Applying Lean Construction with CCPM
in Real Estate Development projects
Nerius Jasinavicius, TOC sprendimai, LithuaniaAugustinas Voldemaras, Lean Construction Institute Lithuania27 April 2014
12th International Conference of the
TOC Practitioners Alliance TOCPAwww.tocpractice.com April 26-27, 2014 Moscow, Russia
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
What is construction ?
Delays;
Low productivity;
High prices and increasing;
Chaotic project meetings on sites;
Big staff turnover;
Waves of activities;
Nobody keeps promises;
Clients look for the ways not to pay;
Very low cooperation between client, architects and
contractors
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
What is Lean Construction ?
Lean construction is a way to design production
systems to minimize waste of materials, time, and
effort in order to generate the maximum possible
amount of value, (wikipedia)
Value is "What the Customer is actually paying for the
project to produce and install.
Major Lean Construction developments relate to the
planning, execution, and control paradigms
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Lean construction offers two important goals
towards which to strive in the implementation
of each project:
1) maximizing the value created in the project;
2) reduction of all kinds of losses.
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
LEAN construction
Improvement circle
Goals
Initial draft
Project concept
Planning process
Product details
Detailed planning
Production, procurement
Construction
Ready for use
Maintenance
Repare and demolition
Idea Project Supply CAW Using
Control
Work planning
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Last Planner
Lean Constructions main tool for making design
and construction processes more predictable
is the Last Planner System and derivatives of
it.
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Last Planner
The collaborative, commitment-based planning
system that integrates should-can-will-did
planning (pull planning, make-ready, look-
ahead planning) with constraint analysis,
weekly work planning based upon reliable
promises, and learning based upon analysis of
PPC (plan percent complete) and reasons for
variance.
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
The Last Planner
Master Scheduling (setting milestones and strategy;
identification of long lead items);
Phase "Pull" planning (specify handoffs; identify operational
conflicts);
Make Work Ready Planning (look ahead planning to ensure
that work is made ready for installation; re-planning as
necessary);
Weekly Work Planning (commitments to perform work in a
certain manner and a certain sequence); and
Learning (measuring percent of plan complete (PPC), deep
dive into reasons for failure, developing and implementing
lessons learned).
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Planning
Technical project
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
The Last Planner: PERT
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
PERT
visualisation
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
PERT
visualisation
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Start of the project
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Last Planner
Weekly planning
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Project status
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Project progress
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Typical in construction
It is common to think that as long as we are
completing some tasks, we are making the
progress.
But how true is that ?
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Progress analysis
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
The problem: delayed
Critical Chain Task
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Focused efforts to
increase the speed
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Major milestone
ON TIME
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Conclusions
Last Planner concept is very useful in creating
project plan
CCPM helps to focus weekly planning on
proper tasks and ensuring full kit
CCPM helps to focus LEAN improvement
efforts
Old habits die hard
We gained some trust, next step Integrated
Project Team
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Name of the presenter
Construction Engineer
20 year in construction:
- 9 years construction director,
- 3 director of Lithuanian LeanConstruction Institute.
-
12th International Conference of the TOC Practitioners Alliance - TOCPAwww.tocpractice.com
Nerius Jasinavicius
8 TOCPA
Founder of TOC sprendimai
Founding Member of TOCPA
Consultant for unique clients
TOCICO certified SC, TP
Certified Management
Consultant