James Watt College Carbon Management Programme€¦ · James Watt College - Carbon Management...
Transcript of James Watt College Carbon Management Programme€¦ · James Watt College - Carbon Management...
James Watt College - Carbon Management Programme Carbon Management Plan working with
James Watt College
Carbon Management Programme
Carbon Management Plan (CMP)
Date: 22-07-2010 Version number: 1 Owner: Health, Safety and Environment Service Approval route: Climate Change Action Plan Group Leadership Team BoM (for info) Approval status: Approved
Page 1
James Watt College - Carbon Management Programme Carbon Management Plan working with
Contents
Foreword from Sue Pinder OBE Principal and Chief Executive 3
Foreword from the Carbon Trust 3
Management Summary 4
1 Introduction 5 1.1 James Watt College 5 1.2 Cirriculum Led Estates Strategy 5
2 Carbon Management Strategy 6 2.1 Context and drivers for Carbon Management 6 2.2 Our low carbon vision 6 2.3 Strategic themes 6 2.4 Targets and objectives 7
3 Emissions Baseline and Projections 7 3.1 Scope 7 3.2 Baseline 7 3.3 Projections and Value at Stake 9
3.4 Targets 9
4 Carbon Management Projects 10 4.1 Existing projects 10 4.2 Planned / funded projects 10 4.3 Opportunities identified by CT 11 4.5 Projected achievement towards target 12
5 Implementation 13 5.1 Financing 13 5.2 Governance for Implementation 15
5.2.1 Embedding Carbon Management 15 5.2.2 Data Management – measuring the difference, measuring the benefit 15
5.3 Resource commitment 15 5.3.1 Implementing the Initiatives 16 5.3.2 Maintaining quality over time 16 5.3.3 Leadership and Management of the CMP 16
5.4 Implementation Plan 16
Appendix A: Definition of Projects 19
Page 2
James Watt College - Carbon Management Programme Carbon Management Plan working with
Foreword from Sue Pinder OBE The environments in which James Watt College operates present us with many challenges and opportunities. As we move forward, the College will pay close attention to the environmental impact of our work related to ongoing operational issues and new developments. We are committed to environmental sustainability and to the reduction of our carbon footprint through our Carbon Management Programme.
We have joined the Carbon Trust Carbon Management Programme to help us quantify our carbon footprint and focus on areas we can improve. The Carbon Management Programme is also significant in helping us towards our commitment to the Universities and Colleges Climate Commitment for Scotland (UCCCfS).
Sue Pinder Principal & Chief Executive
Foreword from the Carbon Trust Cutting carbon emissions as part of the fight against climate change should be a key priority for local authorities - it's all about getting your own house in order and leading by example. The UK government has identified the public sector as key to delivering carbon reduction across the UK inline with its Kyoto commitments and the Public Sector Carbon Management programme is designed in response to this. It assists organisations in saving money on energy and putting it to good use in other areas, whilst making a positive contribution to the environment by lowering their carbon emissions.
James Watt College was selected in 2009, amidst strong competition, to take part in this ambitious programme. James Watt College partnered with the Carbon Trust on this programme in order to realise vast carbon and cost savings. This Carbon Management Plan commits the organisation to a target of reducing CO2 by 25% by 2013-14 and underpins potential financial savings to the organisation of around £1 million.
There are those that can and those that do. Public sector organisations can contribute significantly to reducing CO2 emissions. The Carbon Trust is very proud to support James Watt College in their ongoing implementation of carbon management.
Richard Rugg Head of Public Sector, Carbon Trust
Page 3
James Watt College - Carbon Management Programme Carbon Management Plan working with
Management Summary Climate change is a high profile issue. The Scottish Government has passed the Climate Change (Scotland) Act 2009, which has set targets for the year 2050 of at least 80% lower than the baseline, an interim target for the year 2020 of at least 42% lower than the baseline 2020, and to provide annual targets, for the reduction of greenhouse gas emissions. Within this context the targets set by James Watt College are being developed to ensure that the college plays its part within this important national agenda. Prior to joining the Carbon Trust’s Carbon Management Programme in February 2010 the College had already embarked on some initiatives related to the environment and our impact on its sustainability e.g. recycling and estates development. The Carbon Trust has carried out an Assessment of Energy Saving Opportunities and prepared a report which recommends a number of “Opportunities” that we could put in place to reduce our energy consumption. A number these are included as projects in this plan. The partnership with the Carbon Trust in preparing this Carbon Management Plan compliments the work being done for the Climate Change Action Plan following our signing up to the Universities and Colleges Climate Commitment for Scotland (UCCCfs) James Watt College is a leading Scottish college with more than 800 staff and 20,000 students. As such, we recognise that we have an opportunity and a responsibility to influence a significant number of people to make an individual and collective contribution to saving energy and reducing carbon emissions. James Watt College is committed to reducing our Carbon Footprint over the forthcoming years. This document explains the financial and environmental benefits of the Carbon Management Plan for the College. James Watt College will be raising Environmental Awareness with our staff and students in all disciplines through College initiatives and by providing them with the appropriate tools to understand the consequences for their actions. The Carbon Management Plan focuses on the reduction of our carbon emissions through the performance of the College. The College has identified projects/initiatives that will contribute to reducing our carbon footprint by 25% over a five year period. Our baseline carbon footprint is: Data for baseline year 2008-09 Total CO2
Emission (tonnes)
Buildings Transport Housing Waste Water
Baseline CO2 emissions (tonnes)
3,841
3,188
468
-
172
13
Baseline Cost (£)
£736,638
£451,278
£209,778 -
£12,735
£62,848
Page 4
James Watt College aims to reduce CO2 emissions from our operation by 25% by 2014-15 from 2008-09 levels.
James Watt College - Carbon Management Programme Carbon Management Plan working with
1. Introduction
1.1 James Watt College With over 100 years of learning, James Watt College remains one of Scotland’s most dynamic and progressive Colleges. Whatever your background, your ambitions or your abilities we can offer a range of options to develop your skills, knowledge and understanding - to help you learn for life. Since opening in Greenock in 1908, James Watt College has developed into one of Scotland’s largest colleges with approximately 20,000 students and 800 staff spread across four campuses on the West Coast of Scotland. We offer a diverse range of courses in a variety of subjects including: Beauty & Hairdressing; Business & Computing; Construction & Engineering; Creative Industries; Education, Health, Social Care & Social Sciences. Hospitality, Tourism & Sport; Science and Supported Learning Programmes. With campuses in Kilwinning, Largs and two in Greenock, the College offers a wide range of programmes that allows learners to choose the location that suits them. Our courses tend to be “vocational” or work related, typically including strong practical elements where students gain hands-on experience to take into the workplace, further enhancing job prospects. Our flexibility allows the opportunity to study part-time, full-time, day-release, through open learning, on-line learning or at one of our evening classes. Our learners come from wide ranging and diverse backgrounds; from school leavers to International students to adult returners, we have opportunities for all at James Watt College.
1.2 Curriculum Led Estates Strategy Estates Strategy The Colleges Estates Strategy seeks to follow the Scottish Funding Councils published guidance which seeks to ensure that our Strategy is aligned with, and supports the key business objectives within the College. A recent review of the Estates Strategy (in November 2009) sought to verify the assumptions that had led to the original strategy and to set out the actions required to implement the approved elements of that strategy.
The key elements of the modified Estates Strategy are that the College should:-
1. Acquire land from North Ayrshire Council adjacent to the main Kilwinning Campus in order to build a new vocational centre.
2. Construct 8 new classrooms at the main Kilwinning Campus. 3. Terminate the lease agreement in respect of the rented accommodation at Melvin House. 4. To renounce the lease agreement in respect of the Three Towns Learning Centre. 5. To establish a negotiating group to review the options and work with our lawyers in negotiating
the buyout of the PFI agreement. 6. To undertake an options review in respect of the method and location of delivery of the sports
curriculum currently delivered at Largs. 7. To remodel the workshop block at Finnart Street, thereby allowing the disposal of leased
accommodation at Port Glasgow and Fort Matilda. 8. Retain the Waterfront Campus and increase the area of teaching space.
Page 5
James Watt College - Carbon Management Programme Carbon Management Plan working with
9. To undertake a review of the need for the student accommodation, the issues associated with its management and day to day running costs to establish whether the facility can be operated without burdening the overall College finances.
10. To outline a business case for the re-cladding of the Finnart Tower. 11. To undertake a detailed study of the current and future demand, the commercial viability,
potential funding and if appropriate, identify suitable locations for the provision of new Nursery accommodation to serve our students at Finnart Street.
12. To investigate the possibility of creating new car parking at Finnart and Kilwinning.
2 Carbon Management Strategy
2.1 Context and drivers for Carbon Management James Watt College is committed to sustainability and to reducing its carbon emissions by 25% over a period of 5 years.
Participation in this phase of the Carbon Management Programme is central to James Watt College’s progress towards meeting the above target.
The Carbon Management Plan will allow us to measure our performance and future developments against previously agreed targets.
Measures to reduce energy consumption and improve energy efficiency are particularly important in light of predicted increases in energy cost and reductions in public spending.
2.2 Our low carbon vision The College recognises that Climate Change will have a considerable impact on the Scottish economy, Scotland’s people and environment and is determined to play its part in rising to this challenge. Our objective is to operate our estate in the most environmentally sustainable manner and to ensure that staff and students in all disciplines are aware of the consequences of their actions and can make informed decisions regarding environmental issues.
2.3 Strategic themes James Watt College has joined the Carbon Management Programme to assist us in achieving the reduction of our Carbon Footprint. Our aim is to reduce our carbon emissions with a range of projects and initiatives that will deliver a significant carbon reduction and to embed these into the way the College operates. Our Carbon Management Plan will:
• Reduce our Carbon emissions by 25% from 2008 levels by 2014 -15 • Reduce energy consumption and promote energy efficiency • Encourage waste reduction, recycling and responsible disposal • Promote responsible and active travel through sustainable travel planning • Identify and confirm a range of projects to be incorporated in our Estates strategy
Page 6
James Watt College - Carbon Management Programme Carbon Management Plan working with
2.4 Targets and objectives Estates, ICT and travel are key areas where we want to embed carbon management and where we see significant opportunities for reducing carbon emissions. We also want to ensure that sustainability is embedded in all curriculum areas. James Watt College has joined the Carbon Management Programme to ensure that our Carbon Management Plan reflects the aims and objectives within the public sector and to ensure that we achieve the high standards expected of a teaching organisation. James Watt College’s aim is to develop a range of projects that will deliver significant carbon reductions, contribute cost savings and embed Carbon Management in all College operations. The Carbon Management Programme will help us to:
• Reduce energy consumption and use energy more efficiently • Encourage waste reduction, recycling (50%) and responsible disposal • Reduce business travel by 10% (in the first year) • Identify a range of projects to be incorporated in our Estates strategy • Reduce our carbon emissions by 25% from 2008-09 levels by 2014-15
3 Emissions Baseline and Projections
3.1 Scope Our baseline emissions included carbon emissions from all owned or leased buildings. The baseline includes energy used in buildings, fuel used for business travel and emissions associated with waste disposal. We did not include emissions related to commuting to/from College or from procurement of goods/services by the College.
The James Watt College Carbon Management Plan encompasses:
• Energy use in owned/leased buildings
• Emissions related to business travel (staff and fleet vehicles)
• Waste produced from all College operations
• Water used in buildings and operations
• Influencing appropriate behavioural modification among staff and students
• Embedding sustainability in all curriculum areas
3.2 Carbon Emissions Baseline 2008-09 James Watt College’s baseline Carbon Footprint was based on the 2008-09 academic year (1st August 2008 – 31st July 2009). The main data sources were:
• Invoices and consumption figures from energy providers (Electricity & Gas) • Business travel information (staff expenses forms) from Finance • Fleet fuel consumption / mileage from Estates • Waste disposal details from waste disposal contractors
Page 7
James Watt College - Carbon Management Programme Carbon Management Plan working with
Obtaining energy consumption figures was a manual activity and was more difficult for gas than for electricity. We should work with our energy providers to improve this for the future. Establishing the necessary information for staff business travel involved a very time consuming trawl through expenses forms. Measures have been put in place to make this easier and more accurate for future years. Fleet fuel consumption was estimated and we need to improve this for the future. However, our fleet is small so does not constitute a significant element of our baseline. Information on waste was particularly difficult to obtain and verify due to the various waste disposal organisations and waste streams involved. We don’t have a high level of confidence in the waste figures included in the baseline. This is an aspect for improvement in future years. Total CO2
Emission (tonnes)
Buildings Transport Housing Waste Water
Baseline CO2 emissions (tonnes)
3,841
3,188
468
-
172
13
Baseline Cost (£) £ 736,638
£ 451,278
£ 209,778
£ -
£ 12,735
£ 62,848
Table 1: Summary table of emissions for baseline year 2009
Baseline CO2 emissions (tonnes)
Buildings 84%
Waste 4%
Transport12%
Water 0%
Buildings Transport Waste Water
Graph 1: Summary of emissions for baseline year 2009 From the above graph it can be seen that buildings contribute 84% of our Carbon Footprint. Based on this we will focus our efforts on reducing energy consumption and improving efficiency of energy use
Page 8
James Watt College - Carbon Management Programme Carbon Management Plan working with
across all areas of the College. Projects in these areas will be given priority. This includes ICT projects which will contribute significant reductions in energy use. However, viable projects in transport, waste, water use and behavioural change will be pursued as part of our overall carbon management initiative. We will also work to embed sustainability / carbon management in all curriculum areas.
3.3 Projections and Value at Stake In a Business As Usual (BAU) scenario College carbon emissions are likely to increase due to deterioration of the Estate and associated services. With the economic downturn there could also be an increase in student numbers resulting in a greater demand on College services. As can be seen from the BAU projections (Graph 1) even a modest growth and rise in energy prices will result in a significant cost.
Comparison of emissions with BAU increases and reduction targets - financial
-
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017Year
£
Actual cost BAU cost Target cost
Graph 2: Projected Business As Usual (BAU) compared with Target Costs
3.4 Targets The carbon management plan sets a target of a 25% reduction in carbon emissions against a baseline year of 2008-09. See table below for target annual % CO2 reductions and associated Value at Stake (VAS) targets.
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
BAU (£m) 0.74 0.80 0.87 0.95 1.03 1.12 1.21
Target (£m) 0.80 0.83 0.86 0.90 0.93
Savings (£k) 73 116 165 220 281
Table 2: Financial savings for each year
Page 9
James Watt College - Carbon Management Programme Carbon Management Plan working with
4 Carbon Management Projects This section covers projects which have been implemented (but not quantified in terms of carbon emissions reductions), projects which are planned, funded and have been quantified and projects recommended in the Carbon Trust “Energy Saving Opportunities Assessment” carried out in April 2010. Project in this third category are to be reviewed and verified by our Estates Department (see note at Table …).
4.1 Existing projects • Raising awareness on Carbon Management:
o Climate Change Action Plan Group set up o Poster Campaign launched o “Enviro Ideas” email address set up for employees to submit ideas.
• Recycling introduced at North Ayrshire Campus and Finnart Street Campus reducing waste to landfill
• Energy efficient and sensor controlled lighting installed in refurbished office areas. • Energy efficient hand dryers installed in refurbished toilets to replace less efficient machines
and discontinue use of paper towels • Use of recycled products – All printing paper purchased is from recycled sources
Note! These projects have not been quantified in terms of carbon emissions reductions.
4.2 Planned / funded projects
Cost Annual Saving Ref Project Lead Cap’l Rev’ue Res’ce Fin tCO2 Pay back
% of Target Year
1 ICT Power Mngt John Denny - £12,500 - £7,535 40 1.66 5.7% 2010/11
2
ICT Server Replacement Programme (Virtualisation)
John Denny - £80,000 - £15,824 85 5.06 11.9% 2010/11
3 Office Equipment Rationalisation
John Denny - N/A - £9,042 49 - 6.9% 2010/11
4 Rationalisation of Premises
Peter Thorne - N/A - £7,312 55 - 7.7% 2010/11
5 Marketing Campaign Carrie Gibson - £5,000 - £3,312 26 1.51 3.6% 2010/11
6 Travel Plan Bill McNeice - £3,000 - £5,287 12 - 1.7% 2010/11
7 Increased recycling across all campuses
Nancy Forbes - £4,000 - - 86 - 12.1% 2010/11
Page 10
James Watt College - Carbon Management Programme Carbon Management Plan working with
4.3 “Opportunities” identified by CT (to be verified by JWC)
Cost Annual Saving
Project Lead Cap’l Rev’ue Res’ce Fin CO2 Pay back % of
Target Year
8
NAC: Minimise Energy Consumption During Holiday Period
£ 12,365 - - 9.5% 2010/11
9 Optimise Time Schedules for Building Services Plant
£ 1,728 - - 4.6% 2010/11
10 Increase Temperature Set-points in Server Rooms
£ 1,245 - - 1.0% 2010/11
11 WFC: Programme Boiler Operation
£ 99 - - 0.3% 2010/11
12
Utilise Energy Savings Functions on Personal Computers
£ 900 - - 0.7% 2010/11
13 NAC: Phase-out Tungsten Lamps in Residence Blocks
£ 69 - - 0.1% 2010/11
14 NAC: Do not Maintain High-level Foyer Lighting
£ 153 - - 0.1% 2010/11
15 FSC: Switch off Booth-side Lighting in Food Hall
£ 33 - - 0.0% 2010/11
16 Fit Time Switches to Vending Machines
£ 610 - - 0.5% 2010/11
17
Utilise Half Hourly Data to Eliminate/Reduce Unnecessary Electricity Usage
£ 26,200 - - 20.1% 2010/11
18 FSC: Sequence Boiler Operation
£ 657 - - 1.7% 2010/11
19
NAC: Alter Boiler Control Settings to Allow Low-Fire Operation
£ 110 - - 0.3% 2010/11
20 Insulate Valves £ 582
- - 1.5% 2010/11
21 NAC: Install PIRs on Corridor Lighting
£ 3,225 - - 2.5% 2010/11
22 NAC: Install Day Light Control on Refectory Lighting
£ 230 - - 0.2% 2010/11
23 NAC: Install Tamper-proof Thermostats
£ 2,720 - - 2.1% 2010/11
24 WFC: Install PIRs on Corridor Lighting
£ 1,515 - - 1.2% 2010/11
25 NAC: Install Day Light Control to Entrance Hall Lighting
£ 120 - - 0.1% 2010/11
26 FSC: Begin Gradual Phasing Out of Inefficient T12 Lighting
£ 1,255 - - 1.0% 2010/11
27
WFC: Overhaul of Academic Building Air-Conditioning System
-£ 1,633 -
does not
payback -1.2% 2010/11
Page 11
James Watt College - Carbon Management Programme Carbon Management Plan working with
Note! The above projects are recommendations from the Carbon Trust “Energy Saving Opportunities Assessment” carried out at James Watt College in April 2010. Due to current workload we have not been able to verify the figures provided above. Due to our “Summer Works” programme it will not be possible to carry out the verification before the end of August 2010. As they stand, the projects are included in our plan subject to them being quantified and agreed. This will be completed by December 2010 and our plan will be fully reviewed, up-dated and re-submitted to the Carbon Trust. By December 2010 we also hope to have identified around six additional “Big Ticket” projects which will make a significant contribution to achieving our target of a 25% reduction in carbon emissions.
4.4 Projected achievement towards target The graph below shows how CO2 emissions would increase if we do nothing (BAU). Our target of 25% reduction in carbon emissions over 5 years is shown and the contribution that planned projects, plus as yet unverified projects, will make towards meeting our target can be seen.
Carbon progress against target
-500
1,0001,5002,0002,5003,0003,5004,0004,500
2008 2009 2010 2011 2012 2013
YearPredicted Business as Usual EmissionsTarget EmissionsEmissions in chosen plan
Graph 3: Business as usual emissions compared with target and planned / potential projects
Page 12
James Watt College - Carbon Management Programme Carbon Management Plan working with
5 Implementation By implementing this Carbon Management Plan James Watt College will be making a contribution to national emissions reduction targets.
Direct benefits to the College will be:
• Cost savings resulting from reduced energy consumption
• Meeting our pledge to the Universities & Colleges Climate Commitment for Scotland
• Enhancing the College’s environmental reputation
5.1 Financing In this section we concentrate solely on the benefits to the institution in completion a Carbon Management Plan. The benefits to the institution can be summarised as a significant reduction in costs allied to an improvement in the college’s ‘green’ credentials and the production of a template which will assist in meeting the Universities and Colleges Climate Commitment for Scotland.
5.1.1 Financial costs and sources of funding In the first year a budget of £50,000 has been allocated to the programme, in order to fund any capital purchases. These funds will be used for projects which are considered viable and have not been included in 2010/11 budget submissions. The day to day maintenance of carbon management should be absorbed within the normal departmental budgets e.g. introducing energy efficient light bulbs. Any projects which have initially been implemented should then be sustainable in future year’s budgets. The department budgets that are going to be used to fund 2010/11 revenue expenditure are as follows:
• ICT
• Estates
• Marketing
• Health & Safety
In subsequent years any substantial projects that require additional funding will be funded through savings achieved from initial projects, These types of projects are likely to be more expensive and have longer pay back periods. In order for the real savings to be reinvested in the programme all projects will be monitored through the Climate Change Action Group. The table below illustrates that as savings accumulate the year-on-year savings should continue to cover the cost of the programme
Page 13
James Watt College - Carbon Management Programme Carbon Management Plan working with
Per Baseline 2008 2009 2010 2011 2012 2013 2014 2015
BAU cost in £ 736,638 800,681 870,302 945,987 1,028,267 1,117,715 1,214,960 1,320,679
RES cost in £ 736,638 766,364 797,289 829,463 862,934 897,757 933,984 971,674
Targeted Savings, PA in £
0 34,317 73,013 116,524 165,233 219,958 280,976 349,005
Cumulative Savings in £
0 34,317 107,330 223,854 389,087 609,045 890,021 1,239,026
Based on Confirmed Projects
BAU cost in £ 736,638 800,681 870,302 945,987 1,028,267 1,117,715 1,214,960 1,320,679
RES cost in £ 736,638 800,681 755,698 786,193 817,919 850,926 885,263 920,986
Targeted Savings, PA in £
0 0 114,604 159,794 210,348 266,789 329,697 399,693
Cumulative Savings in £
0 0 114,604 274,398 484,746 751,535 1,081,232 1,480,925
* Business as usual
** Reduced Emissions Scenario
Page 14
James Watt College - Carbon Management Programme Carbon Management Plan working with
5.2 Governance for Implementation
5.2.1 Embedding Carbon Management Our Principal has signed up to the Universities and Colleges Climate Commitment for Scotland (UCCCfS) and is fully supportive of this Carbon Management Plan (CMP). The Climate Change Action Plan group is charged with delivering the CMP. The group is made up of the following:
• Project Sponsor: Margaret Tierney (Assistant Principal – Organisational Development) • Project Leader: Bill McNeice (HS&E Manager) • Finance Champion: Fiona McEwan (Finance Manager) • ICT Champion : John Denny (ICT and e-Learning Manager) • Estates Champion: Peter Thorne (Estates Manager) • Learning Champion: Iain MacKay (Learning Manager – Engineering & Construction) • Procurement Champion: Brian Bradley (Procurement Officer) • Student Champion: Geraldine Shambach (Student President) • Administration: Caroline Rennie (HS&E Admin Assistant)
During the Carbon Management Programme the group met on a monthly basis. It is intended that the group will continue to meet regularly to review and keep the CMP on track. The Marketing Department will champion awareness campaigns, aimed at staff and students, to support the work of the Climate Change Action Plan group and reinforce priorities as the 5-year CMP develops. The Project Leader will continue to report progress to the College Leadership Team via the Project Sponsor. Progress will also be reported to the Board of Management, through the HRD Committee.
5.2.2 Data Management – measuring the difference, measuring the benefit The software tools, provided via the Carbon Trust Carbon Management Program, will be the main resource for tracking the progress of our Carbon Management Plan. As detailed in Project JWC___ we will also use half-hourly electricity use data to eliminate / reduce unnecessary usage. Information from these sources will be reported and monitored at regular meetings of the Climate Change Action Plan group. Progress and agreed actions, from group meetings, will be reported to the College Leadership Team via the Project Sponsor (AP Organisational Development). The Project Leader will provide progress reports for each meeting of the HRD Committee. By comparing progress against the annual targets in graph 2 we will be able to see if we are on track or not.
5.3 Resource commitment Financial: In year one £50,000 has been committed to implement viable projects which have not already been budgeted for. In subsequent years College departments will be expected to include carbon management initiatives in their Operational Plans and to include appropriate funding in their annual budget submissions. Overall, the aim will be to invest real savings, from improved carbon management, in future carbon reduction projects. People: The members of staff, on the Climate Change Action Plan group, will commit time for the work of the group and for any carbon management projects for which they are responsible.
Page 15
James Watt College - Carbon Management Programme Carbon Management Plan working with
Page 16
The owners of carbon management projects will commit appropriate time and resources to ensure implementation of those projects.
5.3.1 Implementing the Initiatives The Carbon Management Plan (CMP) is “owned” by the Climate Change Action Plan group and the Project Leader is responsible for reporting on the plan’s progress. The owners of specific carbon management projects are responsible for implementation and reporting progress on those specific projects to the Climate Change Action Plan group.
5.3.2 Maintaining quality over time The CMP will be a live document which will be monitored, maintained and revised by the Climate Change Action Plan group. Proposed, new carbon management initiatives will be judged on their practicability and contribution to our target of a 25% reduction in carbon emissions. Proposed projects will also be required to fit within the College’s Strategic and Operational Plans.
5.3.3 Leadership and Management of the CMP As with any 5-year programme our CMP relies on strong strategic leadership and committed management to ensure success. As the project sponsor and a member of the College Leadership Team, the Assistant Principal – Organisational Development provides strategic leadership. The HS&E Service Manager is the project leader and is responsible for ensuring that the programme remains on track, that progress is monitored and that any blockages are identified and removed where possible. Project owners will be brought together, at key stages of the programme, to co-ordination and consistency in carbon reduction activity. If any key members of the Climate Change Action Plan group leave post or change role their immediate successor will assume responsibility for their role in the group.
5.4 Implementation Plan The official start date of our 5-year Carbon Management Programme will be 1st August 2010 (the start of our Financial Year 2010-11). Annual programme reviews will follow the financial year cycle. The Climate Change Action Plan group will have a “kick off” meeting and will meet quarterly. Project owners will be required to report project progress to the group. Quarterly programme progress reports will be produced.
James Watt College - Carbon Management Programme Carbon Management Plan working with
Page 17
Proposed Carbon Management Projects Project Ref. Number
Description of Project Would you like advanced analysis?
Owner Total KWh,
tonnes or m3
saving in yr 1
£ Net Savings in yr 1 (Incl
OpEx)
Lifetime of project from start year (years)
Simple Payback (years)
CO2 savings in yr 1
(tonnes)
% of target
Lifetime CO2 saving
(tonnes)
JWC001 ICT Power Mngt Yes John Denny
75,351 £ 7,535 10 1.66 40 5.7% 1173.2
JWC002 ICT Server Replacement Programme (Virtualisation) Yes
John Denny 158,237 £ 15,824 10 5.06 85 11.9% 1476.8
JWC003 Office Equipment Rationalisation Yes John Denny 90,421 £ 9,042 3 - 49 6.9% 141.5
JWC004 Rationalisation of Premises Yes Peter Thorne 182,336 £ 7,312 10 - 55 7.7% 485.0
JWC005 Marketing Campaign Yes Carrie Gibson 89,071 £ 3,312 3.5 1.51 26 3.6% 211.4
JWC006 Travel Plan Yes Bill McNeice 46,780 £ 5,287 10 - 12 1.7% 103.6
JWC007 Increased recycling across all campuses Yes
Nancy Forbes 193 £ - 10 - 86 12.1% 477.2
JWC008
NAC: Minimise Energy Consumption During Holiday Period Yes 123,650 £ 12,365 10 - 66 9.5% 583.4
JWC009 Optimise Time Schedules for Building Services Plant Yes 172,750 £ 1,728 - 32 4.6% 0.0
JWC010 Increase Temperature Set-points in Server Rooms Yes 12,450 £ 1,245 - 7 1.0% 0.0
JWC011 WFC: Programme Boiler Operation Yes 9,900 £ 99 - 2 0.3% 0.0
James Watt College - Carbon Management Programme Carbon Management Plan working with
Page 18
JWC012 Utilise Energy Savings Functions on Personal Computers Yes 9,000 £ 900 - 5 0.7% 0.0
JWC013 NAC: Phase-out Tungsten Lamps in Residence Blocks Yes 690 £ 69 - 0 0.1% 0.0
JWC014 NAC: Do not Maintain High-level Foyer Lighting Yes 1,525 £ 153 - 1 0.1% 0.0
JWC015 FSC: Switch off Booth-side Lighting in Food Hall Yes 330 £ 33 - 0 0.0% 0.0
JWC016 Fit Time Switches to Vending Machines Yes 6,100 £ 610 - 3 0.5% 0.0
JWC017
Utilise Half Hourly Data to Eliminate/Reduce Unnecessary Electricity Usage Yes 262,000 £ 26,200 - 141 20.1% 0.0
JWC018 FSC: Sequence Boiler Operation Yes 65,700 £ 657 - 12 1.7% 0.0
JWC019 NAC: Alter Boiler Control Settings to Allow Low-Fire Operation Yes 10,950 £ 110 - 2 0.3% 0.0
JWC020 Insulate Valves Yes 58,200 £ 582 - 11 1.5% 0.0
JWC021 NAC: Install PIRs on Corridor Lighting Yes 32,250 £ 3,225 - 17 2.5% 0.0
JWC022 NAC: Install Day Light Control on Refectory Lighting Yes 2,300 £ 230 - 1 0.2% 0.0
JWC023 NAC: Install Tamper-proof Thermostats Yes 27,200 £ 2,720 - 15 2.1% 0.0
JWC024 WFC: Install PIRs on Corridor Lighting Yes 15,150 £ 1,515 - 8 1.2% 0.0
JWC025 NAC: Install Day Light Control to Entrance Hall Lighting Yes 1,200 £ 120 - 1 0.1% 0.0
JWC026 FSC: Begin Gradual Phasing Out of Inefficient T12 Lighting Yes 12,550 £ 1,255 - 7 1.0% 0.0
JWC027 WFC: Overhaul of Academic Building Air-Conditioning System Yes - 16,326
-£ 1,633
does not
payback - 9 -1.2% 0.0
James Watt College - Carbon Management Programme Carbon Management Plan working with
Appendix A: Projects
Project: Reference:
ICT Power Management Programme JWC-001
Owner (person) John Denny (ICT and e-Learning Manager)
Department ICT and e-Learning
Description Introduction of Software to Manage PC and Server Power Consumption
Benefits Reduction by c. 1/3 rd of current electricity consumption for PCs and Servers (Approx. 200kWh per PC per yr) Estimated saving of £36,000 % of Target: 5.7%
Funding Project cost, c. £12,500 Estimated payback 1.66 years Source of funding: internal
Resources Delivered within current resources
Ensuring Success
Funding currently in place. Current resources capability in place. No foreseeable risks.
Measuring Success
Reduction of electricity costs. Success progress of project will be measured on annual basis.
Timing Milestones / key dates e.g. • start date: June 2010 • completion date (when it will deliver savings): June 2010 • interim deliverable / decision points June 2011, June 2012
Notes
Page 19
James Watt College - Carbon Management Programme Carbon Management Plan working with
Project: Reference:
ICT Server Replacement Programme JWC-002
Owner (person) John Denny (ICT and e-Learning Manager)
Department ICT and e-Learning
Description Replacement of current server stock with newer more energy efficient equipment and reduction in number of servers
Benefits Reduction by c. 1/3 rd of current electricity consumption for servers % of Target: 11.9%
Funding Project cost, c. £80,000 Source of funding: internal
Resources Delivered within current resources
Ensuring Success
Funding currently in place. Current resources capability in place. No foreseeable risks.
Measuring Success
Reduction of electricity costs. Optimal no. of servers reached. Success progress of project will be measured on annual basis.
Timing Milestones / key dates e.g. • start date: 01/03/2010 • completion date (when it will deliver savings): 01/03/2010 • interim deliverable / decision points 01/03/2011, 01/03/2012
Notes
Page 20
James Watt College - Carbon Management Programme Carbon Management Plan working with
Project: Reference:
Office Equipment JWC-003
Owner (person) Brian Bradley/John Denny
Department ICT
Description To rationalise the existing printing and copying resource, reduce the cost of delivering the service, reduce the volume of paper being used, gather information on what drives our print/copy habits and use this to make informed decisions regarding the allocation of printers/photocopiers, to reduce electricity consumption, to provide staff with an alternative means of distributing documents rather than print, to have all devices on the one contract for maintenance and service, to improve service levels for print/copy devices, to pass responsibility for disposal of equipment on to the contractor and to keep pace with changes in technology.
Benefits Financial savings: circa £150,000 in the first year (approximately £98,000 from fixed costs attached to the current contract, approximately £30,000 from reduction in electricity use, approximately £8,000 from a reduction in paper use and approximately £14,000 from a reduction in the number of toner and ink cartridges needed to deliver the service) % of Target: 6.9%
Funding The fixed cost at the time of writing is circa £53,000 per quarter. This is in comparison to the £78,000 we are currently paying. Note that the new fee also includes an entirely new printer (or multi-functional device) fleet rather than just photocopiers provided under the existing fleet. There are variable costs attached to this project which vary depending on the device used. We have yet to estimate how much this may cost us and the final outcome will depend greatly on how effectively staff use the new set-up This project will be funded internally.
Resources To be delivered within current resources
Ensuring Success
Key success factors: reduction in volume of paper used, reduction in amount of electricity consumed, equipment downtime minimised. Principal risks: staff accepting the change and using the new set-up effectively
Measuring Success
Measuring volume of paper purchased, comparing year-on-year electricity consumption, records of downtime To be measured at least quarterly
Timing Milestones / key dates e.g. • start date: 01/07/2010 • completion date (when it will deliver savings): 01/07/2010 onwards • key dates will be quarterly reports and meetings with supplier
Notes With equipment downtime we are also aiming to replace toner cartridges before the toner runs out.
Page 21
James Watt College - Carbon Management Programme Carbon Management Plan working with
Project: Reference:
Rationalisation of Premises JWC-004
Owner (person) Peter Thorne
Department Estates Department
Description The leases on a number of “satellite” sites are being given up and the activities are being brought in-house at our North Ayrshire Campus (NAC) and Finnart Street Campus (FSC)
Benefits Financial savings: £7,312 (in year 1) Payback period: [x] years CO2 Emissions reduction: 55 tonnes of CO2 % of target: 7.7%
Funding Project cost: Operational costs: the costs associated with this project are being incurred for wider business reasons and should not be attributed to the CMP. Source of funding: internal
Resources This project will be delivered within current resources
Ensuring Success
Key success factors will be eliminating the costs of operating the satellite sights, including energy costs (with associated carbon reductions) Principal risks: having in-house facilities available for the start of the new term
Measuring Success
Metrics for displaying performance or achievement: reduced energy consumption figures When success will be measured / evaluated: on-going
Timing Milestones / key dates e.g. • start date: 25/06/2010 • completion date (when it will deliver savings): 25/06/2010 • interim deliverable / decision points
Notes
Page 22
James Watt College - Carbon Management Programme Carbon Management Plan working with
Project: Reference:
Marketing Campaign JWC-005
Owner (person) Carrie Gibson
Department Marketing
Description The Marketing Department will run awareness campaign(s) aimed at staff and students to support the Carbon Management Programme
Benefits Financial savings: £3,312 Payback period: 1.51 years CO2 Emissions reduction: 26 tonnes of CO2 % of target: 3.6%
Funding Project cost: £5,000 for the 1st year campaign(s) Operational costs: Marketing will include funding for awareness campaigns in future years of the programme Source of funding: internal
Resources Additional resource e.g. printing will be met from budget All other resources are internal
Ensuring Success
Campaigns will be evaluated through participation and feedback Principal risks: pressures on funding
Measuring Success
See “Ensuring Success” above
Timing Milestones / key dates e.g. • start date: dd/mm/yyyy • completion date (when it will deliver savings): dd/mm/yyyy • interim deliverable / decision points
Notes
Page 23
James Watt College - Carbon Management Programme Carbon Management Plan working with
Project: Reference:
Travel Plan JWC-006
Owner (person) Bill McNeice
Department Health, Safety and Environmental Service
Description To promote an Environmental Travel Programme through all campuses
Benefits Financial savings: £5,287 Payback period: CO2 Emissions reduction: 12 tonnes of CO2 % of target: 1.7%
Funding Project cost: £3,000 Source of funding: internal
Resources Additional resource e.g. software management All other resources are internal
Ensuring Success
Campaigns will be evaluated through participation and feedback Principal risks: pressures on funding
Measuring Success
See “Ensuring Success” above
Timing Milestones / key dates e.g. • start date: 2010 • completion date (when it will deliver savings): on-going
Notes
Page 24
James Watt College - Carbon Management Programme Carbon Management Plan working with
Page 25
Project: Reference:
Increased Recycling across all campuses JWC-007
Owner (person) Nancy Forbes
Department Estates and Facilities
Description Estates & Facilities and Health, Safety and Environmental Services will work together to promote Recycling throughout the campuses and distribute the required equipment e.g. bins etc
Benefits Financial savings: Payback period: CO2 Emissions reduction: 86 tonnes of CO2 % of target: 12.1%
Funding Project cost: Are unknown Operational costs: Marketing will include funding for awareness campaigns
in future years of the programme Source of funding: internal
Resources Additional resource e.g. recycling bins, printing All other resources are internal
Ensuring Success
Campaigns will be evaluated through participation and feedback Principal risks: pressures on funding
Measuring Success
See “Ensuring Success” above
Timing Milestones / key dates e.g. • completion date (when it will deliver savings): on-going • interim deliverable / decision points
Notes