ITER CODAC
description
Transcript of ITER CODAC
F4E Industrial Colloquium Barcelona,Oct. 2008
1
ITER CODAC
Wolf-Dieter Klotz
ITER Organization, Cadarache, France
F4E Industrial Colloquium Barcelona,Oct. 2008
2
• ITER at a glance
•CODAC overall architecture
• ITER procurement model
•Standardization for
Instrumentation & Control (I&C)
F4E Industrial Colloquium Barcelona,Oct. 2008
4
The Core of ITER
Toroidal Field CoilNb3Sn, 18, wedged
Central SolenoidNb3Sn, 6 modules
Poloidal Field CoilNb-Ti, 6
Vacuum Vessel9 sectors
Port Plug heating/current drive, test blanketslimiters/RHdiagnostics
Cryostat24 m high x 28 m dia.
Blanket440 modules
Torus Cryopumps, 8
Major plasma radius 6.2 m
Plasma Volume: 840 m3
Plasma Current: 15 MA
Typical Density: 1020 m-3
Typical Temperature: 20 keV
Fusion Power: 500 MW
Machine mass: 23350 t (cryostat + VV + magnets)- shielding, divertor and manifolds: 7945 t + 1060 port plugs- magnet systems: 10150 t; cryostat: 820 t
Divertor54 cassettes
29m
~28m
F4E Industrial Colloquium Barcelona,Oct. 2008
6
Tokamak building
Tritium building
Cryoplant buildings
Magnet power convertors buildings
Hot cell
Cooling towers
The ITER Site
• Area about 60 ha• Buildings up to 60m high and 200m long
F4E Industrial Colloquium Barcelona,Oct. 2008
7
ITER Site Preparation
Courtesy AIFCourtesy AIF
• The building construction permit was granted in April, 2008.
• Building construction will begin in 2009.
• The building construction permit was granted in April, 2008.
• Building construction will begin in 2009.
F4E Industrial Colloquium Barcelona,Oct. 2008
8
International Cooperation
Seven Parties are involved in ITER Construction
F4E Industrial Colloquium Barcelona,Oct. 2008
10
Construction Sharing
C
“Contributions in Kind”Major systems provided directly
by Parties
B
Residue of systems,jointly funded,purchased by
ITER Project Team
A
Systems suited only to Host Party industry- Buildings- Machine assembly- System installation- Piping, wiring, etc.- Assembly/installation labour
Overall cost sharing: EU 5/11, Others 6 Parties 1/11 each
Overall contingency up to 10% of total.
Total amount: 3577 kIUA (5079 M€-2007)
Overall costs shared according to agreed evaluation of A+B+C
F4E Industrial Colloquium Barcelona,Oct. 2008
11
What makes ITER different?• Internationally exploited experiment
• “In-kind” procurement from 7 Parties
• Nuclear installation – new rules
• Reliability/availability higher than any
previous fusion project
• Continuous operation rather than pulsed
• Long timescale to construct, operate,
maintain
F4E Industrial Colloquium Barcelona,Oct. 2008
12
Roles & Responsibilities for Roles & Responsibilities for ConstructionConstruction
ITER Organization Seven Parties
•Planning/Design •Integration / QA / Safety / Licensing / Schedule
•Installation •Testing + Commissioning
•Operation
•Detailing / Designing
•Procuring•Delivering•Support installation
F4E Industrial Colloquium Barcelona,Oct. 2008
13
CODAC Architecture
F4E Industrial Colloquium Barcelona,Oct. 2008
14
ITER seen by CODACControl, Data Access and
Communication
• ~150 ‘one off’ industrial plant systems • delivered ‘in-kind’ with corresponding
package• including
•science•diagnostics•plasma control•industrial control
• interconnected by dedicated networks
• ~150 ‘one off’ industrial plant systems • delivered ‘in-kind’ with corresponding
package• including
•science•diagnostics•plasma control•industrial control
• interconnected by dedicated networks
F4E Industrial Colloquium Barcelona,Oct. 2008
15
3 Tier Segregation
CODAC PBS 4.5
Interlocks PBS 4.6
Nucl.Safety
PBS 4.8
Comm. overNetworks
F4E Industrial Colloquium Barcelona,Oct. 2008
16
Remote AccessCODAC - 4.5
CIS - 4.6
CSS - 4.8
Plant Operation
Zone
Plant Operation
Zone
F4E Industrial Colloquium Barcelona,Oct. 2008
17
A Different View
18
CONTROL INTERLOCK SAFETY
19
PLANT SYSTEMS
CODAC, CIS, CSSPBS 4.5, 4.6, 4.7
20
21
22
23
24
80-100
25
60-80
26
<60
27
unknown
F4E Industrial Colloquium Barcelona,Oct. 2008
28
CODAC Integrates all Systems
29
• Control room equipment
•Engineering and configuration workstations
•Scientific tools
•Remote control rooms management SW
•Mass data storage
•Configuration databases
•Central supervision system
•Central Alarm system
•Central timing system
•Plant interface systems
•Fast control systems
•Fast data acquisition systems
•Plant monitoring systems
•Slow control systems
•Industrial automation and control
• Process instrumentation
•Various type of networks
CODAC required equipment
30
• Highly reliable and available PLC systems (SIL3 and class 2)
• Various type of transducers
• Various type of networks: TCP/IP, Safety field buses, monitored hardwired links
• Supervisory systems
• Long term safe data storage
• Safety operator’s desks
Interlock & Safety required equipment
31
• I&C Support for plant systems
• Eng. support for CODAC
• Eng. support for Interlock&Safety
• Technical specifications
• Engineering Design
• Detailed Design
• Prof-of-concept with prototypes
• Procurement of equipment
• SW programming
• HW assembly
• HW and SW integration
• Factory testing
• Installation and Commissioning
CODAC, Interlock & Safety required activities
F4E Industrial Colloquium Barcelona,Oct. 2008
32
20192018201720162015201420132012201120102009
Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1 Q4Q3Q2Q1
I&C Support for Plant Systems
CODAC Support
Central Interlock and Safety Systems Support
I&C Plant Systems DevelopmentI&C Plant Systems DevelopmentI&C Plant Systems DevelopmentI&C Plant Systems realization (~ x100)
CODAC sub-systems DevelopmentCODAC sub-systems DevelopmentCODAC sub-systems DevelopmentCODAC sub-systems realization (~x 10)
Central Safety Systems realization (x 3)
Central Interlock Systems realization (x 3)
In fund, contracts placed by ITER IOIn kind, contracts placed by ITER DAsTask agreements, most probably no contracts with with Industry
Assistance Contracts
Central Safety Systems realization (x 3)Central Safety Systems realization (x 3)
Central Interlock Systems realization (x 3)Central Interlock Systems realization (x 3)
Start Integrated commissioning
First Plasma
Procurement Contracts
Start of Tokamak assembly
Prototypes realization (x 10)Prototypes realization (x 10)
ITER IO Contract Strategy
F4E Industrial Colloquium Barcelona,Oct. 2008
33
ITER Procurement Model
F4E Industrial Colloquium Barcelona,Oct. 2008
34
Fund versus In-Kind Procurement
IN KIND - Procurement
IN FUND - Procurement
F4E Industrial Colloquium Barcelona,Oct. 2008
35
Procurement Allocation pg.1
F4E Industrial Colloquium Barcelona,Oct. 2008
36
Procurement Allocation pg.2
F4E Industrial Colloquium Barcelona,Oct. 2008
37
Procurement Allocation pg.3
F4E Industrial Colloquium Barcelona,Oct. 2008
38
Procurement Allocation pg.4
F4E Industrial Colloquium Barcelona,Oct. 2008
39
Plant System I&C Costs• Assume CODAC + Plant System I&C is 7% of total cost
• low end of typical range
• amounts to about ➟ 317M€
• CODAC (the supervisory part) + CIS + CSS is funded at ➟ 75M
• needs to be verified if CSS can be included
• A first (top-down) estimate of Plant System I&C inside procurement arrangements is therefore the remaining ➟ 242M€
• EU has ~32.9% of procurement, and probably a greater fraction (~42.2%) of Plant System I&C ➟ 102M€
• ~75% is dominated by engineering costs ➟ 76.8M€, rather than component costs ➟ 25.2M€
F4E Industrial Colloquium Barcelona,Oct. 2008
40
Procurement Schedule
YEAR 2008 2009 2010 2011 2012
No.of
Procurements13 32 22 11 6
extracted form Integrated Project ScheduleIPS version 16-May-2008
• Peak in preparing Procurement Arrangements: now to 2010• no new Procurement Arrangements after 2012
F4E Industrial Colloquium Barcelona,Oct. 2008
41
CODAC BoundaryCODAC componentProvided to supplier“Ambassador”
CODAC componentProvided to supplier“Ambassador”
Procurement agreementFactory-testingSite acceptanceCommissioning
Procurement agreementFactory-testingSite acceptanceCommissioning
CODAC componentProvided to supplier“Ambassador”
CODAC componentProvided to supplier“Ambassador”
F4E Industrial Colloquium Barcelona,Oct. 2008
42
The Procurement Chain
F4E Industrial Colloquium Barcelona,Oct. 2008
43
Integrated Project Teams in the DAs
• There is need for efficient communication between CODAC and the Domestic Agency.
• A model is suggested based on expert centers in the DAs.
• Experts from the different DAs could spend time in Cadarache to develop a full understanding of CODAC, while at the same time contributing to the development of CODAC itself.
• When in their Participant Teams, their knowledge can be passed on to the domestic industries or research institutions which, in turn, enhance the contact with the end-suppliers.
F4E Industrial Colloquium Barcelona,Oct. 2008
44
Standardization for Instrumentation &
Control
F4E Industrial Colloquium Barcelona,Oct. 2008
45
Reliability, Availability and Serviceability (RAS) Open Standards Conservative Solutions Commercial off-the-shelf (COTS) Minimize New Development Very easy to use Low Risk Fast Delivery Low Total cost per channel Bottom Up and Top Down Engineering to PLC
Standards RequirementsProcurement cannot work without Standardization
F4E Industrial Colloquium Barcelona,Oct. 2008
46
Standards ToBeDefined’sProcurement cannot work without Standardization
• Plant System Controllers• PLCs• PCs/PCI• Chassis based systems: Compact PCI, PXI, ATCA, AMC, μTCA
• Open Software• Operating Systems (LINUX distribution)• SCADA frameworks: EPICS, TANGO• RT-OS
• Development Methodologies/Frameworks• PLC programming• Application IDEs: Eclipse, Control Studio, ...
• Network Standards based on Gbit Ethernet• Protocols over IP and TCP
F4E Industrial Colloquium Barcelona,Oct. 2008
47
Standards How To - 3 SourcesProcurement cannot work without Standardization
• Plant System Host - will be provided by CODAC• works as gateway between Plant System and CODAC• contains communication middleware• maps plant data and protocols to a universal CODAC format
• miniCODAC - will be provided by CODAC• works as portable system for plant design and SAT (may be FAT as well)• contains SCADA tools to set up autonomous plant control systems
• Plant Control Design Handbook - is provided by CODAC• is the reference for mandatory and recommended standards
F4E Industrial Colloquium Barcelona,Oct. 2008
48
The End