Joint BI – ANNUAL Review of the HIV Response in Tanzania 2006 to 2008 MILESTONES IMPLEMENTATION...
-
Upload
victoria-gilmore -
Category
Documents
-
view
213 -
download
0
Transcript of Joint BI – ANNUAL Review of the HIV Response in Tanzania 2006 to 2008 MILESTONES IMPLEMENTATION...
Joint BI – ANNUAL Review of the HIV Response in Tanzania 2006 to
2008
MILESTONES IMPLEMENTATION ASSESSMENT OF PROGRESS REPORT
BY RBM KALINGA1
THE MILESTONES SET 2006 AJR WERE 31
• FULLY IMPLEMENTED 13• PARTIALLY IMPLEMENTED 13• NOT IMPLEMENTED 5
WHAT IS OUR PERFORMANCE ?
2
1.PRIVATE SECTOR AND BUSINESS COALITION
3
4
PRIVATE SECTOR AND BUSINESS COALITION
MILESTONES RESPONSIBLE STATUS PROGRESS
1. Number of Companies Mainstreaming HIV/AIDS increased from 52 to 104 by , 2007
ABCT PARTIALLY ACHIEVED
THE INCREASE OF COMPANIES MAINSTREAMING HIV /AIDS WAS FROM 52 TO 68 AGAINST THE TARGET OF 52 TO 104 COMPANIES
2. Advocacy for including HIV/AIDS control clause in investment agreements initiated by , 2007
ABCT/OTHERS NOT INITIATED
THIS MAY BE ACHIEVED WHEN THE NEW HIV LAW WILL START FUNCTIONING
5
PRIVATE SECTOR AND BUSINESS COALITION…
MILESTONE RESPONSIBLE STATUS PROGRESS
3. ABCT has a strategy for promoting best practices in workplace programmes by , 2007
ABCT NO SPECIFIC STRATEGY WAS DEVELOPED
ABCT IS PROMOTING WORK PLACE PROGRAMMES THROUGH WORKSHOPS AND SEMINARS
6
PRIVATE SECTOR AND BUSINESS COALITION…
MILESTONE RESPONSIBLE STATUS PROGRESS
4. 50% funding of ABCT by members
ABCT PARTIALLY ACHIEVED
ONLY 29% COVERED BY MEMBERSHIP FEES OUT OF TARGET OF 50%
7
PRIVATE SECTOR AND BUSINESS COALITION…
MILESTONE RESPONSIBLE STATUS PROGRESS5. Instructions given to LGAs to facilitate financing to support the sector in all the Councils by ,2007
ABCT NOT ACHIEVED
DIALOGUE IS GOING ON AS PROCESS
8
PRIVATE SECTOR AND BUSINESS COALITION…
MILESTONE RESPONSIBLE STATUS PROGRESS6. Scaling up best practices with support from various sources including ABCT by 2007
ABCT PARTLY ACHIEVED
MORE PARTNERS /ACTORS ARE NOW TAKING PART IN SCALING UP GOOD PRACTICES
2.POLICY AND PLANNING
.
9
10
POLICY AND PLANNING …
MILESTONE RESPONSIBLE STATUS PROGRESS7.Technical Assistance Facility to be in place by , 2007
TACAIDS PARTIALLY ACHIEVED
THERE IS GENERIC DOCUMENT OUTLINING THE TECHNICAL ASSISTANCE PLAN OF NMSF DEVELOPED AND IN DRAFT FORM. CONSULTATION IS CONTINUING
11
POLICY AND PLANNING …
MILESTONE RESPONSIBLE STATUS PROGRESS8. NMSF revised in light of MKUKUTA through a participatory process BY 2007
TACAIDS FULLY ACHIEVED
NMSF WAS REVISED IN LINE OF MKUKUTA AND PARTICIPATORY AND A DOCUMENT IS PRODUCED
12
POLICY AND PLANNING …
MILESTONE RESPONSIBLE STATUS PROGRESS9. Regular consultative forums with key sectors
TACAIDS FULLY ACHIEVED
TWICE A YEAR THERE IS CONSULTATIVE FORUMS WITH KEY SECTORS
13
POLICY AND PLANNING …
MILESTONE RESPONSIBLE STATUS PROGRESS10. HIV/AIDS included in MDA’s quarterly reports to PMO by 2007
MDAS AND PMO FULLY ACHIEVED
MORE 54 MDAS ARE NOW INCLUDING HIV REPORT IN QUARTERLY REPORT SUBMITTED TO PRIME MINISTERS OFFICE
MONITORING,EVALUATION AND RESEARCH
.
14
15
MONITORING AND EVALUATION
MILESTONE RESPONSIBLE STATUS PROGRESS13. TACAIDS M&E unit to be functional by 2006
TACAIDS FULLY ACHIEVED WITH 4 TECHNICAL STAFF
THERE IS A PLAN TO EMPLOYEE ONE EPIDEMIOLOGIST AND , STATISTICIAN TO REINFORCE THE UNIT
16
MONITORING AND EVALUATION …
MILESTONE RESPONSIBLE STATUS PROGRESS
14.M&E system is functional including financial monitoring by , 2007
TACAIDS PARTIALLY ACHIEVED
TOMSHA GUIDELINES ADOPTED 2006, ALL COMPONENTS ARE IN PLACE (EXCEPT SOME INITIATIVES CONCERNING ADVOCACY AND
INFORMATION) HOWEVER , MORE EFFORT IS REQUIRED FOR COVERAGE , TIMELY AND ACCURACY REPORTING
17
MONITORING AND EVALUATION …
MILESTONE RESPONSIBLE STATUS PROGRESS15.Develop the Operational Road Map By 2006
TACAIDS FULLY ACHIEVED
THE ROAD MAP WITH 12 COMPONENTS OF THE M AND E SYSTEM DEVELOPED AND IN USE . UPDATE IS REQUIRED
DISTRICT AND COMMUNITY RESPONSE
.
18
19
DISTRICT AND COMMUNITY RESPONSE
MILESTONE RESPONSIBLE STATUS PROGRESS1. All eligible LGAs accessing funds through the block grant by 2007
MOFA/CIDA CANADA
FULLY ACHIEVED
ALL ELIGIBLE LGAS ARE ACCESSING THE BLOCK GRANTS . THE PROCESS WAS DELAYED AND FINALIZED MID 2008 . CIDA CANADA IS SUPPORTING THIS PROCESS
20
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS
2. The Regional Secretariats well placed to ensure sustainability after the RFAs by 2007
TACAIDS PARTIALLY ACHIEVED
THE 11 RFAS WHOM CONTRACTS ARE OVER NOW IN THEIR TORS WERE SUPPOSE TO SUPPORT RS TO TAKE THE ROLE. THROUGH EXIT MEETINGS IT IS CLEAR THAT MORE CAPACITY IS REQUIRED FOR THEM TO TAKE THE ROLES OF RFAS
21
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS3. LGAs allocate resources to address identified capacity strengthening needs BY 2007
TACAID S /RS PARTIALLY ACHIEVED
ALTHOUGH , ACHIEVED MORE CAPACITY BUILDING IS REQUIRED THROUGH DIALOGUE
22
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS4. Revision of CMACs guidelines to be finalized by 2007
TACAIDS FULLY ACHIEVED
THE CMACS GUIDELINES ARE DEVELOPED /REVISED AND WILL BE DISSEMINATED TO STAKEHOLDERS 2008/09
23
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS5. HIV/AIDS Mainstreamed into the O&OD Methodology and implementation BY 2007
PMO-RALG FULLY ACHIEVED
IN COLLABORATION WITH MANY PARTNERS NOW COUNCILS ARE SUPPORTED TO MAINSTREAM HIV AND AIDS INTO THE O& OD PLANNING INSTRUMENT
24
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS6. Increase the number of CSOs accessing funds BY 2006
TACAIDS, LGAS PARTIALLY ACHIEVED
AROUND 7,500 CSOS AND CPPS THROUGH DIFFERENT FINANCING MECHANISMS RECEIVED FUNDS
25
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS7. Have a regular forums for all RFAs by 2007
TACAIDS FULLY ACHIEVED
AROUND TWO FORUMS A YEAR WITH RFAS WAS CONDUCTED TO DISCUSS THE PROGRESS OF IMPLEMENTATION
26
DISTRICT AND COMMUNITY RESPONSE …
MILESTONE RESPONSIBLE STATUS PROGRESS8. At least one functioning model WAMAC at every LGA by 2007
TACAIDS FULLY ACHIEVED
AROUND 22 WMACS IN DIFFERENT LGAS WERE ESTABLISHED AS ROLE MODEL DURING 2006/07. THE CHALLENGE IS HOW TO SUSTAIN THIS GOOD PRACTICES
FINANCE AND ADMINISTRATION
.
27
28
FINANCE AND ADMINISTRATION
MILESTONE RESPONSIBLE STATUS PROGRESS1. Mini-study on “Funds System for CSOs and Introduce systematic resource tracking and information dissemination” include in next PER, 2007
TACAIDS PARTIALLY ACHIEVED
THE MINI- STUDY ON FUNDS SYSTEMS FOR CSOS WAS CONDUCTED. HOWEVER WAS NOT INTRODUCED IN RESOURCES TRACKING IN PER , 2007 AND NOT YET DISSEMINATED
29
FINANCE AND ADMINISTRATION …
MILESTONE RESPONSIBLE STATUS PROGRESS2. Timely disbursement of funds to implementers by 2007
TACAIDS PARTIALLY ACHIEVED
DUE TO TECHNICAL REASONS SOME DISBURSEMENT CONGESTION OCCURRED WHEN MANY RFAS REQUESTED FUNDS ON SHORT PERIOD
30
FINANCE AND ADMINISTRATION …
MILESTONE RESPONSIBLE STATUS PROGRESS3. Increase of donor support on financing “budget support on HIV/AIDS” BY 2007
TACAIDS PARTIALLY ACHIEVED
•MORE FUNDS ON HIV AND AIDS ARE CHANNELED THROUGH HIV-GBS
. DURING FY 2006/07 HIV FUNDS WAS ESTABLISHED THROUGH GOVERNMENT MACHINERY : THE EXCHEQUER SYSTEMS TO LGAS. CIDA - CANADA IS SUPPORTING
31
FINANCE AND ADMINISTRATION
MILESTONE RESPONSIBLE STATUS PROGRESS4. Next round of the Global Fund should be designed using the GBS-HIV by 2007
TACAIDS NOT DONE
IT WAS RECOMMENDED BY TANZANIA NATIONAL COORDINATING MECHANISM (TNCM) THAT A STUDY TO BE CARRIED OUT BEFORE EMBARKING TO THIS PROCESS
32
FINANCE AND ADMINISTRATION
MILESTONE RESPONSIBLE STATUS PROGRESS 5.Reorganization of TACAIDS for more effective operations by 2007
TACAIDS /PSM PARTIALLY ACHIEVED
THE PROPOSED ORGANIZATION STRUCTURE HAS BEEN FINALIZED WAITING THE APPROVAL FROM PRESIDENTIAL IMPLEMENTATION COMMITTEE. TACAIDS WILL HAVE EXTENDED STRUCTURE TO THE REGIONS
ADVOCACY AND INFORMATION
.
33
34
ADVOCACY AND INFORMATION
MILESTONE RESPONSIBLE STATUS PROGRESS
1. First Lady’s HIV/AIDS campaign supported by, 2007
TACAIDS/ WAMA FULLY ACHIEVED
THE YOUTH AND CHILDREN AGE GROUPS THAT ARE COVERED IN THIS CAMPAIGNS. THE CHALLENGE IS COVERAGE AND SUSTANABILITY
35
ADVOCACY AND INFORMATION
MILESTONE RESPONSIBLE STATUS PROGRESS
2. National Advocacy and Communication strategy ( NAHACAS) disseminated and operationalised by 2007
TACAIDS FULLY ACHIEVED
NAHACAS WAS ADOPTED 2005 AND DISSEMINATION WAS DONE DURING 2007 AND WILL CONTINUE TOGETHER WITH NMSF
36
ADVOCACY AND INFORMATION
MILESTONE RESPONSIBLE STATUS PROGRESS3. Eleven Mobile Cinema Vans and theatre arts available at the community level BY 2007
TACAIDS/WB FULLY ACHIEVED
ELEVEN MOBILE CINEMA VANS
WERE PROCURED AND
DISTRIBUTED TO ELEVEN
REGIONS . TEN MORE VANS ARE ORDERED TO THE
REST OF THE REGIONS FOR COMMUNITY LEVEL MASS EDUCACTION
37
ADVOCACY AND INFORMATION
MILESTONE RESPONSIBLE STATUS PROGRESS4. National HIV/AIDS Youth and Women Campaign launched by 2007
TACAIDS NOT ACHIEVED
HOWEVER, NATIONAL WIDE YOUTH DRIVEN BEHAVIOR CHANGE CAMPAIGNS (ISHI) IS OPERATIONAL AT LIMITED SCALE IN ALL REGIONS . RURAL CAMPAIGNS IS NOW INITIATED IN 7 DISTRICTS
38
Thank you