Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1...

23
Jonah Field H 2 S Mitigation Strategy 10/26/16 Alex Davidson – Facilities Engineer

Transcript of Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1...

Page 1: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

Jonah Field H2S Mitigation Strategy

10/26/16 Alex Davidson – Facilities Engineer

Page 2: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Background –  Personal –  Jonah Field Overview

•  Water Management Strategy –  Production & Flowback phases –  Transportation & Treatment

•  H2S Source –  Sulfate-Reducing Bacteria (SRB) –  Historical Mitigation Strategy –  New Mitigation Strategy

•  Conclusions –  Treatment Performance

•  Questions

Agenda

Page 3: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Personal – BS Chemical Engineering 2008 - Colorado School of

Mines (CSM) – MS Chemical Engineering 2009 - CSM

•  Focus on Palladium-Silver Membranes for Hydrogen Separation

– 4 years in Alaska with ConocoPhillips •  Seawater Treatment Plant •  Potable and Waste Water Treatment

– 3+ years in Denver with Jonah Energy & Encana

Background

Page 4: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Located in Sublette County, WY •  1,700+ gas wells within 11,700

acres •  510 MMSCFED Production* •  9,000 BPD Produced Water* •  Initially developed by McMurray

Oil in 1993 then Encana in 2000 •  Jonah Energy LLC formed in

2014 after divestiture by Encana

*Approximate Gross Jonah Energy LLC daily volumes

Background – Jonah Field

Page 5: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Extensive road network due to the development of the field

•  Individual production units for each well were used for initial field development

•  Consolidation to Central Delivery Points (CDP’s) has reduced equipment footprint

•  Due to a number of factors, water is trucked throughout the field

Background – Jonah Field

Page 6: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

Well1

Well2

Well3

Well4

Meter

Meter

Meter

Meter

ProducedWater(PW)

Condensate

3-phaseSeparator

ContactTower

SalesGas

CondensateSales

Meter

3-PhaseProdu

ctiontoCDP

On-TruckFiltration

PWToFracStagingTanks

PWToTreatmentFacilities

•  Three-phase (3-ph or 3φ, a stream with condensate (AKA oil), water, and gas) production flows from individual wells

•  3-ph Separator at CDP separates water, oil, and gas

•  Gas is dehydrated using tri-ethylene glycol (TEG)

•  Oil and water are stored in tanks

•  PW trucked either to treatment facilities or directly to completions

Water Management Strategy – Production Phase

Page 7: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Slickwater completions primarily used

•  Flowback sites typically handle 100+ bbls/hour of fluids

•  Flowback Water (FW) trucked to water treatment facilities or to another completion

•  Typically achieve 30% recovery of water from completions

Water Management Strategy - Flowback

FracWell2

Meter

Meter

GasandCondensatetoCDP

ResidualCondensatetoCDPCondensateTank

FlowbackUnit

SettlingTank FlowbackWater(FW)

Well1

Well2

Well3

Well4

Meter

Meter

Meter

Meter

ProducedWater(PW)

Condensate

3-phaseSeparator

ContactTower

SalesGas

CondensateSales

Meter

3-PhaseProdu

ctiontoCDP

On-TruckFiltration

On-TruckFiltration

TypicalFlowbackOperation

PWToFracStagingTanks

PWToTreatmentFacilities

FWToFracStagingTanks

FWToTreatmentFacilities

Page 8: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Process-flow diagram (PFD) for the Section 36 Water Treatment Facility •  Separate process trains for PW and FW •  FW additionally treated by a Dissolved-Air Flotation Unit (DAF) •  FW stored in Ponds for future completions •  PW can be sent to Ponds for storage if necessary

Water Management Strategy

Meter

PWSurgeTanks

Chemicals

TransferPump PWSeparators

Condensate

PWBreakTanks InjectionPumps

InjectionWells

PWOffload&Header

FWOffload&Header

FWSurgeTanks TransferPump FWSeparators

Meter

Chemicals

DAFUnitPonds

CondensateSales

Filtration

Filtration

On-TruckFiltration

PWfromCDP

FWfromFlowback

PondWatertoFrac Biocide

Page 9: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Primarily Sulfate-Reducing Bacteria (SRB) •  Sulfidogen - reduces sulfate (SO4

2-) to sulfide (S2-) •  Anaerobic respiration •  “Inhales” sulfate instead of oxygen, “exhales” H2S •  Consumes organic compounds as “food” •  Known to “sour” fields due to improper water treatment (especially water-floods)

•  Small H2S concentrations in water = large H2S concentrations in air •  Sulfide Stress Cracking/Corrosion •  Generates FeS (plugging agent)

H2S Source

Page 10: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Section 36 Water Treatment Facility upgraded in 2010 •  Several ponds have been closed •  FW stored in covered ponds to control emissions and comply with

MBTA •  Pond covers installed in 2012 •  Light color chosen to reduce solar heating impact •  Warm ambient temperatures result in SRB population blooms

H2S Source

Page 11: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Utilize bio-stat chemical batch treatment to suppress SRB growth ($$)

•  Occasional H2S breakout still occurred in pond water loading tanks and at staging tanks during hot summer months – Pond water not accepted for completions – Pond required to be treated with additional biocide and/or disposed

•  Single pond pump could not keep up with completions demand

Historical Mitigation Strategy

Page 12: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

Objectives •  Protect personnel from H2S exposure at pond water loading

tanks, staging tanks, and frac sites •  Improve water deliverability for recycling •  Reduce chemical costs •  Reduce trucking costs •  Customize water storage volumes based on completion

demand •  Provide flexibility for future operations •  Extend life expectancy for ponds

New Mitigation Strategy

Page 13: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Address stagnant water in pond –  Poor dispersion of chemical = ineffective treatment

•  Stagnant water allows for sessile bacteria growth

•  Sample probes encountered 1 to 3.5 ft of loose slurry

•  Analysis confirmed presence of DRO and GRO

New Mitigation Strategy – Existing Pond Configuration

PondInlet PondDischarge

Stagnant

Stagnant

PondCircula5on

Stagnant

SampleLoca5ons

Page 14: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Installed new circulation piping at pond bottom

•  Installed new pond pumps to improve water deliverability rates and circulation

•  Intended to move slurry at bottom of pond to pond discharge line for in-situ processing

•  Chemical delivery accomplished through new circulation lines for better dispersion

•  Utilized shop-fabricated skids to minimize field construction activity

New Mitigation Strategy – Pond Modifications

NewCircula,onPiping

NewPumphouse

Page 15: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Grundfos 475S200 Multi-stage submersible pump previously used

–  Rated for 475 gpm @ 100 ft H but never delivered on curve

•  Consistent failure due to solids (mainly biofilm) •  Pump replacement was difficult and expensive •  New centrifugal pumps installed to handle solids •  Capable of delivering 1000 gpm with two pumps

New Mitigation Strategy – Pump Modifications Before

A<er

Page 16: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Installed Valve Manifold with Motor-Operated Valves (MOV)

•  MOV’s direct water to loading tanks, circulation, between ponds, and to disposal

•  Eliminates trucking of water between ponds or to disposal

•  Provides single injection point for chemical delivery •  Designed for future expansion or modifications •  Eliminated unnecessary loading tank battery

New Mitigation Strategy – Control Change

Page 17: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Front End of water treatment facilities designed to separate residual hydrocarbon from water

•  Gunbarrel separators for oil-water separation

•  Emulsion in FW separators leads to oil carryover to DAF process

•  Emulsion breaker injected upstream of separators unable to break emulsion

•  Emulsion caused by high polymer content in water from drilling rigs mixing with FW

•  Established rig water recycling program to eliminate problem

•  Increased condensate recovery

New Mitigation Strategy – Separation Efficiency

Page 18: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  DAF treatment essential for removing TSS and residual hydrocarbon

•  Relatively inexpensive treatment

•  Improved front-end separation = Improved water quality from DAF

New Mitigation Strategy – DAF Treatment Efficiency

0

5

10

15

20

25

30

35

8/17/2014 8/21/2014 8/25/2014 8/29/2014 9/2/2014 9/6/2014

Iron,Dissolved(m

g/L)

Pre-DAF Post-DAF

0

50

100

150

200

250

300

350

400

450

8/17/2014 8/21/2014 8/25/2014 8/29/2014 9/2/2014 9/6/2014

Oil&GreaseCo

nten

t(mg/L)

Pre-DAF Post-DAF

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

8/17/2014 8/21/2014 8/25/2014 8/29/2014 9/2/2014 9/6/2014

SRBCo

unt(cfu/mL)

Pre-DAF Post-DAF

0

200

400

600

800

1000

1200

1400

1600

1800

8/17/2014 8/21/2014 8/25/2014 8/29/2014 9/2/2014 9/6/2014

TSS(m

g/L)

Pre-DAF Post-DAF

Page 19: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Performed biocide kill studies –  Matrix of different biocides & concentrations

•  Iterations of biocide treatment programs

–  Glutaraldehyde/quaternary amine at 50 ppm •  Continuously injected upstream of DAF to treat FW •  Implemented before facility modifications •  Not ideal treatment location, but only place to get continuous injection

–  DDAC quaternary amine at 50 ppm •  Implemented after facility modifications •  50 ppm dosed only to weekly added pond volumes •  Injected into circulation lines

–  DDAC quaternary amine at 10 ppm •  Implemented after SRB counts stabilized •  10 ppm dosed only to weekly stored pond volumes •  Injected into circulation lines

New Mitigation Strategy – Biocide Treatment

Page 20: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Chemical vendor change in June 2015 •  Continuous injection of glutaraldehyde/

quaternary amine (glut/quat) upstream of DAF at 50 ppm

•  Batch treatment of glut/quat utilized to suppress SRB explosion in September (50 ppm)

•  SRB growth resulted in occasional H2S detection events at pond water loading tanks and frac sites

•  Delivered approximately 13,000 bbls of pond water per completion

Conclusions – Historical Performance

-50

-30

-10

10

30

50

70

90

0

5

10

15

20

25

30

35

40

45

50

6/1/2015 7/11/2015 8/20/2015 9/29/2015 11/8/2015

Tempe

rature(°F)

BoTleCou

nts

2015APB&SRBTes5ngResults

APB

SRB

AmbientTemperature

Page 21: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Changed chemical vendors again in January 2016

•  System operational March 2016 •  DDAC quaternary amine injected in

circulation system at 50 ppm for new volumes, 10 ppm for storage volume

•  Stable SRB and APB counts •  No H2S detection events •  Reduced drilling program still resulted in

only approximately 13,000 bbls of pond water per completion

•  Significant cost savings compared to historical bio-stat treatments

Conclusions – 2016 Performance

-50

-30

-10

10

30

50

70

90

0

2

4

6

8

10

12

4/15/2016 5/25/2016 7/4/2016 8/13/2016 9/22/2016

Tempe

rature(°F)

BoTleCou

nts

2016APB&SRBTes5ngResults

APB

SRB

AmbientTemperature

Page 22: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

•  Key Takeaways –  Several aspects of water treatment affect H2S generation

•  Hydrocarbon removal •  TSS removal •  Circulation •  Biocide

– Effective SRB management in storage = Effective treatment during completions

•  System changes resulted in 90% reduction of chemical costs

•  Recycling system better prepared for future development

Conclusions – System Performance

Page 23: Jonah Field H2S Mitigation Strategy - LBCG...Flowback Unit Settling Tank Flowback Water (FW) Well 1 Well 2 Well 3 Well 4 Meter M etr Meter Meter Produced Water (PW) Condensate 3-phase

Questions?