ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local...

46
Development Management Ref No 0/2012/2295 No weeks on day of committee PPA Expires - 21/03/14 Parish Wokingham Crest Nicholson Operations Ltd Ward Norreys Kentwood Farm West Warren House Road Wokingham ITEM NO: 112.00 Listed By Major Applicant Location Proposal Hybrid application, Phase 2 of the North Wokingham Strategic Development Location. Outline Application for the development of up to 225 dwellings and associated works at Kentwood Farm West (Phase 2 of the North Wokingham Strategic Development Location) (all matters reserved). Type PS Category Officer Outline 1 Connor Corrigan FOR CONSIDERATION BY REPORT PREPARED BY Planning Committee on 5 March 2014 Head of Development Management SUMMARY 1) The application site is situated to the north of Wokingham and forms part of the Strategic Development Location, as identified within the Core Strategy. 2) The site forms part of the Kentwood Farm development site which is an allocated site for a total of 510 dwellings. The two development sites are split by Warren House Road. The eastern section has planning consent for 274 dwellings (ref: 0/2011/0699). This site has commenced with the roundabout forming part of the access to this site on Warren House Road being constructed. 3) The proposal is for an outline application which sets out the principle of housing in this location for up to 225 dwellings. All matters, such as landscaping, design and access, are reserved. The application does provide an indicative layout and access to the south onto Warren House Road. The proposal will provide a section of the Northern Distributor Road running though the site. 4) The SANG and noise bund required for this development, which comprises the construction of a 3.5 metre high landform and 2.5 metre fence running parallel with the A329(M) to act as a noise barrier for the A329(M) was approved under the 2011 consent. The SANG is already laid out and comprises ponds which will accommodate Great Crests Newt's from the Phase 1 site. 5) The Local Planning Authority considered an Environmental Impact Assessment as part of this development proposal and it was found to be acceptable. 6) The North Wokingham Consortia are made up of Crest Nicholson (Kentwood) and Bovis and Gleeson Homes (Matthewsgreen) areas. PLANNING STATUS Within North Wokingham Strategic Development Area 7KM Thames Basin Heath SPA Great Crested Newt Consultation Zone Aerodrome Safequardinq for Wind 5

Transcript of ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local...

Page 1: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Development Management Ref No 0/2012/2295

No weeks on day of committee PPA Expires -21/03/14

Parish

Wokingham

Crest Nicholson Operations Ltd

Ward

Norreys

Kentwood Farm West Warren House Road Wokingham

ITEM NO: 112.00 Listed By

Major

Applicant Location Proposal Hybrid application, Phase 2 of the North Wokingham Strategic Development

Location.

Outline Application for the development of up to 225 dwellings and associated works at Kentwood Farm West (Phase 2 of the North Wokingham Strategic Development Location) (all matters reserved).

Type PS Category Officer

Outline 1 Connor Corrigan

FOR CONSIDERATION BY REPORT PREPARED BY

Planning Committee on 5 March 2014 Head of Development Management

SUMMARY 1) The application site is situated to the north of Wokingham and forms part of the Strategic

Development Location, as identified within the Core Strategy.

2) The site forms part of the Kentwood Farm development site which is an allocated site for a total of 510 dwellings. The two development sites are split by Warren House Road. The eastern section has planning consent for 274 dwellings (ref: 0/2011/0699). This site has commenced with the roundabout forming part of the access to this site on Warren House Road being constructed.

3) The proposal is for an outline application which sets out the principle of housing in this location for up to 225 dwellings. All matters, such as landscaping, design and access, are reserved. The application does provide an indicative layout and access to the south onto Warren House Road. The proposal will provide a section of the Northern Distributor Road running though the site.

4) The SANG and noise bund required for this development, which comprises the construction of a 3.5 metre high landform and 2.5 metre fence running parallel with the A329(M) to act as a noise barrier for the A329(M) was approved under the 2011 consent. The SANG is already laid out and comprises ponds which will accommodate Great Crests Newt's from the Phase 1 site.

5) The Local Planning Authority considered an Environmental Impact Assessment as part of this development proposal and it was found to be acceptable.

6) The North Wokingham Consortia are made up of Crest Nicholson (Kentwood) and Bovis and Gleeson Homes (Matthewsgreen) areas.

PLANNING STATUS • Within North Wokingham Strategic Development Area • 7KM Thames Basin Heath SPA • Great Crested Newt Consultation Zone • Aerodrome Safequardinq for Wind

5

Page 2: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

1 · Tree Preservation Order

RECOMMENDATION

A. That the committee authorise the Head of Development Management to GRANT PLANNING PERMISSION subject to conditions and completion of the legal agreement including:

• Affordable Housing - 35% (Proposed 30% on-site/ 5% commuted sum)

• Education - Primary (if required), Secondary, Post 16 and SEN (if required)

• Healthcare

• Community Sports I Leisure Facilities - contributions towards Cantley improvements

• Sports Halls

• Swimming Pools

• SANG (Provided by Phase 1) and Strategic Access Monitoring and Maintenance

• Country Park and Countryside Access

• Amenity Open Space I Childrens Play Maintenance Commuted Sums

• Biodiversity

• Children's Play

• Public Rights of Way

• Highways including contribution towards the Strategic Highway Improvements (e.g. FNDR and Coppid Beech roundabout improvements)

• Railway Station Improvements

• Station Link Road

• Coppid Beech Park and Ride

• Travel Plan

• Libraries

• Allotments (allotments on-site)

• Burial

• Community facilities and Community Manager

• Legal and Monitoring fees.

B) And subject to the following conditions it is recommended that planning permission be GRANTED.

6

Page 3: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Plans 1. This permission is in respect of Location Plan (2119-A-1001-D); Site Survey (2119-A-1003-A), Parameter Plan Land Use (2119-SK-1102-B), Parameter Plan Heights (2119-SK-1103-B), Parameter Plan Access and Circulation (2119-SK-1104-B), Parameter Plan Landscape (2119-SK-1105-B), Design and Access Plan dated November 2013; Planning Statement dated November 2013; Preliminary Geo - Environmental Risk Assessment dated October 2013, Aboricultural Constraints and Opportunities (8617 _AN.001) dated November 2013 and Utilities Statement (50401087) dated November 2013. The development hereby permitted shall be carried out in accordance with the approved details unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure that the development is carried out in accordance with the application form and associated details hereby approved.

Reserved Matters 2. a) Approval of the details of the layout, access, scale, external appearance of the building(s), and the landscaping treatment of the site) (hereinafter called "the reserved matters") shall be obtained from the Local Planning Authority in writing before any development is commenced.

b) Application for approval of the reserved matters referred to in a) above shall be made to the Local Planning Authority before the expiration of three years from the date of this permission.

c) The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: In pursuance of s91 of the Town and Country Planning Act 1991 (as amended by s51 of the Planning and Compensation Act 2004).

Materials 3. Before the development hereby permitted is commenced, samples and details of the materials to be used in the construction of the external surfaces of the buildings shall have first been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.

Reason: To ensure a high quality development in accordance with Wokingham Borough Core Strategy Policies CP1 and CP3, Borough Design Guide, CC04 and CC05 of the Managing Development Delivery Local Plan (Feb 2014) and the North Wokingham Strategic Development Location Supplementary Planning Document (October 2011 ).

Levels 4. No development shall take place until a measured survey of the site and a plan prepared to scale of not less than 1 :500 showing details of existing and proposed finished ground levels (in relation to a fixed datum point) and finished floor levels shall be submitted to and approved in writing by the local planning authority, and the approved scheme shall be fully implemented prior to the occupation of the building(s).

Reason: In order to ensure a satisfactory form of development relative to surrounding buildings and landscape. Relevant policy: NPPF and Core Strategy policies CP1 and CP3.

Permitted Development 5. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (as amended) (or any Order revoking and re-enacting that Order with or without modification), no buildings, extensions or alterations permitted by Classes A, B, C, D, E, F and G of Part 1 of the Second Schedule of the 1995 Order (or any order revoking and re-enacting that order with or without modification) shall be carried out.

7

Page 4: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Reason: To safeguard the character of the area and residential amenity of neighbouring properties. Relevant Policies: Core Strategy policies CP1 and CP3.

Lighting 6. The Reserved Matters applications shall include details of all external lighting strategy including lighting for all principle highways, cycleways footpaths and any non-residential buildings which shall be submitted to and approved in writing by the Local Planning Authority. The details including the type of lighting, contour illumination plans and measures to prevent light pollution shall be submitted to and approved in writing by the Local Planning Authority and lighting shall be provided in accordance with the approved details before the site comes into use.

Reason: To prevent an adverse impact upon wildlife and safeguard amenity and highway safety. Relevant Policies: Core Strategy policies CP1, CP3, CP6 and CP7.

Construction Management 7. Before the development hereby permitted is commenced a Construction Environmental Management Plan (CEMP) in respect of that phase shall have been submitted to and approved in writing by the Local Planning Authority. Construction shall not be carried out otherwise than in accordance with each approved CEMP. The CEMP shall include the following matters:

i) a construction travel protocol or Green Travel plan for the construction phase including details of parking and turning for vehicles of site personnel, operatives and visitors; ii) loading and unloading of plant and materials; iii) storage of plant and materials; iv) programme of works (including measures for traffic management and operating hours); v) piling techniques; vi) provision of boundary hoarding; vii) protection of the aquatic environment in terms of water quantity and quality; viii) details of proposed means of dust suppression and noise mitigation; ix) details of measures to prevent mud from vehicles leaving the site during construction; x) details of any site construction office, compound and ancillary facility buildings. These facilities shall be sited away from woodland areas; xi) lighting on site during construction; xii) measures to ensure no on site fires during construction xiii) monitoring and review mechanisms; xiv) implementation of the CEMP through an environmental management system; xv) details of the haul routes to be used to access the development; xvi) details of the temporary surface water management measures to be provided during the construction phase; xvii) details of the excavation of materials and the subsurface construction methodology xviii) appointment of a Construction Liaison Officer.

Reason: To protect occupants of nearby dwellings from noise and disturbance during the construction period, in the interest of highway safety and convenience and to minimise the environmental impact of the construction phase in accordance with Wokingham Borough Core Strategy Policies CP1, CP3 and CP6.

Construction Times 8. No work relating to the development hereby approved, including preparation prior to building operations, shall take place other than between the hours of 07:30 am and 6 pm Monday to Friday and 08:00 am to 1 pm Saturdays and at no time on Sundays or Bank or National Holidays.

Reason: To protect the occupiers of neighbouring properties from noise and disturbance

8

Page 5: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

outside the permitted hours during the construction period. Relevant Policies: Core Strategy policies CP1 and CP3.

Tree Protection and Landscaping 9. Prior to the commencement of the residential development, full details of both hard and soft landscape proposals will have been submitted to and approved in writing by the Local Planning Authority. These details shall include, as appropriate, proposed finished floor levels or contours, means of enclosure, car parking layouts, other vehicle and pedestrian access and circulation areas, hard surfacing materials and minor artefacts and structure (e.g. furniture, play equipment, refuse or other storage units, signs, lighting, external services, etc). Soft landscaping details shall include planting plan, specification (including cultivation and other operations associated with plant and grass establishment), schedules of plants, noting species, planting sizes and proposed numbers/densities where appropriate, and implementation timetable. The details shall include details of the hedgerow along the western and southern boundaries and will demonstrated how these will be retained in perpetuity and include a buffer zone to the development along the western hedgerow.

Reason: In the interests of visual amenity. Relevant Policies: NPPF, Core Strategy policy CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014).

10. All hard and soft landscape works shall be carried out in accordance with the approved details prior to the occupation of any part of the development or in accordance with the timetable agreed with the Local Planning Authority. Any trees or plants which, within a period of five years after planting, are removed, die or become seriously damaged or defective, shall be replaced in the next planting season with others of species, size and number as originally approved and permanently retained.

Reason: In the interests of visual amenity. Relevant Policies: NPPF, Core Strategy policy CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014).

11. No trees, shrubs or hedges within the site which are shown as being retained on the approved plans shall be felled, uprooted wilfully damaged or destroyed, cut back in any way or removed without previous written consent of the Local Planning Authority; any trees, shrubs or hedges removed without consent or dying or being severely damaged or becoming seriously diseased within 5 years from the completion of the development hereby permitted shall be replaced with trees, shrubs or hedge plants of similar size and species unless the Local Planning Authority gives written consent to any variation.

Reason: To secure the protection throughout the time that development is being carried out, of trees, shrubs and hedges growing within the site which are of amenity value to the area. Relevant Policies: NPPF, Core Strategy policy CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014).

12. a) No development or other operations shall commence on site until the works outlined within a to be submitted and approved Arboricultural Method Statement have been implemented which provides for the retention and protection of trees, shrubs and hedges growing on or adjacent the site. No development or other operations shall take place except in complete accordance with the approved protection scheme. b) No operations shall commence on site in connection with development hereby approved (including any tree felling, tree pruning, demolition works, soil moving, temporary access construction and or widening or any other operation involving use of motorised vehicles or construction machinery) until the tree protection works required by the approved scheme are in place on site. c) No excavations for services, storage of materials or machinery, parking of vehicles, deposit or excavation of soil or rubble, lighting of fires or disposal of liquids shall take place within an area designated as being fenced off or otherwise protected in the approved scheme. d) The fencing or other works which are part of the approved scheme shall not be moved or removed, temporarily or otherwise, until all works including external works have

9

Page 6: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

been completed and all equipment, machinery and surplus materials removed from the site, unless the prior approval of the Local Planning Authority has first been sought and obtained.

Reason: To secure the protection throughout the time that development is being carried out, of trees, shrubs and hedges growing within the site which are of amenity value to the area. Relevant Policies: NPPF, Core Strategy policy CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014).

13. Before the residential development hereby permitted is commenced details of all boundary treatment(s) shall first be submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented prior to the first occupation of the development or phased as agreed in writing by the Local Planning Authority. The scheme shall be maintained in the approved form for so long as the development remains on the site.

Reason: To safeguard amenity and highway safety. Relevant policy: Core Strategy policies CP1, CP3 and CP6.

Contamination 14. Before development is commenced, a scheme to deal with potential contamination of the site shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include an investigation and assessment to identify the extent of any contamination and the measures to be taken to avoid risk when the site is developed. No building shall be occupied and the use of public open space shall not commence until the approved measures have been carried out and a validation report has been submitted to and approved in writing by the Local Planning Authority.

Reason: to ensure that any contamination of the site is remedied and to protect existing and future occupants of the application site and adjacent land in accordance with Wokingham Borough Core Strategy Policy CP1.

15. In the event that contamination is found at any time when carrying out the approved development it must be reported in writing immediately to the Local Planning Authority. Any subsequent investigation/remedial/protective works deemed necessary by the LPA shall be carried out to agreed timescales and approved by the LPA in writing. If no contamination is encountered during the development, a letter confirming this fact shall be submitted to the LPA upon completion of the development.

Reason: To ensure any contamination on the site is remedied to protect the existing/proposed occupants of the application site and adjacent land in accordance with Wokingham Borough Core Strategy Policy CP1.

Access and movement 16. Prior to the commencement of development, details of cycle parking shall be submitted and approved in writing by the Local Planning Authority. No building shall be occupied until the cycle parking has been implemented I installed. The cycle parking shall be permanently retained.

Reason: In order to ensure the development contributes towards achieving a sustainable transport system and to provide parking for cycles in accordance with Wokingham Borough Core Strategy Policies CP1 and CP6, the Parking Standards Study within the Borough Design Guide 2010 and the North Wokingham Development Location Supplementary Planning Document (October 2011) and CC07 of the Managing Development Delivery Local Plan (Feb 2014).

17. The reserved matters to comply with Condition 3 shall include details of car and motorcycle parking in accordance with the Council's policies at the time of the reserved

10

Page 7: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

matters application. No dwelling shall be occupied until the vehicular accesses, driveways, parking and turning areas to serve it including any unallocated space have been provided in accordance with the approved details and the provision shall be retained thereafter. The vehicle parking shall not be used for any other purposes other than parking and the turning spaces shall not be used for any other purposes than turning.

Reason: In the interests of highway safety and convenience in accordance with Wokingham Borough Core Strategy Policies CP1 and CP6, CC07 of the Managing Development Delivery Local Plan (Feb 2014), the Parking Standards Study within the Borough Design Guide 2010, and the North Wokingham Development Location Supplementary Planning Document (October 2011 ).

18. No dwelling shall be occupied until the vehicular accesses, driveways, parking and turning areas to serve it including any unallocated space have been provided in accordance with approved details and the provision shall be retained thereafter. The vehicle parking shall not be used for any other purposes other than parking and the turning spaces shall not be used for any other purposes than turning.

Reason: In the interests of highway safety and convenience in accordance with Wokingham Borough Core Strategy Policies CP1 and CP6, CC07 of the Managing Development Delivery Local Plan (Feb 2014), the Parking Standards Study within the Borough Design Guide 201 O and the North Wokingham Strategic Development Location Supplementary Planning Document (February 2010).

19. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (as amended) or any Order revoking and re-enacting that Order within or without modification), any garage, carport or area of parking accommodation on the site shall be kept available for the parking of vehicles ancillary to the residential use of the site at all times. Parking shall be constructed in accordance with the approved plans and shall not be enclosed beyond any enclosure shown on the approved drawings without the prior written approval of the Local Planning Authority. Garages, carports and parking areas shall not be used for any business use nor as habitable space.

Reason: To ensure provision of adequate parking and reduce the likelihood of unplanned roadside parking in accordance with Wokingham Borough Core Strategy Policies CP1 and CP6, CC07 of the Managing Development Delivery Local Plan (Feb 2014), the Parking Standards Study within the Borough Design Guide 2010 and the North Wokingham Development Location Supplementary Planning Document (October 2011 ).

20. Details of any construction access(es) to be provided shall be submitted to, and approved by the Local Planning Authority, prior to commencement of development.

Reason: In the interests of highway safety and convenience in accordance with Wokingham Borough Core Strategy Policies CP1 and CP6.

21. No more than 100 dwellings to be constructed until full detailed designs are submitted for Forest Road I Twyford Road (DWG 1087/SK/006 Rev D) and Warren House Road I Bell Foundry Lane (DWG 1087/SK/004 Rev E) and approved by the Local Planning Authority.

Reason: In the interests of highway safety and convenience. Relevant policy: Core Strategy policies CP1 and CP6 and CCOB of the Managing Development Delivery Local Plan (Feb 2014).

22. Prior to the first occupation of any dwelling, a Parking Management Strategy for the management of on-street parking shall be submitted to and approved in writing by the local planning authority.

11

Page 8: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Reason: to ensure satisfactory development and in the interests of sustainable travel in accordance with Wokingham Borough Core Strategy Policies CP1, CP6 and CP20 and CC07 of the Managing Development Delivery Local Plan (Feb 2014).

23. The development shall not be commenced until either a full travel plan has been submitted to and approved in writing by the Local Planning Authority or the developer has agreed to contribute to the WBC 'My Journey' scheme.

Reason: To ensure the provision of sustainable transport measures in accordance with Wokingham Borough Core Strategy Policies CP1, CP6 and CP20.

24. Prior to the first occupation of any dwelling within the development, a Walking and Cycling Strategy for the whole development shall be submitted to and approved in writing by the Local Planning Authority. The development shall be implemented in accordance with the agreed strategy thereafter.

Reason: To ensure satisfactory development in the interests of sustainable travel in accordance with Wokingham Borough Core Strategy Policies CP1, CP6 and CP20.

25. No dwelling within the development shall be occupied until details of the off-site works comprising of the pedestrian and cycle improvements on Warren House Road have been submitted to and approved in writing by the Local Planning Authority.

Reason: In the interests of highway safety and convenience. Relevant policy: Core Strategy policies CP3 & CP6, and the North Wokingham Strategic Development Location Supplementary Planning Document (October 2011 ).

Noise 23. The dwellings hereby approved shall be designed and/or insulated so as to provide attenuation against externally generated noise in accordance with a mitigation scheme to be submitted to and approved in writing by the Local Planning Authority before commencement of development. The scheme shall ensure that all noise implications are mitigated so that internal ambient noise levels for dwellings shall not exceed 35 dB LAeq (16 hour) 07:00-23:00 during the daytime and 30 dB LAeq (8 hour) 23:00-07:00 during the night. The design and/or insulation measures identified in the scheme shall ensure that ambient internal noise levels and the noise levels within gardens for the dwellings meet the Internal noise BS8233:1999 (Table 5 Sound Insulation and noise reduction for buildings - Code of Practice). The approved mitigation measures to serve each dwelling shall be implemented prior to occupation and retained thereafter.

Reason: To protect future residents from the harmful effects of high noise levels, in accordance with Wokingham Borough Core Strategy Policies CP1, CP3 and CC06 of the Managing Development Delivery Local Plan (Feb 2014) and External Noise - WHO Guidelines for Community Noise.

24 Before the development hereby permitted commences the applicant shall submit to the local planning authority for written approval details of a scheme to protect gardens and other external amenity areas from road traffic noise. The applicant shall ensure that the noise level in gardens does not at any time exceed 55dB LAeq, measured over 1 hour. The mitigation measures identified shall be installed before any dwellings are occupied and shall be retained and maintained for the duration of the development.

Reason: To protect the amenity of future residents of the site from the effects of high noise levels in accordance with Wokingham Borough Core Strategy Policies CP1 , CP3 and CC06 of the Managing Development Delivery Local Plan (Feb 2014) and External Noise - WHO Guidelines for Community Noise.

12

Page 9: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Sustainable Development 26. The reserved matters shall demonstrate that all of the market residential units will achieve a minimum Code Level 3 for Sustainable Homes and all affordable Housing will be designed to achieve at least Code for Sustainable Homes Level Four (or such national measure of sustainability for house design that replaces that scheme) or the equivalent relevant codes at the time of construction. Development shall be carried out in accordance with the approved details and so retained thereafter unless otherwise agreed in writing by the Local Planning Authority. No dwelling shall be occupied until a Final Code Certificate has been issued for it certifying that the Code Level stated above has been achieved and which has been submitted to the Local Planning Authority for approval.

Reason: In the interests of promoting sustainable forms of developments and to meet the terms of the application. Relevant Policies: Core Strategy policies CP1 and CP3 and CC04 and CC05 of the Managing Development Delivery Local Plan (Feb 2014).

27. Before submission of the applications pursuant to reserved matters either: i) a strategy detailing how the development will secure a 10% reduction in carbon emissions above the minimum requirements of Part L: Building Regulations shall be submitted to and approved in writing by the local planning authority; or ii) an alternative strategy which can demonstrate a greater carbon saving than would be achieved by i) above shall be submitted to and approved in writing by the Local Planning Authority.

The subsequent reserved matters applications to comply with Condition 3 shall include details of the measures to fulfil the approved strategy and the approved measures shall be installed and functional before first occupation of the buildings they are intended to serve.

Reason: In the interests of promoting sustainable forms of developments and to meet the terms of the application. Relevant Policies: Core Strategy policies CP1, and CC04 and CC05 of the Managing Development Delivery Local Plan (Feb 2014), the Sustainable Design and Construction Supplementary Planning Document (2010) and the North Wokingham Strategic Development Location Supplementary Planning Document (October 2011 ).

28. The reserved matters to comply with Condition 3 shall identify internal or external spaces for the storage of refuse and recyclable materials for all and provision in accordance with the approved details shall be implemented prior to occupation of any building and retained thereafter.

Reason: To ensure that adequate prov1s1on is made for the storage of recyclables in accordance with Wokingham Borough Core Strategy Policy CP1 and CC04 of the Managing Development Delivery Local Plan (Feb 2014), the Sustainable Design and Construction Supplementary Planning Document and the North Wokingham Strategic Development Location Supplementary Planning Document (October 2011 ).

29. All dwellings shall be provided with ducting that shall enable the connection of broadband or similar technologies.

Reason: To ensure that an adequate level of infrastructure is provided in accordance with Wokingham Core Strategy Policy CP1 and CC04 of the Managing Development Delivery Local Plan (Feb 2014).

Flooding and Drainage 30. None of the dwellings shall be occupied until works for the disposal of foul and storm water sewage have been provided on the site to serve the development hereby permitted, in accordance with details to be submitted to and approved in writing by the local planning authority.

13

Page 10: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Reason: In order to ensure satisfactory provision is made. Relevant Policy: NPPF and Core Strategy Policy CP1 and CC09 and CC10 of the Managing Development Delivery Local Plan (Feb 2014).

31. The development permitted by this planning permission shall be carried out in accordance with the approved Flood Risk Assessment (FRA) Kentwood Farm West, Wokingham, Flood Risk Assessment, dated 14/11/2013, prepared by WSP and the following mitigation measures:

(i) Finished Floor Levels for the proposed residential dwellings to be set at 50.15m above Ordnance Datum (AOD) (100 year plus climate change fluvial flood with a 300mm freeboard allowance) level or greater and be at least 150mm above the surrounding proposed ground levels and not be located in hollows.

(ii) The mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the timing I phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority.

Reason: To reduce the risk of flooding to the proposed development and future occupants in accordance with NPPF and Core Strategy Policy CP1.

32. No development shall take place until a surface water drainage scheme for the site, based on the agreed Flood Risk Assessment (Kentwood Farm West, Wokingham, Flood Risk Assessment, WSP 14/11/2013) has been submitted to and approved in writing by the local planning authority. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. The scheme and supporting calculations shall:

Take account of the findings of intrusive site investigations (including groundwater level monitoring and soakage testing in accordance with BRE 365) and the local hydrogeological conditions to develop suitable SuDS for the site.

Demonstrated that the use of SuDS has been given priority over more traditional pipe and tank systems, providing justification where it is not considered practicable to utilise infiltration based SuDS on site. • Demonstrate that, using the SuDS drainage methods, runoff from the site for events up to and including the 100 year event, including an allowance for climate change (30%), will be retained on the site and discharges from the site restricted to 1.8 l/s/ha whilst remaining safe for users of the site .

Apply the CIRIA publication 'C635 Designing for exceedance in urban drainage- Good practice'. • Employ storage ponds/SuDS drainage systems as outlined in the FRA.

Reason: To prevent the increased risk of flooding to others, to protect the proposed residential developments from flood risk and to improve and protect water quality, improve habitat and amenity, and ensure future maintenance of these in off in accordance with NPPF and Core Strategy Policy CP1 and CC09 and CC10 of the Managing Development Delivery Local Plan (Feb 2014).

Waste and Water 33. Development shall not commence until a drainage strategy detailing any on I off site drainage works, have been submitted to and approved by the Local Planning Authority in consultation with the sewage undertaker. No discharge of foul or surface water from the site shall be accepted into the public system until the drainage works as approved have been completed.

Reason: The development may lead to sewage flooding; in order to ensure sufficient

14

Page 11: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

capacity for to cope with the new development and to avoid any adverse environmental impact in accordance with NPPF and Core Strategy Policy CP1 and CC09 and CC10 of the Managing Development Delivery Local Plan (Feb 2014).

34. Development should not be commenced until impact studies of the existing water supply infrastructure have been submitted to and approved by the Local Planning Authority in consultation with Thames Water. The studies should determine the magnitude of any additional capacity required in the system and a suitable connection point.

Reason: To ensure that the water supply infrastructure has sufficient capacity to cope with the additional demand in accordance with NPPF and Core Strategy Policy CP1 and CC09 and CC10 of the Managing Development Delivery Local Plan (Feb 2014).

Odour 35. Prior to submission of reserved matters, a detailed odour assessment will be undertaken to assess any potential impacts from odour to the amenities of future residents from the nearby sewerage works. The assessment shall be submitted to and approved in writing by the local planning authority and the mitigation measures deemed appropriate shall be installed I implemented and be operational prior to first occupation.

Reason: To protect the amenity of future occupants from odour and to inform the location of development on the site and any necessary mitigation in accordance with the NPPF, Wokingham Borough Core Strategy Policies CP1 and CP3 or by a timetable to be agreed in writing.

Ecology 36. Prior to submission of a reserved matters for any sub phase of the development, a detailed hedgerow mitigation and compensation strategy shall be submitted to and approved in writing by the local planning authority for that sub phase of the development.

(a) Details of any buffer zones required to protected the retained hedgerows, such buffer zones to be a minimum of 1 Om unless there are exceptional circumstances. (b) The buffer zones required to protected the retained hedgerows should be free from any development including residential gardens, although internal highways can be within the 1 Om buffer zone providing they are not within 5m of the hedgerow. (c) A detailed method statement for the translocation of any hedgerows to be removed as a result of the sub phase of the development including details of the proposed management arrangements for the receptor site that will secure the long term future of the translocated habitat. (d) A detailed hedgerow compensation strategy to address all other impacts on the local hedgerow network as a result of the sub phase of the development.

The plan shall be carried out as approved, unless otherwise approved in writing by the local planning authority. ·

Reason: The application site appears to support suitable reptile habitat and the area around the site is known to support populations of native reptiles which are protected species. However the scale of the development proposed is unlikely to have a significant adverse impact on the local reptile population and consequently we should attach the following condition in order to protect individual reptiles from harm during development. Relevant policy: NPPF and Core Strategy policies CP6 and TB23 of the Managing Development Delivery Local Plan (Feb 2014).

37. No development shall take place (including demolition and site clearance) until full details of a protected reptiles contingency plan has been submitted to and approved in writing by the local planning authority. The plan shall include :

15

Page 12: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

(a) Surveys at agreed periods during April May or September by an agreed expert. (b) Details of appropriate mitigation measures and contingency plans should such reptiles be found to be present.

The plan shall be carried out as approved, unless otherwise approved in writing by the local planning authority.

Reason: The submitted ES identified that the site has the potential to support Hedgehogs which are a UK Biodiversity Action Plan (BAP) Priority Species (Species of Principal Importance or Section 41 NERC Act species) and consequently we should attach the following condition in order to protect individual reptiles from harm during development. Relevant policy: NPPF and Core Strategy policies CP6 and TB23 of the Managing Development Delivery Local Plan (Feb 2014).

38. No development shall take place until full details of a scheme to maintain the ecological permeability of the site (especially with regard to reptiles, amphibians and hedgehogs) has been submitted to and approved in writing by Wokingham Borough Council. The mitigation and contingency measures contained within the plan shall be implemented in accordance with the approved plan unless otherwise approved in writing by the local planning authority.

Reason: In order to protect and enhance ecology on the site. Relevant policy: NPPF and Core Strategy policies CP6 and TB23 of the Managing Development Delivery Local Plan (Feb 2014).

39. The mitigation and Enhancement measures contained within Table 11.6 of the submitted Environmental Statement shall be implemented in accordance with the approved plan unless otherwise approved in writing by the local planning authority.

Reason: In order to protect and enhance ecology on the site. Relevant policy: NPPF and Core Strategy policies CP6 and TB23 of the Managing Development Delivery Local Plan (Feb 2014).

Archaeological 40. No development shall take place until the applicant or their agents or successors in title have secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation, which has been submitted by the applicant and approved by the planning authority.

Reason: The site lies in an area of archaeological potential, particularly in relation to the Iron Medieval and later periods, as demonstrated by the Berkshire Archaeology Historic Environment Record. The area has not been intensively studied and therefore it is possible that remains relating to earlier periods may also be present, indeed a small number of Prehistoric findspots are already known in the vicinity of the site. Relevant Policies: NPPF and TB25 of the Managing Development Delivery Local Plan (Feb 2014).

C. That the committee authorise the Head of Development Management to refuse planning permission in the event of an S106 agreement not being completed as outlined above within 6 months of the date of the committee resolution.

1. The proposal fails to demonstrate how the development will make satisfactory provision of the necessary infrastructure required through the cumulative impact of development within the SOL and therefore represents a piecemeal approach that does not accord with the overarching infrastructure approach envisaged in the Core Strategy. As such the proposal is likely to compromise the delivery of the necessary infrastructure within the North Wokingham SOL and is contrary to policies CP4, CP6, CP10, CP20 and Appendix 7 of the Core Strategy and the Council's adopted North Wokingham SOL SPD and

16

Page 13: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Infrastructure Delivery and Contributions SPD.

lnformatives

1. You are advised, in compliance with The Town & Country Planning (General Development Procedure) (England) (Amendment) Order 2000, that the following policies and/or proposals in the development plan are relevant to this decision:

National Planning Policy Framework (NPPF)

Adopted Core Strategy: CP1, CP2, CP3, CP4, CP5, CP6, CP7, CP8, CP9, CP10, CP11, CP13 CP14, CP15, CP17, CP20 and Appendix 7.

Managing Development Delivery Local Plan Document (MOD Local Plan) adopted February 2014: CC01, CC02, CC03, CC04, CC05, CC06, CC07, CC08, CC09, CC10, TB05, TB07, TB08, TB21, TB23, TB25 and SAL05.

North Wokingham Strategic Development Location SPD adopted October 2011. Infrastructure Delivery and Contributions SPD for the Strategic Development Locations adopted October 2011. Sustainable Design and Construction SPD adopted 2010

Wokingham Borough Council Design Guide: Borough Guide Design SPD June 2012 Affordable Housing SPD adopted June 2011.

The councils parking standards as set out within appendix 2 of the Managing Development Delivery Local Plan (Feb 2014) and referred to in para. 4.38 of the adopted Core Strategy.

2. S106 This permission should be read in conjunction with the legal agreement under Section 106 of the Town and Country Planning Act (yet to be finalised) the contents of which relate to this development.

3. Work on Highway The Corporate Head of Environment at the Council Offices, Shute End, Wokingham should be contacted for the approval of the access construction details before any work is carried out within the highway. This planning permission does NOT authorise the construction of such an access.

4. Mud on Road Adequate precautions shall be taken during the construction period to prevent the deposit of mud and similar debris on adjacent highways. For further information contact Corporate Head of Environment on tel: 0118 97 4 6302.

5. Highway Adoption If it is the developer's intention to request the Council, as local highway authority, to adopt the proposed access roads etc. as highway maintainable at public expense, then full engineering details must be agreed with the Corporate Head of Environment at the Council Offices, Shute End, Wokingham. The developer is strongly advised not to commence development until such details have been approved in writing and a legal agreement is made with the Council under S38 of the Highways Act 1980.

6. Highway Management Any works/events carried out either by, or at the behest of, the developer, whether they are located on, or affecting a prospectively maintainable highway, as defined under Section 87 of the New Roads and Street Works Act 1991, or on or affecting the public highway, shall be coordinated under the requirements of the New Roads and Street Works Act 1991 and the

17

Page 14: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Traffic management Act 2004 and licensed accordingly in order to secure the expeditious movement of traffic by minimising disruption to users of the highway network in Wokingham.

7. Utilities Any such works or events commissioned by the developer and particularly those involving the connection of any utility to the site, shall be co-ordinated by them in liaison with Wokingham Borough Council's Street Works Team, (telephone 01189 746302). This must take place at least three month in advance of the works and particularly to ensure that statutory undertaker connections/supplies to the site are coordinated to take place wherever possible at the same time.

8. Noise The attention of the applicant is drawn to the requirements of Section 60 of the Control of Pollution Act 197 4 in respect of the minimisation of noise on construction and demolition sites. Application, under Section 61 of the Act, for prior consent to the works, can be made to the Environmental Health and Licensing Manager.

9. Thames Water In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777.

10. Thames Water - Odour Assessment The applicant is advised that Thames Water have raised concerns regarding the location of the development and its proximity to the sewerage works. Thames Water recommend that the developer carries out a dispersion odour assessment with odour sampling, under the requirements of BSEN13725:2003. The applicant should contact Thames Water Developer Services Team to confirm the scope of odour modelling required. They can be contacted on 0845 850 2777.

The odour modelling will confirm whether future occupiers of the proposed development would be significantly adversely affected by odour from the sewage works. Should the assessment confirm that proposed occupiers will be significantly adversely affected by odour from the sewage works, the developer would need to fund odour mitigation to address this impact. No development should be occupied until the odour mitigation is operational.

11. Environmental Permits Licences, consents or permits may be required for work on this site. For further information on environmental permits and other licences please visit http://www. busi nesslin k. gov. uk/bdotg/action/layer? r. s=tl&r. lc=en&topicl d= 1 079068363

12. Local Labour The applicant is advised that the Council seeks that employers or developers within the borough commit to using local labour I contractors where possible. This should include:

• Advertisement of jobs within local recruitment agencies I job centres; • Recruitment and training of residents from the local area; • Seek tender of local suppliers or contractors for work.

13. Construction Noise The applicant or the operator is advised to submit to the Council's Environmental Health Team a 'prior consent' application under s.60 of the Control of Pollution Act 197 4.

18

Page 15: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

14. Code for Sustainable Homes The applicant has made a commitment that the development will seek to achieve at least Code Level 3 of the Code for Sustainable Homes and Code Level 4 for the affordable housing units. Furthermore to the provision of on-site energy generation and to achieve a minimum reduction of 10% of total energy consumption through on-site renewable energy generation.

16. Design Standards The applicant is advised that the Council will expect the reserved matters to adhere to the Council's adopted Design Standards in terms of Internal Floor-space, garden sizes and parking provision.

17. Fire Hydrants The development will provide adequate fire hydrant provision in association with advice from the Royal Berkshire Fire and Rescue Service.

PLANNING HISTORY 0/2011/0699; Hybrid application, Phase 1 of the North Wokingham Strategic Development Location.

A) OUTLINE APPLICATION FOR:

The development of 27 4 dwellings, garages, driveways, car ports (total 557 parking spaces), internal roads, pathways, sub-stations, gas governor, the construction of a new access from Keephatch road and two new access points from Warren House road with associated amenity space, incorporating allotments (Matters for approval: Access and Layout).

B) FULLPLANNING PERMISSION FOR:

1) The laying out of an area of Public Open Space (informal) and a Suitable Alternative Natural Greenspace (SANG) on land west of Warren House Road (to serve the proposal phase 1 and future development at Kentwood Farm), including a car park (6 spaces), pathways, associated landscaping and pathway features.

2) The construction of a 3.5 metre high landform (noise bund) and 2.5 metre fence for a distance of 405 metres on the west side of Warren House Road and 635 metres on the East side of Warren House Road, parallel with the A329(M).

3) The erection of a sewage pumping station with interim access from the present access from Warren House Road.

This application was consent at appeal (ref: APP/X0360/A/11/2157754);

0/2010/0943; Hybrid application on the site which was refused. Under this proposal, outline approval was sought for the development of 357 dwellings garages and associated infrastructure and landscaping, with two new access from Keephatch Road and Warren House Road, the erection of a substation and gas governor and associated amenity space (matters for approval access and layout). (REFUSED)

Scoping Opinion (ref: S0/2007/2997) was undertaken for 2500 dwellings, community centre, medical centre, retail centre, nursery and primary school. This set out that an environmental statement was required.

Also of relevance to this application are:

Land East of Buttercup Close (planning ref: F/2012/2035) for;

1 9

Page 16: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

65 Plough Lane (planning ref: F/2011/0182 I appeal ref: X0360/A/11/2152037/NWF) for proposed erection of two 4 bedroom detached dwellings with associated access, landscaping and parking.

SUMMARY INFORMATION Site Area Number of residential units Provision of SANG

Approx. 8.4 ha Up to 225 Approx. 2.66 ha (provided on Phase 1) Approx. 1.45 ha (required 0.53 ha) Approx. 0.08 ha (required 0.14 ha) plus a contribution for off-site provision

Public Open Space Children's Play Space

Allotments Parking Numbers

Approx. 0.28 ha (required 0.28 ha) Dependant on Housing Nos. (in accordance with oarkinq standards)

CONSULTATION RESPONSES • Berkshire

Archaeology:

• Urban Design and Conservation

• Countryside Officer (Biodiversity) and Public Open Space:

No objection subject to conditions on Written Scheme of Investigation (see condition 40).

The site contains no listed buildings but identifies 10 listed buildings within 500m of the site boundary, 7 of these form two farmstead groups; a group of 4 listed buildings at Ashridge Farm (including the 2* farmhouse) to the southwest of the site and the group of 3 at Rustons. The other 3 listed buildings are Keepers Cottage to the south east, Dowlesgreen Farmhouse further to the south east and Ashridge Cottage to the south west.

No objection subject to the green buffer/corridor mitigation measures between the application site and Ashridge Farm.

No objection subject to contributions for Public Open Space (POS), Allotments, Sports, Children's Play Provision, Country Parks, Countryside Access, SANG and SPA Mitigation and Biodiversity.

Thames Basin Heaths Special Protection Area Satisfied that sufficient SANG capacity has already been provided for this development under the previous permission for Kentwood Farm East (phase 1) and that providing the applicant is prepared to pay the required SAMM contribution in line with our PAN then this development is unlikely to have an adverse impact on the nearby Thames Basin Heaths SPA.

Other Ecology This development has the potential to have an adverse effect on the buffer zones required to protect the boundary hedgerows on the site which have been identified as UK Biodiversity Action Plan (BAP) Priority Habitats (Habitats of Principal Importance or Section 41 NERC Act habitats - hedgerows). The following conditions should be included

• Detailed hedgerow mitigation and compensation strategy (Condition 36).

The application site appears to support suitable reptile habitat and the area around the site is known to support populations of native reptiles which are protected species. However the scale of the development

ro osed is unlike! to have a si nificant adverse im act on the local

20

Page 17: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Countryside Access Officer I Public Rights of Way:

• Environmental Health:

reptile population and consequently we should attach the following condition in order to protect individual reptiles from harm during development.

• Full details of a protected reptiles contingency plan to be submitted (Condition 37).

The submitted ES identified that the site has the potential to support Hedgehogs which are a UK Biodiversity Action Plan (BAP) Priority Species (Species of Principal Importance or Section 41 NERC Act species) and consequently we should attach the following condition in order to protect individual reptiles from harm during development.

• Full details of a scheme to maintain the ecological permeability of the site (Condition 38).

I have considered the implications of this application against EC Habitats Directive 1992 and the Conservation of Habitats and Species Regulations 2010 and subject to the following condition the actions authorised will not be detrimental to the maintenance of the bat species concerned at a Favourable Conservation Status in their natural range or the sites wider biodiversity interest.

• The mitigation and Enhancement measures contained within Table 11.6 of the submitted Environmental Statement shall be implemented in accordance with the approved plan unless otherwise approved in writing by the local planning authority (Condition 39).

No objections to the principle of the development. Appear to be opportunities to enhance access to the countryside to the north and east of the A329(M) for both walkers and cyclists.

• Footpath 14 (running from Keephatch Road north-eastwards over the motorway) may already be planned for enhancement in connection with the Kentwood Farm East Phase 1 development, but, if not, this path should be upgraded legally and physically to a cycle track with a suitable surface and a cycle friendly approach to and from the motorway bridge instead of the existing steps.

• Desirable for Warren House Road as it runs north from the site to the bridge over the motorway, and north from the bridge, to have footways and a safe cycling area.

Both these measures would help to fulfil the Council's aims for sustainable transport and healthy living through increased informal recreation. They would also help to compensate for the increased pressure of use on the existing rights of way resulting from large numbers of additional people living in the area.

No objection in principal:

Air Quality Additional information has been provided regarding air quality with confirmation that the cumulative effect has been accounted for. This means that a condition will not be required.

21

Page 18: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Environment Agency:

Odour Further information has been provided regarding odour from the Sewage Treatment Works. There is no information available to justify the restriction of development on this site. No condition is required to cover this aspect

Noise The site is located in the vicinity of the A329(M) and the proposed Northern Distributor Road (NDR) will run through from the north east to the south west of the site. An assessment of road traffic noise has been carried out and the findings have been submitted with the application.

Road Traffic Noise - A329(M) (Internal Noise Levels) The noise assessment predictions take into account mitigation provided an acoustic barrier constructed as part of the Kentwood Farm East development (3m high earth bund and 2.5m high acoustic fence along the boundary of the A329(M). The assessment concludes that some properties at the northern boundary of the proposed development with facades facing the A329 will fall into Noise Exposure Category B during the day and all will fall with NEC A at night. Those properties falling into NEC B during the day will require some additional protection against noise that could be adequately be provided by double glazing. On the assumption that the acoustic barrier will be built, no concerns about noise from the A329(M) .

Road Traffic Noise - NDR (Internal Noise levels) An assessment of noise from the proposed NDR predicts that some plots close to the proposed NDR will fall within NEC C during the day and at night and that 'reasonable' internal noise levels for resting and sleeping (in accordance with BS8233) will be achieved by high specification double glazing if kept shut with alternative means of acoustic ventilation (ES Para 9.5.11 ). Satisfied that a reasonable internal noise level can be achieved if windows on facades facing the NDR are kept shut but it is for others to decide whether the solution is acceptable in terms of the quality of design (condition 23).

Garden Noise The noise assessment predicts that the target (maximum) noise level for gardens (55dB LAeq, 1 hr) will be achieved for all plots except plot 116 which will be 0.4dB above the criteria. However the 'predictions assume that the perimeter walls I fences are 1.Bm high and 'acoustically sound" (ES Para 9.4.12). Documents submitted include no reference to perimeter walls or fencing nor any find any specification for their height or acoustic performance. Therefore not clear where the 1.Bm walls or fences will be installed. As such recommend condition is applied to ensure that adequate mitigation measures are installed to protect gardens and other external amenity areas from road traffic noise (condition 24).

The site lies in Flood Zone 1 and a Flood Risk Assessment (FRA) including a Surface Water Drainage Strategy has been submitted along with the application for outline planning permission.

No objections to the proposal as submitted, subject to the development being undertaken in accordance with the FRA and the inclusion of the following planninq conditions (Conditions 30 - 32) to anv subsequent

22

Page 19: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Highways and drainage:

planning permission granted relating to floor levels and surface water drainage.

No objection in principal subject to conditions (conditions 16 -25) and agreement of developer to the necessary highway upgrades in accordance with the Council's modelling which will include contributions towards NOR and associated highway network improvements works such as Coppid Beech Roundabout Improvements.

Proposal includes improvements to pedestrian I cycle links and contribution towards the Council's Borough wide Travel Plan.

Summary responses to representations made:

NOR should be provided upfront - failure to provide NOR will result in significant congestion on existing roads and impacts to amenity of residents, in particular Warren House Road and Keephatch Road;

The NOR is highlighted within the Core Strategy and has progressed through public consultation. The highways study has considered the timeframe for the NOR and has assessed the potential impacts prior to delivery which has identified minimal impacts.

Inadequate provision of highway infrastructure will lead to congestion and highway safety issues throughout Wokingham;

Off-Site junction improvements are promoted around the site to mitigate the development impact alongside the delivery of the NOR to provide the required capacity.

Route of NOR in this planning application is inconsistent with SPD;

The NOR route identified within the SPO was an indicative alignment and as such requires further assessment and feasibility work before final alignment is determined. The first stage of this was undertaken recently with the NOR Highway Study which has identified potential alignments that the road could follow. The assessment work undertaken by the applicant is consistent with the study report.

NOR will be a mix of 30 and 40 mph stretches - will result in patchwork of individual, inconsistent roads, and not a strategic carriageway;

The distributor road would be a single carriageway, tree lined road. It would have a speed limit between 30mph between Reading Road and Pebblestone Cottage and 40mph east to Coppid Beach as no development is proposed in this section at this time.

In addition, the layout of the road has been considered in great detail by the county to make sure the full length will not form a patchwork of individual links by developing such a pallet of materials and agreed cross sections that all developments will need to follow.

Diverting Warren House Road into the new estate would only enhance the road network for occupiers of the new properties but will have a negative impact for residents of existing dwellings to the west of Wokingham who would want to travel in either direction along Warren House Road without delays. A T-junction would orovide an aooropriate

23

Page 20: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Highways Agency:

• Education:

• Housing:

balance between the needs of existing residents and new residents and maintain Warren House Road as a standard straight highway;

The layout of the NDR and Warren House Road are still being determined following the public consultation. The final layout promoted by the applicant will have been assessed to make sure no delay is subjected to the local residents.

Location of pedestrian crossing could cause nuisance I disturbance to existing residents and also road safety issues;

All pedestrian crossings will be of an appropriate type for that location and will be safety audited and illuminated. The new crossings will be a benefit for both the new residents and existing residents however care will be taken to cause minimal disturbance to existing or new residents.

No al/owance has been made for residents on Benning Way to exit onto road when traffic increases;

The modelling undertaken looks at impacts to the residents of Benning Way and this has not indicated any significant impacts should Warren House Road be used as the NDR.

New junction along Warren House Road could result in accidents;

The junction arrangement has been designed to the appropriate standards and will be subject to road Safety Audits. As such, WBC see no reason for any safety concerns.

No objection however concerned at proposals that have the potential to impact the safe and efficient operation of the Strategic Road Network.

The supporting TA has not considered the impacts to the M4 however the impacts are unlikely to be significant from the proposal. To minimise any potential impacts to SRN, the HA would strongly recommend that the promoters of the development seek opportunities to encourage trips outside of the peak periods during both the construction and operational phases of development. This might be through a travel plan to support the proposal.

It is understood that the proposal is not reliant on the delivery of the North Wokingham Distributer Road (NWDR). The HA look forward to early discussions with Wokingham Borough Council on the need for, deliverability of, and the impacts to the M4 (particularly junction 10) from the proposed NWDR. The HA are concerned about the cumulative impacts from development in both Bracknell and Wokingham on M4 Junction 10, and look to the Councils to consider how any cumulative impacts can be reasonably mitigated.

Contributions required towards Secondary, Post 16 and SEN. No contributions required towards Primary however this is subject to new schools coming forward in advance of this development.

Acceptable in principle provided:

To meet the requirements of Policy CP5 of the Core Strategy, a minimum of 35% of the total number of units (net) should be provided

24

Page 21: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Landscape and Trees:

• Land Use and Transport:

• English Heritage:

• Natural England:

as affordable housing, this equates to 78.75 unit on the proposed 225 dwellings on this site.

The affordable housing unit should be built to Homes and Communities Agency Design and Quality Standards and be transferred to the Council's Local Housing Company (Wokingham Housing Limited) or one of the Council's preferred Registered Provider (RP) partners for a price that will enable the RP or Local Housing Company to deliver the affordable housing without the need for public subsidy.

The applicant has proposed 65 affordable dwellings on site with the remaining 13.75 provided as a commuted sum, which is in principle acceptable.

It is envisaged that the on-site affordable units will be split as 70% social rent, of which up to 12% may be affordable rent and 30% shared ownership, at 35% equity shares and rent on the unsold equity capped at 1.5% per annum. We would expect the units to be aligned with the guide mix set out in the Affordable Housing SPD and note that the proposal is somewhat adrift from this mix, particularly in respect of 3 and 4 bedroom units, however having considered this, we would be willing to accept the proposed unit mix as follows:

6 x 1 bedroom flats 21 x 2 bedroom flats 28 x 2 bedroom houses 10 x 3 bedroom houses

WBC would expect the on-site affordable housing to be indistinguishable from the private market housing and to meet the minimum space requirements as set out in the Borough Design Guide and Policy TB07 of the MOD DPD.

In terms of the commuted sum, based on the Viability Study undertaken by Levvel Ltd, the Council's approach to calculating commuted sums for affordable housing is based on the difference in the residual development value of a scheme without on-site affordable housing and the same scheme with on-site affordable housing. As mentioned above, the proposed on-site unit mix is light on 3 and 4 bedroom units, WBC have therefore based the calculation of the commuted sum to accord more to that within the Affordable Housing SPD.

No objection in principle subject to conditions relating to tree protection and planting (Conditions 9 - 13).

No objection despite differences in quantum of development compared to amount envisaged in NWSDL SPD (reduction of 11 dwellings from that envisaged from this part of the SOL). This represents less than 1% of the around 1,500 units allocated to the site in the Core Strategy and as such this reduction is considered acceptable.

No objection.

No objection in principle however requires SAMM contribution for the SANG.

25

Page 22: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Royal Berkshire Fire and Rescue Service:

• Sport England:

• Thames Water:

Requirement for the applicant to provide suitable private fire hydrants.

Sport England raises no objection to the principle of the development however seeks provision of sports facilities. As no on­site facilities are proposed, Sport England welcomes off-site financial contribution however requires further information to ensure that the development adequately contributes towards the provision of indoor and outdoor sports facilities made necessary by the development.

No objection.

Waste Comments Following initial investigation, Thames Water has identified an inability of the existing waste water infrastructure to accommodate the needs of this application. Should the Local Planning Authority look to approve the application, Thames Water would like the following 'Grampian Style' condition imposed relating to submission of a drainage strategy detailing any on and/or off site drainage works, in consultation with the sewerage undertaker.

Where a developer proposes to discharge groundwater into a public sewer, a groundwater discharge permit will be required.

Water Comments No water comments

Supplementary Comments Investigations into impact from the proposed development are advised and developers will be required to demonstrate that there is adequate waste water capacity both on and off the site to serve the development and that it would not lead to problems for existing or new users.

Odour Phase 2 is located in close proximity to Wokingham Sewage Treatment Works, being ca. 150m from the sewage works.

Given the scale and nature of the development and its proximity to the sewage works TW do have concerns regarding the amenity for potential future residents of the proposed development. TW do not consider that these concerns have been addressed by the limited odour survey carried out by WSP.

TW object to the proposal as no modelled odour assessment has been taken to establish the amenity impact on potential future occupiers.

To address our objection, and to be in accordance with government planning policy, recommend that the developer carries out a dispersion odour assessment with odour sampling, under the requirements of BSEN13725:2003.

The odour modelling will confirm whether future occupiers of the proposed development would be significantly adversely affected by odour from the sewage works.

Should the assessment confirm that pro osed occu iers will be

26

Page 23: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Thames Valley Police (RPS):

• Waste Services:

significantly adversely affected by odour from the sewage works, the developer would need to fund odour mitigation to address this impact. No development should be occupied until the odour mitigation is operational (Condition 35).

No objection. Suggests considerations to be made when designing layout.

No objection subject to:

Waste & Recycling Collection (non multi occupancy I dwelling houses) Vehicular access must be available to within 25 metres of single road facing properties. This access must either be adopted or built to adoptable standards. Residents should place their own waste at the edge of their own property for collection as collection points are not preferred.

Waste & Recycling Collection (multi occupancy I flats) Multi occupancy properties should allow vehicular access to within 10 metres of bin stores/areas and these must also be adopted or built to adoptable standards. If bulk bin containment is preferred then this will be at the expense of the developer/managing agent and should be based on 120 litres per property per week.

Recycling If a community hub is to be installed then the positioning of a glass recycling facility should be considered.

• Southern Gas Point out the existence of gas pipes within the area. Networks:

• Reading No response at date of writing . . Borough:

• Bracknell Forest No response at date of writing. Council:

REPRESENTATIONS • Local Residents:

7 received objecting to the proposals, summarised as follows:-

NOR should be provided upfront - failure to provide NOR will result in significant congestion on existing roads and impacts to amenity of residents, in particular Warren House Road and Keephatch Road; Inadequate provision of highway infrastructure will lead to congestion and highway safety issues throughout Wokingham; Route of NOR in this planning application is inconsistent with SPD; NOR will be a mix of 30 and 40 mph stretches - will result in patchwork of individual, inconsistent roads, and not a strategic carriageway; Diverting Warren House Road into the new estate would only enhance the road network for occupiers of the new properties but will have a negative impact for residents of existing dwellings to the west of Wokingham who would want to travel in either direction along Warren House Road without delays. A T-junction would provide an appropriate balance between the needs of existing residents and new residents and maintain Warren House Road as a standard straight highway; Location of pedestrian crossing could cause nuisance I disturbance to existing residents

27

Page 24: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

and also road safety issues; No allowance has been made for residents on Benning Way to exist onto road when traffic increases; New junction along Warren House Road could result in accidents; Lack of provision of social infrastructure to support the new development will result in increased pressure on local services - schools, dentist's, GP surgeries, public transport etc. (see section 81 - 104); Increased number of residents and traffic would result in pollution, in addition to noise and disturbance to existing residents; Loss of landscape from the site will result in harm to the appearance of the area and negative impacts to wildlife habitats and in particular protected species (see section 119 - 124); Flooding from development. Local roads and area have been flooded in recent times, development may only make this worse. What plans are being made to ensure that the waterworks can cope with the additional houses?

(See Highway comments and sections 46 - 77 for responses to these).

Wokingham Town Council That the Committee would make no objection to the proposal but should include:

• Six dementia care dwellings should be provided as part of the affordable housing allocation (see section 103);

• The junction between the southern end of the proposed road known as "The Avenue" and Warren House Road must give vehicles on the final route of the Northern Relief Road priority over local traffic (route specifics will be assessed as part of NDR Study).

St Nicholas Hurst Parish Council - object: • The layout proposed appears to allow for the North Wokingham Distributor Road route to

pass through the development however the precise route is not clear particularly as to whether it allows for the continuation westwards across the Thames Water land (Outline application - access does not form part of assessment at this stage however alignment remains flexible).

• The EA Transport Assessment cuts off immediately North of the Forest Road and thus totally fails to assess the impact of the development on the north of the WBC area that includes the parish of St Nicholas Hurst (TA looks at road network to north of site).

• The Parish Council (PC) is of the view that the generated traffic from this proposed development and related ones in North Wokingham SDL will almost certainly have been underestimated and will inevitably have an adverse effect on the parish (As above).

• Areas of this Phase 2 site are at risk of Zone 3 and Zone 2 flooding according to the Environment Agency's flood map as available on their website (FRA identifies development within Flood Zone 1 (Low Risk); see para. 126). The remaining area of the North Wokingham SOL contains the Toutley Brook that feeds into the Emmbrook and both of these are at risk of flooding on the map. There is a flood risk assessment in the application documents but it is clear that the additional hard area that goes with 225 dwellings will cause a faster runoff and exacerbate the risk of flooding in the remaining area of the SOL and downstream into the parish of St Nicholas Hurst. The PC believes that insufficient attention is paid to the effects of flooding and any mitigation measures required particularly downstream of the development (See section 125-126). However proposal will include SuOs which will improve water run-off situation).

• The PC believe that this is another step in the development of the North Wokingham SDL and that this application should be refused on the grounds that it does not deal with the whole North Wokingham SOL so it is not possible to assess the effect of a number of

28

Page 25: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

vital issues including overall compliance with the Core Strategy and, as stated above, traffic impact and flooding (Applicant submitted IDP - approach considered acceptable under Kentwood Phase 1 appeal decision).

• The PC is extremely disappointed that this is submitted as an Outline application. For such an important development it is in the Council's view most important that the whole matter, including the remainder of the SOL, is out in the open and not left for later Reserved Matters applications when the principle has been decide. Nevertheless the Council recognises that the applicant is within his rights however disappointing this is.

Winnersh Parish Council - (adjoining parish application) no objections.

APPLICANTS POINTS Note letter dated 301

" January 2014 from Charlie Collins, Savills, responding to the comments submitted against the application (see appendix 1)

PLANNING POLICY National Planning Policy Framework (NPPF)

Adopted Core Strategy: CP1, CP2, CP3, CP4, CPS, CP6, CP7, CPS, CP9, CP10, CP11, CP13 CP14, CP1S, CP17, CP20 and Appendix 7.

Managing Development Delivery Local Plan Document (MOD Local Plan) adopted February 2014: CC01, CC02, CC03, CC04, CCOS, CC06, CC07, CCOB, CC09, CC10, TBOS, TB07, TBOB, TB21, TB23, TB2S and SALOS.

North Wokingham Strategic Development Location SPD adopted October 2011. Infrastructure Delivery and Contributions SPD for the Strategic Development Locations adopted October 2011.

Wokingham Borough Council Design Guide: Borough Guide Design SPD June 2012 Affordable Housing SPD adopted June 2011. Sustainable Design and Construction SPD adopted 2010

The councils parking standards as set out within appendix 2 of the Managing Development Delivery Local Plan (Feb 2014) and referred to in para. 4.38 of the adopted Core Strategy.

PLANNING ISSUES The Site and Surrounding Area

1) The application site comprises 8.42 hectares and is situated to the north of Wokingham and south of the A329(M). The site is located approximately 1 km to the north west of Wokingham town centre and forms part of the Strategic Development Location (SOL), as identified within the Core Strategy Policy 20.

2) The Core Strategy SOL proposes 1 SOO new homes within this SOL. 180 of these are already consented (1SO constructed) at Plough Lane, therefore leaving a balance of 1320 to be constructed in the two other allocated sites. The SOL is made of two main development areas, one located to the west at Matthewsgreen and Kentwood which includes the application site. The Core Strategy I SPD identities Kentwood East and West as providing S10 new dwellings.

3) The site consists of open fields, ditches, hedgerows and a mixture of trees, in terms of aQe and type. The topoQraphy of the site is relatively similar throughout.

29

Page 26: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

4) The eastern boundary is made up by Warren House Road. There is a new roundabout which will provide access to the site and link with Kentwood Farm East development site (approved for 274 dwellings). This will form part of the Northern Distributor Road (NDR). Directly to the east of Warren House Road there is also an existing employment site, known as Kentwood Industrial area within the SDL boundary, which does not form part of the application site.

5) Directly north lies the SANG created under the Phase 1 or Kentwood Farm East development and beyond that the A329(M) and open countryside.

6) To the south, there are existing residential developments comprising mostly two storey housing, which will remain separated from the development by the Warren House Road. Keephatch Road links onto south eastern corner of the site.

7) To the west are open fields, Ashridge Farm which is listed and the sewerage works which are approximately 700m to the west. The site is bounded to the east, west and south by an existing hedgerow and with a small number of mature trees within these hedgerows, most notably along the western boundary.

8) The nearest existing neighbourhood centre is on Ashridge Road which is located approximately 300m away from the site. This comprises shops, public house and doctors surgery. Keephatch Primary School, Ashridge Nursery and All Saints Primary School are also located in this area. St Crispins comprehensive school (11-18) is located to the south along London Road. Matthewsgreen neighbourhood centre, which forms the main centre within the SDL, is located approximately 2km to the west. Cantley Sports facilities are located approximately 1 km to the west.

Proposal

9) The current proposals comprise an outlined application for up to 225 dwellings with all matters reserved.

10) The Crest (Kentwood) sites are split by Warren House Road, with the main element of the site (Phase 1 or Kentwood Farm West for 274 dwellings) of the proposed housing delivery of the 510 residential units located to the east of the road. Both sites will comprise the proposed housing, open space, access roads, the Northern Relief Road (NRR) and allotments. A children's play area will be provided on the site however sports provision will provided off-site at Cantley.

11) The land to the north of the development site incorporates the permanent SANG which will include car parking. The car parking and recycling facilities which were approved under the Phase 1 application will need to be relocated while the sewerage pumping station is no longer required. However no details are shown at this time given the scheme is outline with all matters reserved.

12) As advised as this is an outline planning application all matters are reserved for determination at a later date. However an indicative masterplan has been submitted which indicates that the site can accommodate the residential development, allotments, open space, play area and associated infrastructure. The development is likely to replicate Phase 1 in terms of design and layout. The residential units are likely to comprise mostly 2 storey dwelling houses with gardens but also include some flats up to 3 storey's in height as with Phase 1. The density of the proposal is approximately 30 dwellings per hectare in accordance with the Core Strategy.

13) Affordable housing provision is proposed at 30% (65 units) subject to viability. These should be located in clusters of no more than 20 dwellin s. However no issues of

30

Page 27: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

viability have been submitted to the Council as part of this application. Moreover it would not be appropriate to deal with this issue post determination.

Layout and Design

14) As the application is an outline proposal with all matters reserved, issues such as layout or more detailed matters such as design are not included within this application and therefore cannot be considered at this time however are likely to be informed by the character on the consented scheme on Phase 1. However any future application will be expected to accord with the Council's Borough Design Guide, in terms of internal floor standards, garden sizes, separation distances and also parking standards.

15) Recycling facilities will also be provided on this site, the location of which will be considered under the reserved matters.

16) A new sewage pumping station that was proposed on the north of the site adjacent the SANG as part of Phase 1 scheme is no longer required as there is capacity in the existing system and through infrastructure upgrades where necessary.

Open Space and Allotments

17) It is proposed the site will accommodate informal public open space, comprising green infrastructure, formal play area, informal open space, allotments, together with retained landscape features including a green buffer along the hedgerow forming the western boundary. Improved pedestrian and cycle links to the town centre and west to Cantley are also proposed.

18) The site will also include basins or dry ponds which will act as flood attenuation ponds which would serve as part of the Sustainable Urban Drainage System (SUDs) strategy.

19) Under this indicative scheme allotments are located to the south eastern corner of the site adjacent to the commercial development along Warren House Road. These comprise 0.28 ha which is in accordance with the requirements set out within Appendix 4 of the Core Strategy (0.34 ha based on 0.52 ha / 1000 population).

20) A Children's Play Area (Local Equipped Area of Play - LEAP) will be provided on the site comprising 0.08ha. The shortfall will be provided by a contribution towards off­site provision. This approach is considered acceptable.

Suitable Alternative Natural Greenspace (SANG)

21) The land to the north of the site and west of Warren House Road comprises the SANG and is made up of approximately 2.66 ha to provide adequate mitigation upon the impact of the new residential development on the Thames Basin Heaths Special Protection Area (SPA), which is a requirement of Habitats Regulations. The SANG is large enough to serve both phases 1 and 2 of Kentwood Farm development with respect to the mitigating its impact upon the Thames Basin Heaths Special Protection Area. The SANG will be transferred to the Council with a maintenance contribution.

22) The SANG comprises informal open space comprising mainly open grass areas, planting (including a woodland along the northern edge of the SANG to provide screening of the A329(M}}, ponds, which will form a wetland in addition to forming part of the SUDs, and a network of informal public footpaths. A earth bund, 3.5m in height and 2.5m high fence (totalling 1061 metres in length) is to be installed between the SANG and road, in order to miti ate against road noise from the

31

Page 28: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

A329(M).

23) Parking for the SANG will need to be provided on this site and this parking needs to be maintained in perpetuity. The SANG would include multiply accesses including the main entrance from Kentwood East or Phase 1 which will be gained via a non­signalised crossing I island across Warren House Road linked by footpaths located on both sides of Warren House Road.

Policy and Principle of development

24) The requirement for new housing is supported by Core Strategy Policy CP17 which seeks the delivery 13,230 new homes by 2026.

25) On the basis of the need to provide new housing, Wokingham Borough responded by identifying four Strategic Development Locations in the Wokingham Core Strategy (each with an SPD). The concentration of the majority of houses in four locations enables not only the delivery of houses but also importantly, the delivery of associated infrastructure.

26) In the Core Strategy Examination in Public, the Inspector stated that the overall strategy of concentrating new dwellings in four key locations was the most "suitable and balanced way forward" and would enable the provision of fully funded social, environmental and transport infrastructure. He also stated that sites within the SOL boundary, which are to be developed, should not be specified in the Core Strategy but should be determined through a master planning process which is to be approved as SPD, as endorsed by the Inspector at paragraph 3.19 of the Adopted Core Strategy. It is important to note that the Strategic Development Locations were considered the best way to ensure not only the delivery of sufficient high quality houses but also the delivery of satisfactory and necessary infrastructure.

27) The application site is located within the North Wokingham Strategic Development Location (SOL) and therefore the broad principle of development here is acceptable. Within North Wokingham SOL, there is a phased allocation for around 1500 new dwellings to be provided.

28) It is important that the SOL sites are treated as a single development site and not simply an area comprising of a number of development sites. In this respect the SOL approach is that the location of facilities, dwellings and infrastructure within the SOL is to be determined by the overarching Masterplan SPD. The Masterplan for North Wokingham SOL envisages that developments would be delivered through a phased, co-ordinated approach which would allow for a comprehensive development of the whole SOL. This encompasses the provision of new infrastructure (roads, leisure, schools, recreation etc), upgraded and new neighbouring centres and community facilities.

29) Policy CP20 of the Core Strategy is the policy within the Adopted Core Strategy that specifically deals with the North Wokingham Strategic Development Location.

30) Policy CP20 states:-

Within the area identified at North Wokingham, a sustainable, well designed mixed use development will be delivered by 2026 including:

1) Phased delivery of around 1, 500 dwellings including affordable homes in accordance with policy CP5;

2) Appropriate retail facilities; 3 A ro riate em lo ment located west of Tw ford Road, north of Matthews reen

32

Page 29: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Farm and east of Touttey Industrial Estate; 4) Social and physical infrastructure (including provision for one new primary school

if required}; 5) Measures to maintain separation from Binfield/Bracknell and Winnersh; 6) Necessary measures to avoid and mitigate the impact of development upon the

Thames Basin Heaths Special Protection Area in line with Policy CPB to meet the requirements of the Habitats Regulations and in accordance with Natural England's latest standards. This will include sufficient Suitable Alternative Natural Greenspace (subject to monitoring of the quality and quantity standards).;

7) Improvements to transport capacity along the A321 and A329 including the provision of a new route from the A329 (near the M4 over-bridge) to the vicinity of the Coppid Beech roundabout;

8) Measures to improve accessibility by non-car transport modes along the A321 and A329 corridors; and

9) Measures to improve access by non-car modes to Wokingham town centre (including the station interchange).

The development will be guided by a Development Brief Supplementary Planning Document produced with the involvement of stakeholders including all interested landowners in the area covered by the Strategic Development Location as defined on the Proposals Map.

A co-ordinated approach to the development of the Strategic Development Location will be required to deliver the necessary infrastructure, facilities and services to meet the needs of the expanded community.

Strategic Development Location SPD

31) The SOL Supplementary Planning Document for North Wokingham (NW SOL) was originally adopted in 2010 however subsequently the Southern Parishes Planning Group lodged a challenge with the High Court with respect to the validity of the adopted SPD's in January 2011.

32) As a result, the Council decided to go back out to consultation on new draft SOL SPD's and the North Wokingham Strategic Development Location SPD and Infrastructure Delivery and Contributions SPD for the Strategic Development Locations was readopted October 2011.

33) The SPD's were originally adopted after extensive public consultation and assessed and the approach accepted at the Kentwood appeal therefore form a material consideration and carries significant weight in assessing any schemes within the SOL.

Infrastructure

34) The Infrastructure Delivery and Contributions SPD sets out the necessary infrastructure, phasing, funding and planning obligations required to allow for the sustainable development of the SDLs. The SPD advises that the means of delivery should be provided by the developers of the SDLs as part of the development. Any works will be calculated as proportionate costs of the development and where off site works are required these will necessitate pooled contributions for the works.

35) As advised the main aim of the Strategic Development Locations SPDs is to ensure that development goes hand in hand with the provision of essential physical and community infrastructure. The key infrastructural requirements identified at North Wokingham are;

33

Page 30: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Provision of Northern Distributor Road (formerly called Relief Road) (NOR); • Provision of park and ride and interchange improvements at Coppid Beech

roundabout. This includes the Coppid Beech Roundabout Improvements; • Improved pedestrian, cycle and bus links throughout the SDLs and to the Town

Centre; • Provision of Station Road link; • Station Improvements; • Contributions towards southern distributor road; • M4 Junction 10 improvement works; • Provision of new Primary School; • Expansion of existing Secondary School; • Special Educational Needs, Early years and childcare provision contribution; • New Community Centre (GP surgery, community facilities, meeting rooms, retail

etc); • Two drop in Neighbourhood Police I Management facilities; • Contribution to Library provision; • Expansion of existing Children's Centre; • Sports facilities (Cantley); • Need for enhancement of retail facilities at existing centres at Clifton Road, Bean

Oak Road and Ashridge; • Housing Provision (35% affordable, wheelchair assessable etc); • Expansion of Toutley Industrial Park (to NW of SOL); • Provision of SANG I Country Parks; • Open Space and play areas; • Allotments and Public Rights of Way; • Sustainable provision (SUD's, renewable) • Provision of Noise Bund

(The junction at Ashridge has been discarded under the NOR Study undertaken by the Council as it was found to be ineffective)

36) Appendix 1 to this report sets out how the application meets Infrastructure Delivery SPD requirements.

37) In considering development, both the Core Strategy and SPDs, advise that the Local Planning Authority will seek overarching infrastructural applications for each SOL in order to deliver the infrastructure requirements and that these outline applications should include highways, transport, community buildings, affordable housing, schools, open space and SANG for consideration. As part of the Kentwood Phase 1 appeal decision, it was demonstrated that an SOL wide outline application was not required to support development within the SOL subject to an appropriate IDP being submitted.

38) The I DP should demonstrate how the proposals provide the infrastructural requirements and services laid down in the Core Strategy and SPDs in a coordinated manner and do not prejudice delivery of the SOL.

Overview of Applicants Approach

39) At the Kentwood appeal, the Secretary of State (SoS) found that the developers approach was acceptable however required that the Council needed undertake further highway assessment work (Northern Highway Study or NOR Study) to determine the requirements for the road network within North Wokingham.

40) It is noted that fundamental to the delivery of the NWSDL is the provision of a Northern Distributor Road (NOR and that without its rovision, the scale of NWSDL

34

Page 31: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

residential developments would not be acceptable due to its impact on the local and strategic road network. This view was agreed with by the Inspector at the Examination in Public (EiP) for the Core Strategy and again by the SoS at the Kentwood appeal.

Highway Provision I Approach

41) Policy CP20 of the Core Strategy seeks improvements to transport capacity along the A321 and A329 and the provision of the Northern Distributor Road (NDR). The proposed NDR route, as outlined in the Masterplan runs from the A329 (near the M4 over-bridge) Forest Road in the west, through the SDL development (not using existing roads) and eventually to Coppid Beech Roundabout, where a park and ride is proposed to be located.

42) Although at the Examination in Public the Council's preferred option was for a partial NRR, which would link Forest Road with the application site and include a new Ashridge Interchange with east facing access onto the A329(M), following the NDR Study options assessment, this option was not found to be the most suitable option. Instead the full NDR from Coppid Beech to Reading Road was found to be the most appropriate option and the Council is proceeding on this basis.

43) Appendix 7 clearly sets out the principles that should be achieved by the SDL approach:

"Development should be integrated into the existing town through connections to the existing highway network, and through the provision of a network of streets around the outer edge of the town, in order to disperse wider traffic movement and allow for direct journeys, thus supporting the feasible use of more sustainable modes of travel, including buses.

These new connections should be planned and designed as high quality residential streets, defined by development frontage. Their primary role will be for local movement.

In particular, direct pedestrian and cycle access to the proposed Park & Ride facilities at Coppid Beech and any other public transport interchanges within or near to the site should be provided to facilitate more sustainable movement across a wider area. These will need to take into account various opportunities along the current A329(M) corridor which are currently under consideration".

Connections with the existing highway network should be provided for higher and lower order streets to ensure a high degree of integration with the existing town, to help disperse traffic movement and to facilitate public transport movement through the site. This will tie in to the Council's town centre traffic reduction scheme and reduce the need for residents living in the vicinity of the North Wokingham SOL to drive through the town centre in order to access local strategic highways.

An internal network of Greenway routes should be provided to connect to existing routes within the town and to provide safe routes for primary and secondary school children. Where possible, existing cul-de-sacs should be opened up to connect into this network.

Easy and safe access to the Park & Ride facility at Coppid Beech and any of public transport interchanges within or near to the site should be provided. These will create opportunities for the new and existing communities to 'walk and ride' and 'cycle and ride' to Bracknell, Reading and national rail links at Wokingham station.

35

Page 32: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Easy and safe access to the new park and ride must be provided to create an opportunity for 'walk and ride' and 'cycle and ride'.

Facilities and stops for local bus services to link to Wokingham town centre and mainline railway station should be provided.

A Personalised Travel Planning Service should be delivered for new home owners to inform them of their transport options.

Improvements to transport capacity along the A321 and A329 could include a variety of measures such as: -

i) widening the existing highway; ii) provision of bus lanes; iii) signalisation of junctions; iv) delivery of new sections of road connecting into the existing network such as an

additional junction on the A329(M); and v the provision of improvements to permeability east-west in a route north of

Wokingham Centre from the M4 over-bridge to Coppid Beech. Any measures will need to be modelled to ensure it is an effective solution and should be capable of delivery at an appropriate time in the delivery of the development".

The Inspector at the Inquiry found this approach to be sound and stated that he considered that the development of North Wokingham could not be achieved without the Northern Relief Road. Para. 5.41 of the Inspector Report on the examination of the Core Strategy, states that;

"From my knowledge of the area and residents' comments, it would be surprising if the addition of a large number of new homes did not put unacceptable pressure on the roads if a full new link to the A329 were not provided".

44) It is noted that the consortia agreed at the Inquiry that the approach comprising an outline application to determine infrastructure was acceptable and could be achieved.

45) Recently the Inspector at the Managing Development Delivery Local Plan (which has now been adopted February 2014) considered that it is appropriate for the Council to continue to rely on the Core Strategy

The Applicant's Transport Assessment

46) The applicant has submitted a Transport Assessment (TA) with the application which assesses what is required to mitigate the impacts of the development in terms of junction and highway improvements based on the Council's modelling and NOR Study. It also at the pedestrian and cycling linkages to and from the site.

Consideration of the Proposal. NOR and off-site Highway works

47) The proposal includes the route for the NOR and whilst the NW SPD and NOR study recommends utilising a route running to the north of Ashridge Farm, the application has also assessed Warren House Road be used as the primary route for the NOR. However as this is an outline application and layout and access are not fixed at this time, the alignment of the route within the site remains flexible and the proposals do not prejudice the future alignment of the NOR.

48) It is also noted that the indicative masterplan has indicated direct accesses from dwellings at certain locations along both proposed route. Further work will be re uired to determine whether these can be accommodated as reposed within the

36

Page 33: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

NOR. However this will be a reserved matters consideration and by such time these come forward the final NOR alignment should be known.

49) It is noted that the NOR route will allow for a 6.1m carriageway, 2m footway and 3m cycleway along the NOR in accordance with the design principles of the NOR study. It should be noted that the NOR is expected to have a speed limit of 30 mph. However it should be noted that flexibility is required to allow for varying widths along its length allowing for centralised features to act as traffic calming measures, pedestrian and cycle crossings, as well as the use of verges along the route for other design features. In addition, there is potential that 3m footway I cycleways could be provided on both sides of the road, issues that again will be considered in detail at reserved matters stage.

50) The development will be accessed to the east from the new roundabout located on Warren House Road, which has been recently constructed as part of the Kentwood Farm East development. Along the southern boundary, it is proposed to provide a new access from Warren House Road onto the site by either re-routing Warren House Road into the site (should Warren House Road be used as the NOR) or by installing a new T-junction, if the SPD alignment is more appropriate. The junction will be fully assessed at reserved matters stage.

51) The indicate masterplan which shows the allotments on the south eastern corner will be served by a T-junction off Warren House Road. It should be noted that officers would prefer to see access gained internally from the site.

Parking

52) The applicants TA sets out that the site would provide both vehicle and cycle parking in line with the boroughs adopted standards. A review of the indicative layout indicated that the level of parking expected could be accommodated for the 225 dwellings while maintaining the housing density required.

Pedestrian and Cycle Links

53) The Core Strategy and NW SPD seek to promote good linkages within Wokingham. The Northern Distributor Road (NOR) will include a new pedestrian I cycle route along its full length providing connections between the proposed Park and Ride at Coppid Beech to Old Forest Road I Reading Road. These are proposed to help provide better sustainable access and links between the new and existing communities and facilities such as Cantley, Matthewsgreen School, community facilities and the SANG's and will link into the Council's Greenway Study.

54) The submitted TA and masterplan have also highlighted how the proposals will seek to promote good walking and cycling by providing good pedestrian links through the site and to external routes.

55) The TA sets out the existing walking routes on offer for residents of the development by accessing the key links to the town centre and other local facilities. This identifies the primary route to the town centre south through Norreys Avenue and highlights the current condition of the route.

56) Highway Officers are content that the application has shown this route to be acceptable for the primary route to the town centre for both walking and cycling. As part of the Phase 1 application for Kentwood Farm East, the developer has provided funds to improve this route, however at this time, the final detail of improvements along this route are yet to be completed.

37

Page 34: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

57) The developer has also promoted a further improvement along Warren House Road to provide improved access to the west to Cantley Park. This proposal is considered acceptable in principle and will aid in connections to Cantley Park which is a key sport/leisure destination within North Wokingham. Given that the applicant is not providing sports on-site it is important to ensure safe access to Cantley. This proposals would comprise upgrading the existing crossing at Benning Way (new tactile paving) and extending the footpath to the corner with Wiltshire Road

Traffic Modelling and improvements

58) The TA has been developed from the Phase 1 application and has assessed the requirement to provide off-site infrastructure to accommodate the cumulative impacts from the NW SOL.

59) Due to forecast modelling changes and the Council's NOR study being undertaken since the Kentwood Farm phase 1 application, the applicant has undertaken updated assessments to highlight where infrastructure improvements are now required.

60) An interim 2018 modelling assessment was undertaken by the Council when assessing the impacts of the NOR for the consultation process. This identified that there would be acceptable capacity constraints on the highway network prior to full delivery of the NOR. With the delivery currently estimated for around 2018 and the NOR study findings, it was agreed to assess the final 2026 assessment year only.

61) The modelling considered both potential alignments for the NOR, within the vicinity of the development site, that is north of Ashridge Farm and the alternative route that uses Warren House Road.

62) The assessment work has shown that the impact upon the wider network is negligible between the two options, however, locally the change results in an increased level of traffic along Warren House Road and Bell Foundry Lane. Should Warren House Road be used as the primary NOR route, the modelling has indicated that the existing road can accommodate the traffic with limited delay along this link, with only the Warren House Road I Bell Foundry Lane junction showing an increase in delay. Therefore, the TA promotes a new junction at the Warren House Road I Bell Foundry Lane which would aid in the movement of traffic in an east/west direction. It has been agreed that the developer will fund any improvement which the Council will deliver should this route is considered the most appropriate at a later date (completion of NOR study}.

63) The assessment methodology was agreed to be robust in assessing the potential impact of the full SOL. As such, the highway authority is content that the results submitted with both the TA and Addendum (T AA) provide the information to robustly assess the junctions in question.

Off Site Infrastructure

64) As part of the Kentwood Farm East Phase 1 approval, the developers agreed to provide the off-site infrastructure associated with the cumulative development for the NW SOL. These highway improvements (Condition 35 of Phase 1) comprised:

• A329 London Road I Binfield Road • Warren House Road I Wiltshire Road I Bell Foundry Lane • A329 Reading Road I Old Forest Road • A329 Reading Road I Holt Lane • Milton Road I Jubilee Avenue I Twyford Road • Matthews reen Road I A321 Tw ford Road/ A321 Milton Road

38

Page 35: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

• Forest Road I Twyford Road • Junction 25: Forest Road I Warren House Road

65) However, since this approval, the modelling has been improved and certain assumptions have changed. Therefore, as part of this Phase 2 application assessment, it has been agreed that the off-site works identified within this application could supersede those agreed on Phase 1.

66) The proposed Full NDR modelling assessment has identified there is minimal requirement for additional off-site mitigation associated with the development. The modelling has identified 3 locations requiring mitigation as discussed below:

Twvford Road I Forest Road

67) A proposal has been put forward that includes additional capacity on the Forest Road eastern arm with the use of a flared approach. This will allow the small increase in traffic to negotiate the junction safely without creating any additional delay. The safety audit identified an issue with existing signage and road surface which can be addressed at the detailed design stage.

Forest Road I Foxley Lane

68) Following a thorough review of the existing junction, it was determined that a full improvement scheme in this location cannot be accommodated within the existing highway boundary. The proposed junction is located on the Bracknell Forest Council border and as such, any infrastructure improvements within Bracknell may have an impact upon this junction. Following a review of the highway network we also determined that this is not a route that the Council would want to promote additional traffic through an improvements at this junction. Therefore, it was concluded that it would be more prudent for the developer to contribute funds to the Council with which the Council will continue a review of the highway impacts in this location and set out improvements that are considered appropriate for this area. This will allow any infrastructure set out by Bracknell to be implemented prior to WBC providing improvements that are not required.

Warren House Road I Bell Foundry Lane

69) The developer has promoted a new T-Junction in this location that provides priority for the east I west movement should Warren House Road be used as the NDR. The new junction still provides adequate capacity on Wiltshire Road and a new right turn lane at the junction of Wiltshire Road. The delivery of this junction will be dependent upon the local alignment option for the NDR. As such, the developer has agreed to provide contributions to enable this junction or an alternative highway improvement deemed necessary by the local highway authority to deliver the NOR at the time of delivery.

70) All proposed off-site infrastructure has been subject to safety audits. The Highway Authority is satisfied that the audits do not identify any significant risk that cannot be dealt with during the detailed design stage.

71) Therefore, the off-site junction improvements proposed within the application are acceptable and will provide the required mitigation for the development. These will however be subject to either a condition for the developers to provide full detailed drawings associated with the improvements and/or a financial contribution for highway improvements to be delivered by the local highway authority.

Public Trans ort Provision

39

Page 36: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

72) Discussions are ongoing regarding the public transport provision to decide on the most appropriate provision for the proposed developments. Through the Kentwood Farm Phase 1 application funds have already been secured for the delivery of a bus service. A public Transport Strategy will be appended to the S106 setting out how this new service I bus route will be provided to best serve the development and wider SOL.

73) The Council is working with the application in delivery of the S106 package secured through the Kentwood Farm phase 1 application. This has resulted in further reviews on the bus service requirements in NW and the Council is working with the applicant to deliver a sustainable commercial bus service that serve the new development without impacting upon existing services within Wokingham

74) It should be noted that the NOR has been designed to accommodate buses and therefore as further development comes forward such as Matthewsgreen to the west of NW, it will be possible for a bus route to extend into these developments as they come forward.

Travel Plan

75) The developer has decided to contribute towards the WBC 'My Journey' Travel Plan scheme rather than delivering their own. Subject to the funding mechanism being agreed within the S106, this is considered the most appropriate way in delivering alternative modes of transport for residents.

Summary of Highway Issues

76) There are a number of areas that will require refining should the development progress into reserved matters/technical approval, especially with access yet to be determined. However, given the improvements proposed by the developer which include improved connections to Cantley, improved off-site infrastructure, the provision of a bus service, improved walking and cycling routes to the Town Centre and agreed S106 Heads of Terms in line with the IDP, highways recommend no objection to this outline application subject to conditions (Conditions 16 - 25).

77) On the basis the proposals are considered acceptable in accordance with CP6 and 20 of the Core Strategy and SPD's.

Public Right of Ways - Development Permeability I Connectivity

78) There are a range of Public Right of Way (PRoW) footpaths within and around the North Wokingham SOL. Footpath number 14 is the most prominent PRoW within the vicinity of the site. Footpath No. 14 (links into No. 24) runs from Keephatch Road north-eastwards over the motorway and runs along the southern boundary of the Phase 1 development, from Keephatch Road I Dowlesgreen Farm development towards the overbridge which crosses the A329(M). On the north of the A329(M) the route leads through ancient woodland to the west and links in with Benfield Road (No. 24).

79) A contribution has been provided to the Council to improve PRoWs.

Infrastructure Delivery Approach

80) The Council within the adopted polices and SPD's set out that all schemes located within SDL's need to contribute towards the comprehensive delivery of infrastructure, services and facilities within SDL's. This approach was supported b the appeal

40

Page 37: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

decisions for residential development at Shinfield Glebe, Plough Lane and Kentwood Farm Phase 1. Failure to contribute to a wider infrastructure, services and facilities required to facilitate the SOL would severely impact upon the Council's capacity to deliver its spatial vision up to 2026.

81) The Sos on the Kentwood Phase 1 appeal found that the prov1s1on of a comprehensive IDP was sufficient to ensure delivery of infrastructure and services in a coordinated manner and this would not prejudice the Council's spatial vision.

Infrastructure associated with Proposal

82) As part of this application, the applicant has advised that they are willing to agree to contributions for the provision of infrastructure (where they are in accordance with Community Infrastructure Levy Regulation 122) which mitigate against their proposal. The submitted Infrastructure Delivery Plan contains costs of how the burden of delivery will be divided out between the three main SOL developers (Crest, Bovis and Gleeson). A draft S106 which sets out the heads of terms is currently being negotiated.

83) The IDP, which is an updated version from the Phase 1 scheme, now includes the Council's updated work and costings from the NOR Study and Cantley Masterplan. It seeks to apportion out the costs for infrastructure and services required to mitigate this phase of the development between the North Wokingham Consortia.

84) To summarise the applicant has agreed, in accordance with the requirements set out in Appendix 7 of the Core Strategy and Infrastructure SPD and Kentwood IDP, to contribute towards the following in order to mitigate the schemes impacts:

• Education - Secondary, Post 16 and SEN (Primary - if required) • Healthcare • Community Sports I Leisure Facilities - No on-site provision therefore

contributions towards Cantley improvements • Sports Halls • Swimming Pools • Strategic Access Monitoring and Maintenance (SAMM) • Country Park and Countryside Access • Biodiversity • Children's Play- Part on-site provision and contributions towards off- sit • provision • Amenity Open Space I Childrens Play Maintenance Commuted Sums • Public Rights of Way • Strategic Highway Improvements (e.g. FNDR and Coppid Beech roundabout

improvements, other highways improvements) • Railway Station Improvements • Station Link Road • Coppid Beech Park and Ride • Travel Plan • Libraries • Allotments - On-site provision • Burial - no on-site provision therefore contributions towards off-site provision • Community facilities and Community Manager

85) Officers are currently negotiating with the developers on what is a fair and reasonable contribution for this development. The Heads of Terms have been agreed and the revised IDP is considered acceptable and would not prejudice delivery of the SOL.

41

Page 38: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

Community and Social Infrastructure Delivery

86) In terms of providing sustainable communities, the core aim is that the SDL sites should provide community centres or hubs, in which provision is made for a range of local services including shops, community meeting rooms, surgeries, policing, education, childcare facilities etc. New facilities should be provided within the new development in order to ensure that additional pressure is not placed upon existing facilities. These should be provided by the developer as part of the development.

87) The Kentwood East scheme established that a contribution of £750,000 would be the provided for a new community centre for the SOL which would be provided within the Matthewsgreen area of the SDL. This new community building could be included with the new neighbourhood centre and primary school. The SPD identifies that the community building should be provided I secured as part of the first phase of the development at Matthewsgreen.

88) A contribution is provided for a community manager for the SDL. The aim of the manager is to facilitate the rapid development of community networks and with the integration of new residents into Wokingham.

89) It is noted that there have been requests for funding to go towards improvements to Ashridge I Norreys centre however there are a number of issues with this. Firstly Ashridge does not have a community building that could serve the development and secondly spreading resources from the SDL developments would be at the expense of the new centre and could prejudice its delivery by resulting in viability issues with providing a new centre. However it should be noted that the Council is looking at ways of improving the Ashridge I Norreys area and providing enhanced communities facilities in this area.

Education

90) The nearest schools to this site would be All Saints and Keephatch Primary Schools; and St Crispins Secondary School. It should be noted however that primary and secondary school places may not all be taken up solely by these schools but other schools within the borough, for example at Holt and Forest Schools or by the new schools within the North or South Wokingham SDL developments.

91) The applicant is proposing contributions towards Special Education Needs and Secondary Schooling. No contributions are proposed towards primary provision as there is capacity within All Saints and Keephatch Primary Schools. This approach was agreed at the Kentwood appeal.

92) Since the Kentwood appeal the Council has undertaken further work with regards to the requirements of Special Education Needs (SEN). This demonstrates that there is a requirement for SEN places I provision of new facilities within existing sites within the borough and that new developments need to contribute towards SEN provision.

93) The applicant has agreed to this and is proposing contributions based on the Planning Advice Note.

Leisure

94) No formal play pitches or sports facilities are being provided on site. Instead the applicant has put forward that the leisure facilities to serve the development should be located at Cantley Recreation Ground.

42

Page 39: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

95) It has always been the Council's position that contributions that are based on the PAN should not be used for developments within the SDL's as the PAN cannot identify the level of funding required to provide improved and new sport/leisure facilities required.

96) On the Phase 1 appeal, the applicant put forward that the leisure facilities to serve their development should be located at Cantley Recreation Ground. They also used PAN to calculate their contributions in the absence of other evidence however pooled the sport/ leisure contributions (Playing Pitches, Sports Halls, Swimming Pools etc.) in order to allow the Council flexibility in the use of the funds for improvements to be undertaken to Cantley Recreational Ground. As there was no alternative detailed evidence to understand what was required and calculate the contributions at that time, this approach was considered acceptable by the Inspector I SoS as it was not considered to compromise future delivery of facilities within the SDL.

97) Since the Kentwood appeal however the Council has completed a review of sports I leisure facilities (Open Space Audit) within the borough. This looks at the shortfall, future needs and how these facilities can be provided. As part of this review a specific North Wokingham study was undertaken called the Cantley Masterplan. The plan identifies the longer term options for development at Cantley and specifically looks at the requirements of the SDL's. The report looks at various options how to undertake qualitative and quantitative improvements to Cantley. A key component is that the report identifies that that additional land for playing pitches and associated facilities (parking, changing rooms) will be required in addition to improving the existing facilities at Cantley in order to provide sufficient sports facilities and land for developments within NW SDL to mitigate their impacts.

98) Although this document is not adopted, it has been out for consultation and draws conclusions based on Sport England standards and costs and costs identified by other developments SDL within Wokingham. Given the above and as no other alternative proposals have been put forward by the developers within the NW SDL, it is considered that the evidence contained within the Cantley Masterplan is relatively robust and provides a robust starting point to negotiate contributions towards the sport and leisure infrastructure that is required for developments within the NW SDL.

99) For these reasons the contributions towards sports requirements should not be based on PAN. The applicant has accepted this approach.

100) Sports Hall and Swimming Pools contributions are based on the PAN. This approach has been agreed by the applicant for Phase 2.

Other community requirements

101) Other requirements set out in Appendix 7 of the Core Strategy and Infrastructure SPD relating to healthcare requirements have been in part included as part of the draft unilateral undertaking.

102) The siting of community housing (provision of six dementia care dwellings) as part of the affordable housing has been raised by the Wokingham Town Council however it is considered that this should be provided at Matthewsgreen as these facilities are better located next to community facilities and shops. As there are no facilities I shops provided on Kentwood sites, it is not considered the most appropriate site for this type of housing.

Affordable Housing

103) Polic CP5 of the Core Strate and the North Wokingham SPD seek to provide a

43

Page 40: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

maximum of 50% and a minimum of 35% of Affordable Housing on the SOL sites. The Affordable Housing provision is based upon 70:30 split between social rent and shared ownership housing as detailed within the Affordable Housing Viability Study. The applicant is proposing 30% provision of affordable housing on-site with 5% commuted off-site. This approach has been agreed on the Phase 1 application and other SOL sites and is considered acceptable. The tenure and mix will need to be negotiated.

Relationship with nearby properties

104) Although the scheme is an outline, there are no obvious issues in relation to future impacts upon neighbouring amenities from the indicative masterplans submitted with the application. The site is an allocated site and the nearest properties are some distance away across Warren House Road. The indicative plans which show building heights and land use appear to be acceptable in principal.

105) On this basis, no in principle objection is raised at this time.

Impact on Listed Buildings and Heritage

106) There are no listed buildings directly adjacent, however the Environmental Statement advises of 10 listed buildings within 500m of the site boundary. The most relevant one are the buildings on Ashridge Farm (group of 4 listed buildings at Ashridge Farm including the 2* farmhouse) to the southwest of the site.

107) Ashridge Farm is considered to retain its agricultural character and is located approximately 300m away from the application, with several field boundaries and hedgerows separating the two sites. It is considered that the distance and intervening features, together with the proposed retention of a green buffer/corridor along the western boundary of the site, will mitigate against any impacts to the setting of this listed group of buildings.

108) Keepers Cottage which is located to the east will not be impacted by the development proposals.

SANG

109) The development is required to mitigate the impact of the new residential development on the Thames Basin Heaths Special Protection Area (SPA), which is a requirement of Habitats Regulations. Policy CP 7 Biodiversity of the Core Strategy reinforces this requirement. In mitigating developments impacts, larger developments should provide a Suitable Alternative Natural Greenspace (SANG) to encourage residents not to travel to the SPA. In order to do this, these should be of high quality and of a sufficient size.

110) The methodology used for the calculation of the quantity of SANG required by this development (2.16ha per 1000 population) is considered adequate to avoid any impacts on the designated Thames Basin Heaths SPA.

111) The proposed SANG which was provided as part of the Phase 1 scheme comprises 2.66ha and is of sufficient size to permanently mitigate the impacts upon the designated Thames Basin Heaths SPA for both phases of the development. On­street parking will be provided as part of this scheme for the SANG.

112) The Council's Countryside Officer and Natural England have not objected to the proposed scheme for the SANG. However issues relating to ownership, maintenance and the car park have et to be resolved.

44

Page 41: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

113) Therefore subject to the appropriate SPA Monitoring or Strategic Access Monitoring and Maintenance (SAMM) for the SPA contributions being provided, the proposal is acceptable.

114) The SANG will be transferred to the Council prior to occupation of the first dwelling on the Phase 1 scheme.

Public Open Space Provision

115) Again as this is an outline application no details of public open space are provided. The indicative masterplan and land use plans show a buffer along the western boundary, allotments located on the south eastern corner adjacent Warren House Road and two areas of open space, larger area in the middle which can accommodate the children's play and a smaller area. However these matters will be assessed in detail at reserved matters stage.

116) The applicant has indicated that they will provide a LEAP on the site and an off-site contribution towards facilities off-site. It should be noted that this contribution is to provide quality areas of play both locally and in the wider area. The Council are proposing a destination play areas (such as the one at Dinton Pastures), one of which is proposed at Cantley which this contribution could go towards and the facility is likely to be used by the residents of this site. As such, it is important that the pedestrian I cycle links between this site, Phase 1 and Cantley are improved and are safe. As such the applicant is now proposing improvements to the link along Warren House Road. This comprises an extension to the footpath on the southern section of Warren House Road at the junction with Wiltshire Road.

Other Issues

117) A contribution towards Country Parks and Countryside Access is included in accordance with PAN as it is considered that the proposed Public Open Space / SANG areas will not provide a Country Park experience. Therefore it is likely that future residents of this scheme would visit the boroughs existing Country Parks. For this reason contributions should be included to mitigate the developments impact. The application also provides a Biodiversity contribution in accordance with the PAN.

Landscape, Trees and Visual Character

118) The applicant has undertaken a survey showing the location and condition of all trees on the site. The site contains limited large trees which are sited on the eastern, western and southern boundaries of the site. There is an existing hedgerow bounding the site. As part of the Kentwood Phase 1 scheme, individual trees on the site and were given protected status.

119) The proposals should seek to retain the larger trees along the boundaries and reinforce planting where possible. The hedgerow along the western boundary is considered to be important hedgerow and will have a buffer with the development included in future any design. It is considered that retention of the hedgerows along the southern and eastern boundaries would also enhance the development (Condition 9).

120) As with the Phase 1 scheme, it is expected that along the primary routes significant tree planting will be installed. On the reserved matters it will be important to ensure that sufficient space is maintain around trees to allow for adequate protection for new trees and for root protection of the retained trees to be maintained however this will be dealt with at reserved matters sta e.

45

Page 42: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

121) The Council's Tree and Landscape Officer has not raised any in principle objections however has raised concern with the location of the access to the south along Warren House Road in relation to an existing trees. However the plans are indicative and this will be looked at in detail as part of the reserved matters.

122) It should also be noted that the location of the SUD's running parallel to the western boundary will need to take account of the root protection area of the trees along this boundary. The SUD's scheme should also be a multi-functional especially when dry.

123) For this reason the proposals are considered acceptable subject to retention and protection of the existing trees and also the hedgerow to the western boundary (Conditions 9 - 13).

Flooding/Drainage

124) The applicant undertook a Flood Risk Assessment which determined that the residential part of the site is not within areas shown to be at risk of flooding, as indicated by Flood zone 1 on the Environment Agency's Flood map.

125) It is noted that Hurst and neighbours are concerned with the development resulting in flooding issues however the applicant undertook a Flood Risk Assessment which determined that the site is not within areas shown to be at risk of flooding, as indicated by Flood Zone 1 on the Environment Agency's Flood map. Although drainage cannot be assessed in detail at this stage, it is envisaged the site will provide SUDs which will incorporate flood attenuation ponds in the areas which should improve the current situation by preventing water from running of the land quickly and a condition is recommended for details of the drainage strategy (Condition 32). As such there is no reason to consider the development will cause additional significant flooding issues locally or elsewhere.

Ecology

126) The Ecology Officer has not objected to the proposals however has recommended precautionary conditions. The development has the potential to have an adverse effect on the buffer zones required to protect the boundary hedgerows on the site which have been identified as UK Biodiversity Action Plan (BAP) Priority Habitats, as such a condition is recommended for of a detailed hedgerow mitigation and compensation strategy (Condition 36).

127) It has been identified that the site appears to support suitable reptile habitat as the area surrounding (Kentwood Phase 1 site) is known to support populations of native reptiles which are protected species. However given the scale of the development proposed and as the field is farmed intensively, it is unlikely to have a significant adverse impact on the local reptile population. Therefore a condition is recommended to protect individual reptiles from harm during development (Condition 37).

128) The submitted ES identified that the site has the potential to support hedgehogs which are a UK Biodiversity Action Plan (BAP) Priority Species and as such a condition is recommended to protect individual reptiles from harm during development (Condition 38).

129) Having considered the implications of this application against EC Habitats Directive (1992) and the Conservation of Habitats and Species Regulations (2010), it is considered that subject to the application of the details outlined within the Environmental Statement in relation to bats, the proposals will not be detrimental to the local bats ecies population.

46

Page 43: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

130) It is noted that neighbours have raised concerns over the loss of wildlife habitat and although this is regrettable, the site is allocated for housing and biodiversity enhancements are proposed such as bird and bat boxes.

131) On this basis the proposed development is considered not considered to have significant impacts to biodiversity or ecology either on the site or within the local area and is therefore acceptable.

Air Quality and Odour

132) Policy CP20 seeks to ensure that development proposals minimise the emission of pollutants on the wider environment.

133) Appendix 3 of the adopted Sustainable Design and Construction SPD provides guidance on air quality considerations for new development and advises on whether air quality assessment may be required.

134) The applicant has submitted an Environmental Statement (ES) in support of the proposals and the report assessed the impacts from traffic and construction and includes mitigation measures. The results of the assessment demonstrated that the impacts are principally from traffic and construction and these are not significant ("moderate adverse to negligible significance") and that the entire site is suitable for residential development.

135) The ES also looked that the impact of the sewerage works on the development. During the promotion of the site within the Core Strategy, Thames Water recommended that a precautionary odour zone be imposed on the area. This includes the area to the south western corner next to the existing sewerage treatment plant. As such the applicant undertook odour assessments I surveys and the results found little or no odour from the works on the development site and this informed the indicative masterplan for the site.

136) However Thames Water have raised concerns regarding potential amenity issues for future residents of the proposed development. Thames Water has advised that they do not consider that these concerns have been addressed fully and have requested that further modelling of odour assessments are undertaken and recommend that the developer carry out a dispersion odour assessment with odour sampling to establish the amenity impact on potential future occupiers. This modelling will confirm whether future occupiers of the proposed development would be significantly adversely affected by odour from the sewage works. Should the assessment confirm that proposed occupiers will be significantly adversely affected by odour from the sewage works, Thames Water recommend that the developer would need to fund odour mitigation to address this impact and that no development should be occupied until the odour mitigation is operational.

137) It should be noted that further assessment work including on-site observations was undertaken following concerns raised by Environmental Health regarding potential smells. From the evidence submitted there is nothing to suggest there is an issue on this part of the site or that development should be restricted. As such, the results conclude that the site is suitable for residential development and Environmental Health have raised no in principle objections to the scheme.

138) In any case the proposal is outline and therefore the location of residential development on the site is not fixed. As such a condition is recommended for further assessment work to be undertaken in accordance with Thames Waters comments to establish whether there could be an issue.

47

Page 44: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

139) For these reasons, no objections are raised to the proposals subject to condition (Condition 35).

Land Contamination

140) There is no evidence of contamination on the site during inspection and trial pit evacuation. The site has historically been in continuous agricultural use and there is no evidence of contaminating activities operating on or within the immediate area. As such it is concluded that the risk of contamination is considered to be very low but as a precautionary measure conditions are recommended (Condition 14 and 15).

141) The Environmental Health Officer has reviewed the information submitted and has not raised any objections to the proposals.

Pollution

142) There is potential for adverse impacts on the environment during excavation and the construction process, from dust, mud on the roads and noise. Therefore the applicant would be required to provide Construction Environmental Management Plan, prior to construction to minimise any impacts (Condition 7). This would be enforced by planning condition.

143) On this basis, no objection is raised.

144) The housing will be screened from noise from the A329(M) by the construction of the 3.5m high land bund and 2.5m fence running for the entire length of the development site adjacent the A329(M). This will be in place prior to occupation.

145) A noise assessment was submitted which concludes that the majority of the site falls within Category A where noise is not a problem however some properties at the northern boundary of the development with facades facing onto the A329(M) will fall into Noise Exposure Category B during the day. However all will fall within NEC Category A at night. Those properties falling into NEC B during the day will require some additional protection against noise however this could be adequately provided by double glazing.

146) With respect to road noise from the NOR (Internal Noise levels) the assessment predicts that some plots adjacent to the NOR will fall within NEC Category C during the day and at night and that 'reasonable' internal noise levels for resting and sleeping can be achieved by high specification double glazing and alternative means of acoustic ventilation included (Condition 23). Again Environmental Heath are satisfied that a reasonable internal noise level can be achieved if windows on facades facing the NOR are double glazed and kept shut, particularly at night. Although keeping windows shut on properties is never an ideal solution, it must be noted that the NOR is required to allow development within North Wokingham and moving the dwellings further away from the NOR is likely to reduce the housing numbers on the SOL sites significantly and could lead to viability issues in delivering the road. It should also be noted that this scheme is outline and the masterplan is indicative only and that the layout and design issues will be assessed in detail at the reserved matters stage.

147) With respect to noise onto the proposed gardens, the noise assessment predicts that the target (maximum) noise level for gardens (55dB LAeq, 1 hr) will be achieved for all

lots exce t plot 116 which will be 0.4dB above the criteria. It is noted that the

48

Page 45: ITEM NO: 112.00 Ref No - Modern Mindset · CP3 and CC03 of the Managing Development Delivery Local Plan (Feb 2014). 10. All hard and soft landscape works shall be carried out in accordance

'predictions' assume that the perimeter walls I fences are 1.8m high and 'acoustically sound.". Given this is an outline application there is no reference to the type I specification of perimeter walls or fencing proposed (in terms of height or acoustic performance). As such it is proposed to condition is recommended to control garden fencing (Condition 24).

148) On this basis, no objection is raised.

Archaeology Report

149) Although the site is considered to be limited in potential, the Berkshire Archaeology Officer has advised that a scheme of investigation be conditioned on the site to monitor the site (Condition 40).

Energy Efficiency and Renewable Energy

150) Policy CP1 of the Core Strategy relates to sustainable development while the Council's adopted Sustainable Design and Construction SPD sets out the requirements for new developments.

151) Although this is not a consideration at this outline stage, it is expected that the development will achieve at least Code Level 3 of the Code for Sustainable Homes and Code Level 4 for the affordable housing units (Condition 26).

152) The development should also seek to achieve a minimum reduction of 10% of total energy consumption through either on-site renewable energy generation or fabric first approach (Condition 27).

CONCLUSION The outlined proposal with all matters reserved which sets out the principal of up to 225 houses on the site is considered to be acceptable as it is located on an allocated Local Plan housing site and does not compromise the delivery of infrastructure within the SDL, subject to agreement of the contributions. The proposal promotes the comprehensive and coordinated development approach outlined within the Core Strategy, NWSDL and the Infrastructure Delivery and Contributions SPDs. The development will make the necessary contributions towards the delivery of infrastructure required for the development within the SDL. The proposed development also makes adequate provision for affordable housing provision within the scheme.

Officers are currently negotiating the appropriate contributions for the delivery of the infrastructure, however as the Heads of Terms have been agreed and this approach is not considered to prejudice delivery of infrastructure for the SDL.

It is considered that the proposal is in accordance with policies and associated guidance and does not result in significant harm to the occupiers of the neighbouring properties, future occupiers or the local environment.

As such the development is acceptable subject to conditions and agreement of the S106 contributions.

Details will be assessed under reserved matters application at a later date.

NB All reports seek to identify environmental, community safety, customer care and equal opportunities implications. Consultation with residents and organisations which has or is about to take place, will also be reported