounted for
skyrocketed coal price, the profits are expected to grow a
CAGR of 34% during FY10-FY12E, driven by a gigantic ramp u
the capacity and consistent realization ra
Discounted cash flow values the stock at Rs.95 per share
Our valuation model based on discounted cash flow give
value of Rs.95 per share to JSW energy. It has 33.8% ups
from the current market price of Rs.71. we have used a disco
rate of 11.8% for the model.
0
0.5
1
1.5
2
2.5
3
3.5
FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12E
Fuel cost per unit
-
8/6/2019 JSWEnergy Hedge 090511
15/21
INITIATING COVERAGE- BUY : JSW ENERGY L
12 May 3, 201
Sensitivity Analysis
It has been found from our analysis that JSW energy is very sensitive to
factors like coal price, plant load factor and realization per unit (ARPU). We h
done a sensitivity analysis of share price to those factors.
Average Realization per Unit
Coal Price
@58003.75 4 4.25 4.5
PLF
0.70 16 52 89 125
0.75 56 95 133 172
0.80 95 137 178 220
0.85 135 179 223 267
Taking the coal price constant at Rs.5800/ton, PLF between 70% and 80% andARPU between Rs.3.75 and 4.5, the stock is found to have potential to move
the range of Rs.16 to 267.
Average Realization per Unit
Load Factor
@0.753.75 4 4.25 4.5
CoalPrice 5200 91 130 169 207
5500 73 112 151 190
5800 56 95 133 172
6200 32 71 110 149
When we consider the plant load factor at 75%, the coal price between Rs. 52
and 6200/ton and the ARPU in the range of Rs.3.75 and 4.5, the stock could
move amid Rs.91 and 149.
Coal Price
ARPU @4.00 5200 5500 5800 6200
P
LF
0.70 88 70 52 29
0.75 130 112 95 71
0.80 172 155 137 113
0.85 215 197 179 156
Also, we also found that the stock may move in the range of Rs.88 and 156
when we take the ARPU at Rs.4, PLF in the range of 70% to 85% and the coal
price between Rs.5200 and 6200/ton.
-
8/6/2019 JSWEnergy Hedge 090511
16/21
INITIATING COVERAGE- BUY : JSW ENERGY L
13 May 3, 201
Due to environmental
concerns, Indias annual
thermal coal production
growth is slowing to 1-2
per cent now from 6-7 per
cent earlier.
Risks
But among all these, the sector reels under certain major issu
which act as a bottleneck for the growth of the industry. JS
Energys earnings and stock valuations are highly sensitive availability of coal and its prices, given that about 46 per cent of
planned capacity, about 11,390 Mw, is dependent on import
coal. Fuel availability and its high leveled price is the chief proble
that the company faces, which further puts brakes on the pl
process. Thermal coal a key input for power generation h
become costly in the global markets in the recent months. Sup
constraints for domestic coal remain and are expected to contin
going forward. Further, industry estimates suggest that dema
from China and India could hold the price at current levels or mo
In the long run, given the nuclear crisis in Japan, any increase
preference towards coal-based power plants would only lead
further pressure on coal prices. The situation could have be
better, had the supply of domestic coal (which costs less) be
sufficient. Due to environmental concerns, Indias annual therm
coal production growth is also slowing to 1-2 per cent now fr
6-7 per cent earlier. Recently, Coal India lowered its product
growth to 3 per cent. Since domestic coal supply constrai
remain to continue, some public and private sector entities ha
embarked upon imported coal as a means to bridge the deficit. T
has led to some Indian entities to take upon the task of purchasi
developing and operating coal mines in international geographiWhile this is expected to secure coal supplies it has again thro
upon further challenges. The failure to achieve the planned targ
from the captive coal blocks presents itself as a major challenge
the power sector, as only 24 blocks have become operational out
the total 210. Experts believe that the non-operational status
majority of these blocks is attributed to land acquisition (R&
issues, permit delays and infrastructure problems.
Declining merchant power realization rates, too, stand as anoth
concern as almost 67 per cent of JSWs current capacity caters
merchant power sales. The rate is always competitive and bound
volatile. Hence, though it remains well above the PPA rate, t
inability to lock in the cost and the downward trend of t
merchant rate are seemed to be the key concerns for the compa
-
8/6/2019 JSWEnergy Hedge 090511
17/21
INITIATING COVERAGE- BUY : JSW ENERGY L
14 May 3, 201
Financial Highlights
DESCRIPTION Mar-10 Mar-09 Mar-08
Inc / Exp PerformanceGross Sales 2355.09 1835.02 1293.14
Total Income 2429.26 1852.16 1326.07
Total Expenditure 1141.61 1303.17 416.68
PBIDT 1287.65 548.99 909.39
PBIT 1151.55 488.78 850.79
PBT 867.85 367.84 762.24
PAT 745.49 276.69 625.27
Cash Profit 881.59 336.90 683.87
Sources of Funds
Equity Paid Up 1640.05 546.57 514.76
Reserves and Surplus 3138.47 932.14 488.87
Net Worth 4778.52 1478.71 1003.63
Total Debt 7870.14 5927.16 2272.66
Capital Employed 12665.56 7422.03 3365.30
Application of Funds
Gross Block 3683.89 1169.07 1139.60
Investments 1434.44 170.47 20.73
Cash and Bank balance 604.82 175.10 294.94
Net Current Assets -267.83 -1226.23 0.65
Total Current Liabilities 1900.64 1766.19 502.82
Total Assets 12665.56 7422.03 3365.30Cash Flows
Cash Flow from Operations 846.96 468.31 801.19
Cash Flow from Investing activities -3582.31 -4045.99 -2251.08
Cash Flow from Finance activities 4386.14 3461.84 1467.31
Free Cash flow -2422.29 -3540.36 -1604.85
Market Cues
Close Price (Unit Curr.) 111.80 0.00 0.00
High Price (Unit Curr.) 123.90
Low Price (Unit Curr.) 99.90
Market Capitalization 18335.76 0.00 0.00
Adjusted EPS 4.55 2.02 4.86
Price / Book Value(x) 3.84 0.00 0.00
CEPS 5.38 2.47 5.31
Equity Dividend % 7.50 0.00 20.00
Source: Ace Equity
-
8/6/2019 JSWEnergy Hedge 090511
18/21
INITIATING COVERAGE- BUY : JSW ENERGY L
15 May 3, 201
Financial Ratios
Description Mar-10 Mar-09 Mar-08
Operational & Financial Ratios
Earnings Per Share (Rs) 4.55 5.06 12.15
Adjusted EPS (Rs.) 4.55 2.02 4.86
CEPS(Rs) 5.38 2.47 5.31
DPS(Rs) 0.75 0.00 2.00
Adj DPS(Rs) 0.75 0.00 2.00
Book Value (Rs) 29.14 27.05 19.50
Adjusted Book Value (Rs) 29.14 10.82 7.80
Tax Rate(%) 14.10 24.78 17.97
Dividend Pay Out Ratio(%) 16.50 0.00 16.47Margin Ratios
PBIDTM (%) 54.68 29.92 70.32
EBITM (%) 48.90 26.64 65.79
Pre Tax Margin(%) 36.85 20.05 58.94
PATM (%) 31.65 15.08 48.35
CPM(%) 37.43 18.36 52.88
Performance Ratios
ROA (%) 7.42 5.13 18.58
ROE (%) 23.83 22.29 62.30
ROCE (%) 11.47 9.06 25.28
Asset Turnover(x) 0.23 0.34 0.38
Inventory Turnover(x) 11.67 58.89 43.03
Debtors Turnover(x) 11.54 17.80 18.66
Sales/Fixed Asset(x) 0.97 1.59 1.13
Sales(x)/Working Capital -8.79 -1.50 0.00
Growth Ratios
Net Sales Growth(%) 28.34 41.90
Core EBITDA Growth(%) 134.55 -39.63
EBIT Growth(%) 135.60 -42.55
PAT Growth(%) 169.43 -55.75
EPS Growth(%) -10.21 -58.32
Financial Stability Ratios
Total Debt/Equity(x) 1.65 4.01 2.26
Current Ratio(x) 0.93 0.31 1.32
Quick Ratio(x) 0.72 0.29 1.24
Interest Cover(x) 4.06 4.04 9.61
Source: Ace Equity
-
8/6/2019 JSWEnergy Hedge 090511
19/21
INITIATING COVERAGE- BUY : JSW ENERGY L
16 May 3, 201
Financials Graph and Peer Group Comparison
Source: Multiple Sources
Peer Group Comparison (Consolidated)
Company NameYearEnd
Net Sales PBIDT PATAdj.
EPS(Rs)PBIDTM% PATM% ROCE% ROE%
Rel.Power 201003 20.72 717.03 683.89 2.85 3459.98 0 4.47 4.84
Tata Power 201003 18985.84 4442.08 2138.64 82.91 23.38 11.26 12.54 19.74
NTPC 201003 48311.5 16021.7 8837.7 10.72 32.98 18.19 12.64 14.73
Adani Power 201003 434.86 275.74 170 0.78 63.41 39.09 2.02 4.22
NHPC 201003 5227.32 4783.17 2277.56 1.77 91.5 43.57 8.52 10.15
Source: Ace Equity
Revenues
PAT
EPS
PE
0.00
10000000000.00
20000000000.00
30000000000.00
40000000000.00
50000000000.00
60000000000.00
70000000000.00
80000000000.00
90000000000.00
FY08 FY09 FY10 FY11 FY12E
Revenues 12930000000. 18350200000. 23550900000. 44280000000. 83800000000.
PAT 6252700000.0 2766900000.0 7454900000.0 8420000000.0 13388500000.
EPS 3.81 1.69 4.55 5.13 8.16
PE 19.12 43.21 16.04 14.20 8.93
19.12 43.21 16.04 14.20 8.93
Financials Graph
-
8/6/2019 JSWEnergy Hedge 090511
20/21
INITIATING COVERAGE- BUY : JSW ENERGY L
17
Analyst Notes And Company News
-
8/6/2019 JSWEnergy Hedge 090511
21/21
INITIATING COVERAGE- BUY : JSW ENERGY L
18
Researched and prepared by:
Muhammed Aslam E
Fundamental Analyst
Email:[email protected]
Ph:(0484) 3040400, 3040419
In co-operation with:
Neha Mahajan
Fundamental Analyst
Email:[email protected]
Amar Chandramohan
Sr. Fundamental Analyst
Email:[email protected]
Krishnan Thampi K
Head of Research and Strategies
Email:[email protected]
HEDGE RESEARCH & STRATEGIES GROUP
Head of Research: Krishnan Thampi K
Sr. Fundamental Analyst: Amar Chandramohan
Jr. Fundamental Analyst: Muhammed Aslam E
Jr. Fundamental Analyst: Neha Mahajan
Sr. Equity Technical Analyst: Anish Chandran C V
Sr. Commodity & Equity Technical Analyst: Kesavamoorthy B
Futures & Options Analyst: Yunus Ismail
Access all our research reports online at www.HedgeEquities.com
DIRECT ALL RESEARCH QUERIES TO:
Research & Strategies Group
Hedge Equities Ltd
12 Floor, -Mini Muthoot Tech Towers
Kaloor, Kochi682017, Kerala, India
Phone: (0484) 3040400
Email: [email protected]
DisclaimerThe information contained in our report does not constitute an offer to sell securities or the solicitation of an offer to buy, any security. This report is prepared fo
private circulation only. The information in our report is not intended as financial advice. Hedge Equities Ltd does not undertake the responsibility for an
investment decision taken by the readers based on this report. Moreover, none of the information in the research report is intended as a prospectus within thmeaning of the applicable laws of any jurisdiction. The information and opinions contained in our research reports have been compiled or arrived at from
sources believed to be reliable in good faith, but no representation or warranty, express or implied, is made by Hedge Equities Ltd, to their accuracy. Moreove
you should be aware of the fact that investments in securities or other financial instruments involve risks. Past results do not guarantee future performance.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]