Jewel Avenue & 164th StreetTraffic Calming for Complete Streets
June 25, 2007Presentation to CB 8 Transportation Committee, Queens
Division of Street Management & SafetyTraffic Operations Bureau
![Page 2: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/2.jpg)
2
Why are we here?• 140+ signature petition from school
community• Letter from Assemblywoman Mayersohn• PlaNYC 2030 initiative to add 200 miles of
new bicycle lanes by 2009• Community input to improve designs
![Page 3: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/3.jpg)
3
Timeline
• 11/06: A/M Mayersohn contacts DOT with parents’ petition requesting safety improvements in front of PS 200
• 12/06: Initial DOT response to A/M Mayersohn; DOT study of location begun
• 12/15/06: Fatal crash• 12/06: Input received from DOE• 4/07: Design finalized; initial signal
improvements made
![Page 4: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/4.jpg)
4
Project Area
Long Island Expressway
Long Island Expressway
Jewel Avenue
Jewel Avenue
164th
Street164
thStreet
Grand Central ParkwayGrand Central Parkway
![Page 5: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/5.jpg)
5
Jewel-164th Intersection
PS 200 Site of fatality
![Page 6: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/6.jpg)
6
Major Issues
• Speeding– Jewel Ave– 164th St
Jewel Ave (looking west)
![Page 7: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/7.jpg)
7
Major Issues
• Turning conflicts at 164th St/Jewel Ave– Poor alignment
JEWEL AVE
164T
HST
![Page 8: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/8.jpg)
8
Major Issues
• Turning conflicts at 164th St/Jewel Ave– Poor alignment– Multiple
conflict points JEWEL AVE
164T
HST
![Page 9: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/9.jpg)
9
Major Issues
• Turning conflicts at 164th St/Jewel Ave– Poor alignment– Multiple
conflict points– Left turns
• Multiple focuspoints forturning vehicles
• Wide arc3) ID’ing gap in right lane
3) ID’ing gap in right lane 4) ID’ing pedestrians
in crosswalk4) ID’ing pedestrians
in crosswalk
JEWEL AVE
164T
HST
2) Identifying gap in left lane
2) Identifying gap in left lane
1) Vehicles approaching from behind
1) Vehicles approaching from behind
![Page 10: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/10.jpg)
10
Major Issues
• Pedestrian Crossing Times– Long distances– Turning vehicles
South crosswalk (looking west)
![Page 11: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/11.jpg)
11
Crash History
Non-Ped Crashes
Pedestrian Injuries
0
2
4
6
8
10
12
14
1998 1999 2000 2001 2002 2003 2004 2005 2006
Num
ber o
f Cra
shes
• 82 crashes from 1998-2006• 8 included pedestrian injury or fatality
![Page 12: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/12.jpg)
12
Goal: Safe Streets for All Users
• First Priority: Safety• Other Objectives:
– Improved connections between schools, parks & greenways
– Road Diet: Manage excess roadway capacity• Reduce high speeds• Organize vehicle movements
– Provide quality bicycle routes
![Page 13: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/13.jpg)
13
Project Highlights
• Safety Improvements at Jewel Ave/164th
St Intersection– One-way conversion of Jewel Ave– Increased pedestrian crossing times– Improved school crossing signage
• “Road Diet” on Jewel Ave– 4 2 lanes– Striping to widen median
• Bicycle Lanes on Jewel Ave & 164th St
![Page 14: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/14.jpg)
14
Traffic Calm 164th St
• Bike lanes added; no lane removal
Existing Proposed
Bike lanes added
![Page 15: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/15.jpg)
15
Traffic Calm Jewel Ave
New Marking Plan• Auto lane removed in each direction• Buffered
bike lanesadded
• Medianwidenedw/ markings
Existing
Proposed Bike lanes added
![Page 16: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/16.jpg)
16
Traffic Calm Jewel Ave
• Jewel Avenue has excess capacity:– Jewel Ave: 9,100 vehicles per day (vpd)
• 2 lanes per direction
– 164th St: 16,300 vpd• 2 lanes and left turn bays per direction
• Thru Lane Removal – 1 Lane: lead vehicle sets pace– Past successes
• e.g. – Shorefront Parkway
![Page 17: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/17.jpg)
17
Jewel Avenue Traffic Volumes
0
200
400
600
5-6a
7-8a
9-10
a
11-1
2a
1-2p
3-4p
5-6p
7-8p
9-10
p
11-1
2p
Veh
Per H
our
Traffic Calm Jewel Ave
Eastbound
Westbound
• One lane of traffic can accommodate >500 Vehicles
AMPeak468
PMPeak443
![Page 18: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/18.jpg)
18
Traffic Calm Jewel Ave
• Roadway width unchanged• MTA buses accommodated
Stopped vehicles can be passed
MTA bus stop
![Page 19: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/19.jpg)
19
New Bike Lanes
• Create a Queens network:
Connection toKissena Park
Greenway
Connection to73rd Avenue
bike lane
Queens College
St. John’s
University
Futureconnection toJamaica hub
Connection toexisting Jewel Ave
bike lane Flushing Meadow
Corona Park
![Page 20: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/20.jpg)
20
Bike Lanes
• Jewel Avenue
Oriental Boulevard, BrooklynJewel Avenue (Existing)
![Page 21: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/21.jpg)
21
Bike Lanes
• 164th Street
Cross Bay Boulevard164th Street (Existing)
![Page 22: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/22.jpg)
22
Jewel Ave One-way Conversion
• Turning conflicts eliminated
JEWEL AVE
164T
HST
BEFORE
![Page 23: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/23.jpg)
23AFTER
Jewel Ave One-way Conversion
• Turning conflicts eliminated
JEWEL AVE
164T
HST
![Page 24: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/24.jpg)
24
Jewel Ave One-way Conversion
• Between 164th and 168th St– Low vehicle volumes (300 WB in peak hour)– Narrow road (30’)– No Standing Anytime regulations
• Parking could be added if made one-way
30’ street width 40’
No Standing Anytime(both sides) BEFORE
![Page 25: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/25.jpg)
25AFTER
Jewel Ave One-way Conversion
• Between 164th and 168th St– Low vehicle volumes (300 WB in peak hour)– Narrow road (30’)– No Standing Anytime regulations
• Parking could be added if made one-way
30’ street width 40’
Add parking(both sides)
![Page 26: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/26.jpg)
26
Jewel Ave One-way Conversion
![Page 27: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/27.jpg)
27
Increased Pedestrian Crossing Time
• Pedestrian crossing times increased at Jewel Ave/164th St intersection
• Implemented in April
40 sec27 sec164th St
50 sec33 secJewel AveAfterBeforeCrossing:
![Page 28: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/28.jpg)
28
Summary
• Pedestrians –– Substantially safer with slower vehicle speeds,
reduced conflicts with vehicles, and longer crossing times
• Motorists –– Safer operations with minimal impact– Potential for added parking
• Cyclists –– Improved experience– New connections to schools and parks
Project Goal: A Safer and More Comfortable Jewel Ave & 164th St for ALL Street Users
Next Steps: Refine Plans Based on Community Input
![Page 29: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/29.jpg)
29
P.S. 200 – Jewel/164th
Summary of Safety Improvements1. Signalization –
– Additional crossing time to cross both streets
2. Jewel Ave – Main St to 164th St– Lane removal with buffered bike lane and median widening
3. Jewel Ave – 164th St to 168th St– Conversion to one-way westbound
4. 164th St – Oak Ave to 84th Rd– Bicycle lane
5. School Signs & Regulations– Signage restoration– Monitoring curb regulations
![Page 30: Jewel Avenue & 164 Street2. Jewel Ave – Main St to 164th St – Lane removal with buffered bike lane and median widening 3. Jewel Ave – 164 thSt to 168 St – Conversion to one-way](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f448aa7a58608c268d066/html5/thumbnails/30.jpg)
30
End of Presentation