✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

iTM Timeline Update Summary

v1.01 (2012)

iTM Launch in NA

Global Software

v2.00.02 (2013)

• First US Specific Software

• Vote method for auto changeover

v2.01 (2014)

• D-net expansion for VRV HR units

v2.02 (2016)

BACnet Client software

v2.03 (2016)

v2.04 (2016)

BACnet Server with

virtual routing

v2.05 (2017)

• SD card Failure Alert

v2.06 (2018)

• Operation Data

• Trendlog

• Operation Data on BACnet

v2.07 (2019)

Security update

v2.08 (2021)

• HTML5 support

v2.09 (2021)

• Operation data update

• Hydrobox

v2.10 (2021)

• Demand Control

• HTTP option

• PPD with BACnet server

© 2021 Daikin North America, LLC

Intelligent Touch Manager (iTM)

• LT Hydrobox Compatibility: Monitor and Control

• Schedule ODU Low Noise and capacity control

• Demand Control Interlock

• HTTP option : integration to BMS or HAS

• PPD is now compatible with BACnet Server

• HTML 5 compatibility for Web Browsers

• Operational data logging for

• VRV-4, 4X, 4S, Aurora (575V) models

• VRV-W(T), VRV-4W

• VRV-3,3S

• VRV-Life

• BACnet data points for operation data*

• VRV-4, 4X, 4S, Aurora (575V) models

• VRV-W(T), VRV-4W

• VRV-3, 3S

• VRV-Life

v2.10 Update Overview

*For use with iTM BACnet Server gateway function

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand Control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

• HTTP option part number is DCM007A51

• HTTP option should be purchased and activated like the BACnet Client, BACnet Server and PPD options.

• Allows the BMS to monitor and control the VRV indoor unit through HTTP protocol.

• The BMS will be able to monitor and control the following items:

• Normal/ Error monitor

• ON/OFF

• Operation Mode

• Setpoint

• Room Temp

• Fan speed

• Louver direction

• Ventilation mode

• Ventilation amount

HTTP Option

ITM (DCM601A71) with HTTP option (DCM007A51)

LAN(Ethernet)

HTTP protocol

Building Management System Or Home Automation System

HTTP = Hypertext Transfer Protocol

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

Hydrobox Control

▪ iTM v2.10 software provides Hydrobox control.

▪ On/Off control

▪ Timer Extension Settings

▪ Remote controller Prohibits

▪ Leaving Water setpoint (cool)

▪ Leaving Water setpoint (Heat)

▪ Monitors Hydrobox error codes

▪ Hydrobox can be added to the iTM with a group address

Preliminary

© 2021 Daikin North America, LLC

Hydrobox Control

On/Off

Control

Timer

Extension

Settings

Leaving

Water

Setpoints

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

Schedule Update

Add outdoor unit to the ITM

▪ AirNet address should be assigned to the ODU using outdoor field settings (2-13) or using the remote remote controller

▪ An outdoor unit can be added to the iTM as a management data point with an AirNet address.

▪ Enable ODU demand control using ODU field settings (2-12)

▪ Assign a demand address to the ODU using ODU field settings (2-02)

© 2021 Daikin North America, LLC

Schedule Update

Schedule function improvement:

Added VRV Outdoor Unit capacity suppression and low noise to the schedule function of iTM.

Example:

A project is requiring:

1- A low noise control schedule from 12 to 4 am to meet a city low noise ordinance during the specified time.

2- ODU capacity reduction schedule for 70% from 1 pm to 5 pm to avoid a higher utility rate (Critical Peak Pricing) during the afternoon hours.

Select

outdoor unit

Low Noise and

Capacity Value

added to the

schedule

function

Schedule events

created to meet

project

requirements

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

3rd Party

Demand

Controller Up to 7 adaptors

Demand Control

Di4

▪ Power Limit Control (Demand Control) is intended to reduce power consumption when a 3rd party demand controller sends demand control signals to the iTM.

▪ Demand signals can be interlocked with the iTM or the iTM plus adaptor digital inputs.

▪ The following demand control strategies can be executed by the iTM

▪ Indoor unit setpoint shift control

▪ Indoor unit thermo on/off control

▪ Outdoor unit capacity control

▪ 3rd party equipment (lighting) On/Off control with the use of WAGO DO module.

▪ iTM support up to 3 demand control signals

▪ A facility manager can use the iTM web function to configure or disable the demand control remotely.

Di2 Di3

Signals from a

demand controller

iTM Web interface

(PC)

© 2021 Daikin North America, LLC

• Enable “Power Limit control” through the Dealer Option

Demand Control

▪ Energy Save Mode icon will be available on the Service Settings Menu

Energy Saving

is the default

selected option

© 2021 Daikin North America, LLC

Demand Control

• Enable “Power Limit controller interlock Mode”

• A 3rd party demand controller signals can be interlocked with the iTM’s digital inputs (Di2,Di3 and Di4)

Power Limit Controller Interlock Mode

Level2

Level3

Level1

Schematic drawing of the Di connection

Associate the

demand controller

signals to the digital

inputs

Select Power limit

controller Interlock

Mode

© 2021 Daikin North America, LLC

Demand Control

How demand control works?

▪ The below table shows the load cut-off levels corresponding to the iTM Di inputs

© 2021 Daikin North America, LLC

Demand Control

Example of switching to a higher level Example of switching to a lower level

Once an input signal

turns on, demand

control switches to

the corresponding

load cut off level

Demand Control doesn’t switch to a lower

load cut off level for 5 min. after turning on. (if

the level 3 signal turns off withing 5 min. after

turning on, the load cut off level remains at 3

without changing to 0

5min. After the input

signal turns on, the

load cut off level

changes to a lower

level (5 min. later,

only the level 2 is

on. Therefore, the

load cut off level

changes to 2)

© 2021 Daikin North America, LLC

Demand Control

Three different control strategies

Indoor Unit Settings Temp Control

Outdoor Unit Capacity Control

Indoor Unit Thermo On/Off Control

▪ Decide on the demand control strategy based on the project requirement.

▪ Avoid applying demand control to critical zones like server rooms

© 2021 Daikin North America, LLC

Demand Control

Indoor Unit Settings Temp Control

Setpoint shift based on the configured levels from the current setpoint.

▪ Up to 128 indoor units can be assigned per group

▪ Up to 8 control groups

▪ It is not possible to register one unit (management point) in more than one groups.

▪ Configured cooling setpoint upper limit and heating setpoint lower limit.

▪ Example:

▪ If the indoor unit is in cooling 72F and level 2 signal is activated, the cooling setpoint will be shifted to 74F

▪ If level 3 signal is activated, the cooling setpoint will be shifted to 76F (2F setpoint shift)

▪ When the signal is released, the cooling setpoint will go back to 72F(4F setpoint shift)

4

Note: Cut-off Level 3 should be always the highest level of energy saving.

© 2021 Daikin North America, LLC

Demand Control

• A group of outdoor units can be assigned to capacity limit control logic

• Outdoor unit capacity can be configured for 0, 40, 70,100% when the digital input signal activated.

• Multiple levels of reduced capacity can be applied

• Example:

• When the level 2 signal is activated, the ODU capacity will be reduced to 40%.

Outdoor Unit Capacity Control

Note: • Cut-off Level 3 should be always the highest level of energy saving.

• Outdoor unit capacity control is only applicable for VRV system.

© 2021 Daikin North America, LLC

Demand Control

• A group of indoor units can be assigned to the demand signal level for the thermo on/off control.

• Example:

• When the demand control signal for level 1 is activated, the indoor units in the group control A will be forced thermo-off.

• The remote controller will display “S” icon (Energy Saving)

Indoor Unit Thermo On/Off Control

Note: Cut-off Level 3 should be always the highest level of energy saving.

© 2021 Daikin North America, LLC

Demand Control

Control Status Screen

The display is refreshed

automatically every 30

seconds.

Displays the

current

setpoint shift

amount

Displays the

current ODU

capacity

control value

Displays the

current on/off

status

© 2021 Daikin North America, LLC

Demand Control

Display updates when power limit control is activated

Outdoor unit is

under power limit

control

Power limit

control icon Power limit

control icon

Indoor units are

under power limit

control

Displayed when any of the demand control program is executed

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

Outdoor unit Operation Data Compatibility

▪ VRV4

▪ RXYQ_T(A)

▪ REYQ_T(A)

▪ RXLQ_T(A) - Aurora

▪ RXLQ_T(A) - 575V Aurora

▪ RELQ_T(A) - Aurora

▪ RELQ_T(A) - 575V Aurora

▪ VRV 4X:

▪ REYQ_XA

▪ RXYQ_XA

▪ VRVW (T): RWEQ_T

▪ VRVW_IV: RWEYQ_PC

▪ VRV3

▪ RXYQ_PA

▪ REYQ_PA

▪ RXYQ_PB

▪ REYQ_PB

▪ REYQ_PC

▪ VRV3S: RXYMQ_P

▪ VRV III W: RWEYQ_P

▪ VRV LIFE: RXSQ_TA

▪ VRV4S: RXTQ_TA

Not Applicable for SkyAir, Mini-split, Multi-Split.

VRV Indoor unit compatibility is not affected by this table.

Commissioning by AirNet Engineering Tool is Required

NEW

NEWNEW

NEW

NEW

NEW

NEW

NEW

NEW

NEW

NEW

© 2021 Daikin North America, LLC

• Records data every 1 minute for a rolling 5-days period.

• Indoor unit functional data (setpoint, mode, room temperature etc.)

• Indoor unit operation data (liquid pipe temperature, gas pipe temp etc.)

• Outdoor unit operation data (inverter speed, fan step etc.)

• External I/O points

• BACnet client management points.

• User can specify start and end date and time for the data download.

• Trend CSV is generated for each of the categories below:

• Indoor units

• Outdoor unit

• WAGO and BACnet Client Points

• AirNet Engineering tool is required to address IDU and ODU to get operational data.

• Macro tool to review and process the data is available from Daikin City.

Operation Data

USB

Computer with web access

© 2021 Daikin North America, LLC

• Data can be downloaded from the Operation Data Export menu.

• Download data by using the menu function from the iTouch Manager or by using the web function.

• You can specify start and end data & time for the data export.

• The data is available in CSV format.

Operation Data

Trendlog can be downloaded using a USB drive or by using web browser.

© 2021 Daikin North America, LLC

Standard Trendlog Data# Point Name Description # Point Name Description

1 Occupancy ModeDisplays Occupancy status of indoor unit; available

with DCM014A5116 Fan Speed Monitors fan speed of the indoor unit

2 Unit On_Off Status Monitors indoor unit On/Off status 17 Airflow Direction Monitors airflow direction of the indoor unit

3 Alarm Status Monitors alarms status of indoor unit 18 Timed Override Operation Monitor timed override status of the indoor unit

4 Error Code Monitors and displays error code of the unit. 19 Current Unit OperationMonitor the current unit operation of indoor

unit.

5 Room Temperature Monitor the room temperature of indoor unit 20 Remote Controller Prohibit (On_Off)Monitor remote controller On/Off button

prohibit status.

6 Occ Cooling Setpoint Monitor the occupied cooling setpoint 21 Remote Controller Prohibit (Operation Mode)Monitor remote controller operation mode

button status.

7 Occ Heating Setpoint Monitor the occupied heating setpoint 22 Remote Controller Prohibit (Setpoint)Monitor remote controller setpoint button

status.

8 Unocc Cooling Setpoint Monitor the unoccupied cooling setpoint 23 Filter Sign Status Monitor filter status of indoor unit

9 Unocc Heating Setpoint Monitor the unoccupied cooling setpoint 24 Filter Sign Reset Monitor the filer sign reset command status

10 Max Cooling Setpoint Monitor the maximum cooling setpoint 25 Indoor Fan Status Monitor the indoor unit fan status

11 Min Cooling Setpoint Monitor the minimum cooling setpoint 26 Thermo-on Status Monitor the indoor unit thermo-on status

12 Max Heating Setpoint Monitor the maximum heating setpoint 27 Compressor Status Monitor the compressor status

13 Min Heating Setpoint Monitor the minimum heating setpoint 28 Aux Heater Status Monitor the Aux.heater status

14 Min Setpoint Differential (Cooling & Heating) Monitor setpoint differential 29 Forced Thermo-off Monitor the forced thermo off status

15 Cooling & Heating Setpoint Tracking Mode Monitor heating and cooling tracking mode 30 Indoor Unit Changeover OptionMonitor the indoor unit changeover option

status

© 2021 Daikin North America, LLC

Indoor Unit Operation Data Log

# Point Name Description

1 Discharge Air Temperature Monitors and displays the discharge air temperature of the FXMQ_PB indoor unit. (displays zero all other units)

2 Liquid Pipe Temperature Monitors and displays the liquid pipe temperature.

3 Gas Pipe Temperature Monitors and displays the gas pipe temperature.

4 EEV Position Monitors and displays the electronic expansion valve position.

5 Freeze Protection Monitors if the freeze protection is active for FXFQ_T, FXUQ_P or FXEQ_P indoor unit. (displays Off all other unit)

6 Return Air Temperature Monitor and displays the return air temperature.

© 2021 Daikin North America, LLC

General ODU Operation in Log

# Point Name Description

1 Communication Status Monitors and displays the communication status

2 Operation Mode Monitors and displays the operation mode (Cool, Heat, Fan or Heat &Cool)

3 Outdoor Unit Alarm Status Monitors whether or not the outdoor unit is operating normally.

4 Defrost Mode Monitors if the defrost mode is active.

5 Oil Return Mode Monitors whether or not the outdoor unit is in oil return operation.

6 Electric Power Monitors and displays the electric power. Calculated

7 Electric Current Monitors and displays the electric current. Calculated

8 System Capacity Code Monitors and displays the system capacity code.

9 Outdoor Air Temperature Monitors and displays the outdoor air temperature.

Not Applicable SkyAir, Mini-split, Multi-Split

© 2021 Daikin North America, LLC

Main/Sub-1/Sub-2 ODU Operation in Log# Point Name Description # Point Name Description

1 Condensing Pressure Monitors and displays the condensing pressure 12 Liquid Pipe TemperatureMonitors and displays the liquid pipe

temperature

2 Evaporating Pressure Monitors and displays the evaporating pressure 13 Liquid Pipe Temperature (HX Upper)Monitors and displays the liquid pipe

temperature for the upper HX

3 Condensing Temperature Monitors and displays the condensing temperature 14 Liquid Pipe Temperature (HX Lower)Monitors and displays the liquid pipe

temperature for the lower HX

4 Evaporating Temperature Monitors and displays the evaporating temperature 15 Liquid Pipe Temperature (De-Icer)Monitors and displays the liquid pipe

temperature for the de-icer

5 Inverter Compressor 1 SpeedMonitors and displays the speed of the inverter

compressor1 16 Gas Pipe Temperature (HX Upper)

Monitors and displays the gas pipe temperature

for the upper HX

6 Inverter Compressor 2 SpeedMonitors and displays the speed of the inverter

compressor2 17 Gas Pipe Temperature (HX Lower)

Monitors and displays the gas pipe temperature

for the lower HX

7 Fan Step Monitors and displays the fan step 18 Suction Temperature Monitors and displays the suction temperature

8 EV Position 1Monitors and displays the position of the expansion

valve1 19 Compressor Suction Temperature

Monitors and displays the compressor’s suction

temperature

9 EV position 2Monitors and displays the position of the expansion

valve2 20 Subcool Inlet Temperature

Monitors and displays the subcool inlet

temperature

10 Hot Gas Temperature (Compressor 1)Monitors and displays the hot gas temperature of the

compressor1 21 Subcool Outlet temperature

Monitors and displays the subcool outlet

temperature

11 Hot Gas Temperature (Compressor 2)Monitors and displays the hot gas temperature of the

compressor2 22 Subcool EV Position

Monitors and displays the subcool expansion

valve position

Not Applicable SkyAir, Mini-split, Multi-Split

© 2021 Daikin North America, LLC© 2021 Daikin North America, LLC

✓ Introduction

✓ HTTP option

✓ Hydrobox control

✓ Schedule update

✓ Demand control

✓ Operation data update

✓ Summary

iTouch

Manager

© 2021 Daikin North America, LLC

• HTTP function allows VRV integration to BMS and Home Automation

Systems

• PPD is compatible with BACnet Server for ITM v2.10

• iTM v2.10 is compatible with HTML5 supported web browsers like

Microsoft Edge.

• Allows user to login to iTM from Mobile devices (Android, IOS)

• Operation data is supported for VRV, VRV-W, VRVs and VRV Life

models

• Also, BACnet ODU data points are available.

• Energy Saving function allows demand control to the VRV system