ITP Mini Pile

download ITP Mini Pile

of 2

Transcript of ITP Mini Pile

  • 8/10/2019 ITP Mini Pile

    1/2

    Client : PT. KRAKATAU DAYA LISTRIK Doc. No. :

    Main Contr. : PT PP (Persero) Tbk. Revision No. :

    Project : KDL 120 MW COMBINED CYCLE POWER PLANT Date :Location : Cilegon, Banten

    NO

    DOCUMENTQC PP SNC L KDL/BVI

    INSPECTION & TEST PLAN

    MINI PILING WORK

    ITEM ACTIVITIES VERIFYING INSPECTION APPROVAL

    1. Construction Specification

    1.1. Technical Specification

    1.1.1. Review Approval technical specification R A R/A11.1.2. Finalize deviation, Amendments or Queries R A R/A

    1.1.3. Drawing for construction R A R/A

    1.2. Piling Procedure R A R/A

    2. Material Inspection

    2.1. Verification document / Mill Certificate A1 R/A

    2.2. Check for damage Inspection Report A1 A2

    2.3 Dimensional check if necessary Inspection Report A1 A2

    3. Installation Work

    3.1 Survey coordinat point Drawing A1 SW

    3.1.1. Tolerance for X and Y coordinates are 75 mm Inspection Report A1 R/A

    3.1.2. Tolerance for longitudinal axis is 1 : 100. Inspection Report A1 R/A

    3.2 Welding Joint Procedure, Inspection Report A1 A2

    R/A

    SW

    SW

    Approved Technical Spec.

    SW

    R

    R

    SW

    Approved Procedure

    Approved Technical Spec.

  • 8/10/2019 ITP Mini Pile

    2/2

    NO

    DOCUMENTQC PP SNC L KDL/BVI

    ITEM ACTIVITIES VERIFYING INSPECTION APPROVAL

    4. Final Set

    4.1. Record the penetration of each pile Procedure, recording A1 A

    5. Piling Test

    5.1. PDA test, 2 % from total pile Applicable Standar R A R/A

    6. Documentation

    6.1 R AAll inspection as per ITP has been done & the inspection report

    has already been generated and signed Contract, Tech. Spec., drawing, R/A

    The pile and penetration condition on the Final Set shall be met

    Testing shall be done at the approved location

    R

    6.2

    A1 - 100% INSPECTION OR TEST ; Execution or inspection by KPI

    A2 - RANDOM INSPECTION ; Inspection at random sample.

    W - WITNESS ; Witness of inspection by Client / Owner and Sub-Contractor may proceed if Client / Owner not appearance at the pointed time

    Witness point shall be given by Notification

    SW - SPOT WITNESS ; Witness of inspection by Client / Owner and to be done at spot or random ( random sample )

    R - REVIEW ; Review of certificate / document to ensure compliance with specification.

    A - APPROVAL ; Approval documentation ( Procedure, Work instruction, Inspection report, etc. )

    reportAll NCR or any deviation of contract already closed and

    documented