ITER CODAC

45
F4E Industrial Colloquium Barcelona,Oct. 2008 1 ITER CODAC Wolf-Dieter Klotz ITER Organization, Cadarache, France

description

ITER CODAC. Wolf-Dieter Klotz ITER Organization, Cadarache, France. ITER at a glance CODAC overall architecture ITER procurement model Standardization for Instrumentation & Control (I&C). Toroidal Field Coil Nb 3 Sn, 18, wedged. Central Solenoid Nb 3 Sn, 6 modules. Poloidal Field Coil - PowerPoint PPT Presentation

Transcript of ITER CODAC

Page 1: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

1

ITER CODAC

Wolf-Dieter Klotz

ITER Organization, Cadarache, France

Page 2: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

2

• ITER at a glance

•CODAC overall architecture

• ITER procurement model

•Standardization for

Instrumentation & Control (I&C)

Page 3: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

4

The Core of ITER

Toroidal Field CoilNb3Sn, 18, wedged

Central SolenoidNb3Sn, 6 modules

Poloidal Field CoilNb-Ti, 6

Vacuum Vessel9 sectors

Port Plug heating/current drive, test blanketslimiters/RHdiagnostics

Cryostat24 m high x 28 m dia.

Blanket440 modules

Torus Cryopumps, 8

Major plasma radius 6.2 m

Plasma Volume: 840 m3

Plasma Current: 15 MA

Typical Density: 1020 m-3

Typical Temperature: 20 keV

Fusion Power: 500 MW

Machine mass: 23350 t (cryostat + VV + magnets)- shielding, divertor and manifolds: 7945 t + 1060 port plugs- magnet systems: 10150 t; cryostat:  820 t

Divertor54 cassettes

29m

~28m

Page 4: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

6

Tokamak building

Tritium building

Cryoplant buildings

Magnet power convertors buildings

Hot cell

Cooling towers

The ITER Site

• Area about 60 ha• Buildings up to 60m high and 200m long

Page 5: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

7

ITER Site Preparation

Courtesy AIFCourtesy AIF

• The building construction permit was granted in April, 2008.

• Building construction will begin in 2009.

• The building construction permit was granted in April, 2008.

• Building construction will begin in 2009.

Page 6: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

8

International Cooperation

Seven Parties are involved in ITER Construction

Page 7: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

10

Construction Sharing

C

“Contributions in Kind”Major systems provided directly

by Parties

B

Residue of systems,jointly funded,purchased by

ITER Project Team

A

Systems suited only to Host Party industry- Buildings- Machine assembly- System installation- Piping, wiring, etc.- Assembly/installation labour

Overall cost sharing: EU 5/11, Others 6 Parties 1/11 each

Overall contingency up to 10% of total.

Total amount: 3577 kIUA (5079 M€-2007)

Overall costs shared according to agreed evaluation of A+B+C

Page 8: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

11

What makes ITER different?• Internationally exploited experiment

• “In-kind” procurement from 7 Parties

• Nuclear installation – new rules

• Reliability/availability higher than any

previous fusion project

• Continuous operation rather than pulsed

• Long timescale to construct, operate,

maintain

Page 9: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

12

Roles & Responsibilities for Roles & Responsibilities for ConstructionConstruction

ITER Organization Seven Parties

•Planning/Design •Integration / QA / Safety / Licensing / Schedule

•Installation •Testing + Commissioning

•Operation

•Detailing / Designing

•Procuring•Delivering•Support installation

Page 10: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

13

CODAC Architecture

Page 11: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

14

ITER seen by CODACControl, Data Access and

Communication

• ~150 ‘one off’ industrial plant systems • delivered ‘in-kind’ with corresponding

package• including

•science•diagnostics•plasma control•industrial control

• interconnected by dedicated networks

• ~150 ‘one off’ industrial plant systems • delivered ‘in-kind’ with corresponding

package• including

•science•diagnostics•plasma control•industrial control

• interconnected by dedicated networks

Page 12: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

15

3 Tier Segregation

CODAC PBS 4.5

Interlocks PBS 4.6

Nucl.Safety

PBS 4.8

Comm. overNetworks

Page 13: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

16

Remote AccessCODAC - 4.5

CIS - 4.6

CSS - 4.8

Plant Operation

Zone

Plant Operation

Zone

Page 14: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

17

A Different View

Page 15: ITER CODAC

18

CONTROL INTERLOCK SAFETY

Page 16: ITER CODAC

19

PLANT SYSTEMS

CODAC, CIS, CSSPBS 4.5, 4.6, 4.7

Page 17: ITER CODAC

20

Page 18: ITER CODAC

21

Page 19: ITER CODAC

22

Page 20: ITER CODAC

23

Page 21: ITER CODAC

24

80-100

Page 22: ITER CODAC

25

60-80

Page 23: ITER CODAC

26

<60

Page 24: ITER CODAC

27

unknown

Page 25: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

28

CODAC Integrates all Systems

Page 26: ITER CODAC

29

• Control room equipment

•Engineering and configuration workstations

•Scientific tools

•Remote control rooms management SW

•Mass data storage

•Configuration databases

•Central supervision system

•Central Alarm system

•Central timing system

•Plant interface systems

•Fast control systems

•Fast data acquisition systems

•Plant monitoring systems

•Slow control systems

•Industrial automation and control

• Process instrumentation

•Various type of networks

CODAC required equipment

Page 27: ITER CODAC

30

• Highly reliable and available PLC systems (SIL3 and class 2)

• Various type of transducers

• Various type of networks: TCP/IP, Safety field buses, monitored hardwired links

• Supervisory systems

• Long term safe data storage

• Safety operator’s desks

Interlock & Safety required equipment

Page 28: ITER CODAC

31

• I&C Support for plant systems

• Eng. support for CODAC

• Eng. support for Interlock&Safety

• Technical specifications

• Engineering Design

• Detailed Design

• Prof-of-concept with prototypes

• Procurement of equipment

• SW programming

• HW assembly

• HW and SW integration

• Factory testing

• Installation and Commissioning

CODAC, Interlock & Safety required activities

Page 29: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

32

20192018201720162015201420132012201120102009

Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1

I&C Support for Plant Systems

CODAC Support

Central Interlock and Safety Systems Support

I&C Plant Systems DevelopmentI&C Plant Systems DevelopmentI&C Plant Systems DevelopmentI&C Plant Systems realization (~ x100)

CODAC sub-systems DevelopmentCODAC sub-systems DevelopmentCODAC sub-systems DevelopmentCODAC sub-systems realization (~x 10)

Central Safety Systems realization (x 3)

Central Interlock Systems realization (x 3)

In fund, contracts placed by ITER IOIn kind, contracts placed by ITER DAsTask agreements, most probably no contracts with with Industry

Assistance Contracts

Central Safety Systems realization (x 3)Central Safety Systems realization (x 3)

Central Interlock Systems realization (x 3)Central Interlock Systems realization (x 3)

Start Integrated commissioning

First Plasma

Procurement Contracts

Start of Tokamak assembly

Prototypes realization (x 10)Prototypes realization (x 10)

ITER IO Contract Strategy

Page 30: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

33

ITER Procurement Model

Page 31: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

34

Fund versus In-Kind Procurement

IN KIND - Procurement

IN FUND - Procurement

Page 32: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

35

Procurement Allocation pg.1

Page 33: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

36

Procurement Allocation pg.2

Page 34: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

37

Procurement Allocation pg.3

Page 35: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

38

Procurement Allocation pg.4

Page 36: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

39

Plant System I&C Costs• Assume CODAC + Plant System I&C is 7% of total cost

• low end of typical range

• amounts to about ➟ 317M€

• CODAC (the supervisory part) + CIS + CSS is funded at ➟ 75M

• needs to be verified if CSS can be included

• A first (top-down) estimate of Plant System I&C inside procurement arrangements is therefore the remaining ➟ 242M€

• EU has ~32.9% of procurement, and probably a greater fraction (~42.2%) of Plant System I&C ➟ 102M€

• ~75% is dominated by engineering costs ➟ 76.8M€, rather than component costs ➟ 25.2M€

Page 37: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

40

Procurement Schedule

YEAR 2008 2009 2010 2011 2012

No.of

Procurements13 32 22 11 6

extracted form Integrated Project ScheduleIPS version 16-May-2008

• Peak in preparing Procurement Arrangements: now to 2010• no new Procurement Arrangements after 2012

Page 38: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

41

CODAC BoundaryCODAC componentProvided to supplier“Ambassador”

CODAC componentProvided to supplier“Ambassador”

Procurement agreementFactory-testingSite acceptanceCommissioning

Procurement agreementFactory-testingSite acceptanceCommissioning

CODAC componentProvided to supplier“Ambassador”

CODAC componentProvided to supplier“Ambassador”

Page 39: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

42

The Procurement Chain

Page 40: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

43

Integrated Project Teams in the DAs

• There is need for efficient communication between CODAC and the Domestic Agency.

• A model is suggested based on expert centers in the DAs.

• Experts from the different DAs could spend time in Cadarache to develop a full understanding of CODAC, while at the same time contributing to the development of CODAC itself.

• When in their Participant Teams, their knowledge can be passed on to the domestic industries or research institutions which, in turn, enhance the contact with the end-suppliers.

Page 41: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

44

Standardization for Instrumentation &

Control

Page 42: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

45

Reliability, Availability and Serviceability (RAS) Open Standards Conservative Solutions Commercial off-the-shelf (COTS) Minimize New Development Very easy to use Low Risk Fast Delivery Low Total cost per channel Bottom Up and Top Down Engineering to PLC

Standards RequirementsProcurement cannot work without Standardization

Page 43: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

46

Standards ToBeDefined’sProcurement cannot work without Standardization

• Plant System Controllers• PLCs• PCs/PCI• Chassis based systems: Compact PCI, PXI, ATCA, AMC, μTCA

• Open Software• Operating Systems (LINUX distribution)• SCADA frameworks: EPICS, TANGO• RT-OS

• Development Methodologies/Frameworks• PLC programming• Application IDEs: Eclipse, Control Studio, ...

• Network Standards based on Gbit Ethernet• Protocols over IP and TCP

Page 44: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

47

Standards How To - 3 SourcesProcurement cannot work without Standardization

• Plant System Host - will be provided by CODAC• works as gateway between Plant System and CODAC• contains communication middleware• maps plant data and protocols to a universal CODAC format

• miniCODAC - will be provided by CODAC• works as portable system for plant design and SAT (may be FAT as well)• contains SCADA tools to set up autonomous plant control systems

• Plant Control Design Handbook - is provided by CODAC• is the reference for mandatory and recommended standards

Page 45: ITER CODAC

F4E Industrial Colloquium Barcelona,Oct. 2008

48

The End