Joint Regional Planning Panel Thursday, 16 October 2014 THE HILLS SHIRE COUNCIL

Transcript of Joint Regional Planning Panel - thehills.nsw.gov.au · (Sydney West Region) ... DCP Part D Section...

Joint Regional

Planning

Panel

Thursday, 16 October 2014

THE H

ILLS S

HIR

E C

OU

NC

IL

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 2

ITEM SUBJECT PAGE

ITEM-2 FURTHER JRPP REPORT - DA NO. 824/2013/JP –

RESIDENTIAL DEVELOPMENT INCLUDING SIX (6)

RESIDENTIAL FLAT BUILDINGS (174

APARTMENTS), AT-GRADE AND BASEMENT CAR

PARKING, LANDSCAPING AND COMMUNAL

FACILITIES - LOT 31 DP 247442, NO. 28 FAIRWAY

DRIVE, KELLYVILLE

3

ITEM-3 JRPP REPORT - DA 1194/2014/JP –

AN INTEGRATED HOUSING DEVELOPMENT

COMPRISING 153 DWELLINGS AND COMMUNITY

TITLE SUBDIVISION - LOT 48 DP 280036 CADDIES

BOULEVARD, ROUSE HILL

73

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 3

ITEM-1 FURTHER REPORT – DA 824/2013/JP

(Sydney West Region)

JRPP No 2013SYW029

DA Number FURTHER REPORT - 824/2013/JP

Local Government Area THE HILLS SHIRE COUNCIL

Proposed Development

RESIDENTIAL DEVELOPMENT INCLUDING SIX (6)

RESIDENTIAL FLAT BUILDINGS (174 APARTMENTS), AT-

GRADE AND BASEMENT CAR PARKING, LANDSCAPING

AND COMMUNAL FACILITIES.

Street Address LOT 31 DP 247442, NO. 28 FAIRWAY DRIVE, KELLYVILLE

Applicant/Owner ARDEN CH (NSW) PTY LTD

Number of Submissions TWO (2) – AMENDED PLANS

Regional Development

Criteria (Schedule 4A

of the Act)

CAPITAL INVESTMENT VALUE EXCEEDS $20 MILLION

List of All Relevant

s79C(1)(a) Matters

The Hills LEP 2012

The Hills DCP 2012

SEPP No. 65 – Design Quality of Residential Flat

Development

Residential Flat Design Code

Recommendation APPROVAL

List all documents

submitted with this report

for the panel’s

consideration

NIL

Report by DEVELOPMENT ASSESSMENT COORDINATOR

ROBERT BUCKHAM

BACKGROUND MANDATORY REQUIREMENTS

Owner: Arden CH (NSW)

Pty Ltd

1. Section 79C (EP&A Act) -

Satisfactory

Zoning: R4 High Density

Residential and

SP2 Infrastructure

2. The Hills LEP 2012 - Satisfactory

Area: 19,693m2 3. SEPP 65 – Design Quality of

Residential Flat Development –

Satisfactory

Existing Development: Dwelling house 4. DCP Part D Section 7 – Balmoral

Road Release Area – Satisfactory

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 4

5. DCP Part B Section 5 – Residential

Flat Buildings – Satisfactory

6. DCP Part C Section 1 – Parking –

Satisfactory

7. BHSC Multi Unit Housing Guidelines

Satisfactory

8. Section 94 Contribution – Currently

$4,440,570.69

9. Capital Investment Value:

$71,400,000

SUBMISSIONS REASONS FOR REFERRAL TO JRPP

1. Exhibition: 1st - Yes, 31 days.

2nd – N/A

3rd – N/A

1. Capital Investment Value in excess

of $20 million pursuant to SEPP

(Major Development) 2005.

2. Notice Adj Owners: 1st - Yes, 31 days.

2nd – Yes, 14 days

3rd – Yes, 14 days

3. Number Advised: Nine

4. Submissions

Received:

1st - Six

2nd – One

(After the

notification period)

3rd (Amended

Plans) – Two, one

in support, one

against.

EXECUTIVE SUMMARY

The Development Application is for the construction of a residential development

including 7 x four storey residential flat buildings with a total of 174 units consisting of

65 x 1 bedroom units, 89 x 2 bedroom and 20 x 3 bedroom units. Three hundred and

seventy (370) off-street car parking spaces are proposed. The Capital Investment Value

is $71,400,000.

The proposed development includes variations to The Hills DCP Part B Section 5 –

Residential Flat Buildings in respect to parking, building setbacks, and building length.

On 7 August 2014 the Joint Regional Planning Panel considered the matter. The Panel

unanimously decided that the matter be deferred pending finalised plans and further

notification.

The applicant was requested to amend the proposal to provide increased setbacks to

Horatio Avenue. The amended plans were renotified to adjoining owners including those

of a recently completed integrated housing development to the north. Two submissions

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 5

were received, one in support of the modifications and another raising concern with the

development as a whole.

As addressed in the previous report to the JRPP, an assessment of the proposal against

the recently adopted DCP controls finds that 100% of the 174 units comply with the type

3 apartment size categories. In addition, 65 out of the 174 units (37%) comprise one

bedroom, 89 units comprise 2 bedroom (51%) and 20 out of the 174 units (12%)

comprise apartments with three or more bedrooms. Only the mix of one bedroom units

exceeds the 25% mix control but all these units are 75m2 in area or greater. It is

considered that the level of compliance is satisfactory when considered on merit and

given when the application was lodged.

The development was previously considered acceptable with the exception of the

setbacks to Horatio Avenue. The amendments to the design now provide a 10 metre

building setback and an eight metre balcony setback which affords an appropriate

transition to the R3 zoned land to the north. The proposal is now recommended for

approval.

In the absence of the JRPP process the matter would be determined by Council’s

Development Assessment Unit.

HISTORY

07/08/2014

Joint Regional Planning Panel meeting held. The Panel

unanimously decided that the matter be deferred pending

finalised plans and further notification.

22/08/2014 Amended Plans received detailing an increased setback to

Horatio Avenue. A 10m building setback and 8m balcony

setback provided in lieu of a 6m setback.

26/08/2014 Application notified for 14 days.

09/09/2014 New DCP controls for Residential Flat Buildings adopted by

Council.

REPORT

As identified in the history section of this report, at the JRPP meeting on 7 August 2014

the panel resolved to defer the application pending finalised plans and further

notification.

The applicant has provided additional information on 22 August 2014 and Council staff

have reviewed the information (refer Attachment 2).

The amended proposal has been assessed against the relevant planning controls and

remains consistent with the assessment outlined in the previous report to the JRPP with

the exception of building setbacks.

The amendments provide a 10m building setback and 8m balcony setback provided in

lieu of a 6m setback to Horatio Avenue. This remains a variation to the DCP which is

addressed below.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 6

(i) Building Setbacks

The following table summarises the proposed Residential Flat Building Setbacks against

the setback requirements of Clause 3.3 of The Hills DCP Part B Section 5 – Residential

Flat Buildings:

APARTMENT REQUIRED PROPOSED COMPLIANCE

Apartment Block 1

(one street frontage to

Fairway Drive)

Front (one

street frontage

= 10 metres

Side = 6 metres

Front = 11.2

metres

Side = 7.8

metres

Yes

Yes

Apartment Block 2

(one street frontage to

Fairway Drive)

Front (one

street frontage

= 10 metres

Side = 6 metres

Front = 11.9

metres

Side = 6 metres

Yes

Yes

Apartment Block 3

(internal to the site)

Side = 6 metres Side = 6.8

metres

Yes

Apartment Block 4

(one street frontage to

Horatio Avenue)

Front (one

street frontage

= 10 metres

Front = 10m

building and

8m balcony

setback from

Horatio

Avenue

No.

Apartment Block 5

(internal to the site)

Side = 6 metres Side = 6 metres Yes

Apartment Block 6

(primary street frontage to

Horatio Avenue and

secondary street frontage

to Lucinda Avenue)

Front (primary

frontage to

Horatio Avenue)

= 10 metres

Front

(secondary

frontage to

Lucinda Avenue)

= 6 metres

Front = 10m

building and

8m balcony

setback form

Horatio

Avenue

Front = 6

metres

No

Apartment Block 7

(primary street frontage to

Lucinda Avenue and

secondary street frontage

to Horatio Avenue)

Front (primary

frontage to

Horatio Avenue)

= 10 metres

Front

(secondary

frontage to

Lucinda Avenue)

= 6 metres

Side = 6 metres

Front = 10m

building and

8m balcony

setback form

Horatio

Avenue

Front = 7.2

metres

Side (south) =

6m

No

Yes

Yes

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 7

The objectives for setbacks under Clause 3.3 of The Hills DCP Part B Section 5 –

Residential Flat Building are as follows:

(i) “To provide setbacks that complement the setting and contribute to the

streetscape and character of the street while allowing flexibility in siting of

buildings.

(ii) To ensure that the space in front of the building is sufficient to permit

landscaping that will complement the building form and enhance the

landscape character of the street.

(iii) Side and rear setbacks are to be proportioned to the slope of the site having

regard to the height and relationship of the buildings on adjoining properties.

(iv) The setbacks of proposed buildings are to minimise any adverse impacts such

as overshadowing and privacy on adjacent and adjoining properties.

(v) To ensure placement of buildings takes into account the retention and

protection of existing trees.”

In support of the variation, the applicant has provided the following justification:

The proposed encroachments are minor and relate to articulated building

components and balconies and will enable sufficient landscaping to be established

around the site perimeter.

There is no unreasonable impact on the privacy or solar access of adjoining

properties and will not result in adverse amenity impacts on surrounding

development.

The proposed setback to Horatio Avenue is consistent with the setbacks approved

along the opposite side of Horatio Avenue at No. 24 – 26 Fairway Drive which

approved townhouses setback 5m to 7m from Horatio Avenue.

The proposed landscaping across the site exceeds Council’s requirements and will

be provided within the setbacks, improving visual amenity and privacy.

Internal separation distances between buildings have been provided.

The amended plans provide an increased setback to Horatio Avenue which was originally

6m. The amendments provide a main building setback of 10 metres and a setback of 8

metres to balconies fronting Horatio Avenue.

The amendments to the design now provide an appropriate transition to the R3 zoned

land to the north and the proposal can now be recommended for approval.

ii. Issues Raised in Submissions

The amended plans were renotified to adjoining owners including those of a recently

completed integrated housing development to the north who have not previously been

notified as the property at that time had not been subdivided. Two submissions were

received, one in support of the amendments and another raising concern with the

development concept as a whole.

The following issues raised in the objection are addressed in the following table:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 8

ISSUE/OBJECTION COMMENT OUTCOME

Concern is raised about

noise and privacy issues. It

is suggested that the

proposed development be

amended to townhouses,

free standing dwellings or

low density apartments.

The proposed development is

permissible on land zoned R4

High Density Residential under

The Hills LEP 2012. The proposed

development is consistent with

the aims and objectives of the R4

High Density Residential zone.

The development provides

adequate separation from

adjoining properties.

Issue addressed.

One of the entry/exits via

Horatio Avenue will

substantially increase

vehicular volume of this

internal feeder road. All

entry/exit should be via

ramp across creek to

Fairway Drive.

The applicant is permitted to

provide access to public roads

fronting the site. A bridge

crossing over the creek would be

cost impracticle.

Issue addressed.

CONCLUSION

The Development Application has been assessed against the provisions of Section 79C of

the Environmental Planning and Assessment Act, 1979, The Hills Local Environmental

Plan 2012, The Hills Development Control Plan 2012, and State Environmental Planning

Policy No. 65 – Design Quality of Residential Flat Development.

The applicant provided amended plans with an increased setback to Horatio Avenue. The

applicant has provided a main building setback of 10 metres and a setback of 8 metres

to balconies fronting Horatio Avenue. The amended plans were renotified to adjoining

owners. One objection was received. The issues raised in the submissions have been

addressed in the report.

The application is recommended for approval subject to conditions.

RECOMMENDATION

The Development Application be approved subject to the following conditions of consent.

GENERAL MATTERS

1. Development in Accordance with Submitted Plans

The development being carried out in accordance with the approved plans and details

submitted to Council, as amended in red, stamped and returned with this consent. No

work (including excavation, land fill or earth reshaping) shall be undertaken prior to the

issue of the Construction Certificate, where a Construction Certificate is required

The amendments in red include:

Deletion of bridge across SP2 zoned land in accordance with Sydney Water

Requirements.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 9

REFERENCED PLANS AND DOCUMENTS

DRAWING NO. DESCRIPTION REVISION DATE

DA-1.05 Site Plan H 13 August 2014

DA-02.01 Basement Plan (West) G 1 April 2014

DA-02.02 Basement Plan (East) H 13 August 2014

DA-02.03 Ground Floor Plan (West) G 1 April 2014

DA-02.04 Ground Floor Plan (East) H 13 August 2014

DA-02.05 Typical Floor Plan (West) G 1 April 2014

DA-02.06 First Floor Plan (East) H 13 August 2014

DA-2.07 Typical Floor Plan 2-3

(West)

G 1 April 2014

DA-2.07 Typical Floor Plan 2-3

(East)

H 13 August 2014

DA-3.01 North Elevation H 13 August 2014

DA-3.02 South Elevation H 13 August 2014

DA-3.03 East and West Elevation H 13 August 2014

DA-4.01 Section A-A H 13 August 2014

DA-4.02 Section B-B and C-C H 13 August 2014

DA-4.03 Section D-D H 13 August 2014

DA-1.03 Proposed Riparian Zone D 15 August 2013

2. Construction Certificate

Prior to construction of the approved development, it is necessary to obtain a

Construction Certificate. A Construction Certificate may be issued by Council or an

Accredited Certifier. Plans submitted with the Construction Certificate are to be amended

to incorporate the conditions of the Development Consent.

3. Building Work to be in Accordance with BCA

All building work must be carried out in accordance with the provisions of the Building

Code of Australia.

4. Compliance with NSW Office of Water

Compliance with the requirements of the NSW Office of Water as outlined in their letter

dated 14 March 2013 Ref: 10 ERM2012/0981 attached to this consent as Appendix A.

5. Compliance with NSW Police Force Requirements

The following is required by the Police, unless otherwise agreed by the Police and Council

in writing:

i. Fencing should be vertical style to stop unauthorised access to ground floor units;

ii. Materials chosen should have regard to the potential for graffiti.

iii. There is potential for unauthorised access to car parks and tenant storage areas.

Police suggest a use of a swipe card or keypad access for residents to access

these areas. Each garage door should be secured and it is recommended that a

alarm system be installed.

iv. It is recommended that during the construction phase security sensor lights be

used and security guards monitor the site.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 10

6. Liquid Storage - Pool Chemicals

All liquids onsite are to be stored within bunded areas so as to prevent water pollution.

All secondary and site containment mechanisms are to be implemented as per Appendix

2: Technical Considerations within the Storing and Handling Liquids: Environmental

Protection – Participants Manual prepared by the Department of Environment and

Climate Change NSW dated May 2007.

7. Salinity Assessment & Site Salinity Management Plan

The recommendations of the Salinity Assessment and Management Plan prepared by

Environmental Investigation Service, referenced as E26168KBrpt2-sal, dated November

2012 and submitted as part of the Development Application are to be implemented as

part of this approval. In particular:

8.5 Surface-water, Stormwater and Drainage

Surface water, storm water and drainage design should include the following:

The disturbance of natural drainage patterns should be avoided;

Where the drainage patterns are altered, appropriate, alternative artificial

drainage should be installed;

Slabs, foundations and retaining walls should be designed with subsoil drains and

good drainage to avoid water logging;

Stormwater should be managed appropriately in order to reduce infiltration.

Stormwater infrastructure should be designed to minimise leakage;

Guttering and down pipes should be properly connected and maintained;

Subsoil drains should be provided in areas where seepage discharge from the

underlying natural soil may occur, such as retained cuts, cut slopes, low lying

areas or significant changes in grade, etc; and

Surface water runoff should be directed around all stockpiles and work areas.

8. Property Numbering for Integrated Housing, Multi Unit Housing, Commercial

Developments and Industrial Developments

The responsibility for property numbering is vested solely in Council.

Buildings 1, 2 & 3 will be addressed to Fairway Drive with one letterbox bank to be

located at this frontage to accommodate units 1-84. Due to development that will occur

along Fairway Drive in the future, current street numbers will be changed. As a result of

this the site will not have an address of 28 Fairway Drive. The new street number

cannot be allocated at this time.

Buildings 4-6 will be addressed to the proposed new road Lucinda Avenue and will be

allocated the street number one (1). One bank of letterboxes is to be located at the

Lucinda Avenue frontage to accommodate units 85-176.

Unit numbers are allocated as follows

Building 1 - Units 1-24 Fairway Drive Kellyville

Building 2 - Units 24-44 Fairway Drive Kellyville

Building 3 - Units 45-84 Fairway Drive Kellyville

Building 4 - Units 85-124 / 1 Lucinda Avenue Kellyville

Building 5 - Units 125-152 / 1 Lucinda Avenue Kellyville

Building 6 - Units 153-174 / 1 Lucinda Avenue Kellyville

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 11

Please refer to approved numbering correspondence and marked plan numbers DA-1.05

(Revision D) & DA-2.03 to DA-2.09 (revision D). These numbers, unless otherwise

approved by Council in writing, are to be displayed at street frontages and on all door

entrances.

If this development is subdivided in stages and given different strata numbers, this will

have an impact on the proposed unit numbers.

A diagrammatic plan is to be erected on site at driveway entry points. Clear and

accurate external directional signage is to be erected on all buildings, stairways, lift

shafts, units and lobby entry doors.

It is essential that all numbering signage throughout the complex is clear to assist

emergency service providers locate a destination with ease and speed, in the event of an

emergency.

9. Australia Post Mail Box Requirements

The number of mail boxes to be provided is to be equal to the number of residences and

one (1) for the proprietors. Mail boxes are to have a minimum internal dimension of

230mm wide x 160mm High x 330mm long and are to be provided with an opening of

230mm x 30mm for the reception of mail.

10. Subdivision Certificate Pre-Lodgement Meeting/ Check

Prior to the submission of a Subdivision Certificate application a draft copy of the final

plan, administration sheet and Section 88B instrument (where included) must be

submitted in order to establish that all conditions have been complied with.

11. Approved Street Naming

Street naming must comply with Council’s approved map which can be found on

Council’s website.

12. Street Trees

Street trees must be provided for the section of Fairway Drive, Horatio Avenue and

Lucinda Avenue within or fronting the development site spaced between 7m and 10m

apart. The location of street trees must be considerate of driveways, services, drainage

pits and sight lines at intersections. The species and size of street trees must comply

with the requirements of Council. Details demonstrating compliance with the above must

be submitted for approval before any street trees are planted.

A performance/ maintenance bond is required to be submitted to Council once the street

trees are planted. The bond will be held for one year and may be extended if

replacement street trees are required to be planted. The bond is refundable upon written

application to Council. Alternatively, street trees can be planted by Council subject to

payment of the applicable fee as per Council’s Schedule of Fees and Charges.

13. Recycled Water

The subject site must be connected to Sydney Water’s Rouse Hill Recycled Water

Scheme, unless written evidence from Sydney Water is submitted advising that this

service is not available.

14. Water Sensitive Urban Design Handover Process

An operations and maintenance plan must be prepared for all WSUD proposals. The

operations and maintenance plan must include:

a) The location and type of each WSUD element, including details of its operation and

design;

b) A brief description of the catchment characteristics, such as land uses, areas etc;

c) Estimated pollutant types, loads and indicative sources;

d) Intended maintenance responsibility, Council, landowner etc;

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 12

e) Inspection method and estimated frequency;

f) Adopted design cleaning/ maintenance frequency;

g) Estimate life-cycle costs;

h) Site access details, including confirmation of legal access, access limitations etc;

i) Access details for WSUD measure, such as covers, locks, traffic control requirements

etc;

j) Description of optimum cleaning method and alternatives, including equipment and

personnel requirements;

k) Landscape and weed control requirements, noting that intensive initial planting is

required upfront to reduce the requirement for active weed removal;

l) A work method statement;

m) A standard inspection and cleaning form.

For the purposes of complying with the above a WSUD treatment system is considered

to include all functional elements of the system as well as any landscaped areas directly

surrounding the system.

15. Separate Application for Strata Subdivision

A separate application must be submitted for any proposed strata titled subdivision of

the approved development.

16. Protection of Public Infrastructure

Council must be notified of any damage to public infrastructure caused by the

development. Adequate protection must be provided prior to work commencing and

maintained during building operations. Any damage caused must be made good, to the

satisfaction of Council, before an Occupation Certificate can be issued. Public

infrastructure includes the road pavement, kerb and gutter, concrete footpaths, drainage

structures, utilities and landscaping fronting the site.

17. Vehicular Access and Parking

The formation, surfacing and drainage of all driveways, parking modules, circulation

roadways and ramps are required, with their design and construction complying with:

a) AS/ NZS 2890.1

b) AS/ NZS 2890.6

c) AS 2890.2

d) Council’s DCP Part C Section 1 – Parking

e) Council’s Driveway Specifications

Where conflict exists the Australian Standard must be used.

The following must be provided:

i. All driveways and car parking areas must be prominently and permanently line

marked, signposted and maintained to ensure entry and exit is in a forward

direction at all times and that parking and traffic circulation is appropriately

controlled.

ii. All driveways and car parking areas must be separated from landscaped areas by

a low level concrete kerb or wall.

iii. All driveways and car parking areas must be concrete or bitumen. The design

must consider the largest design service vehicle expected to enter the site. In

rural areas, all driveways and car parking areas must provide for a formed all

weather finish.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 13

iv. All driveways and car parking areas must be graded, collected and drained by pits

and pipes to a suitable point of legal discharge.

18. Detailed Design Requirements – Car Parking

The detailed design/ Construction Certificate plans must comply with the following

requirements:

f) Drawing DA-C-305 Issue B dated 12 February 2014 prepared by LP Consulting shows

a gradient of 34.8% for the driveway/ basement ramp “Lucinda Avenue Basement

East”. This must be reduced to 25% (maximum), being the maximum driveway

gradient permitted for passenger vehicles as per AS/ NZS 2890.1. Also, access to

this driveway/ basement ramp will be limited to passenger vehicles only as a result of

this steep grade. AS 2890.2 includes more stringent requirements relating to service

vehicles, including waste collection.

g) All visitor parking spaces must be 2.5m wide (minimum).

h) All resident parking spaces must be 2.4m wide (minimum).

i) Blind aisles that include visitor parking spaces require a dedicated turning area as per

AS/ NZS 2890.1.

j) No security gates/ roller shutters or the like are permitted unless the design also

includes a dedicated turning area in front of any such gate/ shutter, so that a person

is able to turn and leave the site if access is not available. Also, the gradient of this

queuing/ turning area in front of the gate/ shutter must have a gradient no steeper

than 6%.

19. Gutter and Footpath Crossing Application

Each driveway requires the lodgement of a separate gutter and footpath crossing

application, accompanied by the applicable fee as per Council’s Schedule of Fees and

Charges.

20. Minor Engineering Works

The design and construction of the engineering works listed below must be provided for

in accordance with the following documents and requirements:

a) Council’s Design Guidelines Subdivisions/ Developments

b) Council’s Works Specifications Subdivisions/ Developments

Any variance from these documents requires separate approval from Council.

Works on existing public roads or any other land under the care and control of Council

must be approved and inspected by Council in accordance with the Roads Act 1993 or

the Local Government Act 1993. A separate minor engineering works application and

inspection fee is payable as per Council’s Schedule of Fees and Charges.

i. Driveway Requirements

The design, finish, gradient and location of all driveway crossings must comply with the

above documents and Council’s Driveway Specifications.

The proposed driveways must be built to Council’s heavy duty standard.

A separate driveway application fee is payable as per Council’s Schedule of Fees and

Charges.

ii. Site Stormwater Drainage

The entire site area must be graded, collected and drained by pits and pipes to a suitable

point of legal discharge.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 14

21. Excavation/ Anchoring Near Boundaries

Earthworks near the property boundary must be carried out in a way so as to not cause

an impact on adjoining public or private assets. Where anchoring is proposed to sustain

excavation near the property boundary, the following requirements apply:

- Written owner’s consent for works on adjoining land must be obtained.

- For works adjacent to a road, anchoring that extends into the footpath verge is not

permitted, except where expressly approved otherwise by Council, or the RMS in the

case of a classified road.

- Where anchoring within public land is permitted, a bond must be submitted to

ensure their removal once works are complete. The value of this bond must relate to

the cost of their removal and must be confirmed by Council in writing before

payment.

- All anchors must be temporary. Once works are complete, all loads must be

removed from the anchors.

- A plan must be prepared, along with all accompanying structural detail and

certification, identifying the location and number of anchors proposed.

- The anchors must be located clear of existing and proposed services.

Details demonstrating compliance with the above must be submitted to the Principal

Certifying Authority and included as part of any Construction Certificate or Occupation

Certificate issued.

22. Adherence to Waste Management Plan

All commitments of the Waste Management Plan submitted as part of the Development

Application must be implemented during construction of the development. The

information submitted can change provided that the same or a greater level of reuse and

recycling is achieved as detailed in the plan. Any material moved offsite is to be

transported in accordance with the requirements of the Protection of the Environment

Operations Act 1997 and only to a place that can lawfully be used as a waste facility.

Receipts of all waste/ recycling tipping must be kept on site at all times and produced in

a legible form to any authorised officer of the Council who asks to see them.

23. Management of Construction and Demolition Waste

Waste materials must be appropriately stored and secured within a designated waste

area on site at all times, prior to its reuse on site or being sent off site. Building waste

containers are not permitted to be placed on the public way at any time unless a

separate application is approved by Council to locate a building waste container in a

public place. Any material moved off site must be transported to a place that can lawfully

be used as a waste facility or to facilities that can otherwise lawfully receive waste. The

separation and recycling of the following waste materials is required: metals, timber,

masonry products, clean waste plasterboard and mixed plastics and cardboard. This can

be achieved by source separation on site, that is, a bin for metal waste, a bin for timber,

a bin for bricks and so on. Alternatively, mixed waste may be stored in one or more bins

and sent to a waste contractor or transfer/ sorting station that will sort the waste on

their premises for recycling. Receipts of all waste/ recycling tipping must be kept on site

at all times and produced in a legible form to any authorised officer of the Council who

asks to see them.

24. Surplus Excavated Material

The disposal of surplus excavated material, other than to a licenced waste facility, is not

permitted without formal approval from Council, prior to works commencing on site. Any

unauthorised disposal of waste, which includes excavated material, is a breach of the

Protection of the Environment Operations Act 1997 and subject to substantial penalties.

Receipts of all waste/ recycling tipping must be kept on site at all times and produced in

a legible form to any authorised officer of the Council who asks to see them.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 15

25. Commencement of Domestic Waste Service

The property owner or agent acting for the owner must ensure to arrange the

commencement of a domestic waste service with Council no later than two days after

occupancy and no earlier than two days prior to occupancy of the development. The

service is to be arranged by telephoning Council on (02) 9843 0310. All requirements of

Council’s waste collection service must be complied with at all times.

26. Construction of Waste Storage Areas (Buildings One-Six)

All work involving construction of the waste storage areas is required to comply with the

requirements of Council’s Bin Storage Facility Design Specifications. Storage facility is to

be provided for a minimum of:

Buildings One-Three: Nine (9) 1100 litre bulk garbage bins and forty (40) 240 litre

mobile recycling bins.

Buildings Four-Six: Nine (9) 1100 litre bulk garbage bins and forty-two (42) 240 litre

mobile recycling bins.

27. Construction of Waste Storage Area (Building 7)

All work involving construction of the waste storage area is required to comply with the

requirements of Council’s Bin Storage Facility Design Specifications. The storage area is

required to be sized to comfortably store and manoeuvre a minimum of two (2) 660 litre

bulk garbage bins and six (6) 240 litre mobile recycling bins. The waste servicing door to

the storage area is required to open directly to the street, and have a direct access path

leading to the street, with a maximum gradient of 5%, including kerb crossing.

28. Restricted Development Area Fencing

The Restricted Development Area, being the area labelled on the riparian zone plan

(Reference: DA-1.03, revision D) is to be delineated with an appropriate fence (post and

rail or similar) to distinguish the riparian zone from the landscaped areas. No barbed

wire is to be used.

29. Vegetation Bond

Lodgement of a security bond of $40,000.00 to ensure satisfactory completion and

maintenance of the vegetation works.

The security bond will be progressively released at the following stages subject to the

submission of progress reports and the satisfactory completion of works in accordance

with the Council-approved Vegetation Management Plan (VMP):

Release of 25%, 12 months after the initial planting;

Release of a further 25%, 36 months after the initial planting;

Final release of 50%, 60 months after the initial planting.

Progress reports are required to be submitted prior to each progressive partial bond

release demonstrating compliance with the Council-approved VMP. The progress reports

shall be prepared by a professional ecologist/bush regeneration specialist and certified

by Council’s Manager – Environment and Health.

PRIOR TO THE ISSUE OF CONSTRUCTION CERTIFICATE

30. Erosion & Sediment Control Plan

Submission of an Erosion and Sediment Control Plan to the Principal Certifying Authority,

including details of:

a) Allotment boundaries

b) Location of the adjoining roads

c) Contours

d) Existing vegetation

e) Existing site drainage

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 16

f) Critical natural areas

g) Location of stockpiles

h) Erosion control practices

i) Sediment control practices

j) Outline of a maintenance program for the erosion and sediment controls

(NOTE: For guidance on the preparation of the Plan refer to ‘Managing Urban

Stormwater Soils & Construction’ produced by the NSW Department of Housing).

31. Section 94 Contribution – Balmoral Road Release Area

The following monetary contributions must be paid to Council in accordance with Section

94 of the Environmental Planning and Assessment Act, 1979, to provide for the

increased demand for public amenities and services resulting from the development.

Payments comprise of the following:-

Prior to payment of the above contributions, the applicant is advised to contact Council’s

Development Contributions Officer on 9843 0268. Payment must be made by cheque or

credit/debit card. Cash payments will not be accepted.

This condition has been imposed in accordance with Contributions Plan No. 12.

Council’s Contributions Plans can be viewed at www.thehills.nsw.gov.au or a copy may

be inspected or purchased at Council’s Administration Centre.

32. Underground of Overhead Services

A Construction Certificate cannot be issued until an agreement has been reached with

Endeavour Energy, confirmed in writing, in relation to the undergrounding/ relocation of

the existing high voltage overhead power lines and the removal of the associated

easement from the title of the property.

33. Bank Guarantee Requirements

Any bank guarantee submitted in lieu of a cash bond must comply with the following:

a) Have no expiry date;

b) Be sent to Council direct from the bank;

c) Reference the development application, condition and matter to which it relates;

d) The amount must match that required to be paid;

e) If a single bank guarantee is used for multiple bonds, it must be itemised.

Should Council need to uplift the bank guarantee, notice in writing will be forwarded to

the applicant 14 days beforehand.

34. Controlled Activity Authority – NSW Office of Water

A copy of the Controlled Activity Authority required to be obtained from the NSW Office

of Water must be submitted to Council before a Construction Certificate is issued.

35. Separate Approval for WIK/ MPB Agreement

Separate approval is required where a works in kind (WIK) or material public benefit

(MPB) is proposed in lieu of the part or full payment of either a monetary contribution or

Purpose: 1

bedroom unit

Purpose: 2

bedroom unit

Purpose: 3

bedroom unit

Purpose:

Credit

No. of 1

Bedroom units:

65

No. of 2

Bedroom units:

89

No. of 3

Bedroom

units: 20

Sum of UnitsNo. of

Credits: 1Total S94

Open Space - Land 12,930.96$ 17,904.40$ 18,865.47$ 18,865.47$ 840,512.40$ 1,593,491.60$ 377,309.40$ 2,811,313.40$ 18,865.47$ 2,792,447.93$

Open Space - Capital 3,431.83$ 4,751.77$ 5,006.83$ 5,006.83$ 223,068.95$ 422,907.53$ 100,136.60$ 746,113.08$ 5,006.83$ 741,106.25$

Transport Facilities - Capital 2,443.64$ 3,383.50$ 3,565.11$ 3,565.11$ 158,836.60$ 301,131.50$ 71,302.20$ 531,270.30$ 3,565.11$ 527,705.19$

Community Facilities - Land 255.72$ 354.08$ 373.09$ 373.09$ 16,621.80$ 31,513.12$ 7,461.80$ 55,596.72$ 373.09$ 55,223.63$

Community Facilities - Capital 1,047.63$ 1,450.57$ 1,528.43$ 1,528.43$ 68,095.95$ 129,100.73$ 30,568.60$ 227,765.28$ 1,528.43$ 226,236.85$

Administration 179.48$ 248.51$ 261.85$ 261.85$ 11,666.20$ 22,117.39$ 5,237.00$ 39,020.59$ 261.85$ 38,758.74$

Drainage Facilities - Capital 273.64$ 378.88$ 399.22$ 399.22$ 17,786.60$ 33,720.32$ 7,984.40$ 59,491.32$ 399.22$ 59,092.10$

Total 20,562.90$ 28,471.71$ 30,000.00$ 30,000.00$ 1,336,588.50$ 2,533,982.19$ 600,000.00$ 4,470,570.69$ 30,000.00$ 4,440,570.69$

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 17

the dedication of land. Any WIK or MPB application must be made in writing. Contact

Council to ascertain the information required to accompany any such application.

The WIK or MPB agreement must be finalised before a Construction Certificate is issued.

Once the WIK or MPB agreement has been finalised an application must be submitted to

modify the Section 94 Contribution amount identified in this consent, unless it is agreed

that the difference can be reimbursed after payment is made.

36. Sediment and Erosion Control Plan

A sediment and erosion control plan prepared in accordance with Council’s Works

Specification Subdivision/ Developments must be submitted. The plan must include:

a) Allotment boundaries;

b) Adjoining roads;

c) Contours;

d) Existing vegetation;

e) Existing site drainage;

f) Critical natural areas;

g) Location of stockpiles;

h) Erosion control practices;

i) Sediment control practices; and

j) A maintenance program for the erosion and sediment controls.

37. Stormwater Pump/ Basement Car Park Requirements

The stormwater pump-out system must provide for the following:

a) A holding tank sized to store the runoff from a 12 hour, 1 in 100 year design storm

event;

b) An alternating two pump system capable of emptying the holding tank at either the

Permissible Site Discharge rate or the rate of inflow for a five hour, 1 in 5 year design

storm event, whichever is lower;

c) An alarm system to alert a pump failure;

d) 100mm freeboard to all nearby parking spaces;

e) The system must be connected to the Onsite Stormwater Detention system before

being discharged to the street along with the remaining site runoff, under gravity.

All plans, calculations, hydraulic details and manufacturer specifications for the pump

must be submitted with certification from the designer confirming compliance with the

above requirements.

38. Draft Legal Documents

Where an encumbrance on title is required to be created as part of this consent, draft

copies of all legal documents must be submitted to Council for checking before a

Construction Certificate is issued.

39. Security Bond – Road Pavement and Public Asset Protection

In accordance with Section 80A(6)(a) of the Environmental Planning and Assessment Act

1979, a security bond of $118,320.00 is required to be submitted to Council to

guarantee the protection of the road pavement and other public assets in the vicinity of

the site during construction works. The above amount is calculated at the rate of $85.00

per square metre based on the road frontage of the subject site plus an additional 50m

on either side (174m) multiplied by the width of the road (8m).

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 18

The bond must be lodged with Council before a Construction Certificate is issued.

The bond is refundable upon written application to Council and is subject to all work

being restored to Council’s satisfaction. Should the cost of restoring any damage exceed

the value of the bond, Council will undertake the works and issue an invoice for the

recovery of these costs.

40. Security Bond – External Works

In accordance with Section 80A(6)(b) of the Environmental Planning and Assessment Act

1979, a security bond is required to be submitted to Council to guarantee the

construction, completion and performance of all works external to the site. The bonded

amount must be based on 150% of the tendered value of providing all such works. The

minimum bond amount is $10,000.00. The bond amount must be confirmed with Council

prior to payment.

The bond must be lodged with Council before a Construction Certificate is issued.

The bond is refundable upon written application to Council and is subject to all work

being completed to Council’s satisfaction.

41. Engineering Works and Design

The design and construction of the engineering works listed below must be provided for

in accordance with the following documents and requirements:

a) Council’s Design Guidelines Subdivisions/ Developments

b) Council’s Works Specifications Subdivisions/ Developments

Variation from these documents can only be approved by Council’s Manager –

Subdivision and Development Certification.

Engineering works can be classified as either “subdivision works” or “building works” as

categorised below:

1. Works within an existing or proposed public road, or works within an existing or

proposed public reserve. These works can only be approved, inspected and certified

by Council in accordance with the Roads Act 1993 and the Local Government Act

1993 respectively. For Council to issue this approval the following must be provided:

a) A completed application form.

b) An electronic copy of the design plans and accompanying documentation.

c) Payment of the applicable application and inspection fees.

d) Payment of any required security bonds.

2. Works within the development site, or an adjoining private property, that relates to

existing or proposed Council infrastructure assets, such as the laying of a stormwater

pipeline or the formation of an overland flow path within a public drainage easement.

These works can only be approved, inspected and certified by Council because

Council will have an ongoing risk exposure and management/ maintenance liability

with respect to these assets once completed.

A “compliance certificate” as per Section 109(1)(a)(ii) of the Environmental Planning

and Assessment Act 1979 can be issued certifying that the detailed design for these

works complies with the requirements listed and the above documents. This

“compliance certificate” can be issued by Council’s Manager – Subdivision and

Development Certification and not a private certifier, as discussed. Once approved,

the works must be carried out under the supervision of Council’s Construction

Engineer in accordance with the terms attached to the issued “compliance

certificate”. Post construction, a further “compliance certificate” as per Section

109(1)(a)(i) of the Environmental Planning and Assessment Act 1979 can be issued

certifying that the as-built infrastructure and associated works have been carried out

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 19

to the satisfaction of Council’s Construction Engineer. Alternatively, these works can

be incorporated into any construction approval granted under category (1) above.

3. Works within the development site, or adjoining private properties, that do not relate

to existing or proposed Council infrastructure assets, such as water sensitive urban

design elements or inter-allotment drainage pipelines. Such works can be approved,

inspected and certified by either Council or a private certifier, so long as the private

certifier is accredited to do so.

This certification must be included with the documentation approved as part of any

Construction Certificate. The designer of the engineering works must be qualified,

experienced and have speciality knowledge in the relevant field of work.

The following engineering works are required:

i. Full Width Road Construction

The full width construction of the roads listed below is required, including footpath

paving and other ancillary work to make this construction effective:

Road Name: Formation:

(Footpath/ Carriageway/ Footpath) (m)

Lucinda Avenue Road Type:

DCP Access Street (1)

3.5m/ 8.5m/ 3.5m (15.5m total)

Pavement Design:

Access (Design Guidelines Section 3.12)

The design must incorporate a standard kerb return radius of 7.5m based on a 4m splay

corner unless otherwise directed by Council.

ii. Partial Width Road Construction

The partial width construction of the roads listed below is required, including footpath

paving and other ancillary work to make this construction effective:

Road Name: Formation:

(Footpath/ Carriageway/ Footpath) (m)

Horatio Avenue Road Type:

DCP Access Street (1)

3.5m/ 8.5m/ 3.5m (15.5m total)

Pavement Design:

Access (Design Guidelines Section 3.12)

The design must incorporate a standard kerb return radius of 7.5m based on a 4m splay

corner unless otherwise directed by Council.

As partial width construction exists opposite, the completed road must comply with the

overall requirements outlined in the table above.

iii. Partial Width Road Reconstruction

The partial width reconstruction of the existing roads listed below is required, including

any necessary service adjustments and ancillary work required to make the construction

effective:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 20

Road Name: Formation:

(Footpath/ Carriageway/ Footpath) (m)

Fairway Drive Road Type:

DCP Enhanced Collector Road with Cycleway (3C)

4.5m/ 12m/ 3.5m (20m total)

Pavement Design:

Enhanced Collector (Design Guidelines Section 3.12)

The design must incorporate a standard kerb return radius of 7.5m based on a 4m splay

corner unless otherwise directed by Council.

Where partial width reconstruction exists opposite, the completed road must comply with

the overall requirements outlined in the table above. Where partial width reconstruction

does not exist opposite, you will be responsible for the formation of the footpath verge,

kerb and gutter and the reconstruction of 6m of road pavement. This new road

pavement must transition into the existing road pavement opposite to provide for a total

minimum carriageway width of 10m, which may require additional pavement

reconstruction.

Any requirements relating to partial width road reconstruction from the relevant section

of Council’s DCP must also be complied with. All works must be carried out in accordance

with the submitted traffic safety statement.

Where the existing road reserve width exceeds that required to be provided, the

additional width is to be evenly distributed on either side of the road carriageway to

provide for a wider footpath verge.

The wider 4.5m verge must be located on the eastern side of Fairway Drive correlating

with the cycleway required by the DCP at this location.

iv. Temporary Turning Heads

A temporary cul-de-sac turning head must be provided at the end of all roads that will

be extended into adjoining properties if/ when they are developed. The cul-de-sac must

have a diameter of 19m measured from the edge pavement.

A temporary turning head is required at the southern end of Lucinda Avenue extending

into the development site.

v. Street Names Signs

Street name signs and posts are required in accordance with the above documents and

Council’s Standard Drawing 37. Details for all signage and line-marking must be

submitted to Council for checking prior to works commencing.

vi. Concrete Footpath

A 1.2m wide concrete footpath, including access ramps at all intersections, must be

provided on one side of Lucinda Avenue and Horatio Avenue in accordance with the DCP

and the above documents.

vii. Concrete Cycleway

A 2.5m wide concrete cycleway, including access ramps at all intersections, must be

provided on the eastern side of Fairway Drive in accordance with the DCP and the above

documents.

viii. Disused Layback/ Driveway Removal

All disused laybacks and driveways must be removed and replaced with full kerb and

gutter together with the restoration and turfing of the adjoining footpath verge area.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 21

ix. Service Conduits

Service conduits to the development site, laid in strict accordance with the relevant

service authority’s requirements, are required. Services must be shown on the

engineering drawings.

x. Stormwater Drainage – Temporary Works

Grassed swale drains or temporary piped drainage must be installed to intercept, control

and redirect surface stormwater runoff from upstream undeveloped properties.

xi. Stormwater Drainage – Creek Outlets

The two piped stormwater outlets/ connections to Strangers Creek must comply with the

requirements of Council and the NSW Office of Water as well as Sydney Water, in the

case of stormwater management zoned land.

xii. Water Sensitive Urban Design Elements

Water sensitive urban design elements, being those shown on the plans prepared by LP

Consulting, are to be located generally in accordance with the plans and information

submitted with the application. With respect to rainwater reuse, a 20,000 litre rainwater

tank is required for each building (or an equivalent combined volume across the

development site as a whole).

Detailed plans for the water sensitive urban design elements must be submitted for

approval. The detailed plans must be suitable for construction, and include detailed and

representative longitudinal and cross sections of the proposed infrastructure. The design

must be accompanied, informed and supported by detailed water quality and quantity

modelling. The modelling must demonstrate a reduction in annual average pollution

export loads from the development site in line with the following environmental targets:

- 90% reduction in the annual average load of gross pollutants

- 85% reduction in the annual average load of total suspended solids

- 65% reduction in the annual average load of total phosphorous

- 45% reduction in the annual average load of total nitrogen

All model parameters and data outputs are to be provided.

These elements must be designed and constructed in accordance with best practice

water sensitive urban design techniques and guidelines. Such guidelines include, but are

not limited to, the following:

- Water Sensitive Urban Design – Technical Guidelines for Western Sydney, 2004,

http://www.wsud.org/tools-resources/index.html

- Australian Runoff Quality – A Guide to Water Sensitive Urban Design, 2005,

http://www.ncwe.org.au/arq/

42. Design of Waste Storage Area (Buildings One, Two and Three)

Prior to a Construction Certificate being issued, amended plans are required to be

submitted to Council to the satisfaction of the Resource Recovery Project Officer. The

plans must demonstrate that the waste storage room is sized to comfortably store and

manoeuvre a minimum of nine (9) 1100 litre bulk garbage bins and forty-two (40) 240

litre mobile recycling bins. Additionally, the bay width of the waste servicing area is to be

increased to be at least 4m, and the bay is not permitted to have a dog leg angle.

43. Design of Waste Storage Area (Buildings Four, Five and Six)

Prior to a Construction Certificate being issued, amended plans are required to be

submitted to Council to the satisfaction of the Resource Recovery Project Officer. The

plans must demonstrate that the waste storage room is sized to comfortably store and

manoeuvre a minimum of nine (9) 1100 litre bulk garbage bins and forty-two (42) 240

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 22

litre mobile recycling bins. Additionally, the bay width of the waste servicing area is to be

increased to be at least 4m.

44. Relocation of Waste Storage Area (Building 7)

Prior to a Construction Certificate being issued, amended plans are required to be

submitted to Council to the satisfaction of the Resource Recovery Project Officer. The

waste storage room is required to be relocated to be within 8m of the street, unless it is

within the building footprint, where the maximum distance is 12m.

45. Internal Pavement Structural Design Certification

Prior to a Construction Certificate being issued, a Certified Practicing Engineer (CPEng)

must submit a letter to Council confirming the structural adequacy of the internal

pavement design (porte-cochere and rubbish collection areas). The pavement design

must be adequate to withstand the loads imposed by a loaded heavy rigid waste

collection vehicle (i.e. 28 tonne axle load) from the boundary to the waste collection

point including any manoeuvring areas.

46. Landscape Plan

A site specific Landscape Plan is to be submitted to Council’s satisfaction prior to any

works commencing on site. This plan is to show how landscaping will incorporate the use

of local provenance plants native to the local vegetation communities being River-flat

Eucalypt Forest and Cumberland Plain Woodland. Eighty percent of the plants used in the

street tree planting and in common areas are to be of local provenance groundcovers,

shrubs and trees (excluding turf and the riparian zone).

47. Biodiversity Offsetting Requirements

To offset the loss of biodiversity from the site including the removal of Cumberland Plain

Woodland, the development must purchase and retire seven (7) HN528 or HN529

ecosystem credits. A retirement certificate from the NSW BioBanking Office to

demonstrate compliance with this condition is to be provided to The Hills Shire Council’s

Manager – Environment and Health prior to issue of a Construction Certificate.

48. Landscape Plan Bond

Lodgement of a landscape bond in the amount of $10,000 to ensure satisfactory

completion is to be lodged with Council. It shall be refunded six months following issue

of the Final Occupation Certificate provided works are to the satisfaction of Council’s

Manager – Environment and Health. Works are to be certified by a qualified Landscape

Architect via the submission of appropriate documentation demonstrating compliance

with the approved landscape plan.

49. Landscape Plan Plant Procurement

The bush regeneration contractor shall order all local provenance plants that are

required to be planted as part of the Council approved Landscape Plan. Invoices detailing

the procurement shall be submitted to Council.

50. Vegetation Management Plan

A Vegetation Management Plan is to be submitted to Council prior to the release of the

construction certificate. The Vegetation Management Plan must be prepared to the

satisfaction of Council's Manager Environment and Health. The Vegetation Management

Plan is required to include information regarding how the RDA will be rehabilitated and

then managed into the future past the first 5 year rehabilitation plan.

51. Special Infrastructure Contribution – Growth Centres

The applicant is to make special infrastructure contribution in accordance with any

determination by the Minister administering the Environmental planning and Assessment

Act 1979 under Section 94EE of the Act that is in force on the date of this consent, and

must obtain a certificate to that effect from the Growths Centres Commission before a

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 23

Construction certificate or subdivision certificate is issued in relation to any part of the

development to which this consent relates

More information on the Special Infrastructure Contribution can be found at the Growth

Centres Commission’s website at www.gcc.nsw.gov

To obtain an estimate of the Special Infrastructure Contribution that may be payable for

the application please email [email protected]

PRIOR TO WORK COMMENCING ON THE SITE

52. Principal Certifying Authority

A sign is to be erected in accordance with Clause 98 A (2) of the Environmental Planning

and Assessment Regulations 2000.

53. Consultation with Service Authorities

Applicants are advised to consult with Telstra, NBN Co and Australia Post regarding the

installation of telephone conduits, broadband connections and letterboxes as required.

Unimpeded access must be available to the electricity supply authority, during and after

building, to the electricity meters and metering equipment.

The building plans must be submitted to the appropriate Sydney Water office to

determine whether the development will affect Sydney Water’s sewer and water mains,

stormwater drains and/or easements. If the development complies with Sydney Water’s

requirements, the building plans will be stamped indicating that no further requirements

are necessary.

54. Approved Temporary Closet

An approved temporary closet connected to the sewers of Sydney Water, or alternatively

an approved chemical closet is to be provided on the land, prior to building operations

being commenced.

55. Erosion and Sedimentation Controls – Minor Works

Erosion and sedimentation controls shall be in place prior to the commencement of site

works; and maintained throughout construction activities until the site is landscaped

and/or suitably revegetated. The controls shall be in accordance with the details

approved by Council and/or as directed by Council Officers. These requirements shall be

in accordance with Managing Urban Stormwater – Soils and Construction produced by

the NSW Department of Housing (Blue Book).

56. Stabilised Access Point

A stabilised all weather access point is to be provided prior to commencement of site

works, and maintained throughout construction activities until the site is stabilised. The

controls shall be in accordance with the requirements with the details approved by

Council and/or as directed by Council Officers. These requirements shall be in

accordance with Managing Urban Stormwater – Soils and Construction produced by the

NSW Department of Housing (Blue Book).

57. Site Water Management Plan

A Site Water Management Plan is to be submitted to Council for approval. The plan is

required to be site specific and be in accordance with "Managing Urban Stormwater -

Soils and Construction" (The Blue Book) produced by the NSW Department of Housing.

58. Erosion & Sediment Control Plan Kept on Site

A copy of the Erosion and Sediment Control Plan must be kept on site at all times during

construction and made available to Council officers on request.

59. Traffic Control Plan

A Traffic Control Plan is required to be prepared and submitted to Council for approval.

The person preparing the plan must have the relevant accreditation to do so. Where

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 24

amendments to the plan are required post approval, they must be submitted to Council

for further approval prior to being implemented.

A plan that includes full (detour) or partial (temporary traffic signals) width road closure

requires separate specific approval from Council. Sufficient time should be allowed for

this to occur.

60. Sediment and Erosion Control

The approved sediment and erosion control measures, including a stabilised all weather

access point, must be in place prior to works commencing and maintained during

construction and until the site is stabilised to ensure their effectiveness. For major

works, these measures must be maintained for a minimum period of six months

following the completion of all works.

61. Service Authority Consultation – Subdivision Works

Before subdivision works commence:

a) Documentary evidence must be submitted confirming that satisfactory arrangements

have been made for the relocation, undergrounding and/ or provision of electrical

services for the non-residue lots created by the subdivision.

b) Documentary evidence, including a notice of requirements from Sydney Water, must

be submitted confirming that satisfactory arrangements have been made for the

provision of water and sewerage facilities.

c) Consultation with the relevant telecommunications provider authorised under the

Telecommunications Act regarding the installation of telephone conduits is required.

The design and construction of these works must comply with current NBN

standards, where applicable.

62. Public Infrastructure Inventory Report

A public infrastructure inventory report must be prepared and submitted to Council

recording the condition of all public assets in the direct vicinity of the development site.

This includes, but is not limited to, the road fronting the site along with any access route

used by heavy vehicles. If uncertainty exists with respect to the necessary scope of this

report, it must be clarified with Council before works commence. The report must

include:

a) Planned construction access and delivery routes; and

b) Dated photographic evidence of the condition of all public assets.

63. Demolition Works and Asbestos Management

The demolition of any structure is to be carried out in accordance with the Occupational

Health and Safety Regulations 2001 Part 8 and AS 2601-2001. All vehicles transporting

demolition materials offsite are to have covered loads and are not to track any soil or

waste materials on the road. Should demolition works obstruct or inconvenience

pedestrian or vehicular traffic on adjoining public road or reserve, a separate application

is to be made to Council to enclose the public place with a hoard or fence. All demolition

works involving the removal and disposal of asbestos must only be undertaken by a

licenced asbestos removalist who is licenced to carry out the work. Asbestos removal

must be carried out in accordance with the WorkCover, Environment Protection Authority

and Office of Environment and Heritage requirements. Asbestos to be disposed of must

only be transported to waste facilities licenced to accept asbestos. No asbestos products

are to be reused on the site.

64. Discontinuation of Domestic Waste Service

Prior to the commencement of demolition works, and where the site ceases to be

occupied during works, the property owner or site manager must ensure to notify to

Council to collect any garbage and recycle bins from any dwelling that is to be

demolished. Trade workers are not permitted to use Council supplied bins for the

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 25

disposal of any waste. The service is to be discontinued by telephoning Council on (02)

9843 0310.

65. Landscaping/ Planting – Seed Collection

Prior to clearance of the vegetation in the development area, all collectable floristic

material shall be harvested for use in future landscaping on site. Seed and other genetic

material collected from the site is to be placed in the care of a Council recognised bush

regeneration specialist for use in bush rehabilitation projects in the local area.

Details prepared by the project ecologist (in writing) demonstrating compliance is to be

submitted to The Hills Shire Council.

66. Tree Removal and Fauna Protection

A pre-construction survey is to be undertaken by a qualified ecologist to confirm no bats

are roosting in buildings on the site. Any individuals found should be captured and

released. A bat management plan shall be prepared to the satisfaction of Council to

detail how this will be undertaken if the bats are present.

If hollow-bearing tree removal is unavoidably to occur during August to February in the

hollow-dependant fauna breeding seasons, the following is required. A fauna breeding

season action plan prepared by a suitably qualified and experienced ecologist prior to

tree removal being undertaken is required. The plan must be to the satisfaction of

Council and submitted and approved prior to tree removal works being undertaken.

Prior to the clearing of any trees, a pre-clearing fauna survey will be conducted by a

qualified ecologist to identify and minimise impacts to resident fauna. All trees containing

hollows are to be clearly marked as habitat trees.

During any tree removal a Project Ecologist is to be present to re-locate any displaced

fauna that may be disturbed during this activity.

Trees marked as habitat trees will be shaken by machinery prior to clearing to encourage

any fauna remaining to leave the hollows and move on.

Trees shall be lopped in such a way that the risk of injury or mortality to fauna is

minimised, such as top-down lopping, with lopped sections gently lowered to the ground,

or by lowering whole trees to the ground with the “grab” attachment of a machine.

An experienced wildlife handler/ecologist shall be in attendance during the felling of trees

on this site in order to rescue any injured wildlife. Potential hollows in lowered trees or

sections of trees shall be searched by an experienced ecologist and any fauna shall be

removed and, if uninjured, either released into roost boxes on the site or fed, warmed

and released in the evening, or, if injured, transferred to the care of a wildlife carer and

released on the site when re-habilitated (microbats bats should only be handled by

appropriately vaccinated persons).

Details prepared by the project ecologist (in writing) demonstrating compliance is to be

submitted to The Hills Shire Council.

DURING CONSTRUCTION

67. Hours of Work

Work on the project to be limited to the following hours: -

Monday to Saturday - 7.00am to 5.00pm;

No work to be carried out on Sunday or Public Holidays.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 26

The builder/contractor shall be responsible to instruct and control sub-contractors

regarding the hours of work. Council will exercise its powers under the Protection of the

Environment Operations Act, in the event that the building operations cause noise to

emanate from the property on Sunday or Public Holidays or otherwise than between the

hours detailed above.

68. Survey Report

Survey Certificate to be submitted to the Principal Certifying Authority at footings and/or

formwork stage. The certificate shall indicate the location of the building in relation to all

boundaries, and shall confirm the floor level prior to any work proceeding on the

building.

69. Compliance with BASIX Certificate

Under clause 97A of the Environmental Planning and Assessment Regulation 2000, it is a

condition of this Development Consent that all commitments listed in BASIX Certificate

No.’s 460254M_02 (Building 1), 460269M_02 (Building 2), 460021M_02 (Building 3),

460276M_02 (Building 4), 460339M_02 (Building 5), 460342M_02 (Building 6), and

460344M_02 (Building 7) be complied with. Any subsequent version of these BASIX

Certificates will supersede all previous versions of the certificate.

A Section 96 Application may be required should the subsequent version of these BASIX

Certificates necessitate design changes to the development. However, a Section 96

Application will be required for a BASIX Certificate with a new number.

70. Roof Water Drainage

Gutter and downpipes to be provided and connected to an approved drainage system

upon installation of the roof covering.

71. Compliance with Critical Stage Inspections and Other Inspections

Nominated by the Principal Certifying Authority

Section 109E(d) of the Act requires certain specific inspections (prescribed by Clause

162A of the Regulations) and known as “Critical Stage Inspections” to be carried out for

building work. Prior to permitting commencement of the work, your Principal Certifying

Authority is required to give notice of these inspections pursuant to Clause 103A of the

Regulations.

N.B. An Occupation Certificate cannot be issued and the building may not be able to be

used or occupied where any mandatory critical stage inspections or other inspections

required by the Principal Certifying Authority are not carried out.

Where Council is nominated as Principal Certifying Authority, notification of all

inspections required is provided with the Construction Certificate approval.

NOTE: You are advised that inspections may only be carried out by the PCA

unless by prior agreement of the PCA and subject to that person being an

accredited certifier.

72. Stockpiles

Stockpiles of topsoil, sand, aggregate or other material capable of being moved by water

shall be stored clear of any drainage line, easement, natural watercourse, footpath, kerb

or roadside.

73. Dust Control

The emission of dust must be controlled to minimise nuisance to the occupants of the

surrounding premises. In the absence of any alternative measures, the following

measures must be taken to control the emission of dust:

Dust screens must be erected around the perimeter of the site and be kept in good

repair for the duration of the construction work.

All dusty surfaces must be wet down and suppressed by means of a fine water

spray. Water used for dust suppression must not cause water pollution; and

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 27

All stockpiles of materials that are likely to generate dust must be kept damp of

covered.

74. Construction Noise

The emission of noise from the construction of the development shall comply with the

Interim Construction Noise Guideline published by the Department of Environment and

Climate Change (July 2009).

75. Filtration Motor

The swimming pool filter and pump shall be fully enclosed in a purpose built acoustic

enclosure to attenuate noise emitted by the swimming pool equipment. The acoustic

enclosure shall reduce the sound pressure level of the swimming pool filter and pump

equipment to a level not greater than 5dB (A) above the background noise level in

accordance with Protection of the Environmental Operations Act 1997.

76. Pool Discharge Water

Discharge and/or overflow pipe from the swimming pool and filtration unit to be

connected to the sewer where available.

All backwash water from the filtration unit is to be similarly disposed, or alternatively,

must be piped to an absorption trench.

The pool excavations not to conflict with the position of household drainage trenches or

lines, the position of which must be ascertained before pool excavation commences.

77. Swimming Pool Safety Fencing

All pools and safety barriers are to comply with the Swimming Pools Act 1992, the

Swimming Pools Regulation 2008 and Australian Standard 1926.1-2012. A fact sheet

titled Swimming Pool Fencing Requirements is available from www.thehills.nsw.gov.au.

78. Resuscitation Warning Notice

In accordance with the Swimming Pools Regulation 2008, a Warning Notice is to be

displayed in a prominent position, in the immediate vicinity of the swimming pool. The

notice is to contain a diagrammatic flow chart of resuscitation techniques, the words:

(i) "YOUNG CHILDREN SHOULD BE SUPERVISED WHEN USING THIS SWIMMING POOL",

and

(ii) "POOL GATES MUST BE KEPT CLOSED AT ALL TIMES", and

(iii) "KEEP ARTICLES, OBJECTS AND STRUCTURES AT LEAST 900 MILLIMETRES CLEAR

OF THE POOL FENCE AT ALL TIMES",

and all other details required by the Regulation.

79. Pool not to be Filled Until Occupation

The pool is not to be filled with water until the dwelling is occupied.

80. Temporary Fencing of Pools

This condition applies to unoccupied land.

On excavation and prior to installation of the pool shell or placement of the steel re-

enforcement, a fence is to be provided around the pool excavation, so as to isolate and

prevent access to it.

The fence provided is to be 1.8m high and to no less a standard than correctly joined

and secured, temporary fence panels or chainmesh. The fence is to remain in place until

the site (dwelling) has been approved for occupation.

81. Critical Stage Inspections – Subdivision Works

The subdivision works must be inspected by Council in accordance with the schedule

included in Council’s Works Specification Subdivisions/ Developments. A minimum of 24

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 28

hour’s notice is required for inspections. No works are to commence until the first

inspection has been carried out.

82. Standard of Works

All work must be carried out in accordance with Council’s Works Specification

Subdivisions/ Developments and must include any necessary works required to make the

construction effective. All works, including public utility relocation, must incur no cost to

Council.

PRIOR TO ISSUE OF AN OCCUPATION AND/OR SUBDIVISION CERTIFICATE

83. Safety Glazing for Pool Fencing

If glazing is chosen to be incorporated into the pool safety fencing system, a safety

glazing certificate is to be provided to Council, or the Principal Certifying Authority,

indicating all materials and installation are in accordance with AS 1288.

84. Compliance with NSW Office of Water Requirements

A letter from the NSW Office of Water must be submitted confirming that all works

associated with the Controlled Activity Authority have been completed to their

satisfaction.

85. Completion of Subdivision Works

A Subdivision Certificate cannot be issued prior to the completion of all subdivision works

covered by this consent.

86. Compliance with Sydney Water Requirements

A letter from Sydney Water must be submitted confirming that the works have been

completed to their satisfaction.

87. Works as Executed Plans

Works as executed (WAE) plans prepared by a suitably qualified engineer or registered

surveyor must be submitted to Council when the subdivision works are completed. The

WAE plans must be prepared in accordance with Council’s Design Guidelines

Subdivisions/ Developments.

The plans must be accompanied by pavement density results, pavement certification,

concrete core test results, site fill results, structural certification, CCTV recording,

signage details and a public asset creation summary, where relevant.

88. Performance/ Maintenance Security Bond

A performance/ maintenance bond of 5% of the total cost of the subdivision works is

required to be submitted to Council. The bond will be held for a minimum defect liability

period of one year and may be extended to allow for the completion of necessary

maintenance or in the case of outstanding/ bonded works. The minimum bond amount is

$5,000.00. The bond is refundable upon written application to Council and is subject to a

final inspection.

89. Confirmation of Pipe Locations

A letter from a registered surveyor must be provided with the WAE plans certifying that

all pipes and drainage structures are located within the proposed drainage easements.

90. Removal of Sediment and Erosion Control Measures

Where the sediment and erosion control measures are required to be retained post

construction to allow the site to establish, as directed by Council’s Construction Engineer,

a $5,000.00 bond must be submitted to ensure their eventual removal, along with any

collected debris.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 29

91. Section 73 Compliance Certificate

A Section 73 Compliance Certificate issued under the Sydney Water Act 1994 must be

obtained from Sydney Water confirming satisfactory arrangements have been made for

the provision of water and sewer services. Application must be made through an

authorised Water Servicing Coordinator. The certificate must refer to this development

consent and all of the lots created.

Sydney Water’s guidelines provide for assumed concurrence for the strata subdivision of

a development approved by an earlier consent covered by a compliance certificate.

92. Provision of Electrical Services

Submission of a notification of arrangement certificate confirming satisfactory

arrangements have been made for the provision of electrical services. This must include

the under-grounding of the existing electrical services fronting the site and removal of all

redundant poles and cables, unless otherwise approved by Council in writing. The

certificate must refer to this development consent and all of the lots created.

93. Provision of Telecommunication Services

Submission of a telecommunications infrastructure provisioning confirmation certificate

issued by the relevant telecommunications provider authorised under the

Telecommunications Act, or a design compliance certificate and an as-built compliance

certificate from the company engaged to design and construct the pit and pipe

infrastructure, confirming satisfactory arrangements have been made for the provision,

or relocation, of telecommunication services including telecommunications cables and

associated infrastructure. This must include the under-grounding of the existing

telecommunication services fronting the site and removal of all redundant poles and

cables, unless otherwise approved by Council in writing. The certificate must refer to this

development consent and all of the lots created.

94. Subdivision Certificate Application

When submitted, the Subdivision Certificate application must include:

a) Three copies of the final plan.

b) The original administration sheet and Section 88B instrument, along with one copy of

each.

c) All certificates and supplementary information required by this consent.

d) An AutoCAD copy of final plan (GDA 1994 MGA94 Zone56).

95. Stormwater CCTV Recording

All piped stormwater drainage systems and ancillary structures which will become public

assets must be inspected by CCTV. A copy of the actual recording must be submitted

electronically for checking.

96. Public Asset Creation Summary

A public asset creation summary must be submitted with the WAE plans. A template is

available on Council’s website.

97. Building Adjacent to Proposed Boundary

Where any part of an existing/ partially constructed building is located within 2m of a

proposed boundary the location of such must be determined by a registered surveyor

and shown on the final plan.

98. Building Services

A letter from a registered surveyor must be submitted certifying that all facilities

servicing the existing/ partially constructed buildings are located wholly within their

respective lot or are otherwise contained within a suitable easement.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 30

99. Final Plan and 88B Instrument

The final plan and Section 88B Instrument must provide for the following. Council’s

standard recitals must be used.

i. Dedication – New Road

The dedication of the proposed public roads must be included on the final plan in

accordance with the undertaking submitted relating to dedication.

ii. Easement – Temporary Public Access

A temporary public access easement must be created over the temporary cul-de-sac

turning head a the southern end of Lucinda Avenue using the “temporary public access

easement” terms included in the standard recitals.

iii. Easement – Private Stormwater Drainage

Inter-allotment drainage easements must be created to ensure each and every lot is

provided with a legal point of discharge. Easement widths must comply with Council’s

Design Guidelines Subdivisions/ Developments.

iv. Restriction/ Positive Covenant – Riparian Corridor

The site must be burdened with a restriction and a positive covenant using the “riparian

corridor requirements/ restricted development area” terms included in the standard

recitals.

100. Creation of Restrictions / Positive Covenants

Before an Occupation Certificate is issued the following restrictions/ positive covenants

must be registered on the title of the subject site via a request document, Section 88B

instrument associated with a plan or the like. Council’s standard recitals must be used.

i. Restriction – Bedroom Numbers

The subject site must be burdened with a restriction using the “bedroom numbers” terms

included in the standard recitals.

ii. Restriction/ Positive Covenant – Water Sensitive Urban Design

The subject site must be burdened with a restriction and a positive using the “basement

stormwater pump system” terms included in the standard recitals.

iii. Positive Covenant – Stormwater Pump

The subject site must be burdened with a positive covenant that refers to the WSUD

elements referred to earlier in this consent using the “water sensitive urban design

elements” terms included in the standard recitals.

101. Security Bond – Temporary Turning Head

A $20,000.00 security bond must be provided in order to guarantee the maintenance

and subsequent removal of the temporary cul-de-sac turning head. The bond is

refundable upon written application to Council and is subject to a final inspection. If

Council is required to maintain or remove the temporary cul-de-sac turning head these

costs will be deducted from the security bond. If these costs exceed the value of the

bond Council will issue an invoice for the recovery of the outstanding amount.

This bond is not required if the temporary cul-de-sac turning head is not required to be

constructed.

102. Completion of Engineering Works

An Occupation Certificate must not be issued prior to the completion of all engineering

works covered by this consent, in accordance with this consent.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 31

103. Public Infrastructure Inventory Report - Post Construction

Before an Occupation Certificate is issued, an updated public infrastructure inventory

report must be prepared and submitted to Council. The updated report must identify any

damage to public assets and the means of rectification for the approval of Council.

104. Public Road/ Road Widening Dedication

An Occupation Certificate must not be issued until the proposed public roads/ road

widening have been dedicated in accordance with the undertaking submitted relating to

dedication.

105. Pump System Certification

Certification that the stormwater pump system has been constructed in accordance with

the approved design and the conditions of this approval must be provided by a suitably

qualified hydraulic engineer.

106. Water Sensitive Urban Design Certification

An Occupation Certificate must not be issued prior to the completion of the WSUD

elements conditioned earlier in this consent. The following documentation must be

submitted in order to obtain an Occupation Certificate:

a) WAE drawings and any required engineering certifications;

b) Records of inspections;

c) An approved operations and maintenance plan; and

d) A certificate of structural adequacy from a suitably qualified structural engineer

verifying that any structural element of the WSUD system are structurally adequate

and capable of withstanding all loads likely to be imposed on them during their

lifetime.

Where Council is not the PCA a copy of the above documentation must be submitted to

Council.

107. Internal Pavement Construction

Prior to an Occupation Certificate being issued, a Certified Practicing Engineer (CPEng)

must submit a letter to Council confirming that the internal pavement has been

constructed in accordance to the approved plans, and is suitable for use by a loaded

heavy rigid waste collection vehicle.

108. Final Inspection of Waste Storage Areas

Prior to an Occupation Certificate being issued, a final inspection of the waste storage

areas and all other waste facilities must be arranged by the Principal Certifying Authority

and must be undertaken by Council. This is to ensure compliance with Council’s design

specifications. The time for the inspection must be arranged with Council at least 48

hours prior to the Principal Certifying Authority’s suggested appointment time.

109. Agreement for Onsite Waste Collection

Prior to an Occupation Certificate being issued, an Indemnity Agreement is to be

obtained from Council, completed, signed and two original copies returned to Council for

approval. This is to enable Council and its contractor to enter onto private property with

its collection vehicles to enable it to service bins.

110. Planting Local Provenance plants for Landscaping purposes

Planting of the required local provenance plants is to be completed in accordance with

the Council-approved Landscape Plan.

Invoices detailing the source of the local provenance plant species used for Landscaping

shall be submitted to Council.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 32

111. Final Plan and 88B Instrument

a) Restriction/ Positive Covenants – Restricted Development Area

A restriction must be placed on the title to ensure that any built form on the affected lot

is located outside of the restricted development area, which must be shown on the final

plan, in accordance with the requirements of Council.

b) Restriction/ Positive Covenants – Vegetation Management Plan

A positive covenant must be placed on the title of the property to ensure the ongoing

maintenance of the restricted development area (see above) in accordance with the

(approved) vegetation management plan, in accordance with the requirements of

Council.

THE USE OF THE SITE

112. Offensive Noise

The use of the premises, building services, equipment, machinery and ancillary fittings

shall not give rise to “offensive noise” as defined under the provisions of the Protection

of the Environment Operation Act 1997. Ventilation systems, car park exhausts and

pumps and filters associated with the swimming pool shall be treated to minimise noise

so that the noise is not more than 5 dB above the background noise level when

measured at the boundary of any adjoining premise or at the window or balcony of any

unit within the site.

113. Lighting

Any lighting on the site shall be designed so as not to cause a nuisance to other

residences in the area or to motorists on nearby roads and to ensure no adverse impact

on the amenity of the surrounding area by light overspill. All lighting shall comply with

the Australian Standard AS 4282:1997 The Control of Obtrusive Effects of Outdoor

Lighting.

114. Waste and Recycling Collection

Engagement of a caretaker responsible for the movement of all bins provided to the

development to and from the waste storage and collection points (as nominated by

Council) on the day allocated by Council. Bins presented to the street for servicing must

be removed from the street within 6 hours of servicing.

115. Landscaping

Landscaping is to be maintained in accordance with the Council-approved Landscape

Plan in perpetuity.

116. Vegetation Management Plan

The Riparian Corridor is to be maintained in accordance with the Council-approved

Vegetation Management Plan in perpetuity.

ATTACHMENTS

1. Locality Plan

2. Amended Site Plan

3. Office of Water General Terms of Approval

4. Previous Report

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 33

ATTACHMENT 1 – LOCALITY PLAN

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 34

ATTACHMENT 2 – AMENDED SITE PLAN

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 35

ATTACHEMNT 3 – OFFICE OF WATER GENERAL TERMS OF APPROVAL

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 36

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 37

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 38

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 39

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 40

ATTACHMENT 4 – PREVIOUS REPORT TO JRPP MEETING 7 AUGUST 2014

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 41

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 42

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 43

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 44

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 45

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 46

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 47

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 48

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 49

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 50

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 51

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 52

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 53

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 54

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 55

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 56

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 57

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 58

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 59

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 60

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 61

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 62

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 63

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 64

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 65

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 66

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 67

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 68

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 69

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 70

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 71

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 72

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 73

ITEM-2 JRPP REPORT - DA 1194/2014/JP

(Sydney West Region)

JRPP No 2014SYW052

DA Number DA 1194/2014/JP

Local Government Area THE HILLS SHIRE COUNCIL

Proposed Development AN INTEGRATED HOUSING DEVELOPMENT COMPRISING

153 DWELLINGS AND COMMUNITY TITLE SUBDIVISION

Street Address LOT 48 DP 280036 CADDIES BOULEVARD, ROUSE HILL

Applicant/Owner LEND LEASE GPT ROUSE HILL PTY LTD

Number of Submissions One

Regional Development

Criteria (Schedule 4A

of the Act)

Capital Investment value exceeding $20 Million

List of All Relevant

s79C(1)(a) Matters

LEP 2012

DCP Part D Section 6 – Rouse Hill Regional Centre

SEPP 32 – Urban Consolidation (Redevelopment of

Urban Land)

SREP 20 – Hawkesbury Nepean River

List all documents

submitted with this report

for the panel’s

consideration

Nil

Recommendation Approval subject to conditions

Report by Kristine McKenzie

Principal Executive Planner

EXECUTIVE SUMMARY

The proposal is for the erection of 153 detached dwellings and associated Community

Title subdivision and associated Community Title subdivision. The dwellings all have 3

bedrooms and comprise a variety of external designs and finishes.

The proposal includes a variation to the minimum 240m2 lot size for integrated housing

development under LEP 2012. The proposed lots the subject of the variation range from

181.1m2 to 239.2m2, being a maximum variation of 24.6%. Small lot housing was

always envisaged in the planning of the Rouse Hill Release Area and the concept pre-

dates the minimum lot size provisions of LEP 2012. Overall, Lend Lease have advised

that integrated housing will form approximately 19% of the housing yield within the

Regional Centre. The development site is close to the Town Centre, schools, community

and open space. Integrated housing delivered to date has been of a good quality and

readily accepted by the market.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 74

The proposal also includes variations to DCP Part D Section 6 – Rouse Hill Regional

Centre in regard to height, front articulation zone, corner articulation zone, non-

provision of a blade privacy wall, side setbacks and solar access. The proposed variations

are considered satisfactory as they will not result in an adverse impact to the

streetscape. The use of an integrated scheme also allows a known built form outcome for

adjoining dwellings.

The proposed development is similar in style to a number of existing developments

constructed within the Rouse Hill Regional Centre and the subject site is a discrete site

separated by public roads and open space from adjoining existing or future residential

development.

The proposal was advertised and notified to adjoining property owners. There was one

submission received to the proposal which raised concern regarding traffic and vehicle

safety at the intersection of Caddies Boulevard and Sanctuary Drive. The traffic volume

generated by the proposal is satisfactory and will not adversely impact on local roads, is

in keeping with the outcomes expected from the approved Masterplan and will not

adversely impact on intersections.

The Development Application is recommended for approval subject to conditions.

In the absence of the JRPP process, this matter would be determined by Council due to

the variation to LEP lot size standard exceeding 10%.

BACKGROUND MANDATORY REQUIREMENTS

Owner: Minister

administering the

EP and A Act

1. LEP 2012 – Permissible with

consent. Variation to lot size which

requires use of Clause 4.6.

Zoning: Part R3 Medium

Density

Residential, R4

High Density

Residential and B4

Mixed Use

2. DCP Part D Section 6 – Rouse Hill

Regional Centre - Variations

required, see report.

Area: 3.47 hectares 3. Section 79C (EP&A Act) –

Satisfactory.

Existing Development: Vacant land 4. Section 94 Contribution - N/A

however a Planning Agreement

applies to the site.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 75

SUBMISSIONS REASON FOR REFERRAL TO JRPP

1. Exhibition: Yes, 14 days. 1. Capital Investment Value in excess

of $20 million pursuant to SEPP

(Major Development) 2005.

2. Notice Adj Owners: Yes, 14 days.

3. Number Advised: 23

4. Submissions

Received:

One

HISTORY

10/01/2013 Development Application 1210/2011/HB approved for the

revised Central Precinct Plan at Council’s Delegated Authority

Meeting.

24/01/2013 Subdivision Development Application 250/2013/ZB approved

under Delegated Authority for the subdivision of Lot 8 and Lot 23

DP 270520 into a Community Title subdivision creating six

residential lots, 18 residue lots and eight community association

lots including a new road in three stages.

18/10/2013 Modification Application 250/2013/ZB/A approved under

Delegated Authority for amendments including lot numbering,

road pattern, lot dimensions and lot areas.

31/03/2014 Subject Development Application lodged.

12/05/2014 Letter sent to the applicant requesting additional information

regarding compliance with DCP Part D Section 6 – Rouse Hill

Regional Centre, submission of additional/revised plans,

additional information regarding secondary dwellings,

submission of landscape plans, submission of an acoustic report,

timing of park embellishment works, waste collection details and

engineering matters.

24/06/2014 and

17/07/2014

Additional information submitted by the applicant.

03/09/2014 Modification Application 250/2013/ZB/B approved under

Delegated Authority for amendments including lot numbering,

road pattern, new/amended laneways and amended staging.

08/09/2014 Email sent to the applicant requesting additional information

regarding balcony locations for the secondary dwellings and

setbacks.

12/09/2014 and

16/09/2014

Additional information submitted by the applicant.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 76

PROPOSAL

The Development Application is for an integrated housing development of 153 detached

dwellings and associated Community Title subdivision. The site is located within the

‘Central Residential Precinct’ of Rouse Hill Regional Centre.

The proposed dwellings are all two storey in design, with eight designs and five façade

treatments. The dwellings will have external finishes including brick and moroka painted

finishes with colorbond roofing.

In addition, five secondary dwellings are proposed above detached garages. The Granny

flat is a studio unit containing one larger room with kitchen at one end with an en-suite.

The granny flat has separate external stairs to provide access.

As outlined in the history, Subdivision Development Application 250/2013/ZB has been

approved which created parent development lots and included road and laneway

construction. These works include the ‘link’ of Civic Way to White Hart Drive i.e.: the

Central Residential Precinct to the Town Centre. This approval has not been acted upon.

ISSUES FOR CONSIDERATION

1. SEPP State and Regional Development 2011

Clause 20 of SEPP (State and Regional Development) 2011 and the Schedule 4A of the

Environmental Planning and Assessment Act, 1979 provides the following referral

requirements to a Joint Regional Planning Panel:-

Development that has a capital investment value of more than $20 million.

The proposed development has a capital investment value of $30,722,195 thereby

requiring referral to, and determination by, a Joint Regional Planning Panel.

2. Compliance with LEP 2012

The site is zoned part R3 Medium Density Residential, part R4 High Density Residential

and part B4 Mixed Use. The proposed works are located on the part of the site which is

zoned R3 Medium Density Residential and R4 High Density Residential. The proposed use

is for integrated housing which is a permissible use in the R3 Medium Density Residential

and R4 High Density Residential zones.

The proposal includes a variation to the minimum 240m2 lot size for integrated housing

development under LEP 2012. The proposed lots the subject of the variation range from

181.1m2 to 239.2m2, being a maximum variation of 24.6%.

LEP 2012 states as follows:

4.1B Exceptions to minimum lot sizes for certain residential development

(1) The objective of this clause is to encourage housing diversity without adversely

impacting on residential amenity.

(2) This clause applies to development on land in the following zones:

(a) Zone R3 Medium Density Residential

(b) Zone R4 High Density Residential

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 77

(3) Development consent may be granted to a single development application for

development to which this clause applies that is both of the following:

(a) the subdivision of land into 3 or more lots,

(b) the erection of an attached dwelling or a dwelling house on each lot

resulting from the subdivision, if the size of each lot is equal to or greater

than:

(i) for the erection of a dwelling house - 240 square metres or

(ii) for the erection of an attached dwelling - 240 square metres.

The proposal satisfies the definition in that the proposal is for subdivision and the

erection of dwellings however 115 of the 153 proposed lots do not exceed 240m2. The

proposed lots are:

LOT AREA (m2) COMPLIES LOT AREA (m2) COMPLIES

132 272 Yes 209 230.8 No

133 181.1 No 210 205.2 No

134 181.1 No 211 205.2 No

135 181.1 No 212 205.2 No

136 293.9 Yes 213 301.4 Yes

137 293.9 Yes 214 344.6 Yes

138 181.1 No 215 229.9 No

139 181.1 No 216 247.5 Yes

140 181.1 No 217 314.8 Yes

141 227.6 No 218 196.5 No

142 276.6 Yes 219 195.6 No

143 217.7 No 220 307 Yes

144 232.5 No 221 193.3 No

145 190.7 No 222 192.4 No

146 231.9 No 223 239.2 No

147 181.1 No 224 300.3 Yes

148 181.1 No 225 312.3 Yes

149 250.8 Yes 226 272.3 Yes

150 224.9 No 227 248.6 Yes

151 181.1 No 228 228 No

152 181.1 No 229 228 No

153 188.7 No 230 228 No

154 190.8 No 231 250.7 Yes

155 187.9 No 232 250.7 Yes

156 192.9 No 233 219.1 No

157 277.9 Yes 234 260.6 Yes

158 279.9 Yes 235 358.9 Yes

159 191.9 No 236 184.3 No

160 191.9 No 237 207.6 No

161 227.9 No 238 215 No

162 272.9 Yes 239 233.8 No

163 187.1 No 240 316.7 Yes

164 265.7 Yes 241 253.6 Yes

165 238 No 242 230.5 No

166 219.5 No 243 292.7 Yes

167 231 No 244 362.1 Yes

168 193.1 No 245 212.7 No

169 289.6 Yes 246 215.3 No

170 209 No 247 217.8 No

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 78

171 208.9 No 248 198.9 No

172 210.2 No 249 232.3 No

173 212.4 No 250 217.7 No

174 238.4 No 251 223.5 No

175 258.5 Yes 252 226.6 No

176 382.5 Yes 253 201.4 No

177 203.7 No 254 295.7 Yes

178 203.7 No 255 267.6 Yes

179 203.7 No 256 201.4 No

180 203.7 No 257 201.4 No

181 203.7 No 258 226.6 No

182 203.7 No 259 201.4 No

183 203.7 No 260 201.4 No

184 203.7 No 261 226.6 No

185 203.7 No 262 201.4 No

186 233 No 263 201.4 No

187 324.3 Yes 264 226.6 No

188 211.3 No 265 201.4 No

189 181.1 No 266 201.4 No

190 181.1 No 267 201.4 No

191 181.1 No 268 221.9 No

192 181.1 No 269 217.6 No

193 289.6 Yes 270 232.3 No

194 289.5 Yes 271 207.1 No

195 181.1 No 272 201.4 No

196 224.3 No 273 201.4 No

197 305.8 Yes 274 201.4 No

198 240.2 Yes 275 226.6 No

199 228 No 276 201.4 No

200 228 No 277 201.4 No

201 225.9 No 278 226.6 No

202 219 No 279 201.4 No

203 311.9 Yes 280 201.4 No

204 283.9 Yes 281 226.6 No

205 205.2 No 282 201.4 No

206 230.9 No 283 201.4 No

207 205.2 No 284 267.6 Yes

208 205.2 No

The applicant has submitted the following as justification:

Clause 4.6 of the Hills Shire LEP 2012 provides a process the make exceptions to

standards and comment is provided for each as follows:-

(3) Development consent must not be granted for development that contravenes a

development standard unless the consent authority has considered a written

request from the applicant that seeks to justify the contravention of the

development standard by demonstrating:

(a) that compliance with the development standard is unreasonable or unnecessary

in the circumstances of the case, and

(b) that there are sufficient environmental planning grounds to justify contravening

the development standard.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 79

Both the parent lot provision requiring 1,800m2 and the minimum lot size provision are

new controls that previously did not apply to this form of housing under the previous

planning controls. Indeed, most of the integrated housing and medium density

development so far delivered in the Rouse Hill Release Area has been approved on lots

less than 240m2.

The variation of the parent lot provision (Clause 4.1A) still enables lot sizes for the

development of a comprehensive housing solution in this part of the site as only laneway

and pedestrian connections break up the lots to result in parcels less than 1,800m2. The

DCP controls have been tailored to address the design of dwellings on lots less than

240m2 consistent with the street blocks already approved in the Central Precinct, which

in part facilitates the overall housing density range to be delivered from the Rouse Hill

Regional Centre.

All townhouses and integrated housing product delivered to date has been of superior

quality with high levels of amenity that has been well accepted in the market place. This

track record confirms that LLGPT are capable of delivering this product on lots less than

240m2 and hence this provision should be varied. The proposed development is

generally consistent with all controls which guide built form, provision of landscape,

private open space and control amenity impacts.

The proposed lot size is considered suitable to accommodate the proposed development.

(4) Development consent must not be granted for development that contravenes a

development standard unless:

(a) the consent authority is satisfied that:

(i) the applicant’s written request has adequately addressed the matters required to be

demonstrated by subclause (3), and

(ii) the proposed development will be in the public interest because it is consistent with

the objectives of the particular standard and the objectives for development within the

zone in which the development is proposed to be carried out, and

The proposed development is in the public interest as it is consistent with the objectives

and the planning framework for Rouse Hill which did not, up until the gazettal of the new

LEP, contain these minimum lots size provisions for what was previously integrated

housing. Council has consistently confirmed that the LEP process was not to remove

development rights which were built into the planning framework for the delivery of

Rouse Hill. Clause 4.6 of the LEP, which enables variation of the development standard,

will ensure Council can maintain this commitment.

(b) the concurrence of the Director-General has been obtained.

Practice Note PS08-003 issued by the Department of Planning and Infrastructure notifies

Councils of arrangements where the Director General’s concurrence can be assumed.

This applies to the standards for which exceptions are sought.

Comment:

The proposed lot areas have been reviewed. Whilst 115 lots do not comply with the LEP

2012 provision, the proposal will result in a satisfactory built form outcome. The

objective of Clause 4.1B is:

The objective of this clause is to encourage housing diversity without adversely

impacting on residential amenity.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 80

The proposed integrated housing development will encourage housing diversity as it

allows for a smaller lot size and built form. The dwellings proposed are modest in size

and design. The proposed dwellings will not adversely impact upon adjoining properties

in respect to residential amenity.

The proposed development is similar in style to a number of existing developments

constructed within the Regional Centre area. The proposal is in keeping with the existing

streetscape of the area and provides a modern dwelling design. Whilst the proposal does

not achieve the minimum site area required under LEP 2012, the proposal provides

adequate landscaped private open space areas, privacy between dwellings and a

functional internal design.

The built form reflects the design of dwellings within the immediate area and allows

reasonable solar access to courtyard areas. The proposal provides an opportunity for a

mix of dwelling types within close proximity to the established Town Centre. Schools,

community facilities and open space are also available within walking distance of the

site.

Based on the above comments it is considered that an appropriate built form outcome

will be achieved which increases housing diversity without adversely impacting upon

residential amenity.

Clause 4.6 (4) of LEP 2012 states:

Development consent must not be granted for development that contravenes a

development standard unless:

(a) the consent authority is satisfied that:

(i) the applicant’s written request has adequately addressed the matters required to

be demonstrated by subclause (3), and

Comment: The applicant has adequately addressed the matters required to be addressed

by subclause (3).

(ii) the proposed development will be in the public interest because it is consistent

with the objectives of the particular standard and the objectives for development

within the zone in which the development is proposed to be carried out, and

Comment: As detailed above, the proposal is an appropriate development outcome in

regard to public interest and is consistent with the objectives of the R3 Medium Density

Residential and R4 High Density Residential zones.

(b) the concurrence of the Director-General has been obtained.

Comment: Council has assumed concurrence under the provisions of Circular PS 08–003

issued by the Department of Planning and infrastructure.

On the basis of the above comments, the proposed variation to the lot size is considered

reasonable and will not result in an adverse impact on residential amenity to future

residents.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 81

2. Compliance with DCP 2011 Part D Section 6 – Rouse Hill Regional Centre

The proposal has been assessed against the provisions of DCP 2011 Part D Section 6 –

Rouse Hill Regional Centre as follows:

Criteria Required Provided Complies

Density 30-60 dwellings per

hectare.

32 dwellings per

hectare.

Yes

Building

Form

Building forms that

complement the area and

have consideration to

streetscape, impact and

landscape.

The proposal is

considered to be

satisfactory in regard to

building form.

Yes

Site

Frontage

For small lot housing, 7-9

metres or 6 metres where

rear loaded.

All other lots comply. Yes

Building

Height

Building heights to be

consistent with LEP 2012.

Floor to ceiling height for

the ground floor of 2.7m

and upper floor preferably

2.55m with a minimum of

2.4m.

Buildings within the 70m

curtilage of Mungerie House

will be one storey.

The dwellings are all

within the LEP height

limit. The ground floor

has a height of 2.75m

and the upper floor a

minimum 2.4m.

Variation to height for

buildings within

Mungerie House

curtilage.

No, however the

height limit

adjacent to

Mungerie House

is considered

satisfactory and

will not impact

on the heritage

curtilage.

Front

Building

Setback

Front setback 3m.

Articulation is permitted to

intrude into front setback to

1.5m for various

percentages dependent on

lot width.

Articulation to the front

building line is required and

is permitted up to 1.5

metres for:

Lot width less than 11

metres - max 40% of

length of dwelling

facade.

Lot width 11 metres or

greater - max 50% of

length of dwelling

facade.

Variation required to

articulation zone for lots

135, 145, 147, 152,

154, 159, 173, 175,

176, 205, 209, 210,

214, 220, 227, 232 and

239.

No, however the

proposed

streetscape

outcome is

satisfactory.

Corner Side

Setback

Corner setback 2m.

Articulation to the side

(corner) setback on a corner

lot permitted up to 1 metre

for max 40% of length of

dwelling facade.

Lot 166 has a 2m side

setback proposed

however the articulation

zone is 43%.

No, however the

design will not

adversely

impact on

streetscape.

Garage

Front

Setbacks

5.5 metres All garages fronting

public roads have a

5.5m setback.

Yes

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 82

Rear

Setback

Ground floor rear setback

4m.

Upper floor setbacks to rear

boundary:

Lot depth less than 30m -

5m.

Lot depth 30m or greater –

7m

Garage setback to rear lane

- 0.5m

Articulation in the rear

setback is permitted up to

1.5m and shall include a

blade wall.

The proposed rear

setback to Lot 234 is

3.7m however no blade

wall has been provided.

No, however the

rear setback and

impacts on

privacy are

considered

reasonable.

Side

Setbacks

Detached or zero lot line:

Lot width less than 11m –

1m

Lot width 11-13.5m – 1.2m

Lot width greater than

13.5m – 1.5m

Note: zero lot lines are

permitted.

Variation to side

setbacks for Lots 132,

136, 137, 143, 162,

193, 194, 196, 197,

214, 220, 224, 227 and

232.

No, however the

separation

between

buildings is

considered

adequate to

maintain

amenity.

Building

Appearance

and

Articulation

The provision of interest in

design, articulation, and an

attractive streetscape.

The proposed buildings

are considered to be

satisfactory in terms of

design and external

appearance.

Yes

Roof Design Roof designs are to create

interest and diversity in

design.

The proposed roof

designs are considered

to be satisfactory.

Yes

Driveways 500mm landscape strip

required along all

driveways, and crossovers

widths required to be 3m.

All dwellings provide a

500mm landscape strip.

Yes

Carparking Dwellings with 1-3

bedrooms are required to

provide 1 space.

All lots have either a

single or double garage.

Yes

Garage

Design

Garages are to be designed

to be consistent with the

dwelling design and external

materials.

The proposed garages

are satisfactory in

regard to their design.

Yes

Solar Access Dwellings to comply with

BASIX. Buildings are to be

designed to optimise solar

access requirements and to

minimise impact to

adjoining properties.

Typically a minimum of 3

hours solar access to a

living area of each dwelling

is required.

All dwellings provide

satisfactory BASIX

outcomes. All dwellings

have been designed to

achieve reasonable

solar access outcomes.

Yes

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 83

Landscaping A minimum 40% of each lot

shall be soft landscaping.

All lots provide in

excess of 40% soft

landscape area.

Yes

Private and

Common

Open Space

Minimum of 23% of the lot

area for lots up to 400m2,

primary area of 4m x 6m.

A portion of the private

open space areas can be

roofed or covered however

no roofing to encroach into

setback areas.

All lots provide in

excess of 23%, with

appropriate dimensions

and which are useable

areas.

Yes

Solar Access

to Private

Open Space

50% of required private

open space shall receive 3

hours of solar access

between 9am and 3pm on

June 21 (exception may be

considered if in specific

circumstances the

compliance would unduly

affect functionality or

liveability).

A variations is proposed

to the following lots:

133, 134, 135, 143,

144, 145, 146, 147,

148, 223, 231, 248,

269 and 271.

No, however the

solar access

provided to the

dwellings is

reasonable.

Fencing and

Courtyard

Walls

Fencing is to complement

the design of the building

and define private space.

Front fence height to be a

maximum 1.2m and be 25%

transparent. Side and rear

fencing is to be 1.8m high

and either masonry or

timber.

Corner lot fencing that is

1.8m high is to be no more

than 50% of the length of

the lot.

The proposed fencing is

satisfactory and will

complement the

dwelling designs.

Yes

Designing

for Privacy

Second storey windows

within or 4.5m of a side

boundary are to have

privacy measures, and 5m

of a rear boundary of a 25m

deep lot are to have

permanent privacy

measures applied.

A condition of consent

has been recommended

requiring the use of

privacy measures on

relevant windows. See

Condition 27.

Yes

a. Height within Heritage Curtilage

The DCP requires that dwellings within the 70 metre curtilage of Mungerie House are to

be single storey in design. The height limit is also required in the Masterplan and the

Central Precinct Plan. The applicant has proposed two storey dwellings in the 70 metre

curtilage. Attachment 6 shows the 70 metre curtilage around Mungerie House.

The applicant has submitted a Statement of Heritage Impact addressing the proposed

height which concludes as follows:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 84

This report concludes that the proposal for the inclusion of 2 storey town house dwellings

within the single storey limit of the Mungerie House Curtilage:

will not affect preservation of the heritage significance of the Homestead and its

setting,

will not affect any significant views to or from Mungerie House or its precinct,

will contribute to the establishment of an attractive streetscape in the New Rouse

Hill Regional Centre, complementing the setting of the Mungerie House Precinct.

Comment:

The proposal has been reviewed by Council’s Senior Strategic Planner who has concluded

as follows:

The proposed development will have a shared streetscape relationship with Mungerie

House, at the perimeter of its established curtilage. Mungerie House is separated

from the proposed development by a road, car parking bays, streets tree plantings,

the reconstituted landscape gardens of Mungerie House and the water-tank tower. It

is unlikely that these relationships will be affected by the proposal to include two

storey dwellings within the outer area of the perimeter of the curtilage;

The prominence of Mungerie House, including primary vistas to and from the house

will be retained. It is unlikely that any identified views to and from Mungerie House

would be unreasonably affected by the proposed development;

The proposed dwellings will be constructed of a range of materials that are

sympathetic to the character of the Mungerie House Precinct with articulated massing

to minimise adverse visual impacts on Mungerie House. The proposed colour and

materials schedule is considered to be appropriate and sympathetic to the heritage

item;

The proposed orientation of the dwellings towards Mungerie House provides a better

urban design outcome with respect to activation of the street frontage and visual

appearance when viewed from Mungerie House as compared to the single storey

streetscape outcome. The proposed dwellings will ultimately contribute to the

establishment of an attractive streetscape, complementing the setting of Mungerie

House; and

The proposed two storey dwellings are unlikely to reduce the prominence of Mungerie

House within its setting. The use of sympathetic materials with articulated building

massing and established landscaping and street trees are expected to minimise any

adverse visual impacts from the increased height of the dwellings.

On this basis no objection is raised to the proposed two storey design.

b. Front Articulation Zone

The DCP requires a front setback of 3 metres and allows articulation into the front

setback to either 40% or 50% of the frontage dependent on lot width. The proposal

includes variations to the extent of the articulation zone on the following lots:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 85

Proposed

Lot

Articulation

Zone

Required

Proposed

Articulation

Zone

Proposed

Lot

Articulation

Zone

Required

Proposed

Articulation

Zone

135 40% 48.2% 205 40% 58.5%

145 50% 57.6% 209 40% 62.7%

147 40% 48.2% 210 40% 58.5%

152 40% 57.6% 214 50% 56%

154 40% 48.2% 220 50% 51.6%

159 40% 58.5% 227 50% 57.6%

173 40% 58.4% 232 50% 57.6%

175 40% 62.4% 239 40% 58.5%

176 50% 58.7%

The applicant has addressed the variation as follows:

The DCP requires an assessment of the articulation against the length of the dwelling

façade. It is disagreed that the DCP allows assessment at different levels as this would

result in very undesirable streetscape, limiting variation and interest, particularly on an

upper level where the setting back upper floors would lead to tokenistic gestures rather

than features that add amenity for residents and improve streetscape.

The principles for setting controls for setbacks are primarily to allow solar access to open

space areas, minimise impacts on adjacent allotments, contribute to reducing bulk to the

streetscape, reduce the impact of garages, and allow for landscape spaces within each

allotment to address the streetscape.

Articulations in the front setback and façade are required to allow larger gardens, private

front courtyard solutions, and visual interest in the front of the home. The current DCP

controls preserve the ability to ensure the objectives and principles for the front setback

are upheld when assessing individual dwelling designs in the absence of designs

for adjacent dwellings. As such the controls ensure the outcomes can be achieved

despite in the absence of the benefit of having dwelling design for all adjacent dwellings.

The current application contains details for the façade, articulation, landscaping and

privacy measures for all adjacent dwellings whereby the impacts on adjacent dwellings

resulting from to the additional articulation can be reviewed and assessed. The features

that extend into the articulation zone, not only contribute to the streetscape, but also

add to the livability of the dwelling for future residents. They do not typically extend into

the articulation zone to the maximum allowed by the DCP, and are designed to be

usable, rather than an architectural gesture which has no function or benefit to the

resident.

Despite some dwellings containing front articulation areas exceeding the ratio compared

to the length of dwelling nominated in the DCP controls, there are no adverse impacts on

the adjacent dwellings, the streetscape or residential amenity.

Comment:

The principles within the DCP relate to defining the built area, provision of solar access

to rear yards, minimising impact to adjoining property, streetscape appearance and

minimising bulk of garages, and allowing landscape works to be undertaken.

The proposed variation has been assessed having regard to the objectives of the DCP

and is considered to be satisfactory given that the proposal will not create an adverse

impact upon streetscape and allows for appropriate articulation for the scale and design

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 86

of the dwellings. Adequate area remains for landscape planting on the site, the provision

of a useable private open space and solar access.

As the development is proposed as an ‘integrated’ form of development the adjoining

development is a known outcome. As such, future residents will have appropriate levels

of amenity.

On this basis the proposed setback is considered satisfactory.

c. Articulation to a Corner Lot

The DCP limits the articulation zone to 40% for a corner lot. For Lot 166 the proposed

articulation zone is 43% which relates to the provision of a pergola over an entry to the

courtyard.

The applicant has addressed the variation as follows:

The proposed articulation along the secondary frontage extends for 43% of the dwelling

façade exceeding the DCP by 3% or 0.342m however this extended articulation zone

increases solar access into the dwelling without adverse impacts to solar access on

adjacent dwellings, assists in reducing the bulk of the frontage while providing for a

continuous landscape space along the entire frontage.

Comment:

The principles within the DCP relate to defining the built area, provision of solar access

to rear yards, minimising impact to adjoining property, streetscape appearance and

minimising bulk of garages, and allowing landscape works to be undertaken.

The proposed variation has been assessed having regard to the objectives of the DCP

and is considered to be satisfactory given that the proposal will not create an adverse

impact upon streetscape and allows for appropriate articulation for the scale and design

of the dwellings. The provision of the pergola allows for additional shading over the entry

to the courtyard and is integrated into the design of the dwelling.

On this basis the proposed variation to the articulation zone is considered satisfactory.

d. Rear Setback and Non-Provision of a Blade Wall

The DCP requires a 5m rear setback however an articulation zone can be provided to the

rear building line up to 1.5m. The DCP states that rear articulation shall include a blade

wall for the purpose of increasing privacy. The proposed rear setback to Lot 234 is 3.7m

however no blade wall has been provided.

The applicant has submitted the following justification:

The DCP refers to building articulation can be generated through such features, at no

point does the DCP mandate that articulation zones must include these features or that

articulation zones are expressly prohibited from including such areas as bedrooms. The

example of the rear articulation zone in Council’s report of 23 April 2013 shows

bedrooms within the articulation zone.

The only aspect of the proposed design not complying with this portion of the DCP is the

lack of a blade wall incorporated into the building design to increase privacy between

internal rooms of dwellings sharing a common rear boundary.

In this regard:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 87

The corner of the dwelling provides privacy from Lot 236,

The blade wall on lot 237 (bed 3) provides privacy to Bed 2 in lot 234.

The distance between bedrooms 2 of lots 234 & 237 is greater than the DCP

control for minimum building separation (8m) eliminating the requirement for the

blade wall as the separation exceeds the combined setback requirement without

utilising the articulation zone.

Comment:

The principles within the DCP relate to defining the built area, provision of solar access

to rear yards, minimising impact to adjoining property, streetscape appearance and

minimising bulk of garages, and allowing landscape works to be undertaken.

The proposed dwelling is provided with reasonable access to private open space, solar

access and landscape works. The rear setback is considered satisfactory given that the

development provides a known built form outcome. The dwelling sits at an angle on an

irregularly shaped lot and the non-provision of the blade wall is not considered to reduce

privacy between the subject site and the adjoining rear dwelling.

As such no objection is raised to the proposed variation.

e. Side Setbacks

The DCP requires a varying side setback dependent on the lot width as follows:

Lot width less than 11m 1m side setback

Lot width 11-13.5m 1.2m side setback

Lot width greater than 13.5m 1.5m side setback

The applicant has addressed the variation as follows:

Setbacks address impacts of amenity, privacy, solar access, streetscape and setting.

Because the proposed setback is a minor reduction from the existing standard and

exceeds the requirements under the Codes SEPP and the BCA, it is considered unlikely

that the proposed side setback will create any adverse impact on residential amenity. It

is recommended that the minimum proposed 1m side setback be supported on the basis

that it is unlikely to create adversely impact on residential amenity exceeds the

requirements of State Environmental Planning Policy (Exempt and Complying

Development Codes) 2008 and the Building Code of Australia.

Comment:

The principles within the DCP relate to defining the built area, provision of solar access

to rear yards, minimising impact to adjoining property, streetscape appearance and

minimising bulk of garages, and allowing landscape works to be undertaken.

The proposed variation has been assessed having regard to the objectives of the DCP

and is considered to be satisfactory given that the dwellings have been designed as an

integrated development and as such the adjoining dwelling design is known and impacts

can be considered. The proposed design does not unreasonably impact upon privacy or

overshadowing and adequate area is available for landscape works to be undertaken. the

proposed side setbacks will not create an adverse impact upon streetscape.

On this basis the proposed side setback is considered satisfactory.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 88

f. Solar Access

The DCP requires that 50% of required private open space shall receive 3 hours of solar

access between 9am and 3pm on June 21 (exception may be considered if in specific

circumstances the compliance would unduly affect functionality or liveability). Variations

are proposed to the following lots: 133, 134, 135, 143, 144, 145, 146, 147, 148, 223,

231, 248, 269 and 271.

The applicant has submitted the following as justification:

The shadow diagrams included in the architectural plans shows all the majority of lots

comply with the exception of those street blocks with an east west orientation.

The DCP for Rouse Hill Regional Centre states that “50% of required private open space

shall receive 3 hours of solar access between 9am and 3pm on June 21 (exception may

be considered if in specific circumstances the compliance would unduly affect

functionality or liveability).”

Because of the orientation of these east west blocks there is a higher potential for

dwellings to overshadow each other. One can see from the size of the dwelling that it

also has one of the smallest footprints and hence further reducing the building to

facilitate more solar access would unduly affect the functionality and live-ability of the

dwelling.

The areas of private open space are located directly accessible to living areas for private

recreation and will receive adequate solar access. Solar access is achieved in summer

and mid Spring and Autumn. Given the orientation of the site, the proposed solar access

is considered satisfactory.

Comment:

The principles of the DCP relate to the provision of a usable private open area which

caters to the needs of residents in respect to leisure, recreation and outdoor

entertaining. An adequate area of private open space has been provided which exceeds

the DCP requirements. The private open space area is directly accessible from living

areas of the dwelling and will cater for private recreation needs.

Given the orientation of the site, the proposed solar access is considered satisfactory.

3. Secondary Dwellings

Five of the proposed dwellings will also include a granny flat above the detached garage.

The granny flat is a studio unit containing one larger room with kitchen at one end with

an en-suite and balcony. The granny flats have separate external stairs to provide

access.

The proposed secondary dwelling has been assessed against the relevant provisions of

SEPP (Affordable Rental Housing) 2009.

The SEPP defines a Secondary Dwelling as follows;

“development for the purposes of a secondary dwelling includes the

following:

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 89

(a) the erection of, or alterations or additions to, a secondary dwelling,

(b) alterations or additions to a principal dwelling for the purposes of a

secondary dwelling.

Note.

The standard instrument defines secondary dwelling as follows:

secondary dwelling means a self-contained dwelling that:

(a) is established in conjunction with another dwelling (the principal dwelling),

and

(b) is on the same lot of land (not being an individual lot in a strata plan or

community title scheme) as the principal dwelling, and

(c) is located within, or is attached to, or is separate from, the principal dwelling.”

The proposal includes construction of a detached secondary dwelling above the garage to

the rear/side of the proposed principal dwelling.

The SEPP states that a consent authority must not consent to development unless:

SEPP Requirement Proposal Compliance

Total floor area of the principal

dwelling and the secondary dwelling

to be no more than that permitted

under another EPI for a dwelling

house.

LEP 2012 does not set a limit on

floor space on the subject site

therefore the SEPP development

standard is not applicable to the

site.

Yes

Floor area of secondary dwelling

must be no more than 60m²

29m² (all secondary dwellings). Yes

The SEPP also states that the consent authority must not refuse a development on either

of the following grounds:

(a) Site Area if:

(i) the secondary dwelling is located within, or is attached to, the principal

dwelling, or

(ii) the site area is at least 450 square metres,

(b) Parking

if no additional parking is to be provided on the site.

The secondary dwellings are detached from the proposed principal dwelling as they are

located above the detached garage. The following lot sizes apply:

Lot 176 – 382.5m2

Lot 204 – 283.9m2

Lot 216 – 247.5m2

Lot 255 – 267.6m2

Lot 284 – 267.6m2

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 90

The applicant has addressed these matters and has stated as follows:

The Masterplan for Rouse Hill has always identified the need to provide a broad range of

housing type including studio apartments and other commitments to increase the range

of smaller housing types to improve affordability. The concept of secondary dwellings is

also specifically addressed in the newly adopted DCP (see Clause 3.1.7 for setbacks for

secondary dwellings above garages).

Comment:

The aims of the SEPP relate to ensuring that a consistent planning regime is provided to

facilitate the effective delivery of affordable rental housing.

In regard to the design the following applies:

• The proposed secondary dwellings are being established with the principal

dwelling on the lot;

• The proposed secondary dwellings are located above the garage for the principal

dwelling. The principal and secondary dwelling are designed to complement each

other;

In terms of impact to adjoining properties, the secondary dwellings are located on lots

which have a rear access laneway or right-of-carriageway. As such there is appropriate

separation between building forms to allow privacy to be maintained to adjoining lots.

A balcony has been provided the secondary dwellings. The balconies are small in area,

and face the lane/right-of-carriageway and are not considered highly useable. In this

respect the use of the balconies is unlikely to result in privacy impacts to adjoining

properties.

On the basis of the design and layout of the secondary dwellings and given the

integrated format of the design ie: all dwellings will be constructed as one development,

it is considered that the proposed layout of the secondary dwellings is satisfactory and

can be supported.

Based on the above the proposed secondary dwellings are permissible and are

satisfactory.

4. Consistency with Approved Precinct Plan and Design Guidelines

a. Approved Precinct Plan

Development Consent was granted on 10 January 2013 for the Central Residential

Precinct Plan (Development Application 1210/2011/HB) at Council’s Delegated Authority

Meeting.

The Precinct Plan contained a number of conditions of consent. The proposal is generally

consistent with the conditions with the exception of Condition 5 which states as follows:

5. Mungerie House Curtilage

All buildings/dwellings within the 70 metre curtilage of Mungerie House as shown

in the Design Guidelines are limited to single storey in height.

The height of the development is addressed in Section 3 above.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 91

The Precinct Plan also included a number of plans which were approved as part of the

Development Consent as follows:-

(i) Drawing 01 - Location Plan – Satisfactory;

(ii) Drawing 02 – Land Use Context – the subject site is identified as being for

residential use. The current proposal is for integrated housing and is satisfactory.

(iii) Drawing 03 – Structure Plan – the road locations and development lots are

consistent.

(iv) Drawing 04 – Pedestrian and Cycle Network – the required pedestrian and cycle

links which affect the site have been provided within the underlying subdivision

application.

(vi) Drawing 05 – Open Space – the site includes a centralised neighbourhood park

and pocket parks.

b. Design Guideline Requirements

In addition to the DCP, the approved Precinct Plan includes Design Guidelines which

provide additional criteria for assessment of any proposal in the Precinct. The Design

Guidelines contain criteria relevant to this application relating to building character and

external materials and colours. The proposed design and external finishes are reflective

of the desired modern character of the area and is considered satisfactory.

5. Submissions

The proposal was advertised and notified to adjoining property owners for 14 days.

There was one submission received which raised the following concerns (summarised):

This development should only be approved subject to upgrade of the intersection

between Caddies Boulevard and Sanctuary Drive to improve safety.

This intersection is already unsafe due to: speed of traffic travelling along

Sanctuary Drive, foliage in the central median strip of Sanctuary Drive, the bend

in the road obscures visibility when turning from Caddies Boulevard into

Sanctuary Drive, cars use this intersection as a u-turn, and fog settles in this

location.

The proposed development and the development of sports fields and housing

estate to the south of Sanctuary Drive will further increase the risk of accidents at

this intersection due to increased traffic volumes.

Council are requested to urgently review and improve the safety of this

intersection, ideally by installing a roundabout which will make the intersection

much safer for traffic turning into Sanctuary Drive from Caddies Boulevard.

Comment:

The proposed development has been reviewed by Council’s Principal Traffic and

Transport Co-ordinator who advised:

The intersection of Caddies Boulevard and Sanctuary Drive is currently operating at a

satisfactory level of service and there is no established accident history. Caddies

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 92

Boulevard is a Collector Road with a capacity of up to 6000 vehicles per day and

Sanctuary Drive is a Sub-Arterial Road with a capacity of up to 15,000 vehicles per day.

The roads are not currently operating at these maximum capacities due to future

development potential in the Rouse Hill Regional Centre, Kellyville, Rouse Hill and North

Kellyville. The sight distance has been reviewed and is satisfactory for all turning

movements. There is no requirement for works to be undertaken at the intersection to

improve vehicle access. The concerns raised about overgrown foliage have been

reviewed and there is no trimming works required.

In the future, the intersection of Caddies Boulevard and Sanctuary Drive will be

signalised. This is likely to be paid for jointly by Lend Lease GPT and Council. This will

occur when the warrant for traffic signals and pedestrian access has been met and is

likely to be required when the playing fields and residential development occurs to the

south (around 2016). These works, in conjunction with the on-going development of the

Regional Centre, will form the basis for the future signalisation.

No objection raised to the proposal and no conditions.

SUBDIVISION ENGINEERING COMMENTS

No objection raised to the proposal. Relevant conditions are included in the

recommendation.

TRAFFIC MANAGEMENT COMMENTS

No objection raised to the proposal and no conditions.

TREE MANAGEMENT COMMENTS

No objection raised to the proposal. Relevant conditions are included in the

recommendation.

HEALTH & ENVIRONMENTAL PROTECTION COMMENTS

No objection raised to the proposal. Relevant conditions are included in the

recommendation.

WASTE MANAGEMENT COMMENTS

No objection raised to the proposal. Relevant conditions are included in the

recommendation.

HERITAGE COMMENTS

No objection raised to the proposal. Relevant conditions are included in the

recommendation.

CONCLUSION

The proposal has been assessed against the provisions of Section 79C of the

Environmental Planning and Assessment Act, 1979, Local Environmental Plan 2012 and

Development Control Plan Part D Section 6 – Rouse Hill Regional Centre. The proposed

variation to lot area under Local Environmental Plan 2012 and to height, front

articulation zone, corner articulation zone, non-provision of a blade privacy wall, side

setbacks and solar access under the DCP have been assessed and will not adversely

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 93

impact upon amenity to future residents. The submission received to the proposal has

been assessed and does not warrant refusal of the application.

Accordingly the application is recommended for approval subject to conditions.

IMPACTS:

Financial

This matter has no direct financial impact upon Council's adopted budget or forward

estimates.

The Hills Future - Community Strategic Plan

The proposal is considered satisfactory in regard to The Hills Future Community Strategic

plan and will provide housing diversity within the Shire through the provision of smaller

lots with a known built form outcome.

RECOMMENDATION

The Development Application be approved subject to the following conditions.

GENERAL MATTERS

1. Development in Accordance with Submitted Plans

The development being carried out in accordance with the following approved plans and

details, stamped and returned with this consent except where amended by other

conditions of consent.

REFERENCED PLANS AND DOCUMENTS

DRAWING NO. DESCRIPTION DATE

A20321 Sheet 1 Part Product Mix 19.5.14 Rev. D

A20321 Sheet 2 Part Product Mix 19.5.14 Rev. D

A20321 Sheet 2 Overall Site Plan 19.5.14 Rev. E

A20321 Sheet 3 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 4 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 5 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 6 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 7 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 8 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 9 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 10 Part Ground Site Plan 19.5.14 Rev. E

A20321 Sheet 11 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 12 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 13 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 14 Part First Site Plan 19.5.14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 94

A20321 Sheet 15 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 16 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 17 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 18 Part First Site Plan 19.5.14 Rev. E

A20321 Sheet 19 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 20 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 21 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 22 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 23 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 24 Streetscape Elevations 19.5.14 Rev. E

A20321 Sheet 25 Private Open Space 19.5.14 Rev. E

A20321 Sheet 26 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 27 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 28 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 29 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 30 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 31 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 32 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 33 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 34 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 35 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 36 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 37 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 38 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 39 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 40 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 41 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 42 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 43 Shadow Analysis Plans 19.5.14 Rev. E

A20321 Sheet 45 BASIX & Colour Pallet 19.5.14 Rev. E

A20321 Sheet 3 Type A/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 4 Type A/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 5 Type A/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 6 Type A/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 7 Type A/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 8 Type A/Façade C Elevations 19.5.14 Rev. D

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 95

A20321 Sheet 9 Type A/Façade D Floor Plans 19.5.14 Rev. D

A20321 Sheet 10 Type A/Façade D Elevations 19.5.14 Rev. D

A20321 Sheet 11 Type A/Façade E Floor Plans 19.5.14 Rev. D

A20321 Sheet 12 Type A/Façade E Elevations 19.5.14 Rev. D

A20321 Sheet 13 Type B/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 14 Type B/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 15 Type B/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 16 Type B/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 17 Type B/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 18 Type B/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 19 Type C/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 20 Type C/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 21 Type C/Façade A Studio Elevations 19.5.14 Rev. D

A20321 Sheet 22 Type C/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 23 Type C/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 24 Type C/Façade B Studio Elevations 19.5.14 Rev. D

A20321 Sheet 25 Type C/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 26 Type C/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 27 Type C/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 28 Type E/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 29 Type E/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 30 Type E/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 31 Type E/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 32 Type F/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 33 Type F/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 34 Type F/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 35 Type F/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 36 Type G/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 37 Type G/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 38 Type G/Façade A Garage Elevations 19.5.14 Rev. D

A20321 Sheet 39 Type G/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 40 Type G/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 41 Type G/Façade B Garage Elevations 19.5.14 Rev. D

A20321 Sheet 42 Type G/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 43 Type G/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 44 Type G/Façade C Elevations 19.5.14 Rev. D

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 96

A20321 Sheet 45 Type H/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 46 Type H/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 47 Type H/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 48 Type H/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 49 Type H/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 50 Type H/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 51 Type H/Façade D Floor Plans 19.5.14 Rev. D

A20321 Sheet 52 Type H/Façade D Elevations 19.5.14 Rev. D

A20321 Sheet 53 Type J/Façade A Ground Floor Plan 19.5.14 Rev. D

A20321 Sheet 54 Type J/Façade A First Floor Plan 19.5.14 Rev. D

A20321 Sheet 55 Type J/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 56 Type J/Façade B Ground Floor 19.5.14 Rev. D

A20321 Sheet 57 Type J/Façade B First Floor 19.5.14 Rev. D

A20321 Sheet 58 Type J/Façade B Elevations 19.5.14 Rev. D

A20321 Sheet 59 Type J/Façade C Ground Floor 19.5.14 Rev. D

A20321 Sheet 60 Type J/Façade C First Floor 19.5.14 Rev. D

A20321 Sheet 61 Type J/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 62 Type C/Façade A Floor Plans 19.5.14 Rev. D

A20321 Sheet 63 Type C1/Façade A Elevations 19.5.14 Rev. D

A20321 Sheet 64 Type C1/Façade A Studio Elevations 19.5.14 Rev. D

A20321 Sheet 65 Type G/Façade B Floor Plans 19.5.14 Rev. D

A20321 Sheet 66 Type C1/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 67 Type C1/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 68 Type J/Façade C First Floor 19.5.14 Rev. D

A20321 Sheet 69 Type G1/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 70 Type G1/Façade B Garage Elevations 19.5.14 Rev. D

A20321 Sheet 71 Type G/Façade C Floor Plans 19.5.14 Rev. D

A20321 Sheet 72 Type G1/Façade C Elevations 19.5.14 Rev. D

A20321 Sheet 72 Type G1/Façade C Garage Elevations 19.5.14 Rev. D

Sheet F-01 Fencing Key Plan 20-06-14 Rev. D

Sheet F-02 Fencing Key Plan 20-06-14 Rev. D

Sheet F-03 Fencing Key Plan 20-06-14 Rev. D

Sheet F-04 Fencing Key Plan 20-06-14 Rev. D

Sheet F-05 Fencing Key Plan 20-06-14 Rev. D

L-01 Landscape Plan – Lot 132 Galara Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 132 Galara Street 07-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 97

L-03 Fencing Details 07-07-14 Rev. E

L-01 Landscape Plan – Lot 133 Galara Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 133 Galara Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 134 Galara Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 134 Galara Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 135 Galara Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 135 Galara Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 136 Galara Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 136 Galara Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 137 Jimbuck Lane 07-07-14 Rev. E

L-02 Landscape Plan – Lot 137 Jimbuck Lane 07-07-14 Rev. E

L-01 Landscape Plan – Lot 138 Romney

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 138 Romney

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 139 Romney

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 139 Romney

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 140 Romney

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 140 Romney

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 141 Romney

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 141 Romney

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 142 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 142 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 143 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 143 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 144 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 144 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 145 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 145 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 146 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 146 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 147 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 147 Galara Street 08-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 98

L-01 Landscape Plan – Lot 148 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 148 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 149 Galara Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 149 Galara Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 150 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 150 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 151 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 151 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 152 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 152 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 153 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 153 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 154 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 154 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 155 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 155 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 156 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 156 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 157 Jimbuck

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 157 Jimbuck

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 158 Jimbuck

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 158 Jimbuck

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 159 Jimbuck

Street

07-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 99

L-02 Landscape Plan – Lot 159 Jimbuck

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 160 Jimbuck

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 160 Jimbuck

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 161 Jimbuck

Street

07-07-14 Rev. E

L-02 Landscape Plan – Lot 1618 Jimbuck

Street

07-07-14 Rev. E

L-01 Landscape Plan – Lot 162 Jimbuck

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 162 Jimbuck

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 163 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 163 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 164 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 164 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 165 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 165 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 166 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 166 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 167 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 167 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 168 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 168 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 169 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 169 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 170 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 170 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 171 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 171 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 172 Caddies

Boulevard

07-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 100

L-02 Landscape Plan – Lot 172 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 173 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 173 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 174 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 174 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 175 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 175 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 176 Caddies

Boulevard

07-07-14 Rev. E

L-02 Landscape Plan – Lot 176 Caddies

Boulevard

07-07-14 Rev. E

L-01 Landscape Plan – Lot 177 Saxon Lane 07-07-14 Rev. E

L-02 Landscape Plan – Lot 177 Saxon Lane 07-07-14 Rev. E

L-01 Landscape Plan – Lot 178 Saxon Lane 07-07-14 Rev. E

L-02 Landscape Plan – Lot 178 Saxon Lane 07-07-14 Rev. E

L-01 Landscape Plan – Lot 179 Saxon Lane 07-07-14 Rev. E

L-02 Landscape Plan – Lot 179 Saxon Lane 07-07-14 Rev. E

L-01 Landscape Plan – Lot 180 Saxon Lane 07-07-14 Rev. E

L-02 Landscape Plan – Lot 180 Saxon Lane 07-07-14 Rev. E

L-01 Landscape Plan – Lot 181 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 181 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 182 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 182 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 183 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 183 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 184 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 184 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 185 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 185 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 186 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 186 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 187 Saxon Lane 08-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 101

L-02 Landscape Plan – Lot 187 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 188 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 188 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 189 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 189 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 190 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 190 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 191 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 191 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 192 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 192 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 193 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 193 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 194 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 194 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 195 Romney

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 195 Romney

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 196 Saxon Lane 08-07-14 Rev. E

L-02 Landscape Plan – Lot 196 Saxon Lane 08-07-14 Rev. E

L-01 Landscape Plan – Lot 197 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 197 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 198 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 198 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 199 Grazier Road 09-07-14 Rev. E

L-02 Landscape Plan – Lot 199 Grazier Road 09-07-14 Rev. E

L-01 Landscape Plan – Lot 200 Grazier Road 09-07-14 Rev. E

L-02 Landscape Plan – Lot 200 Grazier Road 09-07-14 Rev. E

L-01 Landscape Plan – Lot 201 Grazier Road 09-07-14 Rev. E

L-02 Landscape Plan – Lot 201 Grazier Road 09-07-14 Rev. E

L-01 Landscape Plan – Lot 202 Grazier Road 09-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 102

L-02 Landscape Plan – Lot 202 Grazier Road 09-07-14 Rev. E

L-01 Landscape Plan – Lot 203 Grazier Road 09-07-14 Rev. E

L-02 Landscape Plan – Lot 203 Grazier Road 09-07-14 Rev. E

L-01 Landscape Plan – Lot 204 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 204 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 205 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 205 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 206 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 206 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 207 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 207 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 208 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 208 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 209 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 209 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 210 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 210 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 211 Caddies

Boulevard

20-06-14 Rev. D

L-02 Landscape Plan – Lot 211 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 212 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 212 Caddies

Boulevard

09-07-14 Rev. E

L-01 Landscape Plan – Lot 213 Caddies

Boulevard

09-07-14 Rev. E

L-02 Landscape Plan – Lot 213 Caddies

Boulevard

09-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 103

L-01 Landscape Plan – Lot 214 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 214 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 215 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 215 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 216 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 216 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 217 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 217 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 218 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 218 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 219 Laneway 5 09-07-14 Rev. E

L-02 Landscape Plan – Lot 219 Laneway 5 09-07-14 Rev. E

L-01 Landscape Plan – Lot 220 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 220 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 221 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 221 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 222 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 222 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 223 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 223 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 224 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 224 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 225 Bascule

Street

09-07-14 Rev. E

L-02 Landscape Plan – Lot 225 Bascule

Street

09-07-14 Rev. E

L-01 Landscape Plan – Lot 226 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 226 Bascule

Street

08-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 104

L-01 Landscape Plan – Lot 227 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 227 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 228 Grazier Road 08-07-14 Rev. E

L-02 Landscape Plan – Lot 228 Grazier Road 08-07-14 Rev. E

L-01 Landscape Plan – Lot 229 Grazier Road 08-07-14 Rev. E

L-02 Landscape Plan – Lot 229 Grazier Road 08-07-14 Rev. E

L-01 Landscape Plan – Lot 230 Grazier Road 08-07-14 Rev. E

L-02 Landscape Plan – Lot 230 Grazier Road 08-07-14 Rev. E

L-01 Landscape Plan – Lot 231 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 231 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 232 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 232 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 233 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 233 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 234 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 234 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 235 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 235 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 236 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 236 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 237 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 237 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 238 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 238 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 239 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 239 Bascule

Street

08-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 105

L-01 Landscape Plan – Lot 240 Bascule

Street

08-07-14 Rev. E

L-02 Landscape Plan – Lot 240 Bascule

Street

08-07-14 Rev. E

L-01 Landscape Plan – Lot 241 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 241 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 242 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 242 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 243 Laneway 7 08-07-14 Rev. E

L-02 Landscape Plan – Lot 243 Laneway 7 08-07-14 Rev. E

L-01 Landscape Plan – Lot 244 Civic Way 08-07-14 Rev. E

L-02 Landscape Plan – Lot 244 Civic Way 08-07-14 Rev. E

L-01 Landscape Plan – Lot 245 Civic Way 08-07-14 Rev. E

L-02 Landscape Plan – Lot 245 Civic Way 08-07-14 Rev. E

L-01 Landscape Plan – Lot 246 Civic Way 08-07-14 Rev. E

L-02 Landscape Plan – Lot 246 Civic Way 08-07-14 Rev. E

L-01 Landscape Plan – Lot 247 Civic Way 08-07-14 Rev. E

L-02 Landscape Plan – Lot 247 Civic Way 08-07-14 Rev. E

L-01 Landscape Plan – Lot 248 Bond Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 248 Bond Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 249 Bond Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 249 Bond Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 250 Bond Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 250 Bond Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 251 Bond Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 251 Bond Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 252 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 252 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 253 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 253 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 254 Peppin Street 08-07-14 Rev. E

L-02 Landscape Plan – Lot 254 Peppin Street 08-07-14 Rev. E

L-01 Landscape Plan – Lot 255 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 255 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 256 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 256 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 257 Peppin Street 07-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 106

L-02 Landscape Plan – Lot 257 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 258 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 258 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 259 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 259 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 260 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 260 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 261 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 261 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 262 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 262 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 263 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 263 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 264 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 264 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 265 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 265 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 266 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 266 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 267 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 267 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 268 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 268 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 269 Peppin Street 07-07-14 Rev. E

L-02 Landscape Plan – Lot 269 Peppin Street 07-07-14 Rev. E

L-01 Landscape Plan – Lot 270 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 270 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 271 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 271 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 272 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 272 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 273 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 273 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 274 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 274 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 275 Civic Way 07-07-14 Rev. E

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 107

L-02 Landscape Plan – Lot 275 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 276 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 276 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 277 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 277 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 278 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 278 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 279 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 279 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 280 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 280 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 281 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 281 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 282 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 282 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 283 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 283 Civic Way 07-07-14 Rev. E

L-01 Landscape Plan – Lot 284 Civic Way 07-07-14 Rev. E

L-02 Landscape Plan – Lot 284 Civic Way 07-07-14 Rev. E

H222 Sheet 1 of 4

Sheets

Plan of Proposed Subdivision Stage 3A 11.06.2014 Rev.a

H222 Sheet 2 of 4

Sheets

Plan of Proposed Subdivision Stage 3B 11.06.2014 Rev.a

H222 Sheet 3 of 4

Sheets

Plan of Proposed Subdivision Stage 3C 11.06.2014 Rev.a

H222 Sheet 4 of 4

Sheets

Plan of Proposed Subdivision Stage 3D 11.06.2014 Rev.a

21478 Sheet 1 of 2

Sheets

Survey Plan 23/7/2010

21478 Sheet 2 of 2

Sheets

Survey Plan 23/7/2010

21478 Sheet 1 of 1

Sheets

Survey Plan 23/7/2010

--- Perspective (Lodged with DA) Lodged 31/03/2014

--- Perspective (Lodged with DA) Lodged 31/03/2014

--- Plan showing Balcony for Secondary

Dwelling Lot 176

Submitted

11/09/2014

--- Plan showing Balcony for Secondary

Dwelling Lot 204

Submitted

11/09/2014

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 108

No work (including excavation, land fill or earth reshaping) shall be undertaken prior to

the issue of the Construction Certificate, where a Construction Certificate is required.

2. External Finishes

External finishes and colours shall be in accordance with the details submitted with the

development application and approved with this consent.

3. Rouse Hill Regional Centre Planning Agreement

Contributions for the 153 detached dwelling houses created are to be made in

accordance with the provisions of the Rouse Hill Regional Centre Planning Agreement

dated 29/12/2006.

4. Further Development Application for Park Works

The submission of further Development Application/s, where required, for the proposed

central and pocket parks.

5. Construction Certificate

Prior to construction of the approved development, it is necessary to obtain a

Construction Certificate. A Construction Certificate may be issued by Council or an

Accredited Certifier. Plans submitted with the Construction Certificate are to be amended

to incorporate the conditions of the Development Consent.

6. Building Work to be in Accordance with BCA

All building work must be carried out in accordance with the provisions of the Building

Code of Australia.

7. Planting Requirements

All trees planted as part of the approved landscape plan are to be minimum 75 litre pot

size. All shrubs planted as part of the approved landscape plan are to be minimum

200mm pot size. Groundcovers are to be planted at 5/m2.

8. Approved Subdivision Plan

The subdivision component of the development must be carried out in accordance with

the approved plan of subdivision prepared by Whelans Insites Drawing H222 Sheets 1 to

4 Revision A dated 11/06/2014 except where amended by other conditions of consent.

9. Protection of Public Infrastructure

Council must be notified of any damage to public infrastructure caused by the

development. Adequate protection must be provided prior to work commencing and

maintained during building operations. Any damage caused must be made good, to the

satisfaction of Council, before an Occupation Certificate can be issued. Public

infrastructure includes the road pavement, kerb and gutter, concrete footpaths, drainage

structures, utilities and landscaping fronting the site.

10. Structures Adjacent to Piped Drainage Easements

Buildings and structures, including footings and brick fences, adjacent to existing or

proposed drainage easements must be located wholly outside the easement. A design

must be provided by a structural engineer certifying that the structure will not impart a

load on the pipe in the easement.

11. Gutter and Footpath Crossing Application

Each driveway requires the lodgement of a separate gutter and footpath crossing

application, accompanied by the applicable fee as per Council’s Schedule of Fees and

Charges.

12. Minor Engineering Works

The design and construction of the engineering works listed below must be provided for

in accordance with the following documents and requirements:

a) Council’s Design Guidelines Subdivisions/ Developments

b) Council’s Works Specifications Subdivisions/ Developments

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 109

Any variance from these documents requires separate approval from Council.

Works on existing public roads or any other land under the care and control of Council

must be approved and inspected by Council in accordance with the Roads Act 1993 or

the Local Government Act 1993. A separate minor engineering works application and

inspection fee is payable as per Council’s Schedule of Fees and Charges.

i. Driveway Requirements

The design, finish, gradient and location of all driveway crossings must comply with the

above documents and Council’s Driveway Specifications.

The proposed driveways must be built to Council’s residential standard.

A separate driveway application fee is payable as per Council’s Schedule of Fees and

Charges.

ii. Disused Layback/ Driveway Removal

All disused laybacks and driveways must be removed and replaced with kerb and gutter

together with the restoration and turfing of the adjoining footpath verge area.

iii. Site Stormwater Drainage

The entire site area must be graded, collected and drained by pits and pipes to a suitable

point of legal discharge.

iv. Inter-allotment Stormwater Drainage

Piped inter-allotment stormwater drainage catering for the entire area of each lot must

be provided. Each lot must be uniformly graded to its lowest point where a grated

surface inlet pit must be provided. All collected stormwater is to be piped to an approved

constructed public drainage system.

Where OSD is required, a minimum level difference of 800mm measured between the

surface level and the invert of the outlet pipe must be provided.

v. Earthworks/ Site Regrading

Earthworks are limited to that shown on the approved plans. Where earthworks are not

shown on the approved plan the topsoil within lots must not be disturbed.

vi. Service Conduits

Service conduits to each of the proposed new lots, laid in strict accordance with the

relevant service authority’s requirements, are required. Services must be shown on the

engineering drawings.

13. Subdivision Certificate Pre-Lodgement Meeting/ Check

Prior to the submission of a Subdivision Certificate application a draft copy of the final

plan, administration sheet and Section 88B instrument (where included) must be

submitted in order to establish that all conditions have been complied with.

Street addresses for the lots within this subdivision will be allocated as part of this

preliminary check process, for inclusion on the administration sheet.

14. Proposed Street Naming

A written application for street naming must be submitted to Council for approval, along

with the applicable fee as per Council’s Schedule of Fees and Charges. The street names

proposed must comply with requirements of the NSW Geographical Names Board and

Council.

The application must nominate three suggested names per street, in order of preference,

and the source of the names proposed.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 110

15. Street Trees

Street trees must be provided for the public and private roads within or fronting the

development site (excluding laneways) spaced between 7m and 10m apart and with a

minimum of one tree per lot frontage. The location of street trees must be considerate of

driveways, services, drainage pits and sight lines at intersections. The species and size

of street trees must comply with the requirements of Council. Details demonstrating

compliance with the above must be submitted for approval before any street trees are

planted.

For public roads, a performance/ maintenance bond is required to be submitted to

Council once the street trees are planted. The bond will be held for one year and may be

extended if replacement street trees are required to be planted. The bond is refundable

upon written application to Council. Alternatively, street trees can be planted by Council

subject to payment of the applicable fee as per Council’s Schedule of Fees and Charges.

16. Recycled Water

The subject site must be connected to Sydney Water’s Rouse Hill Recycled Water

Scheme, unless written evidence from Sydney Water is submitted advising that this

service is not available.

17. Road Opening Permit

Should the subdivision/ development necessitate the installation or upgrading of utility

services or any other works on Council land beyond the immediate road frontage of the

development site and these works are not covered by a Construction Certificate issued

by Council under this consent then a separate road opening permit must be applied for

and the works inspected by Council’s Maintenance Services team.

The contractor is responsible for instructing sub-contractors or service authority

providers of this requirement. Contact Council’s Construction Engineer if it is unclear

whether a separate road opening permit is required.

18. Management of Construction Waste

Any waste generated as a result of construction of the development is to be reused and

recycled where possible, and any residual waste is to be disposed of at a licensed waste

facility. Waste materials must be appropriately stored and secured within a designated

waste area on site at all times, prior to its reuse on site or being sent off site. Building

waste containers are not permitted to be placed on the public way at any time unless a

separate application is approved by Council to locate a building waste container in a

public place. The separation and recycling of the following waste materials is required:

metals, timber, masonry products, clean waste plasterboard and mixed plastics and

cardboard. This can be achieved by source separation on site, that is, a bin for metal

waste, a bin for timber, a bin for bricks and so on. Alternatively, mixed waste may be

stored in one or more bins and sent to a waste contractor or transfer/ sorting station

that will sort the waste on their premises for recycling. Receipts of all waste/ recycling

tipping must be kept on site at all times and produced in a legible form to any authorised

officer of the Council who asks to see them.

19. Commencement of Domestic Waste Services

The property owner or agent acting for the owner must ensure to arrange the

commencement of an individual domestic waste service with Council no later than two

days after occupancy and no earlier than two days prior to occupancy of a dwelling. The

service is to be arranged by telephoning Council on (02) 9843 0310. All requirements of

Council’s waste collection service must be complied with at all times.

20. Provision of Domestic Waste Storage Areas

Sufficient space must be allocated within the lot boundary of each property to store

three 240 litre mobile bins (for garbage, recycling and garden organics). The location is

required to ensure that bins are not visible from public or private roads and that the bins

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 111

can be wheeled to the street without the need to go over steps, landscape edging or

gutters or through a habitable area of the dwelling.

21. Zero Lot Line Dwellings – Easement Encroachment

No element of those dwellings located on the boundary line with an adjoining lot (zero

lot line dwellings) can be located within that adjoining lot. Construction tolerances should

be accounted for when surveying and constructing these dwellings.

Similarly, the dwellings on the lots adjacent, being those lots burdened by an easement

for repair; must be located wholly outside of the easement except where it is shown on

the approved plans that the encroaching eaves/ guttering does not impede maintenance

access to either dwelling and that the encroachment is no closer than 450mm to the

boundary.

22. Acoustic assessment of certain dwellings

Any development consent granted for dwellings opposite the Northern Tributary and

Caddies Boulevard will require acoustic assessment to be submitted prior to the issue of

Construction Certificates for the individual dwellings. The acoustic assessment shall

demonstrate how compliance with the acoustic goals in clause 87 of the Infrastructure

SEPP are to be achieved.

23. Sound Level Output

The use of the premises, building services, equipment, machinery and ancillary fittings

shall not give rise to “offensive noise” as defined under the provision of the Protection of

the Environment Operation Act 1997. The sound level output shall not exceed 5 dB(A)

above the ambient background level at the closest neighbour’s boundary.

24. Contamination

Any new information, which comes to light during construction works, which has the

potential to alter previous conclusions about site contamination, shall be immediately

notified to Council.

25. Stockpiles

Stockpiles of topsoil, sand, aggregate, spoil or other material capable of being moved by

water, to be stored clear of any drainage line, easement, natural watercourse, footpath,

kerb or roadside.

26. Property Numbering for Integrated Housing

The responsibility for property numbering is vested solely in Council.

The street addresses for these lots are as follows:-

Lot 132 = 15 Galara Street Lot 165 = 14 Saxon Lane Lot 198 = 3 Bascule Street

Lot 133 = 17 Galara Street Lot 166 = 12 Saxon Lane Lot 199 = 23 Grazier Road

Lot 134 = 19 Galara Street Lot 167 = 10 Jimbuck Lane Lot 200 = 21 Grazier Road

Lot 135 = 21 Galara Street Lot 168 = 8 Jimbuck Lane Lot 201 = 19 Grazier Road

Lot 136 = 23 Galara Street Lot 169 = 54 Caddies Boulevard Lot 202 = 17 Grazier Road

Lot 137 = 3 Jimbuck Lane Lot 170 = 56 Caddies Boulevard Lot 203 = 15 Grazier Road

Lot 138 = 8 Romney Street Lot 171 = 58 Caddies Boulevard Lot 204 = 74 Caddies Boulevard

Lot 139 = 6 Romney Street Lot 172 = 60 Caddies Boulevard Lot 205 = 76 Caddies Boulevard

Lot 140 = 4 Romney Street Lot 173 = 62 Caddies Boulevard Lot 206 = 78 Caddies Boulevard

Lot 141 = 2 Romney Street Lot 174 = 64 Caddies Boulevard Lot 207 = 80 Caddies Boulevard

Lot 142 = 25 Galara Street Lot 175 = 66 Caddies Boulevard Lot 208 = 82 Caddies Boulevard

Lot 143 = 27 Galara Street Lot 176 = 68 Caddies Boulevard Lot 209 = 84 Caddies Boulevard

Lot 144 = 29 Galara Street Lot 177 = 17 Saxon Lane Lot 210 = 86 Caddies Boulevard

Lot 145 = 31 Galara Street Lot 178 = 19 Saxon Lane Lot 211 = 88 Caddies Boulevard

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 112

Lot 146 = 33 Galara Street Lot 179 = 21 Saxon Lane Lot 212 = 90 Caddies Boulevard

Lot 147 = 35 Galara Street Lot 180 = 23 Saxon Lane Lot 213 = 92 Caddies Boulevard

Lot 148 = 37 Galara Street Lot 181 = 27 Saxon Lane Lot 214 = 1 Yet to be named

Lot 149 = 39 Galara Street Lot 182 = 29 Saxon Lane Lot 215 = 3 Yet to be named

Lot 150 = 26 Romney Street Lot 183 = 31 Saxon Lane Lot 216 = 5 Yet to be named

Lot 151 = 24 Romney Street Lot 184 = 33 Saxon Lane Lot 217 = 21 Bascule Street

Lot 152 = 22 Romney Street Lot 185 = 35 Saxon Lane Lot 218 = 19 Bascule Street

Lot 153 = 20 Romney Street Lot 186 = 37 Saxon Lane Lot 219 = 17 Bascule Street

Lot 154 = 18 Romney Street Lot 187 = 39 Saxon Lane Lot 220 = 15 Bascule Street

Lot 155 = 16 Romney Street Lot 188 = 17 Peppin Street Lot 221 = 13 Bascule Street

Lot 156 = 14 Romney Street Lot 189 = 15 Peppin Street Lot 222 = 11 Bascule Street

Lot 157 = 12 Romney Street Lot 190 = 13 Peppin Street Lot 223 = 9 Bascule Street

Lot 158 = 5 Jimbuck Lane Lot 191 = 11 Peppin Street Lot 224 = 7 Bascule Street

Lot 159 = 7 Jimbuck Lane Lot 192 = 9 Peppin Street Lot 225 = 5 Bascule Street

Lot 160 = 9 Jimbuck Lane Lot 193 = 13 Romney Street Lot 226 = 4 Bascule Street

Lot 161 = 11 Jimbuck Lane Lot 194 = 11 Romney Street Lot 227 = 2 Bascule Street

Lot 162 = 6 Jimbuck Lane Lot 195 = 43 Saxon Lane Lot 228 = 29 Grazier Road

Lot 163 = 7 Romney Street Lot 196 = 41 Saxon Lane Lot 229 = 31 Grazier Road

Lot 164 = 16 Saxon Lane Lot 197 = 1 Bascule Street Lot 230 = 33 Grazier Road

Lot 231 = 21 Peppin Street Lot 249 = 5 Bond Street Lot 267 = 6 Peppin Street

Lot 232 = 23 Peppin Street Lot 250 = 3 Bond Street Lot 268 = 1 Civic Way

Lot 233 = 6 Bascule Street Lot 251 = 1 Bond Street Lot 269 = 3 Civic Way

Lot 234 = 8 Bascule Street Lot 252 = 34 Peppin Street Lot 270 = 5 Civic Way

Lot 235 = 10 Bascule Street Lot 253 = 36 Peppin Street Lot 271 = 7 Civic Way

Lot 236 = 12 Bascule Street Lot 254 = 38 Peppin Street Lot 272 = 9 Civic Way

Lot 237 = 14 Bascule Street Lot 255 = 30 Peppin Street Lot 273 = 11 Civic Way

Lot 238 = 16 Bascule Street Lot 256 = 28 Peppin Street Lot 274 = 13 Civic Way

Lot 239 = 18 Bascule Street Lot 257 = 26 Peppin Street Lot 275 = 15 Civic Way

Lot 240 = 20 Bascule Street Lot 258 = 24 Peppin Street Lot 276 = 17 Civic Way

Lot 241 = 42 Peppin Street Lot 259 = 22 Peppin Street Lot 277 = 19 Civic Way

Lot 242 = 40 Peppin Street Lot 260 = 20 Peppin Street Lot 278 = 21 Civic Way

Lot 243 = 3 Yet to be named Lot 261 = 18 Peppin Street Lot 279 = 23 Civic Way

Lot 244 = 41 Civic Way Lot 262 = 16 Peppin Street Lot 280 = 25 Civic Way

Lot 245 = 39 Civic Way Lot 263 = 14 Peppin Street Lot 281 = 27 Civic Way

Lot 246 = 37 Civic Way Lot 264 = 12 Peppin Street Lot 282 = 29 Civic Way

Lot 247 = 35 Civic Way Lot 265 = 10 Peppin Street Lot 283 = 31 Civic Way

Lot 248 = 7 Bond Street Lot 266 = 8 Peppin Street Lot 284 = 33 Civic Way

PRIOR TO THE ISSUE OF CONSTRUCTION CERTIFICATE

27. Privacy Measures for Windows

Second and third storey habitable room windows within 4.5 metres of a side boundary,

within 5 metres of a rear boundary of a 25 metre deep lot or within 7 metres of a rear

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 113

boundary of a 30 metre lot are to have permanent privacy measures. Acceptable privacy

measures include landscaping, alternative window arrangements, external louvers, 1.5

metre sill height or fixed and obscured glass to 1.5 metres with clear and/or operable

glass over. Details are to be provided the Private Certifying Authority prior to issue of

the Construction Certificate.

28. Balconies for Lots 176 and 204

Balconies are to be provided for the secondary dwellings for Lots 176 and 204, as shown

on the approved plans. Details are to be provided prior to issue of the Construction

Certificate.

29. Approved Plans to be Submitted to Sydney Water

The approved plans must be submitted to a Sydney Water Quick Check agent to

determine whether the development will affect any Sydney Water wastewater and water

mains, stormwater drains and/or easement, and if any requirements need to be met.

Plans will be appropriately stamped.

Please refer to the web site www.sydneywater.com.au for:

Quick Check agents details – See building and Developing then Quick Check

and

Guidelines for Building Over/Adjacent to /Sydney Water Assets – see Building and

Developing then Building and Renovating.

30. Security Bond – Road Pavement and Public Asset Protection

In accordance with Section 80A(6)(a) of the Environmental Planning and Assessment Act

1979, a security bond of $187,850.00 is required to be submitted to Council to

guarantee the protection of the road pavement and other public assets in the vicinity of

the site during construction works. The above amount is calculated at the rate of $85.00

per square metre based on the road frontage of the subject site (340m) multiplied by

the width of the northbound road carriageway in Caddies Boulevard (6.5m).

The bond must be lodged with Council before a Construction Certificate is issued.

The bond is refundable upon written application to Council and is subject to all work

being restored to Council’s satisfaction. Should the cost of restoring any damage exceed

the value of the bond, Council will undertake the works and issue an invoice for the

recovery of these costs.

31. Bank Guarantee Requirements

Any bank guarantee submitted in lieu of a cash bond must comply with the following:

a) Have no expiry date;

b) Be sent to Council direct from the bank;

c) Reference the development application, condition and matter to which it relates;

d) The amount must match that required to be paid;

e) If a single bank guarantee is used for multiple bonds, it must be itemised.

Should Council need to uplift the bank guarantee, notice in writing will be forwarded to

the applicant 14 days beforehand.

32. Erosion & Sediment Control Plan

Submission of an Erosion and Sediment Control Plan to the Principal Certifying Authority,

including details of:

a) Allotment boundaries

b) Location of the adjoining roads

c) Contours

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 114

d) Existing vegetation

e) Existing site drainage

f) Critical natural areas

g) Location of stockpiles

h) Erosion control practices

i) Sediment control practices

j) Outline of a maintenance program for the erosion and sediment controls.

(NOTE: For guidance on the preparation of the Plan refer to ‘Managing Urban

Stormwater Soils & Construction’ produced by the NSW Department of Housing).

33. Construction Management Plan (Staged Applications)

A construction management plan must be submitted demonstrating how the potential for

conflict between resident and construction traffic is to be minimised and managed

throughout all stages of the development. The construction management plan must be

submitted before a Construction Certificate is issued and complied with for the duration

of works.

PRIOR TO WORK COMMENCING ON THE SITE

34. Principal Certifying Authority

A sign is to be erected in accordance with Clause 98 A (2) of the Environmental Planning

and Assessment Regulations 2000.

35. Builder and PCA Details Required

Notification in writing of the builder’s name, address, telephone and fax numbers to be

submitted to the Principal Certifying Authority prior to work commencing.

Two days before work commences, Council shall be notified of the Principal Certifying

Authority in accordance with the Regulations.

36. Management of Building Sites – Builder’s Details

The erection of suitable fencing or other measures to restrict public access to the site

and building works, materials or equipment when the building work is not in progress or

the site is otherwise unoccupied.

The erection of a sign, in a prominent position, stating that unauthorised entry to the

site is not permitted and giving an after hours contact name and telephone number. In

the case of a privately certified development, the name and contact number of the

Principal Certifying Authority.

37. Consultation with Service Authorities

Applicants are advised to consult with Telstra, NBN Co and Australia Post regarding the

installation of telephone conduits, broadband connections and letterboxes as required.

Unimpeded access must be available to the electricity supply authority, during and after

building, to the electricity meters and metering equipment.

The building plans must be submitted to the appropriate Sydney Water office to

determine whether the development will affect Sydney Water’s sewer and water mains,

stormwater drains and/or easements. If the development complies with Sydney Water’s

requirements, the building plans will be stamped indicating that no further requirements

are necessary.

38. Public Infrastructure Inventory Report

A public infrastructure inventory report must be prepared and submitted to Council

recording the condition of all public assets in the direct vicinity of the development site.

This includes, but is not limited to, the road fronting the site along with any access route

used by heavy vehicles. If uncertainty exists with respect to the necessary scope of this

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 115

report, it must be clarified with Council before works commence. The report must

include:

a) Planned construction access and delivery routes; and

b) Dated photographic evidence of the condition of all public assets.

39. Approved Temporary Closet

An approved temporary closet connected to the sewers of Sydney Water, or alternatively

an approved chemical closet is to be provided on the land, prior to building operations

being commenced.

40. Erosion and Sedimentation Controls

Erosion and sedimentation controls shall be in place prior to the commencement of site

works; and maintained throughout construction activities until the site is landscaped

and/or suitably revegetated. The controls shall be in accordance with the details

approved by Council and/or as directed by Council Officers. These requirements shall be

in accordance with Managing Urban Stormwater – Soils and Construction produced by

the NSW Department of Housing (Blue Book).

41. Stabilised Access Point

A stabilised all weather access point is to be provided prior to commencement of site

works, and maintained throughout construction activities until the site is stabilised. The

controls shall be in accordance with the requirements with the details approved by

Council and/or as directed by Council Officers. These requirements shall be in

accordance with Managing Urban Stormwater – Soils and Construction produced by the

NSW Department of Housing (Blue Book).

42. Traffic Control Plan

A Traffic Control Plan is required to be prepared and submitted to Council for approval.

The person preparing the plan must have the relevant accreditation to do so. Where

amendments to the plan are required post approval, they must be submitted to Council

for further approval prior to being implemented.

A plan that includes full (detour) or partial (temporary traffic signals) width road closure

requires separate specific approval from Council. Sufficient time should be allowed for

this to occur.

43. Sediment and Erosion Control

The approved sediment and erosion control measures, including a stabilised all weather

access point, must be in place prior to works commencing and maintained during

construction and until the site is stabilised to ensure their effectiveness. For major

works, these measures must be maintained for a minimum period of six months

following the completion of all works.

44. Service Authority Consultation – Subdivision Works

Before subdivision works commence:

a) Documentary evidence must be submitted confirming that satisfactory arrangements

have been made for the relocation, undergrounding and/ or provision of electrical

services for the non-residue lots created by the subdivision.

b) Documentary evidence, including a notice of requirements from Sydney Water, must

be submitted confirming that satisfactory arrangements have been made for the

provision of water and sewerage facilities.

c) Consultation with the relevant telecommunications provider authorised under the

Telecommunications Act regarding the installation of telephone conduits is required.

The design and construction of these works must comply with current NBN

standards, where applicable.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 116

45. Erosion & Sediment Control Plan Kept on Site

A copy of the Erosion and Sediment Control Plan must be kept on site at all times during

construction and made available to Council officers on request.

46. Resubmit Waste Management Plan

Prior to works commencing on site, the Waste Management Plan submitted as part of the

Development Application and dated 31 March 2014 must be resubmitted to and

approved by Council. The plan is required to readdress the following:

Company name of the skip bin hire company or waste transport contractor/s; and

Location of waste disposal and recycling.

All commitments of the approved plan must be implemented during construction of the

development. However, the information provided can change provided that the same or

a greater level of reuse and recycling is achieved as detailed in the plan. Any material

moved offsite is to be transported in accordance with the requirements of the Protection

of the Environment Operations Act 1997 and only to a place that can lawfully be used as

a waste facility Receipts of all waste/ recycling tipping must be kept on site at all times

and produced in a legible form to any authorised officer of the Council who asks to see

them.

DURING CONSTRUCTION

47. Hours of Work

Work on the project to be limited to the following hours: -

Monday to Saturday - 7.00am to 5.00pm;

No work to be carried out on Sunday or Public Holidays.

The builder/contractor shall be responsible to instruct and control sub-contractors

regarding the hours of work. Council will exercise its powers under the Protection of the

Environment Operations Act, in the event that the building operations cause noise to

emanate from the property on Sunday or Public Holidays or otherwise than between the

hours detailed above.

48. Survey Report

Survey Certificate to be submitted to the Principal Certifying Authority at footings and/or

formwork stage. The certificate shall indicate the location of the building in relation to all

boundaries, and shall confirm the floor level prior to any work proceeding on the

building.

49. Compliance with BASIX Certificate

Under clause 97A of the Environmental Planning and Assessment Regulation 2000, it is a

condition of this Development Consent that all commitments listed in the submitted

BASIX Certificates be complied with. Any subsequent version of the BASIX Certificate

will supersede all previous versions of the certificate.

A Section 96 Application may be required should the subsequent version of this BASIX

Certificate necessitate design changes to the development. However, a Section 96

Application will be required for a BASIX Certificate with a new number.

50. Roof Water Drainage

Gutter and downpipes to be provided and connected to an approved drainage system

upon installation of the roof covering.

51. Compliance with Critical Stage Inspections and Other Inspections

Nominated by the Principal Certifying Authority

Section 109E(d) of the Act requires certain specific inspections (prescribed by Clause

162A of the Regulations) and known as “Critical Stage Inspections” to be carried out for

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 117

building work. Prior to permitting commencement of the work, your Principal Certifying

Authority is required to give notice of these inspections pursuant to Clause 103A of the

Regulations.

N.B. An Occupation Certificate cannot be issued and the building may not be able to be

used or occupied where any mandatory critical stage inspections or other inspections

required by the Principal Certifying Authority are not carried out.

Where Council is nominated as Principal Certifying Authority, notification of all

inspections required is provided with the Construction Certificate approval.

NOTE: You are advised that inspections may only be carried out by the PCA

unless by prior agreement of the PCA and subject to that person being an

accredited certifier.

52. Standard of Works

All work must be carried out in accordance with Council’s Works Specification

Subdivisions/ Developments and must include any necessary works required to make the

construction effective. All works, including public utility relocation, must incur no cost to

Council.

53. Critical Stage Inspections – Subdivision Works

The subdivision works must be inspected by Council in accordance with the schedule

included in Council’s Works Specification Subdivisions/ Developments. A minimum of 24

hour’s notice is required for inspections. No works are to commence until the first

inspection has been carried out.

54. Dust Control

The emission of dust must be controlled to minimise nuisance to the occupants of the

surrounding premises. In the absence of any alternative measures, the following

measures must be taken to control the emission of dust:

Dust screens must be erected around the perimeter of the site and be kept in good

repair for the duration of the construction work.

All dusty surfaces must be wet down and suppressed by means of a fine water

spray. Water used for dust suppression must not cause water pollution; and

All stockpiles of materials that are likely to generate dust must be kept damp of

covered.

55. Construction Noise

The emission of noise from the construction of the development shall comply with the

Interim Construction Noise Guideline published by the Department of Environment and

Climate Change (July 2009).

56. Confirmation of Compliance with Zero Lot Line

Prior to the installation of the external roof tiles or sheeting, written advice from a

registered surveyor must be provided to the Principal Certifying Authority confirming

that the constructed guttering and fascia to the wall for each property using a zero lot

line, is located wholly within the property boundary.

57. Location of Dwelling

The dwellings on lots burdened by an easement for repair in response to an adjacent

zero lot line dwelling must be located wholly outside of the easement except where

Council has permitted an encroachment (limited to eaves/ guttering). This includes all

services, equipment and utilities.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 118

PRIOR TO ISSUE OF AN OCCUPATION AND/OR SUBDIVISION CERTIFICATE

58. Landscaping Prior to Issue of Occupation Certificate

The landscaping of the site shall be carried out prior to issue of the Final Occupation

Certificate (within each stage if applicable) in accordance with the approved plan. All

landscaping is to be maintained at all times in accordance with BHDCP Part D, Section 3

– Landscaping and the approved landscape plan.

59. Works as Executed Plans

Works as executed (WAE) plans prepared by a suitably qualified engineer or registered

surveyor must be submitted to Council when the subdivision works are completed. The

WAE plans must be prepared in accordance with Council’s Design Guidelines

Subdivisions/ Developments.

The plans must be accompanied by pavement density results, pavement certification,

concrete core test results, site fill results, structural certification, CCTV recording,

signage details and a public asset creation summary, where relevant.

60. Completion of Engineering Works

An Occupation Certificate must not be issued prior to the completion of all engineering

works covered by this consent, in accordance with this consent.

61. Public Infrastructure Inventory Report - Post Construction

Before an Occupation Certificate is issued, an updated public infrastructure inventory

report must be prepared and submitted to Council. The updated report must identify any

damage to public assets and the means of rectification for the approval of Council.

62. Completion of Subdivision Works

A Subdivision Certificate cannot be issued prior to the completion of all subdivision works

covered by this consent.

63. Confirmation of Pipe Locations

A letter from a registered surveyor must be provided with the WAE plans certifying that

all pipes and drainage structures are located within the proposed drainage easements.

64. Section 73 Compliance Certificate

A Section 73 Compliance Certificate issued under the Sydney Water Act 1994 must be

obtained from Sydney Water confirming satisfactory arrangements have been made for

the provision of water and sewer services. Application must be made through an

authorised Water Servicing Coordinator. The certificate must refer to this development

consent and all of the lots created.

Sydney Water’s guidelines provide for assumed concurrence for the strata subdivision of

a development approved by an earlier consent covered by a compliance certificate.

65. Provision of Electrical Services

Submission of a notification of arrangement certificate confirming satisfactory

arrangements have been made for the provision of electrical services. This must include

the under-grounding of the existing electrical services fronting the site and removal of all

redundant poles and cables, unless otherwise approved by Council in writing. The

certificate must refer to this development consent and all of the lots created.

66. Building Adjacent to Proposed Boundary

Where any part of an existing/ partially constructed building is located within 2m of a

proposed boundary the location of such must be determined by a registered surveyor

and shown on the final plan.

67. Building Services

A letter from a registered surveyor must be submitted certifying that all facilities

servicing the existing/ partially constructed buildings are located wholly within their

respective lot or are otherwise contained within a suitable easement.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 119

68. Prior or Concurrent Registration of Preceding Subdivision

A Subdivision Certificate cannot be issued for this subdivision before the preceding

stage/ subdivision pursuant to Development Consent DA 250/2013/ZB has been

registered, unless the two are registered concurrently.

69. Provision of Telecommunication Services

Submission of a telecommunications infrastructure provisioning confirmation certificate

issued by the relevant telecommunications provider authorised under the

Telecommunications Act, or a design compliance certificate and an as-built compliance

certificate from the company engaged to design and construct the pit and pipe infrastructure,

confirming satisfactory arrangements have been made for the provision, or relocation, of

telecommunication services including telecommunications cables and associated

infrastructure. This must include the under-grounding of the existing telecommunication

services fronting the site and removal of all redundant poles and cables, unless

otherwise approved by Council in writing. The certificate must refer to this development

consent and all of the lots created.

70. Final Plan and 88B Instrument

The final plan and Section 88B Instrument must provide for the following. Council’s

standard recitals must be used.

i. Easement – Private Stormwater Drainage

Inter-allotment drainage easements must be created to ensure each and every lot is

provided with a legal point of discharge. Easement widths must comply with Council’s

Design Guidelines Subdivisions/ Developments.

ii. Easement – Right of Access/ Easement for Services

A right of access/ easement for services must be created over the access handle of

proposed lots 174 to 176 and 201 to 203.

iii. Positive Covenant – Maintenance/ Repair of Shared Driveway

A positive covenant must be placed on the title of proposed lots 174 to 176 and 201 to

203 to ensure the maintenance/ repair of the shared driveway using the “maintenance/

repair of shared access” terms included in the standard recitals.

iv. Easement – Repairs/ Zero Lot Line Dwellings

A 900mm wide (minimum) easement for repairs is required over those lots adjacent to

the zero-lot line dwellings identified on the approved plan using the “zero lot line

dwellings” terms included in the standard recitals.

v. Restriction – Earthworks

All residential lots must be burdened with a restriction using the “earthworks” terms

included in the standard recitals.

vi. Restriction – Restricted Access

Lots 132, 141, 169 to 176 and 203 to 214 must be burdened with a restriction

precluding access to Caddies Boulevard using the “restricted access” terms included in

the standard recitals.

vii. Restriction – Bedroom Numbers

All lots that contain a new dwelling home/ attached dwelling must be burdened with a

restriction using the “bedroom numbers” terms included in the standard recitals.

viii. Restriction – Salinity

All residential lots must be burdened with a restriction that refers to the salinity report

submitted with the development application using the “salinity requirements” terms

included in the standard recitals.

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 120

ix. Positive Covenant – Waste Collection/ Bin Presentation

For those lots that do not present their bins to their lot frontage for collection, as shown

on the waste collection location plan Ref SKC530 dated 19 May 2014 prepared by Hyder

must be burdened with a positive covenant requiring that bins are presented to the

collection location shown on that plan, using the “waste collection/ bin presentation”

terms included in the standard recitals.

71. Subdivision Certificate Application

When submitted, the Subdivision Certificate application must include:

a) Three copies of the final plan.

b) The original administration sheet and Section 88B instrument, along with one

copy of each.

c) All certificates and supplementary information required by this consent.

d) An AutoCAD copy of final plan (GDA 1994 MGA94 Zone56).

72. Site/Lot Classification Report

A site/lot classification report prepared by a suitably qualified geotechnical engineer

must be prepared and submitted following the completion of all subdivision works

confirming that all residential lots are compliant with AS 2870 and are suitable for

development. The report must be accompanied by a table which summarises the

classification of all lots created as part of the subdivision.

73. Resubmit Waste Collection Plan

Prior to an Occupation Certificate being issued, the plan entitled Stage 3 Waste

Collection Locations (drawing no. SKC530) and dated 19 May 2014 must be resubmitted

to and approved by Council. The plan is required to clearly indicate which collection point

is for which lot.

THE USE OF THE SITE

74. Waste and Recycling Collection

The collection of waste and recyclables from the development is required to be

undertaken in accordance with the approved plan entitled Stage 3 Waste Collection

Locations (drawing no. SKC530) and dated 19 May 2014, unless otherwise determined

by Council. Bin presentation will not be permitted within common driveways or to the

right hand side of one way laneways.

NOTE: A copy of the plan must be made available to all future residents to ensure they

are informed of the waste collection arrangements.

ATTACHMENTS

1. Locality Plan

2. Aerial Photograph

3. Site Plan

4. Typical Elevations

5. Typical Streetscape Elevations

6. Mungerie House 70m Curtilage

7. Perspective

8. Perspective

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 121

ATTACHMENT 1 – LOCALITY PLAN

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 122

ATTACHMENT 2 – AERIAL PHOTOGRAPH

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 123

ATTACHMENT 3 – SITE PLAN

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 124

ATTACHMENT 4 – TYPICAL ELEVATIONS

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 125

ATTACHMENT 4 – TYPICAL ELEVATIONS

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 126

ATTACHMENT 5 –TYPICAL STREETSCAPE ELEVATIONS

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 127

ATTACHMENT 5 –TYPICAL STREETSCAPE ELEVATIONS

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 128

ATTACHMENT 6 – MUNGERIE HOUSE 70M CURTILAGE

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 129

ATTACHMENT 7 – PERSPECTIVE

JOINT REGIONAL PLANNING PANEL 16 OCTOBER 2014

PAGE 130