James Cook University Procurement Process … of, and discussions with management. ... Founded in...
Transcript of James Cook University Procurement Process … of, and discussions with management. ... Founded in...
Page 2
Private and confidential
Ms. Tricia Brand Executive Director Division of Finance and Resource Planning James Cook University Angus Smith Drive Douglas, QLD 4811 Dear Tricia We have completed our work to assess and develop a ‘to be’ state and supporting roadmap and implementation plans to improve the University's Procure to Pay process during the period 11 November to 13 December 2013. We conducted our work in accordance with our engagement agreement dated 31 October 2013, and our procedures were limited to those described in that letter. The detailed scope and approach of our work and the findings and recommendations are described in this report. As outlined in our engagement agreement, our report including findings, recommendations and implementation plans delivered to you are based on inquiries of, and discussions with management. We have not sought to verify the accuracy of the data or the information and explanations provided by management.
17 December 2013
Ernst & Young
111 Eagle Street
Brisbane
QLD 4000
Tel: +61 7 3011 3333
Fax: +61 7 3011 3100
ey.com/au
We appreciate the cooperation and assistance provided to us during the course of our work. If you have any questions regarding the content of this report, please contact Peter Rohan on phone: (03) 9655 2668 or via email: [email protected] Yours Sincerely Ernst & Young Date: 17 December 2013
James Cook University P2P
Page 3
Disclaimer
►Our work has been limited in scope and time and we stress that more detailed procedures may reveal issues that this engagement has not. Our report does not constitute an audit or review in accordance with any generally accepted auditing or review standards.
►Our report is intended solely for the information and use of the management of James Cook University and is not intended to be and should not be used by anyone other than these specified parties. Ernst & Young therefore assumes no responsibility to any user of the report other than JCU. Any other persons who choose to rely on our report do so entirely at their own risk.
Presentation title
Page 4
Contents
Executive Summary 5
Introduction 8
Findings & Opportunities 15
Strategy & Governance 16
Policy & Process 20
People & Organisation 25
Risks & Controls 35
Data & Technology 42
Performance Management 49
Sign-off 56
Appendices
Appendix A: Stakeholder Engagement 58
Appendix B: Opportunity Maps 64
Appendix C: ‘To Be’ Process Illustrative Examples 72
Appendix D: Singapore Procurement Processes 81
Appendix E: Implementation Plans 83
Appendix F: Interview Quotes 84
Appendix G: Change Management & Culture 89
James Cook University P2P
Page 6
Executive Summary
Context and Review Objectives:
► Ernst & Young (EY) was appointed by James Cook University (JCU) to assess and improve their Procure to Pay (P2P) process to enable: ► Consistency across the University
► Increased effectiveness and efficiency of the end-to-end process
► Incorporation of adequate controls to prevent risk.
► This work was conducted as part of a broader program of improvement currently being implemented across JCU.
► The focus of our work has been to identify practical steps to improve the P2P process in a manner consistent with better practice, but equally seeking immediate short-term improvements where feasible.
Findings:
Our overall recommendations set out in this report provide details regarding proposed changes to: Strategy & Governance, Policy & Processes, People & Organisation, Risks & Controls, Data & Technology, and Performance Measurement. A summary is provided on the following page. These recommendations address what EY consider to be quite significant scope to improve the current processes that are characterised as too manual, with unclear accountabilities, excessive checking, and without any overarching procurement strategy.
Our recommendations include a number of initiatives that can be implemented progressively, some starting immediately. However, to limit change fatigue, the implementation plan transitions directly towards a best of breed P2P function, rather than an interim transition stage first.
Our work also highlighted the dependency of many major potential improvements on full use of the functionality of existing systems, notably FinanceOne. Our talks with the vendor, as well as other users of FinanceOne, were most helpful in shaping our final recommendations and equally provide an ongoing forum for JCU to engage with other universities confronting similar problems in a similar systems environment.
James Cook University P2P
Page 7
Executive Summary (Cont.)
Area of
Improvement
Recommendations
Strategy & Governance ► Articulate and align the JCU procurement plan with JCU strategic and business objectives and State
Purchasing Policy (SPP)
► Implement formal category management, strategic sourcing and supplier collaboration in selected areas to
extract better value from total spend and reduce suppliers and transactions per supplier
► Establish clear governance for procurement
Policy & Process ► Move to a single requisition method, in addition to use of credit cards
► Eliminate selected non-value add process points (these are identified in the body of the report)
► Assess potential to move to an integrated system and remove manual processes
► Establish end-to-end University processes with identified process owners
People & Organisation ► Clarify roles and responsibilities across the P2P process (the report provides a starting point)
► Appoint a Chief Procurement Officer, (or equivalent) with the capability and authority to drive the benefits
from improved procurement practices
► Assess and build capability of the procurement function
Risks & Controls ► Simplify and increase the transparency of delegations
► Align risks and controls adopting a more risk-based approach (e.g. not funds checking every transaction and
performing additional checks)
► Automate controls where possible
Data & Technology ► Review FinanceOne and Spendvision functionality with vendors
►Better leverage the existing functionality of FinanceOne
► Improve data capture and interfaces to support reporting, analysis and performance management
Performance
Measurement
► Aligned to the procurement plan, introduce a balanced scorecard approach, to measure performance for both
the procurement function and individuals
► Introduce supplier performance and contract monitoring for key suppliers and contracts
James Cook University P2P
Page 9
Introduction
Seeking to improve efficiency and effectiveness of University wide services and operations, JCU collaborated with EY to identify improvement opportunities across a number of services.
Following on from these findings, EY was engaged to assist in reengineering JCU’s P2P process.
The focus was to rapidly design a better practice model for the P2P process, and collaborate with the JCU project team to develop transition and implementation plans to enable:
► Consistency across the University
► Increased effectiveness and efficiency of the end-to-end process
► Incorporation of adequate controls to prevent risk
The project was delivered using a phased approach illustrated below:
James Cook University P2P
Page 10
Approach & Scope
Approach:
A collaborative workshop based approach was used to leverage EYs experience, and existing JCU documentation and knowledge to:
► Understand the current state of P2P at JCU
► Develop a ‘to be’ design leveraging better practice
► Develop a transition and implementation plan for the ‘to be’ state
Details of Stakeholder engagement are contained in Appendix A.
High level benchmarking was conducted to compare JCU’s P2P efficiency against available data (APQC1 benchmark data sets and other data available to EY) to confirm potential improvement opportunities. The focus of this benchmarking was on FTE effort in undertaking key procurement processes.
Scope:
JCU Singapore was considered only in the context of assessing its potential as a location for all P2P processes across JCU. It has not been included in the formal implementation plan, except with respect to recommendations regarding longer- term shared service processing recommendations.
A key assumption of the ‘to be’ design is FinanceOne (JCU’s current Finance system) will not be replaced in the foreseeable future. Therefore, consistent with the JCU’s IT strategy, investigation was undertaken of additional end-to-end procurement functionality of Finance0ne to support JCU’s P2P process. While there are potential other procurement solutions that could integrate with FinanceOne, a market scan of such technology was out of scope for this project.
Noting this project is part of a broader JCU program of work, it was agreed (notwithstanding a separate review JCU’s delegation framework) to the extent improvements to delegations were identified as part of the P2P project they would be included in scope. While there are also touch points between P2P and a project to improve JCU’s travel process, travel processes were out of scope.
1. Founded in 1977, APQC is a member-based non-profit serving 500 organisations worldwide in all industry sectors. APQC spearheaded the Open Standards Benchmarking Collaborative (OSBC) research to develop commonly used processes, measures and benchmarks that are available to organisations worldwide to improve performance. (www.apqc.org).
James Cook University P2P
Page 11
Current & ‘To Be’ State
Current & ‘to be’ State:
In assessing the current state, it was identified the following leading practices were already in place within the P2P process of JCU, and would be retained in the ‘to be’ design:
► Low value purchases <$5 thousand are made via purchase card
► All accounts payable settlements are made via Electronic Funds Transfer (EFT), with no payments made via cheque
► There are some automated controls and workflow systems in use within FinanceOne
► The University has in place standard payment terms
► The University has made some progress to obtaining synergies with the transition towards a shared services model.
Notwithstanding these practices, a number of pain points and opportunities to improve the efficiency and the effectiveness of JCU’s P2P process were identified.
The table on the following page provides an overview of the current and ‘to be’ state of P2P at JCU.
James Cook University P2P
Page 12
Current & ‘To Be’ State (Cont.)
Element To be State Current State
Strategy &
Governance
A clear procurement vision and plan supported by documented strategies communicated across the University with robust risk management plans and a clear governance model across all faculties and divisions
Procurement strategy is out of date, lacks clarity and is poorly communicated. The function is not supported by a structured governance model and is broadly disconnected from its customers (JCU faculties and divisions)
Policy & Process Policies and processes are clear, documented and easily accessible. Processes will be value adding and automated, leveraging technology (where cost effective). Existing good practices will be retained
Policies and processes exist, however, there is not a clear University-wide view of the end-to-end processes. There are also a number of manual and non-value adding processes
People &
Organisation
The procurement organisation plays a strategic role, enabled by an optimised model with clear roles, responsibilities, accountabilities and integrated competencies
The procurement role is operational, with a lack of clarity regarding roles, responsibilities and accountabilities, and may not be leveraging the full benefits from shared services opportunities
Risks & Controls Controls and delegations reflect value, risk and capability, and are automated and preventative where possible
A perception that the procurement process is over-controlled, with no clear link between risk tolerance and control design and a heavy reliance on manual controls
Data &
Technology
A University-wide end-to-end integrated system solution, which reduces manual processes and risks, and captures data to support decision making and performance management
A number of manual processes (including paper based forms), a lack of integrated systems, and limited quality data to support analysis and performance measurement
Performance
Measurement
Monitor the service and value added by the procurement function through clear and integrated internal performance metrics linked to strategy and translated to function and employee level, as well as monitoring supplier performance
No official performance management framework exists for the procurement function. KPIs for both the procurement function and individuals are not aligned to a procurement plan and translated into actions at the employee level. Supplier performance and contract compliance is not officially managed and procurement benefits realisation is not tracked
James Cook University P2P
Page 13
High
0 - 6 months
Low
Medium
Eff
ort
Timeframe
6 - 12 months 12 months +
SG1
Prioritised Opportunities
Opportunities
SG1 Document procurement plan and consistent polices RC4 System based approvals
SG2 Develop procurement risk register RC5 Remove additional funds check
SG3 Implement strategic sourcing and category management RC6 PCI compliance as part of vendor selection
SG4 Rationalise Product Range RC7 Eliminate additional approval requisition & order
SG5 Consolidate and maintain accessible preferred suppliers list RC8 Remove additional supplier data check on set up
SG6 Develop Performance Framework RC9 Centralise receipting and invoice processing
SG7 Integrate ethics and sustainability into strategy RC10 Remove additional invoice processing check
SG8 Restructure procurement governance RC11 Perform a 3 way match
PP1 Simple policy decision tree RC12 Remove additional review of Western Union File
PP2 JCU wide process RC13 Enforce credit card acquittal timelines
PP3 Single requisition method RC14 Eliminate retrospective purchase orders
PP4 System generated Purchase Order RC15 Map risks and controls
PP5 Service levels and ability to monitor workflow DT1 Requisition access to relevant parties
PP6 Remove unnecessary process flows DT2 Solution to monitor credit card purchases
PP7 Use of sundry creditors DT3 Integrated end-to-end solution
PP8 Efficiencies through centralisation DT4 Leverage existing technology functionality
PP9 Remove duplicate data entry DT5 Resolve partial receipts “Carry ons”
PP10 Remove manual process DT6 Data capture to support analysis
PO1 Define roles, responsibilities and accountabilities DT7 Capture un acquitted card commitments
P02 Redefine organisational structure DT8 Single supplier file
PO3 Establish CPO role DT9 Review system functionality and market scan
PO4 Incorporate training and accreditation PM1 Develop procurement function KPIs
PO5 Perform competency assessments PM2 Introduce performance management
P06 Develop performance metrics to incentivise compliance PM3 Develop procurement scorecard
PO7 Engage staff and build careers PM4 Develop employee KPIs
PO8 Re-scope of shared services PM5 Develop supplier performance framework
PO9 Consider leveraging global work force PM6 Implement external benchmarking
RC1 Simplify and increase transparency of delegations PM7 Improve data quality
RC2 System requisition with application controls PM8 Incorporate benefits management
RC3 Materiality threshold for funds check PM9 Enforce consequences for non acquittal of cards
To develop the implementation plan to support JCU in achieving its ‘to be’ state, the expected time and effort across each improvement opportunity was assessed. Initiatives were classified according to the following delivery time horizons:
► Short-term: 0-6 months (including ‘Quick Wins’ in green)
► Medium Term: 6-12 months
► Long Term: 12+ months
The outcomes of this prioritisation process are shown below.
Each of these opportunities is discussed in the body of the report and cross referenced to the implementation plans in Appendix E.
James Cook University P2P
SG2
SG3
SG4 SG5
SG6 SG7 SG8
PP1 PP2
PP3 PP4 PP5 PP6
PP7
PP8
PP9 PP10
PO1 PO2 PO3
PO4 PO5
PO6
PO7 PO8
PO9
RC1
RC2
RC3
RC4
RC5
RC6
RC7 RC8
RC9
RC10
RC11
RC12
RC13
RC14
RC15 DT1 DT2
DT3
DT4
DT5
DT6
DT7
DT8 DT9 PM1
PM2 PM3 PM4 PM5 PM6 PM7 PM8 PM9
Page 14
Next Steps
The following next steps are recommended:
► While prioritisation and timeframes of opportunities were discussed at the ‘to be’ validation workshop with stakeholders, prioritisation must be reviewed in the context of:
► Resource availability, capability and internal priorities (e.g. prioritise ‘quick win’ initiatives in the context of BAU activities and JCU broader program initiatives)
► Interdependent initiatives within this project and the broader program will impact overall success. We have worked with stakeholders to understand these dependencies in the definition of the roadmap. Key dependencies are listed in the opportunities tables on the subsequent pages
► Partnering with IT to validate and align system associated initiatives with the overall IT strategy and roadmap. We have held preliminary discussions with IT to understand the current landscape and future direction to inform development of the roadmap.
► Complete a case for change including the quantification of the impact of the opportunities, noting key inputs requiring further analysis including:
► Assessment of University-wide benefits
► The cost of technology investment
► Human resource investment required.
► JCU Governance to review and endorse the recommended prioritised initiatives and confirm BAU resource level impacts.
► Recognising the significant cultural shift will be key to the successful transition of P2P at JCU, we have included change and culture information in Appendix G.
James Cook University P2P
Page 17
Strategy & Governance Findings
► Corporate Procurement Plan aligning to the SPP and JCU‘s business strategy documented annually
► Efficient, integrated and well documented procure to pay process available to all users
► Key categories sourced and managed centrally:
► Strategic sourcing and category management function
► Fixed price contracts, standing offers and blanket orders
► Specification and product rationalisation
► Leverage Whole-of-Government contracts and standing offers
► Procurement risks are managed, prioritised and mitigated through collaboration with suppliers
► Supplier consolidation and preferred supplier lists are maintained on a regular basis
► Effective supplier collaboration (forward buy plans) and supplier performance management
► A clear governance model across all faculties and divisions, led by a CPO (or equivalent) reporting directly to the Executive Director Finance and Resource Planning (EDFRP)
► JCU procurement plan is not current and lacks clear strategy
► The last Corporate Procurement Plan is dated 2010
► Per SPP the plan should be developed annually
► A procurement risk register and mitigation plan does not exist
► Procurement strategy enablers are not used to full effect:
► Strategic sourcing and category managment is almost non-existent
► Fixed price contracts and standing offers are used but not to great effect
► Supplier consolidation is non-existent
► Preferred supplier lists exist but are not widely communicated or enforced
► Product and/or specification rationalisation is not being used to reduce procurement complexity
► JCU‘s procurement function currently lacks strategic direction, structure and leadership
To Be State Current State
JCUs current procurement strategy is out of date, lacks clarity and is poorly communicated. It does not align to State Purchasing Policy (SPP) requirements and is not driven by clear policies and procedures. The centralised procurement function is not supported by a structured governance model and while there are some strong relationships, it is broadly disconnected with its customers (JCU faculties and divisions).
James Cook University P2P
Page 18
Corporate Procurement Plan and SPP
► The SPP requires JCU to develop an annual Corporate Procurement Plan based on a thorough understanding of the University’s purchasing expenditure, supply markets and demand attributes. It should define: ► The objectives to be achieved through the department’s/agency’s purchasing activities consistent with the objectives of the
State Purchasing Policy
► How the department/agency will meet its specified objectives
► Mechanisms through which the achievement of the department’s/agency’s procurement objectives will be measured SOURCE: Queensland Purchasing – Corporate Procurement Planning – Better Purchasing Guide February 2001
► The SPP states JCU should be driving towards a procurement function that aligns with the following six principles: 1. Principle 1: We drive value for money in our procurement
2. Principle 2: We act as ‘one government’, working together across agency boundaries to achieve savings and benefits
3. Principle 3: We are leaders in procurement practice – we understand our needs, the market, our suppliers and have the capability to deliver better outcomes
4. Principle 4: We use our procurement to advance the government’s economic, environmental and social objectives and support the long-term wellbeing of our community
5. Principle 5: We have the confidence of stakeholders and the community in the government’s management of procurement
6. Principle 6: We undertake our procurement with integrity, ensuring accountability for outcomes ► SOURCE: Queensland Procurement Policy June 2013
“The corporate procurement plan should set out the strategies for improving management of the
University's procurement function and related expenditure, providing a whole-of-university view of
procurement”
James Cook University P2P
Page 19
Strategy & Governance Opportunities
Ref Opportunity Issue Impact Effort Time Frame
Dependencies
SG1 ► Document the corporate procurement plan
aligning to business strategy and SPP
► Clearly document consistent policies for
procurement processes (See also PP2)
► The corporate procurement plan has not been
updated since 2010
► JCU purchasing objectives and strategy are
unclear
M M
0-6 Capability
SG2 ► Develop a procurement risk register and
mitigation strategies, collaborating with key
suppliers
► Mitigation of issues arising from risks is
reactive rather than proactively managed
M
M
0-6 Capability
SG3 ► Implement strategic sourcing and category
management
• Prioritising based on total spend,
operational importance, supply chain risk
and savings opportunities
► There is a further opportunity to leverage
whole-of-Government supply arrangements
► Faculties manage simple procurement
independently
► Cost and time savings through aggregated
volume and contract based procurement are
not leveraged
H H 6-12
Capability Data quality Subject to capacity could be done in conjunction with SG4 & SG5
SG4 ► Rationalise product range and consistency of
specifications to remove procurement
complexity
► A potential large range of similar products
means more complexity for the supplier and
less opportunity for procurement savings
H L/M 0-6 Data quality
SG5 ► Consolidate range of suppliers and develop
and maintain a preferred supplier list that is
easily accessible to users
• Longer-term suppliers are embedded in
system application controls such as
catalogues
► Procurement of the same items from multiple
suppliers is likely resulting in lower savings
from volume aggregation and increased
supplier appraisal complexity
H L/M 0-6 Data quality
SG6 ► Develop a performance framework and metrics
for key contracts and suppliers
• Incorporate these in new contract
arrangements (including supplier reporting)
(See also PM5)
► Supplier adherence to contract and service
level agreements is not formally monitored or
enforced
• Potentially results in poor service
M
M
6-12 Capability Data quality
SG7 ► Integrate university ethics and sustainability
aspects into procurement strategy
► Level of requirement for procuring
goods/services locally and sustainably is
unclear
L M
0-6 Capability
SG8 ► Restructure procurement governance and
recruit a CPO (or equivalent) that reports
directly to the EDFRP
► Procurement function lacks leadership,
strucuture, direction and accountability
H M
0-6
James Cook University P2P
Page 21
Policy & Process Findings
► A user friendly single point of entry:
► Policy and process in the form of a decision tree with links to relevant details
► Clear and documented end-to-end processes and work instructions centrally developed, communicated and easy to locate and access
► Processes are University-wide and end-to-end with a clear process owner
► Processes are automated and leverage system functionality to reduce manual rekeying, review and intervention (subject to cost/ benefit considerations)
► Non-value adding or inefficient processes are removed
► Consider implementing a goods receipting process to support centralised processing of invoices and gain efficiencies
► Purchasing low value goods and services of less than $5,000 via purchase cards and negotiating standard payment terms with suppliers will continue
► Appropriare card purchase controls are to be enforced
Illustrative ‘to be’ processes (subject to system functionality) are included Appendix C.
► Users are challenged by the format and volume of content in FMPM 711
► No clear documented Univeristy-wide end-to-end process:
► Key process documentation is fragmented with organisational units developing their own guidance and work instructions
► A reliance on manual processes:
► Paper based forms, manual entry, approvals, and emails to manage workflow and review
► Varied and non-value adding processes:
► Multiple requisition formats
► Reformatting of Purchase Orders and the generation of Purchase Orders not sent to suppliers
► Duplicated checks
► No formal goods receipting process:
► Receipting is performed via a signature on an invoice which is then sent to accounts payable for processing
Further details regarding the manual and non-value adding processes are identified in the Opportunity Maps in Appendix B and cross referenced with the opportunities below.
To Be State Current State
There is an opportunity to simplify the structure of JCUs procurement policy and develop consistent process documentation to aid user understanding. There are also various process inefficiencies. While some of these are driven by workflow, rework and controls, the most significant opportunities relate to process automation. As such, many of the recommended process improvements are dependant on investment to improve systems functionality.
Note: While there are potential further opportunities that could be obtained from warehousing
and inventory management. Given the current maturity and preferences of the University these
opportunities have not been included in the recommendations and implementation plan for the
‘to be’ state.
James Cook University P2P
Page 22
Policy & Process Opportunities
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
PP1 ► Develop a simplified decision tree with
hyperlinks and communicate to staff. An
example is included in Appendix C Training of
staff should also address this issue. (See also
PO4)
► Procurement policy is documented, however
anecdotally users are unaware of or unclear on
its end-to end application, including exception
handling
M L 0-6 Develop based on as-is process
and refine as processes are
redesigned in conjunction with
system capability
PP2 ► Develop JCU wide processes
• Each process has a process owner (See
PO1) and clear support contacts
Note: It is recognised in some instances there may
be a requirement for varied process. This is to be
approved by the process owner and included into
centrally documented processes.
► Key processes are documented, however
these have been developed in a fragmented
approach by various divisions and faculties
M L 0-6 Technology: Processes will need to
be amended to reflect changes
made as part of changes to the
system landscape
As processes are redesigned,
document the end-to-end chain
commencing with sourcing and
catalogue creation through to
payment
PP3 ► A single requisition method to promote
consistency and clarity of process (See also
PP4)
• Requisitions should be entered into an
integrated system environment
► There are three methods of raising a
requisition, which is inefficient and confusing
for users (See also DT1)
► Requisition information is manually keyed by
Purchasing Officers from paper based
requisitions. Where email or Webreq is used
copy and paste functionality reduces the effort
and some risk of data entry error
H
M 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape
PP4 ► A system generated Purchase Order that
meets JCU requirements and is provided to the
supplier directly (See also DT9)
► The Spendvision Purchase Order requires
amendment before being emailed by the
Purchasing Officer to the supplier, including:
• PO number to match the Webreq number
• Delivery address details
• Reformatting due to legibility
► Staff not using Spendvision prepare manual
Purchase Orders based on a template
Note: in some instances the order is placed over
the internet and no Purchase Order is required.
M M 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape and the future of
Spendvision
PP5 ► Service levels and performance build trust with
customers incentivised by performance
metrics (See also PM4)
► Longer-term staff have access to systems to
monitor the status of their order (See also DT9)
► The Purchasing Officer sends an email to the
requestor notifying them the order has been
placed with the supplier
M M 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape
James Cook University P2P
Page 23
Policy & Process Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
PP6 ► Remove unnecessary process flows
► Maximise efficiency through implementation of
online requisitions with automated workflows
► Manual processes result in unnecessary flows
of documents
M M 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape
PP7 ► Use of sundry creditors in FinanceOne, subject
to:
• Data capture to support analysis and
monitoring of spend by supplier
• Preferred supplier controls to limit use (via
category management and strategic
sourcing)
► Communicate clear service expectations
regarding creditor set up timelines -
consideration given to broadcast emails of
chart changes
► Creditors are established in FinanceOne for
every supplier, student and staff member
where payments are made via Accounts
Payable. This can be up to 30 per day.
► Staff have indicated delays in waiting for
supplier set up. As there is no notification
Purchasing Officers check daily to see if the
creditor has been established
► Restricted access to creditor set up in
FinanceOne was raised as a pain point, this
restriction is a key control and should be
retained
M L 0-6 Data quality: Capturing creditor
details to support analysis
PP8 ► Efficiencies gained through centralising
• Invoice receipt
• AP processing
• Receiving and inventory management by
division, faculty or school (See also RC9)
► Technology to scan all invoices via the mail
room directly to AP
► Inefficient document flows
• Invoices sent to Purchasing Officers in
divisions and faculties, scanned and
emailed to end users, signed manually as
“ok to pay” or a return email, before
sending back to the Purchasing Officer
who emails Accounts Payable
► Risk of double payment as credit card
transactions not recorded in a system until
acquitted. Once acquitted, invoice numbers
and vendors can not be easily identified (See
also DT2 and DT6) . Although thought to be
rare, anecdotally in the past some invoices
have been double or triple paid.
M M 6-12 Data quality: Effectively capturing
all transactions currently not in
FinanceOne
Technology: Supporting the
receipting process FinanceOne.
James Cook University P2P
Page 24
Policy & Process Opportunities(Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
PP9 ► Remove duplicate entry of data already
captured
► There is manual entry of fields that are already
recorded in the system (e.g. Purchase Order
Number and Creditor Code in Narrative Fields)
L L 0-6 Data quality: Subject to use of
fields in other systems (e.g.
FinWeb) and reports
PP10 ► Remove filing processes where documentation
is stored and authorisation is recorded in the
system audit trail
► There are a number of filing conventions that
should be considered for removal:
• Naming convention on supporting
documents
• Manual batch numbering and document
checking report , signing and filing
L L 0-6
James Cook University P2P
Page 26
People & Organisation Findings
► Procurement is viewed as a strategic function, plays a key role in developing and implementing business strategy and has buy-in from functional stakeholders
► Roles and responsibilities are clearly defined with integrated competency models reflected in position descriptions
► There are clear process owners
► Recruiting, staffing and training plans integrate the competencies needed to enable the overall procurement strategy
► Procurement attracts and retains talent, with a clear career path for procurement staff
► The organisational model is:
► Fit for purpose
► Supports strategy delivery
► Leverages fully the shared services model and the potential for commodity processing at the Singapore campus
► Agreed function and individual scorecard performance management processes
Note: At the time of drafting this report, JCU was in the process of releasing a proposal
suggesting a headline restructure of the University. The outcomes and impacts of this
restructure were not fully known, and as such have not been considered in the context of
the findings regarding optimisation of the procurement operating model in this report.
► Operational, process based and reactive rather than a strategic function. Relationships with functional stakeholders vary, but are recognised as important
► A lack of clarity regarding roles, responsibilities and accountabilities both within finance and the broader University engaged in procurement
► A perceived competency gap with stakeholders identifying a lack of onboarding, ongiong training and communications as contributing to inefficiencies
► The organisational model is moving towards a shared services model, but can be further optimised to be a higher value strategic function:
► Further, it was identified that in the current decentralised model, Finance and Business Services (FaBs) staff located within faculties may be driven or pressured by their allegience to the faculty as opposed to the finance function, procurement requirements and better practice procurement
► A limited focus on performance management of the procurement function and individuals
To Be state Current State
While JCU has obtained synergies from transitioning to a shared services model, the P2P function remains fragmented, with a lack of clarity regarding end-to-end roles and responsibilities. Cross industry benchmarking identified that the FTE effort devoted to the overall P2P function at JCU indicates significant opportunities for efficiency improvements. There are further opportunities to optimise the procurement organisation to drive performance and savings.
James Cook University P2P
Page 27
To provide additional insight into opportunities to optimise the organisational model P2P at JCU, benchmark analysis of FTE effort across the various P2P activities was undertaken. This exercise leveraged the JCU data from effort analysis previously performed by JCU, comparable APQC benchmarks and University data in EYs benchmarking repository.
NOTE: Benchmarks from APQC expressed as a function of spend/revenue and comparable university benchmarks have been converted to metrics that are directly comparable to JCUs FTE count based on the following assumptions:
Optimising the Organisational Structure of JCU P2P
Ben
ch
mark
Perf
orm
an
ce
Pro
cess
Evalu
ati
on
JC
U
Cross Industry Cross Industry less than
$1bn Revenue
Government & Public
Sector
Comparable
Australian
University 1
Comparable
Australian
University 2
Comparable
Australian
University 3 Benchmark
Sam
ple
Siz
e
To
p
Med
ian
Sam
ple
Siz
e
To
p
Med
ian
Sam
ple
Siz
e
To
p
Med
ian
FTEs in the procurement process
group 60.6 682 7.9 32.1 336 13.0 24.6 164 16.3 26.5 23.8 25.7 22.2
FTEs that develop sourcing
strategies 1 492 0.3 2.3 186 0.6 1.5 Insufficient Sample Size 1.8 0.8 0.5
FTEs that appraise and develop
suppliers 1.1 482 0.7 3.2 183 1.3 2.5 Insufficient Sample Size 4.3 1.5 4.4
FTEs that select suppliers and
develop/maintain contracts 3.4 496 0.9 5.1 190 1.5 3.2 Insufficient Sample Size 4.2 3.7 2.4
FTEs that order materials and
services 30.3 487 3.2 15.0 188 5.1 11.4 Insufficient Sample Size 8.6 13.6 8.1
FTEs that process accounts
payable 3* 50 2.1 8.3 94 3.7 6.2 7 2.7 3.6 N/A N/A N/A
Number of FTEs that process
accounts payable and T&E expense
reimbursements 9.3 50 4.6 32.8 11 11.0 20.7 Insufficient Sample Size 12.05 8.0 27.0
Underperforming against peer group benchmarks
Comparable against peer group benchmarks
Outperforming against peer group benchmarks
Benchmarking identified that the FTE effort devoted to the overall P2P function at JCU appeared high compared median performers. Further, the scope of procurement work currently being performed by the JCU procurement function is also, based on our experience, less than what would be expected in those organisations in the benchmarking study. Therefore, there remains significant opportunity to increase scope and move to a better practice strategic procurement organisation driving performance and savings.
• JCU Annual Revenue ~ $500M
• JCU Annual Spend ~ $180M
• JCU T&E Expenses ~ $14.5M
• FX rate = 1AUD/USD
James Cook University P2P
* This FTE count is based on staffing levels sighted during on-site work
Page 28
Leveraging the Value of Shared Services
► The benefits of shared services are traditionally obtained through the following four levers:
► Labour economies – lower cost to perform the same activities
► Process simplification – standardising and simplifying processes to enhance efficiency and effectiveness
► Organisational consolidation – consolidating activities in fewer locations to drive management and other scale economies
► Systems consolidation – Rationalising systems onto one platform to drive process efficiency through standardisation and automation, which can deliver cost reduction
► To move towards obtaining maximum benefits from its shared services JCU should:
► Consider leveraging the labour economies of its JCU Singapore campus
► Simplify and automate processes
► Defragment procurement processing
► Integrate systems
► As shown in the table below, finance processes that are candidates for shared services are often routine, non-complex and IT intensive:
Mostly Shared Often Shared Emerging Shared Rarely Shared
► Accounts Payable
► Accounts Receivable
► Travel and expenses
► PO invoice matching
► Supplier contract compliance
► Accounting and close
► Fixed assets
► Cash management
► Project Accounting
► Billing
► Procurement card administration
► Create and manage supplier
contracts
► Management reporting
► Process improvement
► Financial analytics
► Supply chain operations
► Supply / demand planning
► Strategic sourcing
► Control and risk management
► Core treasury
► Decision making authorities
► Appraise supplier performance
While JCU is transitioning towards a shared services finance model, there remains further opportunity to gain efficiencies in the P2P function and broader finance by streamlining functions and integrating people, processes and technology.
James Cook University P2P
Page 29
Option to locate P2P processing at JCU Singapore
►Transitioning P2P processing to JCU Singapore has a number of potential advantages:
► Leverage JCU’s global work force - Preliminary analysis suggests that administrative labour costs at JCU Singapore are ~60% of the labour costs in Australia. In addition to this, offshoring also often results in reduced overhead costs
► Increase business sustainability - Allow JCU Singapore staff to take on routine, non-complex procurement activities, enabling local staff to focus on more strategic initiatives
► Access to a greater pool of talent - Allows JCU to remain competitive as the complexity and volume of work increases and the right kind of talent becomes scarcer
►However, political implications of leveraging a global work force must be considered:
► It is critical that a robust business case is developed to support such an approach, addressing both the financial and non-financial costs/ benefits
► Following any decision, clear and early communication to staff, unions and the broader community will be vital
►Readiness to transition:
► The table below provides an overview transition readiness considerations across the P2P operating model. The most significant barriers to readiness relate to system capability and staff capacity.
EY was asked to assess whether JCU Singapore could be considered as a location for all JCU P2P Processes. In this context, the current state of purchasing at JCU Singapore was considered along with the broader state of readiness for transition. Our observations and findings follow.
James Cook University P2P
Page 30
Option to locate P2P processing at JCU Singapore (Cont.)
Element Considerations
Strategy & Governance
Using a traditional shared service approach, it would be expected that strategy and governance for the Australian campuses would be retained centrally and
locally. Therefore, Singapore’s current strategy and governance capability, is not a factor in determining transition readiness.
Policy & Process JCU Singapore has a documented procurement policy (but does not currently apply FMPM 711). On transition, FMPM711 should continue to be applied to
Australian Purchases. While, Singapore could apply its own policy locally, longer-term a single global policy (with relevant country exceptions) would be
recommended to drive synergies.
JCU Singapore has a heavy reliance on manual processes (as can be seen in Appendix D). Agreed simplified and automated process would be key to
realising the full benefits of transition. In terms of readiness JCU has two options for transition:
1. Transition P2P processes to JCU Singapore substantially as-is to achieve immediate labour savings (subject to capacity and technology capability )
and optimise processes post transition
2. Optimise the P2P processes prior to or in conjunction with transition to Singapore
This decision needs weigh the effort with optimising current P2P processes, against the risk of transferring inefficient processes, and the time value
of expected savings.
People & Organisation
The Singapore procurement function is a small operation within the CEOs office consisting of an Associate Director Operations and a Purchasing Officer and
is responsible for major purchases, with minor purchases being conducted by the business.
The strong service culture in Singapore would strongly align with and support the finance and procurement function in achieving University objectives.
However, additional Singaporean resources and training would be required to enable transition of JCU wide P2P processing to Singapore. Clear handover
points to JCU Singapore in terms of roles and responsibilities would be required to be defined as part of the transition.
Risks & Controls The Singapore and local P2P function rely heavily on manual controls (related to a lack of system functionality). The P2P controls framework could be
transitioned as is, however there is some risk associated with the manual sign off and validation of signatures. Clear delegations and systems based approval
processes would mitigate this risk to some degree. Defined rules and ideally automated controls will be required to obtain maximum benefit of transition.
Data & Technology
JCU Singapore does not currently use Spend Vision or FinanceOne technology to support its procurement function. We understand the provision of
FinanceOne to Singapore requires implementation of a Citrix solution or web based functionality, as well as resolution of Foreign exchange issues if it is to
be the global ERP. System capability is likely to be the largest barrier to the readiness to transition P2P processing to Singapore.
Recognising that often processing centres use their own systems and develop interfaces to clients systems, it is possible that JCU Singapore could use other
solutions, however, further investigation of existing and alternative systems capability and costs would be required to inform such a decision.
Performance Management
It is noted procurement performance management is more mature across the Singapore operation than local operations (including supplier performance and
evaluation and the inclusion of key result areas in staff position descriptions). On transition, clear service level arrangements would need to be established
and incorporated into relevant staff performance metrics.
James Cook University P2P
Page 31
Optimising the Procurement Operating Model
It should be noted that there is no single leading practice procurement operating model or reporting structure. However, based on JCU’s operating environment and current maturity, the following ‘to be’ procurement function structure is provided for consideration. In this model the central functions must maintain good communication with the faculties and divisions to ensure central functions remain relevant and continue to deliver value to end users.
Procurement Strategy
Strategy and
Governance
Controls and risk
management
** Where a category is faculties/division specific (eg Estates/IT ), it may be more practical to locate category management within the faculty/division rather than being managed centrally. These roles would still report to the CPO but would do so from outside the central procurement function. The role of the category manager is to own critical supplier relationships and serve as the single point of contact within the category
Shared Services
PO invoice matching
Accounts Payable
Travel and expenses
Supplier contract
compliance
Technical procurement practitioners Queensland Purchasing Accreditation Recommended, in
addition to experts in University policies and processes
Rules based process-
focused
Vice Chancellor
FaBs
Support procurement with:
Benefits tracking
Planning, budgeting and
forecasting
Financial analysis
Understanding of University processes, systems and
delegations
Chief Procurement Officer *
(or equivalent)
Leading the procurement function
Driving procurement performance
Ensuring the procurement function
effectively supports JCU in meeting its
objectives
Office of Commercial
Services
Complex tendering
Bid evaluation
Contract development &
Management
Operations
Commodity purchasing
Buying assistance
Executive Director
Finance and Resource Planning
Benefits of Structured Operating and Governance Model:
Spend leverage and aggregation
Knowledge and resource sharing
Procurement strategy and direction driven from the centre
Standardised method and process of market and supplier
engagement
Central team facilitates linking of business needs to
market and supply opportunities
Procurement Services
Quality control and
assurance
Procurement
improvement
Policy support services
Technical advice &
support
Category Management
Category management**
Appraise supplier
performance
Supply / demand
planning
Strategic sourcing
James Cook University P2P
Technical specialist
practitioners
Page 32
People & Organisation Opportunities
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
PO1 ► Clearly define end-to-end procurement process
roles, responsibilities and accountabilities
• Each process has a process owner and
defined support contacts
► Roles, responsibilities and accountability
across the end to-end P2P process are unclear
► Support service for P2P processes and/or
systems are not known
M L 0-6
Organisational Restructure
PO2 ► Clearly define organisation and reporting
structure of faculty based FaBs and
purchasing/travel officers
► Incentivising compliance and improved
procurement performance (See PM4)
► FaBs are located within faculties but report to
finance, however anecdotally there may be
pressure on FaBs in the context of allegience
to the faculty as opposed to the finance
function, procurement requirements and better
practice procurement
M L 0-6
Organisational Restructure
Performance Management
P03 ► Establish the position of CPO (or equivalent)
to provide a single point of accountability for
procurement across all JCU spend (see
example competencies and accountabilities on
following slides)
► There is a lack of capacity and accountability
for driving strategic procurement across JCU
► The strategic function is reactive and driven by
operational day to day pressures rather than
being proactive and driven by strategy
M L 0-6 Organisational Restructure
PO4 ► Introduce position specific training and
accreditation based on roles and
responsibilities. This should include regular
ongoing training in relevant subject matter and
use of key systems.
► Further information regarding Queensland
Government Purchasing accreditation is
available online at
http://www.hpw.qld.gov.au/aboutus/BusinessAr
eas/QGCPO/Pages/default.aspx
► Stakeholders consistently identified a lack of
both onboarding and ongoing training for end
users as a key contributor to inefficiencies
across the P2P function
M M 0-6
Organisational Restructure
Training to follow revised policy and
process
PO5
► Perform competency assessments, integrate
position descriptions and competency models,
building capability through recruitment, training
and accreditation
► There is a perceived lack of capacity and
capability to deliver strategic procurement
among other P2P functions at JCU
M M 6-12 Organisational Restructure
PO6 ► In conjunction with clarifying roles and
responsibilities, develop performance metrics
to incentivise compliance (See PM4)
► There is a lack of accountability and
consequences associated with failing to
comply with purchasing policies and
processes. Examples include purchasing
without a Purchase Order or necessary quotes
and failure to acquit credit cards in a timely
manner
M L 0-6
James Cook University P2P
Page 33
People & Organisation Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
P07 ► Engage staff through communication and
training and build careers and respect for
procurement within the University
► High levels of absenteeism and staff working in
acting positions exist in the procurement
function
M M 6-12
Training Plan
PO8 ► Consider increasing the scope of shared
services to further centralise common
processing activities
► A number of shared services processes remain
fragmented (e.g rceieving and receipt of
invoices)
H M 6-12
Organisational Restructure
Technology
PO9 ► Leveraging global work force opportunities
through transitioning processing to JCU
Singapore
► JCU does not take advantage of global labour
economies
H H 12+ Simplified consistent processes and
system functionality
Technology Capability in Singapore
James Cook University P2P
Page 34
Accountabilities: ► Drive whole–of-JCU Procurement improvement to realise sustainable procurement savings and achieve the JCU Corporate Procurement Plan objectives
► Drive procurement policy, governance and practice in line with JCU’s strategic objectives and business model
► Deliver benefits through the initiation of Category Management and value chain improvements
► Ensures the Procurement Function effectively supports its business customers in meeting its service delivery obligations
► Maintain effective relationships with QGCPO, other relevant organisations and industry bodies to share and integrate better practices
► Manage the JCU Procurement risk profile to be within acceptable University tolerances
► Build a high performing Procurement Team and a collaborative procurement culture across JCU
► Ensure Procurement governance and controls are embedded across JCU providing support across governance, legislation, business controls and Procurement business risk
► Embed a culture of Procurement improvement through the implementation of formal Procurement Improvement Programs aimed to deliver sustainable benefits across Procurement
► Drive the performance of a procurement business intelligence function focused on accurate analysis and generation of insights to Procurement decision making across JCU
► Develop Strategic Supplier Relationships across JCU’s supply base across understanding internal and external market conditions
► Work with business customers to drive improvement across Direct Spend to optimise Procurement and operations
Key Procurement Competencies: ► Positions Procurement within JCU
► Procurement strategy development
► Markets Procurement within JCU
► Defines governance and policy
► Sets benefits key performance indicators
► Measures benefits performance
Sample Chief Procurement Officer Accountabilities & Competencies
The Chief Procurement Officer (or equivalent) will lead the JCU Strategic Procurement Function. The CPO will be accountable for performance, driving both commercial value and operational benefits across JCU; embedding Procurement governance and controls, a culture of process improvement; and increasing capability levels across all Procurement disciplines.
James Cook University P2P
Page 36
Risks & Controls Findings
► Risks and controls are mapped and optimised
► Controls are automated and approvals workflowed based on:
► Defined and embedded delegation rules
► A single source of truth
► A risk based funds check threshold is established with monitoring via periodic variance analysis. Longer-term funds checks automated (subject to aggregation requirements)
► Approvals are streamlined where possible (e.g. single system based approval of both requisition and purchase order)
► Approval authority is considered in the context of:
► Risk and risk appetite
► Alignment with budget accountability
► Devolving most authority to the source
► PCI compliance is considered as part of the preferred supplier selection process
► Data requirements are assessed to improve data quality:
► Supporting visibility of purchases and decision making
► Reducing the risk of duplication of payment
Illustrative controls aligned to ‘to be’ processes (subject to system functionality) are included Appendix C.
► No clear link between risk tolerance and control design
► A reliance on manual controls and approvals
► The delegations framework is complex, with the register maintained in a spreadsheet, visible only to central finance staff (due to sensitivities regarding inconsistent delegations in terms of rank and “signature shopping” concerns)
► Anecdotal view that the delegations are overly burdensome and do not align with budget ownership
► Funds checks are:
► Performed for each transaction (irrespective of materiality)
► Duplicated
► May not be performed using accurate data
► There are additional and duplicated approvals driven by:
► Non-integrated manual processes and sytems
► Risk averseness and to provide comfort to senior delegates
► PCI compliance concerns create additional workload
► Current non-integrated systems, field definition and interface configuration adversley impacts visisbility, reporting and analysis
Further details regarding risk and control opportunities are identified in the Opportunity Maps in Appendix B and cross referenced with the opportunities below.
To Be State Current State
There is an absence of a clear link between risk tolerance and control design, a lack of clarity and transparency regarding delegations and a perception the procurement process is over-controlled. The P2P function places a heavy reliance on manual and detective controls, which are more expensive and less effective than automated controls. This reliance on manual controls indicates that JCU is likely underleveraging its investment in technology. There is an opportunity to optimise design of the P2P controls.
James Cook University P2P
Page 37
Risks & Controls Opportunities
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
RC1 ► Review and simplify the delegations in the
context of risk appetite with consideration given
to:
• Alignment with budget accountability
• Devolving most authority to the source
• Adjusting the limits to be GST exclusive
► Increase transparency of the delegations or
automate workflow of approvals based on the
delegation framework with clear position and
cost centre and other accounting “rules” (e.g.
capital vs. expense)
► Leading practice is a ‘single source of truth’ for
delegations
► There is a perception of over control.
However, the dollar limits within the financial
delegation framework for procurement appear
reasonable. based on Univeristy‘s size and risk
appetite and a comparison to other University‘s
► The delegtaions framework is complex and
anecdottally there is a perceptiion of a lack of
alignment with budget responsibility
► The delegations register is maintained and
updated manually in an excel spreadsheet
(maintained by name). To which only Central
Finance have access
► A pain point raised was that only two officers
have delegation to authorise transactions
greater than $1 million, and due to the
segregation of duties both, officers need to be
available. Based on the expected frequency
and urgency of such transactions no
amendment has been proposed. However, in
this context it is important “acting” roles for
these positions are kept up to date (See also
RC7)
M M 0-6 Broader Program: Delegations
Framework Project. Note: mapping
will need to occur prior to
systemising approvals
Technology: Potential Identity
Management Solution and
orchestration package can be
leveraged to automate and
integrate workflow systems
RC2 ► System based requisition with application
controls to minimise the risk of inappropriate,
incomplete and inaccurate requisitions,
reducing rework
► Easy to follow instructions (See PP1& 2) and
provision of training (See PO4 ) would be
expected to improve compliance of requisitions
► Paper based, email and the free text format of
Webreq allow for incomplete and inaccurate
requests to be submitted, resulting in additional
workload
Note: While this risk of inaccurate data is mitigated
by the review process manual detect controls are
more expensive and less efficient than automated
prevent controls.
M H 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape
James Cook University P2P
Page 38
Risks & Controls Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
RC3 ► Establish an appropriate materiality threshold
for funds checks, with greater emphasis on
review of budget to actuals at the end of the
period
► Longer-term investigate:
• Automating the funds check in systems e.g.
FinanceOne (Subject to grouped OPF funds
transfers)
• Using new BI tool for material checks
► System application and automated vendor
controls would assist in improving efficiency
(See also DT9)
► A manual check is performed to confirm funds
are available for each transaction irrespective
of materiality
► This check is performed in FinWeb, however,
delays in data transfer, acquitals, and
preapayments, as well as the treatment of
capitlised costs for certain codes mean that
these checks may not be using accurate data
► The Purchasing Officer also performs a review
to identify if the request is in line with JCUs
purchasing policy
M L 0-6
RC4 ► The approval process is system supported,
based on defined and embedded delegation
rules (with no intermediaries)
► Requisition approval is via email or a physical
signature and review.
► Spendvision workflow capability (as used in the
Travel module) is not utilised for Spendvision
Purchase Orders.
► There are varying requirement to send
requisitions and Spendvision Purhcase Orders
for approval to different parties subject to
school processes
► Additional approvals may be included:
• Segregation of duties where a requisition
and order cannot be approved by the same
delegate (see also RC7)
• Risk averse culture often results in
additional off system approvals being
obtained to provide comfort to delegates
► Anecdotally there is an informal process in one
faculty of not seeking approval for purchases of
less than $2,000 (as they are within
Purchasing Officers Delegation)
H H 6-12
Technology: Subject to JCU
Governance decision regarding
system landscape and automated
approval capability
Delegations: Broader program
streamlining and rules based
delegations
RC5 ► Remove additional funds check ► While funds availability is the responsibility of
the financial delegate, the Purchasing Officer
performs an additional funds check
M L 0-6
James Cook University P2P
Page 39
Risks & Controls Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
RC6 ► As part of supplier qualification and selection,
PCI compliance should be a criterion and
included in contracts
• In the absence of systems that support
“two factor” authentication there is limited
opportunity to gain efficiencies
• An alternative is to pay these suppliers via
EFT
► JCUs concerns regarding PCI compliance of
vendors, has resulted in inefficincies where
vendors are provided with partial credit card
details and required to contact Purchasing
Officers to obtain remaining details
M L 6-12 Strategic sourcing:
Perform in conjunction with
strategic sourcing and supplier
consolidation
RC7 ► Confirm with auditors the potential to eliminate
the requisition and purchase order second
approval with approval only required if the
requestor is a delegate
► Where a system approval occurs a Purchase
Order should be provided directly to the
supplier without additional physical
authorisation
► Current policy requires approval of a purchase
requisition, and a subsequent approval of a
Purchase Order. The policy states the same
delegate can not approve both the Requisition
and the Purchase Order. Note: This may be
driven by the requisition approvals taking place
outside of systems and workflows
► Some purchase orders are printed and signed
physically before being sent to vendors. If
approval is in the system this is an extra
process step. The audit trail should maintain
the record the approving and releasing officers.
M L 0-6
RC8 ► Remove the additional Accounts Payable
check of supplier data, and have the second
check performed by the Systems Team,
ensuring segregation of duties of Accounts
Payable processing staff from supplier file
amendment
• JCU have identified a preference that
approval of new suppliers be included in
the role of Strategic Procurement, with a
view to improving category management
and strategic sourcing and minimising
leakage
► The Systems Team perform a re-check of
supplier source data in the load file as
performed by Accounts Payable.
L L 0-6
James Cook University P2P
Page 40
Risks & Controls Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
RC9 ► Centralising goods receipting would provide
opportunities to manage and aggregate
demand, manage inventory levels and reduce
logistic costs
► As a result of the devolved processes there is
limited management of inventory as part of
procurement decisions with a tendency to be
reactive
M M 6-12 Technology: Devolved receipting
functionality and access
RC10 ► Remove additional reviews and drive
accountability (See also PM04)
► Accounts payable perform review of some of
the same information performed by Purchasing
Officers
M L 0-6
RC11 ► In conjunction PP8 & RC9 adopt a 3 way
match process
► Tolerance thresholds for matching should be
communicated and included in training of staff
► As a result of the devolved and manual
process to receive goods a two way match
occurs
► While there is a tolerance threshold for
matching in FinanceOne staff were not aware
of this with the perception that even a few
cents out would require investigation and steps
to rectify
M M 6-12 Technology: Devolved receipting
functionality and access
RC12 ► Subject to risk, remove the additional review of
Western Union file and drive accountability of
staff
Note: We understand that this may be driven by
the challenges of rectifying any errors overseas
payments.
► There is an additional review of the Western
Union payment file by the Manager Systems,
Process & Design/Manager Procure to Pay
L L 0-6
RC13 ► Acquittal timelines should be strictly adhered to
and enforced via consequences (See also
PM9)
► The bank has direct debit authority to settle
credit card balances. There is some risk in
settling these transactions before acquittal, as
charges may not be accurate
► The ongoing failure of card holders to acquit
credit cards in a timely manner in accordance
with policy. This results in data quality issues
(See DT7)
M M 0-6 Authority to suspend and cancel
cards is being endorsed by
University Senior management
RC14 ► Process invoices through FinanceOne without
a retrospective Purchase Order, subject to
driving compliance through performance
measures and monitoring
► There is anecdotal evidence of Purchase
Orders being created after goods have been
purchased and receipted
M L 0-6
James Cook University P2P
Page 41
Risks & Controls Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
RC15 ► Optimise controls by defining a clear link
between controls, risks and risk appetite and
automating where possible
► There is no clear link between controls and
risks
M M 6-12 Technology: Subject to JCU
Governance decision regarding
system landscape- perform in
conjunction with implementing
system functionality
James Cook University P2P
Page 43
Data & Technology Findings
► The current good practices will be retained:
► Performing Accounts Payable settlements via EFT(with no settlements via cheques)
► Existing automated controls in FinanceOne
► A broad base of employees across JCU have appropriate access to minimise manual requisitions, automate goods receipt and support timely processing
► Consistent with JCU’s IT strategy to maximise the functional footprint of existing strategic systems, where FinanceOne meets JCU’s needs, and is cost effective, JCU should add functionality to support end-to-end P2P process, including:
► Quotation and tender management
► Contract management
► Initiation of procurement
► e-procurement and integrated catalogues (recognising diverse needs purchases in a University environment)
► Automated workflow
► Scanning and potentially digitised functionality
► Web-based functionality upgrade
► Where FinanceOne functionality does not meet needs or is not cost effective, perform a market scan to determine whether to invest in legacy systems and interfaces or to identify alternative system solutions that can be integrated with FinanceOne
► Data warehouses will use standard forms across JCU supporting procurement decision making and performance management
► Purchasing processes rely on a number of manual processes including:
► Paper based forms and scanning
► Rekeying of data between systems
► Emails to obtain approvals
► There are non-integrated systems used in the P2P process resulting in inefficiencies. Systems include:
► Webreq - a web based requiistion form
► Spendvision - used for travel and credit card acquitals
► FinanceOne - the Finance system
► MEX - for maintenance requests and work-order management
► There are underlying access and forign currency reporting constraints meaning JCU Singapore cannot currently use FinanceOne
► Spendvision is leveraged differently across the University, with larger faculties using spendvision to monitor the progress of purchases, with smaller faculties relying on email folders
► Data quality is adversely impacted due to limited system validation (including free text) and integration. There is also a lack of understanding of the data flow and requirements for the end-to-end process
Further details regarding data and technology opportunities are identified in the Opportunity Maps in Appendix B and cross referenced with the opportunities below.
To Be State Current State
JCU P2P has a reliance on manual processes and non-integrated technology, suggesting an underleveraging of and underinvestment in system capability. This lack of integration impacts data quality and availability to support visibility, reporting and analysis of purchases. A lack of technology has also resulted in Spendvision being leveraged differently by different organisational units.
James Cook University P2P
Page 44
FinanceOne Functionality
James Cook University P2P
Preliminary discussions were held with TechnologyOne to understand P2P functionality offered within FinanceOne. The figure below (sourced from TechnologyOne) illustrates the FinanceOne procurement solution. Those modules for which JCU holds a licence are circled in green, with the additional P2P modules discussed with FinanceOne circled in yellow.
While further investigation of the functionality is required by JCU, the table on the following page provides an overview of the additional P2P functionality that could be leveraged by JCU, as discussed with a FinanceOne representative.
Initial costing of modules as provided by TechnologyOne to JCU have been included in the table on the following page. Note: TechnologyOne have offered JCU a 10% discount on implementation costs (across P2P and other functionality being investigated by JCU) which has not been applied on the following page.
Page 45
FinanceOne Functionality (Cont.)
James Cook University P2P
Finance One Module Functionality Cost ($)
Purchasing While JCU holds a licence for the purchasing module there is additional functionality that could be leveraged to gain efficiencies and
improve JCU P2P:
► Functionality to support devolved procurement (See My Modules below)
► Increased automation of approvals and delegation limit checking via workflow (See Workflow Maintenance)
► Application controls via the implementation of a catalogue
► We further understand that FinanceOne is looking to move to web enabled functionality some time in the middle of next year. This
would be expected to improve ability to devolve access .
N/A
Consolidated Purchase
Requisitions
Consolidation of multiple requisitions from a supplier into a single Purchase Order. This would be expected to increase efficiency by
reducing the number of purchase orders and invoices, as well as potentially improving use of supplier volume discounts. Note it was
confirmed the Purchase Order would still contain detail to allow supplier to deliver to multiple locations.
Price not provided
Purchasing Quotations
Provides an application control to embed policy requirements for quotes at the point of requisition. It supports Request For Quote
creation (using a template), distribution, supplier quotes entry and quotation selection, as well as capture of data to monitor reasons for
exceptions to policy. The module can be workflowed. Further analysis of spend and the number of quotes sought annually by JCU is
required to inform the cost/benefit decision regarding this module. Devolved use would require the My Purchasing Quotations module
(see below).
Price: $15,664
Implementation: $10,100
Annual Maintenance: n/a
My Modules The my modules support devolved use of modules. The use of these modules would provide users across JCU capability to enter
requisitions directly to the system, providing application controls and the visibility required to track purchases. The efficiencies gained
through using these modules need to be analysed further in terms of the cost /benefit to JCU. Note: Although FinanceOne have
indicated a per user licence fee, negotiating alternative licence arrangements would be recommended, to provide flexibility.
Licenced on a named user basis
Contracts A contract management module and repository supporting tracking and monitoring of contracts including qualifications management,
such as insurances and variation management . The module can be workflow enabled and prompt users when actions are required.
There is also control capability to compare transactions processed against contracts to monitor contract compliance (e.g. price and
volume discounts).
Price: $43,294
Implementation: $28,535
Annual Maintenance: $9,741
Electronic Procurement Interfaces to supplier catalogues, punches out, returns a cart, Electronic Data Interchange (EDI) transmission of both order to the
supplier and receipt of invoice, and auto match. However, this is dependant on suppliers systems format being compatible and
allowing JCU access. On this basis it is thought that given JCUs market position, there may not be sufficient supplier benefit to warrant
investment in electronic procurement. As such it is recommended further consideration be given to collaborative solutions with other
universities.
Web Catalogue
Price: $7.832
Implementation: $8,055
Annual Maintenance: $2,203
Workflow Maintenance
(Connector)
Standard FinanceOne workflow is in use at JCU and allows for basic delegation approvals . The connector would allow for more
complex delegation rules to be embedded as a system control. This would require the mapping of delegations in the system which
could be quite complex and time consuming, potentially requiring customisation of the software.
Price: $15,664
Implementation: $14,285
Annual Maintenance: $3,524
Purchase Cards Similar functionality to Spendvision to support download of credit card transaction and acquittal, leveraging FinanceOne supplier
information and account codes. This could assist in improving data quality for analysis of purchase transactions. The system does
currently link credit card transaction to requisitions or purchase orders. However, it should be noted that the requirement to raise a
requisition for credit card spend is recommended to be reconsidered by JCU, as raising requisitions and purchase orders eliminates
the efficiencies of purchasing by card.
Price: $15,664
Implementation: $12,125
Annual Maintenance: $3,524
Page 46
Data & Technology Opportunities
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
DTI ► System visibility and access to relevant
students to assist in reducing work load and
on-boarding of research students (See PO4)
► Longer-term requisition system allows for
attachment supporting documentation, includes
system validation and inbuilt help
► Webreq location and functionality result in
additional workload for Purchasing Officers:
• Webreq while used by research students is
hidden from student view
• Webreq does not include the email address
of the party
• Quotes and supporting documents cannot be
attached until after a requisition submission
requiring additional effort to scan email and
combine pdfs in subsequent steps
• There is use of free text and no inbuilt
validation
• It is not considered intuitive by users and
there is no inbuilt guidance (Students
require significant assistance)
M M 6-12 Technology: Subject to technology
landscape decisions determine the
cost benefit of investing in Webreq
vs. other integrated system
capability
DT2 ► Consider system solution to monitor credit card
transactions and commitments and regular
reports to identify items requiring action
► JCU priorities and policy to be confirmed:
• Preferring the efficiencies of purchasing on
card, not raising a purchase order and
accepting a lack of visibility of commitments
• Preferring visibility of commitments and using
FinanceOne for all Purchase Orders (given a
requisition and Purchase Order is being
prepared anyway), with only minor one-off
non-preferred supplier transactions
purchased on card
► Solutions could include:
• Capturing data from requisitions
• Using existing IT help desk solutions to track
the progress of purchases
• Consider FinanceOne catalogue and e-
procurement functionality and associated
refinement of credit card use policy
► Spendvision is used differentially:
• FSE and MHMS raising Purchase Orders in
Spendvision to provide visibility of requisition
progress and follow up action required- staff
use the screen view which provides graphics
• Faculties with smaller spend do not use
Spendvision, but use email folders as a way
of tracking purchases
Note: The FSE & MHMS process of raising of
a Purchase Order mitigates some of the
efficiencies of purchasing via credit card.
► There is no record of these transactions in
FinanceOne until credit cards are acquitted
and in the case of smaller faculties no record in
a system at all until acquitted. This represents
a significant challenge in identifying
commitments, particularly as part of the year
end process.
H M 6-12
Technology
Governance: A decision is required
between the importance of
efficiency versus visibility of
commitments to JCU
James Cook University P2P
Page 47
Data & Technology Opportunities
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
DT3 ► Longer-term consider a fully integrated end-
to- end system solution including quote tender
and contract management systems, as well as
reconsidering integrating MEX
Note: We understand previous investigation by
JCU considered MEX integration was not feasible
► Quotes and tenders are managed manually.
► There is currently no contract management
system adopted by JCU. Anecdotally some
contracts can not be located
► There is no integration between MEX (used for
maintenance and work orders) and
FinanceOne resulting in duplication of effort in
scanning and recording invoices as paid
M H 12+ Technology
DT4 ► Leveraging technology to dispatch Purchase
Orders to suppliers automatically. Investigate
the potential to:
• Include multiple address fields in
FinanceOne creditor files
• Add additional information to Purchase
Orders via free text fields
• Amend standard terms and conditions text or
consider different types of purchase orders
in FinanceOne
► Purchase Orders generated from FinanceOne
are not automatically sent to suppliers. They
are selectively emailed. Reasons include:
• A lack of trust of FinanceOne
• Purchase order contain standard payment
terms and conditions not applicable to all
suppliers
• Additional information not in the purchase
order is required to be sent
• The FinanceOne creditor files do not contain
the sales area contact details
M M 6-12
DT5 ► Determine if workaround for split orders and
partial receipting has any implications on
reporting and analysis:
• If so work with TechnologyOne to identify
and implement a solution
• If there is no impact, consider removing the
goods option if this results in rework
► Invoices are processed in FinanceOne as a
“good “ or “service” . However all Purchase
Orders requiring a “carry on” are processed as
a service, due to the functionality for goods
not working, resulting in the need to cancel and
re-raise purchase orders and process invoices
Note: We were unable to ascertain if this election
has any impact on data quality and reporting.
L M 6-12
James Cook University P2P
Page 48
Data & Technology Opportunities (Cont.)
Ref Opportunity Issue Impact Effort Time
Frame Dependencies
DT6 ► Information is captured in a way that allows for
visibility to perform analysis and inform
decision making
• Determine how to best use the 3 narration
filelds in FinanceOne
• Modify interfaces (subject to technology
decisions)
• Based on agreed use of fields develop
custom reports to support analysis
► The current interface configuration between
Spendvision and FinanceOne impacts data
quality and analysis. Key issues include:
• A 40 Character narration limitation, resulting
in multiple lines in Spendvision Purchase
Orders being condensed to a single 40
character line.
• Limited ability to perform analysis of spend
by supplier
• Only one attachment can be loaded to
FinanceOne, requiring scanning and
combining PDFs
• Not all information collected at requisition is
transferred used or entered in the finance
system e.g. who was the purchaser
M M/L 0-6
DT7 ► System solution to better capture or allocate
un-acquitted credit card transactions
leveraging information already available
► Credit cards transactions are coded to default
organisational units and expense accounts
until acquitted, impacting visibility of spend,
budget review and other analysis
H M 6-12
DT8 ► Single University-wide supplier file would assist
in vendor consolidation and associated
advantages
► FSE & MHMS each maintain an Excel supplier
data base for non FinanceOne vendors and
are looking to move web logins and passwords
to a locked box
H M 0-6
DT9 ► Review FinanceOne and Spendvision
functionality with vendors (including potential
for global rollout)
► Where functionality does not meet JCU
requirements undertake a market scan with a
view to developing an integrated environment.
► Existing systems functionality may not be fully
leveraged, or meet JCU‘s needs
H M 0-6 Technology: As a first priority a
Governance decision is required
regarding the system landscape
James Cook University P2P
Page 50
No official performance management framework for the procurement function exists at JCU. KPIs for both the procurement function and individuals do not align to the procurement plan and are not translated into actions at the employee level. Supplier performance and contract compliance is not officially managed and procurement benefits realisation is not tracked.
Performance Management
► A performance management framework that directly links to the Corporate Procurement Plan and Business Strategy:
► Performance is measured by KPIs driven by both qualitative and quantitative metrics fully integrate with overall business performance KPIs
► Monitor procurement performance on a periodic basis using a balanced scorecards and /or dashboards
► Procurement function KPIs are translated into actions down to employee level linking to KPIs of employees:
► Regularly review employee KPIs and provide timely feedback
► External benchmarking is used to identify performance gaps and set target performance levels:
► Performance gaps identified are reviewed against best practice and opportunities assessment completed to understand potential benefits
► Supplier performance is monitored regularly for compliance to contracts and service level agreements:
► A pre-populated balanced scorecard with agreed metrics and calculation logic should be built into key supplier contracts
► Benefits that are forecast and captured as a result of strategic sourcing and other procurement initiatives are tracked through to realisation
► Maverick spending and policy compliance is monitored regularly with process exceptions escalated for analysis and mitigation
► Currently JCU lacks a robust performance management framework and a set of performance metrics that relate to both the procurement function and individual employees
► Availability and quality of data to track performance is poor
► Lack of knowledge of roles, responsibilities and accountabilities makes it hard for procurement staff to know what they are responsible for. Clarity of roles and responsibilities will incentivise staff compliance and increase accountability
► No official supplier performance management is being carried out:
Contract compliance is unknown
Service levels and customer wiat time is unquantified
Preferred suppliers lists are not developed using supplier performance data
► No benchmarking is incorporated in planning and opportunity assessment for performance improvement across the procurement function
► Currently, JCU does not forecast, capture or track the realisation of benefits associated with strategic sourcing and other procurement savings initiatives
► Despite the move to a service culture customer and supplier satisfaction is largely unknown as JCU performance is not evaluated from a stakeholders perspective
To Be State Current State
James Cook University P2P
Page 51
Performance Management Opportunities
Ref Opportunity Issue Impact Effort Time Frame
Dependencies
PM1 ► Develop procurement function KPIs that link to
procurement plan and business strategy
► JCU does not have a well documented
procurement plan that links to overall strategy
H M 0-6 Strategy: Procurement plan linked to business strategy
PM2 ► Introduce a performance management process
and process owner
► JCUs procurement function performance is not
monitored
H M 0-6 Organisational Restructure
PM3 ► Develop balance scorecards incorporating
procurement function KPIs to measure
performance
► Could use a dashboard to ensure regular
review
► Staff feel the objectives of the procurement
function are not clear
H M 0-6 Data quality
BI Capability
PM4 ► Develop employee role KPIs that align to
delivering KPIs of the procurement function
and incentivise compliance
► Procurement staff targets are not aligned to a
procurement or business strategy
H M 0-6 Organisational Restructure Procurement plan and KPIs
PM5 ► Develop supplier performance management
framework and metrics
► Begin collecting quantitative and qualitative
data for key suppliers
► Include requirement for suppliers to report
agreed performance metrics including benefits
tracking as part of contract for supply
► Supplier performance is not monitored
► Suppliers are not held to account for under
performance
► Preferred supplier lists are not maintained
M M 6-12 Systems functionality for meaningful data collection
PM6 ► Incorporate external benchmarking review to
understand opportunities for improvement
► JCU procurement function is not compared to
best in class practice
M M 6-12 Data quality
PM7 ► Review the quality of the data required to
measure KPIs and supplier performance
• Consider longer-term leveraging BI
Functionality
► Performance analysis is limited as a result of
poor quality and unavailability of data
H M 0-6 ongoing
BI Project: Currently this will only address strategic reporting
Data quality: Incorporate in system design and reporting
PM8 ► Incorporate benefits realisation tracking into
the performance framework for key categories
► Benefits captured as a result of strategic
sourcing and other procurement initiatives are
potentially being eroded away as a result of
lack of management
M M 6-12 Opportunity assessments and strategic sourcing for spend categories
PM9 ► Strictly enforce suspension and cancellation of
credit cards
► A personal liability could be enforced for users
who do not acquitt cards on a timely basis
► Credit cards are not acquitted on a timely
basis resulting in spend being inaccurately
accounted for in the University's ledger
M M 0-6 Authority to suspend and cancel cards being endorsed from University senior management
James Cook University P2P
Page 52
Suggested Performance Metrics Procurement Function Metrics and Supplier Metrics
Example procurement function performance metrics
Number of purchase orders processed per procurement function FTE
Number of invoices processed per accounts payable FTE
Number of T&E reimbursements processed per accounts payable FTE
Total purchase value per procurement function FTE
Total cost per procurement function FTE
Cycle time in days to convert a purchase request into an approved purchase order
Cycle time in days from receipt of invoice until approved and scheduled for payment
Cycle time in days to approve and schedule T&E reimbursements
Cycle time in days to resolve an invoice error
Number of invoices without a Purchase Order
Percentage of invoice line items that are matched the first time
Number of active vendors in the master file per $1 million of purchases
Example supplier performance metrics
Product/service quality
Service Level
Correct Quantity
Delivered on-time
Customer wait-time (CWT)
Cost of goods/service
Savings/ benefits realisation
Level of adoption of systems (eg EDI)
Willingness to collaborate/share information
Level of certification
Ability to respond to unexpected demand or emergencies
Support and customer service
The following are examples of metrics used to measure both procurement function performance and supplier performance. It is important that JCU aligns its performance metrics with both the procurement strategy and University business plan to ensure KPIs drive behaviour towards University objectives and vision.
James Cook University P2P
Page 53
Sample Performance Management Scorecard
►Consumer satisfaction
index
►Vendor satisfaction
index
►Sector skills index
►Capability gap audit
►Training and
development index
►Retention rate –
procurement staff
►Staff satisfaction
survey
►Alignment of plans to
Category
►Timely execution of
procurement event
►Average cost of
procurement activity
►Value added productivity
Balanced Scorecard Perspectives
6.0 Innovation 2.0 Value 3.0 Capability and
Development
4.0 Effectiveness and
Efficiency 1.0 Stakeholders 5.0 Quality
► Service satisfaction
► Customer feedback
► Vendor satisfaction
► Procurement capacity
► Sector skills inventory
(including accreditation)
► Staff satisfaction &
retention
► Process effectiveness,
efficiency and economy
► Proportion of Category
Plans in place
► Procurement cycle times
► Procurement cost
► ROI
► Sector spend
► Forecast spend
► Sector savings
► Cost avoidance
► Leakage reduction
► Controls
simplification
► Procurement policy
compliance
► Demand
management
► Alternate
sourcing
strategies
► Industry
innovation
Critical Success Factors (CSFs)
►ROI factor
►Spend +/- 5%
►Spend under contract
►Savings +/-10%
►Avoidance +/-10%
►Reduction of
duplicate or un-
needed controls
►Orders made
through SRM
►PO compliance
►Demand reduction
►Sourcing through
alternative channels
►Uptake of innovative
solutions offered
Balanced Scorecard Measurements
James Cook University P2P
Page 54
Sample Supplier Performance Management Scorecard
► Contractual cost variances
► Product/deliverable cost
variances
► Total cost variances
► Costs against industry
benchmarks
► Invoice accuracy
► Terms of payment
► Product/deliverable quality
► Delivery in full (quantity)
► Need for returns/rework
► Risk management processes
► After sales service
► Value add
► Guaranteed product supply and service
level agreement
► Change management processes
► Scalable and flexible design
► Level of certification/qualifications
► Change of personnel
► Capability fit
► Ability to mobilise resource
► Turnover/absence rates
► Total spend on/offshore
► Perceived knowledge sharing
► Timesheet accuracy
► IR/provider headcount ratio
Balanced Scorecard Perspectives
2.0 Process 3.0 Quality 4.0 Personnel* 1.0 Finance 5.0 Relationship
► Total cost of supply
► Payment terms
► Value for money
► Product/service fit
► Consistent product/service
► Quality assurance
programs
► Additional value
► Personnel consistency
► Cultural fit
► Teaming
► Proficiency
► Frequency of delivery
► Flexibility/adaptability
to change
► Efficient effective
processes
► Industry compliant
processes
► Supplier collaboration
► Investment/alignment
with University and its
objectives
► Long term, value adding
relationship
► Willingness to share risk
Critical Success Factors (CSFs)
► Outcome requirements
► Quality review processes
► Ease of change requests
► Delivery delays
► Customer wait time on late deliveries
► Ability to react to unexpected
demand or emergencies
► Invoice disputes
► Use of industry standards
► Disruptions to business as usual
► Sustainable local processes
► Overall relationship
► Performance ratings
► Satisfaction ratings
► Number of issues raised
► Collaboration metrics
► Confidence to deliver
► Strength of relationship over
competitors
Balanced Scorecard Measurements
* This critical success factor specifically relates to service delivery
James Cook University P2P
Page 56
Sign-off
Signoff Authority Version Approval Comments
Draft version 1
James Cook University P2P
Ernst & Young LLP
Assurance | Tax | Transactions | Advisory
About Ernst & Young
Ernst & Young is a global leader in assurance, tax, transaction and advisory services. Worldwide, our 167,000 people are united by our shared values and an unwavering commitment to quality. We make a difference by helping our people, our clients and our wider communities achieve their potential.
Ernst & Young refers to the global organization of member firms of Ernst & Young Global Limited, each of which is a separate legal entity. Ernst & Young Global Limited, a UK company limited by guarantee, does not provide services to clients. For more information about our organization, please visit www.ey.com
© 2013 Ernst & Young LLP Published in India. All Rights Reserved.
This publication contains information in summary form and is therefore intended for general guidance only. It is not intended to be a substitute for detailed research or the exercise of professional judgment. Neither EYGM Limited nor any other member of the global Ernst & Young organization can accept any responsibility for loss occasioned to any person acting or refraining from action as a result of any material in this publication. On any specific matter, reference should be made to the appropriate advisor
Page 59
Stakeholder Engagement
Date Stakeholder Department Role Context
11/11/2013 Susan Kinobe Financial & Business Services Manager, Finance Teams Kick-off meeting
11/11/2013
Tom Te Whaiti Finance & Resource Planning
Program Manager (Enablers)
Program and project briefing incl interrelationships with other projects
11/11/2013 Iesha Stewart David Eaton
Commercial Services Commercial Services
Senior Procurement Officer Manager, Commercial Services A/Director, Commercial Services
30 min pain-point discussion
11/11/2013 Emma Griffiths Financial Reporting & Corporate Services
Senior Finance Officer 30 min pain-point discussion
11/11/2013 Kasey Chapman Penny Skerritt
Financial & Business Services Financial & Business Services
Manager. Finance (FSE) Team Leader, Purchasing & Travel (FSE)
30 min pain-point discussion
11/11/2013 Lisa Iafano Financial & Business Services A/AP Team Leader 30 min pain-point discussion
11/11/2013 Jess Neilson FaBS SS - FMH&MS Team Leader - Purchasing & Travel 30 min pain-point discussion
11/11/2013 Rachel Lowe Financial & Business Services Manager, Finance (Divisions) (Cairns) 30 min pain-point discussion
12/11/2013 Petrina Jones Financial & Business Services Manager Systems, Process & Design | Manager Procure to Pay
30 min pain-point discussion
James Cook University P2P
Page 60
Stakeholder Engagement (Cont.)
Date Stakeholder Department Role Context
13/11/2013 Kasey Chapman Penny Skerritt Lisa Iafano Rachel Lowe Patricia Brand Petrina Jones Sonya van Bremen Robyn Fallon Matthew Joyce Susan Kinobe Tom Te Whaiti Kelvin Liu ( Apology) Glen McGregor (Apology) Geoff Murray (Apology)
Financial & Business Services FaBS SS - FSci&Eng Financial & Business Services Financial & Business Services Finance & Resource Planning Financial & Business Services School of Medicine & Dentistry Estate Office Estate Office Financial & Business Services Finance & Resource Planning Singapore Campus Systems Process & Design Planning & Development
Manager. Finance (FSE) Team Leader, Purchasing & Travel A/AP Team Leader Manager, Finance (Divisions) (Cairns) Executive Director Manager Systems Process & Design/ P2P School Manager Deputy Director Deputy Director, Planning & Develop Manager, Finance Teams Program Manager (Enablers) Associate Director Operations Snr Business Analyst (Business Review & Improve) Manager, Capital Projects
Initial planning workshop
15/11/2013 Penny Skerrit FaBS SS - FSci&Eng Team Leader, Purchasing & Travel Walkthough Process
15/11/2013
Vicki Hamilton Tim O'Dea
Corporate Planning & Perform Corporate Planning & Perform
Director, Corporate Planning & Performance Project Manager, Business Intelligence
Scope of the BI Project
15/11/2013
Robyn Fallon Matthew Joyce
Estate Office Estate Office
Deputy Director Deputy Director, Planning & Develop
Walkthrough Procurement Estate Office
18/11/2013 Jonathan Churchill Information Technology & Resources Director, IT & R Finance Technology landscape
James Cook University P2P
Page 61
Stakeholder Engagement (Cont.)
Date Stakeholder Department Role Context
18/11/2013 Lisa Iafano Trisha Flemming Emma Griffiths (Apology) Jonathan Edwards (Apology) Christine Birnie Ashlea Titasey Jess Nielsen Penny Skerrit Leonie Pinches Renee Chanthagoon
Financial & Business Services Financial Operation & Servcies Financial Reporting & Corporate Services Financial Reporting & Corporate Services Financial Reporting & Corporate Services FaBS SS- Divisions FaBS SS - FMH&MS FaBS SS - FSci&Eng FaBS SS - FAE&SS FaBS SS FLB&CA
A/AP Team Leader Team Leader, Purchasing & Travel Senior Finance Officer Finance Officer Finance Officer Client Services Officer Team Leader - Purchasing & Travel Team Leader, Purchasing & Travel Client Services Officer Finance Officer
Improvement workshop to confirm understanding of current state and inform design of ‘to be’ state
19/11/2013
Susan Kinobe Petrina Jones
Financial & Business Services Financial & Business Services
Manager, Finance Teams Manager Systems Process & Design/ P2P
Feedback and Validate Improvement Workshop Feedback and Validate Improvement Workshop
19/11/2013 Trisha Flemming Financial Operation & Services Team Leader, Purchasing & Travel Delegations
20/11/2013
Lisa Iafano Danielle Walsh Lacie Whitehouse
Financial & Business Services Financial Operation & Services Financial Operation & Services
A/AP Team Leader Client Service Officer Client Service Officer
Accounts Payable Walkthough
20/11/2013 Petrina Jones Financial & Business Services Manager Systems, Process & Design | Manager Procure to Pay
P2P System Functionality and Future Plans
James Cook University P2P
Page 62
Stakeholder Engagement (Cont.)
Date Stakeholder Department Role Context
20/11/2013 Emma Griffiths Financial Reporting & Corporate Services Senior Finance Officer Capital Acquisitions Process
25/11/2013 Kelvin Liu Vinabelle Hermoso
Singapore Campus Singapore
Associate Director Operations Manager, Purchasing
P2P Process Singapore
25/11/2013 Penny Skerrit FaBS SS - FSci&Eng Team Leader, Purchasing & Travel Clarify workflow Spendvision
28/11/2013 Susan Kinobe Financial & Business Services Manager, Finance Teams Project update and clarification of brief and timing
29/11/2013
Robyn Fallon Vicki Scott Alex McClure (Apology) Bhanuka Ratnayake
Estate Office Construction & Maintenance Construction & Maintenance Construction & Maintenance
Deputy Director MEX System Assistant Supervisor Construction & Maintenance Building Information Systems Administrator
Discussion MEX process and integration with Purchasing Process
3/12/2013 David Eaton Commercial Services Manager, Commercial Services A/Director, Commercial Services
Discussion of Strategic Purchasing
4/12/2013 Susan Kinobe Financial & Business Services Manager, Finance Teams Teleconference University of New England to discuss P2P Finance Functionality
10/12/13 Susan Kinobe Tom Te Whaiti Craig Butcher
Financial & Business Services Financial & Business Services Commercial Services
Manager, Finance Teams Program Manager (Enablers) Manager, Strategic Procurement
Page turn of ‘to be’ state prior to Validation Workshop
James Cook University P2P
Page 63
Stakeholder Engagement (Cont.)
Date Stakeholder Department Role Context
11/12/13 Susan Kinobe Petrina Jones Craig Butcher
Financial & Business Services Financial & Business Services Commercial Services
Manager, Finance Teams Manager Systems Process & Design P2P Manager, Strategic Procurement
Webex with FinanceOne re Functionality
12/12/2013
Penny Skerritt Lisa Iafano Rachel Lowe Patricia Brand Petrina Jones Sonya van Bremen Susan Kinobe Tom Te Whaiti Kelvin Liu Vinabelle Hermoso Glen McGregor Craig Butcher Kasey Chapman (Apology) Robyn Fallon (Apology) Matthew Joyce (Apology) Geoff Murray (Apology)
Financial & Business Services Financial & Business Services Finance & Resource Planning Financial & Business Services Financial & Business Service School of Medicine & Dentistry Financial & Business Services Finance & Resource Planning Singapore Campus Singapore Campus Systems Process & Design Commercial Services Financial & Business Services Estate Office Estate Office Planning & Development
Team Leader, Purchasing & Travel A/AP Team Leader Manager, Finance (Divisions) (Cairns) Executive Director, FRP Manager Systems Process & Design P2P School Manager Manager, Finance Teams Program Manager (Enablers) Associate Director Operations Purchasing Officer Snr Bus Analyst (Bus Review & Improve) Manager, Strategic Procurement Manager. Finance (FSE) Deputy Director Deputy Director, Planning & Develop Manager, Capital Projects
To be State validation workshop
13/12/13 Susan Kinobe Petrina Jones Craig Butcher
Financial & Business Services Financial & Business Services Commercial Services
Manager, Finance Teams Manager, Capital Projects Manager Systems Process & Design P2P Manager, Strategic Procurement
Teleconference University of South Australia to discuss P2P Finance Functionality
James Cook University P2P
Page 65
Opportunities – Purchase Requestion, Process PO, Submit to Vendor (Minor <$5k)
James Cook University P2P
Purchase Requisition, Process PO, Submit to Supplier (Minor <$5K)
FaBS
Pur
chas
ing
Off
icer
Requ
esto
r (S
taff
/St
uden
t)Su
pplie
rPu
rcha
sing
Del
egat
eFi
nanc
ial D
eleg
ate
(or
Nom
inee
)
Purchasing need <$5k
Prepare RequisitionWebreq/Paper/
Email purchase order to supplier/ or
web purchase
Authorised by Financial
Delegate and complies?
Authorised by Financial
Delegate and complies?
Within POs delegation limit?
Yes
Yes
Purchase Order Received
Need for purchase and
funds available?
Yes
Raise Purchase Order In Spendvision
(FSE & MHMS only)
No
Yes
Authorised by Purchasing Delegate
No
Process Purchase
Order
PP3
DT1
Vendor Accepts Cr Cards
Yes
Yes
RC 3
RC2
Raise Purchase
Order
RC 4
PP4
DT2
PP5
RC 6
RC 4
YesFunds available
RC 5
Yes
No
Email notification of purchase order status received
Email requestor to notify purchase
order status
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
Page 66
Opportunities – Purchase Requestion (Major <$5k)
James Cook University P2P
Purchase Requisition (Major > $5k)
FaB
s P
urc
has
ing
Off
icer
Req
ues
tor
(Sta
ff o
r st
ud
ent)
Fin
anci
al D
eleg
ate
(or
No
min
ee)
Purchasing need >$5k
Prepare Paper requisition or
email and attach supporting documents
Is there a Preferred Supplier?
Obtain quotes:- $5-$20k 2 written quotes-$20-$200k 3 written quotes and evaluation
Is purchase >$200k or high
risk?
Liaise with CSO and develop written
procurement plan and RFT
Yes
PP3
No
Yes
No
Need for purchase and
funds available?
RC 3
Authorised by Financial
Delegate?
DT3
Yes
DT1
RC4
PP6
Authorised by Financial
Delegate and complies?
Funds availableYes
Raise Finance One Purchase
Order
RC 5
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
Note: Supporting Documents IT includes IT approval – Maintenance MEX requisition
Page 67
Opportunities – Purchase Order (Major <$5k)
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
James Cook University P2P
Page 68
Opportunities -Creditor Setup and Maintenance
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
James Cook University P2P
Page 69
Opportunities – Receive Goods/ Services and Process Invoice
James Cook University P2P
Receive Goods/Services & Process Invoice
Acc
ou
nts
Pay
able
Req
ues
tor
(Sta
ff o
r St
ud
ent)
Sup
plie
rFi
nan
cial
Del
egat
eFa
Bs
Pu
rch
asin
g O
ffic
er
Run Document Checking Report
(Batch)
Process Purchase
OrderGoods sent/service
performed
Receive goods/service
Payment authorised?
PP 8
Yes Enter invoice
and attach scan PO in
FinanceOne
Invoice matches goods/service %
complete ?
Yes
Resolve issue
No
Auto 2 way Match
PP 9
RC 11
Pass Matching
RC 9
Issue Payment
Resolve and determine matched
amount
Less than $5k and supplier accepts Cr
Card? Finance OnePO Previously
Raised
Need for purchase and
funds available?
Authorise Request for PaymentSign or email
No
Enter invoiceand attach scan of
supporting documents
Second Officer (subject to $ limits)
approves and posts (Batched)
No
Yes
DT 5
PP10
Receive Invoice email or hard copy
Sign invoice ok to pay and scan and
email or send email approval
Yes
Submit Invoice
PP 8
Receive notification
Requisition raised and
Order placed with supplier ?
Email invoice and confirm good/
service received
Request for Payment
Required?
Yes
Credit Card
Acquittal
Confirm Card Charged
Yes
Yes
Complete Request for Payment, Sign Invoice OK to Pay
scan and email
No
No
Authorisation to pay received
No
Yes
Combine invoice and approvals and
Yes
Email invoice and confirm good/service received and
advise Request for Payment provided
PP 6
RC 10
No
Is vendor setup?
Creditor Setup
No
Yes
No Pay by Credit Card
Process Purchase
OrderLegend:
Process Decision Off Page Ref OpportunityAlternative
Process
Page 70
Opportunities – Issue Payment
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
James Cook University P2P
Issue Payment (FinanceOne)
Acc
ou
nts
Pay
able
Receive Good/
Services
Generate Creditor Selection Report Based on Type of Payment Run and
Dates
Auto email of remittance (if email
in system)Correct amount
and Type
Save onto systems drive and generate
EFT File
Import File (ComBiz)
Dual Authorisation
Finalise FinanceOne Payment Run
Domestic
ForeignImport File
(Western Union)
Dual Authorisation plus additional
reviewEnd
RC 12
Page 71
Opportunities – Credit Card Acquittal
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
James Cook University P2P
Credit Card Acquittal
Ver
ifie
r
Car
d h
old
er
(FaB
P
urc
has
ing
Off
icer
or
End
U
ser)
Syst
ems
Load Credit Card Transactions
Scan Invoices
Match all supporting
documentation(Purchase Order,
Invoice) & Code
SubmitExceeds
Threshold
Authorise Acquittal
Yes
Receive Goods/Services
RC 13
EndAutomatic upload journal of acquittal
No
DT6
DT7
Page 73
Overarching Decision Tree (Current Process)
James Cook University P2P
Identify Need
Is there a legitimate need
for the purchase?
Yes
No
Is there a preferred supplier?
Raise Paper Purchase
Requisition and Attach Quotes and Financial Approval
Yes
Is purchase for >$5k and <$20k?
No
Requisition for purchase of IT?
Liaise with ITYes
Requisition for Estate Office work order purchase?
Yes
Obtain 2 written quotes
Is purchase for >$20k and <$200k?
Yes
Obtain 3 written quotes
Yes
Is purchase for less than <$5k?
No
Does vendor accept credit
card?
Is there a standing offer
arrangement in place?
Supplier receives order
Purchase with Credit Card directly
with Supplier
Raise MEX Request and Liaise with Estate Office
Has financial approval been
obtained?
Will the requisition pose a risk to Health
& Safety
Perform Risk Assessment
(Riskware or Chem Watch)
Reference delegations register and obtain Financial delegates approval
No
Yes
Yes
No
Is the purchase >$200k or high
risk?
Develop written procurement plan and RFT/RFP with
CSO
Yes
No
No
No
FaBs Raise Purchase Order in
FinanceOne
Submit to FaBs
Raise WebReq Requisition and
Provide Approval
Yes
Does Purchaser have purchasing delegation with
credit card?
YesYes
No
No
Is the purchase <$5k
No
Yes
Page 74
‘To Be’ Illustrative Process - Overarching
James Cook University P2P
Overarching ‘To be’ Mega Process (Subject to System Functionality)
Cat
egor
y M
anag
emen
t C
omm
erci
al S
ervi
ces
Proc
urem
ent
Serv
ices
Ope
rati
ons
(Pur
chas
ing)
Ope
rati
ons
(Rec
eivi
ng)
Fina
nce
(Sha
red
Serv
ices
)
Start Category DefinitionRequirements /
Specification Definition
Category Strategy Development
Usage and Compliance
Management
Performance Management
Strategic Sourcing End
Start Plan Contract Manage ContractExecute Contract
Define position, spend, complexity
Specifications met through tailoring
Manage Contract Compliance
Set up in contact management system
End
Supplier Stratification
Start Supplier Integration
Supplier Performance Management
Supplier Development
Supplier Collaboration
End
StartStrategy & Vision
DefinitionPerformance Value Drivers Definition Metrics Definition
Performance Goal & Target Setting
Embed/ Integration Process
Results Reporting End
StartRequisition Processing
Purchase Order Processing
Receive Goods and Services
Invoice Processing Issue Payment End
Procurement goals associated with critical success factors and prioritised
performance drivers
Established and agreed KPIs and Scorecards
Market position, category complexity
identifies relationship
Set up contract compliance
Process Purchase
OrderLegend:
Process Decision Off Page Ref Risk/ControlSub-Process
Page 75
‘To Be’ Illustrative Process- Requisition & Purchase Order
James Cook University P2P
Create Requisition and Process Purchase Order (Subject to System Functionality)
Fina
ncia
l D
eleg
ate
Req
uest
or
(Stu
dent
/Sta
ff)
Purc
hasi
ngSu
pplie
r
Enter search Criteria(product/supplier
etc.)
Is item in catalogue
Create Catalogue Requisition
Yes
Review and Submit
No
Create Non- Catalogue
Requisition
Specify details (Quantity,
Category/Item/Supplier)
Obtain and attach quotes:- $5-$20k 2 written quotes-$20-$200k 3 written quotes and evaluation
Budget Authorisation/
Transfer ?
Approve Requisition?
Catalogue Requisition
PO Automatically Generated and Sent
to Supplier
Receive Purchase Order
Review Approved Requisition
Non-Catalogue Requisition
Generate PO and Send to Supplier
Receive Goods
Identify need
Review Purchasing Policy
Buying Channel Exists?
Assess Risk
No
Credit Card
Use Buying ChanelYes
Expense Reimbursement
SourcingContract
Management
Is spend one-off less than <$5k
Yes
Catalogue/ Purchase Order
No
Credit Card
Direct Invoice
2.R2
2.R1
2.R2
2.R1
Page 76
‘To Be’Illustrative Process- Receipt Goods & Payment
James Cook University P2P
Receive Goods and Process Invoice (Subject to System Functionality)
Supp
lier
Ope
rati
ons
(Rec
eivi
ng)
Fina
nce
(Sha
red
Serv
ices
Acc
ount
s Pa
yabl
e)Re
ques
tor
(Sta
ff o
r St
uden
t)
Create Requisiti
on
Send Goods/Perform Service
Confirm and Determine % of
Service Complete
Services
Receive GoodsInspection Required? Enter Goods/
Services Received and Accepted
Manage Inventory
Inspect Goods
Yes
No
Send Invoice
Electronic Invoice?
Goods
Purchase Order on Invoice?
Does Invoice Match Goods/
Services Received
Approve Matched Invoice for Batch
Processing
3 Way Match Pass Matching Requirements
4.R1
Resolve and determine match
4.R5
Enter meta dataNo
Resolve issue
Yes
Yes
Yes
No
No
Yes
No
Specify Invoices to be paid
Exceptions?
Manage Exceptions
Yes
Receive Payment
Create EFT Payment Batch
Approve PaymentRun Payment
Process
Payment Successfully
MadeYes
Resolve issues
5.R6
No
No
3.R1
Goods
3.R3 3.R4
Send damaged goods to vendor
Receive damaged goods
Damaged Goods
3.R2
4.R3
4.R2 4.R3 4.R4
5.R1
5.R1
5.R7
EFT
5.R2
4.R5
Page 77
‘To Be’ Illustrative Process- Risks & Controls
James Cook University P2P
Ref Risk Controls
Mega Process Consideration
0.R1 Goods are not procured timely and efficiently to meet
organisational objectives
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► Automated requisition, purchasing, receiving and inventory systems
► Appropriate organisational structure (Centralised and shared service vs. decentralised)
► Qualified and well trained staff, including executive oversight
► Regular and effective communication among executives
0.R2 Cost savings opportunities are not recognised or excessive
spending is incurred
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► Enterprise-wide contracts and processes to enforce adherence to contracts
► Rigorous and robust budgeting and monitoring procedures
► Systems applications controls
► Periodic self-analysis of purchasing data
0.R3 Systems and data are inappropriately or improperly
manipulated
► Restrict data and system access to appropriate personnel
► Align system and functional module access to personnel based on need and authority
0.R4 Misstated financial information and/or loss of assets due to
error and fraud
► Adequate staffing to ensure segregation of duties
► Segregate duties between incompatible functions
Vendor Selection and Contracting
1.R1 Inappropriate vendors are used to procure goods/services
which does not result in the optimum combination of cost,
quality and service
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► System application controls
► Vendor Master File controlled for completeness accuracy & validity
1.R2 Contracts/Commitments are not entered into appropriately
and/or are not properly managed
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► System application controls
► Review of significant contracts for financial statement disclosure
► Monitor and analyse spend and compliance with procurement polices
1.R3 Inaccurate, incomplete, or duplicate vendor data, resulting in
inefficiencies, lack of ability to capitalise on favourable
payment terms and incorrect reporting
► System application controls
► Vendor Master File controlled for completeness accuracy & validity
Page 78
‘To Be’ Illustrative Process- Risks & Controls (Cont.)
James Cook University P2P
Ref Risk Controls
Requisition to Purchase Order
2.R1 Goods and services are inappropriately procured ► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► System application controls
► Segregation of duties
► Automated requisition, purchasing, receiving and inventory systems
► Cost centre budget to actual reviews on a periodic basis
► Periodic review of Purchase Orders vs. Non-Purchase Order Purchases
2.R2 Coding of purchases to the system is not accurate ► Purchasing, inventory, payment and accounting systems interface, reconciliation is performed, management follow up and
resolve un-reconciled items
► Purchasing application is configured to restrict purchases, receipts and invoices to defined suppliers in the vendor master and
defined goods and services in the item master file
Receiving
3.R1 Goods Receipts do not comply with order specifications ► Review of bill of lading, packing slip, purchase order and material is conducted on receipt
► System matches purchase order, receiving report and invoice (3 Way Match)
3.R2 Vendor returns are not identified on a timely basis and vendor
credits are not applied to future purchases
► Specified goods are inspected for quality purposes and segregated if they don’t meet standards
► Formal tracking and application of vendor credits
► System automation related to vendor credits
3.R3
Good receipts are not recorded accurately or in the correct
period
► Automated requisitioning, purchasing, receiving and inventory system
► Receiving log and system receipts reconciled
► Accruals performed to identify and record liabilities in proper period
► Physical counts of inventory performed to verify levels
3.R4 Fictitious or duplicate receipts are recorded ► System matches purchase order, receiving report and invoice (3 Way Match)
► Receiving log and system receipts reconciled
► Physical counts of inventory performed to verify levels
Invoice Processing
4.R1 Liabilities are not recorded in appropriate period ► Periodic accruals performed
► Unmatched invoices reviewed at period end
► Cost centre budget to actual review performed on periodic basis
Page 79
‘To Be’ Illustrative Process- Risks & Controls (Cont.)
James Cook University P2P
Ref Risk Controls
4.R2 Inaccurate, fictitious or duplicate vendor invoices (price,
quantity, terms) are processed
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► System applications controls
► Segregation of duties
► Automated requisitioning, purchasing, receiving, and inventory systems
► Cost Centre budget to actual review performed on a periodic basis
► Periodic analysis of payment data
4.R3 Payments related to contracts may be inconsistent with
contract terms
► System application controls
► Review of invoices prior to payment
► Cost Centre budget to actual review performed on a periodic basis
4.R4 Credit/debit memos are inaccurate or not authorised according
to policy
► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► Automated requisitioning, purchasing, receiving, and inventory systems
4.R5 Discrepant invoices are not resolved timely and appropriate ► System application controls
► Qualified and well trained staff, including executive oversight
Payment
5.R1 Payments are not recorded accurately in the correct period ► Updated code of conduct and purchasing policies and procedures, including delegations and authorisation requirements
► System applications controls
► Automated requisitioning, purchasing, receiving, and inventory systems
► Cost Centre budget to actual review performed on a periodic basis
► AP aging/ sub-ledger is reviewed and reconciles to the GL
► Bank reconciliations are prepared and reviewed
► Proposed payment listing is reviewed and approved prior to payments
5.R2 Inappropriate EFTs processed
(Note controls R3 to R5 have been removed as these are not
relevant to JCU)
► System application controls
► Segregation of duties
► Cost center budget to actual review performed on a periodic basis
► Bank reconciliations are prepared and reviewed
5.R6 Payments not issued to vendors on a timely basis resulting in
relationship damage and/or inability to secure credit
► System application controls
► Qualified and well trained staff, including executive oversight
► Regular and effective communication among executives
5.R7
Optimal cash flow opportunities (e.g. early payments, missed
discounts, late charges) are not capitalised on when issuing
payments
► System application controls
► Qualified and well trained staff, including executive oversight
Page 81
JCU Singapore Current Process
Legend:
Process Decision Off Page Ref OpportunityAlternative
Process
James Cook University P2P
Page 88
Interview Quotes (Cont.)
Risks & Controls:
Data & Technology:
Performance Management:
James Cook University P2P
Page 90
Change Management & Culture
► Change management enables change across the various elements of the P2P model operating model to be integrated to achieve the desired results.
► The transition could be particularly challenging for JCU for a number of reasons including:
► The cultural shift required to obtain successful outcomes, including a shift to a whole-of JCU rather than a siloed view, the notion of academic vs. administration staff functions, and the incentivisation of accountabilities
► Change fatigue due to broader change agenda (including the organisational restructure) and consequences incorrectly attributed to this project
► The changes will have implications across divisions and faculties across the university. These will require capability and knowledge to be developed across the University.
► In order to overcome the challenges outlined above, change management and communication will be key to:
► Increasing the readiness for change amongst stakeholders across the University
► Assessing and supporting JCU in building its capability
► Increasing speed and effectiveness of the change
► Enabling the changes to be sustained so that the objectives can be achieved and benefits realised
► As initial steps towards various stakeholders across JCU have been consulted throughout the project to identify
opportunities for improvement and ownership involving operational stakeholders
James Cook University P2P
Page 91
Change Management in the JCU Context
An effective change management approach is based upon creating the conditions for success within an organisation to enable them to realise the benefits of the transition taking place and keep these sustainable. In the JCU context, this will involve leveraging the strength that already exists within the organisation in order to transform the procurement function and drive the improvement. A practical methodology can be used that delivers outcomes throughout the end to end performance improvement process, whilst recognising the journey that individuals need to take.
The diagram indicates three key critical success factors for change (highlighted in yellow) which can enable JCU to minimise risk and realise sustainable benefits. These from part of the implementation plan outlined in Appendix E:
► Engage and Manage Stakeholders - The purpose of a Stakeholder Engagement Strategy and Communication Plan is to facilitate the effective delivery of project activities and improve stakeholder understanding and commitment to future changes being introduced within JCU
► Align the Organisation - Aligning JCU and its impacted
stakeholders to the changes the procurement transformation is likely to introduce. These will be critical to driving the change in a sustainable manner and realise their intended benefits.
► Transition the people - Transitioning the people refers to
understanding the impacts and readiness of individuals who need to change, ensuring the right people are in the right roles and the provision of targeted training and support to develop capability.
James Cook University P2P
Page 92
Culture in the JCU Context
To specifically address organisational culture it is necessary to close the gap between desirable and actual behaviours through a structured program of behavioural change.
A methodology can be used that centres on making culture tangible to generate and sustain desired culture, through targeting the ways in which people behave.
* Based on model developed by David Ripley PhD, 2002 and Dr Thomas F Gilbert, 1996
Ernst & Young’s Behavioural Engineering Model
The diagram illustrates the six drivers of behaviour that need to be aligned in order to close the gap between actual and desired behaviours.
► The model recognises there are factors JCU can control directly to
influence behaviours, and those which increasingly depend upon the will and cooperation of individuals. To deliver real change all of these levers must be applied and aligned, to encourage the behaviours that JCU requires in order to improve its P2P Process.
► This assumes that the desired behaviours can be articulated based
on the JCU and procurement vision and objectives.
James Cook University P2P