ITS Allied! ITS for Lee!. C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE...
-
Upload
keven-bunn -
Category
Documents
-
view
215 -
download
0
Transcript of ITS Allied! ITS for Lee!. C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE...
ITS Allied!
Construction Engineering and
InspectionLee County Computer
Signal System (Advanced Traffic
Management System)
FPID 412636-2-62-01Federal Project No.: 8886 052A
Construction Engineering and
InspectionLee County Computer
Signal System (Advanced Traffic
Management System)
FPID 412636-2-62-01Federal Project No.: 8886 052A
March 21, 2012March 21, 2012
ITS for Lee!
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
Project Overview Design Build Contract
◦ $5.4 Million Lump Sum Contract◦ 565 contract days D/B; 21 Months CEI◦ Federal Aid Project
28 miles, from Bonita to Tara Woods Blvd. north of SR 78◦ Coordination with local governmental agencies (Lee County, Bonita Springs, Estero, City of Fort Myers and Cape
Coral) DBF will design, furnish, install, integrate and test ITS field
devices and connect to the Lee County Traffic Operations Center (TOC)◦ Complete modifications to TOC / 180 days
AWARENESS/APPROACHUNDERSTANDING PROJECT SCOPE
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
Primary Responsibilities of the CEI Act as extension to FDOT staff
◦ Proactively manage the work◦ Anticipate and address project issues
Coordinate all aspects of design and construction◦ Review/ analyze CPM schedules◦ Schedule of Values◦ Provide interpretation of contract documents◦ Phase submittal reviews/ERC◦ Required meetings
Kick-off Design workshops Pre-construction and Pre-integration
Enforce contract requirements and implement CPPR Operate in accordance with FDOT procedures (CPAM)
UNDERSTANDING PROJECT SCOPE
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (DESIGN) Phase Submittals - 60%, 90% & 100% Final
◦ Conformance with Design Build Technical Proposal - “Book of Promises”◦ Conformance with RFP & MTRs◦ Hardware/ Software Compatible with Econolite Centracs® System◦ Review/ Resolution of Potential Integration Issues◦ Compatibility/Coordination with Future Projects
Confirm existing conduit and fiber is viable Provide Clarifications - RFP vs. MTRs Permits
◦ SFWMD◦ NPDES/SWPPP◦ Endangered Species
PIO Support
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (DESIGN)
ERC utilization ◦ Plan submittals◦ Device Cut Sheets◦ Manual Tracking◦ Shop Drawings◦ Other
Field Assessments◦ ITS field device locations / site survey◦ Potential underground utility conflicts◦ Review of Right of Way limits◦ Inventory of existing infrastructure
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
54 NEMA TS2 Type I Controller Assembles 36 CCTV Cameras 4 new Node Cabinets to be integrated into existing system Traffic Control Center (TOC) equipment upgrade and modification 38 Uninterruptable Power Supplies (UPS) 28 System Detection Devices Reconnect existing opticoms in new cabinets (21 locations) 9 County Count Stations ADA improvements to affected intersections The project will be integrated into the existing Lee County TOC
Econolite Centracs® System and Communications Network
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION)Key Components of the Work
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
Fiber Optic Communications Infrastructureo Miles of directional bore due to
existing field conditions◦ Utilize existing as well as new fiber
optic infrastructure Extensive splicing and integration
◦ Three 1¼” conduits (1 for FOC, 1 for locate and 1 spare)
◦ Locate system to be installed in dedicated pull box
◦ Separate conduit for electric (min 2”)
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION)
US 41 AND FOUNTAIN LAKES
MLK AND VERONICA
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION) Fiber Optic Communications
Infrastructure◦ Locate existing utilities (Sunshine One Call);
DBF utilizing SUE◦ Bore logs to verify horizontal locations &
depths◦ Recommend field adjustments to avoid
unforeseen conflicts◦ Update plans to ensure accuracy of as-builts◦ Conduits “proofed” to ensure continuity and
absence of obstructions◦ Review OTDR testing on existing and new
fiber
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
CCTV (Closed Circuit TV)◦ Installed at 36 locations◦ Provide 360 coverage◦ Cannot be installed in the medians◦ Pole height maximum of 50 feet
above ground level◦ Existing or new structures may be
utilized for mounting
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION)
US 41 AND COLONIAL
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (DOCUMENTATION) CEI Reporting
◦ Daily Reporting of Construction Activities/ Site Manager◦ Verification Testing Reports & LIMS Entry◦ MOT / Erosion control field reviews and verification of
contractor reports◦ CPM Reviews◦ Digital Progress Photos & Log◦ Monthly FDOT Project Status Reports (CSRS)◦ Meetings Minutes & Follow-Up Action Items
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (DOCUMENTATION) DBF Submittal Tracking
◦ Design Submittals◦ Cut Sheets/ Shop Drawings◦ CPM Schedule/ Updates◦ Schedule of Values◦ Field Equipment Operational Manuals◦ Software Manuals/ Device Protocols◦ Test Procedures and Results
RTVM◦ Training Manuals◦ Certification of all signal equipment
We will prepare a submittal tracking log in advance of project start & track all submittals via ERC or submittal log**ALL IMPORTANT**
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (DOCUMENTATION) Project Close Out/ Warranties
◦ Timely submittal of all close out documents Final As-Built plans with GPS data in hand before project
acceptance Spare Parts (as required)
◦ Timely/ Accurate Final Estimate Allied’s FE submittal on Charlotte FMS and ATMS was
submitted early with no procedural errors◦ Warranties
Pre/ post-warranty meetings Require warranty documents as soon as devices are installed Ensure warranties per contract/ technical proposal Establish a matrix to track warranty submittals
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION)
Key Inspection Points◦ CEI check lists based on
Final Plans/ RFP/ MTR requirements Standards/ Specifications FDOT 780 Supplemental Specifications FDOT Inspection Guidelists
◦ Components to be QPL/APL approved◦ Splice and pull box conformance
Proper sizing of products◦ Use of expanded RTVM for field
inspections
RTVM Sample
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNDERSTANDING PROJECT SCOPE (CONSTRUCTION) Environmental Concerns - Minimalo Erosion Control Plan / NPDES inspectionso Other Permitso Protected species
Gopher Tortoise Indigo snake Bald Eagle
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNIQUE PROJECT ISSUESCommunication / Coordination is Key Daily communication with Contractor
Superintendent Communication with Utility owners (48 hours prior) Communication and coordination with on-going
construction projects Interface with property owners and general public Interaction with Dept. Public Information
Officer◦ 20+ special events
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNIQUE PROJECT ISSUES MOT/ Safety
◦ MOT Certified Personnel/ Urban; high traffic counts
◦ Minimize traffic disruptions & maximize safety
◦ Ensure advance coordination for lane closures & nighttime operations (PIO, Law Enforcement & Emergency Services)
◦ Conformance with MUTCD & FDOT standards
◦ MOT & Safety will be emphasized at project meetings
US 41 AND ALICO RD
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNIQUE PROJECT ISSUES
Approved MOT Plan vs. existing field conditions
Experienced personnel capable of adjusting MOT to meet field conditions
District One lane closure policy/RFP restrictions/damage recovery
Limited ROW affecting full or partial lane closures and construction equipment placement◦ Directional Bore
MOT verification inspection each day
US 41& ALICO
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNIQUE PROJECT ISSUES
Background ATMS Project Highlights
◦ Testing◦ Signal Cabinet◦ CCTV Pole
Grounding Requirements
Lee County will operate and maintain ATMS after project acceptance Our Goal is to provide grounding
that meets or exceeds project requirements
US 41 AND VICTORIA
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
MTR requires:◦ Preliminary Integration Plan
30 days prior to Pre-Integration Meeting◦ Pre-Integration Meeting
Discuss Preliminary Integration Plan◦ Integration Plan
90 days prior to Integration Work◦ Testing
Factory Stand-Alone Subsystem Operational Test Burn-in
UNIQUE PROJECT ISSUES (TESTING & INTEGRATION)
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
UNIQUE PROJECT ISSUES (TESTING & INTEGRATION) Integration of system
o Equipment compatibility with Econolite Centracs®
Interim Operationso Maintain Operational Functionality
TOC Equipment Installation Early in Project – 180 days from NTP
Signal Groupings Existing ATMS Central Software Existing Communications Existing signal timings and MOT
o Achievable Systematic Deployment / Phasing of
Construction and Procurement Phasing of construction Procurement
Accurate Inventoryo Benefits
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
INNOVATIVE CONCEPTS
If desired, ability to use FDOT ERC system for all submittals Expansion of the RTVM (Traceability Matrix)
o Include additional project requirements such as NECo Expand verification method (Factory, Stand-alone, Subsystem)o Develop comprehensive field check lists using the RTVM
Specialty staff and peak work staff brought in only as-needed Project Share Site for exchange of large files Dual trained staff No cost project office at 5500 Division Drive Environmental Specialist available at no cost to the
Department Real time project tracking
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
INNOVATIVE CONCEPTS
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
PROPOSED STAFFING
Quantity ProposedAvailability of StaffQualifications/ Certifications of StaffQuality/ Experience on Similar ProjectsTeam’s Past Performance on Similar Projects
The Allied TeamAllied * AIM * Atkins * ComVia * Covalt * Gannett Fleming * URS
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUANTITY/ AVAILABILITY PROPOSED
Key staff part-time through design Core inspection/field staff during construction/testing Specialty staff as-needed Reduced staff during Operational Period Under CEI Budget
17514.75
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
PROPOSED STAFF
Quality AssuranceJames White, Allied
Jim Lynch, P.E., VolkertJoe McConnell, P.E., URS
Quality AssuranceJames White, Allied
Jim Lynch, P.E., VolkertJoe McConnell, P.E., URS
Senior Project EngineerVay Scott, P.E., Allied
Senior Project EngineerVay Scott, P.E., Allied
Sr. ITS EngineerAlex Mousadi, P.E., URSJoe McConnell, P.E., URS
Dr. Ayman Mohamed, P.E., URS
Sr. ITS EngineerAlex Mousadi, P.E., URSJoe McConnell, P.E., URS
Dr. Ayman Mohamed, P.E., URS
FDOT District OneMary Wiley
Construction Project ManagerKatherine Duvall/ Mark Roberts
Traffic Operations
FDOT District OneMary Wiley
Construction Project ManagerKatherine Duvall/ Mark Roberts
Traffic Operations
Project Administrator / Contract Support Specialist
Arleny Barrios, Allied
Project Administrator / Contract Support Specialist
Arleny Barrios, Allied
Principal-In-Charge/ Project Manager
Paula McQueen, CPA, Allied
Principal-In-Charge/ Project Manager
Paula McQueen, CPA, Allied
ITS Engineer/InspectorEarl Salley , GF
Matt Cousins, URS
ITS Engineer/InspectorEarl Salley , GF
Matt Cousins, URS
Sr. ITS InspectorJoe King, AtkinsDanny Trigg, GF
Sr. ITS InspectorJoe King, AtkinsDanny Trigg, GF
CEI StaffCEI Sr. Inspector
Scott Franklin (Lead), AlliedNorman Brownlie, Allied
CEI InspectorRyan Scott, Allied
Mark Smalley, Allied
CEI StaffCEI Sr. Inspector
Scott Franklin (Lead), AlliedNorman Brownlie, Allied
CEI InspectorRyan Scott, Allied
Mark Smalley, AlliedITS Inspector
Ron Horn, URSJason Vincent, URS
ITS InspectorRon Horn, URS
Jason Vincent, URS
SecretaryTBD, Allied
SecretaryTBD, Allied
Additional InspectionSr ITS InspectorJose Feliz, Atkins
Edmund Lewandowski, GFITS Inspector
Sean Rouleau, AtkinsFrankie Suarez, Allied
CEI InspectionMatt Hicks, Densel Landrum,
Brian Moore, Allied
Additional InspectionSr ITS InspectorJose Feliz, Atkins
Edmund Lewandowski, GFITS Inspector
Sean Rouleau, AtkinsFrankie Suarez, Allied
CEI InspectionMatt Hicks, Densel Landrum,
Brian Moore, Allied
Specialty StaffPublic Information Officer
Dave Parks (Comvia)Professional SurveyorBob Potter, PSM (AIM)Resident Compliance
SpecialistLori Hoover (Covalt Group)
Specialty StaffPublic Information Officer
Dave Parks (Comvia)Professional SurveyorBob Potter, PSM (AIM)Resident Compliance
SpecialistLori Hoover (Covalt Group)
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Vay Scott, P.E. - Sr. Project Engineer
◦ 28 years experience on FDOT projects◦ Florida Licensed Professional Engineer◦ Significant CEI management experience
Lakeland CCTV Installation Project QA Manager for Charlotte FMS and Charlotte ATMS Projects
◦ Proactive approach to issue identification and resolution
History of completing projects early or on time!
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Alex Mousadi, P.E. - Sr. ITS Engineer
◦ Electrical Engineer◦ Over 22 years experience in the ITS industry◦ Experience encompasses design, construction, testing & integration◦ Key projects include;
23 miles of I-75 for the Charlotte FMS for FDOT District 1 Roadside Animal Detection System (RADS) for FDOT District 1 250+ interstate ITS work in Florida (I-4, I-75, I-275, I-595, I-95) I-595 PPP in District 4 Participated in development/integration of eight (8) TMC’s nationally Lead system designer & integrator for Tampa Bay SunGuide Ph 3
Diverse background allowing for prompt and efficient issue resolutions!
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Arleny Barrios - Project Administrator /
Contract Support Specialist◦ Degreed Civil Engineer – meets requirements of Sr. PE position◦ 11 years of CEI experience; 4 years with FDOT in Sarasota Ops◦ Extremely organized and efficient◦ PA/CSS on Charlotte County ATMS◦ Kept overtime on Charlotte County ATMS to less than 4%◦ Available 50% now; Full-time April 2012
Brought ATMS project in on-time and returned CEI funds to the
Department
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
Jun Jul Aug Sep Oct Nov Dec Jan Feb
Sr. Project Engineer 8.00 18.00 15.00 15.50 26.00 36.00 34.00 46.00 24.00
Project Administrator 10.00 15.00 42.00 56.00 23.00 4.00 3.00 73.00 144.00
CSS 0.00 26.00 31.00 37.00 38.00 0.00 0.00 0.00 107.00
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Below is a summary of hours by month for the management positions.
NTP was issued in July and construction began in February. As you can see, the PA has little involvement until construction began.
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Scott Franklin – Senior Lead Inspector /
Assistant Project Administrator◦ 20 years of CEI experience◦ Senior Lead Inspector and Project Administrator◦ IMSA Level 1 and 2◦ Certified Fiber Optic Technician◦ PA on the Charlotte FMS project◦ Handled scheduling and kept overtime on Charlotte County FMS to
less than 2%◦ Available Full-time Nov/Dec 2012
Exceptional CEI Senior Lead Inspector
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Earl Salley – ITS Engineer / Inspector
◦ BS Civil Engineering◦ 23 years of ITS experience – 21 years with Lee County Traffic Ops◦ Designed, installed and managed the Lee County signal system◦ Knowledgeable about local ordinances◦ Knows the local communities
Lee County Complete Streets Initiative◦ Available part-time now; Full-time Oct 2012
Allied’s Secret Weapo
n
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Joe King – Senior ITS Inspector
◦ Certified IMSA Signal Inspector◦ Sr. ITS Inspector on very complex urban systems in Hillsborough
County and Orange County ◦ Knows Bosch Camera System used by Lee County◦ Experienced in traffic transportation design and ITS system analysis◦ Available part-time now; Full-time May 2012
Five ATMS/ six ITS projects as a Sr ITS Inspector
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF Danny Trigg– Senior ITS Inspector
◦ Certified IMSA Levels 1 & 2 Inspector◦ Worked on five ITS projects in Lee County◦ Knows Bosch Camera System used by Lee County◦ Experience on three FDOT ATMS projects◦ Available Full-time Oct 2012
Knows Lee County’s Signal System
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/ CERTIFICATIONS OF STAFF
Additional Resources◦ AIM Engineering and Survey (Bob
Potter, PSM)◦ ComVia (Dave Parks, PIO)◦ Covalt Group (Lori Hoover, RCS)
CEI o Mark Smalley (Building/
Structural Inspector)
MARK SMALLEY
DAVID PARKS
BOB POTTER
LORI HOOVER
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALIFICATIONS/CERTIFICATIONS OF STAFF Strong QA Program = Quality services QA Team:
◦ Jim Lynch, P.E. (Volkert)◦ Joe McConnell, P.E. (URS)◦ James “J” White (Allied)
50 years CEI experience with significant ITS installations
Reviews per the Scope of Services to include; ◦ Quality & quantity of personnel assigned◦ Quality of project records◦ Communication & feedback with FDOT
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALITY/ EXPERIENCE ON SIMILAR PROJECTS
Recent Relevant Project Experience
Project/ Client Construction Amount ($M) Start End Scope of Work
I-75 Charlotte County FMS/ FDOT District One $10 M Apr-09 Mar-11 23 miles
Charlotte County ATMS/ FDOT District One $6 M Jan-06 May-08 28 miles (84 int.)
Collier Co. & City of Naples ATMS/ FDOT JPA (Ph 1 & 2) $5 M Jun-02 May-06 20 miles
City of Lakeland ATMS $15 M Jul-07 Jan-08 5 miles
Lee/Collier ITS FMS/ FDOT District One $35 M Oct-05 Dec-09 98 miles
Tampa SunGuide Phase 3 $28 M Feb-07 On-going 50 miles
Over 175 Miles of ITS/ATMS Installations in FDOT District One
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
QUALITY/ EXPERIENCE ON SIMILAR PROJECTS
Device Description Charlotte Co. ATMS
I-75 Charlotte Co. FMS
I-75 Sarasota-Manatee FMS
CCTV Cameras 84 30 75 +/-
DMS Signs N/A 10 25
Vehicle Detectors N/A 44 18
HART/ HARB N/A 5/1 10/20
RWIS N/A 1 2
Fiber Optic/Conduit 28 miles+/- 23 miles+/- 56 miles+/-
Wireless Devices 2 5 N/A
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
TEAM’S PAST PERFORMANCE ON SIMILAR PROJECTS Charlotte County ATMS
◦ Returned $80,000 in CEI Fees◦ Final Grade of 4.2◦ Set the standard in communication, coordination & proactive
issue resolution Charlotte County FMS
◦ Returned $50,000 in CEI Fees◦ Final Grade of 3.9◦ Continued to establish new standards in communication,
coordination & proactive issue resolution
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
OTHER CONSIDERATIONS
Coordination with Debbie Tower from day one for all PI activities
Keep Web Site ITSLee.org up to date Two prong approach: day to day PI
issues/overall communication of benefits (awareness and education)
Public meetings Community awareness Maximize existing communication
resources available: TV, Radio, News-Paper
MPO presentation Work with 511 and FL511.com
Public Information
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
OTHER CONSIDERATIONS
Effective Communications with Stakeholders Began in advance of CEI advertisement
◦ FDOT - Traffic Operations, Fort Myers Operations, District Construction, District PIO, SWIFT Center
◦ Lee County, Bonita, Bonita Springs, City of Fort Myers, Cape Coral Facilitate Project Meetings
◦ Action Item Log◦ Thorough Documentations
CEI Performance Evaluation:Provided necessary project information to
all project stakeholders – 5!“Excellent communication between CCEI staff, contractor,
Department & local municipalities”
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
COMMITMENT TO SATISFY DEPARTMENT NEEDS DRB letter recognizing the
Allied team for their outstanding performance on Charlotte FMS
Nominated for FTBA Excellence in Construction Award
Nominated for ITS Florida Outstanding Achievement Award
Make the DOT’s client, Lee County, continue to be the complete streets champion of the year
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
COMMITMENT TO SATISFY DEPARTMENT NEEDS
C E I S E R V I C E S F O R LEE COUNTY COMPUTER SIGNAL SYSTEM UPDATE PHASE I | 0 3 . 2 1 . 2 0 1 2ITS Allied!
COMMITMENT TO SATISFY DEPARTMENT NEEDSProven abilities to interpret the contract and resolve
issues at project levelProven knowledge of technical issuesProven abilities to properly document and inspect the
workProven communication abilitiesProven ability to manage CEI and construction dollarsProven Commitment to FDOT
EXPERIENCED TEAM!
ITS Allied!Consistent, Predictable, Repeatable