Mr. Joseph Richards C/O Power Plant Consulting LC 4801 Woodway Dr. # 300 East Houston, TX 77056 Tele: 001-832-426-3678 (USA) Tele: +84-948-138-126 (Vietnam) Tele: +639167776112 (Philippines) joe@powerplantconsulting. com Resume of Mr. Joseph Richards Career Summary Mr. Richards is 59 years of age and has over 36 years of successful domestic and international power plant experience exclusive to pulverized coal, gas and oil fired utility plants, combined and open/simple cycle gas turbines, co-generation, diesel, nuclear to combined cycle conversion, biomass, waste to energy and facility dismantle- relocation types of power plant projects. Mr. Richards has 25+ years of project management experience with power plant projects each of which ranged between $200 million to $5 billion and has held management positions within public utilities, independent power project-IPP equity owner’s, insurers, developers, lump sum turnkey and direct hire engineering, procurement and construction (“EPC”) contractor organizations. Mr. Richards also has dispute resolution, litigation and claims experience to avoid or mitigate project problems. Mr. Richards also has significant startup commissioning experience and is a licensed power plant operator. In 1996, Mr. Richards founded Power Plant Consulting LC to provide specialized independent management consulting services to worldwide clients and their power plant projects. Power Plant Projects Chronological Experience: Now: Owner’s PM consultant, new project commissioning and close out works for two unit, 1200 MW coal fired project located in Page 1 of 8

Transcript of Joseph Richards PM 2015

Page 1: Joseph Richards PM 2015

Mr. Joseph RichardsC/O Power Plant Consulting LC4801 Woodway Dr. # 300 EastHouston, TX 77056Tele: 001-832-426-3678 (USA)Tele: +84-948-138-126 (Vietnam)Tele: +639167776112 (Philippines)[email protected]

Resume of Mr. Joseph Richards

Career SummaryMr. Richards is 59 years of age and has over 36 years of successful domestic and international power plant experience exclusive to pulverized coal, gas and oil fired utility plants, combined and open/simple cycle gas turbines, co-generation, diesel, nuclear to combined cycle conversion, biomass, waste to energy and facility dismantle- relocation types of power plant projects.

Mr. Richards has 25+ years of project management experience with power plant projects each of which ranged between $200 million to $5 billion and has held management positions within public utilities, independent power project-IPP equity owner’s, insurers, developers, lump sum turnkey and direct hire engineering, procurement and construction (“EPC”) contractor organizations. Mr. Richards also has dispute resolution, litigation and claims experience to avoid or mitigate project problems.

Mr. Richards also has significant startup commissioning experience and is a licensed power plant operator. In 1996, Mr. Richards founded Power Plant Consulting LC to provide specialized independent management consulting services to worldwide clients and their power plant projects.

Power Plant Projects Chronological Experience:

Now: Owner’s PM consultant, new project commissioning and close out works for two unit, 1200 MW coal fired project located in Vietnam.

2014: Developer support for (1) Captive Cogeneration unit and (2) IPP Plants

2014: World Bank Lender Consultant, international locations

2014: Confidential Client, Conducted “operational readiness” review of third party Operations and Maintenance contractor.

2013: Confidential Client, Manila, Philippines (April 1 until November 14), PM support. Conducted turnkey contractor compliance inspection and pre-construction advisory on two power plant projects on behalf of equity owner.

2013: Aramco Services, Houston, TX (Jan until March), Developer PM support of front end engineering and design (“FEED”) study for new 4,000 MW project.

2012: Jamaica Public Service, Developer support (Project Director) to complete development activities (i.e. environmental assessment, finalize EPC Contractor scope, outline permitting, PPA technical clarifications, equipment supply) for a proposed 360 MW LNG-diesel dual fuel fired combined

Page 1 of 5

Page 2: Joseph Richards PM 2015

cycle project. Project was cancelled due to Government’s inability to secure LNG fuel.

Resume of Mr. Joseph Richards

2012: Jubail Water and Power, Saudi Arabia. EVP support. Writing contractual warranty recovery claims on behalf of equity owners (against EPC Contractor).

2009 – 2011: Tata Power, Mundra, India: Owner’s Head of Construction and Commissioning to direct 105 site engineer staff to oversee numerous EPC Contractors performance to deliver 5 x 800 MW supercritical coal fired units and balance of plant (Greenfield).

2009 – 2009: Zorlu Constructors, Istanbul, Turkey. Management Project Director for EPC Contractor (reporting to Director of Projects) to establish site specific project execution plan and systems related to 1,200 MW combined cycle greenfield project (Dorad) located in Israel. Zorlu withdrew due to political tension between governments.

2007 - 2009: Arabian Bemco, Saudi Arabian EPC Contractor, Senior Project Director for Qurayyah Phase I Project, simple cycle, 2,000 MW. Contract completed, no objection certificate issued.

2005 – 2006: Western Greenbriar Cogeneration Company, Greenbriar, WVA. Senior Project Director leading development support for 105 MW waste coal project (design optimization, technical specifications and EPC contractor selection). Project cancelled due to lack of fuel supply.

2005 – 2006 Aker Kvaerner, Management Consultant for EPC Contractor to establish site specific project execution plan and systems related to support for new 850MW supercritical coal fired unit.

2005 – 2006 Kansas City Power & Light, Management PM Consulting, provided construction management and preparation of detailed commissioning program and procedures for use by Owner to certify various EPC contractor’s compliance related to delivery of 850MW supercritical coal fired unit.

2003 – 2006 Insurer’s and Adjuster’s Project Manager/Expert to Oversee Damage Repairs, Commissioning and Restart.

2006: Cerro Prieto, (Mexico), 800MW geothermal facility. (2) 30 cell cooling tower replacements damaged by earthquake.

2006: Salamanca Station (Mexico), 158MW oil & gas fired thermal unit. Boiler replacement damaged by over fueling explosion.

2006: Altimira Station (Mexico), 120MW gas fired thermal unit. Boiler repairs damaged by over fueling explosion.

2005: El Dorad (AZ), 2000 MW. Replacement and re-test of GT static starting module due to electrical fault damages.

2004: Guayama (PR) Unit 1, (PR), 600 MW. (Coal) Steam turbine water quality related damages.

2004: Fluvanna Project,(VA). 800 MW. H.P pipe explosion related damages.

2004: Hatfield’s Ferry Project (PA), 550 MW (coal). Complete Turbine and Generator failure requiring Page 2 of 5

Page 3: Joseph Richards PM 2015

turbine re-blade and generator rewinding while concurrently upgrading boiler and BOP outage.

Resume of Mr. Joseph Richards

2004: El-Rama Project (PA), 120 MW. Coal Boiler repairs damaged by over-fueling explosion.

2004: R.I.S.E.P. Project (MA), 500 MW. GT Air inlet replacement destroyed by fire.

2003: Osceola Project, (AK), 800 MW. Replacement of damaged GSU transformer.

2003: Alabama II Project, (AL), 800 MW. Replacement of (2) damaged GSU transformers.

2003: Commissioning management of 500 MW simple cycle units (SW 501F)

2002 – 2003 Lender’s Due Diligence, Asset Management Support Related to Abandoned Power Plants Mystic Station (MA), combined cycle plant, review of documents only Fore Rivers Station (MA), combined cycle plant, review of documents only Covert, (MI). 1000+MW using M510G and Mitsubishi STG Athens, (NY). 1000+MW using SW501G and SW STG Harquahala, (AZ). 1000+MW using SW 501G and SW STG Milford Power, (CT). 550 + MW using Alstom GT-24/26 and Alstom STG’s Millenium Power (MA). 300 MW using SW 501G and SW STG

2000 - 2002: Insurer’s Project Manager/expert to oversee damage repairs and commissioning of 550 MW combined cycle plant delayed by construction accident (Milford).

1998 - 2000: Marubeni, EPC Contractor’s Project Director to “turn around” and recover distressed 205 MW Combined Cycle Project located in Cali Colombia. Responsible for correcting engineering short comings, construction workmanship failures and poor commissioning.

1997 – 1998: Owner’s Due Diligence Inspector to report findings of EPC Contractor’s performance for: 1) Seng Kang Project, Indonesia (135 MW combined cycle facility) and; 2) Uch Project, Pakistan (500 MW combined cycle facility).

1996 – 1997: LS Power, Owner’s Engineer to witness EPC contractor’s performance during commissioning of two 250 MW combined cycle facilities, Whitewater, (WI) and Cottage Grove (MN) and contract close out matters. Whitewater and Cottage Grove projects were managed concurrently.

1995 - 1996: Northland Power, Owner’s Engineer to witness EPC contractor’s performance during commissioning and contract close out matters, Iraquois Falls, Canada. 120 MW combined cycle facility.

1994 – 1995: NEICO-State, EPC Contractor’s Project Management, Cardinal Project, Canada (150 MW combined cycle facilities). Responsible for “turn around” and mitigation of late delivery and overseeing OEM technical related delay claims.

1993 – 1994: Owner’s Project Manager to relocate 60MW diesel generator facility from U.S.A to Philippines. Responsible for engineering, procurement, construction and commissioning.

Page 3 of 5

Page 4: Joseph Richards PM 2015

Resume of Mr. Joseph Richards

1992 – 1993: EPC Contractor’s Startup Commissioning Manager for two 18 MW waste wood fired thermal units at Fitchburg (MA) and Chateaugay (NY). Fitchburg and Chateaugay were commissioned concurrently

1991 – 1992: Intercontinental Energy Corporation. Owner’s Project Manager overseeing EPC contractor performance to engineer, procure, construct and commission two 300 MW combined cycle facilities located in Sayreville (NJ) and Bellingham (MA). Sayreville & Bellingham projects were managed concurrently.

1991: Hawker Siddley, Houston, Texas. EPC Contractor’s Commissioning manager for two 200 MW combined cycle facilities located in Richmond (VA) and Roanoke Rapids (NC). Richmond and Roanoke Rapids were commissioned concurrently

1990: Brown & Root, EPC Contractor’s Commissioning manager for one 350 MW pulverized coal fired unit located in Springerville (AZ). Unit was mechanically complete for one year prior to my arrival.

1988 - 1990: Fluor Daniel. EPC Contractor’s Commissioning manager for twelve GT unit, Midland nuclear plant converted to 1600 MW combined cycle facility.

1987 – 1988: General Electric EPC Contractor’s Commissioning manager for one 150 MW pulverized coal unit in Dominican Republic.

1985 – 1987: Saudi Electric Company, Saudi Arabia, O&M Operations and Commissioning Supervisor for four 650 MW gas and oil fired thermal units (Qurayyah station)

1983 – 1985: Saudi Electric Company, Saudi Arabia, O&M Operations Supervisor for four 400 MW gas and oil fired thermal units (Ghazlan station).

1977 - 1983: American Electric Power, Plant Operations Dept. (Coal). Held progressive positions on coal fired thermal units sized from 150-800MW commissioning to control room operator.

Miscellaneous Short Term Power Project Experience: Owner’s (El Paso Energy) Auditor of various international projects Paiton Indonesia, Units 1 & 2, coal fired, prepared Owners’ O&M mobilization & training planSt. Johns River Power Park, coal fired, Unit #1. Commissioning and Operations supervisorCommissioning support of 30MW thermal boiler, power barge unit (PR)Commissioning support 18MW waste to energy power plant (CT)Commissioning support 18MW waste to energy power plant (DE)Commissioning support (5) 3.2MW diesel plants, different locations in Egypt (US Corps of Engineers)

Page 4 of 5

Page 5: Joseph Richards PM 2015

Resume of Mr. Joseph Richards

Claims Preparation, Expert/Fact Witness, Litigation Support Dick Corporation versus Westinghouse Power Systems. Monenco Agra/ Northern Engineering versus Sithe Energy. Marubeni Power Corporation versus KMR Energy. Milford Power versus Chubb Insurance (2005) Note: I was Chubb’s expert. Shaw Engineers and Constructors versus PSEG (2005)

Other Experience 1975 – 1977: U.S. Army, Corps of Engineers, Power Generation, Ft. Belvoir, VA. 1971 – 1975: Electrician, residential and light commercial electrical installations Owner or majority shareholder of multiple businesses: apartment building, coffee shop, dental x-ray

laboratory and medical equipment franchise. Previous investor and/or JV partner with Florida Power & Energy, Naylor Industrial, Site Management

Services and Comprehensive Technical Consulting. Real estate development, owner of various apartments

Personal Qualifications and TrainingMechanical Engineer (BS)Licensed First Class Stationary Engineer, City of Houston TexasLicensed First Class Stationary Engineer, State of OhioRegistered American Society of Power Engineers, First Class Power EngineerAmerican Electric Power training, theory, safety and plant operations, management courses NUS correspondence courses in power plant operation ICS correspondence courses in power plant operation CEGB correspondence courses and power plant operations training (UK)Journeyman Electrician and previously licensed electrical contractor (1978-1982)U.S. Army, Power Generation School, Ft. Belvoir, VAPrimavera CPM Project Scheduling Numerous OEM training programsCo-authored "How to Develop a Successful Project with Used Equipment", McGraw Hill, 1996Musician, playing acoustic and electric guitar in various groups.

Hobbies GolfPlaying and teaching musicCycling (spinning) and gymnasium