Jawaharlal Nehru National Solar Mission
-
Upload
nolan-wallace -
Category
Documents
-
view
34 -
download
3
description
Transcript of Jawaharlal Nehru National Solar Mission
Jawaharlal NehruNational Solar Mission
Ministry of New and Renewable Energy8 July, 2011
Present Status & Guidelines for Selection on New Solar Power projects
2
JNNSM Road Map
Application segment Target for Phase I
(2010-13)
Cumulative Target for
Phase 2 (2013-17)
Cumulative Target for
Phase 3 (2017-22)
Grid solar power incl. roof top
1,000 MW100 MW
4,000 MW 20,000 MW
Off-grid solar applications (incl. rural solar lights)
200 MW
2 million
1,000 MW
10 million
2,000 MW
20 million
Solar collectors 7 million sq
meters
15 million sq
meters
20 million sq meters
3
Present StatusApplication segment Target for
Phase I (2010-13)
StatusMarch, 2011
TargetMarch, 2012
Grid solar power incl. roof top & distributed small grid connected plants
1,000 MW
100 MW
704 MW allotted
98 MW allotted
Remaining capacity by December, 2011
Off-grid solar applications
200 MW
40.6 MW sanctioned
Total 100 MW sanctioned by March, 2012
Solar collectors 7 million sq meters
4.5 million sq meters
5.7 million sq meters total by March, 2012
Policy and Regulatory Framework
Tariff for purchase of Solar Power by Regulators
Bundling solar with unallocated thermal power through Central Agency – NTPC Vidyut Vyapar Nigam (NVVN)
Competitive Bidding to select utility scale power projects
Solar specific RPO announced by most of the States
Scheme on RE Certificate announced
Payment Security Mechanism
Customs & Excise Duty concessions on grid solar power projects
5
Grid Solar Power
Present Status/Likely Commissioning
75 projects reported arrangement of funds (120 projects) by mid June, 2011
Most of the other projects expect financial closure by end June/early July 2011
Plant commissioning started in June, 2011.
- 3 plants of MW capacity each commissioned in June,2011
250 MW PV projects expected to be commissioned during September – December, 2011
Technology Choice in Grid PV Power Projects: Phase-I
Technology Choice Grid Solar Thermal Power: Phase-I
8
Guidelines for Selection of Grid Solar PV Power Projects
25th July, 2010
9
Grid Solar Power (1)
1,000 MW Capacity allocation between SPV and Solar Thermal to be 50:50
84 MW capacity projects (54 PV & 30 Thermal) allocated under Migration to be taken into account
Selection of PV projects to be done in two batches.
- First Batch in 2010 and limited to 150 MWp.
- Second batch next year of approx 300 MWp
Solar Thermal : selection for 470 MW done in 2010.
-
Maximum and Minimum capacity &Commissioning period
For SPV- 5 MWp as both maximum and minimum capacity to be commissioned in 12 months from PPA
For Solar Thermal- 5 MW as minimum and 100 MW as maximum capacity to be commissioned in 28 months from PPA
Applications per company
In order to have wider participation only one application per Company including its Parent, Affiliate or Ultimate Parent-or any Group Company shall be permitted for development of one project.
In solar thermal, the company could however propose to set up the capacity at 2 or more sites but within the same permitted application and maximum size
Criteria for short listing
Issuance of Request for Selection (RFS) by NVVN for a period of 30 days.
First – Net worth requirement of Rs 3 cr/ MW for project capacity up to 20MW & Rs. 2 cr/MW for every additional MW beyond this.
Second – Technical requirements. International standards in PV. In Solar Thermal,
defined as minimum levels of experience for technology provider/ EPC contractor
Criteria …. Third - Connectivity to the Grid.
Interconnection with the State Transmission Utility (STU) substation at the voltage level of 33 kV or above.
Project Developer to submit a letter, along with the RFS, from the STU confirming technical feasibility for connectivity at the indicated location.
Criteria…. Fourth - Domestic Content
Promotion of Domestic manufacturing is important objective of the NSM.
For SPV Projects selected in first batch during FY 2010-
11, mandatory for Projects based on crystalline silicon technology to use the modules manufactured in India
Projects selected in second batch, mandatory to use cells and modules manufactured in India
For Solar thermal projects – 30% of project cost to be met with domestic components, excluding the land cost.
Short listing and Selection
If 150 MWp in SPV and 470 MW in Solar thermal or less, get short listed, then Letter of Intent to all developers to invite them for signing PPA with NVVN.
In the event, the total aggregate capacity is more final selection of the Projects shall be done on the basis of discount to be offered by Project Developers on CERC Approved Applicable Tariff .
Short listing…..
The Projects offering the maximum discount in Rs/kWh on the CERC Approved Applicable Tariff would be selected first and so on.
In order to discourage adventurous bids, Bid Bond on graded scale would need to be furnished along with the RfP bid. With increase in discount, bid bond will go on increasing.
Ensuring Performance
Bank guarantee at time of RFS. Increasing bid bond amount as discount
increases. Forfeiture of Bank guarantees and bid bond if
PPA not done by developer Forfeiture of Bank guarantees, if Financial
closure not done within 180 days Forfeiture of guarantees if delay in
commissioning Monitoring equipment, compliance standards
Suggestions Invited by 30 June 2011
What should be maximum capacity of a PV Power Plant at any location
What should be maximum capacity to be set up by a company or a Group
Is there any need to modify or issue clarifications about any specific clause/condition of the guidelines
Suggestions
More than 50 suggestions have been received from various stakeholders including FICCI, CII, ADB, Government of USA, project developers, manufacturers, EPC companies and consultants etc.
Summary of Suggestions
Plant Capacity Majority of suggestions are for Higher
capacity to be allowed (10 – 100 MWp) to encourage economies of scale, bankability, best in class EPC and technology and vendor development
Maximum Capacity per Company/Group 10 - 150 MWp per Company/Group may be
allowed
Summary of Other Suggestions
Pre-qualification criterion- Introduce technical criterion relating to
previous experience of the company in RE/Power projects or firm EPC tie-up at the time of application
- EPC contractor should have done plants of MW size any where in the world
- Enhance net worth requirement- Provide evidence for equity arrangement
Summary of Other Suggestions
Grid Connectivity- Clarify the responsibility of SPD and STU
on meeting the cost- NVVN may meet the cost of grid
extension beyond the plant- State may be asked to meet the cost of
grid extension Land- Facilitate early/timely availability of land
Summary of Other Suggestions
Financial Closure- Extend time from 180 days to 240 days- Clarify about internal funding
arrangements as equivalent of FC- Do not insist on draw down- Do not insist on FC
Summary of Other Suggestions
Bid Bond & Penalties- Reduce bid bond amount- Penalties harsh, give additional time for
project completion- Do not cancel project if FC not achieved
in 180 days- Do not give lower tariff if project is
delayed beyond 3 months
Summary of Other Suggestions
Domestic Content- Continue with Domestic content; cells &
modules should be made in India- Consider enhancing % of domestic content like
Italy - Clarify about sourcing of thin film modules as
they do not use cells- Allow innovation and latest technologies to
come; review domestic content- Do not insist on Domestic content
Summary of Other Suggestions
Others
- Allow time from 15 months ( 5-15 MW) to 21 -24 months (>15 MW) for project completion
- Allow 60 days for submission of RfS- PV capacity should be inspected at DC side;
difficult to demonstrate at AC side- Do not insist on RFID
Thank Youhttp:\\mnre.gov.in