JIGAWA STATE GOVERNMENT govt end...goes to fadama II, fadama III, Ruwasa, MDG and Emir’s lodge...
Transcript of JIGAWA STATE GOVERNMENT govt end...goes to fadama II, fadama III, Ruwasa, MDG and Emir’s lodge...
i
JIGAWA STATE GOVERNMENT
DUE PROCESS AND PROJECT MONITORING BUREAU
LOCAL GOVERNMENT UNIT
OFFICE OF THE EXECUTIVE GOVERNOR
END OF THE YEAR REPORT,2012
ii
CONTENTS
EXECUTIVE SUMMARY
CHARTS
SECTION (A) ----------------------COMPLETED PROJECTS. ................................................................................... 1 – 27
SECTION (B) ----------------------ON-GOING PROJECTS. ...................................................................................... 1 - 27
SECTION (C) ----------------------PRE-CONTRACT EVALUATION. ...................................................................... 1-27
SECTION (D) ----------------------CONTRACTS AWARDED. ................................................................................. 1-27
SECTION (E-----------------------CONTRIBUTION OF 27NO LOCAL GOVERNMENT COUNCILS
STATE/LOCAL GOVERNMENT JOINT ACCOUNT. ....................................... 1-2
SECTION (F) ---------------------APPENDIX-SECTOR BASED REPORTS. ............................................................ 1-27
ROAD/DRAINAGE PROJECTS
WATER SUPPLY PROJECTS
ELECTRIFICATION PROJECTS
BUILDING PROJECTS
iii
JIGAWA STATE GOVERNMENT
DUE PROCESS AND PROJECT MONITORING BUREAU
LOCAL GOVERNMENT UNIT
END OF YEAR REPORT JANUARY-DECEMBER, 2012
EXECUTIVE SUMMARY
In line with the governor’s statement during the year 2012 budget government is Fully Committed to the
Implementation of Annual Budget in its totality and adherence to Due process law. In the award of all government
Contracts from the point of award to the completion stage with proper documentation at all Levels.
However, with the quarterly organised seminars and workshops by the Bureau in Conjunction with the State
Partnership for Accountability, Responsiblenes and Capability (SPARC) on the operation of Due process law and
guide lines, some local government councils have made progress in compliance with the Bureau’s requirements on
contracts award and its administration.
In addition the efforts of other local government councils like; Buji, Miga, Kiyawa, Jahun, Gwiwa K/Hausa
Auyo,Gagarawa and Birniwa deserves more commendation as they always try to abide with the provision of the
Due Process Law as much as possible.
iv
This report consist of six sections, namely; Completed projects, On-going projects, Pre-contract projects
Evaluation, Contracts awarded, contribution of state/local government joint account and Appendix-Sector based
reports.
COMPLETED PROJECTS
This section contains information on projects completed 100% by each of the 27no Local government council as at
December, 2012. A total of (555 ) projects valued at N2,130,130,137.06 [Two Billion One Hundred and Thirty
Million One Hundred and Thirty Thousand, One Hundred and Thirty Naira Six Kobo only] out of
N5,000,636,524.23 being reported on, representing 43% were completed.
ON-GOING PROJECTS
This section deals with projects that have reached various stages of completion. A total of (180) projects valued at
N2,870,506,387.17 [Two Billion Eight Hundred and Seventy Million, Five Hundred and Six Thousand, Three
Hundred and Eighty Seven Naira Seventeen Kobo] out of N5,000,636,524.23 being reported on, representing 57%
were recorded as on-going.
v
PRE-CONTRACT PROJECTS EVALUATION
This section gives account of proposals presented by only 21 out of 27 Local government councils to the Bureau for
Vetting and recommendation. A total of N 1,523,598,663.83 (One Billion Five Hundred and Twenty Three Million,
Five Hundred and Ninety Eight Thousand, Six Hundred and Sixty Three Naira, Eighty Three Kobo) worth of
proposals was presented for Vetting out of which the Bureau recommends N 1,507,258,930.49. [One Billion Five
Hundred and Seven Million, Two Hundred and Fifty Eight Thousand, Nine Hundred and Thirty Naira, Forty Nine
Kobo only] there by saving a total of N 16,339,733.34 [Sixteen Million Three Hundred and Thirty Nine Thousand,
Seven Hundred and Thirty Three Naira, Thirty Four Kobo only which represents (1.08%) of the total forwarded.
Furthermore the amount forwarded for vetting N1,523,598,663.83 represent 20.17% of the total funds released
(N7,554,315,828.05) to the local government councils, out of the total sum budgeted for capital expenditure(N16.23
billion) in the year 2012.
CONTRACT AWARDED
This section deals with Capital projects awarded by the 27no.Local government councils, and all information in this section were made available to the Bureau by the local councils through the Ministry for Local government to the Bureau and Verified within 2012 financial year. Contract worth N 2,744,485,214.,27 (Two Billion, Seven Hundred and Forty Four Million, Four Hundred and Eighty
Five Thousand, Two Hundred and Fourteen Naira, Twenty Seven kobo) were awarded by 27No Local government
councils.
vi
CONTRIBUTION OF 27 LOCAL GOVERNMENT COUNCIL TO STATE/LOCAL GOVERNMENT JOINT ACCOUNT.
The state and local government joint account as approved by the Law has impacted positively to the development
and uplifted the local government status within the year under review.
The total sum of N 4,809,830,613.78 was contributed by all the 27no Local government councils various out of which N4,212,000,000.00 goes to state and local government joint account, while the balance of N597,830,613.78 goes to fadama II, fadama III, Ruwasa, MDG and Emir’s lodge (additional work). See attached Appendix. Some of the major projects executed from the joint account includes:-
1. Rehabilitation and asphalt overlay of Achilafiya – Dandi road.
2. Construction of Hadejia – Garin Gabas road
3. Construction of Kafin Hausa – Ruba – Sabon Sara - Bulangu road
4. Construction of Yar’ Kirya – Kuzunzumi road.
5. Rehabilitation of Kwanar Auyo – Kafin Hausa road
6. Construction of 9km road at Tudun – Kano yamma.
7. Construction of Malam Madori – Dolen kwana – Garin Gabas – Birniwa road.
8. Asphalt overlay of Miga township road.
9. Construction of Malam Madori – Munkawo – Garin Gabas - Birniwa road.
10. Construction of Birnin Kudu – Sundumina – Kiyawa road.
11. Construction of Dawadi – Hammado sule Tankarkar.
vii
APPENDIX –SECTOR BASED REPORT
In this section the whole projects executed by 27 No. local government councils were categorized into 4 sectors,
namely; Road sector, Water supply sector, Electrical sector and Building sector. Relevant Charts were made
available to show the performance of local governments based on sector report.
OBSERVATION
The following observations are critically been made on the following impending bottleneck that effect the
implementation of capital projects been executed by the 27 Local government councils in the state.
Some of the local Government Councils are awarding contracts without proper documentation and
compliance with Due process review and certification before any payments is made.
The number of on-going projects in all the 27No. Local government councils are increasingly accumulating
year by year which this trend will clearly result a great danger of abandoning some projects at long last.
Some Local government councils do not forward the details of their capital projects to the Bureau for vetting
despites the Due process Law provision that stipulated that all capital projects above N5,000,000.00 should be forwarded for vetting and advise e.g. Dutse, Hadejia, Kaugama, Kirikassama, Maigatari and Sule Tankarkar local government councils.
viii
RECOMMENDATION Ministry for local government in conjunction with Due Process and project Monitoring bureau (DP&PMB)
should be organizing workshops for local government officials on project documentation procedure atleast twice a year .
All local government councils should endeavor to make prompt payment to the contractors when due to enable the completion of projects within the stipulated contract period.
The Honorable commissioner ministry for Local government should draw the attention of defaulting Local government Chairmen on the Failure to Comply with all the provision of Due process Law constitutes an offence in the state.
CONCLUSION
In conclusion, the above observations need to be adequately addressed, in order to enable the Bureau to work
effectively and efficiently according to stipulated Due process guidelines. The attention of defaulting local
government council chairmen should be drawn again to comply with Due process guidelines and Laws.
................................................................... .............................................................
JIBRIN KAWU ADO HUSSAINI (MON)
DIRECTOR LOCAL GOVERNMENT UNIT DIRECTOR GENERAL
ix
S/N LOCAL GOVERNMENT Completed (N) On-going (N) Total (N)
1 AUYO 36,184,928.50 137,897,611.77 174,082,540.27 9 11
2 BABURA 34,150,889.14 40,317,203.17 74,468,092.31 8 9
3 BIRNIWA 150,301,764.33 119,904,810.00 270,206,574.33 33 6
4 BIRNIN KUDU 142,202,548.56 499,024,109.28 641,226,657.84 61 7
5 BUJI 114,194,849.93 144,398,197.36 258,593,047.29 22 11
6 DUTSE 36,878,231.26 191,051,305.66 227,929,536.92 12 11
7 GARKI 30,820,000.00 41,895,637.83 72,715,637.83 6 4
8 GAGARAWA 51,082,207.00 49,107,860.39 100,190,067.39 18 2
9 GUMEL 70,591,994.78 154,825,670.84 225,417,665.62 8 7
10 GURI 65,683,274.78 98,172,064.86 163,855,339.64 43 5
11 GWARAM 146,835,203.14 450,302,217.59 597,137,420.73 17 9
12 GWIWA 188,537,060.37 41,217,585.44 229,754,645.81 214,376,028.30 48 5
13 HADEJIA 36,310,247.77 - 36,310,247.77 18
14 JAHUN 118,132,402.14 41,389,775.98 159,522,178.12 19 4
15 KAUGAMA 36,780,436.00 132,446,350.68 169,226,786.68 5 7
16 KAFIN-HAUSA 32,371,027.00 89,882,267.54 122,253,294.54 14 13
17 KAZAURE 27,156,515.25 34,940,369.47 62,096,884.72 6 6
18 KIRI-KASAMMA 169,521,846.59 10,413,043.00 179,934,889.59 49 1
19 KIYAWA 91,955,932.63 71,828,182.96 163,784,115.59 58 16
20 MALAM-MADORI 28,550,800.00 22,897,796.46 51,448,596.46 5 3
21 MAIGATARI 113,791,782.22 32,867,053.25 146,658,835.47 20 3
22 MIGA 157,790,611.51 38,789,695.52 196,580,307.03 41 2
23 RINGIM 33,906,752.33 11,916,794.30 45,823,546.63 5 2
24 RONI 45,535,301.66 57,923,004.52 103,458,306.18 15 10
25 SULE-TANKARKAR 20,000,000.00 97,056,798.42 117,056,798.42 2 9
26 TAURA 39,337,031.55 103,236,652.75 142,573,684.30 4 9
27 YANKWASHI 111,526,498.62 156,804,328.13 268,330,826.75 9 8
TOTAL 2,130,130,137.06 2,870,506,387.17 5,000,636,524.23
555 180
COMPLETED PROJECT ON GOING PROJECT
2,130,130,137.06 2,870,506,387.17
SUMMARY SHEET
x
CHARTS
SHOWING PROJCTS PERFORMANCE
JANUARY – DECEMBER, 2012
xi
COMPLETED PROJECT43%
ON GOING PROJECT57%
Chart showing Completed and On-going projectJanuary - December, 2012
for 27No local Government Council
xii
36
,18
4,9
28
.50
34
,15
0,8
89
.14
15
0,3
01
,76
4.3
3
14
2,2
02
,54
8.5
6
11
4,1
94
,84
9.9
3
36
,87
8,2
31
.26
30
,82
0,0
00
.00
51
,08
2,2
07
.00
70
,59
1,9
94
.78
65
,68
3,2
74
.78
14
6,8
35
,20
3.1
4
18
8,5
37
,06
0.3
7
36
,31
0,2
47
.77
11
8,1
32
,40
2.1
4
36
,78
0,4
36
.00
32
,37
1,0
27
.00
27
,15
6,5
15
.25
16
9,5
21
,84
6.5
9
91
,95
5,9
32
.63
28
,55
0,8
00
.00
11
3,7
91
,78
2.2
2
15
7,7
90
,61
1.5
1
33
,90
6,7
52
.33
45
,53
5,3
01
.66
20
,00
0,0
00
.00
39
,33
7,0
31
.55
11
1,5
26
,49
8.6
2
13
7,8
97
,61
1.7
7
40
,31
7,2
03
.17
11
9,9
04
,81
0.0
0
49
9,0
24
,10
9.2
8
14
4,3
98
,19
7.3
6
19
1,0
51
,30
5.6
6
41
,89
5,6
37
.83
49
,10
7,8
60
.39
15
4,8
25
,67
0.8
4
98
,17
2,0
64
.86
45
0,3
02
,21
7.5
9
41
,21
7,5
85
.44
-
41
,38
9,7
75
.98
13
2,4
46
,35
0.6
8
89
,88
2,2
67
.54
34
,94
0,3
69
.47
10
,41
3,0
43
.00
71
,82
8,1
82
.96
22
,89
7,7
96
.46
32
,86
7,0
53
.25
38
,78
9,6
95
.52
11
,91
6,7
94
.30
57
,92
3,0
04
.52
97
,05
6,7
98
.42
10
3,2
36
,65
2.7
5
15
6,8
04
,32
8.1
3
BAR CHART SHOWING COMPLETED AND ON-GOING PROJECTSFOR THE 27NO LOCAL GOVERNMENT COUNCILS
JANUARY - DECEMBER, 2012.
Completed (N) On-going (N)
xiii
SECTION (A)
COMPLTED PROJECT
JANUARY – DECEMBER, 2012
xiv
AUYO L.G
POST CONTRACT PROJECT EVALUATION AUYO LOCAL GOVERNMENT
S/N HEAD PROJECT EXECUTO
R LOCATION CONTRACT REVISED
COMMENCEMEN
T STAT
US REMARKS
AMOUNT(N) CONTRACT SUM
(N) DATE IN %
1 6001/4 Up-grading of water works
Limis Brother Guyu
5,253,900.25 5,253,900.25
26/4/2012 100 Completed
2 6001/4 Replacement of solar panel
Limis Brother Unik
1,338,750.00 1,338,750.00
26/4/2012 100 Completed
3 5004/4 construction of mosque
A Shuaib Dogo Gatafa
1,084,594.50 1,084,594.50 4/4/2012 100 Completed
4 5004/4 construction of mosque
M. Ali M/shayi Wailare
1,084,594.50 1,084,594.50 4/4/2012 100 Completed
5 5004/4 construction of mosque
Hassan Hassan D/marke
1,084,594.50 1,084,594.50 4/4/2012 100 Completed
6 5004/4 construction of mosque
Muhd fagaci Adaha
1,084,594.50 1,084,594.50 4/4/2012 100 Completed
7 7001/1
0 purchase of official vehicle
M B U Motors Auyo
5,500,000.00 5,500,000.00
14/2/2012 100 Completed
8 7001/1
1 Purchase of Official Vehicles.
M B U Motors Auyo
14,500,000.00 14,500,000.00
14/2/2012 100 Completed
9 6001/4 Up-grading of water works
Limis Brothers Hakudau
5,253,900.25 5,253,900.25
14/2/2012 100 Completed
TOTAL 36,184,928.50 36,184,928.50
xv
BABURA LG
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT(N) CONTRACT
SUM (N) DATE IN %
1 5004/2 Construction of Friday Prayer Mosque Inusa Mati
Kunyafa Village
3,004,000.00
3,004,000.00 11/4/2012 100 Completed
2 5004/2 Construction of Friday Prayer Mosque Sani Musa
Malamawa Village
3,004,000.00
3,004,000.00 28/6/2012 100 Completed
3 5001/9
Islamiyya Schools construction of 1 class room Blocks
A Amadu Lamntani Laminfeni
3,640,670.00
3,640,670.00 11/4/2012 100 Completed
4 5004/2 Nomadic School A Audu Garu Ungu
Tsamiya 3,126,219.14
3,126,219.14 11/4/2012 100 Completed
5 6004/7
Construction of complete motorize water scheme Tijjani Habu
Babura kudu
876,000.00
876,010.00 7/3/2012 100 Completed
6 5004/2 Construction of 5 daily prayer mosque Haladu Gatuta Indurkuba
500,000.00
500,000.00 12/4/2012 100 Completed
7 7001/10 Purchase of official vehicle for chairman M B U Motors Babura
5,500,000.00
5,500,000.00 14/2/2012 100 Completed
8 7001/11
Purchase of official vehicle for Vice chairman, secretary and House Leader M B U Motors Babura
14,500,000.00
14,500,000.00 14/2/2012 100 Completed
TOTAL 34,150,889.14
34,150,899.14
xvi
BIRNIWA LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT COMMENCEMENT STATUS REMARKS AMOUNT(N) DATE IN %
1 6001/1 CONSTRUCTION OF M/ WATER SCHEME
LIMIS BROTHERS DIGINSA
12,420,757.28
12,420,757.28 27/12/2012 100 COMPLETED
2 6001/1 CONSTRUCTION OF M/ WATER SCHEME COROM KARILLA
12,420,757.28
12,420,757.28 27/12/2012 100 COMPLETED
3 CONSTRUCTION OF M/ WATER SCHEME
LIMIS BROTHERS KANDIL WURIYA
12,420,757.28
12,420,757.28 27/12/2012 100 COMPLETED
4 4006/1 ELECTRIFICATION PROJECT TURABU
CONSTRUCTION DAGU; FANI 14,653,125.86
14,653,125.86 12/2/2012 100 COMPLETED
5 6001/7 PURCHASE OF H/ PUMP MATERIALS
DIRECT LABOUR BIRNIWA
3,000,000.00
3,000,000.00 15/5/2012 100 COMPLETED
6 5007/3 IMPROVEMENT OF FRIDAY MOSQUE
SABURU GEN ENT DIGINSA
6,100,000.00
6,100,000.00 1/1/2012 100 COMPLETED
7 6001/2 DRILLING OF HAND PUMP DAN HADEJIA
NIG LTD GGASS
BIRNIWA 400,000.00
400,000.00 16/2/2012 100 COMPLETED
8 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD MAINARI 200,000.00
200,000.00 16/2/2012 100 COMPLETED
9 6001/2 DRILLING OF HAND PUMP IBRAHIM KACHAL M MAI ALLO
200,000.00
200,000.00 16/2/2012 100 COMPLETED
10 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD AREMARI 200,000.00
200,000.00 16/2/2012 100 COMPLETED
11 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD TUKU 200,000.00
200,000.00 16/2/2012 100 COMPLETED
12 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD SUKURINA 200,000.00
200,000.00 16/2/2012 100 COMPLETED
13 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD JALLARI 200,000.00
200,000.00 16/2/2012 100 COMPLETED
14 6001/2 DRILLING OF HAND PUMP I KACHALLA
NJG LTD K/INKIWA AREWA
200,000.00
200,000.00 16/2/2012 100 COMPLETED
15 6001/2 DRILLING OF HAND PUMP I KACHALLA NIG
LTD INKIWA
TSANGAYA 1,000,000.00
1,000,000.00 16/2/2012 100 COMPLETED
16 7001/7 PAYMENT OF LAND COMPENSATION LAND OFFICER BIRNIWA
1,100,000.00
1,100,000.00 15/3/2012 100 COMPLETED
17 7001/10 PURCHASE OF GULF 10 BUS DIRECT BIRNIWA 10/9/2012 100 COMPLETED
xvii
LABOUR 1,100,000.00 1,100,000.00
C/F 66,015,397.70
66,015,397.70
B/F 66,015,397.70
66,015,397.70
18 5003/1 REHABLITATION OF FM RADIO DIRECTOR
JIGAWA RADIO BIRNIWA 3,606,955.10
3,606,955.10 25/5/2012 100 COMPLETED
19 6001/1 CONSTRUCTION OF M/ WATER SCHEME
A.D.Z GLOBAL NIG. LTD KABIWA
12,420,757.28
12,420,757.28 11/4/2012 100 COMPLETED
20 4006/1 ELECTRIFICATION PROJECT TURABU
CONSTRUCTION BURSALI 17,246,843.86
17,246,843.86 13/10/2012 100 COMPLETED
21 5007/4 COMPLETION OF KANYA MOSQUE SADUMU I NIG
LTD KANYA 4,578,234.48
4,578,234.48 13/10/2012 100 COMPLETED
22 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD DAGIL FARI
400,000.00
400,000.00 8/4/2012 100 COMPLETED
23 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD KIRYA
400,000.00
400,000.00 11/4/2012 100 COMPLETED
24 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD FULATANAN
400,000.00
400,000.00 11/4/2012 100 COMPLETED
25 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD KUPSA
400,000.00
400,000.00 11/4/2012 100 COMPLETED
26 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD GORIBA
400,000.00
400,000.00 11/4/2012 100 COMPLETED
27 5007/4 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD BULAMA LUM
400,000.00
400,000.00 11/4/2012 100 COMPLETED
28 7002/1 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD BIRNIWA
2,648,874.69
2,648,874.69 24/4/2012 100 COMPLETED
29 7002/1 RENOVATION OF LG STAFF QTRS Musa Yille Nig.
LTD BIRNIWA 2,396,565.58
2,396,565.58 6/12/2012 100 COMPLETED
30 6001/1 CONSTRUCTION OF MOTORISED WATER SCHEME
LIMIS BROTHERS LTD BEGUWA
10,664,829.82
10,664,829.82 21/11/2012 100 COMPLETED
31 6001/1 CONSTRUCTION OF MOTORISED WATER SCHEME
LIMIS ROTHERS LTD WALAWA
11,323,305.82
11,323,305.82 4/2/2012 100 COMPLETED
32 7001/10 PURCHASE OF OFFICIAL VEHICLE FOR CHAIRMAN MBU Motors BIRNIWA
5,500,000.00
5,500,000.00 14/2/2012 100 COMPLETED
33 7001/11 PURCHASE OF OFFICIAL VEHICLE FOR V CHAIRMAN, SEC MBU Motors BIRNIWA
11,500,000.00
11,500,000.00 14/2/2012 100 COMPLETED
xviii
TOTAL TOTAL
150,301,764.33 150,301,764.33
BIRNIN KUDU LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS REMARKS
AMOUNT (N) CONTRACT SUM DATE IN %
1 5001/1 SUPPLY OF MATRESS ABDULLAHI
YUNUSA LEA 2,621,000.00
2,621,000.00 21/6/12 100 Completed
2 2009F/7 RENOVATION OF JUMAAT MOSQUE
A MOHD MAIGORO INJIWAWA
629,644.00
629,644.00 5/6/2012 100 Completed
3 4006/1 ELECTRIFICATION PROJECT PHASE I
COMPETENCY NIG LTD SHAWU
2,892,198.20
2,892,198.20 18/5/12 100 Completed
4 4006/1 ELECTRIFICATION PROJECT PHASE II
COMPETENCY NIG LTD SHAWU
1,763,375.00
1,763,375.00 18/5/2012 100 Completed
5 4006/1 ELECTRIFICATION PROJECT PHASE I
ALH. USAINI DUNI DANGOLI
1,944,824.00
1,944,824.00 12/o6/12 100 Completed
6 4006/1 ELECTRIFICATION PROJECT PHASE II
ALH. USAINI DUNI DANGOLI
1,416,029.00
1,416,029.00 18/5/12 100 Completed
7 4006/1 ELECTRFICATION PROJECT ALH. YAHAYA
INUWA SHUNGURIN 2,266,742.00
2,266,742.00 18/5/12 100 Completed
8 4006/1 ELECTRFICATION PROJECT ALH. JAMILU
SALE IGGI/UY 2,892,198.00
2,892,198.00 18/5/12 100 Completed
9 4006/1 ELECTRFICATION PROJECT ALH IBRAHIM
NATAJO KAGADAMA 2,062,289.60
2,062,289.60 18/8/12 100 Completed
10 2009B/7 EARTH FILLING ALH SAIDU ZAZIKA 1,861,552.00
1,861,552.00 20/12/12 100 Completed
11 4006/1 ELECTRFICATION PROJECT ALH DAHIRU
DATTI WARWADE 457,296.00
457,296.00 18/5/12 100 Completed
12 2009B/7 INSTALLATION OF CCTV CAMERA
CHAIMAN OFFICE
2,625,280.00
2,625,280.00 17/5/12 100 Completed
13 2007/1 CONSTRUCTION OF WAITING SHED JINJIRI KANGIRE KANGIRE
280,000.00
280,000.00 29/2/12 100 Completed
xix
14 2009F/7 COMPLETION OF BIHSA SECRETARIATE A MAGAJI FAWA B/KUDU
816,783.00
816,783.00 14/5/12 100 Completed
15 2009F/7 FLOORING OF ISLAMIYYA SCHOOL
MAMAJI SHUAIBU
IHIYUSSUNNA
ISLAMIYYA 229,426.00
229,426.00 30/1/12 100 Completed
16 2009F/7 COMPLETION OF DAILY PRAYER MOSQUE
MAIUNGUWA SULE ODOJI
84,000.00
84,000.00 20/5/11 100 Completed
17 2009/7 CONSTRUCTION OF DOUBLE CULVERT
A AMADU MAI KATAKO DOKOKI
2,377,000.00
2,377,000.00 1/11/2012 100 Completed
C/F 27,219,636.80
27,219,636.80
4a
B/F 27,219,636.80
27,219,636.80
18 6001/3 CONSTR. 6M PRESS STEEL TOWER TANK
MAMUDA MASAYA MASAYA
2,970,000.00
2,970,000.00 15/6/12 100 Completed
19 2007C/13 SUPPLY OF SANITATION MATERIAL
MUTARI IBRAHIM
WASH DEPT
451,500.00
451,500.00 6/11/2012 100 Completed
20 4006/1 SUPPLY & INSTALLATION OF I CCTV DOOR
GOLDEN ELECTRICAL
OFFIICE OF CHAIRMAN
1,000,715.52
1,000,715.52 29/2/12 100 Completed
21 2009B/7 REPAIRS OF TOYOTA OFFICIAL VEHICLE
AHMAD ALI GANTSA
OFFIICE OF CHAIRMAN
1,205,000.00
1,205,000.00 3/4/2012 100 Completed
22 6004/1 CONSTRUCTION OF WALL FENCE
A AMADU MAI KATAKO
BLIND CENTER
2,488,443.00
2,488,443.00 14/12/12 100 Completed
23 4006/1 ELECTRFICATION PROJECT
ALHAJI DAN JAURO INJUWAWA
1,865,655.00
1,865,655.00 18/5/12 100 Completed
24 2009B/7 EARTHFILLING A AMADU MAI
KATAKO DOKOKI 2,861,712.00
2,861,712.00 11/11/2012 100 Completed
25 2009F/7 RENOV. OF U/SHARIA COURT JUDGE HOUSE
ABUBAKAR SULEIMAN B/KUDU
470,000.00
470,000.00 17-5-12 100 Completed
xx
26 2009F/7 RENOVATION OF JISIEC OFFICE
ABDULLAHI GAMBO OVER B/KUDU
748,330.00
748,330.00 15-2-12 100 Completed
27 7001/5 PURCHASE OF PEUGEOT VEHICLE MBU MOTORS
OFFIICE OF CHAIRMAN
5,500,000.00
5,500,000.00 14-5-12 100 Completed
C/F 46,780,992.32
46,780,992.32
4b
B/F 46,780,992.32
46,780,992.32
28 6004/1 CONSTRUCTION OFJUMAAT MOSQUE
GARBA UMAR CHANGE
3,269,768.60
3,269,768.60 18-5-12 100 Completed
29 2006A/9 PAYMENT OF SCHOLARSHIP
TRASURY DEPT STUDENT
4,409,000.00
4,409,000.00 25-6-12 100 Completed
30 6004/1 INTERLOCKING OF CENTRALMOSQUE
LAMU & BABALDU NIG. LTD B/KUDU
19,000,000.00
19,000,000.00 16-11-12 100 Completed
31 4003/4 PURCHASE & PLANTING OF SEEDLING 178KM AGRIC DEPT
B/KUDU-SUNDIMIN
A 3,740,000.00
3,740,000.00 1711-12 100 Completed
32 6004/1 RENOVATION OF DAILY PRAYER MOSQUE GAMBARA
523,932.00
523,932.00 20-12-12 100 Completed
33 2009B/7 EARTH FILLING
ABDULKARIM AUYO
Plantation Road B/K
182,000.00
182,000.00 3/10/2012 100 Completed
34 6004/1 CONSTRUCTION OFJUMAAT MOSQUE ALH. ADO GIWA
3,160,410.00
3,160,410.00 3/10/2012 100 Completed
35 6004/1 CONSTRUCTION OFJUMAAT MOSQUE
ALH. AMADU M/KATAKO BUDUSU 4,319,292.92 4,319,292.92 24-3-11 100 Completed
36 6004/1 CONSTRUCTION OFJUMAAT MOSQUE
ABDULLAHI YUNUSA TUKUDA 2,036,222.00 2,036,222.00 24-3-11 100 Completed
xxi
37 6004/1 CONSTRUCTION OFJUMAAT MOSQUE
ALHAJI MAGAJI FAWA MASARU 1,315,005.72 1,315,005.72 24-3-11 100 Completed
38 7001/3 LAND COMPENSATION
GDASS B/KUDU
SUNDRY PERSON 10,710,000.00 10,710,000.00 4/3/2011 100 Completed
39 7001/3 LAND COMPENSATION
SUNDRY PERSON
GJSS Chiyako 583,000.00 583,000.00 4/12/2012 100 Completed
40 7001/3
LAND COMPENSATION OF UNCOMPLETED BUILDING
SUNDRY PERSON
KIYAKO HEALTH
POST 583,725.00 583,725.00 4/12/2012 100 Completed
41 2009/7
COMPENSATION OF UNCOMPLETED BUILDING
ALH. ISAH B/KUDU B/KUDU 761,250.00 761,250.00 8/5/2012 100 Completed
C/F 101,374,598.56 101,374,598.5
6
4c
B/F 101,374,598.56 101,374,598.5
6
42 2009/7 RENOVATION OF HOD WORKS HOUSE
ABDUL HAMID
HAMMADA
STAFF QTRS
B/KUDU 1,911,000.00 1,911,000.00 15/6/12 100 Completed
43 7001/16
PURCHASE OF VEHICLE [HAIHUWA LAFIYA]
KAFILU U ABUBAKAR B/KUDU 937,000.00 937,000.00 7/7/2012 100 Completed
44 7001/16 PURCHASE OF TOYOTA HILUX
UMAR ISYAKU B/KUDU 2,998,500.00 2,998,500.00 18/12/12 100 Completed
45 2009/3 PAYMENT OF HOUSE RENT
YUGUDA DUMUS B/KUDU 500,000.00 500,000.00 11/5/2012 100 Completed
46 2009/3 PAYMENT OF HOUSE RENT
YUSIF USMAN B/KUDU 300,000.00 300,000.00 20/11/12 100 Completed
xxii
47 2009/3 PAYMENT OF HOUSE RENT
ALH. ZUBAIRU
IMAM B/KUDU 200,000.00 200,000.00 20/11/12 100 Completed
48 2009B/7 REPAIRS OF PRISON VEHICLE
ALH. BABA D/HAYA B/KUDU 355,000.00 355,000.00 17/10/12 100 Completed
49 2007C/1
3 SUPPLY OF H/P MATERIALS
MOHD YAHAYA
B/KUDU W/BOARD 3,265,360.00 3,265,360.00 17/9/12 100 Completed
50 2007C/1
3 PAYMENT H/P MATERIALS
AMINU MAGAJI B/KUDU 1,704,000.00 1,704,000.00 7/5/2012 100 Completed
51 2007C/1
3 SUPPLY OF DIESEL HAJ. SADIYA
ADAMU B/KUDU 1,750,000.00 1,750,000.00 23/5/12 100 Completed
52 2007C/1
3 SUPPLY OF DIESEL SUNDRY PERSON B/KUDU 1,501,500.00 1,501,500.00 31/5/12 100 Completed
C/F 116,796,958.56 116,796,958.5
6
4d
B/F 116,796,958.56 116,796,958.56
53 2007A/13 PURCHASE OF DRUGS MOHD KABIR
IBRAHIM B/KUDU 1,892,450.00 1,892,450.00 10/10/2012 100 Completed
54 2007B/13 PURCHASE OF DRUGS A MAGAJI
FAWA B/KUDU 1,489,140.00 1,489,140.00 3/5/2012 100 Completed
55 2007A/13 SUPPLY SANITATION MATERIALS
MUKTAR MUSA ZUBAIR B/KUDU 4,515,000.00 4,515,000.00 14/8/12 100 Completed
56 2008C/13 LIVESTOCK VACCINATION MUSA IDRIS B/KUDU 810,000.00 810,000.00 29/2/12 100 Completed
57 2008A/13 Tractor Repairs AHMAD SARKI
UBA B/KUDU 810,000.00 810,000.00 29/2/12 100 Completed
58 2008A/13 PUR. & DISTRIBUTION OF SEEDS JASCO STORE B/KUDU 582,000.00 582,000.00 12/6/2012 100 Completed
59 2008B/13 DEMARCATION OF GRASING RESERVE
MUKTAR MUSA ZUBAIR
SHAHURERE 457,000.00 457,000.00 11/9/2012 100 Completed
xxiii
60 2008B/13 DEMARCATION OF GRASING RESERVE
MUKTAR MUSA ZUBAIR DANMADIGA 350,000.00 350,000.00 2/10/2012 100 Completed
61 7001/11 PUR. OF OFFICIAL VEHICLE FOR VC, SEC MBU Motors B/KUDU 14,500,000.00 14,500,000.00 14/2/12 100 Completed
TOTAL 142,202,548.56 142,202,548.56
DUTSE LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR
LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS
REMARKS
AMOUNT CONTRACT
SUM DATE IN %
1 5002/2 Construction of V.I.P Toilet NPI
Office 256,912.89 256,912.89 9/11/2012 100 Completed
2 4006/1 Electrification project Galadimawa
ventures Fanisa
u 7,889,773.84 7,889,773.84 3/9/2012 100 Completed
3 5004/2 Construction of Friday mosque Sale chaichai Kyaran 5,455,639.03
5,455,639.03 3/9/2012 100 Completed
4 6001/4 Drilling of 20no Borehole Mr moses Galadi
ma 1,300,000.00
1,300,000.00 19/9/2012 100 Completed
5 7002/4 Construction of Engine room Alkali Sakwaya Galadi
ma 554,468.00
554,468.00 4/12/2012 100 Completed
6 6001/3 Repairs of Solar Borehole Prestige Nig
Ltd
Dundu
bus 284,287.50
284,287.50 14/2/2012 100 Completed
7 6001/3 Repairs of Solar Borehole Prestige Nig
Ltd
Chamo 284,287.50
284,287.50 14/2/2012 100 Completed
8 6001/3 Repairs of Solar Borehole Prestige Nig
Ltd K/Fada 284,287.50
284,287.50 14/2/2012 100 Completed
9 6001/3 Repairs of Solar Borehole Prestige Nig
Ltd
Madobi 284,287.50
284,287.50 14/2/2012 100 Completed
xxiv
10 6001/3 Repairs of Solar Borehole Prestige Nig
Ltd Duju 284,287.50
284,287.50 14/2/2012 100 Completed
11 7001/1
0 Purchase of official vehicle to chairman peugeot 408 MBU Motors Dutse 5,500,000.00
5,500,000.00 14-2-2012 100 Completed
12 7001/1
1 Purchase of official vehicle to chairman peugeot 408 MBU Motors Dutse 14,500,000.00
14,500,000.00 14-2-2012 100 Completed
TOTAL 36,878,231.26 36,878,231.26
BUJI LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM DATE IN %
1 5004/2 Contr. Of Friday Mosque Yayarin Tukur Nig
LTD Kukuma
11,286,056.11
11,286,056.11 23-8-12 100 Completed
2 6001/3
Improvement of Water Supply at YayarinTttukur
Water and Waste Water Nig LTD
Yayarin Tukur
6,119,897.16
6,119,897.16 15-6-12 100 Completed
3 6001/3 Improvement of Water Supply at Buji Town
Water and Waste Water Nig LTD Buji Town
10,989,934.31
10,989,934.31 15-6-12 100 Completed
4 6001/2 Drilling of 10 Hand Pump across to ten wards Y tec invt Nig LTD 10 Wards
6,981,502.50
6,981,502.50 15-6-12 100 Completed
5 6001/3 Complete Motorize Water Scheme at Gantsa kudu Y tec invt Nig LTD
Gantsa kudu
13,242,939.93
13,242,939.93 15-6-12 100 Completed
6 5004/2 Construction of Juma'at Mosque at Lelan Kudu Gwadayi Nig LTD Lelen kudu
11,286,051.11
11,286,051.11 15-6-12 100 Completed
7 4007/2 Construction of Market Stalls at Gantsa
Baffa TO & Mato Kaliya Gantsa
1,282,853.62
1,282,853.62 18-7-12 100 Completed
8 5002/2 Constructioon of Pit Latarine Alh. Tasiu Kanini PHC
Gantsa
797,998.42
797,998.42 18-7-12 100 Completed
xxv
9 5002/2 construction of complete motorized water scheme Dalwa Nig LTD Kawayo
11,923,261.25
11,923,261.25 18-7-12 100 Completed
10 5004/5 Construction of 5 Daily Prayer
Mosque Garba & Others Kwalele
836,181.13
836,181.13 11/12/2012 100 Completed
11 5004/5 Construction of 5 Daily Prayer
Mosque Danyaro & Others Rigar Gada
836,181.13
836,181.13 11/12/2005 100 Completed
12 5004 Construction of 5 Daily Prayer
Mosque Iduka & Others Gambasha
836,181.13
836,181.13 11/12/2012 100 Completed
13 5004/5 Construction of 5 Daily Prayer
Mosque Iduka & Others Jata
836,181.13
836,181.13 11/12/2012 100 Completed
C/F 77,255,218.93
77,255,218.93
5a
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM DATE IN %
B/F 77,255,218.93
77,255,218.93
14 6002/1 Construction of Drianage at Gwadayi Imamu Gwadayi Gwadayi
63,710.00
63,710.00 19-9-12 100 Completed
15 6002/1 Construction of Drinage at Buji Ali buji Buji
Town
327,313.00
327,313.00 1/8/2012 100 Completed
16 6001/3 Construction of Complete Motorized Water Scheme
Water and Waste Water Nig LTD Karanjau
1,370,261.00
1,370,261.00 5/9/2012 100 Completed
xxvi
17 4007/2 Construction of Market Stalls Alhaji Jibrin zangi Gantsa
11,426,445.00
11,426,445.00 23-8-12 100 Completed
18 4007/2 Construction of Market Stalls
Alhaji boloko / Shuhu
haummu/musa musa Gwadayi
1,250,634.00
1,250,634.00 11/12/2012 100 Completed
19 4007/2 Construction of Market Stalls Ibrahim Nuhu and
other Buji
1,250,634.00
1,250,634.00 11/12/2012 100 Completed
20 4007/2 Construction of Market Stalls Inuwa Wanzan
and others Sago
1,250,634.00
1,250,634.00 11/12/2012 100 Completed
21 7001/10 Purchase Vihicle Peugeot 408 for Chaiman MBU Motors Buji
5,500,000.00
5,500,000.00 11/12/2012 100 Completed
22 7001/11
Purchase of Official Vihicle for Vice Chairman Secretary Council Leader MBU Motors Buji
14,500,000.00
14,500,000.00 14/2/2012 100 Completed
TOTAL 114,194,849.93
114,194,849.93
GARKI LOCAL GOVERNMENT
POST CONTRACT PROJECT
xxvii
EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT
SUM (N) DATE IN %
1 6001/3 Construction of hand pump 6No. direct labour
G/ganji/Asayaya/Saban gari/Tagwaye
1,000,000.00
1,000,000.00 28-12-12 100 Completed
2 6001/1 Purchase of 20kva Generator
Lawan babande Gumba
2,500,000.00
2,500,000.00 5/5/2012 100 Completed
3 6001/1 Purchase of 27KVAGenerator Alhaji umaru Kore
2,820,000.00
2,820,000.00 2/5/2012 100 Completed
4 6001/2 Purchase of Hand Pump materials direct labour Kore
4,500,000.00
4,500,000.00 17-6-2012 100 Completed
5 7001/10
Purchase of official vehicle to chairman peugeot 408
MBU Motors Garki
5,500,000.00
5,500,000.00 14-2-2012 100 Completed
6 7001/11
purchase of official vehicle to vice chairman secretary house leader MBU Motors Garki
14,500,000.00
14,500,000.00 14-2-2012 100 Completed
TOTAL 30,820,000.00
30,820,000.00
xxviii
GAGARAWA LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED
CONTRACT COMMENCEMENT STATUS REMARKS
(N) SUM DATE IN %
1 6001/7 Supply of hand pump materials Direct labour Across the
10No Wards 3,000,000.00
3,000,000.00 5/3/2012 100 Completed
2 6001/7 Purchase of 20KVA water pump Generator
Muhd Dan sakoto Nig
LTD Medu 1,950,000.00
1,950,000.00 20-2-12 100 Completed
3 6001/7 Purchase of 20KVA water pump Generator
Muhd Yahaya Nig LTD Gamji
1,950,000.00
1,950,000.00 11/4/2012 100 Completed
4 6001/7 Purchase 20KVA water Generator
M sunusi ibrahim Nig.
LTD Gagarawa
Tasha 2,330,000.00
2,330,000.00 15-8-12 100 Completed
5 7001/11 Purchase of furniture to staff quarters Direct labour
GGW LG Staff
Queters 1,500,000.00
1,500,000.00 20-8-12 100 Completed
6 6001/3 Construction of new hand pump A lhaji Usman
Nig. LTD Bula 800,000.00
800,000.00 20-2-12 100 Completed
7 6001/3 Construction of new hand pump Isyaku yusif
Nig LTD Unguwaar
Liman
400,000.00
400,000.00 20-8-12 100 Completed
8 6001/3 Construction of new hand pump Isyaku yusif
Nig LTD Dan madan
Fulani
400,000.00
400,000.00 6/12/2012 100 Completed
9 6001/3 Construction of new hand pump Isyaku yusif
Nig LTD Akai Allah 400,000.00
400,000.00 6/12/2012 100 Completed
10 6001/3 Construction of new hand pump Isyaku yusif
Nig LTD Digan Fulani 430,000.00
430,000.00 6/12/2012 100 Completed
11 6001/3 Construction of new hand pump A. Isiya Ltd M/shada 400,000.00
400,000.00 9/5/2012 100 Completed
12 6001/3 Construction of new hand pump A. Isiya Ltd Gagarawa
Doni 400,000.00
400,000.00 9/5/2012 100 Completed
13 6001/3 Construction of new hand pump A. Isiya Ltd G/Tu
400,000.00
400,000.00 9/5/2012 100 Completed
14 6001/3 Construction of new hand pump Alhaji Usman G/fulani 430,000.00
430,000.00 9/5/2012 100 Completed
15 6001/3 Construction of new hand pump Alhaji Usman Maihina 1,792,207.00
1,792,207.00 9/5/2012 100 Completed
xxix
16 5004/3 Construction of Five daily prayer Mosque
Alhaji Sabo Zakar
Sarkin Gabas
5,500,000.00
5,500,000.00 16-10-12 100 Completed
17 7001/13 Purchase of official vehicle to chairman (408) MBU Motors
Gagarawa LG
14,500,000.00
14,500,000.00 16-10-12 100 Completed
18 7001/13
Purch. of official vehicle to vice chairman, secretary, council leader MBU Motors
Gagarawa LG
14,500,000.00
14,500,000.00 16-10-12 100 Completed
TOTAL 51,082,207.00
51,082,207.00
GURI LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED
CONTRACT SUM COMMENCEMENT STATUS REMARKS
AMOUNT (N) DATE IN %
1 4007/1 construction of 3 nos. market stall
A. Baya Dole Guri 2,396,836.05 2,396,836.05 27/2/2012 100 Completed
2 4007/1 construction of 3 nos. market stall
A. Adamu umar Kadira
2,396,836.05
2,396,836.05 27/2/2012 100 Completed
3 4005/2 Electrification Project A. Shu'aibu
Guri Dolen Zugo
3,057,459.48
3,057,459.48 27/2/2012 100 Completed
4 6004/2 Completion of Juma'at mosque Umar Dodo Una
1,397,905.95
1,397,905.95 27/2/2012 100 Completed
5 6004/2 Completion of Juma'at mosque Yakubu
Abunabo Yalwan Musari
1,547,067.00
1,547,067.00 27/2/2012 100 Completed
6 6003/5 Drilling of borehole and installation of hand pump.
Ngaloma Drill. Nig.
Rigar A. Baba
500,000.00
500,000.00 11/4/2012 100 Completed
xxx
Ltd
7 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar Hardo
500,000.00
500,000.00 11/4/2012 100 Completed
8 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar lamido
500,000.00
500,000.00 11/4/2012 100 Completed
9 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd
Rigar hardo labbo
500,000.00
500,000.00 11/4/2012 100 Completed
10 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar
Babale
500,000.00
500,000.00 11/12/2012 100 Completed
11 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar mai
gari
500,000.00
500,000.00 11/4/2012 100 Completed
12 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Jaggen Kadawa
500,000.00
500,000.00 11/12/2012 100 Completed
13 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Unguwar
jibrin
500,000.00
500,000.00 11/4/2012 100 Completed
14 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Kotu
500,000.00
500,000.00 11/4/2012 100 Completed
15 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar wakili
500,000.00
500,000.00 11/4/2012 100
16 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Rigar
gambo
500,000.00
500,000.00 11/4/2012 100 Completed
17 6003/5 Drilling of borehole and installation of hand pump.
Ngloma Drill. Nig.
Ltd Galadima
500,000.00
500,000.00 11/4/2012 100 Completed
C/F
16,796,104.53
16,796,104.53
10a
xxxi
B/F
16,796,104.53
16,796,104.00
18 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd
Rigar Hardo Yarima
300,000.00
300,000.00 11/4/2012 100 Comleted
19 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Taka Lafiya
300,000.00
300,000.00 11/4/2012 100 Completed
20 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Alajeri Abur
300,000.00
300,000.00 11/4/2012 100 Completed
21 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Mai Jan
ruwa
300,000.00
300,000.00 11/4/2012 100 Completed
22 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd
Zugo sabuwar unguwa
300,000.00
300,000.00 11/4/2012 100 Completed
23 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Unguwwar
Buzaye
300,000.00
300,000.00 11/4/2012 100 Completed
24 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Unguwar Buzaye
300,000.00
300,000.00 11/4/2012 100 Completed
25 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd Zuba Finj
Ariri
300,000.00
300,000.00 11/4/2012 100 Completed
26 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd G/Yamma
300,000.00
300,000.00 11/4/2012 100 Completed
27 6003/5 Construction of 1 Nos. Borehole
Ngloma Drill. Nig.
Ltd R/Isubu
300,000.00
300,000.00 11/4/2012 100 Completed
28 6003/4 Construction of solar water scheme
ADZ Nig. Ltd Dolen
8,467,082.52
8,467,082.52 27/2/2012 100 Completed
29 4007/1 Construction of market stall Mashiru $ Baba Bala
Guri $ Kadira market
3,195,781.40
3,195,781.40 27/2/2012 100 Completed
30 7002/1 Purchase of 2nos motorcycle for tamowa programme Direct Wash Dept.
250,000.00
250,000.00 20/9/2012 100 Completed
31 6004/2 Renovation of Musari Mosque Alh. Musa Musari
6,800,000.00
6,800,000.00 30/4/2012 100 Completed
32 4008/2 Dole - Wareri road culvert A. Bukar
Arin Wareri -
Dole 1,491,871,50 1,491,871,50 10/8/2012 100 Completed
xxxii
33 4008/2 Earth Filling and Culvert kasaga road
A. Bukar Arin
Kasaga Road
2,800,000.00
2,800,000.00 24/5/2012 100 Completed
C/F 41,308,968.45
41,308,968.45
10b
B/F
41,308,968.45
41,308,968.45
34 4008/2 Culvert filling Dawa Road
Alh. Hussaini
Lafiya Dawaga
Brige
1,600,000.00
1,600,000.00 16/6/2012 100% Completed
35 6001/7 Purchase of generator water pump
Lamis Nig. Ltd Arin
2,800,000.00
2,800,000.00 20/6/2012 100% Completed
36 5004/3 Purchase of fishing gear and eqipment Direct Guri
1,500,000.00
1,500,000.00 20/9/2012 100% Completed
37 4007/1 Purchase of empty sacks A. Rabui Gagiyaru
Guri L.G.A.
5,800,000.00
5,800,000.00 30/4/2012 100% Completed
38 4003/1 Tree planting materials Direct Guri
1,000,000.00
1,000,000.00 10/8/2012 100% Completed
39 6001/1 Purchase of hand pump spare parts Direct Guri
2,000,000.00
2,000,000.00 24/5/2012 100% Completed
40 4008/2
Construction of Arinijasco - Khadira culvert A. Defuru
Arinjasco Bridge
1,975,000.00
1,975,000.00 10/8/2012 100% Completed
41 404/1 Purchase of Canoe Boat Direct Guri
300,000.00
300,000.00 15/8/2012 100% Completed
42 4005/1 H.T. Work Electrification
A. Shu'aibu
Guri Dole Zugo
5,948,000.00
5,948,000.00 11/4/2012 100% Completed
43 4008/2 Construction of Culvert kasaga - margadu
A. Ibrahim margadu
Kasaga - margadu
1,451,306.33
1,451,306.33 24/7/2012 100% Completed
TOTAL
xxxiii
65,683,274.78 65,683,274.78
GUMEL LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT SUM
(N) DATE IN %
1 6003/3 Fencing of Grave Yard Idris ya'u Abuja
Queters 7,071,428.23 7,071,428.23 7/2/2012 100 Completed
2 2009/A Construction of Drainage and Culvert
Ado Dankaggi
Tudun Alhaji
Quaters 619,000.00
619,000.00 13-10-12 100 Completed
3 5001/9 Construction of Islamiyya School Babandi
Alaramma Danun Biri
1,000,000.00
1,000,000.00 17-8-11 100 Completed
4 4002/2 Construction of Slaughter House Isma'il venture Gumel
19,000,000.00
19,000,000.00 4/11/2011 100 Completed
5 2009/C Costructiion of Motorize Borehole
Murtala Dake Dantanoma
450,000.00
450,000.00 26-11-12 100 Completed
6 6003/2 Payment for Compensation for Township Road LG Gumel
22,451,566.55
22,451,566.55 14-3-12 100 Completed
7 7001/10 Purchase of Chairman Official vehicle MBU Motors Gumel
5,500,000.00
5,500,000.00 14-2-12 100 Completed
8 7001/11
purchase of vice chairman secretary council leader official vehicle MBU Motors Gumel
14,500,000.00
14,500,000.00 14-2-12 100 Completed
TOTAL
70,591,994.78
70,591,994.78
xxxiv
GWIWWA LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT
SUM DATE IN %
B/F 169,074,175.45 169,074,175.45
41 5004/2 Fencing of Friday Mosque Alh. Haruna
Salisu Guntai 1,450,000.00 1,450,000.00 20-12-12 100 Completed
42 5004/6 Construction of 5 Daily Prayer Mosque Alh. Yahaya
Sale Furtawa 1,252,419.55 1,252,419.55 18-7-12 100 Completed
43 5004/2 Wall Fencing of Friday Mosque Asa mai bulawus Hungu 2,193,613.08 2,193,613.08 11/1o/12 100 Completed
44 5004/2 Wall Fencing of Friday Mosque Alh. Ado
Kero Shafe 2,587,753.82 2,587,753.82 11/1o/12 100 Completed
45 5004/2 Construction of Friday Mosque Alto
Maidusa Kwarare 5,724,098.47 5,724,098.47 18-7-12 100 Completed
46 6001/4 Purchase of 27KVA Generating set MUSHTEK
Nig Ltd Daurawar Dan dada 2,457,500.00 2,457,500.00 18-4-12 100 Completed
47 6001/4 Purchase of 27KVA Generating set MUSHTEK
Nig Ltd Rorau
Malamai 2,457,500.00 2,457,500.00 25-8-12 100 Completed
48 6001/4 Purchase of 16KVA Generating Set HOD WASH Yola 1,340,000.00 1,340,000.00 Nov-12 100 Completed
TOTAL
188,537,060.37
188,537,060.37
xxxv
GWARAM LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT
EXECUTOR
LOCATION CONTRACT REVISED
CONTRACT SUM
COMMENCEMENT
STATUS REMARKS
AMOUNT DATE IN %
1 5004/4 Construction of Islamiyya
Alh. Samai'la Maishinkafa Zumburu
2,620,445.00
2,620,445.00 26-4-12 100 Completed
2 6001/8 purchase of hand pump materials
Alh. Samai'la Maishinkafa Gwaram
2,000,000.00
2,000,000.00 14-11-12 100 Completed
3 7001/15 purchase of furniture
Interior wood Nig LTD Kila
64,988,848.00
64,988,848.00 21-6-12 100 Completed
4 5004/1 construction of mini stadium phase 11
Bahatu Nig. Ltd Gwaram
22,000,000.00
22,000,000.00 9/6/2012 100 Completed
5 5004/1 purchase of social materials for boarding school
Direct labour Gwaram
2,000,000.00
2,000,000.00 26-9-12 100 Completed
6 5003/5 purchase of security equipment
Direct labour Gwaram
1,000,000.00
1,000,000.00 3/6/2012 100 Completed
7 6001/8 purchase of hand pump materials
Direct labour Gwaram
2,500,000.00
2,500,000.00 10/4/2012 100 Completed
8 5004/12 Renovation of Friday mosque Direct labour Salamanda
1,000,000.00
1,000,000.00 5/9/2012 100 Completed
9 6002/3 construction of drainage at casava processing factory Aya logistic Kila
6,012,239.49
6,012,239.49 9/8/2012 100 Completed
10 5003/4 repairs of Radio FM Basirrka
Royal Tel.com Nig LTD Basirka
12,500,000.00
12,500,000.00 13-5-12 100 Completed
11 7001/10 purchase of official vehicle for chairman
MBU Motors Gwaram
5,500,000.00
5,500,000.00 14-2-12 100 Completed
12 7001/11
purchase for official for vice chairman secretary concil leader
MBU Motors Gwaram
14,500,000.00
14,500,000.00 14-2-12 100 Completed
13 7001/6 Land compensation at Kila cassava processing industry Local Govt. Kila
1,617,638.00
1,617,638.00 3/5/2012 100 Completed
xxxvi
14 5001/11 Construction of Islamiyya Alhaji dalibi dingaya
2,629,646.90
2,629,646.90 15-11-12 100 Completed
15 4002/1 Construction of Slaughter House
Alhaji Mutari Sara Gwaram
3,466,385.75
3,466,385.75 22-11-12 100 Completed
16 4001/6 Puurchase of Grains Alhaji jamilu
Kila Local Govt. 1,500,000.00
1,500,000.00 23-1-12 100 Completed
17 4003/4 Road side Tree planting Local Govt. Local Govt. 1,000,000.00
1,000,000.00 25-7-112 100 Completed
Total
146,835,203.14
146,835,203.14
HADEJIA LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS REMARKS
AMOUNT CONTRACT SUM DATE IN %
1 4000/2 Animals/Cattle Vaccination Direct labour Hadejia
344,200.00
344,200.00 13-12-12 100 Completed
2 5004/2 Construction of Drainage
Alhaji Baban Jiji
L/tsamiyya Gayufa
1,623,657.75
1,623,657.75 27-3-12 100 Completed
3 2009/2
Renovation of Lockup shops (BRNT) Sadiq
Olo Motor park Hadejia
719,504.02
719,504.02 20-5-12 100 Completed
4 4001/2 River Enbakment Direct Labour Hadejia 2,440,000.00
2,440,000.00 5/5/2012 100 Completed
5 4001/2 Desilting work Direct Labour Garko
Transfomer
1,495,800.00
1,495,800.00 5/5/2012 100 Completed
6 4001/2 Desilting work Direct Labour Gagulumarito mailolo
951,750.00
951,750.00 5/5/2012 100 Completed
7 4001/2 Desilting work Direct Labour Transformer
NEPA 951,750.00
951,750.00 5/5/2012 100 Completed
8 4001/2 Desilting work Direct Labour Wuriwa Qtr 609,576.00
609,576.00 5/5/2012 100 Completed
9 4001/2 Desilting work Direct Labour Hadejia to
Majia 1,333,375.00
1,333,375.00 5/5/2012 100 Completed
xxxvii
10 4001/2 Desilting work Direct Labour Yayari Qtrs 270,874.00
270,874.00 5/5/2012 100 Completed
11 4001/2 Desilting work Direct Labour Tagurza to
K/fada
1,071,427.00
1,071,427.00 5/5/2012 100 Completed
12 4001/2 Desilting work Direct Labour K/kudu to
Tano to Atafi
1,416,285.00
1,416,285.00 5/5/2012 100 Completed
13 4001/2 Desilting work Direct Labour G/mati to Kakayi
1,067,915.00
1,067,915.00 5/5/2012 100 Completed
14 4001/2 Desilting work Direct Labour Atafi to K/zaki
1,190,280.00
1,190,280.00 5/5/2012 100 Completed
15 4001/2 Desilting work Direct Labour Hadejia 250,000.00
250,000.00 5/5/2012 100 Completed
16 4001/2 Desilting work Direct Labour Local Govt qtrs Dutse
573,854.00
573,854.00 5/5/2012 100 Completed
17 7001/1
0
Purchase of Official Vehicle for Chairman MBU Motors Hadejia
5,500,000.00
5,500,000.00 14-2-12 100 Completed
18 7001/1
1
Purchase of official Vehicle forV/Chairman Secretary & C/Leader MBU Motors Hadejia
14,500,000.00
14,500,000.00 14-2-12 100 Completed
TOTAL 36,310,247.77
36,310,247.77
xxxviii
JAHUN LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION REVISED
COMMENCEMENT
STATUS
REMARKS
CONTRACT SUM
(N) CONTRACT SUM
(N) DATE IN %
1 5004/4 Construction of five daily prayer Mosque
Alhaji Muhd Gada
Gidan Datti sabuwa 852,000.00 852,000.00 7/3/2012 100 Completed
2 5004/4 Construction of five daily prayer Mosque AM Aujara
Dinzai Gidan mai unguwa 852,000.00 852,000.00 7/3/2012 100 Completed
3 5004/4 General Renovation of Dutse Guest House Direct Labour Dutse 4,555,665.00 4,555,665.00
26/12/2012 100 Completed
4 5004/4 Construction of five daily prayer Mosque
Alhaji Abdulrazak Gora 610,000.00 610,000.00 7/3/2012 100 Completed
5 6001/7 Construction of Complete Water Scheme Engr. Abbas Tazara 13,407,705.30 13,407,705.30 16/12/12 100 Completed
6 6001/6 Up-grading & Raticulation Work Engr. Abbas 8,418,259.30 8,418,259.30 12/6/2012 100 Completed
7 6001/6 Up-grading & Raticulation Work Engr. Abbas Kulluru 2,251,136.00 2,251,136.00 12/6/2912 100 Completed
8 6001/7 Construction of Complete Water Scheme
LIMIS BROTHERS Damutawa 10,006,807.80 10,006,807.80
16/02/2012 100 Completed
9 6001/7 Construction of Complete Water Scheme
LIMIS BROTHERS Zango 11,203,946.25 11,203,946.25
16/02/2012 100 Completed
10 6001/8 Contruction. Of 50No. H/Pumps
LIMIS BROTHERS
Various Places 17,500,000.00 17,500,000.00
17/02/2012 100 Completed
11 6001/2 Construction of 15No. Open Wells Aliyu Auta
Various Places 1,620,000.00 1,620,000.00 2/3/2012 100 Completed
12 5002/2 Construction of Basic Health Clinic
Ibraco Mafrica Nig
Ltd Zango
Bagamaru 14,717,577.29 14,717,577.29 12/6/2012 100 Completed
xxxix
13 6001/8 Electrification Project
Ibraco Mafrica Nig
Ltd Sukullifi 10,680,121.20 10,680,121.20 21/12/201
2 100 Completed
C/F 96,675,218.14 96,675,218.14
14a
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION REVISED
COMMENCEMENT
STATUS
REMARKS
CONTRACT SUM
(N) CONTRACT SUM
(N) DATE IN %
B/F 96,675,218.14 96,675,218.14
14 5004/3 Interlock at Lango Friday Mosque
Ahj. Nura Zango Zango 860,000.00 860,000.00
26/12/2012 100 Completed
15 5004/4 Construction of Toilet and Renovation of NSCDC Abba Kala
NSCDC JAHUN 100 Completed
16 5004/3 Additional Work at Lautai Fiday Mosque
Biyuta Damutawa Lautai 243,000.00 243,000.00
30/07/2012 100 Completed
17 7002/6 Construction of Toilet AbdulAziz Gadawa
Aujara Out Post 354,184.00 354,184.00 100 Completed
18 7001/1
0 Purchase of official vehicle for chairman MBU Motors jahun 5,500,000.00 5,500,000.00 14-2-12 100 Completed
19 7001/1
1
Purchase of official vehicle for vice chairman, secratary and council leader MBU Motors jahun 14,500,000.00 14,500,000.00 14-2-12 100 Completed
Total 118,132,402.14 118,132,402.14
xl
KAFIN HAUSA LOCAL GOVERNMENT
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
REVISED CONTRACT
SUM COMMENCEMENT STATUS REMARKS
(N) DATE IN %
1
Complete motorize water scheme Direct labour Inkaibo
8,834,985.00
8,834,985.00 23-6-10 100 Completed
2 Drilling of Hand pump
Yayandi abubakar Gambawa
250,000.00
250,000.00 30-5-12 100 Completed
3 Drilling of Hand pump Bello Tela Sarawa
250,000.00
250,000.00 13-2-12 100 Completed
4 Drilling of Hand pump
Yaú Malamawa M/tudu
250,000.00
250,000.00 16-7-12 100 Completed
5 Drilling of Hand pump Alhaji Bubu Fadawa
250,000.00
250,000.00 3/5/2012 100 Completed
6 Drilling of Hand pump
Isa masasadi Salawa
250,000.00
250,000.00 26-1-12 100 Completed
7 Drilling of Hand pump
AalhajiYaú Malamawa Kazayare
250,000.00
250,000.00 2/2/2012 100 Completed
8 Drilling of Hand pump new quaters
Umar Mmusa
250,000.00
250,000.00 24-5-12 100 Completed
9 Drilling of Hand pump
Alhaji Adamu Mai
Biredi Maikwalbe
250,000.00
250,000.00 24-5-12 100 Completed
10 Drilling of Hand pump Isah Muhd
Jabarin Fulani
250,000.00
250,000.00 2/5/2012 100 Completed
xli
11 Drilling of Hand pump A lhaji Ismaíl kwarin riga
250,000.00
250,000.00 24-5-12 100 Completed
12
Connecting of100mm motorize borehole Alhaji Ismaíl
Distric Head
Balangu
1,036,042.00
1,036,042.00 22-5-12 100 Completed
13
purchase of offficial vehicle for chaiman MBU Motors K/hausa
5,500,000.00
5,500,000.00 14-2-12 100 Completed
14 Drilling of Hand pump MBU Motors K/hausa
14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total
32,371,027.00
32,371,027.00
KAZAURE LG
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED CONTRACT
SUM
COMMENCEMENT STATUS REMARKS
AMOUNT DATE IN %
1 7002/4
Construction of 1 block of 2 classroom with office
A.Sani Abdulkadir & sons Ltd. Karaftaki 2,964,934.00 2,964,934.00 11/11/2012 100 Completed
2 6002/1 Construction of 1 No Bore hole Murtala Kata'i
L.G. secretariat 801,581.25 801,581.25 10/11/2012 100 Completed
3 4006/1
Electrification at local Government Staff quarters H.O.D. WORKS
L.G. staff quarters 390,000.00 390,000.00 10/11/2012 100 Completed
4 4006/1 Electrification project at Fitari
Kurtu Ventures Dandoka Fitari 3,000,000.00 3,000,000.00 15/3/2012 100 Completed
xlii
5 7001/10 Purchase of official Vehicle for Chairman MBU Motors Kazaure 5,500,000.00 5,500,000.00 14-2-12 100 Completed
6 7001/11
Purchase of official vehicle for vice chairman secretary council leader MBU Motors Kazaure
14,500,000.00
14,500,000.00 14-2-12 100 Completed
TOTAL 27,156,515.25
27,156,515.25
KIRIKASAMMA LG
POST CONTRACT PROJECT EVALUATION
S/N PROJECT
EXECUTOR LOCATION
CONTRACT AMOUNT REVISED
COMMENCEMENT
STATUS REMARKS
(N) CONTRACT SUM
(N) DATE IN %
1 Complete Solar Water Wcheme ADZGlobal
services Masama 10,336,196.32 10,336,196.32 14-2-12 100 Completed
2 Complete Solar Water Scheme ADZGlobal
services Gubusun 10,336,196.32 10,336,196.32 14-2-12 100 Completed
3 Electrification Project Turabu
Costrucion Garin malaji 15,004,496.32 15,004,496.32 14-2-12 100 Completed
4 Electrificatiion Project Turabu
Costrucion Malori 15,004,496.32 15,004,496.32 14-2-12 100 Completed
5 Construction of a new Hand pump Muhd Musa
LTD guri juction 200,000.00
200,000.00 6/4/2012 100 Completed
6 construction of a motorized water scheme
NGA LOMA Gen ent. Turabu gabas 9,152,543.04
9,152,543.04 14-2-12 100 Completed
7 Construction of a new Hand pump Mmai Aji
marma Nig Marrma u/shanu 200,000.00
200,000.00 22-2-12 100 Completed
8 Construction of a new Hand pump
Alhaji abdu marma Nig
LTD Marma islamiyya 200,000.00
200,000.00 22-2-12 100 Completed
9 Construction of a new Hand pump Alhaji Ayuba Madachi 200,000.00
200,000.00 22-2-12 100 Completed
xliii
madachi Nig
10 Construction of a new Hand pump
Alhaji Ali Jannailo Nig LTD Gidan Babayo 200,000.00
200,000.00 22-2-12 100 Completed
11 Construction of a new Hand pump
Lawawn hassan Babuwa Rigar Ado Katinti 200,000.00
200,000.00 22-2-12 100 Completed
12 Construction of a new Hand pump Adamu Ali Dankabo Rigar Wakili Duwale 200,000.00
200,000.00 22-2-12 100 Completed
13 Construction of a new Hand pump Olu sawo
Nig Rigar Gonar Dawa 200,000.00
200,000.00 22-2-12 100 Completed
14 Construction of a new Hand pump Dunduma Shugaba Busuku Makaranta 200,000.00
200,000.00 22-2-12 100 Completed
15 Construction of a new Hand pump
Adamu salari Nig
LTD Daleri jumaat
mosque 200,000.00
200,000.00 22-2-12 100 Completed
16 Construction of a new Hand pump
Abdu Lidalle Nig
LTD Rubban kamaji 200,000.00
200,000.00 22-2-12 100 Completed
17 Construction of a new Hand pump Alhajji Abdu
Izza rigar yakubu m/galadima 200,000.00
200,000.00 22-2-12 100 Completed
18 Construction of a new Hand pump
Adamu Tsauya Nig
LTD Matara fulani 200,000.00
200,000.00 22-2-12 100 Completed
19 Construction of a new Hand pump Adamu Ule fandu Nig Kaiwari 200,000.00
200,000.00 22-2-12 100 Completed
20 Construction of a new Hand pump Musa ziko
Nig Bakadi 200,000.00
200,000.00 22-2-12 100 Completed
21 Construction of a new Hand pump Miko musa KKM Nig Rigar Dina 200,000.00
200,000.00 22-2-12 100 Completed
22 Construction of lock up shop 2nd Usman
Mohd Nig Turabu Market 4,027,605.60
4,027,605.60 11/5/2012 100 Completed
23 Construction of waiting shade Dodo
special Nig Marma 1,518,846.00 1,518,846.00 11/5/2012 100 Completed
24 Construction of waiting shade
Bala Shaaibu
Nig Madachi 1,518,846.00 1,518,846.00 11/5/2012 100 Completed
25 Construction of market stall
Bulama Musa kari
Nig kirikasamma market 1,171,302.72 1,171,302.72 11/5/2012 100 Completed
C/F 71,270,528.64 71,270,528.64
xliv
18a
B/F 71,270,528.64 71,270,528.64
26 Construction of market stall A. Teacher
Nig LTD dilmari market 1,171,302.72 1,171,302.72 11/5/2012 100 Completed
27 Construction of market stall
Dinau jarmau Nig
LTD dilmari market 1,171,302.72 1,171,302.72 11/5/2012 100 Completed
28 Wall of fencing of staff Quarters garoyo
bulama Nig KKM Staff qttrs 3,000,000.00 3,000,000.00 11/5/2012 100 Completed
29 Wall Fencing of staff Quarters B Ganyo bulama KKM Staff qttrs 2,958,988.97
2,958,988.97 11/5/2012 100 Completed
30 Wall Fencing of staff Quarters north south
Bukar magoyo KKM Staff qttrs 2,492,730.00
2,492,730.00 11/5/2012 100 Completed
31 Wall Fencing of staff quarters (North side)
A Garba Matar KKM Staff qttrs 2,000,000.00
2,000,000.00 11/5/2012 100 Completed
32 Wall Fencing of staff quarters (north side) B
A Garba Matar KKM Staff qttrs 2,300,000.00
2,300,000.00 11/5/2012 100 Completed
33 Wall fencing of staff quarters north side additional wall
A Garba Matar KKM Staff qttrs 449,106.36
449,106.36 6/6/2012 100 Completed
34 Wall fencing of staff quarter (bada sidi) additional works
Gayu Bulama Nig
LTD KKM Staff qttrs 947,432.75 947,432.75 6/6/2012 100 Completed
35 Electrification project
Gayu Bulama Nig
LTD Gabta 5,207,521.52 5,207,521.52 1/8/2011 100 Completed
36 Electrification project Muhd T muhd Sunkuye 12,794,311.98 12,794,311.98 25-6-12 100 Completed
37 Road side Tree Planting Direct labour road side 1,000,000.00
1,000,000.00 6/2/2012 100 Completed
38 Electrification project Turabu
Costrucion Kuka Dabo 14,684,997.21 14,684,997.21 28-6-12 100 Completed
39 Purcase of hand pump materials Direct
Purchase LG Secratiat 8,500,000.00 8,500,000.00 17-3-12 100 Completed
40 Purcase of 10 no motor cyles Direct
Purchase LG Secratiat 1,000,000.00 1,000,000.00 17-3-12 100 Completed
41 Purchase of official vehicle for chairman (peugeot408)
MBU Motors Office of Chairman 5,500,000.00
5,500,000.00 17-3-12 100 Completed
xlv
42 Purchase of official vehicle for vice chairman secretary council leader
MBU Motors LG Secratiat 14,500,000.00 14,500,000.00 17-3-12 100 Completed
43 purchase of 4No mass Transit (SHARON)
Kassamma Gen.
Motors LG Secratiat 5,200,000.00 5,200,000.00 26-11-12 100 Completed
44 Improvement of front walling of staff quarters
Ubale Malam Nig LG Qtrs 2,205,280.00
2,205,280.00 6/9/2012 100 Completed
45 Purchase of 1Nopick up (MAZDA)
Kassamma Gen.
Motors DPO office KKM 1,600,000.00 1,600,000.00 31-12-12 100 Completed
46 Purchase of Hand pump materials Direct
Purchase LG 3,500,000.00 3,500,000.00 24-12-12 100 Completed
47 Purchase of working material for commnity dept
Direct Purchase LG 1,500,000.00
1,500,000.00 25-12-12 100 Completed
48 Purchase of furniture for supervisory councilor and advise LG Sert 2,722,500.00
2,722,500.00 28-6-12 100 Completed
49 Renovation of Dilmari Health post
Alhaji Adamu muhd Dilmari 1,845,843.72
1,845,843.72 6/12/2012 100 Completed
Total 169,521,846.59 169,521,846.59
MAIGATARI LG
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT SUM
(N) DATE IN %
1 Purchase of water Generator Direct Labour Arbus
1,950,000.00
1,950,000.00 16-5-12 100 Completed
2 Purchase of water Generator Direct Labour Jaberi
1,950,000.00
1,950,000.00 25-4-12 100 Completed
3 Construction of Hand pump Direct Labour
Jss Maigatari
429,000.00
429,000.00 7/3/2012 100 Completed
4 Construction of Hand pump Direct Labour
Rigar shadali
429,000.00
429,000.00 7/3/2012 100 Completed
5 Construction of Hand Direct Labour Rigar 7/3/2012 100 Completed
xlvi
pump zango 429,000.00 429,000.00
6 Construction of jumaat Mosque Garis Invt. Nig Galadi
29,755,429.22
29,755,429.22 19-3-12 100 Completed
7 Construction of Drainage Alh. Bashir Nig. Tsangaya
619,000.00
619,000.00 7/3/2012 100 Completed
8 Electrification project Yusif sani G/kwalandi
- 949,034.00
949,034.00 15-10-12 100 Completed
9 Electrification Project Alh. Muhd Nig K/Giwa 4,869,700.00
4,869,700.00 15-6-12 100 Completed
10 Extention of Pipeline Alh Yahaya naibi unguwar
gabas mgt 846,195.00
846,195.00 1/6/2012 100 Completed
11 Extention of Pipeline U Umar sale monkey unguwar nasarawa
750,000.00
750,000.00 5/6/2012 100 Completed
12 Purchase of office furnitures Yahaya ibrahim LG sect.
5,082,740.00
5,082,740.00 28-6-12 100 Completed
13 Monthly purchase of hand pump materials Usman mati LG sect.
1,500,000.00
1,500,000.00 10/6/2012 100 Completed
14 Drainage evacuation Annually Rabiu madana
Maigatari town
3,407,884.00
3,407,884.00 14-9-12 100 Completed
15 Renovation of Guest House at Dutse Direct Labour
Dutse quest House
818,000.00
818,000.00 19-7-12 100 Completed
16 Renovation of IC PHC Maigatari House Tanimu magaji
Maigatari PHC
595,000.00
595,000.00 12/5/2012 100 Completed
17
Renovation & Furnishing of chief magistrate House Alh Fando Maigatari
873,800.00
873,800.00 25-12-12 100 Completed
18
Maigatari cattle market Net care Net care
Maigatari market
38,538,000.00
38,538,000.00 22-11-12 100 Completed
19 Purchase of official vehicle to Chairman MBU Motors
Maigatari LG
5,500,000.00
5,500,000.00 14-2-12 100 Completed
20
Purchase of official vehicle to v/ chairman secretary C/ leader MBU Motors Maigatari
14,500,000.00
14,500,000.00 14-2-12 100 Completed
TOTAL
113,791,782.22
113,791,782.22
xlvii
MALAM MADORI LG
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM
(N) DATE IN %
1 PURCHASE OF OFFICIAL VEHICLE FOR CHAIRMAN MBU Motors M/Madori
5,500,000.00
5,500,000.00 14-2-12 100 Completed
2
PURCHASE OF OFFICIAL VEHICLE FOR V/CHAIRMAN, SEC. & C/LEADER MBU Motors M/Madori
14,500,000.00
14,500,000.00 14-2-12 100 Completed
3 SUPPLY OF MATTRESSES BABANNAN KOLI
TRADING M/MADORI
150,800.00
150,800.00 Jun-12 100 Completed
4 PURCHASE OF H/PUMP MATERIALS HOD WASH M/MADORI
7,000,000.00
7,000,000.00 6/5//2012 100 Completed
5 CONSTR. of 4No. H/PUMPs RUWA T/GHANA LTD V/PLACES
1,400,000.00
1,400,000.00 14/11/2012 100 Completed
TOTAL 28,550,800.00
28,550,800.00
KAUGAMA L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR
LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS REMARKS
AMOUNT(N) CONTRACT
SUM (N) DATE IN %
1 4002/2 Construction of Slaughter House Gagaraukam Kaugama
3,000,000.00
3,000,000.00 7/12/2011 100 Completed
2 4006/2 Electrification Project Eng. Rabiú b U/jibrin to Yola
12,000,000.0
0
12,000,000.00 7/10/2011 100 Completed
3 6002/4 Construction of Culverts Abdu Taje Kaugama
1,780,436.00
1,780,436.00 11/10/2011 100 Completed
xlviii
4 7001/1
0 Purchase of official vehicle for chairman MBU Motors Kaugama
5,500,000.00
5,500,000.00 14-2-12 100 Completed
5 7001/1
1 Purchase of official vehicle for vice chairman MBU Motors Kaugama
14,500,000.0
0
14,500,000.00 14-2-12 100 Completed
Total
36,780,436.00
36,780,436.00
MIGA L.G
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT LOCATION CONTRACT
SUM REVISED
CONTRACT SUM
COMMENCEMENT STATUS REMARKS
DATE IN %
1 4006/1 Electrification project jamaga
22,974,216.48
22,974,216.48 13-4-12 100 Completed
2 4006/1 Electrification project Tsagaiwa 33,494,216.48
33,494,216.48 19-4-12 100 Completed
3 5004/2 Construction of 5 daily prayer mosque dawa
1,212,821.70
1,212,821.70 19-4-12 100 Completed
4 5004/2 construction of mosque namako 1,212,821.70
1,212,821.70 19-4-12 100 Completed
5 5004/2 construction of mosque majirga mai
kanya 1,212,821.70
1,212,821.70 19-4-12 100 Completed
6 5004/2 construction of mosque mai ganjara 1,212,821.70
1,212,821.70 19-4-12 100 Completed
7 5004/2 construction of mosque zugawa 1,212,821.70
1,212,821.70 19-4-12 100 Completed
8 5004/2 construction of mosque kadirawa 1,212,821.70
1,212,821.70 19-4-12 100 Completed
9 5004/2 construction of mosque dabakan alh
garba 1,212,821.70
1,212,821.70 19-4-12 100 Completed
xlix
10 5004/2 construction of mosque gidan tsimiya
D/B 1,212,821.70
1,212,821.70 19-4-12 100 Completed
11 5004/2 construction of mosque gamatan gabashi
1,212,821.70
1,212,821.70 19-4-12 100 Completed
12 5004/2 construction of mosque mudiga k/fada 1,212,821.70
1,212,821.70 19-4-12 100 Completed
13 6001/1 Construction of Hand pump wailaba gudu 351,397.00
351,397.00 19-4-12 100 Completed
14 6001/1 Construction of Hand pump gidan yaú
haske 351,397.00
351,397.00 19-4-12 100 Completed
15 6001/1 Construction of Hand pump jamaga 261,091.00
261,091.00 19-4-12 100 Completed
16 6001/1 Construction of Hand pump tsagaiwa 261,091.00
261,091.00 19-4-12 100 Completed
17 6001/1 Construction of Hand pump mujirga 351,397.00
351,397.00 19-4-12 100 Completed
18 6001/1 Construction of Hand pump kadirawa 351,397.00
351,397.00 19-4-12 100 Completed
19 6001/1 Construction of Hand pump sarawuya makaranta
261,091.00
261,091.00 19-4-12 100 Completed
20 6001/1 Construction of Hand pump mai ganjara 261,091.00
261,091.00 19-4-12 100 Completed
21 6001/1 Construction of Hand pump limamai gabas 261,091.00
261,091.00 19-4-12 100 Completed
22 6001/1 Construction of Hand pump gidan na allah 261,091.00
261,091.00 19-4-12 100 Completed
C/F 71,568,783.96
71,568,783.96
22a
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT LOCATION CONTRACT
SUM REVISED
CONTRACT COMMENCEMENT STATUS REMARKS
l
SUM DATE IN %
B/F 71,568,783.96
71,568,783.96
23 6001/1 Construction of Hand pump sabuwar jigawa 351,397.00
351,397.00 19-4-12 100 Completed
24 6001/1 Construction of Hand pump gidan
sarkin hawa 351,397.00 351,397.00 19-4-12 100 Completed
25 6001/1 Construction of Hand pump jiganda fulani 351,397.00
351,397.00 19-4-12 100 Completed
26 6001/3 Motorized water scheme Yanduna 12,402,467.80
12,402,467.80 30-5-12 100 Completed
27 7002/4 Construction of 9No Bedroom
Miga staff quarters
9,907,677.55
9,907,677.55 30-5-12 100 Completed
28 7001/2 Purchase of furniture Office of
miga LGA 2,715,000.00
2,715,000.00 30-5-12 100 Completed
29 4002/5 Purchase of Empty Drums
Demacation of grazing
land 1,097,000.00
1,097,000.00 30-5-12 100 Completed
30 6001/6 Water Extention mudiga 2,559,320.00
2,559,320.00 30-5-12 100 Completed
31 6001/6 Water Extention tsakuwawa 2,242,960.00
2,242,960.00 30-5-12 100 Completed
32 6002/1 Construction of Drainage Dankyatin 1,552,489.23
1,552,489.23 30-5-12 100 Completed
33 6002/1 Construction of Drainage Garbo 1,989,825.46
1,989,825.46 30-5-12 100 Completed
34 7001/13 Renovation of CM Hhouse Miga Staff quarters
4,671,279.45
4,671,279.45 30-5-12 100 Completed
35 4006/1 Electrification project Kirnande
12,213,783.06
12,213,783.06 30-5-12 100 Completed
36 4001/1 River Embakment Miga
Sarayuya
1,700,000.00
1,700,000.00 30-5-12 100 Completed
37 4001/2 Purchase of grain Distribution to People
2,000,000.00
2,000,000.00 30-5-12 100 Completed
38 5002/5 Construction of staaff qtrs zareku BHC
6,506,172.00
6,506,172.00 18-9-21 100 Completed
li
39 6004/2 Wall Fencing of Graveyards miga gabas grave yards
3,609,662.00
3,609,662.00 13-12-12 100 Completed
40 7001/10 purchase of official vehicle for chairman miga
5,500,000.00
5,500,000.00 14-2-12 100 Completed
41 7001/11
purchase of official vehicle for vice chairman secratry council leader miga
14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total 157,790,611.51
157,790,611.51
22b
SULE TANKARKAR L.G
TAURA L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT
SUM DATE IN %
1 7002/3 Purchase of Office Furniture Abdullhi mohd Taura 10,573,049.55
10,573,049.55 18-5-12 100 Completed
2 7002/3 Purchase of house Furniture Jamilu
mujaddadi Taura 8,763, 982.00 8,763,982.00 7/8/2012 100 Completed
3 7001/10 Purchase of Official vehicle for Chairman MBU motors Taura 5,500,000.00
5,500,000.00 14-2-12 100 Completed
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENTSTATUS REMARKS
AMOUNT CONTRACT SUM (N) DATE IN %
1 7001/10 Purchase of vehicle for chairman MBU Motors Sule tankarkar 5,500,000.00 5,500,000.00 3/3/2012 100 Completed
2 7001/11 purchase of vehicle for vice chairman secretary council leader MBU Motors Sule tankarkar 14,500,000.00 14,500,000.00 6/4/2012 100 Completed
TOTAL 20,000,000.00 20,000,000.00
lii
4 7001/11 Purchase of Official Vehicle for Vice Chairman Secretary Council Leader MBU motors Taura
14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total 39,337,031.55
39,337,031.55
RONI L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS REMARKS
AMOUNT(N) CONTRACT
SUM DATE IN %
1 4008/1 Construction of Drainage
Ibrahim Alkassim &
son Sabuwar
unguwa Roni
2,465,489.88 2,465,489.88 15-5-12 100 Completed
2 5004/4 Construction of Islamiyya School
Abdu Dogo and CM Bawa
Sabuwar unguwa Roni
2,064,853.50 2,064,853.50 15-3-12 100 Completed
3 4007/1 Wall Fencing of Roni Motel
Alhaji isa Achilafiya Roni motel
4,101,921.18 4,101,921.18 13-1-12 100 Completed
4 4007/2 Construction of Market Stalls Mal usman Amaryawa
2,143,954.16 2,143,954.16 13-1-12 100 Completed
5 5004/1 Construction of IslamiyyaSchool
Sarkin fawa Garba dantila Kayalwa
2,064,853.50 2,064,853.50 13-1-12 100 Completed
6 7002/4 Purchase of Furniture Hajiya
Shamsiyya Roni staff
Qtrs 2,181,627.00 2,181,627.00 13-1-12 100 Completed
7 7001/1
0
Purchase of Official Vehicle MBU Motors Roni
5,500,000.00 5,500,000.00 14-2-12 100 Completed
8 7001/1
1 Purchase of 3No. Official Vehicles MBU Motors Roni
14,500,000.00 14,500,000.00 14-2-12 100 Completed
liii
9 5004/2 Const. of Daily Prayer Mosque
SAMA'ILA IBRAHIM RONI
1,668,885.00 1,668,885.00 2/5/2012 100 Completed
10 4006/3 Extention of Power Supply
SANI SAMA'ILA RONI
488,117.84 488,117.84 17/5/2012 100 Completed
11 5004/1 Renovation of Islamiyya School
ABDUL DALHA RONI
805,546.90 805,546.90 15/5/2012 100 Completed
12 4008/1 Constr. Of Culvert ABUBAKAR SULAIMAN KWAITA
3,592,913.28 3,592,913.28 18/12/2012 100 Completed
13 4008/1 Annual Drainage Evacuation B.M. SUKAR
SABUWAR UNGUWA
1,657,993.65 1,657,993.65 24/12/2012 100 Completed
14 5004/2 Const. of Daily Prayer Mosque
ALH. YAKUBU NANANA JANGEFE
1,254,590.97 1,254,590.97 15/5/2012 100 Completed
15 5004/2 Const. of Daily Prayer Mosque
ABUBAKAR LAWAN
MAMUDAWA
1,044,554.80 1,044,554.80 24/12/2012 100 Completed
Total
45,535,301.6
6 45,535,301.66
YAN KWASHI L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION
CONTRACT AMOUNT REVISED
COMMENCEMENT
STATUS
REMARKS
(N) CONTRCT
SUM DATE IN %
1 4008/2
Construction of Feeder Road from Kudu to Walaw to firji (6km) (phase 2)
313 Drilling and construction Nig LTD
Walawa to Furji
68,706,332.00
68,706,332.00 21-10-12 100 Completed
2 6001/10 Purchase of Hand pump materials Direct purchase
Various location
2,500,000.00
2,500,000.00 21-10-12 100 Completed
3 7001/5 Construction of Wall Fencing MUSAB
constructionLTD karkarna town 7,000,000.00
7,000,000.00 21-10-12 100 Completed
4 7001/1 Purchase of Land at Karkarna Town Direct purchase
GJSS yankwashi
2,000,000.00
2,000,000.00 21-10-12 100 Completed
liv
5 7001/1 Purchase of land at yankwashi town Direct purchase Primary sch
2,600,000.00
2,600,000.00 21-10-12 100 Completed
6 7001/1 purchase of land at kwarare town Direct purchase kwarari
1,000,000.00
1,000,000.00 21-10-12 100 Completed
7 7001/5 Fencing of karkarna arewa Grave yard
MUSAB constructionLTD karkarna town
7,720,166.62
7,720,166.62 21-10-12 100 Completed
8 7001/10 Purchase of official vehicle for chairman MBU Motors Yankwashi
5,500,000.00
5,500,000.00 21-10-12 100 Completed
9 7001/11
Purchase of official vehicle for vice chairman Secretary council leader MBU Motors Yankwashi
14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total
111,526,498.62
111,526,498.62
KIYAWA L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED
CONTRACT SUM COMMENCEM
ENT STATU
S REMARKS
(N) DATE IN %
1 6001/5 Construction of Hand pump Abdullahi Naola Godawa 328,630.00
328,630.00 27-1-12 100 Completed
2 6001/5 Construction of Hand pump Ismaíl Ahmad Fanteka 328,630.00
328,630.00 14-12-12 100 Completed
3 6001/5 Construction of Hand pump Ismaíl Ahmad Jamaár isah 328,630.00
328,630.00 17-2-12 100 Completed
4 6004/3 Construction of five daily prayer kaila isah Barnawa 642,917.23
642,917.23 24-2-12 100 Completed
5 4008/4 construction of Drainage Garba Yaú Kauta Kiyawa 744,824.56
744,824.56 9/3/2012 100 Completed
6 4008/4 Construction of waste water collection point Sule manja Tsalakawa 236,604.44
236,604.44 14-3-12 100 Completed
lv
7 6001/5 Construction of Hand pump Isah Liman D. Yashi 328,630.00
328,630.00 22-3-12 100 Completed
8 6001/3 Construction of Open well Alh. Ibrahim jet Gidan Bature 280,462.50
280,462.50 13-3-12 100 Completed
9 6001/5 Construction of Hand pump Hamisu Yaú N Chediya 226,800.00
226,800.00 14-3-12 100 Completed
10 6001/5 Construction of Hand pump Tijjani Galadima Galamawa 328,630.00
328,630.00 13-4-12 100 Completed
11 5001/3 Construction of islamiyya school Danladi Biliya Kanti kiyawa 4,570,072.70
4,570,072.70 13-4-12 100 Completed
12 6004/2 Construction of Jumaát Mosque
Amadu Kwaimawa Sabon gari 439,776.60
439,776.60 13-4-12 100 Completed
13 6004/2 Construction of Jumaát Mosque Adamu Mai mai Akar 4,397,776.60
4,397,776.60 13-4-12 100 Completed
14 5001/3 Construction of islamiyya school Yakubu fake harba 4,570,072.70
4,570,072.70 13-4-12 100 Completed
15 6001/5 Construction of Hand pump Bako ahmad Malamawa 328,630.00
328,630.00 11/4/2012 100 Completed
16 6004/3 Construction of five daily prayer Alh. Yaú Usaini Gidan Dachi 642,917.23
642,917.23 2/4/2014 100 Completed
17 6004/3 Construction of five daily prayer Sule Mamuda Harba 637,365.96
637,365.96 19-4-12 100 Completed
18 6004/3 Construction of five daily prayer Haruna Dan ture Bargawa 635,926.34
635,926.34 22-4-12 100 Completed
19 6001/5 Construction of Hand pump Ismaíl Ahmad J. Isah Gabas 328,630.00 328,630.00 22-4-12 100 Completed
20 6001/3 Construction of Open well Alh. Danjuma
Idris Gerawa fulani 183,000.00 183,000.00 22-4-12 100 Completed
21 6001/5 Construction of Hand pump Alh. Danjuma
Idris Dugu 281,062.00 281,062.00 22-4-12 100 Completed
C/F 20,789,988.86 20,789,988.86
19a
lvi
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED
CONTRACT SUM COMMENCEM
ENT STATU
S REMARKS
(N) DATE IN %
B/F 20,789,988.86 20,789,988.86
22 6004/3 Construction of five daily prayer Auwal katanga
Yalwa katanga 635,926.34
635,926.34 2/5/2012 100 Completed
23 6001/5 Construction of Hand pump Alh. Sabo Kwara Ganyo 328,630.00 328,630.00 2/5/2012 100 Completed
24 6004/3 Construction of five daily prayer Badamasi ubani
Unguwar mahauta 328,630.00
328,630.00 10/3/2012 100 Completed
25 4006/1 Electrification Extention Suleiman adamu Madina 1,916,860.00 1,916,860.00 17-5-12 100 Completed
26 6001/5 Construction of Hand pump Ibrahim masaya Auyakawa 328,630.00 328,630.00 17-5-12 100 Completed
27 6001/5 Construction of Hand pump Ibrahim masaya Zawaya 328,630.00 328,630.00 17-5-12 100 Completed
28 6001/3 Construction of Open well lawan salisu Alalau fulani 290,640.00 290,640.00 16-5-12 100 Completed
29 6001/3 Construction of Open well Mutari Gani Lajiko 280,462.00 280,462.00 18-5-12 100 Completed
30 4007/3 construction of motor park Alh Garba Gali balago 7,830,674.42 7,830,674.42 6/6/2012 100 Completed
31 7001/2 Construction of District Head House Ishaq Abubakar Shuwarin 17,155,084.10
17,155,084.10 14-8-12 100 Completed
32 6001/3 Construction of Open well Zailani kwanda karangiya 280,462.50 280,462.50 14-6-12 100 Completed
33 6001/3 Construction of Open well Haruna balago Alagarno 292,625.00 292,625.00 14-6-12 100 Completed
34 6001/5 Construction of Hand pump yunusa datti Tsangayawa 328,630.00 328,630.00 26-6-12 100 Completed
35 6001/3 Construction of Open well umar karaga Abarawa 280,462.00 280,462.00 27-6-12 100 Completed
36 6001/4 Extention of retaculation Network dahiru dangoli Dangoli 358,370.00
358,370.00 2/8/2012 100 Completed
37 6001/5 Construction of Hand pump lawan salisu masaya 328,630.00 328,630.00 2/8/2012 100 Completed
lvii
38 6001/5 Construction of Hand pump lawan salisu Chiwina 328,630.00 328,630.00 2/8/2012 100 Completed
39 6004/3 Construction of five daily prayer Nasiru Ahmad kiyawa 1,029,554.70
1,029,554.70 2/8/2012 100 Completed
40 6001/5 Construction of Hand pump Abdullahi naula Kulluru 635,524.00 635,524.00 3/8/2012 100 Completed
41 6001/5 Construction of Hand pump Garba Mohd K. Shidi 328,630.00 328,630.00 8/8/2012 100 Completed
42 6004/3 Construction of five daily prayer Bala Andaza G Shidi 625,216.00
625,216.00 14-8-12 100 Completed
C/F 55,030,889.92 55,030,889.92
19b
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED
CONTRACT SUM COMMENCEM
ENT STATU
S REMARKS
(N) DATE IN %
B/F 55,030,889.92 55,030,889.92
43 4007/5 Construction of islamiyya school Hussain Abdu Shatari 5,281,928.86
5,281,928.86 14-8-12 100 Completed
44 6001/3 Construction of waiting stall dahiru dangoli Dangoli 511,844.85 511,844.85 23-8-12 100 Completed
45 6001/3 Construction of Open well Abdullahi G Bajidawa 280,462.00 280,462.00 25-8-12 100 Completed
46 6004/3 Construction of five daily prayer Yunusa Muhd Majawa 635,524.00
635,524.00 3/1/2012 100 Completed
47 6004/3 Construction of five daily prayer Tijjani Galadima G makama 635,524.00
635,524.00 3/1/2012 100 Completed
48 6004/3 Construction of five daily prayer Garba G/dole Kanoke 635,524.00
635,524.00 30-7-12 100 Completed
lviii
49 6001/3 Construction of Open well M. Tasiú sha Shadaka 280,462.00 280,462.00 5/9/2012 100 Completed
50 6004/3 Construction of five daily prayer Danladi bilya G. Talo 635,524.00
635,524.00 11/9/2012 100 Completed
51 4006/1 Extention of electricity line Mustapha A kiyawa 515,025.00 515,025.00 19-9-12 100 Completed
52 6001/5 Construction of Hand pump Bashari Adamu G. Tilo 328,630.00 328,630.00 25-9-12 100 Completed
53 4006/1 Extention of electricity line Hassan Maáji kiyawa 209,990.00 209,990.00 25-9-12 100 Completed
54 6004/3 Construction of five daily prayer Tukur Adamu balago 6,355,334.00
6,355,334.00 10/10/2012 100 Completed
55 6001/3 Construction of Open well Baba Zabi Bazabi 290,640.00 290,640.00 16-5-12 100 Completed
56 6001/5 Construction of Hand pump lawan salisu Malajele 328,630.00 328,630.00 18-5-12 100 Completed
57 7001/10 Purchase of official vehicle for chairman MBU Motors kiyawa 5,500,000.00
5,500,000.00 14-2-12 100 Completed
58 7001/11 purchase of official vehicle for vice chairman MBU Motors kiyawa 14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total 91,955,932.63
91,955,932.63
RINGIM L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT(N) CONTRCT
SUM DATE IN %
1 2009F/1 Renovation of chairman guest house Rabiu Dabi Ringim
4,850,983.30
4,850,983.30 12/1/2012 100 Completed
2 6001/8 Construction of Motorised bore hole sabo Mulki Dogaji
7,975,769.03
7,975,769.03 17/1/12 100 Completed
3 5004/2 Completion of juma'at mosque Direct labour
Auramo Haji
1,080,000.00
1,080,000.00 6/11/2012 100 Completed
lix
4 7001/10 purchase of official vehicle for chairman MBU Motors Ringim
5,500,000.00
5,500,000.00 14-2-12 100 Completed
5 7001/11
purchase of official vehicle for vice chairman secretary council leader MBU Motors Ringim
14,500,000.00
14,500,000.00 14-2-12 100 Completed
Total 33,906,752.33
33,906,752.33
lx
SECTION (B)
ON-GOING PROJECT
JANUARY DECEMBER, 2012
lxi
AUYO L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED
COMMENCEMENT DATE
STATUS REMARKS
AMOUNT(N) CONTRACT SUM IN %
1 4106/2 ELECTRIFICATION PROJECT MWT REAL ESTATE KATAJE 6,757,181.22
6,757,181.22 27- 7 - 12 85 ON-GOING
2 5002/5 CONSTRUCTION OF PEADIATRIC WARD ALIH. MUSA AUYO AUYO 10,531,712.60
10,531,712.60 8/7/2012 50 ONGOING
3 6001/4 COMPLETE MOTORISED WATER SCHEME SHAMAKI UMAR KALGWAI 11,212,584.10
11,212,584.10 8/10/2012 70 ONGOING
4 6001/4 COMPLETE MOTORISED WATER SCHEME LIMIS BROTHERS MURAN 8,727,066.16
8,727,066.16 15- 11- 12 70 ON-GOING
5 4006/2 ELSCTRIFICATION PROJECT SHIGO GEN. ENTP SHIYO 18,162,995.13
18,162,995.13 5/12/2012 40 ON-GOING
6 4006/5 ELECTRIFICATION PROJECT GANO VENTURES
NIG MAJIYA 12,433,009.13
12,433,009.13 7/7/2010 75 ON-GOING
7 4006/5 ELECTRIFICATION PROJECT GANO VENTURES
NIG AYAN 28,175,192.80
28,175,192.80 7/7/2010 80 ON-GOING
8 4006/5 ELECTRIFICATION PROJECT GANO VENTURES
NIG GUDITO 14,741,731.79
14,741,731.79 18/05/2011 70 ON-GOING
9 6001/4 COMPLETE MOTORISED WATER SCHEME BUKAR MAKODA HADIYA 7,560,665.00
7,560,665.00 18/05/2011 80 ON-GOING
10 4006/2 ELECTRIFICATION PROJECT TURABU CONST. GASANYA 13,043,370.64
13,043,370.64 11/11/2011 80 ON-GOING
11 5002/5 CONSTRUCTION OF SLAUGHTER HOUSE GANO VENTURES
NIG AUYO 6,552,103.20
6,552,103.20 25/02/2011 60 ON-GOING
lxii
TOTAL
137,897,611.77
137,897,611.77
BABURA L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT(N) CONTRACT SUM DATE IN %
1 5004/2 CONSTR. OF FRIDAY PRAYER MOSQUE Alh. Musa Shehu ACHIYA
3,004,000.00
3,004,000.00 11/11/2012 45 ON-GOING
2 5004/2 CONSTR. OF FRIDAY PRAYER MOSQUE Sani Haru DAN YAYI
3,004,000.00
3,004,000.00 11/4/2012 60 ON-GOING
3 5001/9 COSNTR. OF ISLAMIYYA SCHOOL Mati Danhalili GANA 3,126,219.14
3,126,219.14 11/4/2012 45 ONGOING
4 5001/9 CONSTR. OF ISLAMIYYA SCHOOL Zubairu Kanya TSAMIYA KWANCE
3,126,219.14
3,126,219.14 11/4/2012 45 ONGOING
5 5001/9 CONSTR. OF NOMADIC SCHOOL Sani Mahmud DANZAGO 5,000,000.00
5,000,000.00 20/12/12 45 ONGOING
6 5001/9 CONSTR. OF NOMADIC SCHOOL Alh. Sade Kanya KARFAWA 3,126,219.14
3,126,219.14 11/4/2012 45 ONGOING
7 5004/2 CONSTR. DRAINAGE Ado Mohd Masko MASKO 3,200,000.00
3,200,000.00 16/8/12 45 ON-GOING
8 4006/1 ELECTRIFICATION PROJECT Prestige Inter Nig.
Ltd Unguwa Shuri 9,170,252.00
9,170,252.00 23/3/2010 70 ON-GOING
9 4008/2 CONSTR. OF FEEDER ROAD JIRMA MANGA-
TAKWASA 7,560,293.75
7,560,293.75 12/2/2010 35 ON-GOING
TOTAL 40,317,203.17
40,317,203.17
lxiii
BIRNIWA L.G
POST CONTRACT PROJECT EVALUATION
S/N EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
PROJECT AMOUNT(N) CONTRACT SUM (N) DATE IN %
1 Construction of Slaughter House Gano Ventures Nig
LTD Diginsa 5,874,099.00
5,874,099.00 8/5/2008 95 On-Going
2 Construction of Wall Fencing A Sunusi Isa GGSS Birniwa
25,502,074.00
25,502,074.00 12/5/2008 40 On-Going
3 Electrification Project Gano Ventures Nig
LTD kanya 10,221,305.23
10,221,305.23 13/10/2010 90 On-Going
4 Electrification Project Gano Ventures Nig
LTD Kabuna 6,477,343.33
6,477,343.33 13/10/2010 90 On-Going
5 Electrification Project Gano Ventures Nig
LTD Abbari 54,062,263.47
54,062,263.47 15/10/2010 50 On-Going
6 Additional Works at Computer Room Matrix Nig LTD LG SEC 17,767,725.15
17,767,725.15 10/5/2009 40 On-Going
TOTAL 119,904,810.00
119,904,810.00
BIRNIN KUDU
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT
SUM DATE IN %
1 4008/3 CONSTR. OF MASAYA - TUKUDA TAR ROAD
GERAWA GLOBAL LTD
MASAYA-TUKUDA 17KM
344,522,430.06
444,169,130.74 24/3/11 50 ON-GOING
2 6004/1 CONSTR. OF FRIDAY MOSQUE AUWWALU MATO BUDINGA VILLAGE
4,107,698.00
4,310,492.96 24/3/11 75 ON-GOING
3 4006/1 ELECTRIFICATION PROJECT BLUE SKY NIG LTD B/DANGIWA 17,597,275.20
17,597,275.20 12/9/2011 40
ON-GOING
lxiv
4 4006/1 ELECTRIFICATION PROJECT BLUE SKY NIG LTD KWANGWARA 22,548,477.55
22,548,477.56 15/10/2010 90
ON-GOING
5 6004/1 CONSTRUCTION OF JUMAAT MOSQUE ADO B/KUDU GIWA 2,395,900.00
2,395,900.00 24/03/2011 60
ON-GOING
6 6004/1 CONSTRUCTION OF JUMAAT MOSQUE A AMADU MK BUDISU 4,626,832.50
4,626,832.50 24/03/2011 65
ON-GOING
7 6004/1 CONSTRUCTION OF JUMAAT MOSQUE JAMILU B/KUDU JIKAINA 3,376,000.32
3,376,000.32 24/03/2011 85 ON-GOING
TOTAL 399,174,613.63
499,024,109.28
DUTSE L.G
POST CONTRACT PROJECT EVALUATION
S/N. HEAD PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT
SUM DATE IN %
1 6001/2 CONSTR. OF BORE
HOLE MAHALLI NIG LTD
DUTSE GRAVEYARD
563,840.00
563,840.00 20/4/2012 20 ONGOING
2 6001/2 CONSTR. OF BORE
HOLE MAHALLI NIG LTD
GANDUN FAWA
551,656.00
551,656.00 20/2/2012 20 ONGOING
3 6004/7 COMPLETE WATER
SCHEME ALKALI
SAKWAYA GAKIKWA
7,264,270.00
7,264,270.00 23/10/2012 85 ONGOING
4 6001/3 REPAIRS OF
SOLAR BOREHOLE PRESTEGE
LTD DARAU
284,287.50
284,287.50 14/2/2012 25 ONGOING
5 6001/3 REPAIRS OF
SOLAR BOREHOLE PRESTEGE
LTD WURMA
284,287.50
284,287.50 14/2/2012 20 ONGOING
6 6001/3 REPAIRS OF
SOLAR BOREHOLE PRESTEGE
LTD GALAMAWA
284,287.50
284,287.50 14/2/2012 40 ONGOING
7 6004/1
CONSTRUCTION OF JUMAAT
MOSQUE SAGOGO
VENTURERS KANDI
8,007,618.33
8,007,618.33 7/3/2010 70 ONGOING
lxv
8 4006/1 ELECTRIFICATION
PROJECT
IBRACO INTER. CO
LTD DURU
17,931,655.04
17,931,655.04 23/12/2011 90 ONGOING
9 4006/1 ELECTRIFICATION
PROJECT HARO
SHEHU WURMA
28,018,224.00
28,018,224.00 23/12/2011 70 ONGOING
10 4008/1 CONSTR. OF
FEEDER ROAD SY HASSN
LTD ISARI-ABAWA
113,467,300.00
113,467,300.00 2/6/2010 70 ONGOING
11 5002/2 CONSTR, OF
MODEL CLINIC IBRACO INT
LTD KARNAYA
14,393,879.79
14,393,879.79 28/06/2011 40 ONGOING
TOTAL
191,051,305.66
191,051,305.66
BUJI L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT RIVISED COMCMT STATUS REMARKS
AMOUNT CONTRACT
SUM DATE IN %
1 7002/3 CONSTR. BUJI DISTRCT HEAD HOUSE
YAYARI TUKUR NIG LTD BUJI
11,214,965.81
11,214,965.81 11/12/2012 60 ONGOING
2 5004/2 CONSTR. OF JUMAAT MOSQUE
YAYARI TUKUR NIG LTD MADABE
11,339,700.59
11,339,700.59 11/12/2012 35 ONGOING
3 4007/1 CONSTR. OF LOCK-UP SHOPS IHSAN NIG. LTD SARA MARKET
13,780,694.70
13,780,694.70 11/12/2012 35 ONGOING
4 5004/5 CONSTR. OF DAILY PRAYER MOSQUE SANI AHOTO AHOTO
1,648,372.40
1,648,372.40 11/12/2012 35 ONGOING
5 5004/5 CONSTR OF DAILY PRAYER MOSQUE
GARBA UBALE & OTHER GWADAYI
1,648,372.40
1,648,372.40 11/12/2012 35 ONGOING
6 5002/2 CONSTR OF PIT LATRINE SALE YAU &
OTHERS U/MAINA
616,075.95
616,075.95 30/12/12 35 ONGOING
7 4005/1 ELECTIRIFICATION PROJECT YAYARI TUKUR
NIG LTD SARA-KUKUMA
37,900,795.67
37,900,795.67 18/10/2011 50 ONGOING
lxvi
8 4005/1 ELECTIRIFICATION PROJECT IHSAN NIG. LTD U/MAINA
31,567,217.94
31,567,217.94 18/10/2011 75 ONGOING
9 6002/1 CONSTR. OF CHIRBIN CHAKWAMA ROAD
ALPHA & SGMA NIG LTD
CIRBIN -CAKWAMA
33,449,850.00
33,449,850.00 29/12/2010 53 ONGOING
10 5002/2 CONSTR OF PIT LATRINE HARUNA A IDI Y/ TUKUR
616,075.95
616,075.95 30/12/12 35 ONGOING
11 5002/2 CONSTR OF PIT LATRINE MUDDAFA &
OTHERS GWADAYI
616,075.95
616,075.95 30/1212 35 ONGOING
TOTAL
144,398,197.36
144,398,197.36
GARKI L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT
SUM DATE IN %
1 7001/1 FENCING OF GARKI GGSS SLM AMINCI
LTD GARKI 19,253,694.00
19,253,694.00 2/6/2012 50 ONGOING
2 4006/2 ELECTRIFICATION POJECT MARB ENG
SERV MUKU 14,966,120.85
14,966,120.85 5/6/2012 60 ONGOING
3 5001/7 CONSTR. OF JUMAAT MOSQUE
A MAGAJI GARKI DUNKUMI
4,165,494.61
4,165,494.61 10/9/2012 60 ONGOING
4 5002/2 RENOVATION OF HEALTH POST
DIRECT LABOUR MUKU
3,510,328.37
3,510,328.37 17/06/2012 70 ONGOING
TOTAL 41,895,637.83
41,895,637.83
lxvii
GAGARAWA L.G
GUMEL L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT
SUM (N) DATE IN %
1 4006/2 ELECTRIFICATION PROJECT
BNB GLOBAL NIG LTD KANGARWA KANGARWA
18,175,454.85
18,175,454.85 15/09/2010 80 ON-GOING
2 4006/2 ELECTRIFICATION PROJECT
GANO VENTURES NIG LTD MADAKA
30,932,405.00
30,932,405.54 15/09/2010 45 ON-GOING
TOTAL 49,107,860.39
49,107,860.39
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT
SUM DATE IN %
1 4008/2 CONSTR. OF MOTOR PARK ISMAEL
VENTURES GUMEL KANO
ROAD 43,416,895.65 43,416,895.65 28/06/2012 20 ONGOING
2 6002/2 CONST OF DRAINAGE & CULVERT
BAFSA GLOBAL CONC NASARAWA 3,893,290.00 3,893,290.00 7/10/2010 75 ONGOING
lxviii
GURI L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT RIVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT
SUM DATE IN %
1 4006 CONNECTION OF HT LINE ADAMU YAU GAGIYA
12,863,497.50
12,863,497.50 21/06/2010 20 ON-GOING
2 7001/1 RENOVATION OF MOSQUE MALAM BULAMA MAMUDAWA 150,000.00 150,000.00 20/07/2010 30 ON-GOING
3 4006/1 ELECTRIFICATION PROJECT
TURABU NIG LTD GURI
1,955,938.00 1,955,938.00 20/07/2010 40 ON-GOING
4 4006/1 ELECTRIFICATION PROJECT AMIM NIG LTD
GURI-ADIYANI-TUK
32,299,278.48
32,299,278.48 6/7/2012 75 ON-GOING
5 4008/3 CONSTR. OF FEEDER ROAD
GANO VENTURES GURI - ZUGO
50,903,350.88
50,903,350.88 6/7/2012 65 ON-GOING
Total
98,172,064.86
98,172,064.86
3 5001/4 CONSTR. JUMAAT MOSQUE MAI ZABBI BAIKAYA 5,229,000.00 5,229,000.00 19/07/2010 70 ONGOING
4 7003/5 CONSTR. DWARF FENCING WALL A.A.M KANTI STAFF QTRS 11,053,371.00
11,053,371.00 10/9/2010 75 ONGOING
5 4007/2 CONSTR. OF SHOPPING PLAZA A SARKI ILU GUMEL TOWN 39,322,230.00
39,322,230.00 19/06/2010 50 ONGOING
6 4006/4 ELECTRIFICATION PROJECT SHOW CASE DANFARANTAMA 17,521,651.19
17,521,651.19 5/11/2008 60 ONGOING
7 7002/3 COMPLETION OF SENIOR STAFF QTRS
J IKANDE NIG LTD GUMEL 34,389,233.00
34,389,233.00 8/8/2008 50 ONGOING
TOTAL 154,825,670.84
154,825,670.84
lxix
GWIWWA L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT
SUM (N) DATE IN %
1 CONSTR. OF 9 BEDROOM QTRS ASHALLE NIG LTD GWIWA 6,994,051.35
6,994,051.35 10/10/2010 90 ON-GOING
2 ELECTRIFICATION PROJECT BOK NIG LTD BURMA RUWA 22,506,803.67
22,506,803.55 23/4/12 40 ON-GOING
3 CONSTRUCTION OF DRAINAGE
M/UNGUWA ABDULLAHI RORAU 3,459,318.66
3,459,318.66 21/6/12 40 ON-GOING
4 CONST. OF BLOCK OF 2 CLASSROOMS USMAN NAMADI
ZANGON KAYA 4,128,705.94
4,128,705.94 17/6/12 40 ON-GOING
5 CONST. OF BLOCK OF 2 CLASSROOMS
ALH. TUKUR ALTO DARAGI 4,128,705.94
4,128,705.94 17/6/12 30 ON-GOING
TOTAL 41,217,585.44
41,217,585.44
lxx
GWARAM LG
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM
(N) DATE IN %
1 5001/9 FENCING OF GG UNITY SCHOOL
RINGIM GALADANCI GWARAM
36,825,149.24
36,825,149.24 12/9/2012 60 ONGOING
2 5001/7 CONSTR. OF ISLAMIYYA SCHOOL AS DANKURGWI KUYUNGU
2,629,645.60
2,629,645.60 13/12/2012 85 ONGOING
3 5001/4 CONSTR. OF ISLAMIYYA SCHOOL
SAYYAKO BASIRKA KIJIN
2,629,645.60
2,629,645.60 29/12/2011 70 ONGOING
4 5001/5 CONSTR. OF ISLAMIYYA SCHOOL DANLAMI KILA KILA GABAS
2,629,645.60
2,629,645.60 17/12/2012 75 ONGOING
5 5001/5 CONSTR. OF ISLAMIYYA SCHOOL DANLAMI KILA ZAGANGANDO
2,629,645.60
2,629,645.60 17/12/2012 77 ONGOING
6 5001/5 CONSTR. OF ISLAMIYYA SCHOOL YAU MUSA JIKAS GAGURU
2,629,645.60
2,629,645.60 17/12/2012 65 ONGOING
7 7001/13 NEW LG SECRETARIATE CIROCO GWARAM
357,314,412.85
357,314,412.85 15/12/2012 90 ONGOING
8 5004/1 CONST. OF MINI STADIUM PHASE I BAHUTU NIG LTD KILA
12,000,000.00
12,000,000.00 5/12/2008 87 ONGOING
9 4008/13 CONSTRUCTION OF FEEDER ROAD ALH. SABO ILU KILA LUNGU 31,014,427.50
31,014,427.50 15/12/2012 40 ONGOING
TOTAL 450,302,217.59
450,302,217.59
lxxi
HADEJIA L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM
(N) DATE IN %
1
2
3
4
5 TOTAL
JAHUN L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION REVISED COMMENCEMENT STATUS REMARKS
CONTRACT
SUM (N) CONTRACT SUM
(N) DATE IN %
1 5004/4 GENERAL REHABLITATION OF COMPRE. HEALTH CENTER DIRECT LABOUR KADOAWAWA 14,383,924.00 14,383,924.00 1/12/2012 80 ON-GOING
2 6001/2 CONSTR. OF FRIDAY PRAYER MOSQUE DIRECT LABOUR TARAYE & GWAMPAI 8,000,000.00 8,000,000.00 1/12/2012 60 ON-GOING
3 5005/4 CONSTR. OF FIVE DAILY PRAYER MOSQUE D/MAIGADA GORA 882,589.00 882,589.00 7/3/2012 30 ON-GOING
4 4006/1 ELECTRIFICATION PROJECT IBRACO MARFARICA ATUMAN 18,123,262.98 18,123,262.98 18/11/2011 90 ON-GOING
TOTAL 41,389,775.98
41,389,775.98
lxxii
KAFIN HAUSA L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
SUM (N) REVISED COMMENCEMENT STATUS REMARKS
CONTRACT SUM DATE IN %
1 4006/2 ELECTRIFICATION PROJECT PURE HAND KUNUNU 7,336,100.25
7,336,100.25 21/06/2010 85 Stalled
2 4006/2 ELECTRIFICATION PROJECT PURE HAND ABDALLAWA 8,895,924.81
8,895,924.81 21/06/2010 85 Stalled
3 6001/6 COMPLETE M/ WATER SCHEME WATSAN BIRKIDI 7,688,006.45
7,688,006.45 21/6/2010 50 Stalled
4 6001/6 COMPLETE M/ WATER SCHEME WATSAN KWARMAZA 6,365,933.15
6,365,933.15 21/06/2010 70 Stalled
5 4002/2 CONSTR. OF SLAUGHTER HOUSE A. JAFARU M/GORO K/HAUSA 6,965,171.08
6,965,171.08 10/8/2011 90 ON-GOING
6 4002/2 CONST. OF SLAUGHTER HOUSE A. ISIYAKA BUDAN BULANGU 6,965,171.08
6,965,171.08 10/8/2011 80 ON-GOING
7 4006/5 ELECTRIFICATION PROJECT PURE HAND KORE
8,070,240.00
8,070,240.00 23/6/2010 67 ON-GOING
8 4001/6 COMPLETE M/ WATER SCHEME DIRECT LABOUR AGURAN MAZANA
8,318,479.00
8,318,479.00 23/6/2010 80 ON-GOING
9 6004/2 CONSTR. OF JUMAAT MOSQUE DIRECT LABOUR TAMBALE
2,000,000.00
2,000,000.00 10/8/2011 75 ON-GOING
10 6001/6 REACTIVATION OF SOLAR BOREHOLE LAWAL BUSURI
G/SARKI
1,504,117.00
1,504,117.00 24/4/2012 60 ON-GOING
11 7002/1 RENOVATION OF 2NO. 3-BEDROOM HOUSE Y/INVEST
STAFF QTRS
11,972,003.12
11,972,003.12 10/10/2012 85 ON-GOING
12 7002/1 RENOVATION OF 1NO. 2-BEDROOM HOUSE ALHAJI BABANI
STAFF QTRS
7,185,219.36
7,185,219.36 10/10/2012 69 ON-GOING
13 7002/1 RENOVATION OF 1NO. 5-BEDROOM HOUSE
ALH. ZAKAR A JABO
STAFF QTRS
6,615,902.24
6,615,902.24 10/10/2012 70 ON-GOING
TOTAL
89,882,267.54
89,882,267.54
lxxiii
KIRIKASAMMA L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT STATUS REMARK
(N) CONTRACT
SUM (N) DATE in %
1 4006/2 ELECTRIFICATION PROJECT
TURABU CONSTRUCTION NIG LTD GABTA
10,413,043.00
10,413,043.00 8/9/2011 50 ON-GOING
TOTAL
10,413,043.00
10,413,043.00
MAIGATARI L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
SUM REVISED COMMENCEMENT STATUS REMARKS
(N) CONTRACT SUM
(N) DATE IN %
1 4006/1 ELECTRIFICATION PROJECT
A SANI ADAMU LTD
MAIGATARI
8,524,542.00 8,524,542.00 27/3/2012 30 ON-GOING
2 2009/7
RENOVATION & FURNISHING OF DOCTORS HOUSE
TANIMU MAGAJI
MAIGARI PHC
1,410,000.00 1,410,000.00 30/7/2012 80 ON-GOING
3 2009/7
CONSTRUCTION OF FRIDAY MOSQUE
A I G VENTURES
BOSUWA 22,932,511.25 22,932,511.25 22/12/2011 80 ON-GOING
TOTAL
32,867,053.25 32,867,053.25
lxxiv
MALAM MADORI L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT
SUM (N) DATE IN %
1 6004/3 CONST. OF JUMAAT MOSQUE
DUTSEN TAURA NIG LTD G/ GABAS
14,505,015.21
14,505,015.21 3/11/2011 90 ON-GOING
2 4006/1 ELECTRIFICATION PROJECT
DUTSEN TAURA NIG LTD SHAYYA
3,765,187.84
3,765,187.84 9/10/2012 75 ON-GOING
3 4006/1 ELECTRIFICATION PROJECT
DUTSEN TAURA NIG LTD AKURYA
4,627,593.41
4,627,593.41 6/5/2012 70 ON-GOING
TOTAL 22,897,796.46
22,897,796.46
KUGAMA L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCMENT
DATE STATU
S REMARK
S
AMOUNT(N
) CONTRACT
SUM (N) DATE IN %
1 5004/
1 CONSTR. 0F JUMAAT MOSQUE S. A. H.
VENTURES MARKE 11,550,467.00
11,550,467.00 10/1/2010 60 ON-GOING
2 5004/
3 CONSTR. 0F CENTRAL MOSQUE
S.T.R ALLIA NIG LTD KAUGAMA
35,782,653.00
35,782,653.00 12/5/2010 65 ON-GOING
3 5001/
3 WALL FENCING OF GGASS MARYAM INVEST KAUGAMA 30,206,878.68
30,206,878.68 7/9/2010 70 ON-GOING
4 5006 ELECTRIFICATION PROJECT MARB ENG &
DRILL JA;E 33,867,100.00
33,867,100.00 11/9/2010 70 ON-GOING
5 6001/
3 COMPLETE WATER SCHEME ADZ NIG LTD SHARKAWA 10,766,175.00
10,766,175.00 11/9/2010 50 ON-GOING
lxxv
6 6001/
6 DRILL/INSTAL. OF 25NO. H/PUMP I.Y DRILLING CO V/LOCATIONS
8,750,000.00
8,750,000.00 17/05/2010 65 ON-GOING
7 6002/
4 CONSTR. OF CULVERT & LATRINE MOHD USMAN
ASKANDU/DAKA
1,523,077.00
1,523,077.00 7/5/2010 56 ON-GOING
Total 132,446,350.68
132,446,350.68
MIGA L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM
(N) DATE IN %
1 7001/13 RENOVATION & INTERLOCKING OF CHAIRMAN HOUSE
ADAMU SARKI MIGA
3,000,000.00
3,000,000.00 30/5/2012 80 ON-GOING
2 5004 CONSTR. OF CENTRAL MOSQUE MEGA LINK MIGA TOWN
35,789,695.52
35,789,695.52 30/5/2012 70 ON-GOING
TOTAL 38,789,695.52
38,789,695.52
SULE TANKARKAR
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT CONTRACT SUM
(N) DATE IN %
1 5001/1 CONSTR. NOMADIC PRIMARY SCHOOL ABDULLAHI DODO SULAWA FULANI
3,621,000.00
3,621,000.00 15/4/2012 45 ON-GOING
2 5001/1 CONSTR. NOMADIC PRIMARY SCHOOL TIJJANI SAYYADI GIDAN MARKE
3,621,000.00
3,621,000.00 8/4/2012 45 ON-GOING
3 5001/1 CONSTR. NOMADIC PRIMARY SCHOOL ABUBAKAR MOHD GWADAYI
3,621,000.00
3,621,000.00 4/4/2012 45 ON-
lxxvi
GOING
4 4006/1 ELECTRIFICATION PROJECT SAHEL &
ASSOCIATE MAI TSAMIYA
42,000,000.00
42,000,000.00 10/6/2010 95 ON-GOING
5 4006/1 ELECTRIFICATION PROJECT PRESTIGE NIG LTD DANYARDA
13,875,109.50
13,875,109.50 10/6/2010 50 ON-GOING
6 4003/1 DRILLING OF 2NO BOREHOLES H/SHATTIMA JSS S/TANKAR
6,285,000.00
6,285,000.00 1/2/2008 60 ON-GOING
7 6001/1 RENOVATION. OF LG STAFF QUARTERS MAIWAKE STAFF QTRS
17,688.92
17,688.92 6/1/2010 60 ON-GOING
8 4006/1 DRILLING OF 2NO M/BOREHOLES A SANI FULAWA SHAFTA/U/MAGAJI
13,420,000.00
13,420,000.00 1/2/2008 85 ON-GOING
9 4006/1 DRILLING OF 24NO. H/PUMP TRIL DRILLING LTD V/LOCATIONS
10,596,000.00
10,596,000.00 1/10/2011 50 ON-GOING
TOTAL 97,056,798.42
97,056,798.42
TAURA L.G
POST CONTRACT PROJECT EVALUATION
S/N. PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT (N) CONTRACT SUM (N) DATE IN %
1 5004/5 CONSTR. OF FRIDAY MOSQUE ABDU SHITTU NALEKO 35,577,217.22 35,577,217.22 20/11/2012 60 ON-GOING
2 6002/1 CONSTR. OF HAND PUMP [ 4No.] AMINU TAKO V/PLACES 1,400,000.00 1,400,000.00 25/11/2012 60 ON-GOING
3 6001/4 CONSTR. OF HAND PUMP [ 6No.] A ABBAS MOHD V/PLACES 2,100,000.00 350,000.00 27/11/2012 60 ON-GOING
4 6001/4 CONSTR. OF HAND PUMP [ 5No.] A GAMBO K V/PLACES
1,750,000.00 350,000.00 27/11/2012 30 ON-GOING
5 6001/1 CONST. OF MOTORISED WATER SCHEME 313 DRILLING NIG
LTD WAYU
17,502,570.42 17,502,570.42 27/07/2010 30 ON-GOING
6 5006/1 COMPLETION OF FRIDAY MOSQUE AA SHUAIBU GURJAWA 911,220.80 911,220.80 27/7/2010 80 ON-GOING
lxxvii
7 6001/1 CONST. OF MOTORISED WATER SCHEME IY DRILLING NIG
LTD L/GURJANYA
15,602,166.42 15,602,166.42 24/11/2010 40 ON-GOING
8 7002/1 RENOVATION OF D/HEAD HOUSE NURA USMAN TAURA
4,180,889.00 4,180,889.00 24/11/2010 70 ON-GOING
9 5001/2 COMPLETION OF WALL FENCING RINGIM GALADANCHI
GGSS TAURA
24,212,588.89 24,212,588.89 24/11/2010 36 ON-GOING
TOTAL 103,236,652.75 #############
RONI L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT(N) CONTRACT SUM
(N) DATE IN %
1 5002/2 CONSTR. OF HEALTH CENTER BELLO HARUNA TUTUBE 2,224,624.50 2,224,624.50 13/8/2012 50 ON-GOING
2 5002/2 CONSTR. OF HEALTH CENTER UMAR SALMA & OTHER WUDDI 2,224,624.50 2,224,624.50 15/82012 50 ON-GOING
3 4006/2 ELECTRIFICATION PROJECT ALH. SHEHU UMAR JANGEFE 20,603,306.59 20,603,306.59 10/7/2012 30 ON-GOING
4 6001/5 COSTR. OF MOTORISED WATER SCHEME ALH GARZALI YAU UNGUWAR KAYA 14,289,966.60 14,289,966.60 12/6/2012 30 ON-GOING
5 5004/1 COMPLETION OF ISLAMIYYA SCHOOL A. YUSIF & OTHERS FANFAN ISKA
RONI 1,000,000.00 1,000,000.00 4/6/2012 30 ON-GOING
6 5004/2 CONSTR. OF JUMAAT MOSQUE YANDOMA VENTURES GORA 3,800,000.00 3,800,000.00 13/8/2012 80 ON-GOING
7 4008/1 CONSTR. OF DRAINAGE ALH. ABDU DAM JATAKA 897,028.16 897,028.16 13/4/2012 30 ON-GOING
8 6001/7 DRILLING OF 6NO. H/PUMP LIMIS BROTHERS CO. V/LOCATIOS 7,081,160.00 7,081,160.00 10/10/2011 70 ON-GOING
9 4008/1 CONSTR. OF CULVERT/DRAINAGE GARBART ENTPRISES AMARYAWA 4,383,496.08 4,383,496.08 3/11/2011 80 ON-GOING
10 5001/4 CONSTR. 3 - SEATER LATRINE GARBART
ENTPRISES AMARYAWA 1,418,798.09 1,418,798.09 3/11/2011 70 ON-GOING
Total
57,923,004.52
57,923,004.52
lxxviii
YAN KWASHI L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT REVISED COMMENCEMENT
DATE STATUS REMARKS
(N) CONTRACT SUM
(N) IN %
1 2009/7 RENOVATION OF STAFF QUARTERS MOHD & others STAFF QUARTERS
12,000,000.00 12,000,000.00 18/04/2012 50 ON-GOING
2 7001/5 FENCING OF KARKARNA GRAVEYARD [ AREWA] MARB ENG SERVICES KARKARNA 9,020,488.00 9,020,488.00 18/04/2012 50 ON-GOING
3 7001/5 ELECTRIFICATION OF PROJECT ELDEE CONS NIG LTD RURUMA TOWN 23,235,280.00 23,235,280.00 15/10/2012 50 ON-GOING
4 6001/7 DRILLING OF HAND PUMP H TADE DRILLING NIG LTD 16NO VARIOS LOCATIONS
13,000,000.00 13,000,000.00 15/10/2012 40 ON-GOING
5 4008/4 CONSTR. OF FEEDER ROAD LAND MGMT NIG LTD MURDEN KASA- MURDEN DAMA
10,000,000.00 10,000,000.00 18/04/2012 50 ON-GOING
6 7001/5 FENCING OF KARKARNA GRAVEYARD [ YAMMA ] MARB ENG SERVICES KARKARA YAMMA 9,248,800.00 9,248,800.00 18/04/2012 50 ON-GOING
7 4008/2 CONSTR. OF FEEDER ROAD[ 6KM] 313 DRILLING NIG LTD KUDA- FIRJI
68,709,178.13 68,709,178.13 15/9/2012 35 ON-GOING
8 4008/2 CONSTR. OF FEEDER ROAD [ 1.1KM Y TEK ENGINEERING CO MURDE-U/MAGAJI
11,590,582.00 11,590,582.00 21/10/2012 85 ON-GOING
Total
156,804,328.13 156,804,328.13
lxxix
KIYAWA L.G
POST CONTRACT PROJECT EVALUATION
S/N HEAD PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED COMMENCEMENTSTATUS REMARKS
(N) CONTRACT SUM (N) DATE IN %
1 6004/3 CONST. OF 5 DAILY PRAYER MOSQUE GARBA ISYAKU LTD KATANGA K/ 1,253,293.30 1,253,293.30 11/10/2012 85 ON-GOING
2 6004/3 CONST. OF 5 DAILY PRAYER MOSQUE IBRAHIM SAKAI D/GOLAWA 635,524 635,524 30/7/2012 80 ON-GOING
3 600/11 COMP. SOLAR WATER SCHEME 313 DRILLING N. LTD DANFUSAN 5,222,810.00 5,222,810 10/11/2012 41 ON-GOING
4 6004/1 VARIATION WORKS OF ANDAZA MOSQUE ANDAZA & SONS LTD ANDAZA 1,927,356.10 1,927,356.10 14/12/2011 80 ON-GOING
5 4006/1 ELECTRIFICATION PROJECT IHSAN DRILLING NIG LYTD GARKON ALLI 12,745,923.81 12,745,923.81 12/12/2011 75 ON-GOING
6 4006/1 ELECTRIFICATION PROJECT IHSAN DRILLING NIG LYTD MAJIYAWA 9,009,372.47 9,009,372.47 2/4/2011 75 ON-GOING
7 4006/1 ELECTRIFICATION PROJECT IHSAN DRILLING NIG LYTDFAKE- GIDAN BAYI 10,672,878.57 10,672,878.57 3/4/2011 80 ON-GOING
8 6001/5 DRILLING OF 6NO. BORE HOLE BASHAR V/PLACES 3,876,390.00 3,876,390.00 3/11/2011 50 ON-GOING
9 6004/1 CONSTRUCTION OF JUMAAT MOSQUE A A KWAIMAWA BAKATA 4,397,776.65 4,397,776.65 3/11/2011 80 ON-GOING
10 6001/3 CONSTRUCTION OF OPEN WELL UBA KATUKA K/SHIDI 225,187.00 225,187.00 2/4/2011 0 NOT STARTED
11 6001/3 CONSTRUCTION OF OPEN WELL A HARUNA TAKANADU 235,531.00 235,531.00 5/5/2011 0 NOT STARTED
12 6001/3 DRILLING OF 6NO. BORE HOLE IDRITH AUYO TSADOWA 310,000.00 310,000.00 7/7/2011 O NOT STARTED
13 6004/1 COMPLETION OF JUMAAT MOSQUE ANDAZA & SONS LTD ANDAZA 8,201,673.90 8,201,673.90 18/08/2011 39 ON-GOING
14 6004/1 RENOVATION OF CENTRAL MOSQUE SABO KWARE KIYAWA 6,375,272.12 6,375,272.12 26/07/2010 40 ON-GOING
15 5002/1 CONSTRUCTION OF DISPENSARY A UBA NABERE KAGARA 3,556,765.77 3,556,765.77 26/07/2010 90 ON-GOING
16 5001/2 CONSTRUCTION OF ISLAMIYYA SCHOOL A SALISU ZERO KIYAWA 3,182,428.27 3,182,428.27 5/11/2010 91 ON-GOING
TOTAL 71,828,182.96 71,828,182.96
lxxx
RINGIN L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR
LOCATION CONTRACT REVISED
COMMENCEMENT
STATUS
REMARKS
HEAD AMOUNT(N) CONTRACT SUM
(N) DATE IN %
1 4006/
1 ELECTRIFICATION PROJECT
SURAJO DUNGU GASKOLE 8,635,182.67 8,635,182.67 3/1/2012 85
ON-GOING
2 7001/
6 RENOVATION OF INEC OFFICE
SALMANU UBA RINGIM
3,281,611.63 3,281,611.63 10/1/2012 96
ON-GOING
TOTAL
11,916,794.30 11,916,794.30
KAZAURE L.G
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED COMMENCEMENT STATUS REMARKS
AMOUNT(N) CONTRACT SUM
(N) DATE IN %
1 5004/2 CONSTR. OF 1 BLOCK ISLAMIYYA SCHOOL
HASSAN ADAMU
GIDAN GONA
1,518,000.00 1,518,000.00 3/6/2008 90
ON-GOING
2 7002/3 CONSTR. OF DISTRICT HEAD HOUSE MAN HAB GLOB DANDI
21,931,456.47 21,931,456.47 27/7/2012 50
ON-GOING
3 7002/3 PURCH. OF 18KVA GEN & B/HOLE
BABANGIDA FACI GANGULI
3,637,475.00 3,637,475.00 27/7/2012 90
ON-GOING
4 5001/2 CONSTR. OF CLASSROOM BLOCK
KURTU GEN. ENT
TSOFON KAFI
2,965,934.00 2,965,934.00 8/7/2010 50
ON-GOING
5 5001/2 CONSTR. OF CLASSROOM BLOCK
OPEN WAYES NIG.
KANTI KUNCHI
2,965,934.00 2,965,934.00 8/7/2010 90
ON-GOING
lxxxi
6 5001/2 CONSTR. OF CLASSROOM BLOCK BABA AFFA KARAFTAYI
1,921,570.00 1,921,570.00 15/12/2011 70
ON-GOING
TOTAL 34,940,369.47 34,940,369.47
lxxxii
SECTION (C)
PRE CONTRACTORS EVALUATION
JANUARY-DECEMBER, 2012
lxxxiii
END OF YEAR REPORT JANUARY - DECEMBER,2012 PRE- CONTRACT EVALUATION GENERAL SUMMARY
PRE-CONTRACT PROJECT EVALUATION
S/NO LOCAL GOVERNMENT NO OF PROPOSAL SUBMITTED
QUOTTED SUM (#)
VETTED SUM (#) SAVING/INCREASE (#)
REMARK
1 AUYO 6 92,352,197.64 90,762,937.23 1,589,260.41 saving due to vetting
2
BABURA
1 6,835,731.06 9,934,663.71 (3,098,932.65)
Increase due to rate vetting
3 BIRNIWA 6 77,063,326.88 71,078,728.08 5,984,598.80 saving due to vetting
4 BIRNIN KUDU 5 86,579,090.00 75,586,186.13 10,992,903.87 saving due to vetting
5 BUJI 28 145,228,369.19 131,069,237.13 14,159,132.06 Saving due to rate vetting
6 DUTSE Nill 0.00 0.00 0.00
7 GARKI 3 52,403,210.33 46,936,089.69 5,467,120.64 saving due to vetting
8 GAGARAWA 8 72,924,645.80 79,425,925.70 (6,501,279.90) Increase due to rate vetting
9 GUMEL 4 136,467,268.34 148,096,633.96 (11,629,365.62) Increase due to rate vetting
10 GURI 4 98,647,838.92 99,099,534.40 (451,695.48) Increase due to rate vetting
11 GWARAM 2 28,362,021.14 33,418,598.69 (5,056,577.55) Increase due to rate vetting
12 GWIWA 16 115,090,919.76 112,776,161.02 2,314,758.74 saving due to vetting
13 HADEJIA NILL 0.00 0.00 0.00
14 JAHUN 6 55,107,509.37 53,061,795.72 2,045,713.65 saving due to vetting
15 KAUGAMA NILL 0.00 0.00 0.00
16 KAFIN-HAUSA 13 163,472,703.80 158,851,991.59 4,620,712.21 saving due to vetting
17 KAZAURE 1 20,450,034.51 21,931,456.47 (1,481,421.96) Increase due to rate vetting
18 KIRI-KASAMMA NILL 0.00 0.00 0.00
19 KIYAWA 14 116,446,640.27 122,248,561.96 (5,801,921.69) Increase due to rate vetting
20 MALAM-MADORI 1 5,550,000.00 5,550,000.00 0.00
21 MAIGATARI NILL 0.00 0.00 0.00
22 MIGA 36 142,121,870.93 145,721,888.76 (3,600,017.83) Increase due to rate vetting
lxxxiv
23 RINGIM 1 8,091,374.00 7,975,769.03 115,604.97 saving due to vetting
24 RONI 2 40,262,503.97 34,920,273.19 5,342,230.78 saving due to vetting
25 SULE-TANKARKAR NILL 0.00 0.00 0.00
26 TAURA 1 33,318,310.92 35,577,217.22 (2,258,906.30) Increase due to rate vetting
27 YANKWASHI 1 26,823,097.00 23,235,280.81 3,587,816.19 saving due to vetting
GRAND TOTAL 159 1,523,598,663.83 1,507,258,930.49 16,339,733.34 saving due to vetting
AUYO L.G
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#) SAVING/ INCREASE (#)
REMARKS
1 25/6/2012 Constr. of 7 bedroom duplex house Auyo 36,873,247.00 35,371,392.02 1,501,854.98
2 12/7/2012 Electrification project Shiyo 19,517,595.64 18,162,995.13 1,354,600.51
3 12/7/2012 Complete motorised water scheme Kalgwa 9,471,742.87 11,212,584.10 (1,740,841.23)
4 12/7/2012 Complete motorised water scheme Moran 9,174,067.87 8,727,066.16 447,001.71
5 12/7/2012 Electrification project Kafeje 6,212,527.54 6,757,187.22 (544,659.68)
6 12/7/2012 Construction of peadiatric ward Auyo 11,103,016.72 10,531,712.60 571,304.12
CARRIED TO GENERAL SUMMARY 92,352,197.64 90,762,937.23 1,589,260.41
lxxxv
END OF YEAR REPORT JANUARY - DECEMBER,2012 BABURA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM # VETTED SUM SAVING/ INCREASE # REMARK
1 28/6/2012 Construction of slaughter house kanya Babba 6,835,731.06 9,934,663.71 (3,098,932.65)
Carried to Summary 6,835,731.06 9,934,663.71 (3,098,932.65)
END OF YEAR REPORT JANUARY - DECEMBER,2012 BIRNIWA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM (#) VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 31/10/2012 Electrification project Bursali 7,292,214.37 6,599,931.20 692,283.17
2 31/10/2012 Electrification project Dolen Kwana 25,634,462.52 23,599,542.42 2,034,920.10
3 31/10/2012 Electrification project Matara uku 12,634,330.37 12,677,291.00 (42,960.63)
4 31/10/2012 Electrification project Gabasmari 6,560,805.06 6,213,827.82 346,977.24
5 31/10/2012 Complete water scheme Walawa 12,520,757.28 11,323,305.82 1,197,451.46
6 31/10/2012 Complete water scheme Beguwa 12,420,757.28 10,664,829.82 1,755,927.46
lxxxvi
CARRIED TO GENERAL SUMMARY 77,063,326.88 71,078,728.08 5,984,598.80
END OF YEAR REPORT JANUARY - DECEMBER,2012 BIRNIN-KUDU LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 29/11/2012 Land compensation Birnin Kudu 10,710,000.00 10,710,000.00 0.00
2 29/11/2012 Land compensation Kiyako 14,120,000.00 13,130,000.00 990,000.00
3 29/11/2012 Completion of juma'at mosque Kwari 14,334,545.00 12,587,364.88 1,747,180.12
4 29/11/2012 Renovation of catering rest house Birnin Kudu 28,334,545.00 20,773,321.25 7,561,223.75
5 29/11/2012 Interlocking of central mosque Birnin Kudu 19,080,000.00 18,385,500.00 694,500.00
CARRIED TO GENERAL SUMMARY 86,579,090.00 75,586,186.13 10,992,903.87
lxxxvii
END OF YEAR REPORT JANUARY - DECEMBER,2012 BUJI LOCAL GOVERNMENT PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 23/5/2012 PHCN connection Gantsa 4,347,966.32 4,611,123.45 (263,157.13)
2 23/5/2012 Improvement of water supply Yayarin Tukur 6,301,882.50 6,119,897.16 181,985.34
3 23/5/2012 Improvement of water supply Buji 13,481,467.50 10,989,934.31 2,491,533.19
4 23/5/2012 Drilling of Hand pumps 10 wards 9,101,925.00 6,981,502.50 2,120,422.50
5 23/5/2012 Complete water scheme Gantsa 16,204,516.50 13,242,939.93 2,961,576.57
6 10/7/2012 Complete water scheme Karanjau 11,805,485.50 11,426,445.00 379,040.50
7 10/7/2012 Complete water scheme Kawaya 13,228,140.00 11,923,261.25 1,304,878.75
8 10/7/2012 Construction of Friday mousque Lelen kudu 12,258,550.78 11,286,051.11 972,499.67
9 10/7/2012 Construction V.I.P. toilet Gantsa 797,998.42 616,075.95 181,922.47
10 10/7/2012 Construction V.I.P. toilet Sagu 797,998.42 616,075.95 181,922.47
11 5/12/2012 Construction of 4NO market stall Gwadayi 1,243,053.93 1,250,634.62 (7,580.69)
12 5/12/2012 Construction of 4NO market stall Sagu 1,243,053.93 1,250,634.62 (7,580.69)
13 5/12/2012 Construction of 4NO market stall Gantsa 1,243,053.93 1,250,634.62 (7,580.69)
14 5/12/2012 Construction of 4NO market stall Buji 1,243,053.93 1,250,634.62 (7,580.69)
lxxxviii
15 5/12/2012 Construction of daily prayer mosque Kwalabe 741,849.74 836,181.12 (94,331.38)
16 5/12/2012 Construction of daily prayer mosque Rigar gada 741,849.74 836,181.12 (94,331.38)
17 5/12/2012 Construction of daily prayer mosque Gambasha 741,849.74 836,181.12 (94,331.38)
18 5/12/2012 Construction of daily prayer mosque Tata 741,849.74 836,181.12 (94,331.38)
19 5/12/2012 Construction of daily prayer mosque Unguwar Makera 741,849.74 836,181.12
(94,331.38)
20 5/12/2012 Construction of daily prayer mosque Tsangaya 1,543,451.17 1,648,372.40 (104,921.23)
21 5/12/2012 Construction of daily prayer mosque Gwadayi 1,543,451.17 1,648,372.40 (104,921.23)
22 5/12/2012 Construction of Distric Head house phase iii Gantsa 13,225,795.80 11,214,958.81 2,010,836.99
23 5/12/2012 Construction of 16NO lockup shops Sara 14,348,481.84 10,672,817.24 3,675,664.60
24 5/12/2012 Construction of Juma'at mousque Madabe 11,286,051.00 11,339,700.59 (53,649.59)
25 5/12/2012 Construction of pit laterine Unguwar
Maina 616,075.95 616,075.95 -
26 5/12/2012 Construction of pit laterine Gwadayi 616,075.95 616,075.95 -
27 5/12/2012 Construction of pit laterine Yayarin Tukur 616,075.95 616,075.95 -
28 5/12/2012 Construction of classroom block Jaka 4,425,515.00 5,700,037.15 (1,274,522.15)
CARRIED TO GENERAL SUMMARY 145,228,369.19 131,069,237.13 14,159,132.06
lxxxix
END OF YEAR REPORT JANUARY - DECEMBER,2012 DUTSE LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#) SAVING/ INCREASE (#) REMARK
1
2
3
4
5
CARRIED TO GENERAL SUMMARY 0.00 0.00 0.00
END OF YEAR REPORT JANUARY - DECEMBER,2012 GARKI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 15/10/2012 Electrification project phase 1 Muku 14,966,120.85 15,404,085.65 (437,964.80)
2 15/10/2012 G.G.S.S. wall fencing phase II Garki 19,283,694.06 15,789,537.56 3,494,156.50
3 15/10/2012 G.G.S.S. wall fencing phase III Garki 18,153,395.42 15,742,466.48 2,410,928.94
xc
CARRIED TO GENERAL SUMMARY 52,403,210.33 46,936,089.69 5,467,120.64
END OF YEAR REPORT JANUARY - DECEMBER,2012 GAGARAWA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 27/04/2012 provision of complete motorised water scheme (1,803M)
Mai tsintsiya 7,065,702.00 8,365,601.68 (1,299,899.68)
2 27/04/2012 provision of complete motorised water scheme (891M) Bula 7,065,702.00 7,617,161.68 (551,459.68)
3 27/04/2012 Electrification project
Mai tsintsiya - Mai Adua 29,757,704.00 34,239,299.96 (4,481,595.96)
4 12/9/2012 Solar powered water scheme Jagindi 7,344,000.00 6,330,234.75 1,013,765.25
5 12/9/2012 Construction of women centre Gagarawa 5,679,969.00 6,685,142.97 (1,005,173.97)
6 12/9/2012 Construction of Juma'at mosque Gayawar Mallam 8,943,929.00 8,317,814.34 626,114.66
7 12/9/2012 Construction of classroom block Dogondawa 3,533,819.90 3,935,335.16 (401,515.26)
8 12/9/2012 Construction of classroom block Sarkin Gabas 3,533,819.90 3,935,335.16 (401,515.26)
CARRIED TO GENERAL SUMMARY 72,924,645.80 79,425,925.70 (6,501,279.90)
xci
END OF YEAR REPORT JANUARY - DECEMBER,2012 GUMEL LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 16/04/2012 Construction of modern motor park Gumel 38,692,254.18 43,416,895.68 (4,724,641.50)
2 16/04/2012 Construction of Grave yard wall fencing at Abuja quarters Gumel 6,716,330.82 7,071,428.23 (355,097.41)
3 10/7/2012 Re- construction of shopping complex (variation ) Gumel 56,669,450.34 60,025,385.66 (3,355,935.32)
4 10/7/2012 Re- construction of senior staff quarters type I , II & III, (variation ) Gumel 34,389,233.00 37,582,924.39 (3,193,691.39)
CARRIED TO GENERAL SUMMARY 136,467,268.34 148,096,633.96 (11,629,365.62)
xcii
END OF YEAR REPORT JANUARY - DECEMBER,2012 GURI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM VETTED SUM
SAVING/ INCREASE (#) REMARK
1 25/6/2012 Complete water scheme Giryo 10,846,076.05 7,429,821.52 3,416,254.53
2 25/6/2012 Complete water scheme Dole 10,846,076.05 8,467,083.52 2,378,992.53
3 25/6/2012 Construction of feeder road Guri - Zigo 44,999,146.08 50,903,350.88 (5,904,204.80)
4 25/6/2012 Electrification project Guri - Tukuikui 31,956,540.74 32,299,278.48
(342,737.74)
CARRIED TO GENERAL SUMMARY 98,647,838.92 99,099,534.40 (451,695.48)
xciii
END OF YEAR REPORT JANUARY - DECEMBER,2012 GWARAM LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/ INCREASE (#) REMARK
1 20/12/2012 Construction of modern central mosque Jingino 9,342,464.75 10,470,012.15 (1,127,547.40)
2 20/04/2012 Construction of mini stadium (phase III) Kila 19,019,556.39 22,948,586.54 (3,929,030.15)
CARRIED TO GENERAL SUMMARY 28,362,021.14 33,418,598.69 (5,056,577.55)
END OF YEAR REPORT JANUARY - DECEMBER,2012 GWIWA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM
(#) VETTED SUM (#) SAVING/INCREASE (#) REMARK
1 23/1/2012 Electrification project Unguwar Ganji 9,434,924.62 9,397,465.16 37,459.46
2 23/1/2012 Electrification project
Sabon Garin Gawo 9,511,580.40 8,400,444.89 1,111,135.51
xciv
3 23/1/2012 Construction of Friday mosque Zaumar Gauraye 5,576,445.00 5,724,098.47 (147,653.47)
4 23/1/2012 Construction of Friday mosque Gutai 5,576,445.00 5,724,098.47 (147,653.47)
5 23/1/2012 Construction of Friday mosque Dabi 5,576,445.00 5,724,098.47 (147,653.47)
6 6/7/2012 Construction of line drainage Daragi 7,863,648.00 6,733,474.65 1,130,173.35
7 6/7/2012 Construction of one block of classroom Wailare 3,652,737.10 4,128,705.94 (475,968.84)
8 6/7/2012 Construction of Friday mosque Maraganta 5,724,098.47 5,996,707.85 (272,609.38)
9 5/12/2012 Construction of Friday mosque Yola 5,996,707.85 5,996,707.85 0.00
10 5/12/2012 Construction of drainage Rorau 3,631,832.40 3,459,318.66 172,513.74
11 5/12/2012 Construction of 1 block of 2 classroom Daragi 4,128,705.64 4,128,705.64 0.00
12 5/12/2012 Construction of 1 block of 2 classroom Zongon Kanya 4,128,705.64 4,128,705.64 0.00
13 5/12/2012 Renovation of SDP secretariate Roni 4,964,526.00 5,813,041.03 (848,515.03)
14 29/10/2012 Electrification project Burma - Dabi 23,786,570.64 22,506,803.67 1,279,766.97
15 24/12/2012 Purchase of Hillux Toyota Gwiwa 5,550,000.00 5,550,000.00 0.00
16 31/12/2012 Construction of feeder road (1.7km) Daurawa - Tinkishi 9,987,548.00 9,363,784.63 623,763.37
CARRIED TO GENERAL SUMMARY 115,090,919.76 112,776,161.02 2,314,758.74
END OF YEAR REPORT JANUARY - DECEMBER,2012 HADEJIA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM VETTED SUM SAVING/INCREASE (#) REMARK
xcv
END OF YEAR REPORT JANUARY - DECEMBER,2012 JAHUN LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
1 12/6/2012
Construction of complete motorised wafer scheme and reticulation work (1,383m)
Bagamaru village 13,336,494.49 11,306,386.74 2,030,107.75
xcvi
2 12/6/2012
Construction of complete motorised wafer scheme and reticulation work (2,596m)
G/Dango village 13,465,634.49 13,407,705.30 57,929.19
3 12/6/2012 Reticulation work (2,633m) Damutawa 5,344,500.00 5,004,307.88 340,192.12
4 12/6/2012 Upgrading/Reticulation of water scheme Tazara 7,993,794.49 8,418,259.30 (424,464.81)
5 12/6/2012 Upgrading/Reticulation of water scheme Kulluru 7,267,085.90 7,225,136.50 41,949.40
6 12/6/2012 Construction of 22No Hand pumps at 22 villages
22No villages 7,700,000.00 7,700,000.00 0.00
CARRIED TO GENERAL SUMMARY 55,107,509.37 53,061,795.72 2,045,713.65
END OF YEAR REPORT JANUARY - DECEMBER,2012 KAUGAMA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#) SAVING/INCREASE (#) REMARK
xcvii
Carried to summary 0.00 0.00 0.00
END OF YEAR REPORT JANUARY - DECEMBER,2012 KAFIN-HAUSA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#)
SAVING/INCREASE (#) REMARK
1 16/03/2012 Complete motorised water scheme Tarabu Gabas 9,152,543.04 7,785,187.56
1,367,355.48
2 16/03/2012 Solar powered water scheme Walori 10,336,192.32 9,085,160.00 1,251,032.32
3 16/03/2012 Solar powered water scheme Gubusan 10,336,192.32 8,699,718.85 1,636,473.47
4 16/03/2012 Electrification project Malori 14,590,941.48 11,408,422.59 3,182,518.89
5 16/03/2012 Electrification project Garin - Magaji 15,271,091.76 10,007,145.59
5,263,946.17
6 23/05/2012 Electrification project Dumadimin Toka 27,677,586.72 32,622,579.87
(4,944,993.15)
7 23/05/2012 Electrification project (kore phase II) Kore 13,770,625.26 14,134,934.10 (364,308.84)
8 23/05/2012 Renovation of 2No 3 bedroom Bungalow Kafin Hausa 12,144,081.34 11,972,003.12
172,078.22
9 23/05/2012 Renovation of 1No 5 bedroom Bungalow Kafin Hausa 6,615,902.24 6,568,058.20
47,844.04
xcviii
10 23/05/2012 Renovation of 1No 3 bedroom semi-detached house Kafin Hausa 6,829,213.19 7,185,219.36
(356,006.17)
11 23/05/2012 Construction of comprehensive health centre Kwatalo 16,328,294.88 17,234,777.85
(906,482.97)
12 23/05/2012 Construction of comprehensive health centre
Juma'ar Atsir 16,328,294.88 17,234,777.85
(906,482.97)
13 23/05/2012 Construction of Market stall Kafin Hausa 4,091,744.37 4,914,006.65 (822,262.28)
CARRIED TO GENERAL SUMMARY 163,472,703.80 158,851,991.59 5,442,974.49
END OF YEAR REPORT JANUARY - DECEMBER,2012 KAZAURE LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM # VETTED SUM #
SAVING/INCREASE # REMARK
1 16/03/2012 Construction of Distric Head House Dandi 20,450,034.51 21,931,456.47 (1,481,421.96)
xcix
Carried to summary 20,450,034.51 21,931,456.47 (1,481,421.96)
END OF YEAR REPORT JANUARY - DECEMBER,2012 KIRI-KASAMMA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
c
CARRIED TO GENERAL SUMMARY 0.00 0.00 0.00
END OF YEAR REPORT JANUARY - DECEMBER,2012 KIYAWA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
1 23/1/2012 Construction of Islamiyya school Dangoli 4,235,485.00 4,570,072.70 (334,587.70)
ci
2 23/1/2012 Construction of Islamiyya school Shuwarin 4,235,485.00 4,570,072.70 (334,587.70)
3 23/1/2012 Construction of Islamiyya school Katuka 4,235,485.00 4,570,072.70 (334,587.70)
4 23/1/2012 Construction of Islamiyya school Maje 4,235,485.00 4,570,072.70 (334,587.70)
5 4/6/2012. Construction of Islamiyya school Kiyawa 4,570,072.70 4,994,791.00 (424,718.30)
6 4/6/2012. Construction of Islamiyya school Harba 4,570,072.70 4,994,791.00 (424,718.30)
7 4/6/2012. Construction of Juma'at mosque Akar 4,397,776.60 4,888,798.25 (491,021.65)
8 4/6/2012. Construction of Juma'at mosque S/Gari 4,397,776.60 4,888,798.25
(491,021.65)
9 22/1/2012.
Construction Distric Head house phase II Shuwarin 16,079,346.43 16,365,165.18 (285,818.75)
10 22/1/2012. Construction of motor park and 8No
shop Katuka 11,793,732.00 12,428,664.63 (634,932.63)
11
30/11/2012.
Construction Distric Head house phase I Shuwarin 14,645,216.12 17,155,084.97 (2,509,868.85)
12
30/11/2012.
Construction of Islamiyya school Shatari Sabuwa 4,570,072.70 5,281,928.66
(711,855.96)
13
30/11/2012.
Electrification project Malamawa Maharba 26,649,960.00 27,213,238.21
(563,278.21)
14 30/11/2012.
Construction of motor park Balago 7,830,674.42 5,757,011.01 2,073,663.41
CARRIED TO GENERAL SUMMARY 116,446,640.27 122,248,561.96 (5,801,921.69)
cii
END OF YEAR REPORT JANUARY - DECEMBER,2012 MALAM-MADORI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#)
REMARK
1 24/1/2012. Supply of Toyota Hilux 4WD DC pectrol S/S with radio cassette.
malam madori 5,550,000.00 5,550,000.00 0.00
Carried to summary 5,550,000.00 5,550,000.00 0.00
END OF YEAR REPORT JANUARY - DECEMBER,2012 MAIGATARI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
ciii
END OF YEAR REPORT JANUARY - DECEMBER,2012 MIGA LOCAL GOVERNMENT PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT PROPOSED LOCATION
QUOTED SUM (#)
VETTED SUM (#) SAVING/INCREASE (#)
REMARK
1 19/1/2012 Electrification project Tsagaiwa 32,727,703.71 33,494,450.81 (766,747.10)
2 19/1/2012 Electrification project Jamaga 20,554,279.25 22,794,216.48 (2,239,937.23)
civ
3 30/8/2012 Electrification project Kirnade 11,598,428.68 12,213,783.06 (615,354.38)
4 30/8/2012 Construction of central mosque Miga 37,455,881.05 35,789,695.52 1,666,185.53
5 24/5/2012 Complete water scheme Yanduna 11,338,307.00 12,401,467.84 (1,063,160.84)
6 24/5/2012 Construction of 9 bedroom staff house Miga 9,832,950.24 9,907,677.55 (74,727.31)
7 24/5/2012 Construction of Dairly prayer mosque Dawa 1,212,821.70 1,291,041.03 (78,219.33)
8 24/5/2012 Construction of Dairly prayer mosque Namako 1,212,821.70 1,291,041.03 (78,219.33)
9 24/5/2012 Construction of Dairly prayer mosque Majirga 1,212,821.70 1,291,041.03 (78,219.33)
10 24/5/2012 Construction of Dairly prayer mosque Zugawa 1,212,821.70 1,291,041.03 (78,219.33)
11 24/5/2012 Construction of Dairly prayer mosque Kadirawa 1,212,821.70 1,291,041.03 (78,219.33)
12 24/5/2012 Construction of Dairly prayer mosque Dabakan 1,212,821.70 1,291,041.03 (78,219.33)
13 24/5/2012 Construction of Dairly prayer mosque Gidan Tsamiya 1,212,821.70 1,291,041.03 (78,219.33)
14 24/5/2012 Construction of Dairly prayer mosque Gamatan 1,212,821.70 1,291,041.03 (78,219.33)
15 24/5/2012 Construction of Dairly prayer mosque Maiganjara 1,212,821.70 1,291,041.03 (78,219.33)
16 24/5/2012 Construction of Dairly prayer mosque Mudiga 1,212,821.70 1,291,041.03 (78,219.33)
17 24/5/2012 Construction of hand pump 44mm depth Wailaba 351,397.00 333,219.60 18,177.40
18 24/5/2012 Construction of hand pump 44mm depth Gidan Ya'u 351,397.00 333,219.60 18,177.40
19 24/5/2012 Construction of hand pump 44mm depth Jamaga 351,397.00 333,219.60 18,177.40
20 24/5/2012 Construction of hand pump 44mm depth Tsagaiwa 351,397.00 333,219.60 18,177.40
21 24/5/2012 Construction of hand pump 44mm depth Mujirga 351,397.00 333,219.60 18,177.40
22 24/5/2012 Construction of hand pump 44mm depth Kadirawa 351,397.00 333,219.60 18,177.40
23 24/5/2012 Construction of hand pump 44mm depth Sarawuya 351,397.00 333,219.60 18,177.40
24 24/5/2012 Construction of hand pump 44mm depth Maiganjara 351,397.00 333,219.60 18,177.40
25 24/5/2012 Construction of hand pump 44mm depth Limamai 351,397.00 333,219.60 18,177.40
26 24/5/2012 Construction of hand pump 44mm depth Gidan NaAllah 351,397.00 333,219.60 18,177.40
C/F
139,149,736.93 142,843,897.56 (3,694,160.63)
22a
cv
B/F 139,149,736.93 142,843,897.56 (3,694,160.63)
27 24/5/2012 Construction of hand pump 44mm depth Juma 351,397.00 333,219.60 18,177.40
28 24/5/2012 Construction of hand pump 44mm depth Duja 351,397.00 333,219.60 18,177.40
29 24/5/2012 Construction of hand pump 44mm depth Walawa 351,397.00 333,219.60 18,177.40
30 24/5/2012 Construction of hand pump 44mm depth Ganuwa 351,397.00 333,219.60 18,177.40
31 24/5/2012 Construction of hand pump 22mm depth Gidan Garja 261,091.00 257,518.80 3,572.20
32 24/5/2012 Construction of hand pump 22mm depth Masewa 261,091.00 257,518.80 3,572.20
33 24/5/2012 Construction of hand pump 22mm depth Garbo 261,091.00 257,518.80 3,572.20
34 24/5/2012 Construction of hand pump 22mm depth Sabuwar jigawa 261,091.00 257,518.80 3,572.20
35 24/5/2012 Construction of hand pump 22mm depth Gidan sarki 261,091.00 257,518.80 3,572.20
36 24/5/2012 Construction of hand pump 22mm depth Jigande 261,091.00 257,518.80 3,572.20
CARRIED TO GENERAL SUMMARY 142,121,870.93 145,721,888.76 (3,600,017.83)
END OF YEAR REPORT JANUARY - DECEMBER,2012 RINGIM LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
cvi
1 16/03/2012 Complete motorised water scheme Dogaji 8,091,374.00 7,975,769.03 115,604.97
CARRIED TO GENERAL SUMMARY 8,091,374.00 7,975,769.03 115,604.97
END OF YEAR REPORT JANUARY - DECEMBER,2012 RONI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM VETTED SUM
SAVING/INCREASE (#)
REMARK
1 3/7/2012 Electrification project Jangefe 24,459,391.68 20,630,306.59 3,829,085.09
2 3/7/2012 Complete water scheme Unguwar Kaya 15,803,112.29 14,289,966.60 1,513,145.69
CARRIED TO GENERAL SUMMARY 40,262,503.97 34,920,273.19 5,342,230.78
cvii
END OF YEAR REPORT JANUARY - DECEMBER,2012 SULETANKARKAR LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
CARRIED TO GENERAL SUMMARY 0.00 0.00 0.00
cviii
END OF YEAR REPORT JANUARY - DECEMBER,2012 TAURA LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION QUOTED SUM VETTED SUM
SAVING/INCREASE (#)
REMARK
1 2/2/2012 Construction of Friday mosque Nahuce 33,318,310.92 35,577,217.22 (2,258,906.30)
CARRIED TO GENERAL SUMMARY 33,318,310.92 35,577,217.22 (2,258,906.30)
END OF YEAR REPORT JANUARY - DECEMBER,2012 YANKWASHI LOCAL GOVERNMENT
PRE-CONTRACT PROJECT EVALUATION
S/NO DATE PROJECT
PROPOSED LOCATION
QUOTED SUM (#) VETTED SUM (#)
SAVING/INCREASE (#) REMARK
1 11/6/2012 Electricfication project Ruruma 26,823,097.00 23,235,280.81 3,587,816.19
cix
CARRIED TO GENERAL SUMMARY 26,823,097.00 23,235,280.81 3,587,816.19
L.G CAPITAL RELEASE
CONTRACT AWARDED SUMMAY SHEET JANUARY - DECEMBER, 2012
S/NO LOCAL GOVERNMENT
APPROVED CAPITAL BUDGET
OTHER CAPITAL DEDUCTION
DIRECT EXECUTED PROJECT
(INCLUDING OTHER CAPITAL
DEDUCTION) % IMPLIMENTATION
1 AUYO 566,377,191.00 153,386,817.91 215,432,196.89 #REF!
2 BABURA 575,360,149.00 193,969,786.66 228,120,675.80 #REF!
3 BIRNIWA 648,268,443.00 217,153,456.91 367,455,221.24 #REF!
4 BIRNIN KUDU 771,576,614.00 217,821,041.91 363,657,935.47 #REF!
5 BUJI 835,504,009.00 148,132,625.91 291,692,894.36 #REF!
cx
6 DUTSE 735,175,226.00 204,962,765.91 251,073,625.67 #REF!
7 GARKI 491,596,789.00 165,764,121.91 238,959,759.91 #REF!
8 GAGARAWA 488,146,104.00 139,054,677.91 185,066,884.91 #REF!
9 GUMEL 511,778,353.00 154,366,437.91 268,375,328.34 #REF!
10 GURI 771,543,596.00 153,549,845.91 310,777,443.07 #REF!
11 GWARAM 724,495,285.00 249,254,691.99 452,252,385.13 #REF!
12 GWIWA 629,230,431.00 158,564,225.91 365,512,803.95 #REF!
13 HADEJIA 460,349,419.00 143,729,921.91 180,040,169.68 #REF!
14 JAHUN 718,978,830.00 186,537,657.91 326,136,615.05 #REF!
15 KAUGAMA 508,228,076.00 156,570,945.91 182,570,945.91 #REF!
16 KAFIN-HAUSA 773,872,381.00 203,262,477.91 264,910,746.63 #REF!
17 KAZAURE 453,479,893.00 164,451,609.91 216,375,474.91 #REF!
18 KIRI-KASAMMA 583,256,604.00 171,494,553.91 341,016,400.50 #REF!
19 KIYAWA 649,986,403.00 214,920,525.91 305,922,612.54 #REF!
20 MALAM-MADORI 445,835,137.00 168,572,609.91 205,516,191.16 #REF!
21 MAIGATARI 730,204,814.00 216,035,509.91 389,952,131.28 #REF!
22 MIGA 653,372,784.00 158,759,225.91 318,778,043.78 #REF!
23 RINGIM 494,299,238.00 231,587,373.29 268,775,737.25 #REF!
24 RONI 449,571,829.00 163,321,462.91 231,419,859.19 #REF!
25 SULE-TANKARKAR 590,644,567.00 159,326,421.91 190,189,421.91 #REF!
26 TAURA 476,607,593.00 163,880,597.91 244,044,846.68 #REF!
27 YANKWASHI 505,038,749.00 151,399,221.91 350,289,476.84 #REF!
TOTAL 16,242,778,507.00 4,809,830,613.78 7,554,315,828.05
PRE CONTRACTOR CHART
S/NO LOCAL GOVERNMENT
QUOTTED SUM (#) VETTED SUM (#)
cxi
1 AUYO 92,352,197.64 90,762,937.23
2 BABURA 6,835,731.06 9,934,663.71
3 BIRNIWA 77,063,326.88 71,078,728.08
4 BIRNIN KUDU 86,579,090.00 75,586,186.13
5 BUJI 145,228,369.19 131,069,237.13
6 DUTSE 0.00 0.00
7 GARKI 52,403,210.33 46,936,089.69
8 GAGARAWA 72,924,645.80 79,425,925.70
9 GUMEL 136,467,268.34 148,096,633.96
10 GURI 98,647,838.92 99,099,534.40
11 GWARAM 28,362,021.14 33,418,598.69
12 GWIWA 115,090,919.76 112,776,161.02
13 HADEJIA 0.00 0.00
14 JAHUN 55,107,509.37 53,061,795.72
15 KAUGAMA 0.00 0.00
16 KAFIN-HAUSA 163,472,703.80 158,851,991.59
17 KAZAURE 20,450,034.51 21,931,456.47
18 KIRI-KASAMMA 0.00 0.00
19 KIYAWA 116,446,640.27 122,248,561.96
20 MALAM-MADORI 5,550,000.00 5,550,000.00
21 MAIGATARI 0.00 0.00
22 MIGA 142,121,870.93 145,721,888.76
23 RINGIM 8,091,374.00 7,975,769.03
24 RONI 40,262,503.97 34,920,273.19
25 SULE-TANKARKAR 0.00 0.00
26 TAURA 33,318,310.92 35,577,217.22
27 YANKWASHI 26,823,097.00 23,235,280.81
1,523,598,663.83 1,507,258,930.49
cxii
cxiii
92
,35
2,1
97
.64
6,8
35
,73
1.0
6
77
,06
3,3
26
.88
86
,57
9,0
90
.00
14
5,2
28
,36
9.1
9
0.0
0
52
,40
3,2
10
.33
72
,92
4,6
45
.80
13
6,4
67
,26
8.3
4
98
,64
7,8
38
.92
28
,36
2,0
21
.14
11
5,0
90
,91
9.7
6
0.0
0
55
,10
7,5
09
.37
0.0
0
16
3,4
72
,70
3.8
0
20
,45
0,0
34
.51
0.0
0
11
6,4
46
,64
0.2
7
5,5
50
,00
0.0
0
0.0
0
14
2,1
21
,87
0.9
3
8,0
91
,37
4.0
0 40
,26
2,5
03
.97
0.0
0
33
,31
8,3
10
.92
26
,82
3,0
97
.00
90
,76
2,9
37
.23
9,9
34
,66
3.7
1
71
,07
8,7
28
.08
75
,58
6,1
86
.13
13
1,0
69
,23
7.1
3
0.0
0
46
,93
6,0
89
.69
79
,42
5,9
25
.70
14
8,0
96
,63
3.9
6
99
,09
9,5
34
.40
33
,41
8,5
98
.69
11
2,7
76
,16
1.0
2
0.0
0
53
,06
1,7
95
.72
0.0
0
15
8,8
51
,99
1.5
9
21
,93
1,4
56
.47
0.0
0
12
2,2
48
,56
1.9
6
5,5
50
,00
0.0
0
0.0
0
14
5,7
21
,88
8.7
6
7,9
75
,76
9.0
3
34
,92
0,2
73
.19
0.0
0
35
,57
7,2
17
.22
23
,23
5,2
80
.81
Chart Showing pre contract evaluation Jan-Dec 2012. QUOTTED SUM (#) VETTED SUM (#)
cxiv
SUMMARY OF CAPITAL PROJECT
SUMMARY OF PROJECTS REPORTED JANUARY-
DECEMBER,2012
S/NO VALUES(N)
1 PRE-CONTRACT EVALUATION (QUOTTED) 1,532,598,663.83
2 PRE-CONTRACT EVALUATION (DPPMB RECOMMENDED)
1,507,258,930.49
3 SAVINGS 16,339,733.34
4 APPROVED CAPITAL BUDGET FOR THE 27NO. L.G.COUNCILS
16,381,731,079.00
5 CONTRACTS AWARDED JANUARY-DECEMBER,2011
1,651,811,559.52
cxv
SECTION (D)
CONTRACT AWARDED
JANUARY-DECEMBER, 2012
cxvi
JIGAWA STATE DUE PROCESS AND PROJECT MONITORING BUREAU,LOCAL GOVERNMENT UNIT.
CONTRACT AWARDED SUMMARY SHEET
S/NO LOCAL
GOVERNMENT
NUM. OF CONTRACT AWARDED
2012 APPROVED CAPITAL BUDGET
ACTUAL CAPITAL PROJECT AWARDED
DIRECT EXECUTED PROJECT
% IMPLEMENTATION
1
AUYO 12 556,377,191.00 62,045,378.98 215,432,196.89 39%
2 BABURA
8 575,360,149.00 34,150,889.14 228,120,675.80 40%
3 BIRNIWA
33 648,268,443.00 150,301,764.33 367,455,221.24 57%
4 BIRNIN KUDU
61 771,576,614.00 145,836,893.56 367,455,221.24 48%
5 BUJI
30 835,504,009.00 143,560,268.45 291,692,894.36 35%
6 DUTSE
735,175,226.00 46,110,859.76 251,073,625.67 34%
7 GARKI
10 491,596,789.00 73,195,638.00 238,959,759.91 49%
8 GAGARAWA
18 488,146,104.00 46,012,207.00 185,066,884.91 38%
9 GUMEL
9 511,778,353.00 114,008,890.43 268,375,328.34 52%
10 GURI
45 771,543,596.00 157,227,597.16 310,777,443.07 40%
11 GWARAM
20 724,495,285.00 202,997,693.14 452,252,385.13 62%
12 GWIWA
51 629,230,431.00 206,948,578.04 365,512,803.95 58%
13 HADEJIA
460,349,419.00 36,310,247.77 180,040,169.68 39%
14 JAHUN
22 718,978,830.00 139,598,957.14 512,674,272.96 71%
15 KAUGAMA
4 508,228,076.00 26,000,000.00 339,141,891.82 67%
16 KAFIN-HAUSA
19 773,872,381.00 61,648,268.72 468,173,224.54 60%
17 KAZAURE
8 453,479,893.00 51,923,865.00 380,827,084.82 84%
18 KIRI-KASAMMA
49 583,256,604.00 169,521,846.59 512,510,954.41 88%
19 KIYAWA
58 649,986,403.00 91,002,086.63 520,843,138.45 80%
cxvii
20 MALAM-MADORI 7
445,835,137.00 36,943,581.25 374,088,801.07 84% 21 MAIGATARI 22 730,204,814.00 173,916,621.37 605,987,641.19 83% 22 MIGA 43 653,372,784.00 160,018,817.87 477,537,269.69 73% 23 RINGIM 6 494,299,238.00 37,188,363.96 268,775,737.25 54% 24 RONI 19 449,571,829.00 68,098,396.28 394,741,322.10 88% 25 SULE-TANKARKAR 5 590,644,567.00 30,863,000.00 349,515,843.82 59% 26 TAURA 6 476,607,593.00 80,164,248.77 407,925,444.59 86% 27 YANKWASHI 15 505,038,749.00 198,890,254.93 501,688,698.75 99%
TOTAL 580 16,232,778,507.00
2,744,485,214.27 9,836,645,935.65
cxviii
AU
YO
BA
BU
RA
BIR
NIW
A
BIR
NIN
KU
DU
BU
JI
DU
TSE
GA
RK
I
GA
GA
RA
WA
GU
MEL
GU
RI
GW
AR
AM
GW
IWA
HA
DEJ
IA
JAH
UN
KA
UG
AM
A
KA
FIN
-HA
USA
KA
ZAU
RE
KIR
I-K
ASA
MM
A
KIY
AW
A
MA
LAM
-MA
DO
RI
MA
IGA
TAR
I
MIG
A
RIN
GIM
RO
NI
SULE
-TA
NK
AR
KA
R
TAU
RA
YAN
KW
ASH
I
55
6,3
77
,19
1.0
0
57
5,3
60
,14
9.0
0
64
8,2
68
,44
3.0
0
77
1,5
76
,61
4.0
0
83
5,5
04
,00
9.0
0
73
5,1
75
,22
6.0
0
49
1,5
96
,78
9.0
0
48
8,1
46
,10
4.0
0
51
1,7
78
,35
3.0
0
77
1,5
43
,59
6.0
0
72
4,4
95
,28
5.0
0
62
9,2
30
,43
1.0
0
46
0,3
49
,41
9.0
0
71
8,9
78
,83
0.0
0
50
8,2
28
,07
6.0
0
77
3,8
72
,38
1.0
0
45
3,4
79
,89
3.0
0
58
3,2
56
,60
4.0
0
64
9,9
86
,40
3.0
0
44
5,8
35
,13
7.0
0
73
0,2
04
,81
4.0
0
65
3,3
72
,78
4.0
0
49
4,2
99
,23
8.0
0
44
9,5
71
,82
9.0
0
59
0,6
44
,56
7.0
0
47
6,6
07
,59
3.0
0
50
5,0
38
,74
9.0
0
62
,04
5,3
78
.98
34
,15
0,8
89
.14
15
0,3
01
,76
4.3
3
14
5,8
36
,89
3.5
6
14
3,5
60
,26
8.4
5
46
,11
0,8
59
.76
73
,19
5,6
38
.00
46
,01
2,2
07
.00
11
4,0
08
,89
0.4
3
15
7,2
27
,59
7.1
6
20
2,9
97
,69
3.1
4
20
6,9
48
,57
8.0
4
36
,31
0,2
47
.77
13
9,5
98
,95
7.1
4
26
,00
0,0
00
.00
61
,64
8,2
68
.72
51
,92
3,8
65
.00
16
9,5
21
,84
6.5
9
91
,00
2,0
86
.63
36
,94
3,5
81
.25
17
3,9
16
,62
1.3
7
16
0,0
18
,81
7.8
7
37
,18
8,3
63
.96
68
,09
8,3
96
.28
30
,86
3,0
00
.00
80
,16
4,2
48
.77
19
8,8
90
,25
4.9
3
Bar Chart Showing Budgetary Analysis for 27no Local Government council
2012 APPROVED CAPITAL BUDGET ACTUAL CAPITAL PROJECT AWARDED
cxix
CONTRACT AWARDED
AUYO LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT NUMBER
CONTRACTOR LOCATION AMOUNT
1 26/04/2012
UP GRADING OF WATER WORKS FROM SOLAR TO MOTORIZE 0193 LIMIS BROTHERS GUYU 5,253,900.25
2 26/04/2012
REPLACEMENT OF SOLAR POWER AND REPAIR OF GENERATOR 0193 LIMIS BROTHERS UNIK 1,338,750.00
3 4/4/2012 CONSRUCTION OF MOSQUE 0196
ALH. SHU'AIBU DOGO GATAFA 1,084,594.50
4 4/4/2012 CONSRUCTION OF MOSQUE 0197 M. ALI MAISHAYI WAILARE 1,084,594.50
5 4/4/2012 CONSRUCTION OF MOSQUE 0198 HASSAN HASSAN D/MARKE 1,084,594.50
6 4/4/2012 CONSRUCTION OF MOSQUE 0199 MUHD FAGACI ADAHA 1,084,594.50
7 8/10/2012
UP GRADING WATER WORK FROM SOLAR TO MOTORIZE 0191 SHAMAKI UMAR KALGWAI 5,253,900.25
8 29/07/2012 ELECTRIFICATION WORK 4989 MWT REAL ESTATE KATAJE 6,757,189.22
9 8/7/2012 CONSTRUCT. OF PEDIATRIC WARD 0553 ALH, MUSA AUYO AUYO 10,531,912.00
10 8/11/2012 REPAIRS OF MOTORIZED WATER SCHEME. 0555 SHAMAKI UMAR AUYO 1,121,288.10
11 15/11/2012 COMPLETE MOTORIZED WATER SCHEME 0556 LIMIS BROTHERS MURAN 8,787,066.16
12 5/12/2012 ELECTRIFICATION WORK SHIYO GEN, ENTR SHIYO 18,662,995.00
TOTAL 62,045,378.98
cxx
1
CONTRACT AWARDED
BABURA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATOIN AMOUNT [ N : K ]
1 11/4/2012 Construction of Friday Prayer Mosque Inusa Mati Kunyafa Village 3,004,000.00
2 28/6/2012 Construction of Friday Prayer Mosque Sani Musa Malamawa Village 3,004,000.00
3 11/4/2012 Construction of 1 block classroom Islamiyya Schools A Amadu Lamntani Laminfeni 3,640,670.00
4 11/4/2012 Construction of Nomadic School A Audu Garu Ungu Tsamiya 3,126,219.14
5 7/3/2012 Construction of complete motorize water scheme Tijjani Habu Babura kudu 876,000.00
6 12/4/2012 Construction of 5 daily prayer mosque Haladu Gatuta Indurkuba 500,000.00
7 14/2/2012 Purchase of official vehicle for chairman M B U Motors Babura 5,500,000.00
8 14/2/2012
Purchase of official vehicle for Vice chairman, secretary and House Leader M B U Motors Babura 14,500,000.00
TOTAL 34,150,889.14
cxxi
CONTRACT AWARDED
BIRNIN KUDU LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION AMOUNT
1 21/6/12 SUPPLY OF MATRESS ABDULLAHI YUNUSA LEA 2,621,000.00
2 o5/o6/12 RENOVATION OF JUMAAT MOSQUE A MOHD MAIGORO INJIWAWA 629,644.00
3 18/5/12 ELECTRIFICATION PROJECT PHASE I COMPETENCY NIG
LTD SHAWU 2,892,198.20
4 18/-
5/2012 ELECTRIFICATION PROJECT PHASE II COMPETENCY NIG
LTD SHAWU 1,763,375.00
5 12/o6/12 ELECTRIFICATION PROJECT PHASE I ALH. USAINI DUNI DANGOLI 1,944,824.00
6 18/5/12 ELECTRIFICATION PROJECT PHASE II ALH. USAINI DUNI DANGOLI 1,416,029.00
7 18/5/12 ELECTRFICATION PROJECT ALH. YAHAYA INUWA SHUNGURIN 2,266,742.00
8 18/5/12 ELECTRFICATION PROJECT ALH. JAMILU SALE IGGI/UY 2,892,198.00
9 18/8/12 ELECTRFICATION PROJECT ALH IBRAHIM
NATAJO KAGADAMA 2,062,289.60
10 20/12/12 EARTH FILLING ALH SAIDU ZAZIKA 1,861,552.00
11 18/5/12 ELECTRFICATION PROJECT ALH DAHIRU DATTI WARWADE 457,296.00
12 17/5/12 INSTALLATION OF CCTV CAMERA
CHAIMAN OFFICE 2,625,280.00
13 29/2/12 CONSTRUCTION OF WAITING SHED JINJIRI KANGIRE KANGIRE 280,000.00
14 14/5/12 COMPLETION OF BIHSA SECRETARIATE A MAGAJI FAWA B/KUDU 816,783.00
15 30/1/12 FLOORING OF ISLAMIYYA SCHOOL MAMAJI SHUAIBU IHIYUSSUNNA
ISLAMIYYA 229,426.00
16 20/5/11 COMPLETION DAILY PRAYER MOSQUE MAIUNGUWA SULE ODOJI 84,000.00
17 1/11/2012 CONSTRUCTION OF DOUBLE CULVERT A AMADU MAI
KATAKO DOKOKI 2,377,000.00
18 15/6/12 CONSTRUCTION 6M PRESS STEEL TOWER TANK MAMUDA MASAYA MASAYA 2,970,000.00
19 6/11/2012 SUPPLY OF SANITATION MATERIAL MUTARI IBRAHIM WASH DEPT 451,500.00
20 29/2/12 SUPPLY & INSTALLATION OF I CCTV DOOR
GOLDEN ELECTRICAL
OFFIICE OF CHAIRMAN 1,000,715.52
cxxii
21 3/4/2012 REPAIRS OF TOYOTA OFFICIAL VEHICLE AHMAD ALI GANTSA OFFIICE OF CHAIRMAN 1,205,000.00
22 14/12/12 CONSTRUCTION OF WALL FENCE A AMADU MAI
KATAKO BLIND CENTER 2,488,443.00
C/F 35,335,295.32
4a
CONTRACT AWARDED
B/KUDU L.G
C/F 35,335,295.32
23 18-5-12 ELECTRFICATION PROJECT A AMADU MAI KATAKO DOKOKI 2,861,712.00
24 25-6-12 EATHFILLING ABUBAKAR SULEIMAN B/KUDU 470,000.00
25 16-11-12 RENOVATION OF UPPER SHARIA COURT JUDGE HOUSE
ABDULLAHI GAMBO OVER B/KUDU 748,330.00
26 1711-12 RENOVATION OF JISIEC OFFICE MBU MOTORS OFFIICE OF CHAIRMAN 5,500,000.00
27 3/10/2012 COSTRUCTION OF JUMAAT MOSQUE GARBA UMAR CHAGA 3,269,768.60
28 24-3-11 PAYMENT OF SCHOLARSHIP TO TERTIARY INST. STUDENTS TREASURY DEPT STUDENTS 4,409,000.00
29 24-3-11 INTERLOCKING OF CENTRAL MOSQUE LAMU 7 BABALDU CO, B/KUDU 19,000,000.00
30 24-3-11 PURCHASE AND PLANTING OF SEEDLING AGRIC DEPT B/kudu to sundimiana
raod 74 km 3,740,000.00
31 4/3/2011 RENOVATION OF 5 DAILY PRAYER MOSQUE Gambara 523,932.00
32 4/12/2012 earth filling ALH. AMADU KATAKO plantation road B/K 182,000.00
33 4/12/2012 COSTRUCTION OF JUMAAT MOSQUE ALH. ADO Giwa 3,160,410.00
34 8/5/2012 COSTRUCTION OF JUMAAT MOSQUE ALH. AMADU KATAKO Budusu 4,319,292.92
35 15/6/12 COSTRUCTION OF JUMAAT MOSQUE ABDULLAHI YUNUSA Tukuda 2,036,222.00
36 7/7/2012 COSTRUCTION OF JUMAAT MOSQUE ALH. MAGAJI FAWA Masaru 1,315,005.72
cxxiii
37 18/12/12 LAND COMPENSATION GOV, DAY ARABIC JNR
SEC SCH, Sundry person 10,710,000.00
38 11/5/2012 LAND COMPENSATION SUNDRY PERSON GJSS Chiyako 583,000.00
39 20/11/12 LAND COMPENSATION SUNDARY PERSON Hospital extention
kiyaho 583,725.00
40 20/11/12 COMPENSATION OF UNCOMPLETED BUILDING ALH. ISAH B/KUDU B/KUDU 761,250.00
41 17/10/12 RENOVATION OF HOD WORKS HOUSE ABDULHAMID
HANDAMU Staff Quarters B/K 1,911,000.00
42 17/9/12 PURCHASE OF VEHICLE KAFILU SULEIMAN
ABUBAKAR B/KUDU 937,000.00
C/F 102,356,943.56
4b
CONTRACT AWARDED
B/KUDU L.G
B/F 102,356,943.56
43 7/5/2012 PURCHASE HILUX TOYOTA UMAR ISYAKU ALIYU B/KUDU 2,998,500.00
44 23/5/12 PAYMENT OF HOUSE RENT YUGUDA DUMUS B/KUDU 500,000.00
45 31/5/12 PAYMENT OF HOUSE RENT YUSUF USMAN B/KUDU 300,000.00
46 20/11/12 PAYMENT OF HOUSE RENT A ZUBAIRU IMAM B/KUDU 200,000.00
47 17/10/12 REPAIRS OF PRISON VEHICLE A BABA DANHAYA B/KUDU PRISON 355,000.00
48 17/9/12 SUPPLY OF H/PUMP MATERIALS MOHD YAHAYA B/KUDU W/BOARD 3,265,360.00
49 7/5/2012 PAYMENT H/P MATERIALS AMINU MAGAJI B/KUDU 1,704,000.00
50 23/5/12 SUPPLY OF DIESEL H. SADIYA ADAMU B/KUDU 1,750,000.00
51 31/5/12 SUPPLY OF DIESEL SUNDRY PERSON B/KUDU 1,501,500.00
52 2007A/13 PURCHASE OF DRUGS MOHD KABIR
IBRAHIM B/KUDU 1,892,450.00
53 2007B/13 PURCHASE OF DRUGS ALH. MAGAJI FAWA B/KUDU 1,489,140.00
54 2007A/13 SUPPLY OF SANITATION MATERIALS MUKTAR MUSA
ZUBAIR B/KUDU 4,515,000.00
cxxiv
55 2008C/13 LIVESTOCK VACCINATION MUSA IDRITH B/KUDU 810,000.00
56 2008A/13 TRACTOR REPAIRS AHMED SARKI UBA B/KUDU 810,000.00
57 2008A/13 PURCHASE & DISTRIBUTION OF SEED INPAT
JASCO STOREKEEPER B/KUDU 582,000.00
58 2008B/13 DEMACATION OF GRAZIN LAND MUKTAR MUSA
ZUBAIR SHAHURERE 457,000.00
59 2008B/13
DEMACATION OF GRAZING RESERVEPURCHASE OF OFFICIAL VEHICLE FOR CHAIRMAN
DANMADIGA 350,000.00
60 7001/10 purchase of official vehicle for chairman peogeot 408 MBU Motors B/KUDU 5,500,000.00
61 7001/11 PURCHASE OF OFFICIAL VEHICLE FOR V/CHAIRMAN, SEC & SPEAKER MBU Motors B/KUDU 14,500,000.00
TOTAL 145,836,893.56
CONTRACT AWARDED
BUJI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION AMOUNT [ N: K]
B/F 48,620,350.03
6 15/6/2012 CONSTRUTION OF FRIDAY MOSQUE AT LELEN KUDU
0005 GWADAYI NIG. LTD
LELEN KUDU 11,286,051.11
7 18/7/2012 CONSTRUCTION OF MARKET STALL AT GANTSA
0006 BAFFA T.O./MATO KALIYA
GANTSA 1,282,853.62
8 18/7/2012 CONSTRUCTION OF PIT LATERINE AT GANTSA
0007 ALH TASI'U/KANINI GANTSA
GANTSA PHC 787,998.42
cxxv
9 23/8/2012 CONSTRUCTION OF PIT LATERINE AT SAGU
0008 M.ABDU KAWAYA CADDORI IBRAHIM
SAGU PHC 787,998.42
10 19/9/2012 CONSTRUCTION OF COMPLETE MOTORIZED WATER SCHEME AND RETICULATION AT KAWAYA
0011 DALWA NIG. LTD KAWAYE 11,923,261.25
11 1/9/2012 CONSTRUCTION OF TWO CLASSROOMS WITH HEADMASTERS OFFICE AT JAKA
0013 A.S. GWANGWAZO NIG.LTD
JAKA 5,700,037.15
12 5/9/2012 CONSTRUCTION OF DRAINAGE AT GWADAYI
0009 IMAMU GWADAYI GWADAYI 327,313.00
13 23/8/2012 CONSTRUCTION OF DRAINAGE AT BUJI
0012 ALI BUJI BUJI LOCAL GOVERNMENT
1,370,261.00
14 11/12/2012 CONSTRUCTION OF COMPLETE MOTORIZED WATER SCHEME AT KARANJAU
0010 WATER AND WATER WASTE NIG LTD
KARANJAU 11,426,445.00
15 11/12/2012 COMPLETION OF BUJI DISTRICT HEAD HOUSE
0014 YAYARIN TUKUR NIG, LTD
BUJI 11,214,965.81
C/F 104,727,534.81
5b
cxxvi
CONTRACT AWARDED
BUJI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT NUMBER
CONTRACTOR LOCATION AMOUNT [ N : K ]
B/F 104,727,534.81
16 11/12/2012 CONSTRUCTION OF JUMA'AT MOSQUE AT MADABE
0015 YAYARIN TUKUR NIG, LTD
MADABE 11,339,700.59
17 11/12/2012 CONSTRUCTION OF LOCK UP SHOPS AT SARA MARKET
0016 IHSAN NIG LTD SARA 13,780,694.70
18 11/12/2012 CONSTRUCTION OF DAILY PRAYER MOSQUE AT AHOTO
0017 SANI AHTO AND OHERS
AHOTO 1,648,372.40
19 11/12/2012 CONSTRUCTION OF DAILY PRAYER MOSQUE AT GWADAYI
0018 GARBA UBALE AND OTHERS
GWADAYI 1,648,372.40
20 11/12/2012 CONSTRUCTION OF MARKET STALL AT GANTSA
0019 ALH JIBRIN ZANGI
GANTSA 1,250,634.00
21 11/12/2012 CONSTRUCTION OF MARKET STALL AT GWADAYI
0020 ALI BOLOKO,SHEHU KALMU,MUSA MUHD & MUHD DANLITI
GWADAYI 1,250,634.00
22 11/12/2012 CONSTRUCTION OF MARKET STALL AT BUJI
0021 IBRAHIM NUHU AND OTHERS
BUJI 1,250,634.00
23 11/12/2012 CONSTRUCTION OF MARKET STALL AT SAGU
0022 INUSA WANZAN AND OTHERS
SAGU 1,250,634.00
24 11/12/2012 CONSTRUCTION OF DAILY PRAYER MOSQUE AT KWALELE
0023 CARBA AND OTHERS
KWALELE 836,181.13
25 11/12/2012 CONSTRUCTION OF DAILY PRAYER MOSQUE AT RIGAR
0024 DANYARO AND OTHERS
RIGAR GADA 836,181.13
cxxvii
GADA
C/F 139,819,573.16
5c
CONTRACT AWARDED
BUJI
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 139,819,573.16
26 11/12/2012
CONSTRUCTION OF DAILY PRAYER MOSQUE AT 0025
IDUKA AND OTHERS GAMBASHA 836,181.13
27 11/12/2012
CONSTRUCTION OF DAILY PRAYER MOSQUE AT 0026 USAINI 2 OTHERS JATA 836,181.13
28 11/12/2012
CONSTRUCTION OF DAILY PRAYER MOSQUE AT 0027
DANBIRNI AND OTHERS CHAKWAMA 836,181.13
29 30/12/2012 PIT LATERIN AT YAYARIN TUKUR 0029
A. HARUNA, ALH. IDI YAYARIN TUKUR 616,075.95
30 30/12/2012 PIT LATERIN AT GWADAYI 0030
MUDDAFA, KANO TAI'ASARA GWADAYI 616,075.95
TOTAL 143,560,268.45
cxxviii
CONTRACT AWARDED
BIRNIWA LOCAL GOVT.
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 27/12/2012
CONSTRUCTION OF MOTORISED WATER SCHEME LIMIS BROTHERS DIGINSA 12,420,757.28
2 27/12/2012
CONSTRUCTION OF MOTORISED WATER SCHEME COROM KARILLA 12,420,757.28
3 27/12/2012
CONSTRUCTION OF MOTORISED WATER SCHEME LIMIS BROTHERS KANDIL WURIYA 12,420,757.28
4 12/2/2012 ELECTRIFICATION PROJECT
TURABU CONSTRUCTION DAGU; FANI 14,653,125.86
5 15/5/2012 PURCHASE OF HAND PUMP MATERIALS DIRECT LABOUR BIRNIWA 3,000,000.00
6 1/1/2012 IMPROVEMENT OF FRIDAY MOSQUE
SABURU GEN ENT DIGINSA 6,100,000.00
7 16/2/2012 DRILLING OF HAND PUMP
DAN HADEJIA NIG LTD GGASS BIRNIWA 400,000.00
8 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD MAINARI 200,000.00
9 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD M MAI ALLO 200,000.00
10 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD AREMARI 200,000.00
11 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD TUKU 200,000.00
cxxix
12 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD SUKURINA 200,000.00
13 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD JALLARI 200,000.00
14 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD K/INKIWA AREWA 200,000.00
15 16/2/2012 DRILLING OF HAND PUMP
IBRAHIM KACHALLA NJG
LTD KUKA INKIWA
TSANGAYA 1,000,000.00
C/F 63,815,397.70
3a
B/F 63,815,397.70
16 15/3/2012 PAYMENT OF LAND COMPENSATION LAND OFFICER BIRNIWA 1,100,000.00
17 12/3/2012 PURCHASE OF GULF 10 BUS DIRECT LABOUR BIRNIWA 1,100,000.00
18 25/5/2012 REHABLITATION OF FM RADIO
DIRECTOR JIGAWA RADIO BIRNIWA 3,606,955.10
19 11/4/2012
CONSTRUCTION OF MOTORISED WATER SCHEME
A.D.Z GLOBAL NIG. LTD KABIWA 12,420,757.28
20 13/10/2012 ELECTRIFICATION PROJECT
TURABU CONSTRUCTION BURSALI 17,246,843.86
21 13/10/2012 COMPLETION OF KANYA MOSQUE
SADUMU H KANDAMI NIG
LTD KANYA 4,578,234.48
22 8/4/2012 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD DAGIL FARI 400,000.00
23 11/4/2012 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD KIRYA 400,000.00
cxxx
24 11/4/2012 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD FULATANAN 400,000.00
25 11/4/2012 RENOVATION OF DAILY PRAYER MOSQUE
ZANGANA NIG LTD KUPSA 400,000.00
26 11/4/2012 RENOVATION OF DAILY PRAYER MOSQUE ZANGANA NIG LTD GORIBA
400,000.00
27 11/4/2012 RENOVATION OF DAILY PRAYER MOSQUE ZANGANA NIG LTD BULAMA LUM
400,000.00
28 24/4/2012 RENOVATION OF DAILY PRAYER MOSQUE ZANGANA NIG LTD BIRNIWA
2,648,874.69
29 6/12/2012 RENOVATION OF LG STAFF QTRS Musa Yille Nig. LTD BIRNIWA
2,396,565.58
30 21/11/2012 CONSTRUCTION OF MOTORISED WATER SCHEME LIMIS BROTHERS LTD BEGUWA
10,664,829.82
31 4/2/2012 CONSTRUCTION OF MOTORISED WATER SCHEME LIMIS ROTHERS LTD WALAWA
11,323,305.82
32 14/2/2012 PURCHASE OF OFFICIAL VEHICLE FOR CHAIRMAN MBU Motors BIRNIWA
5,500,000.00
33 14/2/2012
PURCHASE OF OFFICIAL VEHICLE FOR V /CHAIRMAN, SEC MBU Motors BIRNIWA
11,500,000.00
TOTAL 150,301,764.33
3b
CONTRACT AWARDED
GARKI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 23/4/2012 Construction of Wall Fencing
Sim ANIKEF International LTD GGSS Garki 19,283,694
2 23/4/2012 Electrification Project Marb Eng. Nig Ltd Muku 14,966,120.85
3 23/4/2012 Construction of Friday Mosque A Magaji Garki Dunkumi 4,615,494.61
4 12/5/2012 Constr. Of 6No. H/Pump Direct Labour Various places 1,000,000.00
cxxxi
5 12/5/2012 Constr, of Health Post Direct Labour Muku 3,510,328.37
6 12/5/2012 Supply of Water Project [20KVA Generator] Lawan Babande Gumba 2,500,000.00
7 15/8/2012 Supply of Water Project [27KVA Generator] A Umaru Kore 2,820,000.00
8 15/8/2012 Purchase H/Pump Materials Direct Labour Various places 4,500,000.00
9 14/2/2012 Purchase of Official Vehicle 408 MBU Motors Garki 5,500,000,.00
10 14/2/2012 Purchase of 2N0. Official Vehicles MBU Motors Garki 14,500,000.00
TOTAL 73,195,638.00
CONTRACT AWARDED
DUTSE LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 9/11/2012 Construction of V. I. P. Toilet N.I.P. office 256,912.89
2 3/9/2012 Electrification Project Galadimawa Ventures Fanisau 7,889,773.84
3 3/9/2012 Construction of Friday Mosque Sale Chaichai Kyaran 5,455,639.03
4 19/9/2012 Drilling. Of 20No. Borehole Alkali Sakwaya Galadima 1,300,000.00
5 4/12/2012 Constr, of Engine room Mr moses Galadima 554,468.00
6 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Dundubus 284,287.50
7 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Chamo 284,287.50
8 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited K/fada 284,287.50
9 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Madobi 284,287.50
10 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Duju 284,287.50
11 14/2/2012 Purchase of Official Vehicle 408 MBU Motors Dutse 5,500,000,.00
cxxxii
12 14/2/2012 Purchase of 2N0. Official Vehicles MBU Motors Dutse 14,500,000.00
13 20/4/2012 Construction of Borehole Mahalli Nig. Ltd. Duste Grave yard 563,840.00
14 20/4/2012 Construction of Borehole Mahalli Nig. Ltd. Gandun fawa 551,656.00
15 23/10/2012 complete water scheme Alkali Sakwaya Gakikwa 7,264,270.00
16 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Darau 284,287.50
17 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Wurma 284,287.50
18 14/2/2012 Repairs of Solar Borehole Prestige Nig. limited Galamawa 284,287.50
TOTAL 46,110,859.76
CONTRACT AWARDED
GAGARAWA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 5/3/2012 Supply of hand pump materials Direct labour Across the 10No Wards 3,000,000.00
2 20-2-12 Purchase of 20KVA water pump Generator
Muhd Dan sakoto Nig LTD Medu
1,950,000.00
3 11/4/2012 Purchase of 20KVA water pump Generator Muhd Yahaya Nig LTD Gamji
1,950,000.00
4 15-8-12 Purchase 20KVA water Generator
M sunusi ibrahim Nig. LTD Gagarawa Tasha
2,330,000.00
5 20-8-12 Purchase of furniture to staff quarters Direct labour GGW LG Staff Queters 1,500,000.00
6 20-2-12 Construction of new hand pump A lhaji Usman Nig. LTD Bula 800,000.00
7 20-8-12 Construction of new hand pump Isyaku yusif Nig LTD Unguwaar Liman
400,000.00
8 6/12/2012 Construction of new hand pump Isyaku yusif Nig LTD Dan madan Fulani
400,000.00
9 6/12/2012 Construction of new hand pump Isyaku yusif Nig LTD Akai Allah
cxxxiii
400,000.00
10 6/12/2012 Construction of new hand pump Isyaku yusif Nig LTD Digan Fulani 430,000.00
11 9/5/2012 Construction of new hand pump A. Isiya Ltd M/shada 400,000.00
12 9/5/2012 Construction of new hand pump A. Isiya Ltd Gagarawa Doni 400,000.00
13 9/5/2012 Construction of new hand pump A. Isiya Ltd G/Tu
400,000.00
14 9/5/2012 Construction of new hand pump Alhaji Usman G/fulani 430,000.00
15 9/5/2012 Construction of new hand pump Alhaji Usman Maihina 430,000.00
16 16-10-12 Construction of Five daily prayer Mosque Alhaji Sabo Zakar Sarkin Gabas
1,792,207.00
17 16-10-12 Purchase of official vehicle to chairman (408) MBU Motors Gagarawa LG
14,500,000.00
18 16-10-12 Purch. of official vehicle to vice chairman, secretary, council leader MBU Motors Gagarawa LG
14,500,000.00
TOTAL 46,012,207.00
8
cxxxiv
CONTRACT AWARDED
GUMEL LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 7/2/2012 Fencing of Grave Yard Idris ya'u Abuja Queters 7,071,428.23
2 13-10-12 construction of drainage and culvert Ado Dankaggi Tudun Alhaji Quaters 619,000.00
3 17-8-11 construction of islamiyya school Babandi alaramma Danun Biri
1,000,000.00
4 4/11/2011 construction of slaughter House Isma'il venture Gagarawa Road
19,000,000.00
5 26-11-12 costructiion of motorize borehole Murtala Dake Dantanoma
450,000.00
6 14-3-12 payment for compensation for tonwship road LG Gumel
22,451,566.55
7 14-2-12 purchase of chairman official vehicle peogeot 408 MBU Motors Gumel
5,500,000.00
8 14-2-12 purchase of vice chairman secretary council leader official vehicle MBU Motors Gumel
14,500,000.00
9 28/6/2012 Construction of motor pack Isma'il venture Gumel
43,416,895.65
114,008,890.43
CONTRACT AWARDED
GURI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 27/2/2012 Construction of 3 nos. Market Stall A. Baya Dole Guri 2,396,836.05
2 27/2/2012 Construction of 3 nos. Market A. Adamu umar Kadira 2,396,836.05
cxxxv
Stall
3 27/2/2012 Electrification Project A. Shu'aibu Guri Dolen Zugo 3,057,459.48
4 27/2/2012 Completion of Juma'at mosque Umar Dodo Una 1,397,905.95
5 27/2/2012 Completion of Juma'at mosque Yakubu Abunabo Yalwan Musari 1,547,067.00
6 23/6/2012 Drilling Borehole & Installation of H/Pump
Ngaloma Drill. Nig. Ltd Rigar A. Baba 500,000.00
7 11/4/2012 Constr. Of Guri- Zugo Feeder Road Gano Ventures Guri-Zugo 50,903,350.88
8 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar lamido 500,000.00
9 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar hardo labbo 500,000.00
10 11/12/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar Babale 500,000.00
11 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar mai gari 500,000.00
12 11/12/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Jaggen Kadawa 500,000.00
13 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Unguwar jibrin 500,000.00
14 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Kotu 500,000.00
15 11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar wakili 500,000.00
C/F 66,199,455.41
10a
CONTRACTS AWARDED
GURI L.G.
C/F
66,199,455.41
16 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Rigar Hardo Yarima
300,000.00
17 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Taka Lafiya
300,000.00
cxxxvi
18 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Alajeri Abur
300,000.00
19
11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Galadima 500,000.00
20
11/4/2012 Drilling Borehole & Installation of H/Pump
Ngloma Drill. Nig. Ltd Rigar gambo 500,000.00
21 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Mai Jan ruwa
300,000.00
22
11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Zugo sabuwar unguwa
300,000.00
23 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Unguwwar Buzaye
300,000.00
24 7/8/2012 Completion of Zugobiya Mosque Maifawa Zugobiy
220,000.00
25 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd Zuba Finj Ariri
300,000.00
26 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd G/Yamma
300,000.00
27 11/4/2012 Construction of 1 Nos. Borehole Ngloma Drill. Nig. Ltd R/Isubu
300,000.00
28 27/2/2012 Complete Water Scheme ADZ Nig. Ltd Dolen
8,467,082.52
29 27/2/2012 Construction of market stall Mashiru $ Baba Bala Guri $ Kadira market
3,195,781.40
30 20/9/2012 Purchase of 2nos motorcycle for
tamowa programme Direct Wash Dept.
250,000.00
31 30/4/2012 Renovation of Musari Mosque Alh. Musa Musari
6,800,000.00
32 10/8/2012 Dole - Wareri road culvert A. Bukar Arin Wareri - Dole
1,491,871.50
33 24/5/2012 Earth Filling and Culvert kasaga
road A.Bukar Arin Kasaga Road
2,800,000.00
34 16/6/2012 Culvert filling Dawa Road Alh. Hussaini Lafiya Dawaga Brige
1,600,000.00
35 20/6/2012 Purchase of generator water
pump Lamis Nig. Ltd Arin
2,800,000.00
36
20/9/2012 Purchase of fishing gear and eqipment
Direct Guri 1,500,000.00
37 30/4/2012 Purchase of empty sacks A. Rabui Gagiyaru Guri L.G.A.
5,800,000.00
cxxxvii
38 10/8/2012 Tree planting materials Direct Guri
1,000,000.00
39 24/5/2012 Purchase of hand pump spare
parts Direct Guri
2,000,000.00
40 6/7/2012 Construction Solar Water
Scheme Ngloma Drill. Nig. Ltd Giryo
7,429,821.52
41 6/7/2012 Electrification project AMIM Nig Ltd Guri-Adiyani-Tuk
32,299,278.48
42 11/4/2012 Arinijasco - Khadira culvert A. Defuru Arinjasco Bridge
1,975,000.00
43 24/7/2012 Purchase of Canoe Boat Direct Guri
300,000.00
44 7/8/2012 Electrification project A. Shu'aibu Guri Dole Zugo
5,948,000.00
45 10/8/2012 Culvert kasaga - margadu A. Ibrahim margadu Kasaga - margadu
1,451,306.33
TOTAL
157,227,597.16
10b
CONTRACT AWARDED
GWARAM LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 26/4/2012 CONSTRUCTION OF
ISLAMIYYA SCHOOL 1042 A. SAMAILA ZUMBURU 2,620,445.60
2 9/5/2012 CONSTR.OF MINI
STADIUM,KILA 1043 BAHUTU GLOBAL NIG LTD KILA 22,000,000.00
3 31/10/2012
CONSTRUCTION OF ISLAMIYYA 0048 A.S.D/KURGWI KILA 2,629,645.60
4 22/11/2012 CONSTR.OF ISLAMIYYA
SCHOOL 0601 A.MUTARI SARA GWARAM 3,466,385.75
5 4/10/2012 CONSTR.OF ISLAMIYYA
SCHOOL 1047 BASIRKA NIG.LTD. DINGAYA 2,629,645.60
6 13/12/2012
CONSTR. OF FRIDAY MOSQUE 0602 A.MUTARI SRA GWARAM 10,470,012.15
7 9/12/2012 CONSTR.OF DRAINAGE AT
CPF KILA 1046 A.Y.A.LOGISTIC KILA 6,012,239.49
cxxxviii
8 13/5/2012 REPAIRS OF BASIRKA
RADIO F.M. 1044 ROYAL TELLCOM BASIRKA 12,500,000.00
9 26/4/2012 CONSTR.OF ISLAMIYYA
SCHOOL A S.M/SHINKAFA 2,000,000.00
10 21/6/2012
PURCHASE OF FURNITURES INTERIOR DEC. LG SECRTARIATE 64,988,848.00
11 Oct-12 PURCH.OF OFFICIAL VEHICLE TO CM MBUMOTORS GWARAM 5,500,000.00
12 DITTO TO VCM AND LEADER MBU MOTORS GWARAM 14,500,000.00
13 15/11/2012 CONSTR.OF ISLAMIYYA
SCHOOL A.DALIBI 2,629,645.00
14 23/12/2012 PURCHASE OF GRAINS A.JAMILU KILA LG SECRTARIATE 1,500,000.00
15 12/9/2012
FENCING OF GSS UNITY RINGIM GALADANCI GWARAM 36,825,149.00
16 4/10/2012 CONSTR.OF ISLAMIYYA SCHOOL BASIRKA NIG LTD. KILA 2,629,645.60
17 22/11/12 CONSTRUCTION OF SLAUGHTER HOUSE A. MUTARI SARA GWARAM 3,466,385.75
C/F 196,368,047.54
11a
CONTRACT AWARDED
GWARAM LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 196,368,047.54
18 5/9/2012 RENOV.OF FRIDAY MOSQUE DIRECT LABOUR SALAMANDA 1,000,000.00
19 24/8/2012 CONSTR.OF ISLAMIYYA SCHOOL A. ISA BASIRKA 3,000,000.00
20 12/9/2012 CONSTR.OF ISLAMIYYA SCHOOL 0056 BASIRKA & CO LTD KUYUNGU 2,629,645.60
TOTAL 202,997,693.14
cxxxix
CONTRACT AWARDED
GWIWA LOCAL GOVT.
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 27-2-12 Electrification Project BOK Nig Ltd S/Gawo 8,400,444.98
2 25-5-12 Electrification Project IHSAN DRILLING NIG LTD U/Gamji 9,397,465.16
3 4/5/2011 Drilling of Boreholes NABO Constr. Ltd Yola 1,771,355.00
4 18-4-12 Construction of Waiting Shed Garba Fate Malga 525,199.00
5 18-4-12 Drilling of Boreholes 2No. NABO Constr. Ltd Jammajen Maharba 3,542,670.00
6 24-4-12 Construction of Jumaat Mosque Chediya Ventures Z/Gauraye 5,724,098.47
7 o6/6/12 Construction of Jumaat Mosque ASA M/Bulawus Dabi 5,724,098.47
8 26-2-12 Construction of Overhead Tank Chediya Ventures Daurawa Dandada 2,160,000.00
9 13-2-12 Additional Work Disrict Head House MUSAB Nigb Ltd Korayal 2,972,256.00
10 18-4-12 Drilling of Borehole NABO Constr. Ltd Indirawa 1,771,335.00
11 25-8-12 Purchase of Furniture Direct Labour Staff Qtrs 3,627,000.00
12 6/5/2012 Raticulation of Water Scheme Direct Labour Various Places 8,376,200.00
13 14-112-12 Fencing of Friday Mosque ASA M/Bulawus Hungu 2,193,613.08
14 11/10/2012 Fencing of Friday Mosque Shafe Alh. Ado Kero 2,587,753.82
15 27-12-12 Purchase of 27KVA Water Gen MUSHTEK Nig Ltd Daurawa Dandada 2,457,500.00
16 11/10/2012 Purchase of 27KVA Water Gen MUSHTEK Nig Ltd Rarau Malamai 2,457,500.00
17 10/10/2012 Purchase of 16KVA Water Gen
HOD WASH Yola 1,340,000.00
18 7/5/2012 Water Works General Drilling & Purchase of pump Direct Labour Various Places 17,628,090.00
cxl
Materials
19 4/4/2012 Purchase of Student Boarding Materials Councillor Education
GWIWA LOCAL GOVT. 2,253,400.00
20 10/12/2012 Purchase of Borehole Materials HOD WASH All Over the LGA 3,000,000.00
C/F 87,909,978.98
12a
CONTRACT AWARDED
GWIWA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 87,909,978.98
21 20-12-12 Purchase of Borehole Materials HOD WASH All Over the LGA 500,000.00
22 18-7-12 Drilling of Borehole NABO Constructions LTD Gwiwa MPHC 1,771,335.00
23 11/1o/12 Construction of Friday Mosque GARBAT Ent. Ltd Tinkishi 5,724,098.47
24 11/1o/12 Construction of Friday Mosque Alh. Ado Kero Shafe 5,724,098.47
25 18-7-12 Construction of Friday Mosque ASA Mai bulawus Hungu 5,724,098.47
26 18-4-12 Const. of Engine Room & Inst of Generator Maikudi Auditor Daurawa Dandada 530,470.98
27 25-8-12 Const. of Engine Room & Inst of Generator
Adamu Kabiru Rorau Rorau Malami 530,470.98
28 6/5/2012 Constr, of Rorau D. Head House MUSAB Plastic Koriyal 14,422,805.00
cxli
29 14-112-12 Drilling of Borehole NABO Constructions LTD Tanda 1,771,335.00
30 11/10/2012 Construction of Five Daily prayer Mosque Alto Mai Dusa Kwarare 5,724,098.47
31 27-12-12 Completion & Furnishing of 9 Bedroom Staff Qtrs Dirct Labour Staff Qtrs 1,513,500.00
32 11/10/2012 Constr. Of Town Gate A&B Dirct Labour Gwiwa 4,246,958.00
C/F 136,093,247.82
12b
GWIWA LOCAL GOVERNMENT
B/F 136,093,248.00
33 11/1o/12 Constr. Of 1 block of 2 Classrooms
Samira Karshi Ventures Wailare 4,128,705.00
34 11/1o/12 Purchse of 27KVA Generator Set Haroline & Sons Buntusu 2,457,500.00
35 18-7-12 Purchse of 27KVA Generator Set Haroline & Sons Jammajen Maharba 2,457,500.00
36 10/10/2012 Constr. Of Drainage Alh. Yahaya Sale Indirawa 457,157.47
37 7/5/2012 Constr. Of 5 Daily Prayer Mosque
Alh. Lawan Abdulrazaq Gwiwa U/malamai 1,252,409.55
38 4/4/2012 Convertion of Old PHC to Offices
Alh. Mutari Mohd Gwiwa Gwiwa 3,260,017.95
39 10/12/2012 Constr. Of Jumaat Mosque ASA Mai Bulawus Maraganta 5,996,707.85
40 10/10/2012 Constr. Of 5 Daily Prayer Mosque Alh. Isa Alasan Korayal 1,252,409.55
cxlii
41 7/5/2012 Purchase of Furniture to D. Head House Daragi & Sons Ltd Korayal 3,127,310.00
42 4/4/2012 Completion of District H House
Alh. Jafaru Badakaya Korayal 1,629,941.51
43 10/12/2012 Supply of Furniture Shuaibu Lawan DPM House 660,590.00
44 7/5/2012 Constr. Of Jumaat Mosque ASA Mai Bulawus Yola 5,996,707.85
45 4/4/2012 Fencing of Friday Mosque Alh.Haruna Salisu Guntai 1,450,000.00
46 10/12/2012 Constr. Of 5 Daily Prayer Mosque Alh. Yahaya Sale Furtawa 1,252,419.55
47 20-12-12 Constr. Of 5 Daily Prayer Mosque Alh. Yahaya Daga Kurneji 1,252,419.55
48 18-7-12 Electrification Project BOK Eng. Ltd Burma Ruwa 22,506,803.67
49 11/1o/12 Constr. Of Drainage Mai Unguwa Abdullahi Rorau 3,459,318.66
50 11/1o/12 Constr. Of 1 block of 2 Classrooms Usaman Namadi Zangon Kya 4,128,705.94
51 18-7-12 Constr.of 1 block of 2 Classrooms Alh. Tukur Alto Daragi 4,128,705.94
206,948,578.04
TOTAL
CONTRACT AWARDED
JAHUN LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 16/12/12
CONSTRUCTION OF COMPLETE WATER SCHEME AND RETICULATION WORK AT TAZARA 0885 ENGR ABBAS TAZARA 13,407,705.30
2 12/6/2012
UPGRADING AND RETICULATION WORK AT TAZARA 0883 ENGR ABBAS TAZARA 8,418,259.30
cxliii
3 16/12/12
UPGRADING AND RETICULATION WORK AT KULLURU 0884 ENGR ABBAS KULLURU ,225136,60
4 16/02/12
CONSTRUCTION OF COMPLETE WATER SCHEME AT DAMUTAWA 0459 LIMIS BROTHERS DAMUTAWA 10,006,807.80
5 16/02/12
CONSTRUCTION OF COMPLETE WATER SCHEME AT ZANGO 0887 LIMIS BROTHERS ZANGO 11,203,946.25
6 17/02/12 50 No. OF HAND PUMPS AT VARIOUS VILLAGES 0851 LIMIS BROTHERS VARIOUS PLACES 17,500,000.00
7 2/3/2012
CONSTRUCTION OF 15No, OPEN WELLS AT VARIOUS VILLAGES 0851 ALIYU AUTA VARIOUS PLACES 1,620,000.00
8 21/12/12 ELECTRIFICATION WORK AT SUKULLIFI 0886
IBRACO MAFRICA NIG LTD SUKULLIFI 10,680,121.20
9
CONSTRUCTION OF BASIC HEALTH CLINIC AT ZANGON B/GAMARU 0461
IBRACO MAFRICA NIG LTD
ZAGON BAGAMARU 14,717,577.29
C/F 87,554,417.14
14a
CONTRACT AWARDED
JAHUN LG
B/F 87,554,417.14
10 7/3/2012
CONSTRUCTION OF FIVE DAILY PRAYER MOSQUE AT GIDAN DATTI 0853
ALH. MOHD D/MAIGODA GIDAN DATTI 852,589.00
11 7/3/2012
CONSTRUCTION OF FIVE DAILY PRAYER MOSQUE AT DANZE 0853
JAHUN CONS. & GEN. ENT DANZE 852,589.00
12 7/3/2012
CONSTRUCTION OF FIVE DAILY PRAYER MOSQUE AT GORA 0495 A.M. AUJARA GORA 610,000.00
cxliv
13 GENERAL RENOVATION AT DUTSE GUEST HOUSE DIRECT LABOUR DUTSE 4,555,665.00
14 26/12/12 INTER LOCK WORK AT ZANGO FRIDAY MOSQUE 0888 ALH. NURA ZANGO ZANGO 860,000.00
15 23/04/12 CONSTRUCTION OF TOILET AT AUJARA OUT POST 0863
ABDULAZIZ GADAWA AUJARA 354,184.00
16 30/07/12 ADDITIONAL WORK AT LAUTAI FRIDAY MOSQUE 0871
BIYUTA DAMUTAWA LAUTAI 243,000.00
17 8/8/2012
CONSTRUCTION OF TOILET AND RENOVATION AT NSCDC 5408 ABBA KALA NSCDC JAHUN 450,000.00
18 8/8/2012 REHABLITATION OF C H CENTER DIRECT LABOUR KADOAWAWA 14,383,924.00
19 8/8/2012 CONSTRUCT. OF FRIDAY MOSQUE DIRECT LABOUR
TARAYE & GWAMPAI 8,000,000.00
20 8/8/2012 CONSTRUCT. OF FIVE DAILY PRAYER MOSQUE D/MAIGADA GORA 882,589.00
21 14/2/12 PURCHASE OF OFFICIAL VEHICLE 408 MBU MOTORS JAHUN 5,500,000.00
22 14/2/12 PURCHASE OF OFFICIAL VEHICLE MBU MOTORS JAHUN 14,500,000.00
139,598,957.14
CONTRACT AWARDED
KAUGAMA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 7/12/2011 Construction of Slaughter House Gagaraukam Kaugama
3,000,000.00
2 7/10/2011 Electrification Project Eng. Rabiú b U/jibrin to Yola
3,000,000.00
cxlv
3 14-2-12 Purchase of official vehicle for chairman MBU Motors Kaugama
5,500,000.00
4 14-2-12 Purchase of official vehicle for vice chairman MBU Motors Kaugama
14,500,000.00
TOTAL 26,000,000.00
CONTRACT AWARDED
KAFIN HAUSA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 23-6-10 Complete Motorize Water Scheme Direct labour Inkaibo 8,834,985.00
2 30-5-12 Drilling of Hand pump Yayandi abubakar Gambawa 250,000.00
3 13-2-12 Drilling of Hand pump Bello Tela Sarawa 250,000.00
4 16-7-12 Drilling of Hand pump Yaú Malamawa M/tudu 250,000.00
5 3/5/2012 Drilling of Hand pump Alhaji Bubu Fadawa 250,000.00
6 26-1-12 Drilling of Hand pump Isa masasadi Salawa 250,000.00
7 2/2/2012 Drilling of Hand pump AalhajiYaú Malamawa Kazayare 250,000.00
8 24-5-12 Drilling of Hand pump new quaters Umar Mmusa 250,000.00
9 24-5-12 Drilling of Hand pump Alhaji Adamu Mai Biredi Maikwalbe 250,000.00
10 2/5/2012 Drilling of Hand pump Isah Muhd Jabarin Fulani 250,000.00
11 24-5-12 Drilling of Hand pump A lhaji Ismaíl kwarin riga 250,000.00
12 24-5-12 Conecting of100mm motorize borehole Alhaji Ismaíl Distric Head Balangu 1,036,042.00
13 24-5-12 Reactivation of solar borehole lawan Busuri G/Sarki 1,504,117.00
14 14-2-12 Renovation of 3bedroom house Y/INVEST Staff Quarters 11,972,003.12
15 14-2-12 Renovation of 2bedroom house Alhaji Babani Staff Quarters 7,185,219.36
cxlvi
16 14-2-12 Renovation of 5bedroom house A. Zakar Jabo Staff Quarters 6,615,902.24
17 14-2-12 purchase of offficial vehicle for chaiman MBU Motors K/hausa 5,500,000.00
18 14-2-12 Purchase of Official Vehicles MBU Motors K/hausa 14,500,000.00
19 24-5-12 Construction of Juma'at mosque Direct labour TAMBALE 2,000,000.00
TOTAL 61,648,268.72
CONTRACT AWARDED
KAZAURE LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 27/7/2012 ELECTRIFICATION PROJECT 9165 HOD WORKS
LG STAFF QUARTERS 390,000.00
2 27/7/2012 CONSTR.OF D/HEAD HOUSE PHS.1-2 9166 MANHAB GLOBAL DANDI 21,931,456.00
3 27/7/2012 PUR.OF13KVA GEN. &2NO.BOREHOLE 9164
BABANGIDA M/FACI KAZAURE 3,637,475.00
4 15/3/2012 ELECTRIFICATION PROJECT
KURTU VENTURE DANDOKA FITARI 3,000,000.00
5 11/11/2012 CONSTR. OF 1 BLOCK OF 2 CLASSROOM
A. SANI ABDULKADIR & SONS KARAFTAKI 2,964,934.00
7 14/2/2012 PURCHASE OF OFFICIAL VEHICLE 408 MBU MOTORS JAHUN 5,500,000.00
8 14/2/2012 PURCHASE OF OFFICIAL VEHICLE MBU MOTORS JAHUN 14,500,000.00
cxlvii
TOTAL 51,923,865.00
17
CONTRACT AWARDED
KIRI-KASAMMA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 14-2-12 Complete Solar Water Wcheme ADZGlobal services Masama 10,336,196.32
2 14-2-12 Complete Solar Water Scheme ADZGlobal services Gubusun 10,336,196.32
3 14-2-12 Electrification Project Turabu Costrucion Garin malaji 15,004,496.32
4 14-2-12 Electrificatiion Project Turabu Costrucion Malori 15,004,496.32
5 6/4/2012 Construction of a new Hand pump Muhd Musa LTD guri juction 200,000.00
6 14-2-12 construction of a motorized water scheme
NGA LOMA Gen ent. Turabu gabas 9,152,543.04
7 22-2-12 Construction of a new Hand pump Mmai Aji marma Nig Marrma u/shanu 200,000.00
8 22-2-12 Construction of a new Hand pump
Alhaji abdu marma Nig LTD Marma islamiyya 200,000.00
cxlviii
9 22-2-12 Construction of a new Hand pump
Alhaji Ayuba madachi Nig Madachi 200,000.00
10 22-2-12 Construction of a new Hand pump
Alhaji Ali Jannailo Nig LTD Gidan Babayo 200,000.00
11 22-2-12 Construction of a new Hand pump
Lawawn hassan Babuwa Rigar Ado Katinti 200,000.00
12 22-2-12 Construction of a new Hand pump Adamu Ali Dankabo Rigar Wakili Duwale 200,000.00
13 22-2-12 Construction of a new Hand pump Olu sawo Nig Rigar Gonar Dawa 200,000.00
14 22-2-12 Construction of a new Hand pump Dunduma Shugaba Busuku Makaranta 200,000.00
15 22-2-12 Construction of a new Hand pump
Adamu salari Nig LTD Daleri jumaat mosque 200,000.00
16 22-2-12 Construction of a new Hand pump
Abdu Lidalle Nig LTD Rubban kamaji 200,000.00
17 22-2-12 Construction of a new Hand pump Alhajji Abdu Izza
rigar yakubu m/galadima 200,000.00
18 22-2-12 Construction of a new Hand pump
Adamu Tsauya Nig LTD Matara fulani 200,000.00
19 22-2-12 Construction of a new Hand pump
Adamu Ule fandu Nig Kaiwari 200,000.00
20 22-2-12 Construction of a new Hand pump Musa ziko Nig Bakadi 200,000.00
C/F 62,833,928.32
18a
CONTRACT AWARDED
K/KASAMMA LG
B/F 62,833,928.32
21 22-2-12 Construction of a new Hand pump
Miko musa KKM Nig Rigar Dina 200,000.00
22 11/5/2012 Construction of lock up shos Usman Mohd Nig Turabu Market 4,027,605.60
cxlix
2nd
23 11/5/2012 Construction of waiting shade Dodo special Nig Marma 1,518,846.00
24 11/5/2012 Costruction of waiting shade Bala Shaaibu Nig Madachi 1,518,846.00
25 11/5/2012 Construction of market stall Bulama Musa kari
Nig kirikasamma market 1,171,302.72
26 11/5/2012 Construction of market stall A. Teacher Nig LTD dilmari market 1,171,302.72
27 11/5/2012 Construction of market stall Dinau jarmau Nig
LTD dilmari market 1,171,302.72
28 11/5/2012 Wall of fancing of staff Queters garoyo bulama Nig KKM Staff qttrs 3,000,000.00
29 11/5/2012 Wall Fencing of staff Quarters B Ganyo bulama KKM Staff qttrs 2,958,988.97
30 11/5/2012 Wall Fencing of staff Quarters north south Bukar magoyo KKM Staff qttrs 2,492,730.00
31 11/5/2012 Wall Fencing of staff queters (North side) A Garba Matar KKM Staff qttrs 2,000,000.00
32 11/5/2012 Wall Fancing of staff querters (north side) B A Garba Matar KKM Staff qttrs 2,300,000.00
33 6/6/2012 Wall fencing of staff querters nort side additional wall A Garba Matar KKM Staff qttrs 449,106.36
34 6/6/2012 Wall fencing of staff querter (bada sidi) additional works
Gayu Bulama Nig LTD KKM Staff qttrs 947,432.75
35 1/8/2011 Electrification projec [ ongoing]
Gayu Bulama Nig LTD Gabta 5,207,521.52
36 25-6-12 Electrificatiion project Muhd T muhd Sunkuye 12,794,311.98
37 6/2/2012 Road side Tree Planting Direct labour road side 1,000,000.00
38 28-6-12 Electrification project Turabu Costrucion Kuka Dabo 14,684,997.21
39 17-3-12 Purchase of hand pump materials Direct Purchase LG Secratiat 8,500,000.00
40 17-3-12 Purcase of 10 no motor cycles Direct Purchase LG Secratiat 1,000,000.00
C/F 130,948,222.87
18b
cl
CONTRACT AWARDED
K/KASAMMA LG
B/F 130,948,222.87
41 17-3-12 Purchase of official vehicle for chairman (peogeot408) MBU Motors Office of Chairman 5,500,000.00
42 17-3-12
Purchase of official vehicle for vice chairman secretary concil leader MBU Motors LG Secratiat 14,500,000.00
43 26-11-12 purchase of 4No mass Traansit (SHARON)
Kassamma Gen. Motors LG Secratiat 5,200,000.00
44 6/9/2012 Improvement of front walling of staff quarters Ubale Malam Nig LG Qtrs 2,205,280.00
45 31-12-12 Purchase of 1Nopick up (MAZDA)
Kassamma Gen. Motors DPO office KKM 1,600,000.00
46 24-12-12 Purchase of Hand pump materials Direct Purchase LG 3,500,000.00
47 25-12-12 Purchase of working material for commnity dept Direct Purchase LG 1,500,000.00
48 28-6-12
Purchase of furniture for supervisory councilor and advise LG Sert 2,722,500.00
49 6/12/2012 Renovation of Dilmain Health post Alhaji Adamu muhd Dimari 1,845,843.72
TOTAL 169,521,846.59
cli
CONTRACT AWARDED
KIYAWA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 27-1-12 Construction of Hand pump Abdullahi Naola Godawa
328,630.00
2 14-12-12 Construction of Hand pump Ismaíl Ahmad Fanteka
328,630.00
3 17-2-12 Construction of Hand pump Ismaíl Ahmad Jamaár isah
328,630.00
4 24-2-12 Construction of five daily prayer kaila isah Barnawa
642,917.23
5 9/3/2012 construction of Drainage Garba Yaú Kauta Kiyawa
744,824.56
6 14-3-12 Construction of waste water collection point Sule manja Tsalakawa
236,604.44
7 22-3-12 Construction of Hand pump Isah Liman D. Yashi
328,630.00
8 13-3-12 Construction of Open well Alh. Ibrahim jet Gidan Bature
280,462.50
9 14-3-12 Construction of Hand pump Hamisu Yaú N Chediya
226,800.00
10 13-4-12 Construction of Hand pump Tijjani Galadima Galamawa
328,630.00
11 13-4-12 Construction of islamiyya school Danladi Biliya Kanti kiyawa
4,570,072.70
12 13-4-12 Construction of Jumaát Mosque Amadu Kwaimawa Sabon gari
439,776.60
13 13-4-12 Construction of Jumaát Mosque Adamu Mai mai Akar
4,397,776.60
14 13-4-12 Construction of islamiyya school Yakubu fake harba
4,570,072.70
15 11/4/2012 Construction of Hand pump Bako ahmad Malamawa
328,630.00
16 2/4/2014 Construction of five daily prayer Alh. Yaú Usaini Gidan Dachi
642,917.23
17 19-4-12 Construction of five daily prayer Sule Mamuda Harba 637,365.96
18 22-4-12 Construction of five daily prayer Haruna Dan ture Bargawa 635,926.34
19 22-4-12 Construction of Hand pump Ismaíl Ahmad J. Isah Gabas
clii
328,630.00
20 22-4-12 Construction of Open well Alh. Danjuma Idris Gerawa fulani 183,000.00
21 22-4-12 Construction of Hand pump Alh. Danjuma Idris Dugu 281,062.00
C/F 20,789,988.86
19a
CONTRACTS AWARDED
KIYAWA L.G
B/F 20,789,988.86
24 2/5/2012 Construction of five daily prayer Auwal katanga Yalwa katanga 635,926.34
25 2/5/2012 Construction of Hand pump Alh. Sabo Kwara Ganyo 328,630.00
26 10/3/2012 Construction of five daily prayer Badamasi ubani Unguwar mahauta 328,630.00
27 17-5-12 Electrification Extention Suleiman adamu Madina 1,916,860.00
28 17-5-12 Construction of Hand pump Ibrahim masaya Auyakawa 328,630.00
29 17-5-12 Construction of Hand pump Ibrahim masaya Zawaya 328,630.00
30 16-5-12 Construction of Open well lawan salisu Alalau fulani 290,640.00
31 18-5-12 Construction of Open well Mutari Gani Lajiko 280,462.00
32 6/6/2012 construction of motor park Alh Garba Gali balago 7,830,674.42
33 14-8-12 Construction of District Head House Ishaq Abubakar Shuwarin 17,155,084.10
34 14-6-12 Construction of Open well Zailani kwanda karangiya 280,462.50
cliii
35 14-6-12 Construction of Open well Haruna balago Alagarno 292,625.00
36 26-6-12 Construction of Hand punp yunusa datti Tsangayawa 328,630.00
37 27-6-12 Construction of Open well umar karaga Abarawa 280,462.00
38 2/8/2012 Extention of retaculation Network dahiru dangoli Dangoli 358,370.00
39 2/8/2012 Construction of Hand pump lawan salisu masaya 328,630.00
40 2/8/2012 Construction of Hand pump lawan salisu Chiwina 328,630.00
41 2/8/2012 Construction of five daily prayer Nasiru Ahmad kiyawa 1,029,554.70
42 3/8/2012 Construction of Hand pump Abdullahi naula Kulluru 635,524.00
C/F 54,077,043.92
19b
cliv
CONTRACT AWARDED
KIYAWA L.G
B/F 54,077,043.92
43 23-8-12 Construction of islamiyya school Hussain Abdu Shatari 5,281,928.86
44 25-8-12 Construction of waiting stall dahiru dangoli Dangoli 511,844.85
45 3/1/2012 Construction of Open well Abdullahi G Bajidawa 280,462.00
46 3/1/2012 Construction of five daily prayer Yunusa Muhd Majawa 635,524.00
47 30-7-12 Construction of five daily prayer Tijjani Galadima G makama 635,524.00
48 5/9/2012 Construction of five daily prayer Garba G/dole Kanoke 635,524.00
49 11/9/2012 Construction of Open well M. Tasiú sha Shadaka 280,462.00
50 19-9-12 Construction of five daily prayer Danladi bilya G. Talo 635,524.00
51 25-9-12 Extention of electricity line Mustapha A kiyawa 515,025.00
52 25-9-12 Construction of Hand pump Bashari Adamu G. Tilo 328,630.00
53 10/10/2012 Extention of electricity line Hassan Maáji kiyawa 209,990.00
54 16-5-12 Construction of five daily prayer Tukur Adamu balago 6,355,334.00
55 18-5-12 Construction of Open well Baba Zabi Bazabi 290,640.00
56 14-2-12 Construction of Hand pump lawan salisu Malajele 328,630.00
57 14-2-12 Purchase of official vehicle for chairman MBU Motors kiyawa
5,500,000.00
clv
CONTRACT AWARDED
MALAM-MADORI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 9/10/2012
ELECTRIFICATION OF SHAYYA VILLAGE 0474
DUTSE TAURA NIG. LTD SHAYYA 3,765,187.84
2 9/10/2012
ELECTRIFICATION OF AKURYA VILLAGE 0475
DUTSE TAURA NIG. LTD AKURYA 4,627,593.41
3 6/5/2012 SUPPLY OF MATTRESS 4857
BABANNAN KOLI TRADING M/MADORI 150,800.00
4 6/5/2012
PURCHASE OF HAND/PUMP MATERIALS 0485
HOD WASH M/MADORI (Direct Purchase) M/MADORI 7,000,000.00
5 14/11/2012
CONSTRUCTION OF HAND PUMP AT RIGAR ISARI,RIGAR DAKIDO,RIGAR ISAH KATO,RIGAR ALH. HARUNA 0470
RUWA T/GHANA LTD RIGAR ISARI, 1,400,000.00
6 14/2/12
PURCHASE OF OFFICIAL VEHICLE 408 MBU MOTORS M/MADORI 5,500,000.00
7 14/2/12 PURCHASE OF OFFICIAL VEHICLE MBU MOTORS M/MADORI 14,500,000.00
TOTAL 36,943,581.25
58 14-2-12 purchase of official vehicle for vice chairman MBU Motors kiyawa
14,500,000.00
Total
91,002,086.63
clvi
20
CONTRACT AWARDED
MAIGATARI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 16/05/2012
PURCH. OF WATER GENERATOR 6001/3
DIRECT LABOUR ARBUS 1,950,000.00
2 25/04/2012 PURCH.OF WATER GENERATOR 6001/3
DIRECT LABOUR JAJERI 1,950,000.00
3 6/1/2012
COMPLETE WATER SOLAR SCHEME 6001/1
RABIU MUHAMMAD GAGO 5,999,730.00
4 10/2/2012
COMPLETE WATER SOLAR SCHEME 6001/1
MUHAMMAD RAMBO G/GALADIMA 5,999,730.00
5 7/3/2012 CONSTR.OF 3 NO.HAND PUMP 6001/3
ALH. DAKE GUMEL VARIOUS PLACES 1,287,000.00
6 25/05/2012 CONSTR.OF JUMA AT MOSQUE 5002/2
GARIS INVESTMENT LTD. GALADI 29,755,429.22
7 7/3/2012 CONSTR. OF DRAINAGE 2004/8 ALH. BASHIR TSANGAYA 619,000.00
clvii
8 15/10/2012 EXTENSION OF LT ELECTR.PROJECT 5002/3 YUSIF SANI
G/KWALAND-GWIMADO 949,034
9 15/06/2012 ELECTRIFICATION PROJECT 4006/1
ALH. MUHAMMADU K/GIWA 4,869,700.00
10 27//03/2012 ELECTR.PROJ. OF UNG KATTA KARA 4006/1
ALH. SANI ADAMU UNGUWAR K KARA 8,524,542.00
11 1/6/2012
EXTEN.OF WATER PIPE LINE AT UNG.GBS 6000/3
ALH. YAHAYA NA IBI UNGUWAR GABAS 846,195.00
12 5/6/2012
EXTN.OF WATER PIPELINE AT NSRW 6000/3
UMAR SULE MONKEY NASARAWA 750,000.00
13 28/06/2012
PURCH. OF OFF.FURN. 7NO. COUNLRS 7001/1
YAHAYA IBRAHIM LG SECRETARIATE 5,082,740.00
14 10/6/2012
MONTHLY PURCH.OF HANDPUMP MATERIAL 6001/4 USMAN MATI LG SECRETARIATE 1,500,000.00
15 14/8/2012
ANNUAL DRAINAGE EVACUATION 5004/3
RABIU MADANA MAIGATARI 3,407,884.00
C/F 73,490,984.22
21a
CONTRACT AWARDED
MAIGATARI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 73,490,984.22
16 19/7/2012 RENOV. OF GUEST HOUSE, DUTSE 2009/F
DIRECT LABOUR DUTSE 818,000.00
clviii
17 12/5/2012
RENOV. OF I/C PHC RESIDENCE, MGR 2009/F
TANIMU MAGAJI MAIGATARI 595,000.00
18 30/7/2012 RENOV. & FURN. OF MAGIST.HOUSE 2009/F ALH. FANDO MAIGATARI 873,800.00
19 20/8/2012
RENOV.OF SLAUGHTER HOUSE PHS 1 2009/F DATTI HALILU MAIGATARI 1,600,000.00
20 22/11/2012
CONSTR.OF MODERN LIVESTOCK MKT 2009/F STATE MAIGATARI 38,538,837.15
21 15/9/2012
MONTHLY PURCH.OF HANDPUMP MATERIALS 6001/4
DIRECT PURCHASE MAIGATARI 18,000,000.00
22 25/10/2012 MDG COUNTER FUNDING 208/13 STATE MAIGATARI 40,000,000.00
TOTAL 173,916,621.37
CONTRACT AWARDED
MIGA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 13/4/2012 ELECTRIFICATION PROJECT 0152 HIGH LIGHT LTD JAMAGA 22,974,216.48
2 19/4/2012 ELECTRIFICATION PROJECT 0153 IHSAN DRILLING & INV TSAGAIWA 33,494,216.48
3 19/4/2012 CONSTRUCTION OF MOSQUE 0154 IHSAN DRILLING DAWA 1,212,821.70
4 19/4/2012 CONSTRUCTION OF MOSQUE 0155 INVESTMENT NIG. NAMAKO 1,212.821.70
5 19/4/2012 CONSTRUCTION OF MOSQUE 0156 WADA ISYAKU MAJIRGA 1,212,821.70
6 19/4/2012 CONSTRUCTION OF MOSQUE 0157 ALI ABDULLAHI ZUGAWA 1,212,821.70
clix
7 19/4/2012 CONSTRUCTION OF MOSQUE 0158 NAMADI HANTSU KADIRAWA 1,212,821.70
8 19/4/2012 CONSTRUCTION OF MOSQUE 0159 MUH'D NATA ALA GIDAN TSAMIYA 1,212,821.70
9 19/4/2012 CONSTRUCTION OF MOSQUE 0160 SALE LADAN GAMATAN 1,212,821.70
10 19/4/2012 CONSTRUCTION OF MOSQUE 0161 UBA KIRNANDE KIRNANDE 1,212,821.70
11 19/4/2012 CONSTRUCTION OF MOSQUE 0162 YUSIF NAFADAW NAFADAWA 1,212,821.70
13 19/4/2012 CONSTRUCTION OF MOSQUE 0163 DAUDA ILU MAIGANJARA 1,212,821.70
14 19/4/2012 CONSTR. OF HANDPUMP 0164 ALH DOGO WAILABA 351,397.00
15 19/4/2012 CONSTR. OF HANDPUMP 0165 BASIRU NANAKO GIDAN YAU 261,091.00
16 19/4/2012 CONSTR. OF HANDPUMP 0166 GARBA KAULASA JAMAGA 261,091.00
17 19/4/2012 CONSTR. OF HANDPUMP 0167 HAMISU RABIU TSAGAIWA 351,397.00
18 19/4/2012 CONSTR. OF HANDPUMP 0168 SABO ROMAWA MUJIRGA 261,091.00
19 19/4/2012 CONSTR. OF HANDPUMP 0169 YAKUBU M/TANGARAN KADIRAWA 261,091.00
20 19/4/2012 CONSTR. OF HANDPUMP 0170 YAKUBU M TANG SARAWUYA 261,091.00
C/F 69,392,077.26
22a
CONTRACT AWARDED
MIGA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 69,392,077.26
clx
21 19/4/2012 CONSTR. OF HANDPUMP 0171 MUHD MARKEWA MAIGANJARA 261,091.00
22 19/4/2012 CONSTR. OF HANDPUMP 0172 ADAMU DMGNW LIMAMAI 261,091.00
23 19/4/2012 CONSTR. OF HANDPUMP 0173 D/SALLAH ADAMU GIDAN NA ALLAH 261,091.00
24 19/4/2012 CONSTR. OF HANDPUMP 0174 IBRAHIM YAYA JUMA 351,397.00
25 19/4/2012 CONSTR. OF HANDPUMP 0175 HARUNA D.MLK DUJA 351,397.00
26 19/4/2012 CONSTR. OF HANDPUMP 0176 TSOHO GANAWA GANAWA 351,397.00
27 19/4/2012 CONSTR. OF HANDPUMP 0177 UMAR HARUNA WALAWA 351,397.00
28 19/4/2012 CONSTR. OF HANDPUMP 0178 ISYAKU DAN YAYA GANUWA 351,397.00
29 19/4/2012 CONSTR. OF HANDPUMP 0179 IDRIS GARBA GIDAN GARJA 351,397.00
30 19/4/2012 CONSTR. OF HANDPUMP 0180 ADAMU AMD MASEWA 351,397.00
31 19/4/2012 CONSTR. OF HANDPUMP 0181 USMAN JIBRIN GARBO 351,397.00
32 19/4/2012 CONSTR. OF HANDPUMP 0182 WAKILI SABO SABUWAR JIGAWA 351,397.00
33 19/4/2012 CONSTR. OF HANDPUMP 0183 YAKUBU MOHD GIDAN SARKI 351,397.00
34 30/5/2012 MOTORIZED WATER SCHEME 0184 LOYALTY PROP. YANDUNA 12,402,467.80
35 30/5/2012 CONSTR.OF 9 BEDROOMS 0185 M.J. AGUFA LG STAFF QTRS 9,907,677.55
36 30/5/2012 WATER EXTENSION 0188 SHUAIBU SANSANI MUDIGA 2,559,320.00
37 30/5/2012 WATER EXTENSION 0187 ABDUL ABBAS TSAKUWAWA 2,242,960.00
38 30/4/2012 CONSTR.OF DRAINAGE 0189 SA ADU MUHD DANGYATIN 1,552,489.23
39 30/4/2012 CONSTR.OF DRAINAGE 0190 ALH.GARBA GARBO 1,989,825.45
40 30/4/2012 INTER LOCKING 0197 ADAMU SARKI MIGA 3,000,000.00
41 30/4/2012 RENOV.OF CM'S HOUSE 0196 ADAMU SARKI MIGA 4,671,279.00
42 30/4/2012 CONSTR.OF FRIDAY MOSQUE,MIGA 0194 MEGA LINKS MIGA 35,789,695.55
43 30/4/2012 ELECTRIFICATION PROJECT 0195 HIGH LIGHT LTD KIRNANDE 12,213,783.03
TOTAL 160,018,817.87
22b
clxi
CONTRACT AWARDED
RINGIM LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 2012 RENOV.OF INEC OFFICE, RINGIM SALMANU UBA RINGIM 3,281,611.63
2 2012 RENOV.OF CHAIRMAN GUEST HOUSE RABIU DABI RINGIM 4,850,983.30
3 2012 MOTORIZED BOREHOLE SABO MULKI DOGAJI 7,975,769.03
4 2012 COMPLETION OF FRIDAYMOSQUE DIRECT LABOUR AURAMO HAJI 1,080,000.00
5 14/2/12 PURCHASE OF OFFICIAL VEHICLE 408 MBU MOTORS RINGIM
5,500,000.00
6 14/2/12 PURCHASE OF OFFICIAL VEHICLE MBU MOTORS RINGIM
14,500,000.00
TOTAL 37,188,363.96
CONTRACT AWARDED
RONI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 15/5/2012 COSTRUCTION OF DRAINAGE 0914
IBRAHIM ALKASSIM AND OTHER S/UNGUWA RONI
2,265,489.88
2 15/5/2012 COSTRUCTION OF HEALTH POST 0905 BELLO HARUNA TUNTUBE
2,224,624.50
3 15/5/2012 COSTRUCTION OF HEALTH POST 0906
UMAR SALMANU & OTHER WUDDI
2,224,624.50
4 15/5/2012 COSTRUCTION OF ISLAMIYYA SCHOOL 0908
ABDU DOGO & MAL. BAWA S/UNGUWA RONI
2,064,855.50
clxii
5 13/2/2012 WALL FENCING OF RONI MOTEL 0902
ALH. ISAH ACHILAFIYA RONI MOTEL
4,101,921.18
6 15/05/201
2 COSTRUCTION OF MARKET STORE 0913
MAL. USMAN & OTHER AMARYAWA
2,143,953.16
7 15/5/2012 COSTRUCTION OF ISLAMIYYA SCHOOL 0907
SARKIN FAWA & GARBA DANTILA KAYALWA
2,064,855.50
8 10/6/2012 ELECTRIFICATION FROM GADA TO JANGEFE 0923 ALH.SHEHU UMAR GADA- JANGEFE
20,603,306.59
9 10/7/2012
COSTRUCTION OF MOTORIZED BOREHOLE WITH OVERHEAD TANK 0920
ALH GARZALI YA'U RONI UNGUWAR KAYA
14,289,966.60
10 4/6/2012 COSTRUCTION OF JUMA'AT MOSQUE AT GORA 0917
YANDUNA VENTURES SUNUSI ABDULLAHI GORA
3,800,000.00
11 15/5/2012 COSTRUCTION OF DRAINAGE 0909 ALH. ABDU DAM 897,028.16
12 2/5/2012 COSTRUCTION OF 5 DAILY PRAYER MOSQUE 5817 SAMA'ILA IBRAHIM
1,668,885.00
13 17/5/2012 EXTENSION OF POWER SUPPLY AT RONI 5837 SANI SAMA'ILA RONI
488,117.84
14 15/5/2012 RENOVATION OF ISLAMIYYA SCHOOL 5832 ABDUL DALHA
805,546.90
C/F 59,643,175.31
24a
CONTRACT AWARDED
RONI L.G
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
B/F 59,643,175.31
15 15/5/2012 COSTRUCTION OF TWO BLOCKS OF CLASS ROOM 5828 ALHAJI MANU
905,168.27
clxiii
16 15/5/2012
RENOVATION OF OF 5 DAILY PRAYER MOSQUE AT JANGEFE 5830
ALH. YAKUBU NANANA JANGEFE
1,254,590.97
17 24/12/201
2 NATIONAL WORK DRAINAGE SABUWAR UNGUWA 0919 B.M. SUKAR
SABUWAR UNGUWA
1,657,993.65
18 24/12/201
2 MAMUDAWA DAILY PRAYER MOSQUE 0921
ABUBAKAR LAWAN MAMUDAWA
1,044,554.80
19 18/12/201
2 KWAITA TSAKANI CULVERT 0922 ABUBAKAR SULAIMAN KWAITA
3,592,913.28
TOTAL 68,098,396.28
CONTRACT AWARDED
SULE-TANKARKAR LOCAL GOVERNMENT
S/NO DATE PROJECT
CONTRACT NUMBER CONTRACTOR LOCATION AMOUNT [N;K]
1 3/32012 Purchase of Vehicle for Chairman MBU Motors Sule tankarkar
5,500,000.00
2 6/4/2012 Purchase of 3No Official Vehicles MBU Motors Sule tankarkar 14,500,000.00
3 15/4/2012 CONSTR. NOMADIC PRIMARY SCHOOL ABDULLAHI DODO SULAWA FULANI
3,621,000.00
4 8/4/2012 CONSTR. NOMADIC PRIMARY SCHOOL TIJJANI SAYYADI GIDAN MARKE
3,621,000.00
5 4/4/2012 CONSTR. NOMADIC PRIMARY SCHOOL ABUBAKAR MOHD GWADAYI
3,621,000.00
TOTAL 30,863,000.00
clxiv
CONTRACT AWARDED
TAURA LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 20/11/2012 CONSTR.OF FRI.MOSQUE AT NAHUCHE 001/2012 A.A.SHITU NAHUCE 35,577,217.22
2 18/5/2012 PURCH.OF OFFICE FURNITURE-MEM. 002/2012
ABDULLAHI MUHAMMED LG SEC 10,573,049.55
3 7/8/2012 PURCH.OF OFFICE FURNITURE-COUNCL 003/2012 JAMILU MUJADDADI LG SEC 8,763,982.00
4 27/11/2012 CONSTR.OF 15 NO. HANDPUMPS 004/2012 SUNDRY PERSONS LG SE. 5,250,000.00
5 14/2/12 PURCHASE OF OFFICIAL VEHICLE 408 MBU MOTORS TAURA 5,500,000.00
6 14/2/12 PURCHASE OF OFFICIAL VEHICLE MBU MOTORS TAURA 14,500,000.00
TOTAL 80,164,248.77
CONTRACT AWARDED
YANKWASHI LOCAL GOVERNMENT
S/NO DATE PROJECT CONTRACT
NUMBER CONTRACTOR LOCATION
AMOUNT [ N : K ]
1 21-10-12 Construction of Feeder Road 6Km 313 Drilling Nig LTD Kuda- Firji 68,706,332.00
2 21-10-12 Construction of Friday Mosque Marb Eng Constructions Yankwashi 16,237,251.93
3 21-10-12 Purchase of H/Pump Materials Direct Labour Various places 2,500,000.00
4 21-10-12 Renovation of Staff Qtrs Mohd Umar & Others Staff Quarters 12,000,321.00
clxv
5 21-10-12 Fencing of Arewa Grave yard Marb Eng Constructions Karkarna Arewa 9,020,488.00
6 21-10-12 Fencing of Kudu Grave yard Musab Construction Nig Karkarna Kudu 7,000,000.00
7 21-10-12 Purchase of Land at Karkarna Direct Purchase Karkarna 2,000,000.00
8 21-10-12 Purchase of Land at Yankwashi Direct Purchase Yankwashi GJSS 2,600,000.00
9 14-2-12 Purchase of Land at Kwarare Direct Purchase Kwarare Primary Sch. 1,000,000.00
10 14-2-12 Electrification Project Eldee Construction Nig Ltd Ruruma 23,235,280.00
11 14-2-12 Drilling of 16No. H/Pump Ht Tade Drilling Nig Ltd Various places 13,000,000.00
12 14-2-12 Construction of Feeder Road 1.3Km Land Mgmt Nig Ltd
Murden Sama- Kasa 10,000,000.00
13 14-2-12 Construction of Feeder Road 1.1km
Y Tek Engineering Cop Ltd Murde- u/Magaji 11,590,582.00
14-2-12 Purchase of official vehicle for chairman MBU Motors YANKWASHI 5,500,000.00
14-2-12 purchase of official vehicle for vice chairman MBU Motors YANKWASHI
14,500,000.00
TOTAL 198,890,254.93
27
clxvi
SECTION (F)
APPENDIX SECTOR BASED REPORTS
JANUARY – DECEMBER, 2013
clxvii
SECTORIAL REPRESENTATION OF POST CONTRACT EVALUTION
FOR 27 NO LOCAL GOVERNMENT COUNCIL
SECTOR AMOUNT
PERCENTAG3E
BUILDING PROJECTS 1,227,437,778.00
49%
ELECTRIFICATION PROJECTS 426,077,246.39
17%
RURAL WATER SUPPLY 552,487,737.55
22%
ROADS PROJECT 306,802,230.62
12%
2,512,804,992.56
100%
clxviii
BUILDING PROJECTS49%
ELECTRIFICATION PROJECTS17%
RURAL WATER SUPPLY22%
ROADS PROJECT12%
SECTORIAL REPRESENTATION OF POST CONTRACT EVALUTION FOR THE 27NO LOCAL GOVERNMENT COUNCIL
clxix
1,227,437,778.00
426,077,246.39
552,487,737.55
306,802,230.62
BUILDING PROJECTS ELECTRIFICATION PROJECTS RURAL WATER SUPPLY ROADS PROJECT
27NO LOCAL GOVERNMENT COUNCILSSECTORIAL EXPENDITURE PERFORMANCE CHART
JANUARY - DECEMBER, 2012
clxx
SUMMARY OF PROJECTS REPORTED
JANUARY-DECEMBER,2012
S/NO VALUES (N)
1 PRE-CONTRACT EVALUATION (QUOTTED) 1,532,598,663.83
2 PRE-CONTRACT EVALUATION (DPPMB RECOMMENDED) 1,507,258,930.49
3 SAVINGS 16,339,733.34
4 APPROVED CAPITAL BUDGET FOR THE 27NO. L.G.COUNCILS 16,381,731,079.00
5 CONTRACT AWARDED JANUARY-DECEMBER,2011. 1,651,811,559.52
clxxi
ELECTRIFICATION PROJECTS
POST CONTRACT PROJECT
EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
1 Electrification project Turabu
construction Dauil Fani
14,653,125.86 BIRNIWA 12/2/2012 100 Completed
2 Electrification project Turabu
construction Bursali
17,246,843.86 BIRNIWA 13/10/2012 100 Completed
3 Electrification project phase 1 Competancy
Nig.LTD shawu
2,892,198.20 B/KUDU 18/5/12 100 Completed
4 Electrification project phase 2 Competancy
Nig.LTD shawu
1,763,375.00 B/KUDU 18/-5/2012 100 Completed
5 Electrification project phase1
Alhaji Hussaini
Duni Dangoli
1,944,824.00 B/KUDU 12/o6/12 100 Completed
6 Electrification project phase 2
Alhaji Hussaini
Duni Dangoli
1,416,029.00 B/KUDU 18/5/12 100 Completed
7 Electrification project
Alhaji Yahaya Inuwa Shungurun
2,266,742.00 B/KUDU 18/5/12 100 Completed
8 Electrification project Alhaji Jamilu
saleh Iggi U/Y
2,892,198.00 B/KUDU 18/5/12 100 Completed
9 Electrification project
Alhaji Ibrahim Natajo Kagadama
2,062,289.60 B/KUDU 18/8/12 100 Completed
10 Electrification project Alhaji
Dahiru Datti Warwade
457,296.00 B/KUDU 18/5/12 100 Completed
11 Electrification project Alhaji
Danjauro Injuwawa
1,865,655.00 B/KUDU 18/5/12 100 Completed
12 Electrification project Galadimawa
ventures Fanisau
7,889,773.84 DUTSE 3/9/2012 100 Completed
13 Electrification project BOK Nig
LTD S/gawo
8,400,444.89 DUTSE 27-2-12 100 Completed
14 Electrification project IHSAN Drill Investment U/gamji
9,397,465.16 GWIWA 25-5-12 100 Completed
15 Electrification project H.O.D. WORKS
L.G. staff quarters
390,000.00 KAZAURE 10/11/2012 100 Completed
clxxii
16 Electrification project at Fitari
Kurtu Ventures Dandoka Fitari
3,000,000.00 KAZAURE 15/3/2012 100 Completed
17 Electrification Project A. Shu'aibu
Guri Dolen Zugo
3,057,459.48 GURI 100 Completed
C/F
81,595,719.89
POST CONTRACT PROJECT
EVALUATION ELECTRIFICATION
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
81,595,719.89
18 Electrification project turabu costrucion
Garin malaji
15,004,496.32
KIRIKASSAMA 14-2-12 100 Completed
19 Electrificatiion project turabu costrucion Malori
15,004,496.32
KIRIKASSAMA 14-2-12 100 Completed
20 Electrification project ongoing
Gayu Bulama Nig
LTD Gabta
5,207,521.52
KIRIKASSAMA 1/8/2011 100 Completed
21 Electrificatiion project Muhd T muhd Sunkuye
12,794,311.98
KIRIKASSAMA 25-6-12 100 Completed
22 Electrification project turabu
costrucion kuka dabo
14,684,997.21
KIRIKASSAMA 28-6-12 100 Completed
23 Extention of LT Electrification project Yusif sani
G/kwalandi
to gwinmado
949,034.00 MAIGATARI 15-10-12 100 Completed
24 Electrification Project Alh. Muhd Nig LTD K/Giwa
4,869,700.00 MAIGATARI 15-6-12 100 Completed
25 Electrification Project Eng. Rabiú
b U/jibrin to Yola
12,000,000.00 KAUGAMA 7/10/2011 100 Completed
26 Electrification project highligh kirnande
12,213,783.06 MIGA 30-5-12 100 Completed
27 Electrification project High light Nig LTD jamaga
22,974,216.48 MIGA 13-4-12 100 Completed
28 Electrification project
Ihsan Drilling and invt. LTD Tsagaiwa
33,494,216.48 MIGA 19-4-12 100 Completed
29 Electrification Extention Suleiman
adamu Madina
1,916,860.00 KIYAWA 17-5-12 100 Completed
clxxiii
30 Extention of electricity line Mustapha A kiyawa
515,025.00 KIYAWA 19-9-12 100 Completed
31 Extention of electricity line Hassan Maáji kiyawa
209,990.00 KIYAWA 25-9-12 100 Completed
32 Electrification project MUL REAL
ESTATE KATAJE
6,757,181.22 AUYO 27- 7 - 12 85 ON-GOING
33 Electrification project SHIGO
GEN. ENTP SHIYO
18,162,995.13 AUYO 5/12/2012 40 ON-GOING
34 ELECTRICATI0N POJECT MARB ENG
SERV MUKU
14,966,120.85 GARKI 5/6/2012 60 ONGOING
35 ELECTRIFICATION PROJECT SHOW CASE DAUFA
RANTUMA
17,521,651.19 GUMEL 5/11/2008 60 ONGOING
C/F 290,842,316.65
S/N PROJECT EXECUTO
R LOCATIO
N CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
290,842,316.
65
36 ELECTRIFICATION PROJECT AMIM NIG
LTD
GURI-ADIYANI-
TUK
32,299,278.4
8 GURI 75 ON-GOING
37 ELECTRIFICATION PROJECT PURE HAND
KORE 8,070,240.00 K/HAUSA 23/6/2010 ON-GOING
38 ELECTRIFICATION PROJECT
A SANI ADAMU
LTD MAIGATA
RI
8,524,542.00 MAIGATARI 27/3/2012 30 ON-GOING
39 ELECTRIFICATION PROJECT
MARB ENG & DRILL JA;E
33,867,100.0
0 KAUGAMA 9/9/2011 ON-GOING
40 ELECTRIFICATION PROJECT
ALH. SHEHU UMAR JANGEFE
20,603,306.5
9 RONI 10/7/2012 30 ON-GOING
41 ELECTRIFICATION PROJECT
ELDEE CONS NIG
LTD RURUMA
TOWN
23,235,280.0
0 YANKWASHI 15/10/2012 50 ON-GOING
clxxiv
42 ELECTRIFICATION PROJECT SURAJO DUNGU
GASKOLE
8,635,182.67 RINGIM 3/1/2012 85 ON-GOING
TOTAL
426,077,246.
39
clxxv
POST CONTRACT PROJECT
EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
1 construction of mosque Gatafa Alh. Shuaib
Dogo
1,084,594.50 AUYO 4/4/2012 100 Completed
2 construction of mosque M. Ali M/shayi Wailare
1,084,594.90 AUYO 4/4/2012 100 Completed
3 construction of mosque Hassan Hassan D/marke
1,084,594.90 AUYO 4/4/2012 100 Completed
4 construction of mosque
Muhd fagaci Adaha
1,084,594.20 AUYO 4/4/2012 100 Completed
5 Construction of Friday Prayer Mosque INUSA MATI
Kunyafa Village
3,004,000.00 BABURA 11/4/2012 100 Completed
6 Construction of Friday Prayer Mosque SANI MAMU
Malamawa Village
3,004,000.00 BABURA 28/6/2012 100 Completed
7
Islamiyya Schools construction of 1 class room Blocks
ALH. AMADU LAMINTANI LAMINTANI
3,640,670.00 BABURA 11/4/2012 100 Completed
8 Construction of Nomadic School
ALH. AUDU GORA
Ungu Tsamiya
3,126,219.14 BABURA 11/4/2012 100 Completed
9 Construction of 5 daily prayer mosque
HALADU GATUTA Indurkuba
500,000.00 BABURA 12/4/2012 100 Completed
10 Improvement of Diginsa Jumaát Mosque
Saburu General Ent.
Diginsa
6,100,000.00 BIRNIWA 1/1/2012 100 Completed
11 Rehabilitation of FM Radio Station
director Dutse Radio station
Birniwa LG Section
3,606,955.10 BIRNIWA 25/5/2012 100 Completed
12 Completion of Kanya Mosque
Sadumu H. Kandami Nig.
LTD Kanya
4,578,234.48 BIRNIWA 13/10/2012 100 Completed
13 Renovation of daily Prayer Mosque
Zarigana Nig. LTD Dagit fani
400,000.00 BIRNIWA 8/4/2012 100 Completed
14 Renovation of daily Prayer Mosque
Zarigana Nig. LTD kirya
400,000.00 BIRNIWA 11/4/2012 100 Completed
15 Renovation of daily Prayer Mosque
Zarigana Nig. LTD fula tannan
400,000.00 BIRNIWA 11/4/2012 100 Completed
clxxvi
16 Renovation of daily Prayer Mosque
Zarigana Nig. LTD kupsa
400,000.00 BIRNIWA 11/4/2012 100 Completed
17 Renovation of daily Prayer Mosque
Zarigana Nig. LTD Goriba
400,000.00 BIRNIWA 11/4/2012 100 Completed
C/F
33,898,457.22
POST CONTRACT PROJECT EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
33,898,457.22
18 Renovation of daily Prayer Mosque
Zarigana Nig. LTD bulama lum
400,000.00 BIRNIWA 11/4/2012 100 Completed
19 Renovation of Staff Quarters No. 1
Zarigana Nig. LTD Birniwa
2,648,874.69 BIRNIWA 24/4/2012 100 Completed
20 Renovation of Staff Quarters No. 2
Musa Yille Nig. LTD Birniwa
2,396,565.58 BIRNIWA 6/12/2012 100 Completed
21 Renovation of jumaát mosque Alhaji Mohd
Maigoro Janwawa
629,644.00 B/KUDU 5/6/2012 100 Completed
22 Construction of waiting shed Jinjiri Kangire Kangire
280,000.00 B/KUDU 29/2/12 100 Completed
23 Completion of BIHSA secretariat
Alhaji magaji Fawa B/kudu
816,783.00 B/KUDU 14/5/12 100 Completed
24 Flooring of islamiyya school Magaji shuáibu
Ihyaussunna islamiyya zarenawa
229,426.00 B/KUDU 30/1/12 100 Completed
25 Completion of daily prayer mosque
Mai unguwa Sule Odoji B/K
84,000.00 B/KUDU 20/5/11 100 Completed
27 Construction of 6m press steel tower tank
Mamuda Masaya Masaya
2,970,000.00 B/KUDU 15/6/12 100 Completed
28 Construction of wall fance Alhaji Amadu Mai Katako
Blind centre B/K
2,488,443.00 B/KUDU 14/12/12 100 Completed
clxxvii
29 Renovation of Upper sharia court jurge house
Abubakar Sulaiman B/kudu
470,000.00 B/KUDU 17-5-12 100 Completed
30 Renovation of JISIEC office Alahji Gambo
Over-Over B/kudu
748,330.00 B/KUDU 15-2-12 100 Completed
31 Construction of V.I.P Toilet NPI Office
256,912.89 DUTSE 9/11/2012 100 Completed
32 Construction of Friday mosque Sale chaichai Kyaran
5,455,639.03 DUTSE 3/9/2012 100 Completed
33 Construction of Engine room Alkali Sakwaya Galadima
554,468.00 DUTSE 4/12/2012 100 Completed
36 Construction of Market stalls at Gantsa
Batta I.O matto kaliya gwantsa
1,282,853.62 BUJI 18-7-12 100 Completed
37 construction of PiT latarine at Sagu
mal abdullahi kawaaya /
ibrahim chiddori
PHC Sagu 797,998.42
BUJI 18-7-12 100 Completed
38 construction of PiT latarine at Gantsa
mal abdullahi kawaaya /
ibrahim chiddori
Alagarno 167,520.00
BUJI 18-7-12 100 Completed
C/F 56,575,915.45
POST CONTRACT PROJECT EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F 56,575,915.45
39 constructioon of Pit latarine mal abdullahi kawaaya / ibrahim
chiddori
Lelen kudu 131,282.00
BUJI 18-7-12 100 Completed
40 constructioon of Pit latarine mal abdullahi kawaaya / ibrahim
chiddori
katirje 210,720.00
BUJI 18-7-12 100 Completed
41 constructioon of Pit latarine mal abdullahi kawaaya / ibrahim
chiddori
jibarin gantsa 84,240.00
BUJI 18-7-12 100 Completed
clxxviii
42 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori Jibarin ahto
123,360.00 BUJI 18-7-12 100 Completed
43 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori kauyere
62,640.00 BUJI 18-7-12 100 Completed
44 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori Gwagan
138,240.00 BUJI 18-7-12 100 Completed
45 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori Lirinde
138,240.00 BUJI 18-7-12 100 Completed
46 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori Mandabo
194,880.00 BUJI 18-7-12 100 Completed
47 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori shewari
151,680.00 BUJI 18-7-12 100 Completed
48 constructioon of Pit latarine
mal abdullahi kawaaya / ibrahim
chiddori Gwadayi
126,600.00 BUJI 18-7-12 100 Completed
52 Construction of Five daily prayer Mosque Alhaji Sabo Zakar
Sarkin Gabas
5,500,000.00 GAGARAWA 16-10-12 100 Completed
53 Fencing of Grave Yard Idris ya'u Abuja
Queters
7,071,428.23 GUMEL 7/2/2012 100 Completed
54 construction of drainage and culvert Ado Dankaggi
Tudun Alhaji Quaters
619,000.00 GUMEL 13-10-12 100 Completed
C/F
71,128,225.68
clxxix
POST CONTRACT PROJECT EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
71,128,225.68
55 construction of islamiyya school Babandi alaramma Danun Biri
1,000,000.00 GUMEL 17-8-11 100 Completed
56 construction of slaughter House Isma'il venture
Gagarawa Road
19,000,000.00 GUMEL 4/11/2011 100 Completed
57 construction of waiting shed Garba fate Malga
525,199.00 GWIWA 18-4-12 100 Completed
58 construction of jumaát mosque Chediya Venture Z/gauraye
5,724,098.47 GWIWA o6/6/12 100 Completed
59 construction of jumaát mosque Asa mai bulawus Dabi
5,724,098.47 GWIWA 26-2-12 100 Completed
60 Additional work at Rorau Distric head House Musab Nig LTD Korayal
2,972,256.00 GWIWA 13-2-12 100 Completed
61 Construction of five daily prayer mosque Also Mai Dusa Kwarare
5,724,098.47 GWIWA 10/12/2012 100 Completed
62 Completion of and furnishing of 9 Bed room staff Quarters Direct labour Gwiwa
1,513,500.00 GWIWA 20-12-12 100 Completed
63 Construction of One Block with Two Classrooms Samira Karshi Venture Wailare
4,128,705.94 GWIWA 18-7-12 100 Completed
65 Construction of five daily prayer mosque
Alhaji Lawan Abbulrazaq
Gwiwa U/Malamai
1,252,409.55 GWIWA 30-8-12 100 Completed
66 Construction of Islamiyya Alh. Samai'la Maishinkafa Zumburu
2,620,445.00 GWARAM 26-4-12 100 Completed
C/F
121,313,036.58
clxxx
POST CONTRACT PROJECT
EVALUATION
BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE STATUS
IN % REMARKS
B/F
121,313,036.58
67 purchase of furniture Interior wood Nig LTD Kila
64,988,848.00 GWARAM 21-6-12 100 Completed
68 construction of mini stadium phase 11 Bahatu Nig. Ltd Gwaram
22,000,000.00 GWARAM 9/6/2012 100 Completed
69 Renovation of Friday mosque Direct labour Salamanda
1,000,000.00 GWARAM 5/9/2012 100 Completed
71 Construction of Islamiyya Alhaji dalibi dingaya
2,629,646.90 GWARAM 15-11-12 100 Completed
72 Construction of Slaughter House Alhaji Mutari Sara Gwaram
3,466,385.75 GWARAM 22-11-12 100 Completed
74 Renovation of Lockup shops (BRNT) Sadiq
Olo Motor park Hadejia
719,504.02 HADEJIA 20-5-12 100 Completed
75 Construction of five daily prayer Mosque Alhaji Muhd Gada
Gidan Datti sabuwa
852,000.00 JAHUN 7/3/2012 100 Completed
76 Construction of five daily prayer Mosque M.I Jahun
Dinzai Gidan mai unguwa
852,000.00 JAHUN 7/3/2012 100 Completed
77 Construction of five daily prayer Mosque M.I Jahun Idandana
852,000.00 JAHUN 30-11-12 100 Completed
78 Construction of five daily prayer Mosque Alhaji Abdulrazak Gora
610,000.00 JAHUN 7/3/2012 100 Completed
79
Construction of 1 block of 2 classroom with office
A.Sani Abdulkadir & sons Ltd. Karaftaki
2,964,934.00 KAZAURE 11/11/2012 100 Completed
80 Construction of lock up shos 2nd Usman Mohd Nig
turabu market
4,027,605.60 KIRIKASAMMA 11/5/2012 100 Completed
81 Construction of waiting shade Dodo special Nig marma
1,518,846.00 KIRIKASAMMA 11/5/2012 100 Completed
82 Costruction of waiting shade Bala Shaaibu Nig madachi
1,518,846.00 KIRIKASAMMA 11/5/2012 100 Completed
83 Construction of market stall
Bulama Musa kari Nig
kirikasamma market
1,171,302.72 KIRIKASAMMA 11/5/2012 100 Completed
clxxxi
84 Construction of market stall A. Teacher Nig LTD
dilmari market
1,171,302.72 KIRIKASAMMA 11/5/2012 100 Completed
85 Construction of market stall
Dinau jarmau Nig LTD
dilmari market
1,171,302.72 KIRIKASAMMA 11/5/2012 100 Completed
C/F
232,827,561.01
POST CONTRACT PROJECT
EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE STATUS IN
% REMARKS
B/F
232,827,561.01
86
Wall of fencing of staff Quarters garoyo bulama Nig KKM Staff qttrs
3,000,000.00 KIRIKASAMMA 11/5/2012 100 Completed
87
wall fencing of staff Quarters B Ganyo bulama KKM Staff qttrs
2,958,988.97 KIRIKASAMMA 11/5/2012 100 Completed
88
wall fencing of staff Quarters north south Bukar magoyo KKM Staff qttrs
2,492,730.00 KIRIKASAMMA 11/5/2012 100 Completed
89
wall fencing of staff quarters (North side) A Garba Matar KKM Staff qttrs
2,000,000.00 KIRIKASAMMA 11/5/2012 100 Completed
90
wall fencing of staff quarrters (north side) B A Garba Matar KKM Staff qttrs
2,300,000.00 KIRIKASAMMA 11/5/2012 100 Completed
95
Renovation of Guest House at Dutse Direct Labour
Dutse quest House
818,000.00 MAIGATARI 19-7-12 100 Completed
96
Renovation of IC PHC Maigatari House Tanimu magaji LTD Maigatari PHC
595,000.00 MAIGATARI 12/5/2012 100 Completed
97 Construction of 5 daily wada isyaku dawa
1,212,821.70 MIGA 19-4-12 100 Completed
clxxxii
prayer mosque
98 construction of mosque sabo haladu namako
1,212,821.70 MIGA 19-4-12 100 Completed
99 construction of mosque ali abdullahi
majirga mai kanya
1,212,821.70 MIGA 19-4-12 100 Completed
100 construction of mosque namadu hantsu mai ganjara
1,212,821.70 MIGA 19-4-12 100 Completed
101 construction of mosque mohd nataala zugawa
1,212,821.70 MIGA 19-4-12 100 Completed
102 construction of mosque sale ladan kadirawa
1,212,821.70 MIGA 19-4-12 100 Completed
103 construction of mosque uba kirnande
dabakan alh garba
1,212,821.70 MIGA 19-4-12 100 Completed
104 Construction of mosque yusif nafawa
gidan tsimiya D/B
1,212,821.70 MIGA 19-4-12 100 Completed
105 construction of mosque dauda ilu
gamatan gabashi
1,212,821.70 MIGA 19-4-12 100 Completed
106 construction of mosque muhd mai jaka mudiga k/fada
1,212,821.70 MIGA 19-4-12 100 Completed
107
Construction of 9No Bedroom muhd jibrin agufa
miga staff querters
9,907,677.55 MIGA 30-5-12 100 Completed
108
Renovation of Chairman House Adamu sarki
miga staff querters
4,671,279.45 MIGA 30-5-12 100 Completed
109 wall fencing of Roni Model Alhaji isa Alkafiya Roni model
4,101,921.18 RONI 13-1-12 100 Completed
110
construction of Market stalls Mal usman Amaryawa
2,143,954.16 RONI 13-1-12 100 Completed
C/F
279,945,329.32
clxxxiii
POST CONTRACT PROJECT
EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
279,945,329.32
111 Construction of islamiyya school
Sarkin fawa Gardadantila Kayalwa
2,064,853.50 RONI 13-1-12 100 Completed
112 construction of wall fancing
MUSAB constructionLTD karkarna town
7,000,000.00 YANKWASHI 21-10-12 100 Completed
113 fencing of karkarna arewa Grave yard
MUSAB constructionLTD karkarna town
7,720,166.62 YANKWASHI 21-10-12 100 Completed
114 Construction of islamiyya school Danladi Biliya Kanti kiyawa
4,570,072.70 KIYAWA 13-4-12 100 Completed
115 Construction of Jumaát Mosque Amadu Kwaimawa Sabon gari
439,776.60 KIYAWA 13-4-12 100 Completed
116 Construction of Jumaát Mosque Adamu Mai mai Akar
4,397,776.60 KIYAWA 13-4-12 100 Completed
117 Construction of islamiyya school Yakubu fake harba
4,570,072.70 KIYAWA 13-4-12 100 Completed
118 Construction of five daily prayer Alh. Yaú Usaini Gidan Dachi
642,917.23 KIYAWA 2/4/2014 100 Completed
119 Construction of five daily prayer Sule Mamuda Harba
637,365.96 KIYAWA 19-4-12 100 Completed
120 Construction of five daily prayer Haruna Dan ture Bargawa
635,926.34 KIYAWA 22-4-12 100 Completed
121 Construction of five daily prayer Auwal katanga
Yalwa katanga
635,926.34 KIYAWA 2/5/2012 100 Completed
122 Construction of five daily prayer Badamasi ubani
Unguwar mahauta
328,630.00 KIYAWA 10/3/2012 100 Completed
123 Renovation of chairman guest house Rabiu Dabi Ringim
4,850,983.30 RINGIM 12/1/2012 100 Completed
124 Completion of juma'at mosque Direct labour Auramo Haji
1,080,000.00 RINGIM 6/11/2012 100 Completed
clxxxiv
125 construction of 3 nos. market stall A. Baya Dole Guri 2,396,836.05 GURI 27/2/12 100 Completed
126 construction of 3 nos. market stall A. Adamu umar Kadira
2,396,836.05 GURI 27/2/12 100 Completed
127 Completion of Juma'at mosque Umar Dodo Una
1,397,905.95 GURI 27/2/12 100 Completed
C/F
325,711,375.26
POST CONTRACT PROJECT
EVALUATION BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
325,711,375.26
128 Completion of Juma'at mosque Yakubu Abunabo
Yalwan Musari
1,547,067.00 GURI 27/2/12 100 Completed
129 Construction of market stall
Mashiru $ Baba Bala
Guri $ Kadira market
3,195,781.40 GURI 27/2/12 100 Completed
130 Renovation of Musari Mosque Alh. Musa Musari
6,800,000.00 GURI 100 Completed
131 Construction of peadatric word ALI MUSA AUYO AUYO
10,531,712.60 AUYO 8/7/2012 50 ONGOING
132 CONSTR. OF FRIDAY PRAYER MOSQUE
ALH. MUSA SHEHU ACHIYA
3,004,000.00 BABURA 11/11/2012 45 ON-GOING
133 CONSTR. OF FRIDAY PRAYER MOSQUE DAN YAYI
3,004,000.00 BABURA 11/4/2012 60 ON-GOING
134 COSNTR. OF ISLAMIYYA SCHOOL MATI DANHALILI GANA
3,126,219.14 BABURA 11/4/2012 45 ONGOING
135 CONSTR. OF ISLAMIYYA SCHOOL ZUBAIRU KANYA
TSAMIYA KWANCE
3,126,219.14 BABURA 11/4/2012 45 ONGOING
136 CONSTR. OF NOMADIC SCHOOL SANI MAHAMUD DANZAGO
5,000,000.00 BABURA 20/12/12 45 ONGOING
clxxxv
137 CONSTR. OF NOMADIC SCHOOL ALH. SADE KANYA KARFAWA
3,126,219.14 BABURA 11/4/2012 45 ONGOING
138 CONSTR. OF FRIDAY MOSQUE AUWWALU MATO
BUDINGA VILLAGE
4,310,492.96 B/KUDU 24/3/11 75 ON-GOING
139
CONSTR. BUJI DISTRCT HEAD HOUSE
YAYARI TUKUR NIG LTD BUJI
11,214,965.81 BUJI 11/12/2012 60 ONGOING
140 CONSTR. OF JUMAAT MOSQUE
YAYARI TUKUR NIG LTD MADABE
11,339,700.59 BUJI 11/12/2012 35 ONGOING
141 CONSTR. OF LOCK-UP SHOPS IHSAN NIG. LTD
SARA MARKET
13,780,694.70 BUJI 11/12/2012 35 ONGOING
142 CONSTR. OF DAILY PRAYER MOSQUE SANI AHOTO AHOTO
1,648,372.40 BUJI 11/12/2012 35 ONGOING
C/F
410,466,820.14
POST CONTRACT PROJECT EVALUATION
BUILDING PROJECTS
S/N PROJECT EXECUTOR
LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE
STATUS IN %
REMARKS
B/F
410,466,820.14
143 CONSTR OF DAILY PRAYER MOSQUE
GARBA UBALE & OTHER GWADAYI
1,648,372.40 BUJI 11/12/2012 35 ONGOING
144 CONSTR. OF DAILY PRAYER MOSQUE GARBA & OTHERS KWALELE
836,181.13 BUJI 11/12/2012 45 ONGOING
145 CONSTR OF DAILY PRAYER MOSQUE DANYARO & OHTERS
RIGAR GADA
836,181.13 BUJI 11/12/2005 55 ONGOING
146 CONSTR OF DAILY PRAYER MOSQUE IDUKA & OTHERS GANBASHA
836,181.13 BUJI 11/12/2012 45 ONGOING
147 CONSTR OF DAILY PRAYER MOSQUE USAINI & OTHERS JATA
836,181.13 BUJI 11/12/2012 45 ONGOING
148 CONSTR OF DAILY PRAYER MOSQUE DANBIRNI & OTHERS U/MAKERA
836,181.13 BUJI 11/12/2012 35 ONGOING
149 CONSTR OF PIT LATRINE SALE YAU & OTHERS U/MAINA
616,075.95 BUJI 30/12/2012 35 ONGOING
clxxxvi
150 CONSTR OF PIT LATRINE HARUNA A IDI Y/ TUKUR
616,075.95 BUJI 30/122012 35 ONGOING
151 CONSTR OF PIT LATRINE MUDDAFA & OTHERS GWADAYI
616,075.95 BUJI 30/12/2012 35 ONGOING
152 FENCING OF GARKI GGSS SLM AMINCI LTD GARKI
19,253,694.00 GARKI 2/6/2012 50 ONGOING
153 CONSTR. OF JUMAAT MOSQUE A MAGAJI GARKI DUNKUMI
4,165,494.61 GARKI 10/9/2013 60 ONGOING
154 RENOVATION OF HEALTH POST DIRECT LABOUR MUKU
3,510,328.37 GARKI 17/06/2012 70 ONGOING
156 CONSTR. OF MODERN MOTOR PARK ISMAEL VENTURES
GUMEL KANO RD 43,416,895.65 GUMEL 28/06/2012 20 ONGOING
157 CONSTR. OF SHOPPING PLAZA ILU GLOBAL VENTLTD
GUMEL TOWN
39,322,230.00 GUMEL 19/06/2010 50 ONGOING
158
COMPLETION OF SENIOR STAFF QUARTERS J KANDE NIG LTD GUMEL
34,389,233.00 GUMEL 8/8/2008 50 ONGOING
159 COMPLETION OF ZUGOBIYA MOSQUE MAIFAWA ZUGOBIYA
2,220,000.00 GURI 80 ON-GOING
C/F
564,422,201.67
POST CONTRACT PROJECT EVALUATION
BUILDING PROJECTS
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE STATUS
IN % REMARKS
B/F
564,422,201.67
160 FENCING OF GG UNITY SCHOOL RINGIM GALADANCI Gwaram
36,825,149.24 GWARAM 12/9/2012 60 ONGOING
161 CONSTR. OF ISLAMIYYA SCHOOL BASIR & CO NIG LTD KUYUNGU
2,629,645.60 GWARAM 13/12/2012 85 ONGOING
162
NEW LG SECRETARIATE CIROCO GWARAM
357,314,412.85 GWARAM 15/12/2012 90 ONGOING
163 RENOVATION OF 2NO. 3-BEDROOM HOUSE Y/INVEST
STAFF QUARTERS
11,972,003.12 K/HAUSA 10/10/2012 67 ON-GOING
clxxxvii
164 RENOVATION OF 1NO. 2-BEDROOM HOUSE ALHAJI BABANI
STAFF QUARTERS
7,185,219.36 K/HAUSA 10/10/2012 80 ON-GOING
165 RENOVATION OF 1NO. 5-BEDROOM HOUSE ALH. ZAKAR A JABO
STAFF QUARTERS
6,615,902.24 K/HAUSA 10/10/2012 56 ON-GOING
166
RENOVATION & FURNISHING OF DOCTORS HOUSE TANIMU MAGAJI
MAIGARI PHC
1,410,000.00 MAIGATARI 30/7/2012 80 ON-GOING
167 CONSTRUCTION OF FRIDAY MOSQUE A I G VENTURES BOSUWA
22,932,511.25 MAIGATARI 20/7/2012 80 ON-GOING
168 CONSTR. 0F JUMAAT MOSQUE S. A. H. VENTURES MARKE
11,550,467.00 KAUGAMA 10/7/2010 75 ON-GOING
169 CONSTR. 0F CENTRAL MOSQUE S.T.R ALLIA NIG LTD KAUGAMA
35,782,653.00 KAUGAMA 20/8/2010 55 ON-GOING
170 WALL FENCING OF GGASS MARYAM INVEST KAUGAMA
30,206,878.68 KAUGAMA 7/1/2009 ON-GOING
171
RENOVATION & INTERLOCKING OF CHAIRMAN HOUSE ADAMU SARKI MIGA
3,000,000.00 MIGA 30/5/2012 80 ON-GOING
172 CONSTR. OF CENTRAL MOSQUE MEGA LINK
MIGA TOWN
35,789,695.52 MIGA 30/5/2012 70 ON-GOING
173 CONSTR. OF NOMADIC PRIMARY SCHOOL ABDULLAHI DODO
SULAWA FULANI
3,621,000.00 S/TANKARKAR 15/4/2012 45 ON-GOING
174 CONSTR. OF NOMADIC PRIMARY SCHOOL TIJJANI SAYYADI
GIDAN MARKE
3,621,000.00 S/TANKARKAR 8/4/2012 45 ON-GOING
175 CONSTR. OF NOMADIC PRIMARY SCHOOL ABUBAKAR MOHD GWADAYI
3,621,000.00 S/TANKARKAR
4/4/2012 45 ON-GOING
176 CONSTR. OF FRIDAY MOSQUE ABDU SHITTU NALEKO
35,577,217.22 TAURA 20/11/2012 60 ON-GOING
177 CONSTR. OF HEALTH CENTER BELLO HARUNA TUTUBE
2,224,624.50 RONI 13/8/2012 50 ON-GOING
C/F
1,176,301,581.25
POST CONTRACT PROJECT EVALUATION
BUILDING PROJECTS
S/N PROJECT EXECUTOR
LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE
STATUS IN %
REMARKS
B/F
1,176,301,581.25
clxxxviii
178 CONSTR. OF HEALTH CENTER UMAR SALMA & OTHER WUDDI
2,224,624.50 RONI 15/82012 50 ON-GOING
179 COMPLETION OF ISLAMIYYA SCHOOL A. YUSIF & OTHERS
FANFAN ISKA RONI
1,000,000.00 RONI 4/6/2012 30 ON-GOING
180 CONSTR. OF JUMAAT MOSQUE YANDOMA VENTURES GORA
3,800,000.00 RONI 13/8/2012 80 ON-GOING
181 RENOVATION OF STAFF QUARTERS MOHD & others
STAFF QUARTERS
12,000,000.00 YANKWASHI 18/04/2012 50 ON-GOING
182 RENOVATION OF INEC OFFICE SALMANU UBA RINGIM
3,281,611.63 RINGIM 10/1/2012 96 ON-GOING
183 CONSTR. OF 1 BLOCK OFFICE & ATTCHMENT. ASAD VENTURES
GIDAN RUWA
2,965,934.00 KAZAURE 16/11/2010 60 COMPLETED
184 CONSTR. OF DAILY PRAYER MOSQUE LALO MAHAUCHI
GADA YAMMA
493,000.00 KAZAURE 16/11/2011 20 ON-GOING
185 CONSTR. OF 1 BLOCK ISLAMIYYA SCHOOL HASSAN ADAMU
GIDAN GONA
1,518,000.00 KAZAURE 3/6/2008 90 ON-GOING
186 CONSTR. OF DISTRICT HEAD HOUSE MAN HAB GLOBAL DANDI
21,931,456.47 KAZAURE 27/7/2012 50 ON-GOING
187 CONSTR. OF HEALTH POST
BABANGIDA M/FACI & NURA MATI
GEZOJI FULANI
1,921,570.15 KAZAURE 26/10/2011 50 ON-GOING
TOTAL
1,227,437,778.00
clxxxix
POST CONTRACT PROJECT EVALUATION
ROADS PROJECT
S/N PROJECT EXECUTOR
LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
1 Construction of double cell culvert
Alhaji Amadu Mai Katako Dokoki
2,377,000.00 B/KUDU 1/11/2012 100 Completed
2
Construction of 6m press steel tower tank
Mamuda Masaya Masaya
2,970,000.00 B/KUDU 15/6/12 100 Completed
3 Earth filling Alhaji Amadu Mai Katako Dokoki
2,861,712.00 B/KUDU 11/11/2012 100 Completed
4 earth filling Abdulkarim Saleh plantation road B/K
182,000.00 B/KUDU 3/10/2012 100 Completed
5 construction of drianage at gwadayi
Imamu Gwadayi Gwadayi
63,710.00 BUJI 19-9-12 100 Completed
6 construction of drianage at buji Ali buji buji town
327,313.00 BUJI 1/8/2012 100 Completed
7
payment for compensation for tonwship road LG Gumel
22,451,566.55 GUMEL 14-3-12 100 Completed
8 Construction of Drainage
Alhaji Yahaya Sale Indirawa 457,157.42 GWIWA 18-7-12 100 Completed
9
construction of drainage at casava processing factory Aya logistic Kila
6,012,239.49 GWARAM 9/8/2012 100 Completed
10 Construction of Drainage
Alhaji Baban Jiji L/tsamiyya Gayufa
1,623,657.75 HADEJIA 27-3-12 100 Completed
11 River Enbakment Direct Labouur Hadejia
2,440,000.00 HADEJIA 5/5/2012 100 Completed
12 Dredging work Direct Labouur Garko Transpomer
1,495,800.00 HADEJIA 5/5/2012 100 Completed
cxc
13 Dredging work Direct Labouur Gagulumarito mailolo
951,750.00 HADEJIA 5/5/2012 100 Completed
14 Dredging work Direct Labouur Transpormer NEPA
951,750.00 HADEJIA 5/5/2012 100 Completed
15 Dredging work Direct Labouur Wuriwa Qtr
609,576.00 HADEJIA 5/5/2012 100 Completed
16 Dredging work Direct Labouur Hadejia to Majia
1,333,375.00 HADEJIA 5/5/2012 100 Completed
17 Dredging work Direct Labouur Yayari Qtrs
270,874.00 HADEJIA 5/5/2012 100 Completed
18 Dredging work Direct Labouur Tagurza to K/fada
1,071,427.00 HADEJIA 5/5/2012 100 Completed
C/F
48,450,908.21
POST CONTRACT PROJECT
EVALUATION
ROADS PROJECT
S/N PROJECT EXECUTOR
LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT. COMMENCEMENT
DATE
STATUS IN %
REMARKS
48,450,908.21
19 Dredging work Direct Labouur K/kudu to Tano to Atafi
1,416,285.00 HADEJIA 5/5/2012 100 Completed
20 Dredging work Direct Labouur G/mati to Kakayi
1,067,915.00 HADEJIA 5/5/2012 100 Completed
21 Dredging work Direct Labouur Atafi to K/zaki
1,190,280.00 HADEJIA 5/5/2012 100 Completed
22 Dredging work Direct Labouur Hadejia
250,000.00 HADEJIA 5/5/2012 100 Completed
23 Dredging work Direct Labouur Local Govt qtrs Dutse
573,854.00 HADEJIA 5/5/2012 100 Completed
24 Road side Tree Direct labour road side KIRIKASAMM
A 6/2/2012 100 Completed
cxci
Planting 1,000,000.00
25 River Embakment direct labour miga sarayuya
1,700,000.00 MIGA 30-5-12 100 Completed
26 Construction of Drainage
Ibrahim Alkassim &
son Sabuwar unguwa Roni
2,465,489.88 RONI 15-5-12 100 Completed
27
Construction of feeder road from kudu to walaw to firji (6km) (phase 2)
313 Drilling and
construction Nig LTD Walawa to Furji
68,706,332.00 YANKWASHI 21-10-12 100 Completed
28 CONSTR. DRAINAGE MASKO BABURA 16/8/12 45 ON-GOING
29
CONSTR. OF MASAYA - TUKUDA TAR ROAD
GERAWA GLOBAL LTD MASAYA-TUDA 17KM
47,200,000.00 B/KUDU 24/3/11 50 ON-GOING
30
CONSTR OF DRAINAGE & CULVERT
BAFSA GLOBAL CONC NASARAW AMANTUS
4,422,862.99 GUMEL 7/10/2010 65 ONGOING
31 CONSTR. OF GURI- ZUGO FEEDER ROAD
GANO VENTURES GURI - ZUGO
50,903,350.88 GURI 65 ON-GOING
32 CONSTR. OF DRAINAGE
ALH. ABDU DAM JATAKA
897,028.16 RONI 13/4/2012 30 ON-GOING
33 CONSTR. OF FEEDER ROAD
LAND MGMT NIG LTD
MURDEN KASA- MURDEN DAMA
10,000,000.00 YANKWASHI 18/04/2012 50 ON-GOING
34 CONSTR. OF FEEDER ROAD[ 6KM]
313 DRILLING NIG LTD KUDA- FIRJI
54,967,342.50 YANKWASHI 18/04/12 35 ON-GOING
35 CONSTR. OF FEEDER ROAD [ 1.1KM
Y TEK ENGINEERING
CO MURDE-U/MAGAJI
11,590,582.00 YANKWASHI 21/10/2011 50 ON-GOING
TOTAL
306,802,230.62
cxcii
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
1 Up-grading of water works Limis Brother Guyu
5,253,900.25 AUYO 26/4/2012 100 Completed
2 Replacement of solar panel Limis Brother Unik
1,338,750.00 AUYO 26/4/2012 100 Completed
3
Construction of complete motorize water scheme Tijjani Habu Babura kudu
876,000.00 BABURA 7/3/2012 100 Completed
4
Improvement of water supply at yayarin tukur
water and waste water
Nig LTD yayarin tukur
6,119,897.16 BUJI 15-6-12 100 Completed
5
improvement of water supply at buji town
water and waste water
Nig LTD buji town
10,989,934.31 BUJI 15-6-12 100 Completed
6
Drilling of 10 hand punp across to ten wards
Y tec invt Nig LTD 10 wards
6,981,502.50 BUJI 15-6-12 100 Completed
7
complete motorize water scheme at Gantsa kudu
Y tec invt Nig LTD Gantsa kudu
13,242,939.93 BUJI 15-6-12 100 Completed
8
construction of complete motorized water scheme
Agiwa Nig LTD Kawayo
797,998.42 BUJI 18-7-12 100 Completed
9
construction of class room with head master office
AS Gwagwazo
Nig LTD Jaka
11,923,261.25 BUJI 23-8-12 100 Completed
10 construction of open wells
AS Gwagwazo Gidan hamma
5,700,037.15 BUJI 19-9-12 100 Completed
cxciii
Nig LTD
11 construction of open wells
AS Gwagwazo
Nig LTD Wuro nagge
51,000.00 BUJI 19-9-12 100 Completed
12 construction of open wells
AS Gwagwazo
Nig LTD Gazari
1,137,280.00 BUJI 19-9-12 100 Completed
13 construction of open wells
AS Gwagwazo
Nig LTD Guringa
113,280.00 BUJI 19-9-12 100 Completed
14 construction of open wells
AS Gwagwazo
Nig LTD Jarede
103,920.00 BUJI 19-9-12 100 Completed
15 construction of open wells
AS Gwagwazo
Nig LTD Beingide
209,280.00 BUJI 19-9-12 100 Completed
16 construction of open wells
AS Gwagwazo
Nig LTD Gidan dab
125,280.00 BUJI 19-9-12 100 Completed
17
construction of complete motorized water scheme
water and waste water
Nig LTD Karanjau
1,370,261.00 BUJI 5/9/2012 100 Completed
C/F
66,334,521.97
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
66,334,521.97
18 Construction of hand pump 6No. Direct labour
G/ganji/Asayaya/Saban gari/Tagwaye
1,000,000.00 GARKI 28-12-12 100 Completed
cxciv
19 Purchase of 20kva Generator
Lawan babande Gumba
2,500,000.00 GARKI 5/5/2012 100 Completed
20 Purchase of 27KVAGenerator Alhaji umaru Kore
2,820,000.00 GARKI 2/5/2012 100 Completed
21 Purchase of Hand Pump materials Direct labour Kore
4,500,000.00 GARKI 17-6-2012 100 Completed
22 Supply of hand pump materials Direct labour
Across the 10No Wards
3,000,000.00 GAGARAWA 5/3/2012 100 Completed
23
Purchase of 20KVA water pump Generator
Muhd Dan sakoto Nig
LTD Medu
1,950,000.00 GAGARAWA 20-2-12 100 Completed
24
Purchase of 20KVA water pump Generator
Muhd Yahaya Nig
LTD Gamji
1,950,000.00 GAGARAWA 11/4/2012 100 Completed
25 Purchase 20KVA water Generator
M sunusi ibrahim Nig.
LTD Gagarawa Tasha
2,330,000.00 GAGARAWA 15-8-12 100 Completed
26 Purchase of furniture to staff quarters Direct labour GGW LG Staff Queters
1,500,000.00 GAGARAWA 20-8-12 100 Completed
27 Construction of new hand pump
A lhaji Usman Nig. LTD Bula
800,000.00 GAGARAWA 20-2-12 100 Completed
28 Construction of new hand pump
Isyaku yusif Nig LTD Unguwaar Liman
400,000.00 GAGARAWA 20-8-12 100 Completed
29 Construction of new hand pump
Isyaku yusif Nig LTD Dan madan Fulani
400,000.00 GAGARAWA 6/12/2012 100 Completed
30 Construction of new hand pump
Isyaku yusif Nig LTD Akai Allah
400,000.00 GAGARAWA 6/12/2012 100 Completed
31 Construction of new hand pump
Isyaku yusif Nig LTD Digan Fulani
430,000.00 GAGARAWA 6/12/2012 100 Completed
32 Construction of new hand pump A. Isiya Ltd M/shada
400,000.00 GAGARAWA 9/5/2012 100 Completed
C/F
90,714,521.97
POST CONTRACT
RURAL WATER SUPPLY
cxcv
PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
90,714,521.97
33 Construction of new hand pump A. Isiya Ltd Gagarawa Doni
400,000.00 GAGARAWA 9/5/2012 100 Completed
34 Construction of new hand pump A. Isiya Ltd G/Tu
400,000.00 GAGARAWA 9/5/2012 100 Completed
35 Construction of new hand pump Alhaji Usman G/fulani
430,000.00 GAGARAWA 9/5/2012 100 Completed
36 Construction of new hand pump Alhaji Usman Maihina
1,792,207.00 GAGARAWA 9/5/2012 100 Completed
37 costructiion of motorize borehole Murtala Dake Dantanoma
450,000.00 GUMEL 26-11-12 100 Completed
38 Drilling of borehole
NABO construction
LTD Yola
1,771,355.00 GWIWA 4/5/2011 100 Completed
39 Drilling of 2No Bore Hole
NABO construction
LTD Jammage N Maharba
3,542,670.00 GWIWA 18-4-12 100 Completed
40 over head tank Chediya Venture Daurawar Dan dada
2,160,000.00 GWIWA 24-4-12 100 Completed
41 Drilling of borehole
NABO construction
LTD Indirawa
1,771,335.00 GWIWA 18-4-12 100 Completed
42 Reticulation of water scheme Direct labour Some village
8,376,200.00 GWIWA 6/5/2012 100 Completed
43
Water works General Drilling & purchase of materials Direct labour Five village
17,628,090.00 GWIWA 11/10/2012 100 Completed
44 purchase of Borehole Materials H.O.D. Wash All over the local govt.
3,000,000.00 GWIWA 11/10/2012 100 Completed
45 Purchase of hand pump materials H.O.D. Wash All over the local govt.
500,000.00 GWIWA 10/10/2012 100 Completed
cxcvi
46 Drilling of borehole
NABO construction
LTD Gwiwa MPHC
1,771,335.00 GWIWA 7/5/2012 100 Completed
47 Drilling of borehole
NABO construction
LTD Tanda
1,771,335.00 GWIWA 4/4/2012 100 Completed
48 Purchase of 27KVA Generating set
Haroline and sons Buntusu 2,457,500.00 GWIWA 11/10/2012 100 Completed
49 Purchase of 27KVA Generating set
Haroline and sons Janmaje Maharba 2,457,500.00 GWIWA 11/10/2012 100 Completed
C/F 141,394,048.9
7
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT EXECUTING
LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
141,394,048.9
7
50 purchase of hand pump materials
Alh. Samai'la Maishinkafa Gwaram
2,000,000.00 GWARAM 14-11-12 100 Completed
51 purchase of hand pump materials Direct labour Gwaram
2,500,000.00 GWARAM 10/4/2012 100 Completed
52
Construction of 2no. Of hand pump in Jahun ward
Alhaji abduláziz
gagarawa fulani and dogawa riga
700,000.00 JAHUN 17-2-12 100 Completed
53
Construction of 2no. Of hand pump in Aujara ward
Alhaji Muazu aujara
babancan and marar gara
700,000.00 JAHUN 17-2-12 100 Completed
54
Construction of 2no. Of hand pump in Harbo Sabuwa ward
Litmus Broth LTD asibiti and kanoke
700,000.00 JAHUN 17-2-12 100 Completed
cxcvii
55
Construction of 2no. Of hand pump in Gauza ward
Litmus Broth LTD
makanin yammaci /kagadama gauta
700,000.00 JAHUN 17-2-12 100 Completed
56
Construction of 2no. Of hand pump in Kanwa ward
Litmus Broth LTD
zango kawai and damutawa G/makaho
700,000.00 JAHUN 17-2-12 100 Completed
57 Complete motorize water scheme Direct labour inkaibo
8,834,985.00 K/HAUSA 23-6-10 100 Completed
58 Drilling of Hand pump
yayandi abubakar gambawa
250,000.00 K/HAUSA 30-5-12 100 Completed
59 Drilling of Hand pump bello tela sarawa
250,000.00 K/HAUSA 13-2-12 100 Completed
60 Drilling of Hand pump
yaú malamawa m/tudu
250,000.00 K/HAUSA 16-7-12 100 Completed
61 Drilling of Hand pump alhaji bubu fadawa
250,000.00 K/HAUSA 3/5/2012 100 Completed
62 Drilling of Hand pump Isa masasadi salawa
250,000.00 K/HAUSA 26-1-12 100 Completed
63 Drilling of Hand pump
alhaji yaú malamawa kazayare
250,000.00 K/HAUSA 2/2/2012 100 Completed
64 Drilling of Hand pump new quaters umar musa
250,000.00 K/HAUSA 24-5-12 100 Completed
65 Drilling of Hand pump
alhaji adamu mai biredi maikwalbe
250,000.00 K/HAUSA 24-5-12 100 Completed
66 Drilling of Hand pump isah muhd jabarin fulani
250,000.00 K/HAUSA 2/5/2012 100 Completed
67 Drilling of Hand pump alhaji ismaíl kwarin riga
250,000.00 K/HAUSA 24-5-12 100 Completed
C/F
160,729,033.97
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT EXECUTING COMMENCEMEN STATUS REMARKS
cxcviii
AMOUNT LOCAL GOVT. T DATE IN %
160,729,033.97
68 Cnnecting of100mm motorize borehole alhaji ismaíl distric head balangu
1,036,042.00 K/HAUSA 22-5-12 100 Completed
69 Complete solar water scheme
ADZGlobal services Masama
10,336,196.32
KIRIKASAMMA 14-2-12 100 Completed
70 Complete solar water scheme
ADZGlobal services Gubusun
10,336,196.32
KIRIKASAMMA 14-2-12 100 Completed
71 Construction of a new Hand pump
muhd musa LTD guri juction
200,000.00
KIRIKASAMMA 6/4/2012 100 Completed
72
construction of a motorized water scheme
NGA LOMA Gen ent. Turabu gabas
9,152,543.04
KIRIKASAMMA 14-2-12 100 Completed
73 Construction of a new Hand pump
mai aji marma Nig marrma u/shanu
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
74 Construction of a new Hand pump
Alhaji abdu marma Nig LTD marma islamiyya
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
75 Construction of a new Hand pump
Alhaji Ayuba madachi Nig madachi
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
76 Construction of a new Hand pump
Alhaji Ali Jannailo Nig
LTD gidan babayo
200,000.00 KIRIKASAMM
A 22-2-12 100 Completed
77 Construction of a new Hand pump
Lawawn hassan Babuwa rigar ado katinti
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
78 Construction of a new Hand pump
Adamu Ali Dankabo rigar wakili duwale
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
79 Construction of a new Hand pump Olu sawo Nig rigar gonar dawa
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
80 Construction of a new Hand pump
Dunduma Shugaba busuku makaranta
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
81 Construction of a new Hand pump
Adamu salari Nig LTD Daleri jumaat mosque
200,000.00
KIRIKASAMMA 22-2-12 100 Completed
cxcix
C/F
365,654,030.62
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
B/F
365,654,030.62
82 Construction of a new Hand pump
Abdu Lidalle Nig LTD rubban kamaji
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
83 Construction of a new Hand pump
Alhajji Abdu Izza
rigar yakubu m/galadima
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
84 Construction of a new Hand pump
Adamu Tsauya Nig
LTD matara fulani
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
85 Construction of a new Hand pump
Adamu Ule fandu Nig kaiwari
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
86 Construction of a new Hand pump Musa ziko Nig bakadi
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
87 Construction of a new Hand pump
Miko musa KKM Nig rigar dina
200,000.00 KIRIKASAMMA 22-2-12 100 Completed
88 purchase of hand pump materials
Direct Purchase LG Secratiat
8,500,000.00 KIRIKASAMMA 17-3-12 100 Completed
89 Purchase of Hand pump materials
Direct Purchase LG
3,500,000.00 KIRIKASAMMA 24-12-12 100 Completed
90 Purchase of water Generator Direct Labour Arbus
1,950,000.00 MAIGATARI 16-5-12 100 Completed
91 Purchase of water Generator Direct Labour Jaberi
1,950,000.00 MAIGATARI 25-4-12 100 Completed
92 Construction of Hand pump Direct Labour Jss Maigatari
429,000.00 MAIGATARI 7/3/2012 100 Completed
cc
93 Construction of Hand pump Direct Labour Rigar shadali
429,000.00 MAIGATARI 7/3/2012 100 Completed
94 Construction of Hand pump Direct Labour Rigar zango
429,000.00 MAIGATARI 7/3/2012 100 Completed
95 Construction of jumaat Mosque
Gare Invt. Nig LTD Galadi
29,755,429.22 MAIGATARI 19-3-12 100 Completed
96 Construction of Drainage
Alh. Bashir Nig. LTD Tsangaya
619,000.00 MAIGATARI 7/3/2012 100 Completed
97 Extention of Pipeline Unguwar Gabas
Alh Yahaya naibi unguwar gabas mgt
846,195.00 MAIGATARI 1/6/2012 100 Completed
98 Extention of Pipeline Unguwar Nasarawa
Umar sale monkey unguwar nasarawa
75,000.00 MAIGATARI 5/6/2012 100 Completed
C/F
415,336,654.84
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
415,336,654.84
99 Monthly purchase of hand pump materials Usman mati LG sect.
1,500,000.00 MAIGATARI 10/6/2012 100 Completed
100 Construction of Hand pump
adamu naiyayi wailaba gudu
351,397.00 MIGA 19-4-12 100 Completed
101 Construction of Hand pump alh dogo gidan yaú haske
351,397.00 MIGA 19-4-12 100 Completed
102 Construction of Hand pump
basiru namako jamaga
261,091.00 MIGA 19-4-12 100 Completed
103 Construction of Hand pump garba kaulasa tsagaiwa
261,091.00 MIGA 19-4-12 100 Completed
104 Construction of Hand pump hamisu rabiú mujirga
351,397.00 MIGA 19-4-12 100 Completed
cci
105 Construction of Hand pump sabo romawa kadirawa
351,397.00 MIGA 19-4-12 100 Completed
106 Construction of Hand pump
yakubu maitangara sarawuya makaranta
261,091.00 MIGA 19-4-12 100 Completed
107 Construction of Hand pump
muhd markewa mai ganjara
261,091.00 MIGA 19-4-12 100 Completed
108 Construction of Hand pump
adamu damaganawa limamai gabas
261,091.00 MIGA 19-4-12 100 Completed
109 Construction of Hand pump
dansalla adamu gidan na allah
261,091.00 MIGA 19-4-12 100 Completed
110 Construction of Hand pump Ibrahim yaya juma
351,397.00 MIGA 19-4-12 100 Completed
111 Construction of Hand pump
haruna danmaliki duja
351,397.00 MIGA 19-4-12 100 Completed
112 Construction of Hand pump tsoho ganuwa walawa
351,397.00 MIGA 19-4-12 100 Completed
113 Construction of Hand pump umar haruna ganuwa
351,397.00 MIGA 19-4-12 100 Completed
114 Construction of Hand pump
isyaku dan yaya g/girja
351,397.00 MIGA 19-4-12 100 Completed
115 Construction of Hand pump idris garba maseri
351,397.00 MIGA 19-4-12 100 Completed
116 Construction of Hand pump adamu AMD garbo
351,397.00 MIGA 19-4-12 100 Completed
117 Construction of Hand pump Usman jibrin sabuwar jigawa
351,397.00 MIGA 19-4-12 100 Completed
118 Construction of Hand pump wakili sabo gidan sarkin hawa
351,397.00 MIGA 19-4-12 100 Completed
C/F
422,971,361.84
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
ccii
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
422,971,361.84
119 Construction of Hand pump yakubu muhd jiganda fulani
351,397.00 MIGA 19-4-12 100 Completed
120 Motorized water scheme
loyalty property yanduna
12,402,467.80 MIGA 30-5-12 100 Completed
121 Water Extention shuaibu sansani mudiga
2,559,320.00 MIGA 30-5-12 100 Completed
122 Water Extention abdullahi
abbas tsakuwawa
2,242,960.00 MIGA 30-5-12 100 Completed
123 Purchase of Hand pump materials
Direct purchase Various location
2,500,000.00 YANKWASHI 21-10-12 100 Completed
124 Construction of Hand pump
Abdullahi Naola Godawa
328,630.00 KIYAWA 27-1-12 100 Completed
125 Construction of Hand pump Ismaíl Ahmad Fanteka
328,630.00 KIYAWA 14-12-12 100 Completed
126 Construction of Hand pump Ismaíl Ahmad Jamaár isah
328,630.00 KIYAWA 17-2-12 100 Completed
127 Construction of Hand pump Isah Liman D. Yashi
328,630.00 KIYAWA 22-3-12 100 Completed
128 Construction of Open well
Alh. Ibrahim jet
Gidan Bature
280,462.50 KIYAWA 13-3-12 100 Completed
129 Construction of Hand pump Hamisu Yaú N Chediya
226,800.00 KIYAWA 14-3-12 100 Completed
130 Construction of Hand pump
Tijjani Galadima Galamawa
328,630.00 KIYAWA 13-4-12 100 Completed
131 Construction of Hand pump Bako ahmad Malamawa
328,630.00 KIYAWA 11/4/2012 100 Completed
132 Construction of Hand pump
Ismaíl Ahmad J. Isah Gabas
328,630.00 KIYAWA 22-4-12 100 Completed
133 Construction of Open well
Alh. Danjuma Idris Gerawa fulani
183,000.00 KIYAWA 22-4-12 100 Completed
133 Construction of Hand pump
Alh. Danjuma Idris Dugu
281,062.00 KIYAWA 22-4-12 100 Completed
cciii
134 Construction of Hand pump
Alh. Sabo Kwara Ganyo
328,630.00 KIYAWA 2/5/2012 100 Completed
135 Construction of Hand pump
Ibrahim masaya Auyakawa
328,630.00 KIYAWA 17-5-12 100 Completed
136 Construction of Hand pump
Ibrahim masaya Zawaya
328,630.00 KIYAWA 17-5-12 100 Completed
137 Construction of Open well lawan salisu Alalau fulani
290,640.00 KIYAWA 16-5-12 100 Completed
138 Construction of Open well Mutari Gani Lajiko
280,462.00 KIYAWA 18-5-12 100 Completed
139 Construction of Open well
Zailani kwanda karangiya
280,462.50 KIYAWA 14-6-12 100 Completed
140 Construction of Open well
Haruna balago Alagarno
292,625.00 KIYAWA 14-6-12 100 Completed
141 Construction of Hand pump yunusa datti Tsangayawa
328,630.00 KIYAWA 26-6-12 100 Completed
142 Construction of Open well umar karaga Abarawa
280,462.00 KIYAWA 27-6-12 100 Completed
143 Extention of retaculation Network dahiru dangoli Dangoli
358,370.00 KIYAWA 2/8/2012 100 Completed
C/F
449,396,782.64
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
449,396,782.64
144 Construction of Hand pump lawan salisu masaya
328,630.00 KIYAWA 2/8/2012 100 Completed
145 Construction of Hand pump lawan salisu Chiwina
328,630.00 KIYAWA 2/8/2012 100 Completed
cciv
146 Construction of Hand pump
Abdullahi naula Kulluru
635,524.00 KIYAWA 3/8/2012 100 Completed
147 Construction of Hand pump Garba Mohd K. Shidi
328,630.00 KIYAWA 8/8/2012 100 Completed
148 Construction of Open well Abdullahi G Bajidawa
280,462.00 KIYAWA 25-8-12 100 Completed
149 Construction of Open well M. Tasiú sha Shadaka
280,462.00 KIYAWA 5/9/2012 100 Completed
150 Construction of Hand pump
Bashari Adamu G. Tilo
328,630.00 KIYAWA 25-9-12 100 Completed
151 Construction of Open well Baba Zabi Bazabi
290,640.00 KIYAWA 16-5-12 100 Completed
152 Construction of Hand pump lawan salisu Malajele
328,630.00 KIYAWA 18-5-12 100 Completed
153 Construction of Motorised bolr hole sabo Mulki Dogaji
7,975,769.03 RINGIM 17/1/12 100 Completed
154 Complete motorised water scheme
SHAMAKI UMAR KALGIRAII
11,212,584.10 AUYO 8/10/2012 70 ONGOING
155 Complete motorised water scheme
LIMIS BROTHERS MURAN
8,727,066.16 AUYO 15- 11 12 70 ON-GOING
156 CONSTR. OF BORE HOLE
MAHALLI NIG LTD DUTSE GRAVEYARD
563,840.00 DUTSE 20/4/2012 20 ONGOING
157 CONSTR. OF BORE HOLE GANDUN FAWA
551,656.00 DUTSE 20/2/2012 20 ONGOING
158 COMPLET WATER SCHEME
ALKALI SAKWAYA GAKIKWA
7,264,270.00 DUTSE 23/10/2012 85 ONGOING
159 REPAIRS OF SOLAR BOREHOLE
PRESTEGE LTD DARAU
284,287.50 DUTSE 14/2/2012 25 ONGOING
160 REPAIRS OF SOLAR BOREHOLE
PRESTEGE LTD WURMA
284,287.50 DUTSE 14/2/2012 20 ONGOING
161 REPAIRS OF SOLAR BOREHOLE
PRESTEGE LTD GALAMAWA
284,287.50 DUTSE 14/2/2012 40 ONGOING
C/F
489,675,068.43
ccv
POST CONTRACT PROJECT
EVALUATION
RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
489,675,068.43
162
CONSTR. OF SOLAR WATER SCHEME
NGLOMA NIG LTD GIRYO
7,429,821.52 GURI 7/4/1905 60 ON-GOING
163 CONSTR. OF OPEN WELL
ABBA DAGAWA FULANI GOUWA
180,000.00 JAHUN 3/7/2012 30 ON-GOING
164 CONSTR. OF OPEN WELL
BABANNAN ADE KWARIN KYARO
180,000.00 JAHUN 24/2/2012 30 ON-GOING
165 CONSTR. OF OPEN WELL
BABANNAN ADE HABUJA
180,000.00 JAHUN 10/10/2012 30 ON-GOING
166 CONSTR. OF OPEN WELL
M. ABDU M/GORO ZULKI
180,000.00 JAHUN 10/10/2012 30 ON-GOING
167 CONSTR. OF OPEN WELL
M. ABDU M/GORO TAKKAWA
180,000.00 JAHUN 10/10/2012 30 ON-GOING
168 CONSTR. OF OPEN WELL ALIYU AUTA JABAINA FULANI
180,000.00 JAHUN 2/3/2012 30 ON-GOING
169 CONSTR. OF OPEN WELL YA U MOHD ISADE FULANI
180,000.00 JAHUN 14/3/2012 30 ON-GOING
170 CONSTR. OF OPEN WELL RUFAI MOHD G/MALAMAI
180,000.00 JAHUN 14/3/2012 30 ON-GOING
171 CONSTR. OF OPEN WELL
MALLAM MATO WAYAKA WOKA
180,000.00 JAHUN 14/3/2012 30 ON-GOING
172 CONSTR. OF OPEN WELL
ABDULLAHI MOHD JARUMAWA FULANI
180,000.00 JAHUN 14/3/2012 30 ON-GOING
173 CONSTR. OF OPEN WELL
A MUSA IDRIS GAMA GANGAWA
180,000.00 JAHUN 4/4/2012 30 ON-GOING
ccvi
174 CONSTR. OF OPEN WELL MOD ALI KABAKA FULANI
180,000.00 JAHUN 4/4/2012 30 ON-GOING
175
COMPLETE MOTORISED WATER SCHEME
DIRECT LABOUR
AGURAN MAZANA 8,318,479.00 K/HAUSA 23/6/2010 50 ON-GOING
176 CONSTR. OF JUMAAT MOSQUE
DIRECT LABOUR
TAMBALE 2,000,000.00 K/HAUSA 10/8/2011 80 ON-GOING
177 REACTIVATION OF SOLAR BOREHOLE
LAWAL BUSURI
G/SARKI 1,504,117.00 K/HAUSA 24/4/2012 ON-GOING
C/F
511,087,485.95
POST CONTRACT PROJECT
EVALUATION RURAL WATER SUPPLY
S/N PROJECT EXECUTOR LOCATION CONTRACT
AMOUNT
EXECUTING LOCAL GOVT.
COMMENCEMENT DATE
STATUS IN %
REMARKS
511,087,485.95
178 CONSTR. OF HAND PUMP AMINU TAKO K/ABAKURA
350,000.00 TAURA 25/11/2012 60 ON-GOING
179 CONSTR. OF HAND PUMP AMINU TAKO BULAR AREWA
350,000.00 TAURA 27/11/2012 60 ON-GOING
180 CONSTR. OF HAND PUMP AMINU TAKO GUJUNGU
350,000.00 TAURA 27/11/2012 60 ON-GOING
181 CONSTR. OF HAND PUMP AMINU TAKO BULAR KUDU
350,000.00 TAURA 27/11/2012 60 ON-GOING
182 CONSTR. OF HAND PUMP
A ABBAS MOHD BITIRINAWA
350,000.00 TAURA 27/11/2012 60 ON-GOING
183 CONSTR.OF HAND PUMP
A ABBAS MOHD R/ ADAKATA
350,000.00 TAURA 27/11/2012 60 ON-GOING
184 CONSTR. OF HAND A ABBAS S/GARI YAYA TAURA 27/11/2012 60 ON-GOING
ccvii
PUMP MOHD 350,000.00
185 CONSTR OF HAND PUMP
A ABBAS MOHD JSS AKASAN
350,000.00 TAURA 27/11/2012 30 ON-GOING
186 CONSTR. OF HAND PUMP
A ABBAS MOHD WALAWA
350,000.00 TAURA 27/11/2012 30 ON-GOING
187 CONSTR. OF HAND PUMP
A ABBAS MOHD FAGEN TSAM
350,000.00 TAURA 27/11/2012 30 ON-GOING
188 CONSTR. OF HAND PUMP A GAMBO K RIGAR GAJRE
350,000.00 TAURA 27/11/2012 30 ON-GOING
189 CONSTR. OF HAND PUMP A GAMBO K R/BABAYO
350,000.00 TAURA 27/11/2012 30 ON-GOING
190 CONSTR. OF HAND PUMP A GAMBO K GAMBAYI
350,000.00 TAURA 27/11/2012 30 ON-GOING
191 CONSTR. OF HAND PUMP A GAMBO K AKWAS FULANI
350,000.00 TAURA 27/11/2012 30 ON-GOING
192 CONSTR. OF HAND PUMP A GAMBO K DOMAWA
350,000.00 TAURA 27/11/2012 30 ON-GOING
193
COSTR. OF MOTORISED WATER SCHEME
ALH GARZALI
YAU UNGUWAR KAYA
14,289,966.60 RONI 12/6/2012 30 ON-GOING
194 DRILLING OF HAND PUMP
H TADE DRILLING NIG LTD
16NO VARIOS LOCATIONS
13,000,000.00 YANKWASHI 15/10/2012 40 ON-GOING
195 COMP. SOLAR WATER SCHEME
313 DRILLING N. LTD DANFUSAN
5,222,810.00 KIYAWA 10/11/2012 41 ON-GOING
196
PURCH. OF 18KVA GEN & DRII OF BORE HOLE
MURTALA KATA'I GANGULI
3,637,475.00 KAZAURE 27/7/2012 90 ON-GOING
TOTAL
552,487,737.55