Jacketed Piping

download Jacketed Piping

of 11

Transcript of Jacketed Piping

  • 8/10/2019 Jacketed Piping

    1/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: TITLETCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET i OF iii

    REV. NO. R0 R1 R2 R3

    INITIALS SIGN. INITIALS SIGN. INITIALS SIGN. INITIALS SIGN.

    ISSUE

    PPD. BY SVR Sd/- RUN Sd/- CSS Sd/- GC

    CHD. BY AMM Sd/- RVR Sd/- RVR Sd/- CSS

    APD. BY RVR Sd/- RL/MSK Sd/-/Sd/- RL Sd/- RL

    DATE 11.09.1990 31.03.1997 02.05.2000 02.06.2003

    R3

    TCE FORM NO. 020R2

    DESIGN GUIDE FOR JACKETED PIPING

  • 8/10/2019 Jacketed Piping

    2/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: TITLETCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET i OF iii

    REV. NO. R0 R1 R2 R3

    INITIALS SIGN. INITIALS SIGN. INITIALS SIGN. INITIALS SIGN.

    ISSUE

    PPD. BY SVR Sd/- RUN Sd/- CSS Sd/- GC

    CHD. BY AMM Sd/- RVR Sd/- RVR Sd/- CSS

    APD. BY RVR Sd/- RL/MSK Sd/-/Sd/- RL Sd/- RL

    DATE 11.09.1990 31.03.1997 02.05.2000 02.06.2003

    R3

    TCE FORM NO. 020R2

    FILE NAMES: M6ME422R3.DOC AND

    M6ME422R3.DWG

  • 8/10/2019 Jacketed Piping

    3/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: CONTENTSTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET ii OF iii

    TCE FORM NO. 120 R1

    ISSUE

    R3

    CONTENTS

    SL. NO. TITLE SH. NO.

    1.0 SCOPE 1

    2.0 JACKETED PIPING 1

    3.0 JACKETED VALVES 2

    4.0 LENGTHS OF HEATING SECTIONS 2

    5.0 FLOW DIRECTIONS 3

    6.0 BRANCHES 37.0 VENTS AND DRAINS 4

    8.0 GENERAL 4

    TABLES

    1. JACKET AND CORE DIMENSIONS 5

    2. JACKET BLANK DIMENSIONS 5

    3. JUMPER LOCATION 6

    4. LENGTHS OF HEATING SECTIONS 6

    FIGURES

    1. SPACERS 7

    2. WELDING OF CORE AND JACKET PIPES 7

    3. JACKET BLANKS 7

    4A, 4B & 4C FLANGE TYPES 8

    5. REDUCING FLANGE 8

    6. JUMPER 9

    7. INSTRUMENT STUB 9

    8. BRANCH INSTALLATION SEQUENCE 10 & 11

  • 8/10/2019 Jacketed Piping

    4/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: REV. STATUSTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET iii OF iii

    TCE FORM NO. 120 R1

    ISSUE

    R3

    REVISION STATUS

    REV. NO. DATE DESCRIPTION

    R0 11.09.1990 - -

    R1 31.03.1997 Generally revised.

    R2 02.05.2000 Generally revised.

    R3 02.06.2003 Paras 2.0 and 6.1.9 revised, para 8.3 added and whole

    document reformatted.

  • 8/10/2019 Jacketed Piping

    5/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: WRITE-UPTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 1 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

    1.0 SCOPE

    This design guide gives general recommendations to be followed for jacketed piping in

    chemical and industrial plants. Where process collaborator has furnished specificrequirements, such specific requirements shall supersede requirements given in this

    guide. The guidelines given in the guide are based on pipe dimensions as per ASME

    B36.10.

    2.0 JACKETED PIPING

    2.1 Jacketed pipe constitutes a core pipe, which conveys the fluid, which needs to be

    heated or cooled by a heating or cooling medium flowing in the jacket pipe. Fluids

    flowing in the jacket may be steam, hot water, thermic fluid, chilled water and chilled

    brine etc.

    2.2 Piping is required to be jacketed where a more efficient heat transfer than, what can be

    provided by tracing, or tracing with heat transfer cement, is required. Jacketed piping

    also provides uniform heat input around the circumference of the core pipe thus

    eliminating hot or cold spots that may cause degradation of fluid in the core pipe or

    localised freezing. Jacketed piping also provides closer and better temperature control.

    Requirements of jacketing are decided by the process or system engineer and are

    indicated in P and I Diagrams (P&I Ds).

    2.3 Depending on the process requirement, the core and jacket materials can be the same

    or different. Also jacketing can be partial or full as dictated by the process

    requirements. Full jacketing may require jacketing of pipes, fittings and valves and

    specialities. Partial jacketing may require jacketing of only straight pipe with other

    items not jacketed or, in some cases, pipes and fittings fully jacketed but valves and

    specialities partially jacketed.

    2.4 Jackets are broken into heating sections using flanged joints or jacket blanks.

    Adjacent jacket sections are connected by "jumper" pipes. Sizes of jumper pipes shall

    be as shown in P&I Ds, but generally are of 15 mm (1/2") for steam and 20 mm (3/4")

    for hot water or thermic fluids.

    2.5 The jacket-core pipe size combinations shall be as stipulated by the process engineer.

    If there is no specific requirement, the combinations given in Table 1 can be

    considered.

    2.6 Core pipe shall be supported and centered within the jacket pipe by spacers located at

    120 degrees around the circumference and at intervals given in Table 1. Spacers are

    to be welded to core pipe. Spacer material shall be same as that of the core pipe.

    Refer Figure 1, for details. Grinding of spacer shall be done if necessary during

    fabrication of jacketed piping, to facilitate assembly.

  • 8/10/2019 Jacketed Piping

    6/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: WRITE-UPTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 2 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

    2.7 At locations of welds on core pipe, jackets shall be broken to permit examination of

    the welds. After successful examination of core pipe welds and completion of leak

    tests, the jacket shall be closed. Refer Figure 2. Degree of examination shall dependon the nature of fluid, pressure and temperature. This is to be decided in consultation

    with process engineer and as per the applicable code.

    2.8 Fittings for core and jacket pipes shall be of butt welding type. Core elbows shall be

    of long radius type (R = 1.5D) and jacket elbows of short radius type (R = 1.0D).

    The jacket elbow may be split, if necessary, to facilitate assembly on core elbow. In

    some cases there may be interference between the elbows and it may be necessary to

    draw to scale and check for interference.

    2.9 Blanks for jacketed piping shall be as shown in Figure 3. For dimensions, refer Table

    2. Material of blanks shall be the same as that of the core pipe. Blanks are used to

    split the piping into various heated sections.

    2.10 FLANGES

    2.10.1 Unless the process demands otherwise, flange size for jacketed piping shall correspond

    to core pipe and the jacket connection at the flange shall be as shown in Figure 4.

    2.10.2 When process demands that jacket be extended right up to the back of the flange, the

    jacket connection at the flange shall be as shown in Figure 5. Flanges shall be of

    reducing type i.e. jacket size X core size.

    2.10.3 For sizes < 50 mm, where stainless steel core pipe is involved, stainless steel flanges

    may be used. For sizes > 80 mm, use either stainless steel stub ends with carbon steel

    lap joint flanges or carbon steel slip on flanges with SS liner. Refer Figures 4 and 5.

    2.10.4 Where stub ends are used with reducing type flanges, lap diameter of stub end shall

    correspond to the jacket size.

    2.11 At all flanged joints, jumpers shall also to be provided with flanged joints to facilitate

    disassembly. These shall be dimensioned as per Figure 6 and Table 3. Connections to

    jackets shall generally be radial. Tangential connections may be required in the case of

    Dowtherm heating to avoid formation of pockets.

    3.0 JACKETED VALVES

    Unless process demands otherwise, jacketed valves shall be of core size and shall have

    partial jackets. If process requires full jackets, then valves shall be of core size and

    have flanges corresponding to jacket size. Heating or cooling medium connections shall

    be provided on the jacket.

  • 8/10/2019 Jacketed Piping

    7/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: WRITE-UPTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 3 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

    4.0 LENGTHS OF HEATING SECTIONS

    4.1 Lengths of heating sections shall generally limited to the values given in Table 4. Whenlengths beyond the values are involved, additional heating or cooling medium supply

    and return points shall be provided.

    4.2 In the case of water, the above length is from the point of supply on the supply header

    to the point of return to the return header.

    4.3 Wherever P&I D indicates requirements different from the above, follow the P&I D in

    consultation with the process engineer.

    5.0 FLOW DIRECTIONS

    Steam or other heating vapour supply shall always be at the top of a heating section

    and condensate drained from the lower end of the section. In the case of liquid media,

    liquid shall enter at the bottom of a jacketed section and exit at the top for proper

    venting.

    6.0 BRANCHES

    6.1 INSTALLATION PROCEDURE

    6.1.1 Install core pipe.

    6.1.2 Move jacket section over core pipe.

    6.1.3 Make cut in core pipe.

    6.1.4 Weld branch to core pipe.

    6.1.5 Move jacket branch over core branch pipe.

    6.1.6 Check weld of core pipe. Leak test core pipe as per specified procedure.

    6.1.7 Bring pipe section into alignment using spacers and weld to jacket. If necessary, use

    split jacket.

    6.1.8 Weld branch jacket.

    6.1.9 Check weld of jacket pipe. Leak test jacket pipe as per specified procedure.

    Refer Figure 8.

  • 8/10/2019 Jacketed Piping

    8/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: WRITE-UPTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 4 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

    6.2 INSTRUMENT CONNECTIONS

    Connections for pressure, temperature or flow measurement, made in core pipe shallbe installed as per Figure 7. The jacket shall be locally swaged and welded to core

    pipe.

    7.0 VENTS AND DRAINS

    7.1 All high points on jacket shall be provided with threaded half coupling and plug for

    hydro test-purpose. Jumper connections can also be used for the purpose.

    7.2 All low points on steam jacket shall be connected to a steam trap.

    7.3 Core vents and drains shall be provided only if required by the process engineer.

    8.0 GENERAL

    The following points shall be borne in mind while designing jacketed pipes if

    specifications are not available from the process collaborator.

    8.1 Core pipe may be subject to external pressure due to fluid pressure acting in the

    jacket. The core pipe shall have adequate thickness to withstand the external pressure.

    Design shall be as per ASME Section VIII, Division 1.

    8.2 If core and jacket pipes are of different materials (for example, stainless and carbon

    steels respectively) having different coefficients of thermal expansion, the assembly may

    give rise to column effect on the core pipe. This is to be checked.

    8.3 It is not necessary that the core pipe and the jacket pipe be supported at the same

    location. Piping engineer shall consider this aspect while showing it clearly in the piping

    drawing, carrying out piping flexibility analysis and giving support data to civil engineer.

    8.4 Flexibility analysis of jacketed piping may be carried out using programmes such as

    CAEPIPE or CAESAR II. If such a programme is not available, the following steps

    are suggested:

    (a) First convert the jacket-core combination into an equivalent pipe having the

    combined moments of inertia of jacket and core pipes and an outside

    diameter same as the jacket pipe. Take the difference in modulii of elasticity

    between core and jacket materials into account.

    (b) Carry out flexibility analysis by conventional methods based on the

    equivalent pipe.

  • 8/10/2019 Jacketed Piping

    9/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: WRITE-UPTCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 5 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

  • 8/10/2019 Jacketed Piping

    10/11

  • 8/10/2019 Jacketed Piping

    11/11

    TCE CONSULTING ENGINEERS LIMITED SECTION: TABLETCE.M6-ME-590-422

    DESIGN GUIDE FOR JACKETED PIPING SHEET 6 OF 11

    TCE FORM NO. 120 R1

    ISSUE

    R3

    TABLE 3

    JUMPER LOCATION (REFER FIGURE 6)

    JACKET

    DIAMETER mm

    (in)

    DIMENSION L1 FOR

    JACKET FLANGE 150# mm

    DIMENSION L1 FOR

    JACKET FLANGE 300# mm

    40 (1.5) 185 220

    50 (2) 200 230

    80 (3) 215 250

    100 (4) 240 270

    150 (6) 275 310

    200 (8) 295 335

    250 (10) 325 365

    TABLE 4

    LENGTHS OF HEATING SECTIONS

    HEATING OR COOLING MEDIUM

    MAXIMUM RECOMMENDED

    LENGTH OF EACH HEATED OR

    COOLED SECTION, m

    Steam 25

    Thermic fluid (such as Dowtherm)

    Core size 100 mm - 15

    150 mm - 12

    200 mm - 8

    Hot or chilled water 30