James Gillespie’s Primary
description
Transcript of James Gillespie’s Primary
1
Rising School Rolls
James Gillespie’s Primary SchoolCrawford McGhie – Asset Planning Manager
Robbie Crockatt – Planning Officer
James Gillespie’s Primary
2
90% catchment P1 population retained
2.6% drop between P1 and P7
9% of total catchment population attend RC (compared to 14% 2009)
17 classes required from August 2015
2 P7 classes exiting in 2014/15
3 P1 classes forecast for 2015/16
3
James Gillespie’s PrimaryCatchment Review – Neighbouring Schools
• Bruntsfield
• Liberton
• Sciennes
• South Morningside
• Tollcross
4
James Gillespie’s PrimaryCatchment Review – Factors to Consider
Populated Areas
5
James Gillespie’s PrimaryWorking Group Proposal: New Build – Permanent; Standalone • Location to be agreed by Working Group and Design Team
Standalone
Time Reduced construction time with Hub Procurement route – build starts in March/April, completed by August.
Cost Approx £800k (compared to approx £500k for TU for 4 years)
For • High standard specification and performance; modern, flexible learning environment;• Allows future opportunity to address long-term issues such as quality of GP provision; small classrooms; use of temporary units;• Controlled build minimising disruption.
Against • Loss of playground space until rolls drop and existing TU removed;• No direct access to existing.
6
James Gillespie’s PrimaryRising Rolls 1: Trinity Primary School
7
James Gillespie’s PrimaryRising Rolls 2: Broughton Primary School