January 31, 2012. …a delivery method in which the construction team is known as the...

15
January 31, 2012

Transcript of January 31, 2012. …a delivery method in which the construction team is known as the...

Page 1: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

January 31, 2012

Page 2: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

…a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed

by the owner, completing the detailed design, and proceeding into construction.

Page 3: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

DB offers the following:◦ Poses Least amount of Project Risk to Owners ◦ “Quickest” Project Delivery Method

Early Construction concurrent with Design ◦ “Integrated” DB Team develops design with

constructability in mind, which: Reduces Changes / Change Orders to Project Reduces need for Value-Engineering / Re-Bidding Improves quality of Final Design

◦ Can be used on any sized Project◦ Use of Design Assist Contractors during design

Page 4: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Minimizes Owner Control over Process May be Difficult Method to Use on Complex

Projects Building Over-Design may Increase DB

Profits …Did the Owner get the Best Price for the

final Product?

Page 5: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Criteria Architect (C-AE) – Defines Design Intent through Schematic Design, selected through co-selection process by owners

Project Cost Consultant (PCC) - Third Party Entity that advises Owner related to Project Cost while in Design and assists in GMP Negotiation, selected by the co-owners

Design Builder (DB) – Provides input in Design, Negotiates GMP, Bids Project and Oversees Construction◦ Architect of Record, General Contractor◦ Design Assist Contractors – usually MEP

Page 6: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Team consists of Criteria Architect (C-AE) and Design-Builder (DB):

Design Begins (POR) Design Ends (GMP)

Criteria Architect

Design Intent Finalized (SD)

Design Builder:

• Architect of Record• General Contractor

• Design Assist Contractors

Criteria Architect / Owner’s Representative

Page 7: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Design-Builder (DB) bids project and oversees construction, with the C-AE serving in an Owner’s Representative (OR) function:

Construction Begins (GMP)

Construction Ends

Design Builder:

• Architect of Record• General Contractor

• Subcontractors

Criteria Architect / Owner’s Representative

Page 8: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Each District/Project is Unique in Some Fashion◦ Construction Experience ◦ Knowledge of Program◦ Community Involvement◦ Decision Making◦ Scope◦ Complexity◦ Schedule

Page 9: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Owner Familiar with Construction Programs & Processes

Owner Availability of Staff (Moderate Level)◦ Single Decision Maker

Owner Risk Tolerance (Low Level) Owner Level of Control (Low Level)

◦ Original Design vs. Project Changes Level of Changes to Original Scope

◦ Original Schedule vs. Project Changes Level of Changes to Original Schedule

Page 10: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Medium to Large Projects (> $2 million) Simple to Moderate Complexity of Projects

◦ Design & Schedule Aggressive Schedule Expectations

Page 11: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
Page 12: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Establish and Procure Project Funding Determine DB Delivery is best method Co-Selection of C-AE – RFQ Process Co-Selection of PCC – RFQ Process Co-Selection of DB Team – RFQ/BVS process, Includes:

Selection of DB – RFQ/BVS process Two Step Selection Process

Negotiation of GMP Occurs between SD & DD Phase Re-Confirmation of GMP to Design Intent

Bidding Pre-Qualification of Potential Bidders by DB DB bids and awards Contracts, may perform work

Construction & Closeout

Page 13: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Occurs between SD and DD Design Phases Small, Select Group from District & OSFC

◦ Cost Estimate from DB / Design Assist Contractors◦ Cost Verification from Project Cost Consultant

Conduct Facilitated Session for Negotiation Upon GMP Agreement, Design Intent is

revisited

Page 14: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.

Experience◦ Financial condition◦ Performance on previous projects◦ Facilities◦ Management skills◦ Ability to contract properly

Goals◦ EDGE etc.

Affirmation of non-violations past (5) years Proof of licenses to perform work Self-Performance

Page 15: January 31, 2012. …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.